environmental management plan for the …eia.met.gov.na/...swakopmund_service_station_final.pdf ·...
TRANSCRIPT
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
1
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL MANAGEMENT PLAN FOR THE ESTABLISHMENT OF A
NEW SERVICE STATION AT OCEAN VIEW EXTENSION 29 IN SWAKOPMUND.
Prepared by:
P. O. Box 70822, Khomasdal, Windhoek, Namibia.
+264 812 683 578
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
2
PREPARED BY
OUTRUN CONSULTANTS CC
PROJECT DETAILS
TITLE ENVIRONMENTAL MANAGEMENT PLAN – THE
ESTABLISHMENT OF A NEW SERVICE STATION AT OCEAN
VIEW EXTENSION 29 IN SWAKOPMUND – ERONGO REGION.
TERMS OF REFERENCE
AND SCOPE OF THE PROJECT DESIGN, CONSTRUCTION AND OPERATION OF A SERVICE
STATION.
AUTHORS OUTRUN CONSULTANTS CC
CLIENT SWAKOPMUND SERVICE STATION CC
REPORT STATUS FINAL ENVIRONMENTAL MANAGEMENT PLAN
DATE 30 OCTOBER 2019
AUTHORISED SIGNATURE:
JOSIAH T. MUKUTIRI
EIA PRACTITIONER
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
3
PREPARED BY
OUTRUN CONSULTANTS CC
Executive Summary
This Environmental Management Plan was compiled following Environmental Impact
Assessment regulations as required by Outrun Consultants CC. The process was
done in line with the Namibian Environmental Assessment Policy (1995) and the
Environmental Management Act (2007). The EMP was triggered by the proposed
establishment of a new service station at Ocean View in Swakopmund. The
Proponent is Swakopmund Service Station, a wholly Namibian Company head
quartered in Swakopmund. The desirability of this project lies on the fact that it
improves fuel availability and convenience for travellers between Swakopmund and
Henties Bay. Public consultations were done and all issues and concerns raised
were addressed as required:
There was a concern that the proposed project site was not zoned for business,
however this was disqualified since the Municipality issued a conditional consent
letter to the Proponent. There was also concern that there are many service station
stations in the area. The study findings do not support this as there is evident growth
in the volume of traffic for both Swakopmund and Henties Bay. The Consultant
recommended the use of South African National Standards (SANS) for the design,
manufacture and construction of new facilities since we do not have our own
standards here in Namibia. An Environmental Management Plan (EMP) was
formulated for implementation by the Proponent so as to mitigate the identified
environmental impacts during the design, construction and operation of the new
service station. The proponent is also advised to adhere to all laws and policies
relevant to this project. It was concluded that the project has both positive and
negative impacts on the environment and should be managed through the
successful implementation of the proposed environmental management plan.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
4
PREPARED BY
OUTRUN CONSULTANTS CC
TABLE OF CONTENTS
Executive Summary .......................................................................................................................... 3
TABLE OF CONTENTS......................................................................................................................... 4
List of Figures .................................................................................................................................... 7
List of Tables ..................................................................................................................................... 8
Table 1: List of Abbreviations and / or Acronyms. ............................................................................ 9
1. INTRODUCTION .................................................................................................................... 10
1.1. Objectives ...................................................................................................................... 10
1.1.1. Location ...................................................................................................................... 10
1.2. Methodology ................................................................................................................. 10
1.3. Terms of Reference for the Environmental Management Plan ............................... 11
1.4. Assumptions And Limitations ......................................................................................... 11
1.5. Project Team .................................................................................................................. 12
2. Project Description .............................................................................................................. 12
2.1. Overview Of The Proposed Technology .......................................................................... 12
2.2. Project activities ............................................................................................................. 14
2.2.1. Design and operation ................................................................................................ 14
3. LEGAL REQUIREMENTS..................................................................................................... 16
3.1. Relevant Treaties, International agreements and Protocols, policies and legislation. ...... 16
3.1.2. Namibia’s Environmental Assessment Policy of 1994. ........................................... 16
3.1.4. Water Resources Management Act (1956) .............................................................. 18
3.1.5. Hazardous Substances Ordinance 14 of 1974 ........................................................ 18
3.1.6. Petroleum Act (Act 2 of 1991) ................................................................................... 18
3.1.7. Pollution Control and Waste Management Bill ........................................................ 18
3.1.8. Atmospheric Pollution Prevention Ordinance 11 of 1976 ....................................... 19
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
5
PREPARED BY
OUTRUN CONSULTANTS CC
3.1.9. Labour Act (1992) ....................................................................................................... 19
3.2. Standards and guidelines for the design and construction of the Fuel station................. 20
3.3. Fuel Storage Facilities ..................................................................................................... 21
3.4. Forecourt Areas and Spillage Drainage ........................................................................... 21
3.5. Tank Gauging Systems .................................................................................................... 22
3.6. Construction .................................................................................................................. 23
3.7. Identification Of Alternatives.......................................................................................... 23
3.7.1. Strategic alternatives ................................................................................................. 23
3.7.2. Alternative Sites ......................................................................................................... 23
3.7.3. No-Go Option ............................................................................................................. 23
4. Identified Aspects And Potential Environmental Impacts ............................................ 24
4.1. Dust ............................................................................................................................... 24
4.3. Noise .............................................................................................................................. 25
4.4. Solid Waste .................................................................................................................... 25
4.5. Oil/Fuel Spills ................................................................................................................. 25
4.6. Employment opportunities ............................................................................................. 25
4.7. Positive economic benefits ............................................................................................. 26
4.8. Social issues ................................................................................................................... 26
4.9. Process issues ................................................................................................................ 26
5. Environmental Management Plan ..................................................................................... 27
5.1. EMP Overview ................................................................................................................ 27
5.2. Guiding Notes Supporting the EMP ................................................................................ 41
5.2.1. Tanks ........................................................................................................................... 41
5.2.2. General safety of public and employees .................................................................. 41
5.2.3. Managing fuel and oil spills ....................................................................................... 41
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
6
PREPARED BY
OUTRUN CONSULTANTS CC
5.2.4. Monitoring wells .......................................................................................................... 41
6. Conclusions And Recommendations ......................................................................................... 42
6.1. Conclusion ..................................................................................................................... 42
6.2. Recommendations ......................................................................................................... 42
6.3. Way Forward.................................................................................................................. 43
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
7
PREPARED BY
OUTRUN CONSULTANTS CC
List of Figures
Figure 1: The location of the proposed site for the new service station in Ocean View Extension 29 -
Swakopmund. ................................................................................................................................. 10
Figure 2: Fuel spills are common during refilling of USTs and refuelling of vehicles. SOURCE: Own
photograph. .................................................................................................................................... 14
Figure 3: An automatic continuous leak detection apparatus for a fuel retail system. Source:
www.petrolplaza.com ..................................................................................................................... 22
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
8
PREPARED BY
OUTRUN CONSULTANTS CC
List of Tables Table 1: List of Abbreviations and / or Acronyms. .............................................................................. 9
Table 2: Environmental Impact Assessment Experts and their Area of Responsibilities ....... 12
Table 3: Summary of legal compliance requirement and the respective regulatory authority.
........................................................................................................................................................ 20
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
9
PREPARED BY
OUTRUN CONSULTANTS CC
Table 1: List of Abbreviations and / or Acronyms.
ACRONYM FULL DESCRIPTION
DEA Directorate of Environmental Affairs
ECC Environmental Clearance Certificate
EMP Environmental Management Plan
GPR Glass fibre Plastic Reinforcement
MET Ministry of Environment & Tourism
MME Ministry of Mines and Energy
SABS South African Bureau of Standards
SANS South Africa National Standards
USTs Underground Storage Tanks
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
10
PREPARED BY
OUTRUN CONSULTANTS CC
1. INTRODUCTION
The applicant, Swakopmund Service Station CC is a Namibian company wholly owned by
Namibians. There is significant traffic flow along the Swakopmund – Henties Bay road and
has been increasing yearly. This has motivated the Proponent to establish a service station
in Ocean View Extension 29 in Swakopmund. The construction of a service station is a
listed activity under the Environmental Management Act, 2007, and requires authorization by
MET before implementation.
1.1. Objectives
• to describe the project in detail for everyone’s understanding
• to describe the project environment and the interrelationships among the various
components
• To identify potential positive and negative impacts of the project.
• To assess the significance of the positive and negative impacts of the project.
• To develop mitigation measures for the identified negative impacts of the project.
• To review the relevant policies and legislation governing the project.
• To develop an environmental monitoring and management plan for the project.
1.1.1. Location
1.2. Methodology Figure 1: The location of the proposed site for the new service station in Ocean View
Extension 29 - Swakopmund.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
11
PREPARED BY
OUTRUN CONSULTANTS CC
The Consultancy Team carried out a detailed study on the possible environmental impacts of
the proposed project. This was achieved by delineating the activities involved during project
implementation and predicting the impacts. The following project activities or elements were
considered:
• Design of the proposed service station;
• Construction of the new service station and;
• Operation of the service station.
Site investigations were done in order to predict the potential environmental impacts
emanating from the activities above. Such investigations included assessing soil texture in
order to infer porosity and permeability of organic fuels / compounds.
1.3. Terms of Reference for the Environmental Management Plan
Swakopmund Service Station CC appointed Outrun Consultants cc to conduct and EIA for
the establishment of service station in Swakopmund. Outrun conducted an environmental
scoping exercise and lodged an application for an Environmental Clearance Certificate
(ECC) with the Ministry of Environment and Tourism (MET). The application was verified and
MET requested for an EMP and a Scoping report. As a requested we compiled this EMP and
should be read together with the accompanying scoping report. The whole exercise took due
consideration of:
• Detailed project description;
• Identification of the possible and known impacts of the project;
• Review of relevant policies and legislation and the development of a legislative
framework compliance plan;
• Development of an Environmental Management Plan (EMP) with workable mitigation
measures for adoption.
1.4. Assumptions And Limitations
No alternative sites were proposed for this study. The unavailability of the specifications of
the equipment to be installed and design of the Fuel station has also placed limitations on
the data available to the consultants for prediction of actual impacts. However, this has
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
12
PREPARED BY
OUTRUN CONSULTANTS CC
created the opportunity to influence the technical design and as a result incorporate
mitigation measures early in the project design stage.
1.5. Project Team
Table 2: Environmental Impact Assessment Experts and their Area of Responsibilities
ORGANIZATION AREA OF RESPONSIBILITY / FIELD OF
EXPERTISE
TEAM MEMBERS
OUTRUN Project management Josiah T. Mukutiri
Enercon (Pty) Ltd Scope of the project Michael Ludeke
OUTRUN Legislation & Policy Review Selma
OUTRUN Development of Environmental Management
Plan (EMP)
Josiah T. Mukutiri
N.B. CVs OF THE EIA PRACTIONER IS ANNEXED
2. Project Description
This section describes the proposed technology and an outline of the proposed activities.
2.1. Overview Of The Proposed Technology
The Proponent proposes to establish a new service station at Ocean View Extension in
Swakopmund. The proposed development will involve the following:
The installation of two (2) 30 000ℓ and two (2) 30 000ℓ underground storage tanks (USTs) (1
x leaded petrol, 1 x unleaded petrol and 2 x diesel); and, four dispensing islands and
associated piping.
Centrifugal or submersible pump units will be used to pump the product through a metering
device into a vehicle fuel tank or to a portable metal container. Remote fuel filling points will
be installed as close to the USTs as possible, although the location of the filler points is
dependent on delivery tanker access. The fuel station will, at a minimum, include the
following:
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
13
PREPARED BY
OUTRUN CONSULTANTS CC
• Monitoring wells and a leak detection system installed around the tanks;
• Installation of petroplas piping for suctions, vents and remote fillers;
• Reconstruction of a concrete forecourt, at least on disturbed areas only;
• Installation of an oil/water separator connected to the surface drainage from the
concrete forecourt and filler containment areas, discharging into the waste water
system;
• Renovation of a suspended forecourt roof above the dispensers to protect customers
and pumping facilities from environmental elements;
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
14
PREPARED BY
OUTRUN CONSULTANTS CC
2.2. Project activities
The realisation of this project will involve a sequential execution of various activities as
follows:
2.2.1. Design and operation
The Proponent has appointed reputable Engineering Consultants to design the new fuel
station and manage the construction. The design and operation will follow the international
standards and guidelines regulating the petroleum industry. The guidelines require
compliance with local legislation but reference will be made to South African National
Standards (SANS) and international standards in instances where we do not have our own
here in Namibia. These standards ensure that environmental compliance is implemented
and maintained and that the potential impacts to the biophysical environment are greatly
reduced.
Figure 2: Fuel spills are common during refilling of USTs and refuelling of vehicles. SOURCE:
Own photograph.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
15
PREPARED BY
OUTRUN CONSULTANTS CC
Some of the key guidelines to be followed during design and construction:
• The storage tanks should be located towards the lower levels of the site as this
allows a natural gradient from the pipelines up to the dispensers, thereby allowing
product in the pipes to drain back into the USTs when it is not actively being pumped;
• Under all circumstances, the tank must be deep enough (i.e. to a minimum depth of
1250mm below finished ground level) to ensure that the suction/delivery line, the filler
and vent lines have a minimum fall of 1:100 back to the tank.
• Where two or more tanks are placed in a common excavation, a minimum spacing of
500mm between tanks must be allowed;
• The tank pit must be located at least 3m clear of any building.
• The minimum safety distance of the closest tank from the stand boundary is
generally 3.5m or the building line restriction, whichever is the greater.
The USTs will be composite tanks constructed of galvanized steel with a GPR coating.
There are various laws, policies, standards and guidelines governing the petroleum industry
and are presented in the following chapter.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
16
PREPARED BY
OUTRUN CONSULTANTS CC
3. LEGAL REQUIREMENTS
This section presents the treaties, policies and legislations that were reviewed in line with
this project. The various compliance requirements are also presented.
3.1. Relevant Treaties, International agreements and Protocols, policies and
legislation.
3.1.1. Namibian Constitution
First Amendment Act 34 of 1998
Article 16(1) guarantees all persons the right to
property. It therefore provides everyone a right to
acquire, own and dispose of property, alone or in
association with others and to bequeath such property.
“The State shall actively promote and maintain the
welfare of the people by adopting policies that are
aimed at maintaining ecosystems, essential ecological
processes and the biological diversity of Namibia. It
further promotes the sustainable utilisation of living
natural resources basis for the benefit of all Namibians,
both present and future.” (Article 95(I)).
3.1.2. Namibia’s Environmental
Assessment Policy of 1994.
The policy contains a list of prescribed projects that
may have significant negative impacts on the
environment. Such projects require authorisation from
the Ministry of Environment & Tourism (MET) -
Directorate of Environmental Assessment (DEA).
Construction of fuel station and bulk fuel storage
facilities are listed activities that warrants an EIA.
Accordingly, the project requires authorisation from
MET: DEA, which will be based on the findings of the
detailed EIA study.
3.1.3. Environmental
Management Act (2007)
The Namibian Environmental Management Act of
(2007) guided the EIA study and made reference to the
principles contained in the Act. This is the very Act that
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
17
PREPARED BY
OUTRUN CONSULTANTS CC
binds all the responsible parties against their
respective environmental obligations against which the
EIA clearance is issued. Failure to comply attracts
fines and / or prosecution depending on the severity of
the matter. The Proponent should meet environmental
conditions upon which the Environmental Clearance
Certificate will be issued.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
18
PREPARED BY
OUTRUN CONSULTANTS CC
3.1.4. Water Resources
Management Act (1956)
Water Act 54 of 1956 and the Water Resources
Management Act 24 of 2004, provides the general
protection against surface and ground water pollution.
It prohibits the pollution of ground and surface water
bodies including liability of clean-up costs after closure
/ abandonment of an activity. Water will be required for
the various uses at the service station including
domestic use. The Proponent should apply to the
Swakopmund municipality for water connection.
Details on prevention of ground water contamination
and leaks detection are presented under section 3.2.1.
3.1.5. Hazardous Substances
Ordinance 14 of 1974
The hazardous substances ordinance 14 of 1974
controls substances with potential to cause injury or ill-
health or death of human beings because of their toxic,
corrosive, irritant, strongly sensitizing or flammable
nature. Petroleum fuels are covered under this Act.
Care should be taken throughout the product lifecycle
right from receiving, storage, product use and disposal.
In cases were special storage facilities are required the
Proponent should provide as such as indicated under
section 3.2.1.
3.1.6. Petroleum Act (Act 2 of
1991)
This Act gives control over the storage of refined
petroleum products, and to provide for matters
incidental thereto. Handling and discharge of oil
products is also regulated under this Act. The
Proponent should apply for a retail license at the
Ministry of Mines & Energy (MME).
3.1.7. Pollution Control and
Waste Management Bill
This bill aims to prevent and regulate the discharge of
pollutants to air, water, and land. It further aims to
promote the establishment of a system of waste
management, and enable Namibia to meet its
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
19
PREPARED BY
OUTRUN CONSULTANTS CC
international obligations. Waste management should
be guided by the 3R principle, Reduce, Reuse and
Recycle. Only unrecyclable and unusable materials will
be disposed of at a designated disposal site.
3.1.8. Atmospheric Pollution
Prevention Ordinance 11 of 1976
This regulation sets the principles for the prevention of
atmospheric pollution and associated matters arising
thereto. Part IV and Part V prevents atmospheric
pollution by dust and vehicles gaseous emissions
respectively.
3.1.9. Labour Act (1992)
The Labor Act governs the employer to employee
relationship including issues pertaining to occupational
health and safety, remuneration, provision of
appropriate protective clothing, grant of leave etc. It is
important to refer to the Act and ensure compliance
with fair labor practices at all project phases.
3.1.10. Road Ordinance 1972
(Ordinance 17 0f 1972)
Width of proclaimed roads and road reserve
boundaries (S3.1) and control of traffic during
construction activities on trunk and main roads (S27.1).
Infringements and obstructions on and interference
with proclaimed roads. (S37.1). Distance from
proclaimed roads at which fences are erected (S38)
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
20
PREPARED BY
OUTRUN CONSULTANTS CC
Table 3: Summary of legal compliance requirement and the respective regulatory
authority.
Act/Regulation Compliance Regulatory Authority
Environmental
Management Act (2007)
Obtain EIA Clearance Certificate Ministry of Environment &
Tourism
Environmental
Management Act
Chapter 20:27
Produce biannual reports; adhere
to the EMP outline in this report
and renewal of EIA certificate after
3 year from the date of issue.
Ministry of Environment &
Tourism
Labour Act (1992) It is important to refer to the Act
and ensure compliance with fair
labour practices and occupational
health and safety.
Ministry of Labour
Water Resources
Management Act (2004)
Monitor groundwater quality and
comply with quality standards.
Prevent both surface and
groundwater contamination.
Ministry of Agriculture, Water &
Forestry
Apply for retail license to buy and
resell fuels / petroleum products.
Ministry of Mines and Energy
Apply for fitness certificate Swakopmund Municipality
3.2. Standards and guidelines for the design and construction of the Fuel station
Namibia Standards Institute is in the process of developing local standards hence the need
to refer to South African Standards (SANS) codes which include:
o SANS 10089-3: The installation of the underground storage tanks,
pumps/dispensers and pipework at filling stations and consumer installations;
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
21
PREPARED BY
OUTRUN CONSULTANTS CC
o SANS 1020: The electrical components of free-standing power dispensing
devices for flammable liquids;
• SABS Code of Practice for the Wiring of Premises SABS 0142 and can only be done
by a contractor registered by NAMPOWER;
• SABS 0228 Classification of dangerous goods in Namibia.
• SANS 10108: The classification of hazardous locations and the selection of
apparatus for use in such locations;
• SANS 10131-2: Storage and handling of liquid fuel Part 2: Large consumer
installation;
• SANS 10089 Parts 2 & 3 which requires:
o The installation of a leak detection system including observation and
monitoring well situated around the tank to facilitate early leak detection;
o The provision of a plastic sheet below the tank that slopes towards an
observation well; and
o Installation of leak detectors on the pressure systems.
• SANS 10098-2: The lighting of certain specific areas of streets and highways.
3.3. Fuel Storage Facilities
The tank farm refers to an area where the fuel storage tanks are installed. The USTs are
manufactured from mild steel and are coated with glass fiber reinforced plastic on the
exterior making a composite tank. The manufacture of composite tanks is governed by
SANS 1535. A self- contained manhole, which is impervious to hydrocarbons, is fitted to the
tank and is sealed to prevent contamination to the surrounding environment. Monitoring
wells are fitted to each end of the tank to allow for ground water sampling.
3.4. Forecourt Areas and Spillage Drainage
All surface areas on the forecourt filling area, as well as the tanker re-fueling area, will be
constructed from concrete to form an impervious surface. This will prevent the contamination
of any soil and/or water resources within the immediate area. The surfaces will be further
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
22
PREPARED BY
OUTRUN CONSULTANTS CC
sloped to allow any fuel spillage and surface washing water to drain or flow freely into a
spillage containment system situated onsite. The spill material will then be able to be
removed thus preventing further contamination of surrounding soil and/or water resources.
3.5. Tank Gauging Systems
Tank gauging is a complete fuel management system (FMS) utilized by fuel retailers. The
purpose of the FMS is to provide leak detection and reconciliation Fuels for fuel retailers,
thus allowing for early leak detection and system monitoring of the tanks. The sophisticated
system very accurately monitors all sales and deliveries relevant to the fuel station, which
then in turn determines if any product / fuel losses occur. An alarm is incorporated into the
system for the purpose of environmental monitoring, which is not only beneficial to the
surrounding environmental elements, but helps the retailer in maintaining up-to date quantity
and quality reports.
Figure 3: An automatic continuous leak detection apparatus for a fuel retail system.
Source: www.petrolplaza.com
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
23
PREPARED BY
OUTRUN CONSULTANTS CC
3.6. Construction
The Consultancy Team appointed to do the designs will be responsible for the appointment
and supervision of the Contractor. This phase will involve the excavation works for the
foundation and establishment of the tank farm, construction of the pipe network, cabling and
wiring, installation of USTs and associated equipment. The Engineering Consultants should
ensure all the standards and guidelines presented herein are met before commissioning and
handover of the upgraded service station to the Proponent.
3.7. Identification Of Alternatives
This section covers a discussion of alternatives to the proposed establishment of a service
station. The “do nothing” alternative is also considered.
3.7.1. Strategic alternatives
The proposed service station has been seen as a great step towards improving fuel supply
services to the locals as well as tourists traveling between Swakopmund and Henties Bay.
3.7.2. Alternative Sites
The proposed site is the only land available to the Proponent, therefore alternative site
consideration does not apply.
3.7.3. No-Go Option
The “no-go” option means maintaining the status quo were no construction of a new service
station will be done. This is not favourable for the local economy given the lost employment
opportunities and for tourists travelling between Swakopmund and Henties Bay.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
24
PREPARED BY
OUTRUN CONSULTANTS CC
4. Identified Aspects And Potential Environmental Impacts
ENVIRONMENTAL ASPECT ENVIRONMENTAL IMPACTS
Air Pollutants
4.1. Dust
Fugitive dust generated during
the removal and construction of
the Fuel station comprising total
suspended particulates and
PM10.
Dust will irritate workers at the site and nearby
accommodation facilities.
May cause or contribute to respiratory illnesses.
Dust also negatively affects flora adversely and
impacts negatively on the outlook or aesthetic
value of the surrounding areas.
4.2. Access to the site
Some of the equipment
especially USTs are bulk
resulting in abnormal loads.
Trees may need to be cut down or pruned to
make way for mobile equipment to navigate easily
on-delivery and laying down of USTs.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
25
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL ASPECT ENVIRONMENTAL IMPACTS
4.3. Noise
Noise will be generated during
the construction of the Fuel
station from the moving
equipment.
Noise associated with
hammering during construction.
Irritating to site workers with the potential of
impairing hearing, nuisance to established
business in the vicinity.
Increased noise is of particular concern to nearby
houses.
4.4. Solid Waste
Solid waste comprised of the
following:
• rubble
• soil from excavation.
• packaging e.g. cement bags.
• wood and steel scraps
• food waste e.g. plastic bottles,
plastic bags, food leftovers.
Improperly managed solid waste can lead to the
harbouring of pests, rodents and vermin.
4.5. Oil/Fuel Spills
Fuel and or Oil spills can occur
at the fuel storage facilities.
Oil/fuel can enter the drainage system and either
contaminates the land surface and ground water.
4.6. Employment
opportunities
New jobs will be created.
No new jobs will be created except temporary
jobs during the construction activities.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
26
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL ASPECT ENVIRONMENTAL IMPACTS
4.7. Positive economic
benefits
Improved convenience for locals
and travellers between Henties
Bay and Swakopmund.
The project is likely to impact positively on the
local tourism.
4.8. Social issues
Health, safety and security
hazards posed by liquid fuel
storage.
Demonstration of social
responsibility
Increased number of visitors
fuelling at this particular service
station.
High risk due to petrol which is highly
inflammable.
The Proponent will compensate any individuals
and parties that may be affected negatively by the
establishment and operation of the fuel station.
Increased revenues for the Proponent.
4.9. Process issues
Lack of adequate knowledge on
the risks associated with the
project.
Educate the IAPs on the associated risks and
hazards and effect on other development plans
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
27
PREPARED BY
OUTRUN CONSULTANTS CC
5. Environmental Management Plan
5.1. EMP Overview
The environmental management plan (EMP) should be adhered to at all levels during design and planning, construction, operation stages of
the project. It is important to note that there are different people responsible for the work at different phases of the project. While the people
doing the work must follow the instructions laid in this EMP, it remains the responsibility of the Proponent to ensure that the EMP is made
available to the people doing the work, that they understand the contents and comply. The EMP is clearly laid out indicating the identified
impacts, the proposed mitigation measures, implementing agent, monitoring agent and the monitoring frequency. The Proponent is encouraged
to extract the different sections and incorporate them in the contracts issued to the Design Engineers and Architects, Contractors and
Employees etc. The project will be managed by the Project Manager. The Project Manager will report to the Commissioner in the
Directorate of Environmental Affairs, Ministry of Environment & Tourism.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
28
PREPARED BY
OUTRUN CONSULTANTS CC
Table 2: Environmental Management Plan
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
DESIGN AND PLANNING PHASE
Night ambience Low night
ambience and
poor signage
increases
accident risk.
-ve Poor lighting
and dull
colours on
signs.
Use bright colours.
Use bright coloured signs that are
visible in the night.
Design
Engineer /
Architects
Project
Manager
DEA At the
design stage
and
commissioni
ng phase.
Accessibility of
fuel station
Poor
accessibility
increases
accident risk
and traffic
flow along the
highway
-ve Poor design,
poor signage
and limited
space
Make use of good signage and
provide enough space or provide an
extra lane for vehicles turning off
from highway to reach the fuel
station
Design
Engineer
Project
Manager
DEA At the
design stage
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
29
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Low water use
efficiency
Depletion of
water
resources
-ve Taps in the
rest rooms
Specify low-flow taps in the rest
rooms.
Design
Engineer and
Architects
Project
Manager /
Proponent
DEA At the
design stage
and
commissioni
ng phase.
Waste Water Water
pollution
-ve Forecourt
wash water
should be
directed to a
collecting
tank that
passes
through an
oil separator.
Design should ensure that grey water
is oil free before discharge into the
waste water network.
Design
Engineer and
Architects
Project
Manager /
Proponent
DEA At design
and
construction
phase of the
project.
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Solid Waste
Solid waste
Harbours
pests, rodents
-ve Generated
from
packaging
Provide adequate waste collection
bins.
Bins should also be strong enough to
Design
Engineer /
Architect /
Project
Manager /
Proponent
DEA Quarterly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
30
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
comprised of
the following:
• soil
• packaging
materials
e.g. cement
bags.
• wood and
steel scraps
• food waste
e.g. leftover
food, plastic
bottles etc.
and vermin.
Affects the
outlook and
aesthetic
value of the
resort.
Causes
sedimentation
and blockage
of drains
during rainy
season.
material
used by
Contractors,
travellers,
customers
etc.
Soil from
excavations.
Solid
materials
from
packaging
materials
keep scavengers away.
Bins should be easily accessible.
Bins should be emptied at least once
every week.
Waste should be disposed of at the
designated waste disposal site.
Project
Manager
Low electricity
use efficiency
Increased
demand on
the national
-ve Fuel pumps
and lights.
Design a system were solar can be
used to power most of the
equipment.
Design
Engineer /
Architects
Project
Manager /
Proponent
DEA,
Ministry of
Mines and
Design stage
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
31
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
grid. Energy
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
32
PREPARED BY
OUTRUN CONSULTANTS CC
CONSTRUCTION PHASE
Traffic flow Disruption of
traffic follow
-ve Interaction
with heavy
construction
vehicles
Municipality traffic management unit
must be informed at least 1 week in
advance if traffic flow will be affected
by the construction works.
Movement of heavy construction
equipment should avoid peak hours
and should be directed by
appropriate warning signs.
Construction
Manager
Project
Manager
Local Traffic
Control Unit
Once off at
the
construction
stage.
On-site
accidents
Injuries and /
or loss of life.
Damage to
property
-ve Un-informed
pedestrians,
passer byes
and drivers.
Persons and vehicle access during
construction should be restricted so
as to prevent potential accidents.
Appropriate danger warning road
signs should be used to control traffic
along the highway. Trained
construction personnel should be
used to direct traffic movements
during construction.
Construction
Manager
Project
Manager
Local traffic
control unit
Weekly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
33
PREPARED BY
OUTRUN CONSULTANTS CC
Dust
Fugitive dust
comprising total
suspended
particulates and
PM10.
Dust irritates
workers at the
site and
nearby
residents.
Causes and /
or contributes
to respiratory
illnesses.
Negatively
affects flora.
Reduces
aesthetic
value of the
surrounding
areas.
-ve Excavation
works,
Construction
vehicle
movements
and mixing
of building
materials.
On-site mixing and unloading
operations, and ensuring adequate
maintenance and repair of
construction machinery.
Wetting of ground surfaces and
providing dust masks to employees.
Environmental
Health
Manager
/Construction
Manager
Project
Manager
DEA
Ministry of
Health &
Social
Services
Monthly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
34
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Noise
Irritates site
workers with
the potential
of impairing
hearing,
nuisance to
nearby
residents in
the vicinity.
-ve Movement
of
equipment
Noise
associated
with
hammering
during
demolition
and
construction
works.
Limit the noise to the site and make
use properly maintained equipment.
Limit site construction activities to
working hours (7:00 am to 4:00 pm)
and noisy activities to morning hours
(8:00 am to 12:00 pm).
Construction
Manager
Project
Manager
DEA Monthly
Health and
safety hazards
Occupational
diseases and
accidents
-ve Machinery
and moving
equipment;
dusts;
contact with
organic
Workers should be provided with
appropriate and adequate personal
protective equipment and be trained
on the use and safety and health
issues they are exposed to. Warning
signs to be posted to indicate
Environmental
Health
Manager
/Construction
Manager
Project
Manager
Ministry of
Labour
Monthly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
35
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
chemicals dangerous areas and risks associated.
Employment
creation
Direct and / or
indirect socio-
economic
benefits.
+ve Employment
during
construction
and
operation
Although there are no significant
numbers of jobs to be created, give
first preference to the locals.
Human
Resources
Officer
Project
Manager
Employment
Council
Monthly
Carbon foot
Increased
carbon foot
print and
increased
climate
change
-ve Construction
of the Fuel
station
Although this particular project may
not singly have a significant impact
the sum total of such projects may
have a huge impact on climate
change. Construction materials to be
sourced preferably from green
companies. Use shortest routes
when disposing of waste materials
that cannot be reused or recycled.
Construction
Manager /
Procurement
Manager
Project
Manager
DEA /
Climate
Change
consultants
Monthly
Soil and water
quality
Soil and water
contamination
/ pollution.
-ve Accidental
spillages of
fuel and oils
as well as
Strict operation procedure to be
followed as provided for by the
construction and site waste
management plans. Storm drains
Construction
Manager
Project
Manager /
Proponent
DEA Monthly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
36
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
paints and
other
construction
liquids.
with oil/water separators to be
constructed prior to the beginning of
major construction activities. Fuel
storage area should be bund walled
and concrete surfaced.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
37
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
OPERATIONAL PHASE
Water quality
Ground and
surface water
contamination
: Both
chemical and
physical
contamination
-ve
Fuel / oil
spillages.
The area will be concretised to avoid
contamination of groundwater and
machinery well–maintained. Storm
water drains leading to oil/water
separator will be constructed and
maintained.
Design
Manager /
Architects /
Fuel Station
Manager.
Project
Manager /
Proponent.
DEA /
NAMWATER
/
Swakopmun
d
Municipality
Monthly
sampling of
the
monitoring
wells.
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBL
E AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Domestic Solid
waste
Hazardous to
health and
reduces the
aesthetic
value of the
area.
-ve Generated
from food
left overs,
packaging
materials
etc.
Provide adequate waste receptacles
or bins should be easily accessible.
Waste collection should be done at
least once per week by the
Municipality of Swakopmund.
Fuel Station
Manager
Project
Manager /
Proponent
DEA Quarterly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
38
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Liquid waste Hazardous to
health and
reduces the
aesthetic
value of the
area.
-ve Waste
generated
from toilets,
sinks etc
Use the flush to sewer system
provided by the Municipality
Fuel Station
Manager
Project
Manager /
Proponent
DEA /
Municipality
of
Swakopmun
d
Quarterly
Accidents
During
offloading
Disruption of
traffic flow.
-ve Bulk Fuel
Tankers
Tankers should drive straight in and
out without reversing.
Fuel station
Manager
Proponent
/Project
Manager
Building
Inspectors /
Engen
Engineers /
Ministry of
Mines &
Energy
At design
and
Construction
stages
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
39
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Occupational
Hazards / Work
place accidents
Potential
accidents and
illnesses.
-ve Operating of
the Fuel
station
resulting in
contact with
organic fuels
and oils etc.
Health and safety regulations should
be enforced on all the workers.
Safety regulations include life and
health insurance, first aid kits;
protective clothing such as uniforms
and gloves.
Proper storage of highly flammable
products on sale such as gas, petrol,
diesel etc. and installation of fire
extinguishers. No smoking, No cell
phone use /naked flame signs should
be posted visibly and enforced.
Workers should not be allowed to
exceed working hours.
Fuel Station
Manager
Environme
ntal Health
Manager
Labour
Inspectors
Quarterly
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN
SWAKOPMUND – ERONGO REGION, NAMIBIA
40
PREPARED BY
OUTRUN CONSULTANTS CC
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
MONITORING
FREQUENCY
Public hazards Negligent
management
impacts
dissatisfied
customers,
accidents etc.
-ve Daily running
of Fuel
station not
properly
managed.
The Fuel station Manager should
manage the daily operations and
ensure good customer care.
Fuel station
Manager.
Project
Manager /
Proponent.
DEA Monthly
ENVIRONMENTAL
ASPECT
IMPACT POSITIVE
\NEGATIVE
SOURCE MITIGATION IMPLEMENTING
AGENT
RESPONSIBLE
AGENT
MONITORING
AGENT
DECOMMISSIONING PHASE
Soil and Water
quality
Soil and water
contamination
or pollution
-ve Spillages
during
decommissio
ning and
subsequent
dismantling
of tanks and
pipe-works.
All fuels should be drained before
dismantling of tanks and pipes.
Rubble from concrete works should
be disposed of at designated sites.
Reusable or recyclable materials
should be separated and treated as
such.
Construction
Manager
Project
Manager /
Proponent
DEA
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
41
PREPARED BY
OUTRUN CONSULTANTS CC
5.2. Guiding Notes Supporting the EMP
5.2.1. Tanks
Installation of USTs and pipe work shall be undertaken in compliance with AS/NZ 1418.3-
1997 Cranes, hoists and winches and AS/NZ 2550.1
5.2.2. General safety of public and employees
The proposed works should be carried out during the tourism off season when Swakopmund
is less congested. In addition, the work area should be cordoned off as a no-go area.
5.2.3. Managing fuel and oil spills
The soil texture analysis shows a predominantly sandy soil with high porosity. It is highly
recommended to use leak proof concrete lining on all surfaces including the base supporting
the USTs.
5.2.4. Monitoring wells
Each fuel station should be fitted with monitoring wells as we have seen the ground water is
the main source of portable water. Protection of ground water from contamination or possible
pollution is key for the sustainable management of the ground water resources as a whole.
In that respect permits for drilling monitoring wells should be obtained from Ministry of
Agriculture, Water & Forestry.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
42
PREPARED BY
OUTRUN CONSULTANTS CC
6. Conclusions And Recommendations
6.1. Conclusion
This report was compiled from information obtained from relevant authorities,
stakeholders, I&APs and technical experts and professionals. It has presented the
context, benefits of the project and the process followed in the development of this
EMP. The Fuel station will be a retail facility selling highly inflammable fuels with high
risk for fires and explosions. The proponent is advised to adhere to SANS and SABS
standards for design, manufacture and construction of USTs. It is also recommended
that a fuel management system be installed for continuous leak detection. The
signage and lighting should be flashy and bright enough in order to reduce accident
risk since its located adjacent to the highway. The setup should not disrupt traffic
flow along the highway. The potential impacts are not very significant and in line with
the Environmental Management Act, neither specialist studies nor full scale EIA were
carried out. However, the EMP developed clearly indicates how each of the identified
environmental impacts can be mitigated or eliminated, the implementing agent,
responsible agent, the monitoring agent and the monitoring frequency throughout the
project.
6.2. Recommendations
The following recommendations are made as they relate to the EMP formulated
during the study:
The Proponent should adhere to the laws, policies, standards and regulations as
presented earlier in the report. Where permits are required, licence to operate a Fuel
station, permit to drill a ground water monitoring borehole etc. must be obtained from
the relevant authorities.
The overall EMP should be implemented so as to avoid predicted environmental
impacts as presented in the report.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
43
PREPARED BY
OUTRUN CONSULTANTS CC
6.3. Way Forward
The EMP will be submitted to the Competent Authority – Ministry of Mines & Energy
and the MET: DEA for issuing of the clearance certificate. The decision made by
MET: DEA will be made known to the Proponent.
END
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
44
PREPARED BY
OUTRUN CONSULTANTS CC
ANNEXURE 1
CONSULTANT’S PARTICULARS
CURRICULUM VITAE Mukutiri, Josiah Tonderai
Name of Firm
: Outrun Consultants CC (Formerly
Outrun Investments CC)
Full Name (s) : Josiah Tonderai Mukutiri
Position : Director
Date of Birth : 28 March 1976
Years with Firm/Entity : 12Years
Nationality : Zimbabwean
Permanent residence : Zimbabwe
Position in Company : Director
Detailed Tasks
assigned
: Compilation of Project Proposals,
BIDs, Carrying out Environmental
Impact Studies and compiling
Environmental Management Plans,
Managing Client Relationship, and
Carrying out feasibility studies, Project
Appraisal, Project Management and
Monitoring & Evaluation. Training and
facilitation, Project Management and
Coordination, Resource Mobilization
and Information Dissemination.
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
45
PREPARED BY
OUTRUN CONSULTANTS CC
Education:
Years Institution Degree/Diploma
1 Year
3 Years
2 Years
City & Guilds of London Institute
University of Zimbabwe
Aldersgate College
Certificate in Quality
Assurance & Materials
Processing Solids
BSC Honours in Applied
Environmental Science
Master in Business
Administration
Employment Record:
2006 to date Outrun Investments CC, Windhoek, Namibia.
Position: Director – Conducting Impact studies and feasibility studies, data
collection, data analysis report writing, training, impact identification and analysis,
developing management plans, business plans, feasibility studies, Agronomy,
Developing training materials, facilitation, training needs assessment and
managing client relationship, Project Management and Coordination, Information
Dissemination.
2003 – 2006 University of Zimbabwe, Harare, Zimbabwe
Position: Research and Teaching Assistant focusing environmental monitoring & management, impact studies and waste management & pollution control.
1997 – 1999 Broken Hill Proprietary (BHP) (Pty) Ltd, Selous, Zimbabwe
Position: Senior Process Controller responsible for production, quality control, safety, health and environmental management.
1995 - 1997 Zimbabwe Alloy Refinery Division (Pty) Ltd, Gweru, Zimbabwe
Position: Process Plant Controller responsible for production, quality control, safety, health and environmental management.
PREVIOUS ACCOMPLISHMENTS IN THE TARGET ENVIRONMENT
PROJECT TITLE: Training of 150 Rural Water Extension Officers for the MAWF – WASH
capacity building programme. Client: Ministry of Agriculture, Water & Forestry
Contact Person: CAVIN MWINGA Cell No.: +264 811 486 360
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
46
PREPARED BY
OUTRUN CONSULTANTS CC
PROJECT TITLE: Feasibility Study and Environmental Impact Assessment for the
Establishment of Omaenene Business Park. Client: OFFSHORE DEVELOPMENT COMPANY
(ODC). ODC is the infrastructure development arm for the Ministry of Trade and Industry
with a focus on Export Processing Zones (EPZ). CONTACT PERSON: PHILLIP NAMUNDJEBO
AND / OR REUBEN AMAAMBO
OTHER PROJECTS:
PROJECT TITLE: Feasibility Study and Business Plan, Environmental Impact Assessment and
Environmental Management Plan for the Establishment of a Dimension stone / Granite
Mine at Otjohorongo in Erongo Region - Namibia, (Four Mining Claims within an EPL).
Client: Ekungungu Trading CC
Contact Person: Lukas Sasamba Cell No.: +264 811 275 423
PROJECT TITLE: Environmental Impact Assessment and Management Plan for the
Installation of New Incinerators at Intermediate Hospital Katutura in Khomas Region.
Client: Ministry of Health & Social Services
Contact Person: Benjamin Ongeri Cell No.: +264 813 462 013
PROJECT TITLE: Environmental Impact Assessment and Environmental Management Plan for
the Establishment of a Lithium Mine and Processing Plant at Karibib in Erongo Region, (Eight
mining Claims within an EPL).
Client: LiCore Mining (Pty) Ltd
Contact Person: Gert Nell Cell No.: +264 812 945 895
LANGUAGE Speaking Reading Writing
English Very Good Very Good Very Good
Afrikaans Bad Not at all Not at all
German Not at all Not at all Not at all
ENVIRONMENTAL MANAGEMENT PLAN – THE PROPOSED DESIGN, CONSTRUCTION ANDOPERATION OF A NEW
SERVICE STATION AT OCEAN VIEW EXTIONSION 29 IN SWAKOPMUND – ERONGO REGION, NAMIBIA
47
PREPARED BY
OUTRUN CONSULTANTS CC
ANNEXURE 2
EIA AUTHORISATION LETTER FROM NWR