ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) FOR THE SOLOMON ISLANDS SUSTIANABLE ENERGY PROJECT (SISEP, PIOO31, IDA GRANT No. H415-SB) PROJECTS PROPOSED FOR FUNDING UNDER WORLD BANK November 2013 Prepared by: Shannette Environmental Management Services Honiara Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 08-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK

(ESMF)

FOR

THE SOLOMON ISLANDS SUSTIANABLE ENERGY PROJECT

(SISEP, PIOO31, IDA GRANT No. H415-SB)

PROJECTS PROPOSED FOR FUNDING UNDER WORLD BANK

November 2013

Prepared by:

Shannette Environmental Management Services

Honiara

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb371432
Typewritten Text
E4364
wb371432
Typewritten Text
wb371432
Typewritten Text
Page 2: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

ii

Acronyms

AP Affected Person

EA Environmental Assessment

ECD Environment Conservation Division

EIA Environment Impact Assessment

EIS Environment Impact Statement

EMP Environment Management Plan

EMS Environment Management System

ERW Explosive Remnants of War

ESMF Environment Social Management Framework

MCA Ministry of Communication Aviation

MECDM Ministry of Environment Climate Change Disaster Management Meteorology

MID Ministry of Infrastructure Development

PE Project Engineer

PER Public Environment Report

RSIPF Royal Solomon Island Police Force

SDA Seventh Day Adventist

SIEA Solomon Islands Electricity Authority

SIG Solomon Islands Government

SINU Solomon Islands National University

SISEP Solomon Islands Sustainable Energy Project

SOPs Standard Operating Procedures

UXO Unexploded Ordinance

WB World Bank

Page 3: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

iii

Executive Summary

This Environmental and Social Management Framework (ESMF) is an assessment tool for the capital works under the Solomon Islands Sustainable Energy Project (SISEP, P100311, IDA Grant No. H415-SB), which the Solomon Islands Government has sought from the World Bank / IDA. The capital works will contribute to improving the reliability of power supplies by reducing the frequency and duration of power supply interruptions in Honiara. SIEA plans to use the IDA money to strengthen the power distribution network in Honiara, to improve the network efficiency and reliability, and to meet growing and new demands for electricity. Planning and design of the Honiara network upgrade is underway by SIEA and its Engineers. The proposed works to be co-financed by the IDA Credits include – upgrading and installing new transformers, up-rating and extending the existing distribution lines and installing a new dispatch / systems control room. Following the requirements for environmental managements in all SIEA projects, an environmental and social management framework (ESMF) has been prepared to provide a mechanism to carryout appropriate environmental and social assessment in line with the World Bank (WB) safeguard policies and the Solomon Islands Government (SIG) legislation. The purpose of the ESMF is to provide a procedure for environmental and social assessment of the proposed SIEA projects. ESMF was selected because even though the footprint of the project is known, design and other details about the investment are not available prior to appraisal of the project. It will guide SIEA in determining the appropriate level of environmental and social assessment required for current and future projects and in preparing the necessary environmental and social mitigation measures for these projects during the preconstruction, construction and operational phases.

OP4.01(Environmental Assessment) sets out the general policies and principles for environmental and social protection for projects financed by WB and the requirements for assessment of impacts and implementation of plans and measures to mitigate or manage impacts. Based on OP4.01 criteria for classifying projects, the proposed project has minimum adverse environmental impacts which are temporary and which can be readily mitigated. Therefore the project has been classified as a Category B project by the Bank. This level of assessment is equivalent to the “screening / scoping” process required to prepare the Public Environment Report (PER) for most development project under the Environment Regulations 2008 of Solomon Islands. The findings of the ESMF show that:

All works related to the upgrading / installation of new transformers in Ranadi and Lungga Power

Station; the addition of a 33kV switchboard at Ranadi, the construction of a new Power System

Control Room and Dispatch Centre at Ranadi; upgrading of switchgears at Lungga; construction of

a Zone Substation and installation of transformer at Kola’a Ridge will be carried out in the existing

facilities and on the lands owned or leased by the SIEA. As such there will be no land acquisition.

Page 4: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

iv

The extension of the overhead Feeder Line 12 from Lungga to the Honiara East substation will be

will be carried out within the public road right of way / easement and no new land acquisition or

impacts are envisaged.

To meet with the Civil Aviation Safety requirements, the power cables crossing the eastern end of

the runway will be buried underground, outside the airport boundary fence.

Since all installations / constructions will be carried out within the fenced boundary and basically

involves installation of equipment, construction related impacts are expected to be minor and of

short duration.

The construction of the overhead power lines will be within the right-of-way of the public road.

During the erection of power poles and stringing of the power lines, SIEA will ensure that there is

minimum impact on the traffic and that safety is strictly observed.

As part of the Project, SIEA plans to clear and maintain the over grown easement for Feeder 12.

The cleared slash will be disposed of in an environmentally safe manner.

Operationally, except for a very low humming noise from transformers, no other environmental

issues are envisaged.

Solomon Islands, like other Pacific Islands, still has a large number of Unexploded Ordinance

(UXO). Sweeping of construction sites for UXO will be carrie

The ESMF report provides a Framework which can be applied to future expansion projects.

However, future investments will prepare site specific instruments according to the environmental

and social impacts identified.

Page 5: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

v

Table of contents

Acronyms .......................................................................................................................................... ii

Executive Summary ........................................................................................................................... iii

1. INTRODUCTION ..........................................................................................................................1

2. POLICY, LEGAL AND ADMINISTRATIVE / REGULATORY FRAMEWORK ...........................................1

2.1 World Bank Safeguard Policies -OP 4.01....................................................................................... 1

2.2 Solomon Island Regulatory Requirements.................................................................................... 2

3. PROJECT DESCRIPTION ................................................................................................................3

3.1 Proposed Project Components ..................................................................................................... 3

3.2 Potential Future Development ..................................................................................................... 4

4. DESCRIPTION OF THE ENVIRONMENT ..........................................................................................5

4.1 Physical environment .................................................................................................................... 5

4.2 Biological environment ................................................................................................................. 5

4.3 Socio-economic Environment ....................................................................................................... 6

4.4 Unexploded Ordinance (UXO) ....................................................................................................... 7

5. ANTICIPATED ENVIRONMENTAL IMPACTS AND POTENTIAL MITIGATION MEASURES....................8

5.1 Significance of Impacts ................................................................................................................. 8

5.2 Pre-construction Impacts .............................................................................................................. 8

5.3 Construction Impacts .................................................................................................................... 9

5.4 Operation Impacts ...................................................................................................................... 12

6. ANALYSIS OF ALTERNATIVES ..................................................................................................... 12

6.1 Project location ........................................................................................................................... 12

6.2 Project technology ...................................................................................................................... 12

6.3 Do nothing................................................................................................................................... 13

7. PUBLIC CONSULTATIONS, INFORMATION DISCLOSURE .............................................................. 13

7.1 Public consultation ...................................................................................................................... 13

7.2 Results of Public Consultation .................................................................................................... 13

7.3 Disclosure .................................................................................................................................... 16

8. INSTITUTIONAL ARRANGEMENT ............................................................................................... 17

8.1 World Bank .................................................................................................................................. 17

8.2 SIEA ............................................................................................................................................. 17

Page 6: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

vi

8.3 Environment & Conservation Division ........................................................................................ 18

8.4 Environmental Monitoring and Reporting Arrangements .......................................................... 18

8.5 Grievances redress mechanism .................................................................................................. 19

9. CONCLUSIONS AND RECOMMENDATIONS ................................................................................. 20

Page 7: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

1 | P a g e

1. INTRODUCTION

The World Bank together with Solomon Islands Electricity Authority (SIEA) are embarking on improving and increasing power capacity of SIEA’s existing network. Following requirements for environmental managements in all SIEA projects, an environmental and social management framework (ESMF) was development to provide a mechanism to carry out appropriate environmental and social assessment in line with World Bank (WB) safeguard policies and the Solomon Islands Government (SIG) legislation.

The purpose of the ESMF is to provide a procedure for environmental and social assessment of SIEA projects. It will guide SIEA in determining the appropriate level of environmental and social assessment required for current and future projects and assist in implementing the appropriate environmental and social mitigation measures for these projects during the preconstruction, construction and operational phases.

2. POLICY, LEGAL AND ADMINISTRATIVE / REGULATORY FRAMEWORK

2.1 World Bank Safeguard Policies -OP 4.01

The proposed project to be financed by World Bank requires Environment Assessment to ensure that it is environmentally friendly and sustainable. OP4.01 (Environmental Assessment) sets out the general policies and principles for environmental and social protection for projects financed by WB and the requirements for assessment of impacts and implementation of plans and measures to mitigate or manage impacts. The OP4.01 has been used to classify projects. The four categories defined in the OP4.01 are:

Category A. The projects are likely to have significant adverse impact on sensitive and valuable ecosystems (protected areas, wetlands, wild lands, coral reefs, and habitats of endangered species), cultural heritage sites (archaeological, historical sites or existing cultural sites), densely populated areas where resettlement is required or pollution may be significant, heavy development areas and conflict in natural resource allocation, water bodies and land or water containing valuable resources. Seeing the impacts are adverse, the required level of assessment is an Environment Impact Assessment (EIA) or EIS as for Solomon Islands.

Category B. Potential adverse impacts on human population and environmentally important areas (e.g. wetlands, forest, grasslands and natural habitats) are less adverse, temporary, reversible and can be mitigated more readily than those of category A projects. The level of assessment required is equivalent to the SIG PER.

Category C. The projects are likely to have minimal or no adverse environmental impacts. Category C projects do not require an EIA/EIS or PER. The projects may require some form of Environment Management Plan developed.

Category FI. Projects involve credit line or an equity investment in a financial intermediary. Involves subprojects that will have insignificant environment impacts and do not require Environment Management System/Plan (EMS).

Page 8: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

2 | P a g e

The Bank has classified the proposed Project as a Category B project because the proposed project is expected to have minimum adverse environmental impacts. These impacts are expected to be temporary and can be readily mitigated. The preparation of Environmental and Social Management Framework (ESMF) was chosen because even though the locations are known, design and other details about the investment are not available prior to the appraisal of the project. The ESMF will guide SIEA in determining the appropriate level of environmental and social assessment required for the current and future projects and in preparing the necessary environmental and social mitigation measures for these projects during the preconstruction, construction and operational phases.

2.2 Solomon Island Regulatory Requirements

The Environment Act covers all the environmental issues in Solomon Islands and makes provisions for conservation and protection of the environment and established the Environment and Conservation Division (ECD). The Act provides for an integrated system of development control, environmental impact assessment (EIA) and pollution control. The Environment Act has considerable power by virtue of article 4 (1) which states that in the event of conflict between the Act and other Acts, the provisions of the Environment Act shall prevail.

The Environment Regulations 2008 covers detailed requirements for EIA. The Act has a schedule which lists all “prescribed’ developments’ that will need to undergo some form of EIA. All prescribed developments require a simple assessment through “screening” or “scoping” process, to see what form of additional assessment is required. Most development projects require a public environment report (PER), while many major projects will also need a second stage of appraisal which include technical, economic, environmental and social investigations presented in an EIA or environmental impact statement (EIS) report. All types and forms of aggregate extraction activities are included in the schedule as a ‘prescribe development” activity and need to undergo some form of environment impact assessment as detailed in the regulation. This report is the fulfilment of the requirement of the Act.

As required in Part III of the Act, all developer who intends to carry out or are carrying out a ‘prescribed development’ activity must make an application for development consent together with the relevant EIA report and any other relevant information as may be required by the Director. The Director with responsible staff and government agency then reviews the application with the relevant EIA report and make decision whether to grant or not to grant development consent. The developer shall not commence operation or continue to carry out any prescribe development unless it has complied with the relevant provisions of the Act, been issued a ‘development consent’ or the Director has exempted the development from the relevant approval requirements. Based on the Project description, the proposed project is expected to require a Public Environmental Report (PER).

Where environmental standards are not provided in the Regulation MECDM requires WHO standards to be used.

Page 9: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

3 | P a g e

3. PROJECT DESCRIPTION

3.1 Proposed Project Components

Under the Solomon Islands Sustainable Energy Project (SISEP, P100311, IDA Grant No. H415-SB), the World Bank is co-financing, together with SIEA, major capital works aimed at strengthening the generation and distribution capabilities of the SIEA to meet future growth demands.

The proposed project components that will be co-financed under the Solomon Islands Sustainable Energy Project grant are summarised in the table below.

The Additional Financing, totaling US$13.0 million over a 3 year period, would support the following components of the parent project: Figure 1: SIEA Project Sites

Page 10: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

4 | P a g e

Component 1, Strengthening Management. Capacity Building ($2.7 million, of which $2.0 million is IDA Grant and $0.7 million IDA Credit). Additional financing under this component will finance the following activities:

a) Technical Assistance and training on dispatch and control, system planning, integration of renewables and Independent Power Producers;

b) Provision of engineering services (owner’s engineer) for project design and supervision (to mid-2017);

c) Capital projects managers from 2014 – 2017; and d) Finance and Due Diligence Technical Assistance (legal, finance officer, procurement

officer, for upcoming Power Purchasing Agreements, e.g., Tina River Hydro and/or Savo Geothermal).

Component 3, Technical Operations. Capital investments for improving the reliability and efficiency of the Honiara power grid ($10.2 million IDA Credit). Four priority network investments would be financed to enhance the capacity of distribution transformers, lines and substations on the Honiara grid in order to enable it to meet existing and growing power demands more efficiently, provide better quality and quantity of electric power for productive uses, and reduce power system losses. Specifically, additional financing under this component would finance the following:

a) Upgrading of the transformer capacity at Ranadi, the city’s main industrial zone, by adding one 5MVA, 33kV/11kV transformer and a second 33kV switchboard at Ranadi;

b) Construction of a new system control room and dispatch centre at Ranadi; c) Installation of a 12.5MVA transformer and upgrading of the switching arrangements at

Lungga Power Station; d) Construction of a 33kV/11kV Substation at Kola’a Ridge, including a 1x7.5 MVA

transformer; and e) Relocation of the second power circuit to supply the residential area to the south of

Honiara Airport (Feeder 12 area) by building a new overhead powerline and an

underground circuit around the airport that links the East Honiara Substation to the Feeder

12 area.

3.2 Potential Future Development

SIEA has also developed a list of a number of potential future development projects to supplement the

improvements in transformer and transmission capacity. The projects in the list are not part of the current

project. However, as an when these projects are designed and implemented, irrespective of the financing

source, the World Bank Safeguard Policy requires that the projects shall follow the same protocol outlined

in this ESMF and prepare site specific instruments to address the identified environmental and social

impacts. This is also consistent with the SIG environmental requirements.

The two near-term projects which may have larger potential environmental impacts are:

1. Construction of a new Lungga Power House and installation of the First set of 2x5 MW Diesel

Generators.

2. Installation of the Second set of 2x5 MW Diesel Generators.

Page 11: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

5 | P a g e

As per the SIEA briefings, the proposed new power house will be built on the grounds and confines of the

existing Lungga Power House. The current workshop will be demolished and rebuilt at another vacant

location on the grounds of the Lungga power plant. The previous workshop site will be cleaned up and

used to house the new power house for the diesel generators. The potential environmental issues

associated with the demolition and clean-up of the old workshop site, the construction and operation of the

new power house, the construction and operation of the new workshop and the upgrading of the operation

of the existing power house should be included in the EA and EMP for the proposed new power projects.

The potential environmental issues to be addressed are given in Annex 6.

4. DESCRIPTION OF THE ENVIRONMENT

4.1 Physical environment

Solomon Islands lie at the convergence of the India-Australia crustal plate which is moving northwards and

the Pacific plate which is moving westwards. The geological processes associated with these plate

movements has resulted in the formation of Solomon Islands. Solomon Islands is geologically young and

dynamic compared to more ancient landmass like Australia. It also has high rates of uplift, active seismicity,

an erosional climate and susceptible geological materials. That is why Solomon Islands are prone to

seismic activities (Hansel et al, 1976)1.

The Solomon Islands is usually subjected to the South-easterly Trade Winds from May to October and the

North-westerly Trade Monsoon Wind from December until March. Air temperature has very little variation

due to its proximity to the equator. The average annual rainfall ranges from 3,000 to 4, 000mm. The wettest

period of the year is between the month of August to November with a daily average of 190 and 330mm.

There are 27 soil groups in Solomon Islands. Depending on parent material and land use, soils exhibit a

range of fertility. The basalt volcanic derived soils are generally rich in nitrogen, phosphorous and organic

carbon, but poor in potassium. The most fertile and agriculturally important of all soils found in Solomon

Islands are the recent alluvial soils located on the northern Guadalcanal alluvial plains.

4.2 Biological environment

The Solomon Islands is characterized by a high level of biodiversity of plants including 3,210 species of

vascular plants, although this is believed to be an under-estimation and a more correct estimate is in the

order of 4,500 when unrecorded species are included. While diversity is high, endemism is low, with no

endemic families and only three endemic genera. Endemism of species is not accurately known but is

thought to range from 10% of fern species to 80% of panadanus species. The islands with the highest rate

of endemism are Santa Cruz (Temotu) and Guadalcanal.

1Hansell, J., F and Wall J., R, D (1976), Land Resources of the Solomon Islands, Land Resource Division

Ministry of Overseas Development, England.

Page 12: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

6 | P a g e

According to State of Environment Report (SOE) 2008, 80 reptiles are known in the country which includes

marine species2. One third is endemic and 5 identified as threatened. The report stated that the prehensile-

monkey-tailed skink (Corucia zebrata) is the largest skink in the world and is endemic to the Solomon

Islands. Solomon Islands is said to have 9 endemic snake species 27 endemic species of lizards. Salt

water crocodile was observed at Aola River and may be present at Mbokokimbo, Moga, Mberande Rivers.

Pickacha et al, 2008 reported an increase from 17 species to a total of 21 frog species for Solomon Islands.

Only 2 species are endemic to Solomon Islands, Discodeles malukuna and Platymantis sp. Of the130

species of butterflies, 35 species are endemic to Solomon Islands. There are 25 endemic snail species. It is

estimated that Solomon Islands has 14,511 described species and 46,015 total insect species. A total of 31

cicada species were recorded in the country, 30 are endemic to the country3.

4.3 Socio-economic Environment

The economy of the Solomon Islands comprises a mix of subsistence production - on which the majority of

the population depends - and a monetized sector, including public services, dominated by large-scale

commercial, and largely resource development based enterprises. In terms of nearly 100,000 tons of the

major export commodities produced in 2000, fish accounts for the largest proportion at 47 per cent, copra

accounts for 23 per cent, palm oil accounts for 13 per cent, coconut oil accounts for 4 per cent, and palm

kernel and cocoa production account for 5 per cent. Log production was in the order of 536,000 m3 (SIG,

2001)4.

The population of the Solomon Islands in the 2009 census was determined as being 515,870 which is

dispersed widely across the archipelago and a population growth rate of 2.3%/yr. The population has a

broad based age-sex structure with 40% of the population below 15 years of age. With population doubling

every 30 years, pressure on available services and natural resources has increased dramatically during the

last decade, which will require the Solomon Islands to invest large resources in social infrastructure.

The Solomon Islands is a culturally diverse country with 120 indigenous languages. Melanesian pidgin is

the lingua franca. The population is made up of 93% Melanesian, 4% Polynesian, 1.5% Micronesian, 0.8%

Europeans, and 0.3% Chinese. Honiara is the capital and main urban center and in 2010 had an estimated

population of about 64,609 persons. This is considered to be an underestimate as the census did not

capture the large number of economic migrants. While this has provided the country with distinctive

cultures the isolation of these groups has also created a high dependence on natural resources.

Development has not been uniform across the country and the resulting migration to urban areas has

created squatter settlements in and around urban areas.

Honiara is the capital of Solomon Islands and is situated on Guadalcanal Island. It serves as the main

Administrative, educational, economic centre for the country and gateway to nine provinces in the Solomon

2MECM, 2008.State of the Environment Report 2008, Honiara: MECM. 3Pikacha, P., Morrison, C and Richards, S. 2008. Frogs of the Solomon Islands. Suva: Institute of Applied Science.

4SIG, 2001.Annual Report 2000.Central Bank of Solomon Islands.

Page 13: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

7 | P a g e

Islands. It has a population of just over 64,600 with an average density of 2,953 people per square

kilometre5. Honiara city was developed from the rubble of an American war base established during the

Second World War, and has grown at a rate of 2.7 percent per annum over the years to become the

primary city in the country. The city is made up of diverse ethnic groups and indigenous people (United

Nations Human Settlements Programme, 2012)6.The settlement patterns here in Honiara are driven by

high urban growth and increasing demands placed on the current urban services and problems relating to

increasing poverty. The settlement pattern is scattered in Honiara with more informal settlements outside

the Town boundary.

Being the nation’s capital, Honiara, is also the centre for the country’s small but growing industrial

establishment and all other urbanized development activities. Many other major national development

activities that play a big role in the country’s economy are hosted by the island of Guadalcanal. These

includes the largest oil palm plantations (GPPOL), the Gold Ridge Mine (GRML), and the now disaster

coconut and cocoa Plantation (RIPEL). The immediate area of the existing underground cable even though

under the jurisdiction of Guadalcanal province, is located within the Ranadi industrial area and is

surrounded by many small scale industrial establishments. These includes small scale and light

manufacturing industries, workshops, retail shops, the Taiwan demonstration farm, schools, road side stalls

and gravel production entities.

The existing land use of the area shows a mixture of multiple uses. These include illegal settlements,

timber yards, private company administrative offices, retail shop outlets, roads, churches, schools, road

side markets, bottle shops, fuel depot, recreation areas etc. The area also has an airfield.

4.4 Unexploded Ordinance (UXO)

Technically WWII ordnance found in the Pacific Islands can be defined as either unexploded (UXO) or

abandoned (AXO). Unexploded ordnance is defined as explosive ordnance that has been primed, fused,

armed or otherwise prepared for use in armed conflict but has failed to explode. Abandoned explosive

ordnance is defined as explosive ordnance unused during an armed conflict and subsequently abandoned

or left behind. UXO and AXO are defined collectively as Explosive Remnants of War (ERW) (Francis and

Alama, 2011)7.

The areas of Solomon Islands were the scenes of bitter fighting during World War II. While this was over 60

years ago, unexploded (UXO) may still be found in the area. Should UXO be discovered, the contractor is

5 SIG (2011), Solomon Islands National Statistics Bulletin 06/2011, Report on 2009 Population and Housing Census, Basic

Tables and Census Description, Honiara, Solomon Islands.

6 UN Habitats (2012), Honiara Urban Profile, Retrieved on the 5th August 2013 at URL:

http://www.google.com.sb/url?sa=t&rct=j&q=&esrc=s&frm=1&source=web&cd=2&ved=0CCwQFjAB&url=http%3A%2F%2Fwww.

unhabitat.org%2Fpmss%2FgetElectronicVersion.asp%3Fnr%3D3324%26alt%3D1&ei=ei4EUqSJEseeiQKeuYGYBg&usg=AFQj

CNHeIf11t_1NdrxxnoivuFA-L2bzCg

7Francis S, L and Alama L, 2011. World War II Unexploded Ordinance, Retrieved at URL on 29thof October 2013 at URL: http://www.forumsec.org/resources/uploads/attachments/documents/UXO%20final.pdf.

Page 14: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

8 | P a g e

to immediately cordon off the area, arrange the evacuation of nearby residences and inform the police of

the find. Currently all UXO finds are reported to the police who arrange the pickup, transport, storage and

ultimate disposal of the finds. While construction sites are expected to be swept for and cleared of UXOs, a

chance find procedure for handling the UXOs during the construction is included in the ESMF. This will be

the responsibility of the contractor. Ultimately, the SIEA will be responsible for the supervision and

monitoring of the contractor.

5. ANTICIPATED ENVIRONMENTAL IMPACTS AND POTENTIAL MITIGATION MEASURES

5.1 Significance of Impacts

The potential environment and social impacts are assessed based on the design, scope of work as well as

the physical and biological environment at the project sites. Mitigation measures for each potential

environment and social impacts are designed to avoid, minimize or remediate the impacts. The impact

mode may be minor, moderate, major or induced. Relevant Standard Operating procedures (SOPs) are

listed in the appendix 5 to support and mange activities undertaken by SIEA on a day to day basis. SIEA

will need to develop this SOPs and train workers on how to use them.

The proposed project involves very little traditional “earth-moving” type construction. The transformers

switch gears and control rooms will be installed in and as part of the existing structures. The only new

construction involve the construction of a substation at Kola’a Ridge, installation of new power line poles to

tie in the Honiara East substation to No 12 Feeder Line from Lungga Power Station and installation of an

underground cable around the east end of the airport runway as part of the No12 Feeder Line connection.

As such the environmental impacts are expected to be minor, if any.

5.2 Pre-construction Impacts

Pre-construction impacts are expected to be associate mostly with the clearance of UXO from the proposed

location of the power line along the road on the north and south sides of the runway, the alignment of the

underground cable around the east end of the runway (along the existing road side) and the existing site of

the new sub-station at Kola’a Ridge. While the general locations of the above infrastructure is known, the

actual alignment of the above ground power line, the underground cable route and the exact location of the

Kola’a Ridge sub-station will be known after the detailed designs and surveys have been carried out.

UXO: During WWII, the area was subject to intense battles and while this occurred over 60 years ago, it is

possible that a chance discovery of a UXO may occur. The proposed project areas and alignments will be

swept for UXO and if found will be cleared as per the established procedures before the sites are handed

over to the Contractors or the SIEA personnel for construction. During construction, should UXO be

discovered, the contractor is to immediately stop work, cordon off the area, arrange the evacuation of

nearby residents and inform the Police of the find.

In Solomon Islands the responsibility for UXO typically resides with The Royal Solomon Islands Police

Force Explosive Ordinance Disposal Unit (RSIPF-EOD Unit).The Ministry of Infrastructure (MID) is in the

process of developing UXO procedures which when completed and approved by the Government, will be

Page 15: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

9 | P a g e

included in the MID Specifications for Roads and Bridges. Refer to annex 3 for the draft MID UXO protocol.

The proposed draft procedure by SIEA (which is neither complete nor approved) is attached for information.

The procedure will be used as a guide and will be updated as appropriate.

The procedure is attached as Annex 3.

Worker Safety: Pre-construction activities may involve survey activities to delineate the location of power

poles and for the overhead line and selection of the route for the laying of the underground power cable.

This would require the Contractor to observe traffic requirements to avoid congestion and minimize the

potential for accidents. The contractor will also need to observe general health and safety requirements and

as a minimum, be compliant with the Labor Act of 1978 and the Safety at Work Act of 1996.

Accidental discovery of archaeological resources: The site clearance, digging and excavation activities

undertaken during pre- construction and construction may un-earth archaeological sites or resources. In the

event this occurs, the work shall cease immediately and the National Museum Tambu Register (the

Authority), Ministry of Culture and MECDM shall be informed.

Construction will not re-commence until the Authority have signed-off that the site/resources have been

dealt with appropriately and that work may continue. The Contractor shall be responsible for complying with

the requirements of authorities, and the SIEA shall monitor the same. A chance find procedure is attaches

as Annex 7.

5.3 Construction Impacts

Soil digging / earth moving activities for the laying the underground power cable, erecting power poles, and

laying foundation for the sub-station at Kola’a Ridge may result in the generation of dust, soil erosion,

potential drainage issue and disposal of the excess excavated materials. However the scale of these

activities is small and the environmental impacts are expected to be minor. None the less the, the

Contractor is expected to prevent pollution emanating from these activities and take remedial measures.

Site Drainage: Where appropriate the Contractor will manage the site drainage as follows:

Install side drains (off-takes) to direct storm-water flows away from the project area;

Where cross drains are required provide stable outlets to carry the runoff safely to the disposal area.

Culverts and drains should not be allowed to terminate above a disposal area without considering the possible effects on the stability of the discharge area;

All drainages should be directed to safe (non-eroding) areas;

Temporary drains should be refilled after construction and the drain area should be rehabilitated.

Soil Erosion: Soil erosion is likely if the cable trench or the foundation areas at the Kola’a Ridge sites are

left open for extended period. The impacts may be either through dust erosion during dry season or soil

erosion during wet season. The scale of the excavation is small and large stock piles of excavated

materials are not expected. Because of potential threat of stealing cables, such operations as the laying of

cables are carried out expeditiously and the trench is refilled and compacted immediately after the cable is

buried.

Page 16: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

10 | P a g e

Poles for the overhead power lines will be installed once every 25 meters. The poles will be encased in

concrete, and the excess soil will be spread in and around the poles.

At the Kola’a Ridge site, excess excavated material will be either spread on site or removed for disposal as

backfill material. Given the scale of construction, the quantity of material is very low.

Figure 2: Map showing the east of the Henderson Runway

Dust: The construction works will have a minor and temporary impact in the form of dust during dry windy

conditions. Some air pollution is expected from vehicles transporting power poles, transformers, cables,

and other construction materials. Except from concrete foundations for sub-stations there will be very little

construction related activities requiring large scale stock piling of materials. There are no air quality or

emission standards in Solomon Islands, and as the project is not a „green-fields‟ development nor is it

highly polluting, preparing a baseline for subsequent monitoring is not considered warranted. There are a

number of good engineering practices that can be employed to ensure that dust and vehicle related air

quality impacts are mitigated during construction. These include:

Construction equipment being maintained to a good standard. The equipment will be checked at regular intervals to ensure they are maintained in working order and the checks will be recorded by the SIEA as part of environmental monitoring;

Page 17: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

11 | P a g e

Prohibition of the use of equipment and machinery that causes excessive pollution(i.e. visible smoke) at the project sites;

Ensuring that all vehicles transporting potentially dust-producing material are not overloaded, are provided with adequate tail-boards and side-boards, and are adequately covered with a tarpaulin (covering the entire load and secured at the sides and tail of the vehicle) during transportation;

Material stockpiles being located in sheltered areas and be covered with tarpaulins or other such suitable covering to prevent material becoming airborne; and

Periodic qualitative air quality monitoring (by observation rather than testing).

Construction and demolition waste: It is possible that remains of construction and demolished materials may accumulate at the project sites. Demolished materials and construction materials will be disposed of at designated site approved by SIEA. These wastes should be removed fairly immediately at the first instance during the construction phase to allow accessibility and for health and safety reasons. Solid wastes, debris, spent oil or fuel from construction machinery or plant, construction material, or waste vegetation removed from worksites will not be dumped in streams or near streams.

Impacts on Noise Levels: There are no noise standards in Solomon Islands, and the noise generated by

the project will be temporary (i.e. during construction) and intermittent.

Construction noise is generally intermittent, attenuates quickly with distance, and depends on the type of

operation, location and function of equipment. During construction, there will be a temporary adverse

impact due to the noise of the construction equipment. However, all of the works are in fairly remote areas,

away from schools or residences. Nonetheless, the following general measures will be taken to mitigate the

effects of noise:

Contractors will be required to maintain all vehicle exhaust systems and noise generating equipment in good working order and maintained regularly.

Prohibition of any construction activities between 9pm and 6am in, or close to, residential sites;

SIEA will prepare a schedule of operations that will be approved by affected stakeholders. The schedule will establish the days, including identifying days on which there should be no work, and hours of work for each construction activity and identify the types of equipment to be used;

Workers will be provided with noise abatement equipment as may be required; and

Any complaints regarding noise will be dealt with by the SIEA in the first instance through the redress grievances mechanism.

Impacts on Access: The project may cause temporary negative impacts, including inconvenience, minor

disruptions to traffic using the road and on local access during the construction period.

Mitigation of impacts on access will include:

Care taken during the construction period to ensure that disruptions to access and traffic are minimized;

Signs and other appropriate safety features will be used to indicate construction works are being undertaken; and

Page 18: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

12 | P a g e

SIEA will ensure access roads to private owned land are not disturbed.

Impacts on Health and Safety: The project’s construction phase may cause potential health and safety

impacts. The main impacts on health and safety are associated with (i) risk of accidents at work sites, and

(ii) traffic safety issues. The risk of spread of communicable disease is considered to be negligible because

there is no expected high influx of people in search of jobs at project sites.

Observing general health and safety requirements, including supply of safety and protective gear and

equipment to workers, to reduce the risk of accidents at the work sites. Mitigation measures for reducing

and avoiding impacts on health and safety include:

Provide construction workers training in health and safety issues, and on the specific hazards of their work;

Provide workers with personal protection equipment, such as safety boots, safety glasses, reflector vests, helmets, gloves, and protective clothing;

Provision of adequate protection to the general public in the vicinity of the work site, including advance notice of commencement of works, installing safety barriers if required and signage or marking of the work areas.

5.4 Operation Impacts

There will be no operation related impacts except for low level humming noise from the transformers. The noise is not discernable from the road side and given the remote locations of these transformers, no impacts are anticipated.

6. ANALYSIS OF ALTERNATIVES

6.1 Project location

The majority of the proposed project components will be installed in the existing facilities. The exceptions to these are the laying of the underground power cable and the extension of the No 12 Feeder line. The proposed new underground cable will replace the existing, dysfunctional (dead) underground cable beneath the airport runway. Barring the digging up of the runway, the proposed new underground cable takes the most direct route around the east end of the runway, along the existing road right of way, and therefore no land acquisition. The new overhead power line construction route provides short and direct connection to the new underground cable and also meets the IATA requirements for safety of the runway, where the power poles are placed over 145 meters from the centre of the runway. SIEA has discussed and agreed on the measures with both the Aviation Authority and the Roads Agency. There is no other realistic alternative to the existing location that will provide the same economic, environmental and social advantage.

6.2 Project technology

Apart from the installation of the new generators and switchgear, the underground cable line will be

constructed using modern, locally and internationally accepted materials to achieve public health, safety,

security and environmental aesthetic requirements. Equipment that guarantee efficient use of locally

Page 19: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

13 | P a g e

available materials will be encouraged to ensure reliability in supply with minimum power loss and good

design to allow efficient distribution of power to Honiara.

6.3 Do nothing

The existing power line networks and transformers supplying Honiara are highly constraints in terms of

capacity and are unable to supply secure network distribution and alternative feed in case of the existing

power line and transformer dysfunction. Therefore, it is imperative for SIEA to establish and install

additional transformers and power line feed connection to provide secure supply.

7. PUBLIC CONSULTATIONS, INFORMATION DISCLOSURE

7.1 Public consultation

IDA/WB’s Safeguard Policies and the Government of Solomon Islands’ regulations require project related ESMF to be subject to public consultations and disclosure. This is done at an early stage of project preparation so as to inform the stakeholders of the project components and to seek / encourage inputs from the stakeholders on environmental and social issues.

For the proposed project, the project information and the call for public consultation was announced on:

Tue 29 October 2013,in press advertisement regarding Public Consultations on Environmental and Social issues relating to proposed network upgrades around Honiara; and

Wed 30 October 2013,in newspaper notice providing summary details on Environmental and Social issues and specific details around public consultations (in English & Pidgin).

Additionally, public consultation was carried out:

On a radio talkback show on Saturday 9 November 2013, at 10 am to 11am;

Through information posters displayed on Wednesday 6 Nov 2013 at two sites readily accessible to the public. The sites were: a) the SIEA's customer service office at the Hyundai Mall, Honiara (next door to the main city market); and b) the SIEA's Headquarters at Ranadi; and

With stakeholder including SIWA, Telecom, Pan Pacific, Solomon Island National University (SINU), Ministry of Communication and Aviation (MCA), Seventh Day Adventist Authority (SDA) and Market Vendors.

7.2 Results of Public Consultation

The result of public consultation with the stakeholder provides opportunity to understand the current social and environment issues and the need for the improving the supply of electricity. Overall, stakeholders consulted express strong support for the project.

Table 1: Consultation-Radio talk back

Page 20: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

14 | P a g e

Caller ID Issues/question/comments SIEA Response

1 Are they any provision from the grant to cover cost incurred by customers for connection installations?

The WB funding will cover cost for the major 5 projects and not SIEA operational cost such as power service connection.

2 Safety concern over the project at East Kola’a ridge.

Public Safety is addressed in the design. The design will ensure maximum safety standards are met by SIEA e.g. raised concrete walls.

3 What time will power serge stops? The current capacity of load does not cater for the Honiara City. The current project intends to improve power serge and provide reliable service to the public.

4 Public safety concerning the substation at East Kola’a ridge.

Again the substation will be design to international requirements.

5 Public are not happy when calling SIEA for information regarding power serge (when it will happen and when it will come back).

Customer service is available on weekdays to answer public concern over power surge. It might not be reliable to call direct to Power House because the officers might be busy with maintenance etc.

Table 2: Stakeholder consultation

Organisation Names of People

Consulted

Issues/comments/questions

raised

SIEA Responses

Guadalcanal Province Victor Totu (CAO)

Pricilar Oliver (SAO)

Public Safety-Signs visible to public;

Land acquisition done before any

operation;

Reduce voltage near roads;

How safe are the cables from being

vandalised;

News letter about services provided

by SIEA published in media

Quarterly; and

Generally the upgrade is important

for the public.

Safety signs informing

the public of the

construction works will

be installed at selected

sites;

The underground

cable will run along the

existing road corridor

and no additional land

take is required;

There is radio talk

back show every

Wednesday.

Solomon Islands National

University (SINU)

Jimmy Hycent (Lecturer);

Laurel Bates (SAO)

Oswald Bako (SAO)

Patrick Turanga (Students

Well Fare Division)

Studies should prove, materials used

can avoid electrocution during

flooding;

Poles design to withstand

earthquakes;

Underground cable reduce line

congestion and land space for

expansion;

The project

components are

design to standard

international

requirements.

Page 21: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

15 | P a g e

Where poles or cables are located,

trees and other structures should not

be there; and

Tougher penalties on public

buildings constructed under

powerlines and transformers.

Ministry of Communication

and Aviation

Nicolous L (Airport

Manager)

The airport itself requires continuous

supply of electricity;

Deliver design details to airport

planners so that it can be integrated

in the MCA management plan;

Existing powerlines within the airside

must be removed to outside

perimeter;

Close dialogue with airport

authorities is important to avoid

plans overlap; and

The cables must be underground.

One of the project

object is to improve the

power serge;

There will be

continuous dialogues

with relevant

authorities about the

project and its

schedule including

designs ect.

Seven day Adventist

Authority

Pr Samuel Panda

(Secretary Solomon Islands

Mission)

Risk of electrocution during rainy

season;

Burnscreek area where the cable

runs underground is prone to

flooding;

Temporary disturbance to access

roads during the construction;

The upgrade of the power supply will

help boost the amount and time

electricity will be available;

Can the upgrade indicate cheaper

rates for institutions?

The trench and cabling

are design to

standards and have

passed standard

safety requirements;

There will be

temporary disturbance

to work areas, affected

stakeholder will be

informed about any

disruptions.

Pan Pacific Eddie (Administration) Questions have been asked

including reducing voltages from

240V to 110 V in residence areas,

due to some electrical appliance

having 110V;

Chances of damages to other

utilities;

SIEA has obligation to provide

efficient power and services to the

public therefore the upgrade is a

good proposal;

Standard safety

requirement are

incorporated in the

design;

Restricted areas will

have safety signs

informing public of the

risk.

Page 22: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

16 | P a g e

Safety signs warning public and

residence of the risk. (Clear caution

signs, restricted area signs, and

etc…); and

The upgrade will help in boost the

production industries.

Market vendor John T Safety signs warning public and

residence of the risk. (Clear caution

signs, restricted area signs, and

etc…);

The upgrade will help in boost the

production industries;

The transformers near the burns

creek betel nut market should be

relocated away from the roads side

and general public; and

The upgrade may require digging of

the ground. Are there any

opportunities for Burnscreek youths

to work as casual workers within the

vicinity of Burnscreek area?

Restricted areas will

have safety signs

informing public of the

risk;

The transformers are

within the road

corridor, additional

land take require land

acquisition.

The ESMF documenting the potential mitigation measures and the outcome of the consultation process will be submitted to MECDM and WB and will be disclosed for public review. Additional consultation and disclosure will be done during implementation through:

The preparation and dissemination of a brochure in English and Pidgin (and other languages as required), explaining the project, works required and anticipated timing of the works;

Setting up a formal grievance redress committee with a representation from the affected people. The contractor will be responsible for managing the grievance redress program; and

Information regarding the approved subproject and the proposed environmental management measures will be posted at suitable locations at the project site.

7.3 Disclosure

Disclosure will conform to the Public Communications Policy of the WB: Disclosure and Exchange of Information which requires that the ESMF report for WB projects be accessible to the interested parties and the general public. Prior to the Appraisal, the ESMF will be disclosed in the World Bank Infoshop and made available to the public from SIEA web site.

Page 23: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

17 | P a g e

8. INSTITUTIONAL ARRANGEMENT

8.1 World Bank

The WB will:

Advise the SIEA about WB Safeguard Policy requirements;

Screen and determine environmental categorization of projects, including the environmental assessment requirements;

Review and clear environmental assessment reports as a basis for project approval;

Publicly disclose the ESMF in the Infoshop and on the WB website;

Review all statutory environmental clearance granted by ECD (particularly the conditions of the Development Consent) and note all conditions in approving a subproject;

Review EMP implementation and where appropriate take actions (as necessary) in close consultation with ECD;

Monitor the EMP implementation and conduct due diligence as part of review missions;

Provide assistance to SIEA, if required, in carrying out its responsibilities and for building capacity for safeguard compliance; and

Ensure that SIEA will conduct the required consultations with project affected groups and local NGOs in the project area and discloses relevant information on the project’s environmental issues in an appropriate form, manner, and language(s) accessible to those being consulted.

8.2 SIEA

The overall management of all monitoring tasks comes under the SIEA. This covers all aspects of the required activities including coordination with other agencies that have national responsibilities over some of the tasks. SIEA is responsible for general project execution and with day-to-day project management activities, as well as monitoring. SIEA will prepare and submit to ECD Monthly Progress Reports.

Once the detailed designs and site surveys are available, SIEA will prepare a detailed Environmental Management Plan (EMP) using the ESMF as a guidance document. The detailed EMP will be submitted to the World Bank and ECD for review, comments and approval. The EMP will be included as an integral part of the Bid Documents to enable the Contractors to bid on the Project with awareness of the environmental issues and mitigation measures to be implemented as part of the Project. The successful contractor will prepare a Construction Environmental Management Plan (CEMP) outlining how he intends to implement and monitor the EMP during construction.

SIEA will be responsible for updating the EMP at construction stage, whenever additional engineering information is available and for implementing the environmental, health and safety actions included in the EMP. Currently, SIEA has no in-house capacity to manage or supervise environmental and social issues related to its own activities, although it has been running a large power generation and distribution operation. It should seriously consider hiring its own in environmental / social officer, to look after its own operations especially if it plans to undertake a large Capex expenditure in the near future. The Environmental / Social Officer should:

Page 24: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

18 | P a g e

Prepare a Brief pertaining to the design issues that are identified in the EMP for action by the technical design team;

Coordinating with ECD for updating the EMP;

Participating in monitoring to ensure that environmental management activities are reported as required; Coordinating and communicating as appropriate; consultation with the affected stakeholders and ensuring smooth implementation of the project; and

Advise SIEA on potential environmental and social impacts and their mitigation measures as they come on board.

As required, SIEA will be responsible for environmental monitoring during construction and operation of the project. The ECD will also be responsible for verifying the monitoring undertaken by the SIEA through audits and spot-checks. The outcomes of the monitoring will be included in the overall monthly progress reports to be submitted by SIEA to ECD.

8.3 Environment & Conservation Division

As the national agency responsible for environment and conservation, the ECD will need to be involved in the various aspects of the environmental management activities. Under the requirements of the Environment Act 1998, ECD will need to review the EIA and monitor the progress of implementation activities if consent is given. The ECD has been fully informed of the status of the project and also awaits the submission of the EIA.

The ECD will need to be consulted during the construction phase of the project to ensure that all monitoring requirements are adhered to. The ECD will be tasked also to assist in the auditing of implementation of the EMPs and ensure that environmental management and mitigation of the project is undertaken to a good standard.

8.4 Environmental Monitoring and Reporting Arrangements

Monitoring is a component of impact assessment setup to combat uncertainties pertaining to unanticipated impacts, to ensure mitigation measures are working and to reassure public on the progress of the development. Progressive monitoring must accompany various stages of the project activities (construction and operational phase). The Environmental monitoring plan is based on the`` potential impacts, significance of the impacts and mitigation approaches identified during the screening study. It comprises of parameters to be monitored, frequencies and responsible authorities as per impact. ECD is responsible for monitoring compliance, review SIEA monthly monitoring report and suggest ways to improve or strengthen mitigation approaches.

The ECD is required to:

Co-ordinate compliance monitoring programs; and

Review SIEA monthly monitoring report and suggest ways to strengthen mitigation approaches.

Page 25: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

19 | P a g e

Table 3: Responsibilities for Environmental Management & Monitoring

Project Stage

Responsible Organization

Responsibilities

Feasibility studies and appointment

SIEA and WB Prepare EA including overall EMP

Preliminary design

Feasibility studies and project review and approval

ECD, SIEA and WB

Review and approval of EIA including overall ESMF / EMP

Review all feasibility study documentation, prepare Board presentation and submit to Steering Committee (as required)

Provide inputs to monitoring requirements

Detailed Design

SIEA Prepare detailed design

Update EMP based on specifics of detailed design

Submit EMP to ECD and IDA/WB for review and approval

Construction SIEA and Contractor

Implementation and Supervision of the EMP

Audit construction phase through environmental inspections and review monitoring data

Preparation and submission of monthly environmental reports

Provide awareness/training to workers

MECDM Ensure compliance with Government requirements

Review complicated issues arising from the project

Operation SIEA Provide budget to undertake long term environmental monitoring

Undertake environmental monitoring and prepare bi-annual reports

8.5 Grievances redress mechanism

Construction: It is anticipated that most complaints arising during construction are expected to be minor complaints concerning dust, health &safety implications and noise that should be able to be resolved quite easily. All complaints arriving at the Contractor’s Site Office will be entered in a Register that is kept at the site by: date, name, contact address and reason for the complaint. A duplicate copy of the entry is given to the Affected People (AP) for their record at the time of registering the complaint. The Register will show who has been directed to deal with the complaint and the date when this was made together with the date when the AP was informed of the decision and how the decision was conveyed to the AP. The Register is then signed off by the person who is responsible for the decision and dated. The Register will be kept at the front desk of the SIEA Office and is a public document. The duplicate copy given to the AP will also show

Page 26: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

20 | P a g e

the procedure that will be followed in assessing the complaint, together with a statement affirming the rights of the AP to make a complaint. There will be no cost to the AP for making the complaint.

In the first instance, the Affected People will be directed to discuss their complaint directly with the Project Engineer (PE). For straightforward complaints, the PE can make an on-the-spot determination to resolve the issue.

For more complicated complaints, the PE will forward the complaint to the SIEA Management. The SIEA Management has a maximum of two days to resolve the complaint and convey a decision to the AP. The AP may if so desired, discuss the complaint directly with the SIEA Management. If the complaint of the AP is dismissed, the AP will be informed of their rights in taking it to the next step. A copy of the decision will be sent to the ECD.

Should the AP not be satisfied, the AP may take the complaint to the Permanent Secretary (PS) in MECDM who will appoint the Director of the ECD to review the complaint. The PS will have 15 days to make a determination.

Operation: During operation, the same procedure applies i.e., there are no fees attached to the AP for making a complaint, the complainant is free to make the complaint which will be treated in a transparent manner and the AP will not be project to retribution for making the complaint.

9. CONCLUSIONS AND RECOMMENDATIONS

The act responsible for EA in the Solomon Islands is the environment Act 1998 and Environment Regulation 2008. The procedures outline in the SIG Acts and WB OP4.01 are integrated in this EMSF which will form a key component and requirement when and where SIEA implements the proposed project.

The EMSF provides screening tools as Annex 2, an overview of the potential environment and mitigations, requirement for environmental management and monitoring, consultation and disclosure, redress grievances processes and institutional arrangement as a corner stone for ESMF implementation. It provides guidance for use in developing a project specific Environmental Management Plan when the detail designs are available.

Page 27: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

Annexes

1. Excerpts of Relevant Sections of Solomon Island Regulations on Environmental Assessment

Act Date Main objectives

Labor Act 1978 This Act deal with employment of workers. Part IX Care of Workers, requires the employer

under:

o Article 65: to provide workers with rations. o Article 66: to protect workers and dependents from malaria. o Article 67: to provide workers with an accessible supply of clean, non-

polluted water for drinking, washing and for other domestic purposes. Water supplies may be inspected by a Health Officer.

o Article 68: requires the employer to make sufficient and proper sanitary arrangements for workers.

o Article 69: requires the employer to provide accommodation for the worker and his family if they are not conveniently located to the work place.

o Article 70: requires the employer to provide medical care at the workplace. o Article 71: states that depending on the circumstances the employer may

be required to provide medical facilities,

Safety at Work

Act

1996 This Act consists of 4 parts.

o Part II: Article 4 states that it is the duty of every employer to ensure the health and safety at work of his employees.

o Article 6: states that it is the duty of the employer to provide a safe workplace for persons other than his employees.

o Articles 7 and 8: requires manufacturers, suppliers of tools and equipment and suppliers of chemicals and other hazardous substances to ensure that these are safe and without health risks.

o Article 12: states that any employer who operates unsafe machinery or substances and is injured will be responsible for the damages.

o Part III: Article 15 requires the employer to protect people from dust, fumes, etc. Article 16 provides for limits of exposure to dust and fumes.

o Articles 17, 18, 19 and 20 require employers to comply with the operating requirements for: (i) pressure and vacuum systems; (ii) machinery; (iii) dangerous machinery; and (v) electrical installations.

Articles 21 and 22 require workplaces to have fire protection and to take precautions against

explosions.

River Waters 1973 Control of river waters for equitable and beneficial use; establishes activities for which

permits are required.

Lands and

Titles

1988 Covers the management of land; defines “customary land” and sets out procedures for land

acquisition. This Act is being reviewed.

Provincial

Government

Act,

1997 The Provincial Government Act of 1997 gives power to the provinces to make their own

legislation including environment and conservation. Schedule 3 of the Act provides a list of

activities for which the provinces have responsibility to pass ordinances.

The State of the Environment Report (2008) shows that eight provincial ordinances have

Page 28: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

been passed which include:

o one environmental protection ordinance, o six wildlife and wildlife management and conservation area ordinances,

and o one marine and freshwater ordinance.

2. Field Screening Check List

E n v i r o n m e n t S c r e e n i n g C h e c k l i s t F o r m ( s o u r c e : C P I U , 2 0 1 2 )

SECTION 1. REQUIRED INFORMATION

This section presents the various information required to be submitted by the project proponent as attachments to the EA Reports.

Attachments Remarks

Topographic map (scale 1:50,000) indicating project site and significant landmarks, or straight line diagram of the project showing water bodies and other relevant areas to be traversed vital in the evaluation of the project

Preliminary engineering design/drawings

Proposed schedules of activities (construction stage)

Community consultation (Attendees)

SECTION 2. GENERAL INFORMATION

2.1 Project Title :

2.2 Project Location :

2.3 Proponent :

Contact Person :

Address :

Tel/Fax # :

E-mail

Page 29: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

SECTION 3. PROJECT DESCRIPTION

3.1 Project Type

3.2 Total Project Cost

3.3 Funding Source:

3.4 Project Components

3.5 Material Requirements

3.4 Location of construction water:

3.6 Manpower and Employment

How many people will be employed by the project?

During the pre-construction/construction period: ________

During the operation and maintenance period: _________

3.7 Construction Schedule

How long will the pre-construction/construction period take? ___months____

SECTION 4. DESCRIPTION OF PROJECT SURROUNDINGS

4.1 Physical Environment

Components/Parameters Remarks

Yes No

What is the general elevation of the project area?

< 100 masl

100-300 masl

301-500 masl

501-1,000 masl

1001-1500 masl

>1,500 masl

(To determine elevation, refer to the topographic map where the elevation per contour line is indicated)

(indicate the area per elevation range or estimate the % to total area)

Slope and topography of the area

Terrain is flat or level (0-3% slope)?

Gently sloping to undulating (3-8% slope)?

Undulating to rolling (8-18% slope)?

Rolling to moderately steep (18-30% slope)?

Steeply sloping (30-50% slope)?

Very steep to mountainous (>50% slope)?

(indicating the area per slope category or estimate the % to total area)

Are there areas in the site where indications of soil erosion are occurring? If yes, what activities are causing erosion?

Causes of erosion:

[ ] heavy rains

[ ] unstable slopes

[ ] others, pls. specify

Page 30: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

Components/Parameters Remarks

Yes No

Do you know of any landslide occurring or that has occurred at the site?

Causes of landslide:

[ ] earthquake

[ ] unstable slopes

[ ] earthmoving

[ ] others, pls. specify

Has the area experienced any flooding during the wet season or cyclones? If yes, when was the last time the area was flooded? What caused the flooding?

Period(s) of flooding:

September through April

Causes of flooding:

[ ] low area/elevation

[ ] poor drainage

[ ] water logged

Soil type of the area:

[ ] sandy soil

[ ] clayey soil

[ ] sandy loam soil

Other soil types:

Are there existing structures or developments around the project site? If yes, please list them in the space below or in the opposite space.

What is the present land use of the area?

[ ] Prime Agriculture Land

[ ] Urban area

[] Others, pls. specify:

4.2 Biological Impacts

Screening Questions Description (Quality of resources, vegetation and habitat) Yes No

Terrestrial

Will agricultural land or plantation forest be affected?

Will a declared or proposed protected area be affected?

Will a community/traditional conservation area be affected?

Will riverbank habitat be affected?

Will a mangrove/wetland area be affected?

Will primary forest be affected?

Will secondary forest be affected?

Are there any rare or endangered species

Page 31: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

(terrestrial or aquatic) known to inhabit the area?

Is the area important for biodiversity protection?

Will the proposal increase access to protected areas or areas important for biodiversity protection?

Will any culturally or historically important sites or resources be affected?

Marine

Will the project affect any MPA

Will the project affect any buffer zone of the MPA

Are there any endangered coral species likely to be affected

Are there any endangered reef fish, pelagic fish, reptiles, ect affected

Potential Magnitude of Impact Area (m2)

Approximate loss of agricultural land or plantation forest area

Approximate loss of riverbank habitat area

Approximate loss of primary forest

Approximate loss of secondary forest

Approximate loss of mangrove/wetland area

Approximate loss of coral reef area

If answer is yes to the above answers, please provide examples of these species (common or local name)

in the table provided below.

Birds and Other Wildlife Trees and Other Important

Vegetation

Fishery Resources

4.3 Information on Environment Impacts What is the predominate type of vegetation to be affected?

What is the estimate of total area of this type of vegetation to be affected?

What is the proportion of affected area of the total area of this type of vegetation?

What is the estimate of total area of mangroves to be affected?

What is the proportion of affected area of total mangrove area at this location?

What is the viability of the total mangrove area (at this location) in respect of the loss? Briefly explain

Page 32: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

What is the estimate of total area of coral reef area to be affected?.

What is the proportion of affected area of total coral reef area at this location?

Are there any other ongoing impacts or proposals which could increase the significance of this loss i.e. cumulative impacts?

What is the estimate of total area of riverbank habitat to be affected?

What is the proportion of affected area of total riverbank habitat at this location?

What is the viability of the riverbank habitat (in this location) in respect of the loss?

SECTION 5. PROJECT CATEGORISATION FOR ENVIRONMENTAL IMPACTS

Based on the definition of impacts in WB Policy OP4.01, what is the category?

Category A, significant environmental impact, a full EIA/EIS is required [ ]

Category B, non-significant environmental impact, a PER is required [ ]

Category C, no EIA/EIS or PER is required but due diligence report to be prepared, EMP developed by the contractor [ ]

Category FI, insignificant environmental impacts and do not require Environment Management System/Plan (EMS).

[ ]

The foregoing has been reviewed and agreed with by:

Name & Signature Date…………………

Name & Signature Date…………………

Name & Signature

Page 33: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

3. Draft MID UXO Protocol

Page 34: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 35: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 36: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 37: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 38: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

4. UXO protocol

Page 39: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 40: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 41: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 42: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 43: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 44: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 45: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 46: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 47: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

5. Relevant Standard Operating Procedures (SOP)

SOP- Managing Air Quality during construction and operation

SOP-Fueling vehicle

SOP-Transportation of fuel + chemicals to project site

SOP-Surface water quality monitoring

SOP- Waste Oil Collection Storage and Removal

SOP- Hydrocarbon Spills

SOP- Erosion and Sediment Control

SOP- Strom water Design – Drainage Techniques

SOP- Vegetation Clearing

SOP- Wood Waste and Timber Off-cuts Handling, Disposal, and Management

SOP- Oily Rags Waste Handling, Disposal, and Management

SOP- Waste Scrap Steel and Metals Handling, Disposal, and Management

Page 48: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

6. Potential Environmental Impacts envisaged for Future SIEA Developments

Preconstruction Impacts Construction Impacts Operation Impacts

Demolition wastes including

disposal of oil, chemicals, debris,

concrete, contaminated soil,

scrap metals ect;

Transportation of demolition

wastes creating dust;

Operation of demolition machines

creating noise and vibrations;

Worker safety a concern;

Accidental spillage of chemicals

to waterways causing pollution.

Operation of construction

machines creating noise and

emissions;

Sedimentation and siltation to

adjacent water bodies;

Water quality can be affected

during construction activities

when soils, wastewater, oils and

lubricants, sewage and other

materials are allowed to move

into the environment;

The project’s construction phase

can cause a range of health and

safety impacts;

It is possible that remains of

construction waste accumulate at

the project sites. Construction

waste will be disposed at

designated site approved by

SIEA;

Accident arises posing risk to

workers-Workers health and

safety;

Operation of generator creating

noise and emissions eg NOx,

SOx, CO and burnt

hydrocarbons;

Accidental spillage of oil and

fuel during the operation of the

generator;

Management of Waste

generated at Power station

(Solid and liquid waste);

Storm water drainages;

Continuous supply of water to

project sites (power station) for

use by generators and for use

in emergency responses when

an accident occurs important;

There are marginal impacts

involving delivery and storage

of fuel. Negligence of protocol

can result in a disaster.

Page 49: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

7. SIEA Consultation Notices (Pidgin and English version)

Page 50: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for
Page 51: ENVIRONMENT AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) · 2016. 7. 10. · iii . Executive Summary . This Environmental and Social Management Framework (ESMF) is an assessment tool for

8. Cultural Find procedure for physical cultural properties