engineering support program (esp) - pdf.usaid.govpdf.usaid.gov/pdf_docs/pa00n3g1.pdf · of the...
TRANSCRIPT
Engineering Support Program (ESP)
CONTRACT NO. AID-306-C-16-00010
BI-WEEKLY REPORT NO. 7
JULY 21, 2017 – AUGUST 3, 2017
SUBMITTED: AUGUST 6, 2017
DISCLAIMER
This publication was produced for review by the United States Agency for International Development. It was
prepared by Tetra Tech. The author’s views expressed in this publication do not necessarily reflect the views of
the United States Agency for International Development or the United States Government.
AU
AF S
ITE V
ISIT
/ T
ET
RA
TEC
H E
NG
INEER
ING
SU
PPO
RT
PR
OG
RA
M
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
i Bi-Weekly Report No. 7: Report Ending 2017-08-03
TABLE OF CONTENTS
CLIN 0003: Technical Services .............................................................................................................................. 1
JO-TS-0003 AMD 3 Sardar Kabuli Girls High School (SKGHS) QA Services ......................................... 1
CLIN 0004: Power Transmission Expansion & Connectivity (PTEC) ............................................................ 2
JO-P-0005 SEPS Completion Transmission Line ............................................................................................ 2
JO-P-0006 SEPS Completion Substations ......................................................................................................... 4
JO-P-0008 Arghandi-Ghazni Transmission Line ............................................................................................. 5
JO-P-0009 Arghandi-Ghazni Substations .......................................................................................................... 8
JO-P-0010 NEPS-SEPS Connector Transmission Lines .............................................................................. 11
JO-P-0011 NEPS-SEPS Connector Substations ............................................................................................. 13
JO-P-0012 Salang Tunnel Substation ............................................................................................................... 14
CLIN 0005: Vertical Structures (VS) .................................................................................................................... 15
JO-VS-0013 American University of Afghanistan (AUAF) QA Services ................................................. 15
CLIN 0006: Roads (R) ............................................................................................................................................. 17
JO-R-0017 Warranty Inspection, QA, and Final Inspection Services for Gardez to Khost (G-K) Road
(Phase IV) ............................................................................................................................................................... 17
CLIN 0007: Other Energy & Water (EW) ......................................................................................................... 18
JO-EW-0015 Kajaki Hydropower Operations Support ............................................................................. 18
CLIN 0008: Internship & Capacity Building (ICB) ............................................................................................. 19
JO-ICB-0007 Internship Program for Afghan Women in Engineering and Architecture ................... 19
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
1 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0003: TECHNICAL SERVICES
JO-TS-0003 AMD 3 SARDAR KABULI GIRLS HIGH SCHOOL (SKGHS) QA SERVICES
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
Nothing to report.
2. UPCOMING ACTIVITIES
Nothing to report.
3. ISSUES
Nothing to report.
4. ACTION ITEMS / KEY NOTES
S# Item Action By Orig. Due
Date
Revised
Due Date
1
USAID noted this will remain open as the warranty inspection is
pending. Prior to the end of warranty inspection, Tt ESP will
conduct an inspection and create the warranty punch list (PL).
This inspection will take place close but prior to October 20,
2017.
Tt ESP
October
10, 2017
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
2 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0004: POWER TRANSMISSION EXPANSION & CONNECTIVITY (PTEC)
JO-P-0005 SEPS COMPLETION TRANSMISSION LINE
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
On July 23, 2017, Da Afghanistan Breshna Sherkat (DABS) Procurement Department
published the Decision of Award to Xinjiang Electric Power Construction (XEPC) in the local
newspaper and notified the unsuccessful bidders on the same day, as per Provisions 82 and 84
of the Procurement Procedure. The protest period commenced on the same day.
On July 31, 2017, the protest period ended. No protest was received.
On August 1, 2017, DABS Procurement sent another letter to the National Procurement
Authority (NPA) requesting that the Job Order be included in the agenda for the National
Procurement Commission (NPC) meeting, tentatively scheduled for August 6, 2017.
On July 29, 2017, Tt ESP’s engineer embedded at DABS met with the DABS Chief Operations
Officer (COO) to discuss DABS’ decision on the future of the existing transmission line from
Kajaki to Kandahar and Lashkar Gah. DABS COO noted that it is DABS’ intent to keep the
transmission line in service as an alternate/backup in the event that the new transmission line
is not functional due to war damage, or is out due to maintenance. The DABS COO instructed
the DABS Project Implementation Unit (PIU) to submit a draft request letter for this proposal
to USAID within 1-2 days. On August 2, 2017, DABS PIU submitted this letter to USAID.
On July 31, 2017, Tt ESP submitted tabular estimated cost for the additional Scope of Work
(SOW), required due to missed design features, to USAID for review.
2. UPCOMING ACTIVITIES
DABS Procurement to defend the Job Order award decision in the NPC meeting tentatively
scheduled for August 6, 2017.
DABS Procurement to issue the Acceptance Letter to the successful bidder within three days
of NPC’s approval of the award, as per Provisions 85 and 86 of the Procurement Procedure.
3. ISSUES
Nothing to report.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1
Assuming a construction contractor NTP of November 1,
2017, the expected project completion date will be July 1,
2019, based on a period of performance of 20 months.
FYI FYI FYI
2 DABS to defend the Job Order award at the NPC meeting,
scheduled on August 6, 2017.
DABS
Procurement
July 31,
2017
[Date to be
inserted]
3
DABS is to decide either to demolish or keep the existing
Transmission Line (TL) by May 20, 2017. Tt ESP cited the
USACE estimation of 100 Land Acquisition Resettlement
Program (LARP) issues with the current line.
USAID directed Tt ESP to assume the existing
transmission line will remain in place and be utilized by
DABS. USAID noted that they had not received direction
regarding DABS’ decision to either keep or demolish the
DABS May 20,
2017
August 2,
2017
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
3 Bi-Weekly Report No. 7: Report Ending 2017-08-03
# Item Action By Orig. Due
Date
Revised
Due Date
line. Tt ESP commented that keeping the line would mean
the substations would need to be redesigned to
accommodate a second circuit, which would mean
additional funds would be required and the contract would
need to be modified.
Tt ESP noted this resolution is critical due to LARP issues
on existing line, which would make repairing existing line
very challenging.
Discussion on issue of lines being too close to one another
and creating technical issues. Tt ESP and USAID noted that
this has been and is being discussed, and suggestions have
been given to DABS. Options include removing the line, or
moving specific sections where the lines would be too
close.
4
Potential Amendment – Tt ESP should provide updates on
potential amendment regarding procurement of
conductors and interconnection of Sangin Substation to
the new line.
Tt ESP provided draft amendment to USAID with
estimated cost for the added scope of work (SOW) on
July 31, 2017.
Tt ESP
July 20,
2017
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
4 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0006 SEPS COMPLETION SUBSTATIONS
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
On July 25, 2017, DABS was notified that USAID rejected the revised Bid Evaluation Report
(BER), as the BER was not consistent with the Observer’s Report.
2. UPCOMING ACTIVITIES
By August 6, 2017, DABS will revise and resubmit the BER to USAID.
3. ISSUES
DABS to resolve the inconsistencies noted in the BER by August 6, 2017.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1
Assuming a construction NTP of August 10, 2017, the expected
project completion date is February 10, 2019, based on a period
of performance (POP) of 18 months. USAID and Tt ESP noted
that should the additional bays be required in the substations (as
discussed in the above JO-P-0005 section), this POP would be
changed.
FYI FYI FYI
2
USAID OAA and OFM to review the BER and provide approval
or comments. USAID noted there will be a meeting today, July
11, 2017, with DABS regarding non-responsiveness of revised
BER to Observer’s Report.
USAID
OAA/OFM
July 25,
2017
July 25,
2017
3 Tt ESP noted need of dates when review will be complete, so that
Tt ESP can plan the work flow of ESP staff. FYI FYI FYI
4
will assume coordination between USACE,
especially regarding SEPS projects. Any communications regarding
these projects should be shared with , and the On-Budget
Monitor (OBM) and Alternate OBM.
FYI FYI FYI
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
5 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0008 ARGHANDI-GHAZNI TRANSMISSION LINE
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
The contractor completed repairs of war damaged Aluminum Conductor Steel Reinforced
(ACSR) at different spans, from Tower No. 18/2 to Tower No. 19/0, and Tower No. 19/6 to
Tower No. 19/7, along the Sayedabad-Ghazni section.
Tt ESP’s on-site inspector checked the electrical Direct Current (DC) resistivity of all mid-
span joints and repair sleeves installed for repair of ACSR. The mid-span joints and repair
sleeves passed the resistivity tests.
The contractor completed ACSR spacer and vibration damper installation from Tower No.
17/0 to Tower No. 18/0, along the Arghandi-Sayedabad section of the transmission line.
Tt ESP, DABS and the contractor have performed war damage materials’ delivery inspection
at the contractor’s warehouse and storage facility. Tt ESP and DABS verified that the materials
adhere to the approved design and contract requirements.
Tt ESP, DABS and the contractor have continued the final inspection of the transmission line
from Tower No. 0/1 to Tower No. 6/0, along the Arghandi-Sayedabad section. The site
inspection team will prepare a punch list (PL) detailing all observed defects, and submit the PL
to DABS and Tt ESP for review.
DABS has received NPC and USAID consent for a one month extension of contract. The
contract completion date is extended to August 31, 2017.
On August 3, 2017, Afghan National Army Forces (ANAF) provided site security, as requested
by DABS, allowing the contractor to complete ACSR and OPGW stringing at LARP-affected
locations, from Tower No. 19/0 to 20/0 along the Arghandi-Sayedabad and from Tower No.
14/3 to 16/0, along Sayedabad-Ghazni section. The contractor continued the ACSR stringing
from Tower No. 19/0 to 20/0.
2. UPCOMING ACTIVITIES
The contractor will continue ACSR, OPGW, and tower war damage repairs, along the
Sayedabad-Ghazni section.
The contractor will continue ACSR and OPGW stringing at LARP-affected locations, with
continued presence from ANAF.
3. ISSUES
The unresolved LARP and security concerns delayed the war damage repair works from July
23-26, 2017 and August 1-2, 2017.
Unresolved Right of Way (ROW) issues continued to halt the last step (wire mesh aka gabion
basket) concrete culvert construction at Tower No. 32/4, along the Arghandi-Sayedabad
section.
Unresolved ROW issues continued to prevent war damaged ACSR repairs at nine different
tower span locations.
The trimming of trees within line clearance has not been able to start, pending compensation.
The control relay panels are not yet delivered to Chimtala Substation, which will negatively
impact the completion of the new line bay, and delay the commissioning date of the Arghandi-
Ghazni Transmission Line. The transmission line is dependent on the new Chimtala Substation
line bay for start-up commissioning power. On July 18, 2017, in the weekly project
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
6 Bi-Weekly Report No. 7: Report Ending 2017-08-03
coordination meeting, the DABS PIU Manager stated that the estimated date for availability of
this start-up commissioning power is August 30, 2017.
Insurgent activities resulted in additional damages sustained to the transmission line, which
will increase the period of time required to complete war damage repairs. Tt ESP is assessing
any additional impact that this recent damage will have.
Late approval of the Contract Amendment No. 3 Agreement, signed by DABS on April 26,
2017, is having a negative impact on materials procurement, delivery, war damage repairs, and
invoice processing. At this time, the contractor cannot place the order for the tower sets, as
the material will arrive after the contract fund cancellation date of September 30, 2017.
Contract Amendment No. 3 does not include welding repair costs, therefore, the towers
recommended for welding will not be repaired by the contractor. On June 18, 2017, Tt ESP
recommended DABS PIU Manager to allow the contractor to replace the tower’s damaged
members, instead of welding. DABS has not yet responded to Tt ESP’s recommendation.
The available spares currently do not include +2 meter, +3 meter, +4 meter, +6 meter, and
+7 meter “leg extensions” to be used for war damage repairs.
The 11 sets of spare towers, required to replenish the project’s spare parts, will be delivered
by September 2017. Delay in replenishing the spare parts may affect handover of the project
to DABS by the agreed project close-out date.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1
USAID questioned how many kilometers (km) were able
to be strung after resolution of LARP issues, Tt ESP will
follow up with exact km. USAID questioned if Tt ESP
could provide a spatial analysis explaining exact lengths.
Tt ESP to share map with USAID showing unstrung and
resolved areas, including information on when the map
was last updated.
Tt ESP will provide the detailed map with analysis by July
22, 2017.
Tt ESP has provided the detailed map with analysis on July
26, 2017.
Tt ESP
July 3, 2017 July 26,
2017
2 USAID to send email to Tt ESP with specification of
concerns on issue of spare parts.
USAID
[Date to be
inserted]
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
7 Bi-Weekly Report No. 7: Report Ending 2017-08-03
5. PHOTOGRAPHS
Photo #1: ACSR repair, span between Tower Nos.
18/4 and 19/0, Sayedabad-Ghazni. AS, 2017-07-22.
Photo #2: Tower leg foundation inspection, Tower
No. 3/3, Arghandi-Sayedabad. AS, 2017-08-01.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
8 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0009 ARGHANDI-GHAZNI SUBSTATIONS
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
During this reporting period, the following construction activities were ongoing at Ghazni
Substation:
o Setting out steel reinforcing bars and placing concrete for the seven meter retaining
wall No. 3.
o Setting out steel reinforcing bars for the seven and 3.5 meter retaining walls.
o Construction of random rubble masonry (RRM) walls.
o Work on switchyard lighting.
o Installation of sewer pipes.
o Installation of trench covers.
o Installation of steel members for gantry structure modifications.
o Bolt torqueing for the gantry structure modifications.
o Backfilling and compacting for the leach field.
During this reporting period, the following construction activities were completed at Ghazni
Substation:
o Installation of roof truss sheet and steel staircase for watchtower No. 4.
o Setting out steel reinforced bars, installation formwork, and placing concrete for the
back side of the control room building sidewalk.
o Floor painting of control building warehouse.
During this reporting period, the following construction activities were ongoing at Sayedabad
Substation:
o Setting out steel reinforced bars, installation of formwork, and placing concrete for
the drainage ditches.
o Cable pulling for switchyard lighting
o Spreading of gravel for switchyard
o Compacting, laying and spreading sub-grade materials in preparation for roads A, B,
and D.
o Installation of outdoor lighting for the switchyard.
o Installation of heater and split air conditioners in the control room building.
o Bottom stiffeners welding for gantry structure modifications.
o Installation of trench covers.
During this reporting period, the following construction activities were completed at
Sayedabad Substation:
o Setting out steel reinforced bars for culvert foundation at road G.
o Connection of fiber optic and OPGW cables to the junction box.
o Installation of water well casing pipes
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
9 Bi-Weekly Report No. 7: Report Ending 2017-08-03
During this reporting period, the contractor submitted the following 15 design submittals. (*
indicates submittals which were sent back to contractor):
o DTS 510: Technical data of expansion joint material for control room building for
both Ghazni and Sayedabad substations.
o DTS 537: Construction material test report (gravel masonry stone and sand) for
distribution works for both Ghazni and Sayedabad substations.
o DTS 16: Final vendor list for main equipment for both Ghazni and Sayedabad
substations.*
o DTS 583: Water well log and screen design for Sayedabad Substation.*
o DTS 584: Equipment test report for Ghazni Substation.*
o DTS 97: Master drawing list for both Sayedabad and Ghazni substations.
o DTS 578: As-built drawing for Ghazni Substation.*
o DTS 585: Electrical polymer of vinyl chloride (PVC) conduit catalogue for switchyard
lighting for both Ghazni and Sayedabad substations. *
o DTS 586: Fence chain link material sample for Ghazni and Sayedabad substations.*
o DTS 543: Asphaltic wearing course design for Sayedabad Substation.*
o DTS 550: Equipment test report for Sayedabad Substation.*
o DTS 42: Codes and standards used in Method Statement of Earthwork Soil
Investigation for design calculations for retaining wall for both Ghazni and Sayedabad
substations.*
o DTS 572: Operation and Maintenance (O&M) manual for both Ghazni and Sayedabad
substations.*
o DTS 587: Cable tag sample for both Ghazni and Sayedabad substations.*
DTS 88: Environmental mitigation and monitoring plan (EMMP) for both Ghazni and Sayedabad
substations.
2. UPCOMING ACTIVITIES
The contractor will continue testing and pre-commissioning activities for electrical equipment
in control switchgear buildings at both Sayedabad and Ghazni substations. The expected
completion date for these activities is August 20, 2017.
The contractor will continue work on gantry structure modifications at both Ghazni and
Sayedabad substations. The expected completion date for these modifications is August 20,
2017 for Ghazni Substation, and August 10, 2017 for Sayedabad Substation.
The contractor will continue work on construction of retaining walls, roads, and drainages at
both Ghazni and Sayedabad substations. The expected completion date for these activities is
September 30, 2017 for Ghazni Substation, and August 31, 2017 for Sayedabad Substation.
3. ISSUES
In October 2016, DABS issued a limited stop work order to the contractor to stop work on
any construction of substation civil works that had not been reviewed and approved by Tt
ESP. This stop work order is still in effect.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
10 Bi-Weekly Report No. 7: Report Ending 2017-08-03
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1
In October 2016, DABS issued a limited stop work order
to the contractor to stop work on any construction of
substation civil works that had not been reviewed and
approved by Tt ESP. This stop work order is still in effect.
FYI FYI FYI
2
The contractor is to respond to Tt ESP’s comments on
all eight outstanding design submittals. The average aging
for the submittals is 102 days.
KEC
March 31, 2017 August 20,
2017
3
Tt ESP will submit the remaining O&M sections upon
receipt from the contractor. As per the construction
contract, all O&M manuals should be submitted one
month before testing and commissioning.
Tt ESP
July 15, 2017
4 Time Extension: On June 30, 2017 KEC requested a two-
month time extension. FYI FYI FYI
5
Tt ESP noted that for both Sayedabad and Ghazni
substations, electrical work should be completed by
August 20, 2017, but civil may not be completed.
FYI FYI FYI
6
Tt ESP submitted a memo on the milestones remaining
after July 31, 2017. This will be simplified to integrate
USAID comments, and resubmitted.
USAID emphasized that the date provided by Tt ESP is
very high confidence (factoring in all concerns).
Tt ESP
July 17, 2017
7
USAID questioned whether it may be possible to do
commissioning with a diesel generator. Tt ESP noted it
would be possible with the correct size generator, which
Tt ESP estimated to be about 1 megawatt. USAID will
discuss this possibility with DABS.
FYI FYI FYI
8
USAID requested that Tt ESP provide a summary of
invoices to date. Tt ESP had recently submitted this
summary to USAID OBMs. USAID will request should
any additional information be needed from Tt ESP.
FYI FYI FYI
5. PHOTOGRAPHS
Photo #1: Setting out steel reinforced bars for the
drainage ditches at roads B, Ghazni Substation. HM, 2017-
07-31.
Photo #2: Compacting subgrade and base coarse
materials in preparation for road G, Sayedabad
Substation. AR, 2017-08-02.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
11 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0010 NEPS-SEPS CONNECTOR TRANSMISSION LINES
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
On August 1, 2017, the Ministry of Finance (MOF) transferred the mobilization payment to
contractor. DABS is in the process of issuing full Notice to Proceed (NTP) to the contractor.
From July 19 to July 25, 2017, Tt ESP witnessed the Factory Acceptance Test (FAT) for tower
type DC at the contractor’s manufacturer’s company. Two of Tt ESP’s engineers witnessed
the test, and confirmed that the test results were in general conformance with the approved
design and contract requirements.
Tt ESP is in the process of finalizing the FAT Reports for tower types DA, DB, and DC. Both
FAT Reports will submitted to USAID by August 8, 2017.
The contractor continued to finalize the initial line route survey and will submit the draft
report to Tt ESP and DABS by August 8, 2017. The contractor is in the process of plotting
locations which were not accessed in the initial line route survey.
Tt ESP is in the process of reviewing the contractor administrative submittal for Price Breakup
for the Ghazni-Kandahar Transmission Line project. The submittal review will be completed
by August 6, 2017.
2. UPCOMING ACTIVITIES
DABS will review the initial line route survey and will assign a DABS representative to verify
the line route site survey.
Upon resolution of site security concerns, the contractor will continue the detailed line route
survey.
3. ISSUES
The detailed line route survey is halted due to site security concerns.
4. ACTION ITEMS / KEY NOTES
# Item Action By
Orig.
Due Date
Revised
Due Date
1
Assuming a construction NTP of August 10, 2017, the
expected project completion date is January 10, 2020, based
on a period of performance of 29 months.
FYI FYI FYI
2
Tt ESP is to provide the submittals log to USAID with the
submission timeline at the deep dive meeting when provided
by the contractor.
The contractor has yet to submit the approved master
submittal time line to Tt ESP. In weekly coordination meeting
contractor stated the submittal list will be transmitted to Tt
ESP by July 25, 2017.
The contractor has submitted the master document list on July
23, 2017. The list is under review by Tt ESP.
Tt ESP
May 2,
2017
July 25,
2017
3
The contractor to submit its pre-construction plans.
In a weekly coordination meeting, contractor stated that the
pre-construction plans will be submitted by August 1, 2017.
The contractor will submit the pre-construction plan on
August 4, 2017
KEC
May 30,
2017
August 4,
2017
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
12 Bi-Weekly Report No. 7: Report Ending 2017-08-03
# Item Action By
Orig.
Due Date
Revised
Due Date
4
On July 11, 2017, DABS has submitted the request for
reimbursement letter (RFRL) for 10 percent mobilization
payment to USAID’s Office of Financial Management (OFM).
USAID requested that (Tt ESP embed at DABS)
follow up with DABS on the above mentioned invoice to
ensure that DABS sends the request for payment to USAID.
USAID requested that provide a status update via
phone by COB Wednesday, July 12, 2017.
Ministry of Finance (MOF) has transferred the mobilization
payment to contractor. DABS will issue the NTP by August 3,
2017.
Tt ESP
Ongoing August 3,
2017
5
DABS to submit 10 percent Mobilization Invoice to USAID.
On July 11, 2017, DABS has submitted the request for
reimbursement letter (RFRL) for 10 percent mobilization
payment to USAID’s Office of Financial Management (OFM).
DABS
(
July 13,
2017
July 11,
2017
6
The FAT report for Tower type DA, DB, and DC is under Tt
engineering review and will be submitted to USAID by August
8, 2017
Tt
July 12,
2017
August 8,
2017
7 Tt ESP will submit all FAT reports to USAID after finalization. FYI FYI FYI
8
The FAT for insulators is anticipated to be held in China. Tt
ESP will send the regular request for travel approval to USAID
for the one Tt representative who will witness this FAT.
Tt has taken USAID approval for Insulator FAT. Tt will send
one electrical engineer to witness the test.
Tt ESP
July 14,
2017
July 30,
2017
5. PHOTOGRAPHS
Photo #1: Tower type DC, FAT test at KEC
manufacturing company, India. KEC, 2017-07-26.
Photo #2: Tower type DC, FAT test at KEC
manufacturing company, India. KEC, 2017-07-26.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
13 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0011 NEPS-SEPS CONNECTOR SUBSTATIONS
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
Nothing to report.
2. UPCOMING ACTIVITIES
DABS is to arrange the negotiation meeting with the winning bidder to review contract
documents and remarks from the NPC.
The Special Conditions of Contract (SCC) is under review by USAID since April 16, 2017.
USAID to review and provide approval and/or comments.
DABS is to issue Notice of Award to the winning bidder upon successful review of the contract
documents.
On July 6, 2017 USAID stated that JO-P-0011 is under review by the Office of the Inspector
General (OIG), and no action will be taken until the review is completed.
NPC approved the award of the contract to CEEG under their letter dated May 31, 2017.
3. ISSUES
This is a 36-month construction project. Funding will expire September 30, 2019.
Further processing of the contract for this Job Order is pending review by OIG.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1
Assuming a construction contractor NTP of July 6, 2017, the
expected project completion date is July 6, 2020, based on a period
of performance of 36 months.
FYI FYI FYI
2 Tt ESP is to print a hard copy of the complete contract documents,
following approval by all relevant stakeholders. FYI FYI FYI
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
14 Bi-Weekly Report No. 7: Report Ending 2017-08-03
JO-P-0012 SALANG TUNNEL SUBSTATION
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
To date, Tt ESP has received 125 submittals out of 583 anticipated Rev0 submittals from the
contractor. This includes 53 resubmittals, 50 approved, 28 approved as noted, 42 disapproved,
three under review and two cancelled submittals. Of 72 Rev0 submittals, 50 are approved, ten
are approved as noted, seven are disapproved, three under review, and two are cancelled.
On August 2, 2017, as per a phone call with the DABS PIU Director, Amendment No. 2 to
the contract has already been signed and stamped by the contractor and DABS. However,
since July 30, 2017, Amendment No. 2 is with MOF for signature by the MOF controller. The
DABS PIU Director noted that DABS CEO will help take care of this issue.
Excavation for concrete stairs and cantilever wall foundation is in progress.
Steel rebar cutting and fabrication for the living quarters building and retaining walls are in
progress.
Concrete pouring and curing for the foundation of counterfort retaining wall are in progress.
Removal of debris from the job site is in progress.
On July 24, 2017, the contractor submitted the baseline construction schedule, which is in line
with the contract period of performance (POP), for Tt ESP’s review.
2. UPCOMING ACTIVITIES
Tt ESP to review the baseline schedule and return to the contractor by August 7, 2017.
The contractor to provide the Afghanistan Builders Association (ABA) certification for their
third party’s onsite laboratory to DABS and Tt ESP prior to conducting concrete testing. If
the contractor does not provide this certification, the contractor must test the concrete
samples at an offsite, certified laboratory.
3. ISSUES
The contractor’s third party onsite testing laboratory has been inspected and awaits
Afghanistan Builders Association (ABA) certification. Immediate testing requirements may
need to be conducted at an offsite, certified laboratory.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1 Tt ESP to review the baseline schedule. Tt ESP (PC
Team)
August 7,
2017
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
15 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0005: VERTICAL STRUCTURES (VS)
JO-VS-0013 AMERICAN UNIVERSITY OF AFGHANISTAN (AUAF) QA SERVICES
1. ACCOMPLISHMENTS, EVENTS, PROGRESS.
During this reporting period, review of construction submittals was ongoing.
On July 27, 2017, Tt ESP shared Observation Report (OBSR) No. 2, on slow progress, with
USAID.
During this reporting period, the following activities were completed:
o Exterior plastering work.
o Installation of the polyvinyl chloride (PVC) window frames.
o Main distribution panel and transformer cable connection.
o Communications room cable pulling.
o Installation of the conduits and cable pulling for public address system.
o Installation of the automatic transfer switch.
During this reporting period, the following activities were in progress:
o Fabrication of gutters and down spouts.
o Installation of the first floor windows burglar bars.
o Dry walls insulation work.
o Installation of the interior electrical switches, receptacles and lighting fixtures.
o Installation of the suspended celling.
o Installation of the stairs’ handrails.
o Window glazing activity.
o Fabrication and installation of the ventilation ducts.
o Installation of the walls’ and floor ceramic tiles.
o Interior primer paint applications.
o Interior walls final paint.
o Installation of the window frames.
o Installation of the heating system pipes.
o Installation of the fire sprinkler system pipes and fittings.
o Installation of the water pipes inside the building.
o Installation of toilets’ plumbing fixtures.
During this reporting period, the following activities were started:
o Installation of fuel tank.
o Installation of the honed marble veneer for exterior walls.
o Roof insulation work.
During this reporting period, the following meetings occurred:
o On July 22, 2017, a safety toolbox meeting on electrical hazards was held.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
16 Bi-Weekly Report No. 7: Report Ending 2017-08-03
o On July 25, 2017, the weekly progress meeting was held.
o On July 29, 2017, a safety toolbox meeting on housekeeping was held.
2. UPCOMING ACTIVITIES
In the next reporting period, the following activities are anticipated to continue:
o All of the in progress activities in the section above, and activities not reported as
completed, will be continued during the upcoming reporting period.
o Installation of the fire doors.
o Construction of the sidewalks.
o Installation of the circulation pump and accessories
3. ISSUES
The majority of the activities planned for progress are either not yet started, delayed, or have
had no progress for many consecutive days. This trend of slow progress has been consistently
observed against all the look ahead plans the contractor has submitted to date.
Some of the mechanical long lead items are not available in the local market. Tt ESP
recommends to hold a separate meeting, or invite the contractor’s heating system
subcontractor to the weekly progress meeting, to discuss the relevant procurement status
and find alternative solutions.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
2
USAID noted many reasons from contractor regarding delays,
and requested that Tt ESP closely follow to identify key
reasons for slow progress. USAID will also raise this at the
Weekly Coordination Meeting. Tt ESP noted that the
contractor needs to submit a recovery plan to the schedule.
Tt ESP
July 20,
2017
5. PHOTOGRAPHS
Photo #1: Exterior walls honed marble installation,
AUAF. YK, 2017-08-01.
Photo #2: Dormitory building front side view, AUAF.
MA, 2017-07-28.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
17 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0006: ROADS (R)
JO-R-0017 WARRANTY INSPECTION, QA, AND FINAL INSPECTION SERVICES FOR
GARDEZ TO KHOST (G-K) ROAD (PHASE IV)
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
On July 24, 2017, Tt ESP submitted the Final Inspection and Warranty Acceptance Report
Rev1 to USAID. USAID noted acceptance of this report on the same day.
On July 25, 2017, Tt ESP collected signatures from the USAID and contractor to the accepted
Final Inspection and Warranty Acceptance Report Rev1.
On July 26, 2017, Tt ESP submitted the signed, accepted Final Inspection and Warranty
Acceptance Report Rev1 to USAID.
On July 26, 2017, Tt ESP sent closure of NRC-0001-CW Rutting Repair to the contractor.
On July 26, 2017, Tt ESP sent administrative closure of NRC-0001H&S Health and Safety
Violations to the contractor.
On July 31, 2017, Tt ESP sent a Job Order closure notification to USAID.
2. UPCOMING ACTIVITIES
USAID to evaluate and send closure of this Job Order to Tt ESP.
3. ISSUES
Nothing to report.
4. ACTION ITEMS / KEY NOTES
# Item Action By
Orig. Due
Date
Revised Due
Date
1
Following submittal of the Final Warranty Punch List
(PL), USAID will address any additional needs. As per Tt
ESP’s understanding, this action closed.
FYI FYI FYI
2
MECC to provide to Tt ESP record (1)Test results
for Maximum specific gravity (density) determined for
each days production according to the used
standards.(2) Test results for Wearing Course Bulk
specific gravity (density) determined for each days
production for Wearing Course according to the used
standards.(3) Provide any contractual documents
showing using 92 % VS 95% compaction requirements.
MECC
FYI FYI
3 Tt ESP to resubmit the Final Inspection and Warranty
Acceptance Report to USAID for approval.
Tt ESP
July 24,
2017 July 24, 2017
4
Tt ESP to submit the signed Final Inspection and
Warranty Acceptance Report to USAID, after receipt
of USAID approval.
Tt ESP
July 26,
2017 July 26, 2017
5 USAID to evaluate and send closure of the Job Order to
Tt ESP.
USAID
(
[Date to
be
inserted]
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
18 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0007: OTHER ENERGY & WATER (EW)
JO-EW-0015 KAJAKI HYDROPOWER OPERATIONS SUPPORT
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
This Job Order has been closed by USAID, and will be removed from future ESP Bi-Weekly
Reports.
2. UPCOMING ACTIVITIES
Nothing to report.
3. ISSUES
Nothing to report.
4. ACTION ITEMS / KEY NOTES
# Item Action By
Orig. Due
Date
Revised
Due Date
1 USAID has formally closed this Job Order USAID
July 23,
2017 July 23, 2017
5. PHOTOGRAPHS
Nothing to report.
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
19 Bi-Weekly Report No. 7: Report Ending 2017-08-03
CLIN 0008: INTERNSHIP & CAPACITY BUILDING (ICB)
JO-ICB-0007 INTERNSHIP PROGRAM FOR AFGHAN WOMEN IN ENGINEERING
AND ARCHITECTURE
1. ACCOMPLISHMENTS, EVENTS, PROGRESS
From July 22 to August 3, 2017, the interns continued plumbing training, including theory and
practical assignments, led by a Tt ESP Mechanical Engineer.
From July 22 to August 3, 2017, interns continued site visits to the ESP office expansion site.
On July 24, 2017, the interns completed the basics of structures class, and were assigned to
begin research on durability and toughness of construction materials.
From July 29 to August 3, 2017, interns continued drafting and revising assignment memos to
respond to comments from reviewers.
On July 31, 2017, interns began reviewing pre-construction submittals for an ESP project, as
part of their capacity building and on-the-job training.
2. UPCOMING ACTIVITIES
From August 5 to 17, 2017, the interns will participate in a water supply training taught by the
Tt ESP Mechanical Engineer. This training will include theory and practical assignments.
From August 6 to 17, 2017, the interns will participate in an electrical wiring training led by
Tt ESP’s electrical engineering department.
From August 5 to 17, 2017, interns will continue reviewing pre-construction submittals as part
of their on-the-job training.
From August 5 to 12, 2017, interns will continue to participate in the plumbing training.
On August 10, 2017, interns will attend a shadowing event at USAID, pending confirmation
from the USAID POC.
On August 15, 2017, interns will attend a site visit at AUAF dormitory construction site,
security permitting.
From August 5 to 17, 2017, interns will continue their research on basics of structures, and
begin drafting their assignment memos.
3. ISSUES
Nothing to report.
4. ACTION ITEMS / KEY NOTES
# Item Action By Orig. Due
Date
Revised
Due Date
1 USAID is to schedule a shadowing event with Tt ESP
interns.
USAID
May 31,
2017
August 30,
2017
2
Tt ESP noted that thus far, attempts to set up a
Memorandum of Understanding (MOU) with universities so
that the internship program participants could receive
university credit have not been successful. Tt ESP will
continue to resolve this issue with universities.
Tt ESP
Ongoing Ongoing
Engineering Support Program (ESP)
Contract No. AID-306-C-16-00010
20 Bi-Weekly Report No. 7: Report Ending 2017-08-03
# Item Action By Orig. Due
Date
Revised
Due Date
Tt ESP noted there has been minimal luck obtaining the
credit, so Tt ESP will proceed in finalizing the MOU without
pursuing academic credit for the internship.
3
USAID is to schedule a meeting with USAID’s PROMOTE
Women in the Economy (WIE) project, and intends to
invite Tt ESP to participate and discuss how PROMOTE can
help interns seeking jobs.
USAID
April 30,
2017
July 30,
2017
4 USAID is to schedule a site visit for interns at US Embassy
to view the buildings under construction.
USAID
August 30,
2017
5. PHOTOGRAPHS
Photo #1: Interns during Plumbing training, Kabul.
MNG, 2017-07-30.
Photo #2: Intern attend the basics of structures
training, Kabul. MNG, 2017-07-22.