engineering & operations committee item 7-1 march 13, 2017

17
E&O Committee Item 7-1 Slide 1 March 13, 2017 Engineering & Operations Committee Item 7-1 March 13, 2017

Upload: others

Post on 13-Jun-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 1 March 13, 2017

Engineering & Operations Committee Item 7-1 March 13, 2017

Page 2: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 2 March 13, 2017

Appropriate $1.65 million

Authorize preliminary design to upgrade the electrical distribution system

Authorize final design to repair the forebay and its outlet tower

Authorize construction of structural repairs to the Lake Mathews Hydroelectric Plant

Page 3: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 3 March 13, 2017

CASTAIC LAKE

GARVEY RESERVOIR

SILVERWOOD LAKE

LAKE PERRIS

DIAMOND VALLEY LAKE

LAKE SKINNER

LAKE MATHEWS

LIVE OAK RESERVOIR

Lake Mathews

Page 4: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 4 March 13, 2017

Unit Power Center (UPC) Underground or Overhead Distribution Line

Hydroelectric Plant

Forebay Outlet Tower

Administrative Buildings

Fixed Cone Discharge Valves

Maintenance & Repair Shops

Incoming Power

Page 5: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 5 March 13, 2017

Planned Work Replace underground & overhead lines Replace UPC’s Integrate elect. system with Metropolitan’s SCADA system

Preliminary Design Activities Confirm exist. & estimate future electrical loads Conduct condition assessment & hazardous material testing Prepare conceptual drawings, envir. documentation & cost estimate

Preliminary Design by Metropolitan

Page 6: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 6 March 13, 2017

Forebay & Outlet Tower

Hydroelectric Plant Control Building

Walkways Walkways

Page 7: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 7 March 13, 2017

Planned Work

Replace damaged concrete

Replace corroded reinforcing steel

Install cathodic protection system

Replace walkways & control building Outlet Tower

Control Bldg

Page 8: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 8 March 13, 2017

Design Activities by Metropolitan Scope of work: Design of forebay repairs, steel walkways & control building Prepare drawings & specifications Prepare construction cost estimate Receive competitive bids

Design Activities by HDR Engineering Scope of work: Design of tower repairs & cathodic protection system Work performed under exist. Board-authorized agreement No action required SBE participation level: 18 percent Estimated cost: $125,000

Page 9: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 9 March 13, 2017

Damaged Concrete at Bldg Exterior

Corroded Reinforcing Steel Within Bldg

Page 10: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 10 March 13, 2017

Construction Contract Contract to be awarded under GM authority Replace spalled, cracked & damaged concrete Replace corroded reinforcing steel & install cathodic protection system

Activities by Metropolitan Construction inspection & project management Submittals review & preparation of record drawings

Page 11: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 11 March 13, 2017

*SBE (Small Business Enterprise) participation level = 14%

Specifications No. 1851

Bids Received:

No. of Bidders:

Low Bidder:

Low Bid:

Range of Other Bids:

Engineer’s Estimate:

SBE Participation*:

January 25, 2017

6

O’Connell Engineering

$207,800

$245,000 to $297,000

$340,000

15.4%

Page 12: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 12 March 13, 2017

Labor

Prelim. Invest.

Final Design

PM, Contract Admin.

Submittals Review

Construction Inspection

Professional Services

Contracts

Remaining Budget

$735,000

-

75,000

-

-

-

50,000

$ 860,000

2. Forebay Repairs

$ - 188,000

67,000

-

125,000

-

50,000

$430,000 Totals

3. Hydroelectric Plant Repairs

$ - -

54,000

20,000

32,000

-

207,800

46,200

$360,000

Total Requested Amount: $1.65 million

1. Elect. Upgrades

Page 13: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 13 March 13, 2017

Board Action Final Design

Completion

2020 2018 2019

3. Hydroelectric Plant Repairs

Construction

2017 Lake Mathews Projects

1. Elect. Upgrades

2. Forebay Repairs

Prelim Design

Page 14: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 14 March 13, 2017

Option #1 Adopt CEQA determination that the proposed actions are categorically exempt

Appropriate $1.65 million

Authorize design of two rehabilitation projects at Lake Mathews

Authorize construction of structural repairs to the Lake Mathews Hydroelectric Plant

Page 15: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 15 March 13, 2017

Option #2 Adopt CEQA determination that the proposed actions are categorically exempt

Appropriate $790,000

Authorize construction of structural repairs to the Lake Mathew Hydroelectric Plant

Authorize design of repairs to the Lake Mathews forebay

Do not authorize electrical upgrades at Lake Mathews

Option #3 Do not proceed with the 3 rehabilitation projects at this time

Page 16: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 16 March 13, 2017

Option #1

Page 17: Engineering & Operations Committee Item 7-1 March 13, 2017

E&O Committee Item 7-1 Slide 17 March 13, 2017