Enhancing Social Stabilization and Cohesion through Supporting Agro Value Chain
Development Project in South Sudan
(Project Number 180209)
PROJECT PROGRESS REPORT
For the Period from April to September 2019
Project Executed by:
UNITED NATIONS INDUSTRIAL DEVELOPMENT ORGANIZATION
Project Funded by:
THE GOVERNMENT of JAPAN
2
Project Details
Project number 180209
Project title Enhancing Social Stabilization and Cohesion through
Supporting Agro Value Chain Development Project in
South Sudan
Government Cooperating
Agency
Ministry of Trade Industry and East Africa Community
Affairs
Government Cooperating
Agency
Ministry of Agriculture and Food Security
Ministry of Health
South Sudan National Bureau of Standards
South Sudan Drug and Food Control Authority
National Public Health Laboratory
Executing Agency United Nations Industrial Development Organization
Donor Government of Japan
Donor Funds US$ 712,500
Project Starting Date April 2019
Duration and expected completion date
12 months (March 31, 2019)
3
Table of Contents
Project Details ............................................................................................................................ 2
List of Tables .............................................................................................................................. 4
List of Figures ............................................................................................................................. 4
Abbreviations ............................................................................................................................. 5
1. Introduction ........................................................................................................................ 6
1.1 Project Context ............................................................................................................ 6
1.2 Current Status of IDPs ................................................................................................. 7
1.3 Country Social and Economic Profile .......................................................................... 8
1.4 Overview of Agriculture and Agro-processing Sector in South Sudan........................ 9
1.5 Groundnuts and Sesame Sub-Sectors in South Sudan .............................................. 10
1.6 Commodity Price ....................................................................................................... 12
2. Project Inception .............................................................................................................. 13
2.1 Identification of Project Beneficiaries ....................................................................... 13
2.2 Identification of Implementing Partners ................................................................... 14
2.3 Establishment of a Project Steering Committee (PSC) ............................................. 17
3. Project Strategy .................................................................................................................... 18
3.1 Output 1: Operationalize the Laboratories at SSNBS and DFCA ............................... 18
3.2 Output 2: Provide Income IDPs and Host community with an Income Generating
Opportunity .......................................................................................................................... 18
4. Project Implementation.................................................................................................... 19
4.1 Output 1: Basic facilities for agro-processing established ........................................ 19
4.2 Output 2: IDPs and host communities trained in agro-processing and
entrepreneurship development skills .................................................................................. 25
5. Challenges experienced during Implementation of the Project ...................................... 32
6. Donor and Project Visibility .............................................................................................. 33
7. Onward Project Implementation for October 2019 to March 2020 ................................ 33
Annexes .................................................................................................................................... 35
Annex 1: Minutes of the First Project Steering Committee (PSC) held on 4 July 2019 ........... 35
Annex 2 Training content for food safety and hygiene for officials of the Government of
South Sudan ............................................................................................................................. 39
Annex 3 Training content for food safety and hygiene for IDPs and host community
members .................................................................................................................................. 40
Annex 4: Article regarding the project activities in Don Bosco and the visit of the
Ambassador of Japan to South Sudan (14 September 2019) .................................................. 41
Annex 5 Status of progress on the project implementation ................................................... 42
4
List of Tables
Table 1 Major IDPs concentrated counties as of June 2019 ...................................................... 8
Table 2 Summary economic status of South Sudan- 2017 ........................................................ 9
Table 3 Summary of commodity prices in South Sudan as of May 2019 ................................ 12
Table 4 Recommendations for SSNBS and DFCA ..................................................................... 23
Table 5 Summary of feedback on the training of food hygiene and safety ............................ 24
Table 6 Summary of feedback from the TOTs in the EDP training .......................................... 28
Table 7 Summary of feedback from the TOTs in the VSLA training ........................................ 30
List of Figures
Figure 1 Estimated IDPs per county as of March 2019 .............................................................. 7
Figure 2 Synopsis of sesame sector in South Sudan ................................................................ 10
Figure 3 Synopsis of groundnut sector in South Sudan ........................................................... 10
Figure 4 Value chain map for sesame in Juba, South Sudan ................................................... 11
Figure 5 Value chain map for groundnuts in Juba, South Sudan ............................................. 11
Figure 6 A sample of edible G/nut and Sesame oil currently in Juba Market- from UNIDO
survey ....................................................................................................................................... 12
Figure 7 Composition of IDPs and HC members from the mobilized 6 groups as of September
2019 (Unit; persons) ................................................................................................................ 14
Figure 8 Some of equipment at SSNBS .................................................................................... 15
Figure 9 H.E Ambassador Mr. Seiji Okada witnessing the signing of MoU on 10 September
2019 ......................................................................................................................................... 16
Figure 10 H.E Ambassador Mr. Seiji Okada after closing the Food Safety and Hygiene
seminar for project beneficiaries of Mazerello Women Promotion Centre (MaWoC) ........... 17
Figure 11 Member of the Project Steering Committee after its Launch on 04th July 2019 ... 17
Figure 12 Project Business Strategy for Project Implementation ........................................... 19
Figure 13 Project Intervention for Output 2 ............................................................................ 19
Figure 14 Site-pictures for pre-construction at MaWoc on 13 Sept 2019 .............................. 20
Figure 15 Staff of DFCA and SSNBS at a 1 day workshop on Food Safety and Hygiene .......... 21
Figure 16 Some of equipment at SSNBS yet to be operationalized ........................................ 22
Figure 17 Beneficiaries at a session of food safety and hygiene ............................................. 26
Figure 18 A group member leading fellow beneficiaries in EDP training ................................ 27
Figure 19 A ToT carrying out an EDP training to group members ........................................... 27
Figure 20 A sample of savings kit to be provided to the 7 groups .......................................... 30
5
Abbreviations
Agro Processing Training Centre APTC
Drug and Food Control Authority DFCA
Entrepreneurship Development Programme EDP
Government of Japan GoJ
Government of South Sudan GoSS
Host community HC
Internally Displaced Persons IDPs
International Organization for Migration IOM
Mazerello Women Promotion Centre MaWoC
Ministry of Trade, Industry and East Africa Community Affairs MTI &EAC
National Project Coordinator NPC
National Project Officer NPO
Project Steering Committee PSC
South Sudan National Bureau of Standards SSNBS
Technical Project Adviser TPA
United Nations High Commission for Refugees UNHCR
United Nations Industrial Organization UNIDO
Village Savings and Loan Association VSLA
World Food Program WFP
6
1. Introduction
1.1 Project Context
The project’s objective is to enhance self-reliance and resilience of IDPs and host communities
and to contribute to social stabilization and cohesion. It received funding of USD 712,500 from
the Government of Japan in March 2019, and effectively started implementation on 01st April
2019. The project focuses to work with at least 200 IDPs and their host community in Juba-
South Sudan, aiming to implement two outputs, i.e.
(i) Basic facilities for agro-processing established.
(ii) IDPs and host communities trained in agro processing and entrepreneurship
development skills.
This project has been established on the background of post conflict era of two civil conflicts
in South Sudan, i.e. December 2013 and July 2016, that have almost wiped out all gains the
country had built from its independence of July 2011. These two conflicts have led to at least
1.9 million South Sudanese to become Internally Displaced Persons (IDP) and around 2.3
million South Sudanese to flee to neighboring countries, as reported by UNHCR in June 2019.
The country still remains vulnerable to instability and hence limiting opportunities for
investment. The general sentiments inside and outside South Sudan is “A wait and see
altitude”, of the outcome of the 12 November 2019, when South Sudan is expected to form
a new cabinet for the transitional government. This cabinet will include both the opposition
and current government, and will be formed on the back of some preconditions like
The number of states to be used in South Sudan and
To gazette and finance military cantonment prior to a unified army.
Due to this conflict, the country’s ability to produce and mobilize investments has been
depleted. This has affected around seven million people being pushed into food insecurity
with high levels of unemployment. The country is experiencing increased level of
unproductiveness in the agricultural sector, on which almost 90% of the population depend.
The situation is further negated by low agricultural productivity combined with low
infrastructure which could support increasing access to market and inclusive finance.
7
1.2 Current Status of IDPs
According to the Data Collection for Mobility Tracking Round 5, which was carried out by IOM in
March 2019 to identify possible changes in displacement and return dynamics in South Sudan, Juba
in Central Equatorial is one of the regions where hosts the highest number of IDPs (at 6% to
the country’s IDP population).
Figure 1 Estimated IDPs per county as of March 2019
Source: IOM
Overall, one-third of IDPs lives across the 94 displacement sites identified by IOM
Displacement Tracking Matrix (DTM) in Round 5, and the other two-thirds are living in host
community settings. The proportion of IDPs living in displacement sites was especially high in
Unity State and Central Equatoria (both hosting large UN Protection of Civilians (PoC) sites)
with 53% each.
The table below also describes the estimated IDPs in Juba; i.e. 81,504, behind Rubkona and
Awerial in Unity and Lakes States respectively.
8
Table 1 Major IDPs concentrated counties as of June 2019
State name County name Estimated # of IDPs (Individual)
% of IDPs in Total
Unity Rubkona 127,437 9%
Lakes Awerial 110,680 8%
Central Equatorial Juba 81,504 6%
Western Bahr El Ghazal Wau 64,461 5%
Upper Nile Luakpiny (Nasir) 61,459 4%
Warrap Tonj North 59,082 4%
Western Bahr El Ghazal Jur River 58,877 4%
Unity Pariang (Ruweng) 35,674 3%
Jonglei Fangak 34,651 2%
Lakes Yirol East 33,305 2%
Upper Nile Malakal 32,122 2%
Others 720,937 51%
Total 1,420,189 100%
Source: IOM
1.3 Country Social and Economic Profile
1.3.1 Poverty and national economic situation
There is still a large number of gender exclusiveness with respect to education and food
insecurity that is almost at the same level. From the UNIDO brief profile of the beneficiaries
done in September 2019 during training, at least 65% of the girls drop out of school due to
preference to boys’ education to the girl’s with few resources. The survey also reflected a
heavy existence of forced marriage and raping of girls at 55% and 30% respectively, which
continually disadvantages the girl child in South Sudan.
It was also reflected from the respondents that food security and a lack of adequate capital
as key needs amongst beneficiaries estimated at 60%.
1.3.2 Economic development status of South Sudan
South Sudan’s economy has been in the decline since 2013 civil war. The country’s GDP as
reported by the World Bank in 2017 was USD2.9 billion (2017) from 17.27billion (2010). It has
been going through negative growth at 13.8% in 2017 and having almost 82% of the
population under poverty.
9
Table 2 Summary economic status of South Sudan- 2017
Source: World Bank (2017)
The Revitalized Agreement on the Resolution of the Conflict in South Sudan (R-ARCISS), signed
by the government, the opposition and civil society on September 12, 2018 in Addis Ababa is
seen as a fresh opportunity for South Sudanese to build durable peace in the country. The oil
production had declined to 120,000 barrels per day after the conflict from levels of 350,000
barrels prior to the recent civil war. This has somehow increased to 245,000 by mid-2019 (as
reported by East Africa newspaper 12-18 Oct’19), which is aligned to the relative fragile peace
the country is experiencing. It is estimated that 90% of the Government of South Sudan
(GoSS) revenue is provided by oil, and thus any dent in its production or market will negatively
impact its revenue bag. This also gives the validity for the GoSS to increase efforts of
diversifying its economy to sectors like agricultural and manufacturing.
It is anticipated that if peace holds after a successful formation of a transition government in
November 2019, South Sudan is likely to see a big increase of investment in humanitarian and
development activities especially in agricultural and manufacturing. These could be exploited
by some of the initiatives that UNIDO has started.
1.4 Overview of Agriculture and Agro-processing Sector in South Sudan
Agriculture is the backbone of the economy of South Sudan. The agricultural industry has
significant potential and around 90% of South Sudan's land is arable, with about 50%
considered prime agricultural land and not more than 4% of it is fully utilized under active
agricultural. The sector host almost 90% of the households and 66% employment (as per 2017
World Bank report). It is evident that about 80% of the population lives in rural areas
depending on agriculture, forestry and fisheries as a primary source of livelihood for a
majority of the households. Much of the rural sector activity is currently focused on low-input
low-output subsistence agriculture instead of production for markets. It is constrained by
lack of professionalized agro based skills, low access of improved seed and other input, access
to market infrastructure and market information, low application of modern technologies in
post-harvest/ processing and a low ability to access finance.
10
There is little evidence of agro processing in South Sudan, which is mainly around donor
related support for organized farmer groups/cooperatives in regions like Gbduwe- Yambio
and Kajo Keji.
1.5 Groundnuts and Sesame Sub-Sectors in South Sudan
The following figures describe the synopsis of sesame and groundnuts sector, as well as the
value chain of sesame and groundnuts in South Sudan.
Figure 2 Synopsis of sesame sector in South Sudan
Figure 3 Synopsis of groundnut sector in South Sudan
11
Figure 4 Value chain map for sesame in Juba, South Sudan
Figure 5 Value chain map for groundnuts in Juba, South Sudan
12
1.6 Commodity Price
The report from the WFP-price monthly monitoring
reported a continuance devaluation of the SSP, which
in May 2019 was at SSP278 per one US dollar (informal
market) while it was SSP159 a year ago at the formal
market ( a spread of 75% over the official rate). As of
September 2019, the informal market rate was at
SSP310 per one US dollar.
In May 2019, the WFP also reported that the price of
groundnuts (G/Nuts) in Juba rose the highest to
SSP550/kg compared to SSP430/kg in March 2019
with the highest price for white sorghum was SSP
171/kg (in Mingakaman).
Table 3 Summary of commodity prices in South Sudan as of May 2019
Source: WFP
At the time the project carried out a market research in July 2019, for edible G/Nut and
sesame oil in Juba, the retail selling price for G/Nuts and Sesame per kg was at SSSP 450 and
SSP 550 respectively. The retail selling price for a processed 450 ml edible oil from G/Nut was
SSP500 while 250ml of sesame was SSP500 respectively.
This reflects great potential for value addition in the G/Nut and sesame sector, if there is
appropriate production supply and processing technology capacity, for retail price of G/Nuts
in Juba being of SSP400-500/kg.
Commodity Highest Price Lowest Price
Market Price (SSP)
Market Price (SSP)
White Sorghum (kg) Mingkaman 171 Yambio 54
Ground Nuts- Shelled (Kg) Juba 430 Wau 171
White Maize (Kg) Aweil 114 Kapoeta South
49
Cooking Oil (liter) Bunj 1,000 Kapoeta South
195
Petrol (liter) Malakal 600 Juba 228
Diesel (liter) Malakal 500 Juba 218
Figure 6 A sample of edible G/nut and Sesame oil currently in Juba
Market- from UNIDO survey
13
2. Project Inception
The project is focused on equipping IDPs and host communities with agro processing and
entrepreneurship skills. The support for these people in South Sudan is led by the Relief and
Rehabilitation Commission (RRC), IOM, UNHCR and other non-governmental agencies.
Output 2 will be supported institutionalized agro processing and training facilities with the
MTI&EAC in Output1.
2.1 Identification of Project Beneficiaries
The project engaged and is still engaging with some agencies as IOM and UNHCR as they are
the lead UN agencies in the IDP and refugee sector. The project hence had to use a criteria
used to select appropriate IDP camp and their host community to work with. The criteria for
selection were;
a. Level of organization of the host community and to participate in the project
b. Level of stability of the IDPs within the host community
c. Access to land for the agro processing facility and agro-production and ability for its
management.
d. Ongoing activities of the IDPs within the host communities
e. UNDSS security clearance for UNIDO, i.e. to work within Juba- Zone One and its
neighborhood
Through IOM and its guidance, the project engaged Don Bosco church compound and through
UNHCR, the project accessed Mahad IDP collective site.
Don Bosco church compound (around 247 acres) is located in Gumbo and managed by a
Roman Catholic institution, the Salesians of Don Bosco (SDB). In this compound, the Salesian
Brothers and Priests, the Salesian Sisters of Don Bosco and Caritas Sisters with a Japanese
NGO, JCCP, assist the IDPs with shelter, medical care, sanitation, food and water and
education.
Mahad IDP collective site is located in Konyokonyo in Juba and hosts over 5,000 IDPs. The
IDPs reside in the compound of Mahad Juba Secondary School, which is next to the old
mosque.
Don Bosco was selected for the following reasons:
a. The Salesian Sisters of Don Bosco had started engaging the IDPs in enterprise work
like confectionary and tailoring, as well as were currently working on agricultural
activities in 40 acres of farmland, inter alia, groundnut production and poultry.
b. Through the Salesian Sisters, Don Bosco could introduce the project Mazerello
Women Promotion Centre (MaWoC) to mobilize women, who could be the main
project beneficiaries.
14
c. Don Bosco Brothers and Priests manage a vocational training center to provide the
youth with vocation training courses including carpentry, plumbing and motor vehicle
which could later be exploited, and more attractive to the youth.
As of September 2019, together with MaWoC, the project has mobilized 200 women and 30
youth into 7 groups. The project has trained 14 trainers of training (ToTs) towards starting
coaching and mentoring the 7 groups in entrepreneurship development programme (EDP)
and Village Savings Loan Association (VSLA) as well as facilitate them to start pilot processing
of groundnuts and sesame oil.
The number of the IDPs and host community (HC) members per each group is described in
the figure below. Among the 6 groups, the members of the host community occupies around
17%.
Figure 7 Composition of IDPs and HC members from the mobilized 6 groups as of September 2019
(Unit; persons)
2.2 Identification of Implementing Partners
The project identified the following partners to implement the project.
(i) Output 1: Ministry of Trade, Industry and East African Community Affairs (MTI&EAC)
and Ministry of Health
The project will provide support to South Sudan National Bureau of Standards (SSNBS) under
MTI&EAC and South Sudan Drug and Food Control Authority (DFCA) under Ministry of Health
to enhance their capacities for carrying out standards and quality testing of agro processed
food. This component is mainly implemented through SSNBS and DFCA whose laboratories
have been assessed and recommendations to address shortcoming discussed. In addition, the
project has trained 7 staff each from DFCA and SSNBS in standards and quality testing and
food safety and hygiene.
16
(iii) Output 2: Mazerello Women Promotion Centre (MaWoC)
The Mazerello Women Centre (MaWoC) managed by the Salesian Sisters of Don Bosco was
selected as the implementation partner of Output 2. A formal Memorandum of
Understanding (MoU) between the project and MaWoC was entered on 10 September 2019
witnessed by the Ambassador of Japan to South Sudan, H.E. Mr. Seiji Okada.
Figure 9 H.E Ambassador Mr. Seiji Okada witnessing the signing of MoU on 10 September 2019
The project works with the IDPs and host communities through the MaWoC with the full
communication and authority of the Head of the Local Payam (Rajaf). The Payam authorities
are aware of the activities of the project and liaise with the national security personnel to
legalize the training activities of the project.
The key staff of the MaWoC, whom the project works with are; Head of Agricultural and
Extension and Head of Cooperatives. It is expected that the continued good will support from
the Payam local authorities will facilitate in continued mobilizing of the community to serve
the planned installed processing plant for communal use. This approach is also good for
sustainability, as the host community and local authorities will be able to carry on with the
activities of the project once UNIDO completes the project implementation.
The next 3 months of October-December 2019, the project intends to keep the momentum
on all fronts, especially in Output 1 in relation to establishing the 2 facilities of agro processing;
a training center at an identified site at SSNBS and an oil processing plant for communal use
at the MaWoc in Don Bosco church compound.
17
Figure 10 H.E Ambassador Mr. Seiji Okada after closing the Food Safety and Hygiene seminar for project beneficiaries of Mazerello Women Promotion Centre (MaWoC)
2.3 Establishment of a Project Steering Committee (PSC)
The project cuts across more than two institutional sectors. It was thus agreed with the
MTI&EAC to establish PSC, composed of key stakeholders from government, Embassy of
Japan and UNIDO.
Implementation of the project has eventually gained momentum on all key output
components. There has been significant progress in the last 3months since July’2019, when
the Project Steering Committee (PSC) was established and launched under the co –chair of
the Under Secretary of MTI&EAC- Hon Mou Mou.
Figure 11 Member of the Project Steering Committee after its Launch on 04th July 2019
18
The role of the PSC is to oversee and provide guidance in the implementation of the project’s
two components, as well as quickly address in bottleneck that may exist between any
stakeholders during implementation. The PSC was launched on 04 July 2019 and is jointly co-
chaired between Undersecretary of MTI&EAC and UNIDO. The PSC was opened and chaired
by the Undersecretary of Ministry of Trade, Industry and East Africa Community Affairs
(MTI&EAC), the Hon Mou Mou.The minutes to the first PSC meeting are attached as Annex 1.
The next PSC meeting will take place in February 2020.
3. Project Strategy
3.1 Output 1: Operationalize the Laboratories at SSNBS and DFCA
The laboratories at SSNBS and DFCA will be operationalized for enhancing the capacity
building of the Government of South Sudan in testing food safety and quality standards for
agro processed foods through the training and the provision of minor equipment as well as
consumables.
3.2 Output 2: Provide Income IDPs and Host community with an Income Generating
Opportunity
The livelihood of IDPs and host community will be supported for strengthening social
cohesion of the IDPs and host communities by equipping them with skills and capacity of agro
processing and business entrepreneurship.
The project although is originating from a relief perspective, it is venturing in piloting to
establish economically viable enterprise for IDPs and their host community members towards
engaging in an economically viable project.
It is thus envisaged if their host community members are equipped with economic skills and
facilitated with a value addition processing plant as well as engage in a competitive value
chain like groundnuts and sesame, they would be able to earn some extra income.
The IDPs and their host community members will be able to access a ready market for their
produce and purchases at favorable prices. When the plant operationalizes and economically
becomes profitable, they will be able to have a share of the profits from the sales of processed
oil. This will be through percentage share for every kg sold for given percentage of profits.
The additional income from Village Saving and Loan Association (VSLA) per member, may also
add to additional capital for the members in procuring/supplying required raw material to the
plant.
The project business strategy and building blocks are described in the figures below;
19
Figure 12 Project Business Strategy for Project Implementation
Figure 13 Project Intervention for Output 2
4. Project Implementation
4.1 Output 1: Basic facilities for agro-processing established
Output 1 has been implemented through 3 sub items of;
(i) Establishing an agro processing training center (APTC)
The project initiated discussions with the Ministry of Trade, Industry and East African
Community Affairs (MTI&EAC) over identifying a suitable land/a place for the establishment
20
of a pilot food processing plant in the area of Food Processing Centers (FPCs) established in
the previous Japanese supplementary budget (JSB 2016) funded project; before the launch of
the PSC meeting. During the course of discussion with the MTI&EAC, both the project and the
MTI&EAC found that the locations of the FPCs were not so suitable for the pilot food
processing plant due to the security deterioration and the congestion around these areas.
Moreover, the MTI&EAC proposed the project not to build the FPC but an agro-processing
training center (APTC) in their premises. The project decided to accept their proposal in order
to cater to their needs. The discussions over the location of the APTC have just been
conclusively completed in late September 2019, when land at the SSNBS laboratory center
was approved. The delay in concluding these discussions emanated from differences of
opinions over the nature of construction between MTI &EAC and UNIDO for the APTC.
(ii) Establishing a communal food processing workshop in Don Bosco
a) Site of the communal food processing workshop
The project completed discussions with MaWoC over establishing a small processing plant for
communal use in Don Bosco. The engineer surveyed the site proposed by MaWoc, where a
simple agro-processing workshop already exists, but still needs the upgrade and provision of
post-harvest equipment of g/nuts and oil extraction machinery. The engineer found it suitable
for the installation. The refurbishing is due to begin in November 2019. The project plans to
launch the first oil processed unit around December 2019 or January 2020.
b) Bidding for the construction
The project has started receiving bids from potential construction firms, and construction is
expected to begin in November 19, and probably completed in December 2019, if the
situation allows. MaWoC has assigned two staff for the management of the plant. One staff
for mainly operating and maintenance and the other to help with the business and market
linkage of the products as well as project management.
Figure 14 Site-pictures for pre-construction at MaWoc on 13 Sept 2019
21
(iii) Enhancing the capacity of Government of South Sudan in agro processing, food
safety and quality testing standards
a) Training of Trainers (TOT) in agro-processing/food safety (11 September 2019)
Eighteen trainers of training drawn from government institutions participated in the TOT on
awareness raising on good practices for quality and safety of food. Participating institutions
included Ministry of Industry Trade and East African Community Affairs (MIT&EAC), Ministry
of Agriculture, Ministry of Health - South Sudan Drug & Food Control Authority (DFCA),
Ministry of Health – Public Health Laboratory (MOH-PHL), South Sudan National Bureau of
Standards (SSNBS), and University of Juba amongst others.
For part of the training course content provided to the prospective ToTs working with the
Government of South Sudan (GoSS), see Annex 2.
Figure 15 Staff of DFCA and SSNBS at a 1 day workshop on Food Safety and Hygiene
The proposed follow up actions to be done between October and December ’19 are:
Have the 18 trained TOTs to further selection criteria to a more willing and technical one
of around 12 ToTs.
Further support through intensive technical (food safety and quality) as well as teaching
and communication training to enhance their knowledge and skills.
Facilitate the 12 ToTs in developing a program to roll them out to project beneficiaries
and as well as start a country promotion program.
22
b) Supporting the GoSS laboratory capacity in Standards and Quality Testing
This activity was undertaken between 23 to 28 September 2019 with two main institutions of
Drug and Food Control Authority (DFCA) and South Sudan National Bureau of Standards
(SSNBS). The main objective was to take inventory of what kind of standard and quality testing
infrastructure the GoSS had, and the level of operation they are being utilized with the
purpose of enhancing their effectiveness in South Sudan.
They all have an array of equipment, although mostly of it not fully operational.
Figure 16 Some of equipment at SSNBS yet to be operationalized
Among the key findings and recommendations from the technical assessment are:
Some equipment have missing parts that need to fix, in order to be able to carry out tests
for agro processed products.
There is need for both DFCA and SSNBS to strategize a future as to which lines of testing
to be undertaken, rather than trying work on everything in the sector. In this particular
aspect, SSNBS agreed to work along three(3) lines of
o Priority 1 Heavy metals analysis was selected and for
o Priority 2 Sugar analysis with HPLC.
o Priority 3 Aflatoxins
Recommendations from the technical assessment done to both DFCA and SSNBS laboratories
are summarized in Table 6 as below;
23
Table 4 Recommendations for SSNBS and DFCA
SSNBS DFCA
1) Negotiate with all vendors of existing equipment to install properly all missing systems.
2) Liaise vendors of installed equipment to train staff, if possible with presence of an external expert to control proper installation.
3) Based on vendor training on spare parts, the basic chemicals need to be identified, purchased with guarantee to proper to operate.
4) Basic laboratory training: handling balances, pipettes, general lab organization and maintenance program.
5) Set-up a work matrix risk–based, what kind of parameter they like to analyze in the near future - possibly orienting on the here proposed Priorities 1 to 3.
6) Purchase the necessary chemicals and materials needed to run methods as given as an example under Priorities 1to 3 above.
7) Method training one-by-one with support of an external trainer should be performed considering, what is feasible in terms of material.
1) Complete the re-installation of the existing HPLC system.
2) Further training by the vendor, if possible (highly recommended!) with presence of an external expert to control proper installation and training.
3) Based on vendor training spare parts and basic chemicals need to be identified for purchasing to guarantee a proper running of all system for longer time resp. a funding by the local government is possible.
4) Basic laboratory training: handling balances, pipettes, general lab organization and maintenance program – could be done together with vendor training and external expert.
5) Set-up a work matrix risk–based, what kind of parameter they like to analyze in the near future - possibly orienting on the here proposed 2 methods.
6) Purchasing necessary chemicals and materials needed to run.
7) Method training one-by-one with support of an external trainer should be performed considering, what is feasible in terms of material.
The project for the period of October-December2019 will facilitate SSNBS to work out a plan
and budget towards filling the missing parts/equipment and operationalize coupled with
appropriate training required for both institutions.
The current skills of the staff at both institution need to enhance in order
to carry out required tests.
The last part of capacity building of the SSNBS and DFCA was through a
chromatography training which was attended by 9 staff.
The table below is the summary of the feedback from the 18 training participants on the
training on food hygiene and safety.
24
Table 5 Summary of feedback on the training of food hygiene and safety
Questions Strongly Agree
: Persons (%)
Agree
: Persons (%)
Don’t Agree
: Persons (%)
1. Level of Satisfaction:
1.1. You achieved your objectives in this training 11(61%) 7 (39%) 0 (0%)
1.2. The event was relevant to your needs 12 (67%) 6 (33%) 0 (0%)
1.3. You will apply what you learnt in your
organization and operations
9 (50%) 8 (44%) 1 (6%)
2. Events Details
2.1. The content of this workshop was adequate 7 (39%) 11 (61%) 0 (0%)
2.2. The training methods and tools used were
appropriate
10 (56%) 7 (39%) 1 (5%)
2.3. There was good participation and interaction
with the trainers(s)
12 (67%) 6 (33%) 0 (0%)
2.4. Supporting documents, hand-outs and material
provided were helpful
12 (67%) 5 (28%) 1 (5%)
2.5. The time allotted to the training was sufficient 4 (22%) 13 (72%) 1 (6%)
2.6. The meeting room and facilities were adequate 9 (50%) 8 (44%) 1 (6%)
3. Specific questions
3.1 This workshop increased your awareness of food
safety requirements for market access.
13 (72%) 5 (28%) 0 (0%)
3.2 This workshop helped you improve your knowledge regarding compliance with market access and
food safety requirements.
- Food safety Hygiene aspects 9 (50%) 9 (50%) 0 (0%)
- To differentiate and explain concepts food safety
management systems e.g. GAP, GHIP, HACCP etc
10 (56%)
8 (44%) 0 (0%)
3.3 This workshop helped you improve your capacities
facilitating a training as a trainer.
13 (72%) 4 (22%) 1 (6%)
4. Additional questions
4.1 How do you intend to apply what you learnt during this workshop/event in your organization and operations?
By developing a project proposal in food safety.
Training my fellow colleagues in the institution.
By conducting training to stakeholders in this aspect.
Train staff in my organization.
Use and apply the knowledge and skills acquired in the training.
By identifying the gaps in food safety and train the target group.
25
4.2 Comments and suggestions for future
workshops/events
The time frame need to be extended.
Stakeholders from NGOs need to be involved.
Let there be practical training i.e. visit to a food processing site.
Study tour to neighboring countries will be ideal for practical experience.
Field visits and practical hand on jobs.
More trainings should be done more often.
Those trained on TOT should be given an opportunity to give presentation in future.
4.3 What additional workshop/training would you be
interested in having in the future?
HACCP
Food processing and more details in Hygiene system.
Water safety.
Standardization
Chemicals safety.
Public Health training.
Nutrition trainings
4.4 Additional comments/suggestions, if any The training was well organized and well facilitated. Keep it up.
Well done.
The trainer is very experienced and is passionate of her work. Good work.
The training was very helpful .thank you very much.
4.2 Output 2: IDPs and host communities trained in agro-processing and
entrepreneurship development skills
Output 2 has been implemented through following activities;
(i) Introduce agro-processing/food safety (10 September 2019)
Over 100 IDPs & Host Community (HC) project beneficiaries were trained on basic food safety
and hygiene practices. The occasion was opened by the Rajaf Payam- Executive Director
Joseph Loro. The event was closed by His Excellency the Ambassador of Japan to South Sudan,
HE Mr. Seiji Okada. For the key topics that IDPs received orientation upon, see Annex 3.
26
Figure 17 Beneficiaries at a session of food safety and hygiene
(ii) Training of Trainers (TOTs) in Entrepreneurship Development Program (EDP);
The project strategy was to select and train the trainers of training (ToTs) from the community
who were fairly literate and could communicate in Juba Arabic. These 14 ToTs underwent a
training for 8 days and later facilitated to carryout training to their 7 groups (2 ToTs per group)
over a period of 7 days in September-October 2019. For this TOT, a manual was printed in
English.
According to the baseline/profile survey of the ToTs, which will help to continuously engage
and evaluate their performance in liaison with the baseline/profile survey of beneficiary to be
rolled out in November 2019, the majority of the women beneficiaries are illiterate, unable
to read or write, young mothers, widows and head their households. Thus training of
beneficiaries by trainers under the supervision of an international EDP Expert and staff took
up adult learning approach full of graphic power point.
The women are mostly traumatized with low self-esteem by the time the project started. As
the project started getting implemented, they slowly regained self-confidence and joy, as one
lady stated at the time of the visit of the Ambassador of Japan on 10 September 2019. The
lady by the names of Apio Jenifer, her own words “If I know how to make oil, I will get more
money and be more economically empowered” when asked by the 13 September 2019-Dawn
newspaper journalist to comment about the relevance of the project.
The capacity building around the beneficiaries was there for challenging from one of semi-
literate to one of illiterate, who were highly traumatized. The project recommends for future
project design around IDPs to have a sub component of psychosocial support for at least 6
months, to address the underlying issues of the communities.
All the 14 ToTs have signed up to Terms of Reference (ToR) to work for the project until March
2020 and will be supervised by the UNIDO project officers assisted by the MaWoC staff. They
27
have also been provided with short monitoring reporting framework amongst their groups to
confirm adoptions of EDP and business progress as well as Village Saving and Loan Association
(VSLA) activities.
(iii) Training for IDPs and host community members in Entrepreneurship Development
Program (EDP);
The EDP training for 200 beneficiaries was conducted by the 14 ToTs under the supervision of
the international EDP expert and National Project Officer in the end of September’19. At the
end of the training, the beneficiaries developed six different business plans (one per group)
around the groundnuts and sesame value chain. They were guided how to register and
operate as micro enterprises composed of 33-37 members related to groundnuts and sesame
enterprises.
In addition, an operational feasibility plan was drafted for the IDPs groups which were used
as a basis on business plan preparations. This will be finalized in November 2019 prior to
installation of the plant.
Figure 18 A group member leading fellow beneficiaries in EDP training
Figure 19 A ToT carrying out an EDP training to group members
28
Some of the challenges and lessons learned to implement the EDP program are as follows;
IDP/HC members rely on casual daily wages for their survival hence occupying them for
more than a day’s activities, implies they demanded for transport allowance which was
not planned for. Sometimes, some training had to be postponed by a few days to clear
pending payments.
High level of illiteracy among the IDP/HC or beneficiaries, needing translation in to local
Arabic and other languages. This was on the back of being very sensitive to their
traumatized background. This sometimes led to a slow approach, and a lot adult learning.
The heavy intensive training for the period of September –October 2019, was a marathon
in nature for EDP ToT and EDP IDP/HC training resulting to fatigue for trainees and is now
following the VSLA. This led to some fatigue to the trainees.
There are number of activities that will need to be completed in the remaining 6 months of
project implementation while also addressing some of the challenges experienced in the
first, 6 months.
Following table is a summary of feedback from the trainees of Training of Trainers (TOT) in
the EDP trainings.
Table 6 Summary of feedback from the TOTs in the EDP training
Questions Responses
1. Summary of the most important things learnt during the training
How to scan environment for business opportunities
Creativity
Qualities of a good entrepreneur
How to train others on EDP
How to start and manage the business
How to develop a business plan based on business idea
How to be a good leader
Business skills
Collaborating with others
2. Please rate the training in terms of its impact and
usefulness in the following areas.
Strongly Agree
Agree Disagree Strongly Disagree
- Useful in your daily work 100% 0% 0% 0%
- Increasing your willingness to train and mentor others 93% 7% 0% 0%
- Increasing your ability to train and mentor mentors 93% 7% 0% 0%
3. Do you think you will have the opportunity to utilize
the training skills you’ve practiced and/or acquired
during this workshop within the next three months?
YES NO
100% 0%
3a If yes, please briefly describe when and how you might apply these skills.
To my family
To IDPs and Host Communities in my
community
29
In my community
To my business
In Church
To myself
Outside the Country
Questions Excellent Very Good
Good Poor Very Poor
4. How do you rate the training overall? 13 (93%) 1 (7%) 0 (0%) 0 (0%) 0 (0%)
5. Please indicate your impressions of the items listed
below
Strongly Agree
Agree Disagree Strongly Disagree
5.1 The training met my expectations. 86% 14% 0% 0%
5.2 I will be able to apply competences acquired 100% 0% 0% 0%
5.3 The training objectives for each topic were identified
and followed.
93% 7% 0% 0%
5.4 The content was well organized and easy to follow. 93% 7% 0% 0%
5.5 The materials distributed were relevant and useful. 100% 0% 0% 0%
5.6 Master Trainer was competent 93% 7% 0% 0%
5.7 The quality of instruction was good during
workshop(s) 86% 14% 0% 0%
5.8 The trainer met the training objectives of the training 100% 0% 0% 0%
5.9 Class participation and interaction were encouraged. 93% 7% 0% 0%
5.10 Adequate time was provided for questions and
discussion. 100% 0% 0% 0%
6 What are the measures would you recommend to improve the quality of training?
Allocating enough time for the training
Provision of enough food
Provision of per diem
Organize EDP training in another place apart from Don Bosco
Transport Allowances or Per diem should be provided on time
Provision of enough materials
(iv) Training in Village Savings and Loan Association (VSLA);
The project is using the VSLA as an entrance point of working with IDPs and host community.
The VSLA was highlighted as the most attractive to mobilize them and action point for social
cohesion. The approach starts with self-identification facilitated by the trained ToTs. The
group focuses on mobilizing their own capital through internal savings and loans among
trusted peers.
The project has been able to mobilize at least 7 groups from 200 females and 30 youth (males
and females). The project has been able to carry out a training for 14 VSLA ToTs who are
carrying out trainings to 230 beneficiaries, with 2 ToTs per group. The training of ToTs was for
30
5 days, and will enable them to later train the beneficiaries for 3 days per group. This will be
supported by coaching and supervision both from the ToTs and project’s staff. The training of
project beneficiaries to adopt Village Savings and Loans Associations (VSLAs) has begun in
October 2019. This will later be followed by actual savings for the first- two months later
followed up with internal loans.
Figure 20 A sample of savings kit to be provided to the 7 groups
This will be supported by monitoring and coaching of the beneficiaries, providing technical
backstopping to the ToTs by the project. In addition, a training manual has been developed
for the ToT which they can use while training and coaching the members.
The training program for VSLA is summarily following stages as below:
1. Group Formation and setting of General Assembly.
2. Sharing the VSLA concepts; along Savings, Loan, Interest and Welfare.
3. Questioning what kind of leadership to be sought. This will also be aligned to support EDP-
agro processing business plan. Some of the positions to be promoted include;
Chairperson, Secretary and Treasurer.
4. Facilitate election of leaders and setting up of Internal rules
Following table is a summary of feedback from the trainees of Training of Trainers (TOT) in
the VSLA trainings.
Table 7 Summary of feedback from the TOTs in the VSLA training
Questions Strongly Agree
: Persons (%)
Agree
: Persons (%)
Don’t Agree
: Persons (%)
1. Level of Satisfaction:
1.1. You achieved your objectives in this training 12(86%) 1 (7%) 1(7%)
1.2. The event was relevant to your needs 12 (86%) 2 (14%) 0 (0%)
1.3. You will apply what you learnt in your
organization and operations
14 (100%) 0 (0%) 0 (0%)
2. Events Details
2.1. The content of this workshop was adequate 10 (71%) 4 (29%) 0 (0%)
31
2.2. The training methods and tools used were
appropriate
13 (93%) 1 (7%) 0 (0%)
2.3. There was good participation and interaction
with the trainers(s)
13 (93%) 1 (7%) 0 (0%)
2.4. Supporting documents, hand-outs and material
provided were helpful
13 (67%) 1 (28%) 0 (0%)
2.5. The time allotted to the training was sufficient 7 (50%) 5 (36%) 2 (14%)
2.6. The meeting room and facilities were adequate 9 (63%) 5 (36%) 1 (1%)
3. Specific questions
3.1 This workshop increased your awareness on VSLA 14 (100%) 0 (0%) 0 (0%)
3.2 This workshop helped you improve your knowledge regarding compliance with market access and
food safety requirements.
- How VSLA works 14 (100%) 0 (0%) 0 (0%)
- How to facilitate groups to develop their by laws 13 (93%) 1 (7%) 0 (0%)
3.3 This workshop helped you improve your capacities
facilitating a training as a trainer.
14 (100%) 0 (0%) 0 (0%)
4. Additional questions
4.1 How do you intend to apply what you learnt during this workshop/event in your organization and operations?
Increase awareness on VSLA, improve knowledge on how VSLA works and how to facilitate groups develop bylaws.
Reviews of VSLA groups.
By conducting training to stakeholders in this aspect.
Train other members of the group and community on how to save together and reduce poverty
Start up a business.
4.2 Comments and suggestions for future
workshops/events
Training on computer packages ie Microsoft excel and power point.
Increase time for training, good food, inter VSLA exposure visits.
Increase time for the workshop.
Expand the training to other states.
Allowances should be paid immediately.
More workshops.
Exposure visit for ToTs to see how other ToTs do their work.
4.3 What additional workshop/training would you be
interested in having in the future?
Ground nut oil processing training, leadership, conflict transformation and trust building at group level
English course, gender training.
Designing and tailoring, salon
32
4.4 Additional comments/suggestions, if any Provide computer training for ToTs.
VSLA tours to existing VSLA and learn from experience.
Improve on services (allowance & food)
Workshops to be held in other places
Thanks for the training and happy to be a ToT
Improve on quality of food.
Timely payment of allowance and ToT facilitation fee.
Generally the whole VSLA training was considered as well undertaken by the ToT beneficiaries
and relevant to them. The best scores were around VSLA relevance to their lives.
The level of satisfaction was rated as strongly satisfactorily and all of them accepted they will
apply what they were trained. There are needs of improvement especially around time for
training. The trainees feel there was too much to be learnt in a very short time. This was due
to delayed start, and hence also calls for continued monitoring and supervision to ensure
desired outputs are achieved in the remaining project period. However, the Trainees
confirmed they are now much better facilitators/trainers and their knowledge of VSLA has
greatly improved. There was no sign of disagreement with the trainees with respect to
capacity building in training of VSLA, and the project hopes this will be reflected when ToTs
engage the beneficiaries here after.
5. Challenges experienced during Implementation of the Project
(i) Client vulnerability with respect to food security and hunger; as mentioned earlier,
the survey carried out on the beneficiaries reflected almost 60% have a need to address
food security and capital. This need overwhelmed the project when the project was
notified that beneficiaries required some daily lunch facilitation allowance when they
attended the training. As mothers they were expected to bring in daily income/food
for the home, and thus suggested the project covers for it. These unplanned logistical
demands from trainees, destabilized the normal planning schedule the project had
planned. Some trainings had to be re-scheduled and sometimes the project team had
to spend time in counselling trainees not to abandon the training and urged them to
patiently wait for processing of this facilitation.
(ii) Highly controlled photographic media; the country has a non-written law of not taking
photos freely. However, in some instances, permission is required from national
security service. It becomes challenging to capture real time photo events, if not within
the training event. The project is currently sourcing for a professional photographer
with license to carry out this activity in South Sudan. He/She will also be able to make
life time video and story for the project.
(iii) Fragility and insecurity in the target community (peri-Juba); under UNDSS procedures,
the project needs always to ask for both UNDSS security clearance followed by the
33
clearance from the national security. The national security officers should be deployed
to the training venue. This is a routine that sometimes causes the project
inconvenience to support their logistics.
6. Donor and Project Visibility
The project worked in collaboration with the Embassy of Japan in Juba for most of the
events with number of consultation meetings. At all events that the project has carried out,
the Government of Japan as the donor was recognized as illustrated below:
(i) Launching of the first Project Steering Committee (PSC) meeting; Mr. Nobuhiro
Kikuchi- Head of Development Cooperation at the Embassy of Japan in Juba on 4 July
2019.
(ii) Ambassador’s visit to the training venue; on 10 September 2019, H.E Ambassador Mr.
Seiji Okada honored the training of the IDPs and host community in food safety and
hygiene.
In both occasions, the events were received media publicity in Dawn newspaper dated 13
September 2019, which is one of the main newspapers in South Sudan.
In the upcoming period, the project plans to hold a graduation ceremony for 14 ToTs and 230
females and youth. The second planned occasion will be during the launch of communal food
processing workshop/plant at Don Bosco for the groups of the IDPs and host community
members likely to be held in between December 2019 and January 2020. On both occasions,
the project intends to have a strong presence of the media and the Government of Japan, and
this will create an ongoing altitude of the great development impact provided by financing
from the Government of Japan. Some of the other products that the project intends to use, in
addition to local publication, are flyers, brochures, T-shirts and caps with description and reflection of
the funding of the Government of Japan. For the article in the Dawn newspaper mentioned above,
see Annex 4.
7. Onward Project Implementation for October 2019 to March 2020
The project continues to utilize the momentum, which has gained till September in order to
complete the remaining activities. The project strategically will need to focus more on the
installation of the agro processing infrastructure for the agro-processing training center
(APTC) and a communal food processing workshop/plant.
This will need to be closely monitored in three months phases, in order to address any bottle
necks before time. Thus for the period of October- December 2019, the project would need
to follow up on the following:
(i) Output 1;
a. Construction of the APTC at the SSNBS to start before the end of November and
complete before the end of December 2019. The project will also need to agree with
SSNBS on the management and operation of the APTC.
34
b. Construction of the communal food processing workshop/plant at MaWoC to start in
November and complete before mid-December 2019. This will also follow 3-4 weeks of
coaching the beneficiaries on its operation, maintenance and management. The
project is tasked to develop a market development plan for the planned processed oil
products.
c. Complete the training of trainers (ToTs) for SSNBS and DFCA, and roll them out with
the support of a promotion program to the project as well as the country.
d. Facilitate SSNBS and DFCA to operationalize their testing laboratories along key
strategic areas.
(ii) Output 2;
a. Complete the training of VSLA to the women and youth and this will make a total
number of 230 beneficiaries against 150 originally targeted.
b. Complete equipping the groups with the startup kit for their operation as EDP/VSLA
active groups. This will include post-harvest handling and VSLA equipment for each
group.
c. Continue to coach and provide technical back stopping to the 14 trained trainers who
later work with 7 groups in operationalizing of EDP and VSLA. The first 3 months will
also be key, as that is when they start saving, obey their own set by laws and later start
to lend each other. The aspect of trust and cohesiveness will be tested then.
All activities will be fully given promotional and donor visibility throughout the
implementation. Among the key events planned will be the graduation ceremony for all the
training beneficiaries under Output 2 in December 2019 and launch of a communal food
processing workshop/plant.
For the progress of whole project activities, see Annex 5.
35
Annexes
Annex 1: Minutes of the First Project Steering Committee (PSC) held on 4 July 2019
Project Title: Enhancing Social Stabilization and Cohesion through Agro Value
Chain Development in South Sudan
Report of Launching of the Project Steering Committee (PSC)
No. 01
Date: 4th July 2019
Time: 10:30am-1:00pm
Venue: Juba Grand Hotel, South Sudan
Published on 11th July 2019
36
1. Opening of the meeting
This Project Steering Committee (PSC) launch and meeting was convened in Juba Grand Hotel,
Juba, South Sudan on 4th July 2019, and was opened by the Undersecretary of Ministry of
Trade, Industry and East Africa Community Affairs (MTI&EAC), the Hon Mou Mou. Each
participant introduced himself/herself stating the institution they were coming from and
position. Participants were drawn from the Ministry of Trade, Industry and EAC Affairs
(MTIEAC), Ministry of Agriculture and Food Security (MAFS), South Sudan National Bureau of
Standards (SSNBS), South Sudan Chamber of Commerce, Industry and Agriculture, media and
Embassy of Japan. The list of participants is hereto attached as Annex D.
2. Remarks by Undersecretary of EAC Affairs and official Launching of the Committee
The Hon. Mou Mou, the Undersecretary for East Africa Community Affairs, MTIEAC thanked
the members from different institutions for attending the meeting. He thanked the
Government of Japan for providing funding and UNIDO for the execution of the project. He
informed the participants that this meeting was an opportunity to reflect on the agricultural
potential of the Republic of South Sudan. He underscored the importance of agro processing
in the country with the potential to be exporting to other regions. He informed the meeting
that many South Sudanese had been concerned when the country was negotiating for the
membership of EAC as there was going to be nothing to be exported to the region, but now a
project of this nature and the assistance of Japan to South Sudan, will see South Sudan
realised its agricultural potential through increased value addition processing. “This project is
going to create many opportunities to our many people as many people especially women
and youth will gained business skills that will be great for our country”, he is quoted to have
said.
The Hon. Mou thanked UNIDO for helping South Sudan to industrialize so we can develop our
country. He underscored the importance that the IDPS will get skills under this project so that
they can have business skills that they can use when they go back to their places.
Furthermore, he informed the meeting that the Ministry of Trade, Industry and EAC Affairs
will ensure the realisation of the Agro-processing Plant as outlined in the project document.
He then declared the meeting opened and officially launched the Project Steering Committee
(PSC).
3. Welcoming Remarks from the Project Technical Advisor
Mr. Hannington Sebaduka, the Technical Project Advisor gave opening remarks on behalf of
the United Nations Industrial Development Organization (UNIDO) Project Team. He thanked
the Hon. Mou Mou, the Undersecretary of EAC who was officiating the launch and Hon.
Mr.Nobuhiro Kikuchi, the First Counsellor and Head of Development Cooperation at the
Embassy of Japan in South Sudan for gracing the occasion of today launching of the Project
Steering Committee. He also thanked all the other participants for attending the meeting. Mr.
37
Sebaduka also up dated the meeting about the project and the roles of Project Steering
Committee.
4. Remark by the Representative of
Embassy of Japan
Mr. Nobuhiro Kikuchi the Head of
Development Cooperation at the Embassy
of Japan in South Sudan thanked the Hon.
Mou and all the participants for attending.
He outlined the priority areas of
Government of Japan in South Sudan that
include Peace Building, Humanitarian
Assistance and Development Assistant. In
the Development Assistance, Government
of Japan through the Embassy in Juba
focuses on agriculture because Japan see a
great potential of agriculture in this
country. He mentioned that
Figure 1 Mr Hiro and Hon MoU Mou attending the launch of the PSC on 04 July 2019
this project is focusing on agro processing
and agribusiness in South Sudan. Mr.
Kikuchi stated that this project would be
helping to enhance and improve food and
agro products production.
He informed the members of PSC that this project in collaboration with UNIDO and MITEAC
will greatly contribute to the capacity building among the micro and small sized farmers to
gain knowledge and skills for the value adding agro-processing and business-oriented
market access so that they can enable to enhance their lives. He thanked the participants
and informed them the willingness of the Embassy to work closely with all the members of
the Project Steering Committee.
38
5. Presentation of the Project Work plan by Technical Advisor
Mr. Hannignton Sebaduka introduced the project outline and work plan on behalf of the United
Nations Industrial Development Organization (UNIDO) Project Team. The details of the
presentation are attached in Annex B.
In relation to output component 1; the participants agreed to form a four-technical
person subcommittee to define the features and scope of the agro-processing Training
Centre and how it will be managed in liaison with UNIDO in addition to availing of space
for its operation. The committee will have to come with their recommendations within
one month. The members of the sub-committee to work on the Agro-processing
Training Centre are as follows:
1. Directorate of Industry, MTIEAC - Chair
2. SSNBS - Secretary
3. MAFS – Cooperatives member
4. Chamber – member
Output component 2; the activities were accepted, as presented. The representatives
from Directorate of cooperatives, also confirmed they will work with the project in
reference to their registration and any other capacity building could be discussed. The
Secretary General of Chambers of Commerce, also accepted to work with the project
in reference to MSEs program with the IDPs, and they have a number of trainings that
could be utilised by the formed enterprises.
6. Presentation from South Sudan National Bureau of Standards (SSNBS)
Mr. Majak Deng Kuol, the Acting Executive Director gave the presentation to meeting. He
outlined the mandates and roles of SSNBS. He said that SSNBS has laboratory and Department
of Standards Development. He informed the meeting that SSNBS will be working with UNIDO
to ensure the standards for edible oils and testing regimes are in place with some help of
UNIDO. A copy of the SSNBS presentation is attached in Annex C.
7. Conclusions and Recommendations
In his concluding remarks, Mr. Nobuhiro Kikuchi said that quality control is a key to build confidence
on the products, as the project looks towards value added products for the market. He said he would
share experience in Japan on how the work on the quality issues over the last fifty years in the next
PSC and would encourage the project to strengthen the quality aspect for the agro processed
products.
39
Annex 2 Training content for food safety and hygiene for officials of the Government of South Sudan
41
Annex 4: Article regarding the project activities in Don Bosco and the visit of the Ambassador of Japan to South Sudan (14 September 2019)
42
Annex 5 Status of progress on the project implementation
4 5 6 7 8 9 10 11 12 1 2 3
1.1 Conduct a Training of Trainers (TOT)
in agro-processing.
1.1.1
Select and train ToTs who will support other
beneficiaries in supplying and processing of the
goods produced to the plant 50%
The ToTs have been selected. They have
received the initial training, with full training
to follow after the installation of the
processing plant.
1.2.1
Pre- qualification and selection of site for processing
plant. This includes determination of the kind of
plant, location, management and operation of plant.100%
As per the request of the GoSS, an agro-
processing training center will be
constructed instead of a pilot food
processing plant in the premises of SSNBS.
1.2.2
Contracting of service provider and constructing.
40%
The service providers are being contacted
through procurement. The delay was due to
delay in being allotted land by the GoSS,
that was done in Sept'19.Construction due
to begin in Nov/Dec'19.
1.2.3
Handover of the training center to SSNBS/MTI&EAC.50%
MTI&EAC will be responsible for the
operation and management of the center.
The project will ensure the sustainable use
of the facility.
1.3.1
Confirm the kind and location of processing plant
required for the beneficiaries.
100%
This is completed.
1.3.2
Confirm the management, operational skills and
supporting markets with the beneficiaries.
100%
The host community will pay a great role in
hosting this facility. A Joint Management
structure between host community and IDPs
will be encouraged.
1.3.3
Construction and handover of the communal food
processing workshop.
30%
Construction is due to begin and end in
Nov/Dec'19.
1.4.1
Selecting the institutions for building skills and
technology for standards and testing of Foods
100%
This is completed and they are DFCA and
SSNBS.
1.4.2
MoU signed with Institution(s) in setting standards
and testing, with attached profile of Technical Needs
for capacity building.70%
The staff needs profile survey has been
undertaken. It will not be necessary to have
an MoU with a Government Institution, but
the project will have an agreed action plan
for Oct/Nov 19.
1.4.3
Building the technical capacity through Training and
Technically Equipping the institutions50%
This is on schedule, and we have 7 ToTs
trained from DFCA and SSNBS each. These
will under go a further selection to remain
with 12, who will implement the program.
1.4.4
Increasing awareness of installed quality standards
and testing required to be certified for the markets
for the different agro processed products50%
This process has been began. The pending
activities will be determined during the
process of finalizing 12 ToTs from DFCA and
SSNBS.
Remarks2019
Output 1; Basic facilities for agro-processing established.
Activities Detailed Activities STATUS2018
Implementation Schedule
1.2 Construct a pilot food processing
plant in the area of Food Processing
Center (FPC). -> Construct an agro-
processing training center (APTC) at
SSNBS (MTI&EAC).
1.3 Construct a communal processing
workshop in a host community.
1.4 Enhance capacities of selected
institutions dealing with quality and
testing of food products.
43
4 5 6 7 8 9 10 11 12 1 2 3
2.1 Conduct a brief value chain
assessment to verify the scope.
Confirming the value chain for
engagement
2.1.1
A brief value chain desk review
80%
This was done utilizing the studies from JICA
and studies from UNIDO completed project.
It will continuously become updated as oil
processing gets launched.
2.2 Train IDPs and host communities
members in agro processing skills as well
as entrepreneurship in collaboration
with the JSB 2016 project for South
Sudan and other UNIDO ongoing projects
2.2.1
Profile & select project beneficiaries (IDPs and host
communities). The priority will be based on IDPs
within the collection centers of Juba, already formed
by key prospective partners
100%
This is completed, and it was done with
assistance with IOM and UNHCR. The groups
are 7 and members are 230.
2.2.2
Confirm the business model for the groups to access
the market of the installed communal processing
plant.
50%
The draft is being done. This needs to be in
line with the kind of plant to be installed in
Nov/Dec'19
2.2.3
Determine Technical Needs Assessment (TNA)
package for the groups in value addition processing,
quality and test management and market linkage50%
The first part was completed and the next is
to follow when the 12 ToT from DFCA &
SSNB are in place.
2.2.4
Build and train link farmers with appropriate skills
for quality products to be received from beneficiaries 50%
The IDPs received initial training on food
safety and hygiene in agro processing. The
second part of training, will be linked to the
installation of the plant.
2.2.6
Assess the business technical and financial needs for
beneficiaries and determine the appropriate EDP
they require to act as viable MSMEs 100%
This is completed.
2.2.7
Train the beneficiaries with basic entrepreneurship
and agribusiness100%
This is completed.
2.3 Provide necessary basic
materials/tools /equipment the trained
IDPs and host community members for
agro-processing.
2.3.1
Develop a package for viable MSEs and trained IDPs/
host community. 50%
A list has been done, and sourcing for them
is on going. To be completed by Dec'19
2.4.1
Facilitate formalizing and registering of MSMEs
within the trained beneficiaries.50%
2.4.3
Establish and operationalize coach/mentors for the
registered MSEs.70%
A coach and mentoring program for EDP and
VSLA is ongoing with 14 ToTs
2.4.4
Facilitate linkage to appropriate financial
institutions to the progressive MSMEs, for
prospective growth.60%
Ongoing market backward and forward
market linkages are ongoing. The installation
of the plant, will trigger the last part of
market linkages for prospective processed
products
2.4.6
Contract a Village Savings and Loans Association
(VSLA) specialist and Institution Development
specialist. This will foster cohesion and increased
collaboration within the groups, in addition to
increasing their economic viability.
100%
This is completed.
2.4.7
Implement intra group cohesion (Institution
Development) through training and implementing
VSLA product. Both capacity building are an all year
coaching process.
70%
Ongoing training for VSLA, and full
participation will be confirmed when the
start saving in Nov/Dec 19 period.
Remarks2018 2019
2.4 Mentor the trained IDPs and Host
Community members in processing
agricultural produce at the pilot food
processing workshop and a communal
processing workshop as well as in the
start up of micro and small processing
business.
Activities Detailed Activities
Implementation Schedule
STATUS
Output 2: IDPs and Host Communities trained in agro processing and entrepreneurship
44
4 5 6 7 8 9 10 11 12 1 2 3
3.1.1
Contract National Project Officer (NPO) 100%This was replaced with a National Project
Officer who was recruited
3.1.2
Carryout a baseline for the project 50%
A frame work is in place, and the ToTs will
lead the exercise. A draft to be delivered in
Nov'Dec'19
3.1.3
Draw and effect a project monitoring framework70%
This is ongoing.
3.1.4 Determining Scope of Work, mobilizing key
stakeholders & launching Project Steering
Committee (PSC).100%
This is completed
3.1.5
Create Promotional Materials; This would involve
participating in sector platform engagements, and
use an approach of encouraging the beneficiaries to
tell their story
30%
Sourcing for suppliers is ongoing. First batch
to be delivered in Nov'19. There were no
tangible results to include in the promotion
materials then
3.2.1
Recruit an International Evaluation Expert.
3.2.2
Prepare and conduct the terminal self-evaluation.
3.2.4
Wrap-up and Handover
3.3.1
Launch of the Agro-processing Training Centre30%
Planning to receive bids from constructors
3.3.2
Organize a graduation ceremony/graduation
ceremonies50%
Plans are on going and to be done before
end of Nov'19
3.3.3
Guide a national/local agency UNIDO PR manuals 100%
This is completed
3.3.4
Recruit a professional photographer based in Juba. 70%Planned to have finalized contracted
photographer by end of Oct'19
Remarks2018 2019
Activities Detailed Activities
Implementation Schedule
STATUS
3.0 Project Management
3.1 Monitoring
3.2 Conduct a terminal self-evaluation to
draw lessons learned3.2.3
Prepare the Terminal Report
3.3 Conduct donor and project visibility
activities.
3.3.5
A Quarterly promotion program about the centre
and its role in quality standards and agro processing
skills enrichment
To be conducted.
30%
The centre, pilot plant and completion of
the 12 ToTs from GoSS have to be completed
to start the promotion program