Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 42010-013 June 2016 PRC: Guangxi Southwestern Cities Development Project Environmental Monitoring Report Prepared by the Project Management Office of Guangxi Zhuang Autonomous Region for the Guangxi Zhuang Autonomous Region Government and the Asian Development Bank.

Upload: vuduong

Post on 19-Mar-2018

229 views

Category:

Documents


2 download

TRANSCRIPT

Environmental Monitoring Report

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily

represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference

to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make

any judgments as to the legal or other status of any territory or area.

Project Number: 42010-013 June 2016

PRC: Guangxi Southwestern Cities Development Project – Environmental Monitoring Report

Prepared by the Project Management Office of Guangxi Zhuang Autonomous Region for the

Guangxi Zhuang Autonomous Region Government and the Asian Development Bank.

Contents

I. INTRODUCTION 1

A. Report Purpose and Rationale 1 B. Project Composition and Implementation Progress 1

II. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION 8

A. Institutional responsibilities for environmental management 8 B. Incorporation of Environmental Requirements into Project Contractual Arrangements 9

III. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS 10

IV. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD 12

A. General 12 B. Observations Specific to Each Component during Site Inspection 17

1. Component F1 and F2: Urban Road Network and Related Municipal Infrastructure for Fangchenggang City, and coastal protection and upgrading 17 2. Component C1 and C2: urban road network and related municipal infrastructure for Chongzuo City, and Shuikou Lake environmental improvement 19 3. Component B1: Urban road network and related infrastructure for Baise City 20 4. Component B2: Longwang Bridge for Baise City 20

V. SUMMARY OF ENVIRONMENTAL MONITORING 21

A. Monitoring plan and responsibilities 21 B. Monitoring Results 24

1. Component F1: Urban Road Network and Related Municipal Infrastructure for Fangchenggang City 24 2. Component F2: Coast environmental protection& remediation of Fangchenggang City29 3. Component C1: Urban Road Network and Related Municipal Infrastructure for Chongzuo City 33 4. Component C2: Shuikou Lake Environmental Improvement for Chongzuo City 38 5. Component B1 and B2: Urban Road Network and Related Infrastructure for Baise City, and Longwang Bridge for Baise City Air quality 40

VI. PUBLIC CONSULTATION 42

VII. INSTITUTIONAL STRENGTHENING AND TRAINING 44

VIII. KEY ENVIRONMENTAL ISSUES 47

IX. CONCLUSION 48

1

I. INTRODUCTION

A. Report Purpose and Rationale

The Environmental Management Plan (EMP) has been established as anindispensable part of Environmental Impact Assessment Report, proposing appropriate mitigation measures and institutional arrangements for all phases of the Project to monitor and ensure (i) compliance with environmental regulations; and (ii) implementation of the proposed mitigation measures. To ensure continuous improvement of environmental performance during project preparation, construction and operation,the borrower/client is required to prepare semi-annual environment monitoring and progress reports that describe progress of EMP implementation, status of environmental compliance and implemented corrective actions.This is the No.6 semi-annual environmental monitoring report developed for the GSCDP.

B. Project Composition and Implementation Progress

The Guangxi Southwestern Cities Development Project is intended to improve livingconditions in the three border cities of Fangchenggang, Chongzuo, and Baise in the GZAR, andenhance their ability to promote and benefit from regional cooperation. The project is estimated to cost a total of approximately $293.41 million, of which $150million will be financed by a loan from ADB and the rest from city government budgets anddomestic commercial loans. The project will be implemented over 5 years, between 2011 and2015. The closing date of this project is delayed for 1 year till the end of 2016, because that Fangchenggang and Chongzuo were not able to close on time. The proposed projectcomprises six components in the three cities, whose description and implementation progress (by June 2016)are detailed in the table below.

Table 1: Description of Components and Implementation Progress by June 2016 Completion of project quantities– Fangchenggang

Contract No. Content Description Completion rate

FCCW-102 Branch road of

Yuzhouping and #2, #3 & #5 road

2016 1stQuater: (1). Subgrade work of # 2Road of K0+012~K0+600and K1+280~`K1+560 have been completed; Pavement work of K0+012~~K0+400 has been completed; Drainage work of K0+012~K0+600 has been completed. (2). All subgrade work, pavement work and drainage work of # 3- 1 Road have been completed; Subgrade work and drainage work of # 3- 2 Road has been completed. (3).Pavement work and drainage work of # V Road of K0+051~K0+280 has been completed; (4).Subgrade work of K0+200~~K0+700 、K1+240~~K1+636 and

68.57%

2

drainage work of K0+200~~K0+700 、K1+240~~K1+636 of Jianzheng Road has been completed. 2016 2ndQuarter: (1) #1 and #2 Road: Subgrade work, drainage work, concrete pavement work of K0+012~K0+600 have been completed; subgrade work of K1+280~`K1+560 has been completed; (2) #3 Road: All subgrade work, pavement work and drainage work of # 3- 1 and #3-2 Road have been completed; (3) #5 Road: Subgrade work and drainage work of K0+051~K0+280 have been completed; (4) Jianzheng Road: Subgrade work and drainage work of K0+200~~K0+700 、K1+240~~K1+636 have been completed, including cement stabilizing layer of K0+200~~K0+700.

FCCW-103 #1 road

2016 1stQuater: (1) Earthwork of K3+100~K3+980 has been completed; (2). Rainfall and sewage pipes of K3+000~K3+240 has been completed; (3). Rainfall and sewage pipes of K3+280~K3+320 has been completed;

2016 2ndQuarter:(1) Subgrade work, drainage work, concrete pavement work of K0+000~K2+940 have been completed; (2) Subgrade work and drainage work of K2+940~K3+400 have been completed; (3) Subgrade work of K4+760~K5+260 has been completed,

53.50%

FCCW-104 Anbujiang Bridge 2016 1stQuater: (1). 0#U type bridge abutment pouring engineering has been

25.72%

3

completed; (2). 6 poles civil work of 1# bridge pier has been completed

2016 2ndQuarter:(1) 24 pile foundation of #1 and #2 bridge pier have done concrete pouring; (2) #0 and #3 abutment have done foundation extension, U- type abutment body and capping concrete pouring; (3) #1 and #2 bridge pier have done excavation, and reinforcing steel bars are under construction.

FCCW-106 Procurement &

installation of streetlight

2016 1stQuarter:Conduits and base potting in the southern part of Shangtian Rd. has been completed

2016 2ndQuarter: (1)Conduits and base potting in the southern part of ShangtianRd.have been completed; (2) Conduits and base potting in #4 Road have been completed; (3) Conduits and base potting in K0+000~K2+940 of #1 Road have been completed.

82.56%

FCCW-107 Traffic Control &

Facilities

2016 1stQuarter: No construction work has been done

2016 2ndQuarter:900 meters marking line of #3-1 Road, 600 meters marking line of #2 Road, 2 kilometers marking line of #1 Road have been completed; Installation of #1, #2 and #3 Road signboards has been partially completed.

38.70%

FCCW-201 Construction of sea bank

2016 1stQuarter: Throwing stone and squeezing sludge of K7+140~K7+220 has been completed; 2. Slope protection and pavement engineering has been completed; 3. Rain pipes in South and North side of

22.24%

4

K8+135~K8+500; 4. Surface clearing, backfill of partial subgrade and cutoff wall engineering has been completed.

2016 2ndQuarter: Subgrade work, drainage work, concrete pavement work of K0+000~K0+680 、K1+540~K2+450 have been completed; Subgrade work and drainage work of K7+280~K8+480 have been completed.

FCCW-202 Mangrove Square

2016 1stQuarter: The couple pavilion, gallery frame, concrete frame of kiosk, the top part of pool pavement side face, 2-meter water permeable brick, arbor planting, tree pool, fountain pool surrounding and 9-meter road have been completed.

2016 2ndQuarter: (1) Paving of all the roads, construction of leisure pavilion, couple pavilion, gallery frame, and greening engineering have been completed; (2) Buried rain and sewage pipes, construction and decoration of water pool and tree pool, and marble tile pavement have been completed; (3) Pile foundation construction of education center has been completed; (4) Most of the concrete pavement has been completed.

81.87%

Completion of project quantities–Chongzuo

Contract No. Content Description Completion

rate

CZCW-101 Subgrade of

Chengnan 9th road and Liancheng road

2016 1stQuarter:Chengnan 9th Road and Liancheng Road Subgrade have been completed investment of 79.09 million, which

101%

5

is 98.31% of total investment. Among them, 98.31% of Chengnan 9th Road Subgrade work, 96.31% of drainage work, 86% of pedestrian crossing pavement work, 85.31% of street base and pipe pavement and 98.7% bridge engineering work have been completed. Remaining pavement works and crash barrier have not been completed. 98.41% of subgrade work of the southern part of LianchengRoad(including Nonggang Road) has been completed, 95.26% of drainage work has been completed, 93% of pedestrian crossing pavement work, 92.3% of street base and pipe pavement, 85% of bridge pavement work have been completed. Pile foundation has all been completed and 35 pieces of box girder preset and the installation of 2 crossing box girders. 2016 2ndQuarter:Chengnan 9th Road: Subgrade work, drainage work and water stable layer construction have been completed during reporting period. Liancheng Road: Prefabrication of 10 box girders and installation of 45 box girders of K1+362 have been completed; Subgrade work and water stable layer of K1+600-K1+720 and K2+040-K2+180 right side have been completed.

CZCW-102 Subgrade of Beiwei

2nd road and Zhongyi Road

2016 1stQuarter:Up to now 89.095 million has been completed in total, which is 59.86% of contract price. Among them, the subgrade work of Beiwei 2th Road has completed investment of 15.7143 million, which is 52.08% of contract price; Drainage work has completed investment of 39.9747 million, which is 57.37% of contract price. The base work of Chongyi Road has completed investment of 7.1292 million, which is 81.08% of contract price; Drainage work and culvert has completed investment of 17.7025 million, which is 83.73% of contract price. 2016 2ndQuarter:Beiwei2nd Road: Water stable layer of K0+520~K10+90 、K1+650~K2+100, and curb and apron pavement of K0+020~K0+600 have been completed. Zhongyi Road: Water stable layer of K0+400~K0+830 and drainage work of K0+860~K1+300 have been completed.

67%

CZCW-103 Subgrade of 100%completed. 100%

6

Shijinglin Road

CZCW-104 Road pavement

2016 1stQuarter:All asphalt works of Chengnan 9th Road of K0+620~K1+300 has been completed, All asphalt works of Liancheng Road South Section of K0+460~K1+140 and K2+240~K2+780, All asphalt works of Beiwei 2th Road K0+020~K0+580 have been completed. 2016 2ndQuarter:No additional work during the reporting period.

45%

CZCW-105

RoadsLandscaping

2016 1stQuarter:Up to now, 309 arbor and shrub planting have been completed, sheet plant arbor and shrub 1016.5 m2, changing planting soil 780 m2; Completing 820 trees planting in the southern part of Laincheng Road, sheet planting 2859m², and changing planting soil 1625 m2. 2016 2ndQuarter:Chengnan 9th Road: Medial divider and sidewalk greening belt of K0+600-K1+320 have been completed during reporting period. Liangcheng Road southern section: Medial divider and sidewalk greening belt of K0+500-K1+140 and K1+680-K1+100 have been completed during reporting period. Medial divider and left sidewalk greening belt of K1+220-K1+780 have been completed.

24%

CZCW-106

Procurement of Street Light and

Installation

2016 1stQuarter: No work has been done. 2016 2ndQuarter:Procurement has been substantially completed. Chengnan 9th Road: Street lamp installation has been completed. Liancheng Road southern section: Street lamp installation of K0+500-K1+100 and left side of K2+340-K2+780 have been completed.

39%

CZCW-107

Traffic Control Facilities

2016 1stQuarter: No work has been done. 2016 2ndQuarter:Procurement has been substantially completed. The implementation agency has completed the foundation of signboards of Chengnan 9th Road and Liancheng Road southern section.

25%

CZCW-201 Shuikou Lake Rehabilitation

Works

2016 1stQuarter:92.84%ofworksis completed. 100% netcagesclearing work has been completed, 96% completed for cofferdam removal (the rest cannot be removed),100%completed for sewage treatment of constructed wetlands,

93%

7

100%ofmonitoringstationconstructed,and98% completed for revetment works,100% completed for monitoring station,49% of subgrades forroadsalongthelakeare finished. Because the work amount of garden show park overlapping region is no longer included in ADB loan project, related work amount need to be calculated to reduce. 2016 2ndQuarter:No further work has been done.

Note: Completion Percentage of Chengnan 9th Road and Liancheng Road is over 100% due to the contract

variation which lead to the increase of construction work amount. The contract amount has not been updated as the variation has not been approved.

Completion of project quantities– Baise

Contract No. Content Description Completion rate BSCW-101 Chengnan ring road (i) municipal road

(3.69km); (ii) related basic constructions including drainage pipe, lighting engineering, traffic control and Landscape greening; (iii)bridge construction (563m); (iv) related basic constructions including drainage pipe, lighting engineering, traffic control and Landscape greening.

100%

BSCW-102 Longwang Bridge 100%

8

II. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION

A. Institutional responsibilities for environmental management

To actively respond the requirements in Project Agreement, institutionally a vertical framework with 3 levels had been set up for the project environmentalmanagement, which is in full consistence with the description in the SEIA developed during project preparation in February 2010:

Level 1: GPMO, which isestablished under the executingagency, Guangxi Zhuang Autonomous Region government (GZARG), is locatedin the GZAR Development and Reform Commission (GDRC), and is headed by thedirector general of GDRC. GPMO draws its members from GDRC, GZAR Finance Department,GEPD, and GZAR Land Resources Bureau. The GPMO has set up an Environment Management Unit (EMU) since the beginning of the project, with 1 dedicated staff in order totake its overall responsibility for supervising EMP implementation and reporting toADB.

Level 2: PICs (POCs for operation phase), which havenominated 1~2 employees each in charge of EMP implementation, reporting to GPMO periodically.

Level 3: Contractors/Supervisors, which have nominated 1~2 full-time staff in charge of daily environment management, reporting to PICs periodically during construction.

Besides abovementioned three levels, GEPD and city EPBs also organize on-site inspection, supervise thefulfillment and effectiveness of environment protection measures, and provide comments and recommendations regularly or from time to time.

It is known that the independent environmental monitor (IEM) (as part ofthe loan implementation consultancy engaged through international competitive bidding) willsoon be mobilized to support the GZARG, GPMO, PICs and POCs in EMP implementation (carrying out training program and preparing semiannual EMP progress reports).

The following figure summarizes the institutional structure/relationship of various agencies involved in EMP implementation and their specific responsibilities.

9

Figure 1: Implemented Institutional Structure of EMP Implementation for GSCDP

B. Incorporation of Environmental Requirements into Project Contractual Arrangements

In compliance with the agreed Project Agreement, the environmental requirements have been incorporated into contractual arrangements of all the components throughout bidding and contracting process, including relevant mitigation and monitoring measures specified in the EIA, SEIA and EMP. The details are provided in the table below.

Table 2: Incorporation of Environmental Requirements into Contractual Arrangements by Each Component

No. Contractual Arrangements of Environmental Requirements

No. of Component (Y/N/NA)

F1 F2 C1 C2 B1 B2

1 Environmental provisions as citedin the EMP of the SEIA will beincluded in the Requests forProposals.

Y Y Y Y Y Y

2 An environmental section will beincluded in the TOR for bidders.

Y Y Y Y Y Y

3

Environmental clauses forcontractors in reference to theimplementation of the EMP andmonitoring plan will be included inthe construction and supplycontracts.

Y Y Y Y Y Y

Note: Y-Yes; N-No; NA-Not Applicable.

GPMO

GZARG/LG

GEPD/EPBs

ADB

IEM PICs (POCs)

Contractors

EMS

Supervision

Supervisor

Coordination Cooperation Consultation and feedback

10

III. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS

All the environment-related project covenants have been complied with or are being complied with, as summarized in the table below.

Table 3: Compliance with Environment-related Project Covenants

Environment-related Project Covenants No. of

Section Compliance Status

Loan Agreement Article IV: Particular Covenants The Borrower shall cause GZARG to carry out the Project with due diligence and in conformity with sound administrative, financial, engineering, environmental and urban development practices.

4.01(a) Being complied with.

Schedule 5: Execution of Project and Operation of Project Facilities GZARG, FMG, CMG and BMG shall, and shall cause the PICs to, ensure that all the project implantation procedures agreed upon with ADB be followed, including environmental and social safeguard requirements.

4 Being complied with.

Project Agreement

Article II: Particular Covenants

FMG, CMG and BMG shall cause the respective concerned PICs to at all times conduct their business in accordance with sound administrative, financial, environmental, urban roads and urban development practices, and under the supervision of competent and experienced management and personnel.

2.11 (b) Being complied with.

FMG, CMG and BMG shall cause the respective concerned PICs to, at all times operate and maintain their plants, equipment and other property, and from time to time, promptly as needed, make all necessary repairs and renewals thereof, all in accordance with sound administrative, financial, engineering, environmental, urban roads, urban development, and maintenance and operational practices.

2.11 (c)

The branch project of Baise is under implementation , other branch projects are under construction,not applicable.

Schedule: Execution of Project Project Implementation Company and Project Implementation Arrangement GZARG, FMG, CMG, and BMG shall, and shall cause the PICs to, ensure that all the project implementation procedures agreed upon with ADB be followed, including environmental and social safeguard requirements.

6 Being complied with.

Environment

GZARG, FMG, CMG and BMG shall, and shall cause PICs to, ensure that all the Project facilities under the Project be constructed, operated, maintained, and monitored in strict conformity with:

(a) all applicable environmental laws and regulations, policies, procedures and guidelines of the Borrower, including national and local regulations and standards for environmental protection, health, labor, and occupation safety;

20(a) Being complied with.

(b) ADB Environmental Policy and related operational procedures; 20(b) Being complied with. (c) the environmental mitigation and monitoring measures detailed in the

approved EIA, SEIA and the related EMP. 20(c) Being complied with.

GZARG, FMG, CMG and BMG shall, and shall cause PICs to, ensure that (a) any adverse environmental impacts arising from the Project be minimized

by implementing the mitigations measures recommended in the EIA, SEIA, and EMP;

21(a) Being complied with.

(b) justifications be provided for any proposed major changes to such mitigation measures required during the detailed design, construction, and operation and maintenance of the project facilities;

21(b) Being complied with. No major change so far.

(c) the civil work contracts entered into with contractors under the Project include obligations of the contractors for environmental protection, including relevant mitigation and monitoring measures specified in the EIA, SEIA, and EMP.

21(c) Being complied with.

GZARG, FMG, CMG and BMG shall, and shall cause PICs to, ensure that all the sludge, dredged materials, and solid waste generated in the course of implementation of the Project be disposed of in accordance with the national and local laws and regulations, and that such disposal shall create no significant risk of secondary pollution.

22 Being complied with.

GZARG, FMG, CMG and BMG shall, and shall cause PICs to, ensure (a) timely elaborating and updating of the mitigation measures included in the EIA, SEIA and the related EMP during engineering design,

23(a) Being complied with.

(b) designate an environmental focal point to ensure effective implementation of the EMP,

23(b) Being complied with.

(c) timely implementation of the mitigation measures specified in EIA, SEIA and EMP,

23(c) Being complied with.

11

Environment-related Project Covenants No. of

Section Compliance Status

(d) regular environmental monitoring of implementation of EMP, be conducted by an independent agency acceptable to ADB, which shall prepare and submit to ADB the external environmental monitoring report on a semi-annual basis.Such reports shall be provided to ADB from the commencement of Project implementation until the Project completion and shall include

(a) progress made on mitigation measures and monitoring, (b) restoration, condition, and return of land temporarily acquired during

construction, (c) problems encountered, and (d)a corrective action plan in the event of any violation of the Borrower’s

environmental standards, rules, regulations or laws having occurred.

23(d)

Being complied with. No.1 semi-annual (second half of 2013) environmental monitoring report was submitted to ADB for review in January 2014; No.2 (first half of 2014) report submitted to ADB in Oct 2014; No.3 (second half of 2014) report submitted to ADB in May 2015; No.4 (first half of 2015) report submitted to ADB in Dec. 2015; No.5(second half of 2015) report submitted to ADB in Feb. 2016.This current report is No.6(first half of 2016) semi-annual environmental monitoring report.

GZARG, FMG, CMG, BMG shall, and shall cause PICs to, in cooperation with the responsible agencies,

...... (b) ensure that public environmental awareness and education programs on health and hygiene behavior and properly managing wastewater and solid waste disposal.

26 Being complied with.

12

IV. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD

A. General

As described in Chapter I, there are fourcomponents under construction during this reporting period, two components are under operation phase. Accordingly, the component EMPs have been executed for all the components under construction, as summarized in the following table.

Table 4: Summary of Potential Impacts, Mitigation Measures and Current Implementation Status during Construction (by June 2016)

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

Pre-construction Phase

EIA and FSR stage

Site and alignment selection

The recommended sites androutes for the individualcomponents were selected fromvarious alternatives to minimizeadverse impacts on theenvironment and land resources.

Site and alignment selection was carried out based on both environmental and land use considerations for all the components. Complied with

Engineering andtechnicalal

ternatives

Engineering and technical alternatives were evaluated basedon predefined environmental andeconomic criteria.

Alternative analysis using environmental and economic criteria has been done for each component. Complied with

Sector strategy

The project designed and suggested a new urban development strategy that feeds into the updates of city urban master plans with the goal of safe and sustainable urban development, with full access to environmental amenities.

Special analysis on the adaptability of project design to local master plan and sector strategy included in each component EIA Report. Complied with

Public consultation

Several rounds of broad public consultations have been conducted on environmental issues, poverty, and resettlement during the course of feasibility studies and EIA and SEIApreparations.

At least two rounds of public consultation have been carried out during the preparation of each component EIA. Complied with

Design stage

EMP updates

Mitigation measures defined in each individual EMP will be reviewed, updated, and incorporated into the detailed design to minimize adverse environmental impacts.

Mitigation measures defined ineach individual EMP has been reviewed with necessary updates during the preparation of detailed design. Complied with

Bidding andconstructionprepar

ation

Biddingdocumentsandcontra

ctors’ qualification

- Environmental provisions as cited in the EMP of the SEIA will be included in the Requests for Proposals.

- An environmental section will be included in the TOR for bidders.

- Environmental clauses for contractors in reference to the implementation of the EMP and monitoring plan will be included in the construction and supply contracts.

Environmental section was included in TOR for bidders, and environmental clauses were included in construction contracts for all the ongoing components. Complied with

Environmentaloperation

andsupervisionmanual

Contractors will be required to prepare an environmental operation and supervision manual, for approval by the PIC.

Environmental operation and supervision manual has been prepared by each component contractor and approved by the PIC. Complied with

Complaintandinformationoffi

ce orappointedpe

rson

- A complaint and information office will be established or aresponsible person appointedbefore construction begins.

- Office staff will be well trained to handle conflicts with residents resulting from environmental impacts.

F1 Established under PIC with responsible staff Complied with

F2 Established under PIC with responsible staff Complied with

C1 Established under PIC with responsible staff Complied with C2

B1 Established under PIC with responsible staff Complied with B2

13

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

Environ-mentalprotecti

ontraining

Environment specialists and/or officials from GEPD will be invited to provide training to relevant persons (and especially construction engineers and managers) on implementation and supervision of environmental mitigation measures.

Relevant on-job training has been provided by GEPD for all the on-going components during regular inspection. Complied with

Taking of land and property

- A resettlement office comprising local government officials will be established to manage there settlement process.

- Information dissemination and community consultation programs will be conducted in accordance with the PRC Land Administration Law and ADB's Involuntary Resettlement Policy (1995).

- All resettlement activities will be reasonably completed before construction starts on any component.

F1 RP updated and being implemented. Complied with

F2 RP updated and being implemented. Complied with

C1 Rp being implemented. Complied with

C2 Rp updated and being implemented. Complied with

B1 Rp updated and being implemented. Complied with

B2 Rp updated and being implemented. Complied with

Engagement of EMC

Prior to starting construction, an environmentalmanagement company will be engaged.

F1 EMC engaged before starting construction. Complied with

F2 EMC engaged before starting construction. Complied with

C1 EMC engaged before starting construction. Complied with

C2 EMC engaged before starting construction. Complied with

B1 EMC engaged before starting construction. Complied with

B2 EMC engaged before starting construction. Complied with

Engagement of IEM

Prior to starting construction, anIEM (as part of the loan implementation consultancy) willbe engaged through QCBS.

F1

The IEM accessed to the site in March 2014.

F2

C1

C2

B1

B2

Construction Phase

Soil erosion

Excavation

- Excavation activities will not beundertaken on days with rainstorms.

- Topsoil will be striped and stockpiled with retaining walls built where necessary before dumping.

- Temporary detention ponds or containment to control silt runoff will be provided.

- Intercepting ditches and chutes will be constructed to prevent outside runoff from entering disposal sites, and to divert runoff from sites to existing drainage or ponds.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Transport and disposalof

soils

- All soils will be used as onsite refill and landscaping materials.

- Settling ponds will be built in construction sites. Soils in settling ponds will be cleared for use as refill materials.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Soil loss fromconstructi

onvehicles

- Straw or cloth will be laid at the entry and exist of each construction site.

- The tires of construction vehicles will be regularly cleaned of soil.

F1 Complied with

F2 Complied with

C1 Complied with

14

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

C2 Complied with

B1 Complied with

B2 Complied with

Exposed surfaces

Re-vegetation with trees and grass will be undertaken as soon as refill and land leveling is complete.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Water Quality

Siltation in water bodies

Siltation in water bodies will be minimized through effective implementation of recommended mitigation measures.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Wastewater fromconstructi

oncamps

- All construction camps are locatedin the urban area, and thereforewastewater from constructioncamps will be diverted tomunicipal sewers.

- Unauthorized dumping ofwastewater will be prohibited.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Handling ofchemicals

- A construction materials handlingprotocol (e.g., storage away fromwatercourses and provision ofretention areas to containaccidental spills of such toxichazardous, and harmfulconstruction materials such as caustic and acidic substances, oil and petroleum products, and asphalt materials) will be prepared and applied to prevent soil and surface and ground water pollution.

- Workers (and especially painters)will be trained on safe and diligent handling of chemicals to avoid accidental spills, and on emergency response should aspill occur.

- A prevention and emergency response plan will be developed and implemented.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Increasedsuspendedsolids

fromdredging atShuikouLak

e

Dredging methods will beevaluated and the most suitablemethod(s) will be adopted.

C2 Complied with

Solid waste Dumping of construction solidwaste and garbage into waterbodies will be prohibited.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Householdchemicals

Prior to demolition, houses will besearched and cleared of household chemicals and any other toxic substances; these will be sent to the municipal toxic wastes depository for safe

F1 Complied with

F2 Complied with

C1 Complied with

15

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

disposal. C2 Complied with

B1 Complied with

B2 Complied with

Air Quality

Dust frommateriald

elivery andconstructio

nvehicles

Vehicles delivering granular and/or fine materials to the sites must be covered.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Dust fromconstructi

onsites

- Materials storage sites must be300m from residential areas and covered or sprayed with water.

- Extra care will be taken during dryads with strong winds, by more frequent spraying of water and covering of dust sources.

- Water will be sprayed on construction sites twice per day.

- Upon completion of civil works, all construction sites will be required to be re-vegetated with trees and grass.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Dust fromconstructi

onroads

- All roads and pavement used by contractors’ or suppliers’ vehicles will be kept clean and clear of all dust, mud, or extraneous materials dropped by these vehicles. Such cleaning will be undertaken on a regular basis.

- Water will be sprayed on access roads twice per day.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Emissionsfrom vehiclesandeq

uipment

- Vehicle emissions will comply withGB18352-2005, GB17691-2005,GB 11340-2005, GB3847-2005and GB18285-2005.

- Equipment and machinery emissions must comply withGB16297-1996.

- A regular inspection and certification system will be initiated.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Noise

Noise fromequipmentand vehicles

- Noise from equipment andmachinery will comply withGB12523-1990.

- An adequate route must beprovided to keep large trucksaway from residential areas.

- At construction sites within 500 mof the nearest habitation, noisyconstruction work will stopbetween 10 p.m. and 6 a.m.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Demolition House demolition at construction sites will be required to stop between 10 p.m. and 6:30 a.m.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Community complaintsabo

- Interviews with residents living adjacent to construction sites will be conducted on a weekly

F1 No complaint so far Complied with

F2 No complaint so far Complied with

16

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

utnoise basis to identify community complaints about noise, and seek suggestions from community members to reduce noise-related annoyance.

- Community suggestions will be used to adjust the work hours of noise-generating machinery.

C1 No complaint by 1

st half year Complied

with

C2 No complaint so far Complied with

B1 No complaint so far Complied with

B2 No complaint so far Complied with

Solid Waste

Domesticwaste

fromconstructioncamps

- Multi-compartment collection bins will be provided to facilitate reuse, recycling and composting of solid waste.

- Waste will be stored away from water bodies and will be regularly collected by the city sanitation bureau and hauled to the municipal sanitary landfill.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Dredgedsediment atShuikou

Lake

Dredged sediment will be processed in a manner not causing nuisance and used for urban landscaping. The dredgedsediments will be contained ingeotubes that will be placed in a storage site lined with geo-textile membrane to prevent leakage into ground water. The storage site will be thoroughly cleaned after the sediments are used up.

C2 Dredging is done. Complied with

Constructionsolid wastes

- Professional demolition companies will be contracted to carry out housing demolition.

- Reusable and recyclable materials (such as bricks, windows and doors, and steel bars) will be collected for reuse and recycle. The remaining construction wastes will be transported to the municipal landfill.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Impact on flora

Vegetation

- Existing vegetation will be preserved where no construction activity is planned; where activity is planned for a later, the vegetation will be temporarily preserved.

- Disposal and borrow sites will be rehabilitated into grassland, woodland, or farmland after closing.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Social and cultural

considerations

Resettlement All affected persons will be compensated and resettled in a timely and adequate manner, in accordance with the resettlement plans.

F1 RP updated and being implemented. Complied with

F2 RPis underimplementation. Complied with

C1 RP being implemented. Complied with

C2 RP updated and being implemented. Complied with

B1 RP updated and being implemented. Complied with

B2 RP updated and being implemented. Complied with

Traffic jam or block

- Interim roads will be built where needed. - Transport routes will be selected to reduce

disturbance to regular traffic. - Traffic will be diverted at peak traffic hours, and

areas reinstated to their original condition on completion of construction.

F1 Complied with

F2 Complied with

C1 Complied with

C2 Complied with

B1 Complied with

B2 Complied with

Cultural - Cultural heritage sites will be preserved where

identified. In accordance with PRC regulations, F1

No identification of cultural heritage site so far Complied with

17

Environment Factor

Potential Impacts /Issues

Mitigation Measures Proposed in Component EMP

Implementation Status

heritage no person shall destroydamage, deface, conceal, or otherwise interfere with a relic.

- If an important site is unearthed, work should be stopped immediately and the matter promptly referred to the county, municipal, provincial, or state-level agencies for evaluation and a decision regarding appropriate actions.

F2 No identification of cultural heritage site so far Complied with

C1 No identification of cultural heritage site so far Complied with

C2 No identification of cultural heritage site so far Complied with

B1 No identification of cultural heritage site so far Complied with

B2 No identification of cultural heritage site so far Complied with

With the implementation of mitigation measures listed above, no significant environmental impact has been resulted from project implementation so far. By the end of this reporting period, the implemented individual EMPs are considered effective and satisfactory.

B. Observations Specific to Each Component during Site Inspection

1. Component F1 and F2: Urban Road Network and Related Municipal Infrastructure for Fangchenggang City,and coastal protection and upgrading

In the reported period, together with road construction, Fangchenggang subcomponent PMOs, contractors and supervising agencies implemented mitigation measures regulated in the environmental management plan for Fangchenggang road network and its infrastructure construction, such as construction time control, dust removal by watering and strengthening of safety management, reducing environmental impact caused by the subcomponent construction. Most of the mitigation measures were implemented efficiently during construction, such as campsite management in Anbujiang Bridge. It was observed that there ispotential safety risk on construction site at 2# Road. Following mitigation measure was suggested: (a) all electricity facilities should be secured in closed boxes and (b) the wires should be protected by rubbercovers. Fangchenggang IA signed a contract with Nanning Xiwan Monitoring Co., Guangxi, which carried out monitoring of air quality, sea water quality and noise level for the road subcomponent and the coastal dyke subcomponent. In the reporting period, Nanning Xiwan Monitoring Co., Guangxi carried out the monitoring activities in the reported period, the result indicates no environmental accident or complaint occurred in the implementation.

18

Coastal protection and upgrading construction site

Electricity facility exposed to air Water spray at construction site

19

2. Component C1 and C2: urban road network and related municipal infrastructure

for Chongzuo City, andShuikou Lake environmental improvement

Overall, the subcomponent of Chongzuo progressed smoothly. Under the subcomponent of road network and its infrastructure construction, 101.0% completed for Chengnan 9th Road (Note: Completion Percentage of Chengnan 9

th Road and Liancheng Road is over 100% due to the contract variation which lead to

the increase of construction work amount. The contract amount has not been updated as the variation has not been approved.), 100.0% completed for Shijinglin Road, 67% completed for Beiwei 2nd Road and Zhongyi Road and 93% completed for Shuikou Lake subcomponent. With subcomponent activities, MPMO and contractors and construction supervision units seriously conducted mitigation measures in project environmental management plan. Net cages have been cleared, and most of the cofferdam has been removed. Good wetland ecosystem has been built with project intervention. However potential safety issue for local residents and unclear environmental management system establishment still exist. Required actions were identified as following: (i) Chongzuo PMO should collect information about the environmental monitoring equipment installation and maintenance under the loan, responsibilities should be clearly setup for each stakeholders; (ii) warning and information boards should be set to avoid unauthorized fishing and swimming activities by local residents to ensure their safety; (iii) During operational period, Jiangnan Street Committee will be responsible for the maintenance of Shuikou Lake. Clearly operational guidance should be prepared on environment management; and ( ) Garbage at certain parts of the construction site should be cleaned and dumped in time to keep city area clean and tidy. The Chongzuo IA had commissioned Chongzuo environmental monitoring station for monitoring the construction of two subcomponents for air, noise and water quality monthly. The result of environmental monitoring reaches the standard except for the total nitrogen of the surface water (the total nitrogen exceeding the standard is due to the higher background value instead of project implementation). By the end of the reported period, no environmental accident or complaint occurred in the implementation.

Landscaping and afforest achievement

Garbage at part of the construction site hasn’t been cleaned

20

3. Component B1: Urban road network and related infrastructure for Baise City

B1 subcomponent construction was completed in December 2014, and the projectcompletionenvironmental inspection was accepted in December 2014. Project completion environmental performance review found that all of the environmental mitigation measures in the EIA report proposed, involving drainage and sewage treatment, noise control, air pollution control, transplant& protection of ancient trees, landscaping and soil conservation has been implemented in the construction process, with a total investment of (approximately 1.31% of the total project investment) 5.19 million yuan. Environmental monitoring results are fully in line with the applicable national standards.Resettlement compensation of the project has been completed. Implementation of the project has not received any environmental complaints. Consultants have reminded implementation party to start the operations of the environmental management plan since January 2015.

4. Component B2: Longwang Bridge for Baise City

B1 subcomponent construction was completed in June 2014, in September 2014 the project completed environmental acceptance. Project completion environmental performance review found that all of the specific environmental projects in the EIA report proposed mitigation measures, involving drainage &sewage treatment, noise control, air pollution control, migration and the protection of trees, landscaping and soil conservation have been implemented in the construction process, with a total investment of (approximately 1.86% of the total project investment) 3.51 million yuan. Environmental monitoring results are fully in line with the applicable national standards. Resettlement compensation of the project has been completed. Implementation of the project has not received any environmental complaints. Consultants have reminded implementation party to start the operations of the environmental management plan since January 2015.

21

V. SUMMARY OF ENVIRONMENTAL MONITORING

A. Monitoring plan and responsibilities

The environmental monitoring programs developed as part ofSEIA and individual EMPs (as summarized in the table below) have been implemented by PICs in order to evaluate the:

(i) extent and severity of environmental impacts; (ii) compliance with related rules and regulations; and (iii) overall effectiveness of the Project EMP with actions taken as necessary based on the monitoring

results.

The monitoring has been implemented by following the methodology provided in the national standard for monitoring environmental indicators and pollutants.Considering current project progress, the monitoringprograms for each ongoing component are limited to the internal monitoring implementedby EMCs during construction phase.

Table 5: Summary of Implemented Environmental Monitoring Program for GSCDP

Item Parameters Location Time and

Frequency Implementation Status

(Y/N/NA)

A. Construction (Internal Monitoring)

1. Surface water

pH, NH3-N,TN, TP, BOD,COD, oils

For eachcomponent, aminimum of 2locations on theriver upstreamanddownstream ofthe constructionsite

3 samples eachtime, at beginningof construction andquarterly thereafter

F1 Y, semiannually

F2 Y, semiannually

C1 Y, monthly

C2 Y, monthly

B1

N, environment inspection & acceptance has completed.Processed to operation stage

B2

N, environment inspection & acceptance has completed.Processed to operation stage

2. Air TSP, PM10, NO2 2 monitoring locations foreachconstruction site

3 samples at each location each time, semiannually

F1 Y, semiannually F2 Y, semiannually C1 Y, monthly C2 Y, monthly

B1

N, environment inspection & acceptance has completed. Processed to operation stage

B2

N, environment inspection & acceptance has completed. Processed to operation stage

3. Noise Leq (dB(A)) 1 location at the borderwithsettlementswithin 200m ofconstruction site

Twice (during both dayand night each time) monthly during peakconstruction,

F1 Y, semiannually F2 Y, semiannually C1 Y, monthly C2 Y, monthly B1 Y, environment

22

Item Parameters Location Time and

Frequency Implementation Status

(Y/N/NA)

quarterly otherwise inspection & acceptance has completed.

B2

Y, environment inspection & acceptance has completed.

4. Soil and vegetation

Removal ofvegetationand exposed surface

All sites Visual inspection weekly

Y, for all ongoing components, implemented as part of individual water and soil control plan.

5. Dredged sludge

Dredged sludge, including grain size,% solids, density or specificgravity, totalorganic carbon, Cd, Cr, Cu, Pb, Hg, Ni, Zn and organic andorgano-metalliccompounds.

Shuikou Lake

Sludge sampling and testing will be conducted at 6evenly distributed monitoringpoints once prior to commencementof dredging. Visual inspection and measurement, weekly.

C2

Y, local environment inspection administration has analyzed the sludge samples, the concentration of .Cd, Cr, Cu, Pb, Hg, Ni, Zn and organic andorgano-metalliccompoundsare below detection limit.

B. Engineering completion environment inspection & acceptance

1. air TSP 2 monitoring point for every construction site

3 samples at each location each time, semiannually

F1 N, not completed

F2 N, not completed

C1 N, not completed

C2 N, not completed

B1

N, environment inspection & acceptance has completed.

B2

N, environment inspection & acceptance has completed.

2. noise Leq (dB(A))

At least set 4 monitoring points, the points should be arranged at project border and sensitive spot

2 samples for every monitoring point

F1 N, not completed

F2 N, not completed

C1 N, not completed

C2 N, not completed

B1

N, environment inspection &acceptance has completed.

B2

N, environment inspection & acceptance has completed.

23

Item Parameters Location Time and

Frequency Implementation Status

(Y/N/NA)

3. soil & vegetation

Vegetation recover and landscape

construction All construction sites Visual inspection

Y, B1 and B2 has been implemented

4. Dredged sediment

Recycling and city landscape

construction Shuikou Lake Visual inspection C2

Y, the sediment is used for vegetation and backfilling

C. Operation period (generally monitoring)

1. Air TSP, PM10 One monitoring point for every construction site

Semiannually, 3 samples per day

F1 N, not completed

F2 N, not completed

C1 N, not completed

C2 N, not completed

B1 Y, PMO get the data of EPA semiannually

B2 Y, PMO get the data of EPA semiannually

2. noise Leq (dB(A))

At least set 4 monitoring points, the points should be arranged at project border and sensitive spot

Per every two months, two samples every time (including day and nigh)

F1 N, not completed

F2 N, not completed

C1 N, not completed

C2 N, not completed

B1 Y, PMO get the data of EPA semiannually

B2 Y, PMO get the data of EPA semiannually

3. soil & vegetation

Vegetation recover and landscape

construction All construction site

Visual inspection, one time annually

Y, B1 and B2 has been implemented

4. Dredged sediment

Recycling and city landscape

construction Shuikou Lake

Visual inspection, one time monthly, until the sediment is used up

Y, the sediment is used for vegetation and backfilling

24

Note: Y-Yes; N-No; NA-Not applicable.

B. Monitoring Results

During this reporting period, the environmental monitoring results provided by PICs of four ongoing components are summarized in the following sections. All the detected incompliance will be highlighted with corrective measures proposed and implemented in the following assessment.

1. Component F1: Urban Road Network and RelatedMunicipalInfrastructureforFangchenggang City

a. Air quality

Table6: Monitoring data of component F1 (Jan. – Jun. 2016)

Monitoring Spot Date TSPmg/m

3)

NO2

mg/m3)

N1 10m to the northeast of the joint of III road and II road

2016-03-16 0.110

0.013

2016-03-17 0.111 0.015

2016-06-15 0.118 0.016

2016-06-16 0.116 0.018

N2 10m to the north of Longteng Road (#IV road)

2016-03-16 0.124 0.011

2016-03-17 0.115 0.014

2016-06-15 0.128 0.019

2016-06-16 0.120 0.015

N3 10m to the south of joint of the #II road and #V road

2016-03-16 0.117 0.013

2016-03-17 0.124 0.016

2016-06-15 0.123 0.017

2016-06-16 0.128 0.014

N4 10m to the north of the joint of the Wanxin Road and #3 road

2016-03-16 0.147 0.014

2016-03-17 0.142 0.017

2016-06-15 0.154 0.015

2016-06-16 0.150 0.017

N5 North of the Jianzheng Road (10m to the east of the joint with Taozhong Road)

2016-03-16 0.124 0.012

2016-03-17 0.119 0.015

2016-06-15 0.134 0.013

2016-06-16 0.131 0.014

N6 10m to the east of the joint of the Jianzheng 2016-03-16 0.143 0.017

25

Monitoring Spot Date TSPmg/m

3)

NO2

mg/m3)

Road and Tianmiao 5th

street 2016-03-17 0.130 0.014

2016-06-15 0.150 0.019

2016-06-16 0.133 0.013

N7 10m to the west of the joint of the Tianmiao 1th

street and Longshan North Road

2016-03-16 0.128 0.012

2016-03-17 0.130 0.016

2016-06-15 0.141 0.014

2016-06-16 0.143 0.015

N8 10m to the north of the joint of Longfeng Road and Xicha 1

st Street

2016-03-16 0.123 0.013

2016-03-17 0.127 0.015

2016-06-15 0.129 0.013

2016-06-16 0.135 0.018

N9 10m to the north of the joint of the Tianzheng Road and Shadun 2

st Street

2016-03-16 0.124 0.013

2016-03-17 0.115 0.012

2016-06-15 0.130 0.015

2016-06-16 0.120 0.014

N10 10m to the south of the end of the Xicha 5st

Street

2016-03-16 0.126 0.015

2016-03-17 0.132 0.014

2016-06-15 0.135 0.016

2016-06-16 0.136 0.013

Class II, air condition standard (GB3095-1996)

≤0.3 ≤0.12

During January to June, 2016, the monitoring result analysis demonstrated that air quality of subproject F1 met the regulation. Monitoring results of PM10 was not provided.

b. Noise

Table 7:Monitoring data of component F1 (Jan. - Jun. 2016)

Monitoring spot Date Value,Leq,dB A Standard Limitation

[dB(A)]

N1 10m to the northeast of the joint of III road and II road

2016-03-16 51.8

2016-03-17 53.3

26

Monitoring spot Date Value,Leq,dB A Standard Limitation

[dB(A)]

2016-06-15 51.3

70

2016-06-16 52.3

N2 10m to the north of Longteng Road (#IV road)

2016-03-16 52.0

2016-03-17 51.4

2016-06-15 51.5

2016-06-16 50.4

N3 10m to the south of joint of the #II

road and #V road

2016-03-16 51.1

2016-03-17 49.7

2016-06-15 50.8

2016-06-16 49.2

N4 10m to the north of the joint of the

Wanxin Road and #3 road

2016-03-16 50.9

2016-03-17 52.7

2016-06-15 50.1

2016-06-16 51.7

N5 North of the Jianzheng Road (10m to

the east of the joint with Taozhong Road)

2016-03-16 53.6

2016-03-17 54.5

2016-06-15 53.3

2016-06-16 54.1

N6 10m to the east of the joint of the

Jianzheng Road and Tianmiao 5th

street

2016-03-16 49.7

2016-03-17 50.0

2016-06-15 49.3

2016-06-16 50.2

N7 10m to the west of the joint of the

Tianmiao 1th

street and Longshan North

Road

2016-03-16 48.8

2016-03-17 49.1

2016-06-15 48.5

2016-06-16 49.0

Based on the data in Table 7, the noise level has reached the standards.

27

c. Seawater quality

Table 8: Seawater monitoring data of component F1 (Jan. – Jun. 2016)

Parameter Date

Monitoring spot

Standard limitation

Class

III,GB3097-1997

1# 2

# 3

#

4#

Temperature ℃

2016-

03-16 19.6 19.4 19.6 19.7

/

2016-

03-17 19.5 19.6 19.7 19.6

2016-

06-15

29.5

29.9 29.1 29.2

2016-

06-16

30.4

29.1 29.6 29.3

PH

2016-

03-16 7.53 7.57 7.59 7.69

6.8~8.8

2016-

03-17 7.51 7.60 7.62 7.73

2016-

06-15

7.44

7.53 7.47 7.49

2016-

06-16 7.47 7.56 7.56 7.54

DO

2016-

03-16 7.73 7.83 7.61 7.73

>4

2016-

03-17 7.76 7.80 7.59 7.76

2016-

06-15 6.98 6.83 6.61 6.73

2016-

06-16 7.04 6.88 6.57 6.79

COD 2016-

03-16 2.15 2.29 2.43 2.20 ≤.

28

2016-

03-17 2.19 2.34 2.50 2.28

2016-

06-15 2.04 2.20 2.23 2.05

2016-

06-16 2.06 2.24 2.30 2.08

BOD5

2016-

03-16 1.4 1.4 1.3 1.4

≤.

2016-

03-17 1.5 1.3 1.4 1.6

2016-

06-15 1.3 1.1 1.1 1.2

2016-

06-16 1.2 1.2 1.1 1.2

inorganic

nitrogen

ammonia

nitrogen

2016-

03-16 0.164 0.161 0.132 0.133

≤.13

2016-

03-17 0.175 0.157 0.135 0.138

2016-

06-15 0.156 0.151 0.122 0.123

2016-

06-16 0.167 0.146 0.125 0.120

nitrate

nitrogen

2016-

03-16 0.102 0.103 0.106 0.107

2016-

03-17 0.106 0.105 0.110 0.104

2016-

06-15 0.099 0.097 0.098 0.090

2016-

06-16 0.104 0.102 0.110 0.102

nitrite

nitrogen

2016-

03-16 0.022 0.027 0.022 0.030

2016-

03-17 0.024 0.024 0.026 0.027

2016- 0.017 0.023 0.021 0.024

29

06-15

2016-

06-16 0.016 0.022 0.024 0.025

reactive phosphate

2016-

03-16 0.047 0.053 0.054 0.059

≤.0590

2016-

03-17 0.045 0.052 0.056 0.055

2016-

06-15 0.040 0.053 0.044 0.048

2016-

06-16 0.042 0.052 0.050 0.045

The concentration of reactive phosphate has not met the regulating requirement. According to the local environmental protection agency, it is due to environmental background value of local sea water quality, which was not impacted by the ongoing projects.

2. Component F2: Coast environmental protection& remediation of Fangchenggang City

a. Air quality

Table 9:Air quality Monitoring Data of Component F2 (Jan. – Jun. 2016)

Monitoring spot

Date TSP mg/m

3) NO2 mg/m

3)

Concentration/hr Concentration/day

1# Gangkou

District

Administration

2016-03-11 0.138 0.016

2016-03-12 0.160 0.018

2016-06-12 0.118 0.011

2016-06-13 0.126 0.010

2# Wanxin

Building

Materials

Factory

2016-03-11 0.134 0.014

2016-03-12 0.127 0.013

2016-06-12 0.150 0.012

2016-06-13 0.152 0.014

3# Gangkou

District

Procuratorate

2016-03-11 0.149 0.012

2016-03-12 0.149 0.014

2016-06-12 0.130 0.013

30

Monitoring spot

Date TSP mg/m

3) NO2 mg/m

3)

Concentration/hr Concentration/day

2016-06-13 0.139 0.011

4# Hongxing

Village

2016-03-11 0.130 0.013

2016-03-12 0.134 0.015

2016-06-12 0.124 0.009

2016-06-13 0.130 0.011

5# Gangkou

District Police

Office

2016-03-11 0.148 0.019

2016-03-12 0.144 0.017

2016-06-12 0.148 0.011

2016-06-13 0.143 0.013

6# Gangkou

District Traffic

Police

2016-03-11 0.132 0.013

2016-03-12 0.156 0.016

2016-06-12 0.141 0.010

2016-06-13 0.139 0.012

7# Gangkou

District real

estate agency

2016-03-11 0.140 0.019

2016-03-12 0.143 0.017

2016-06-12 0.138 0.013

2016-06-13 0.144 0.015

Class II, air quality standard

(GB3095-1996) ≤0.30 ≤0.12

Table 9 demonstrated that air quality of Component F2 has reached the regulation and standard.

b. Noise

Table 10:Noise Monitoring Data of Component F2 Jan. – Jun. 2016

Monitoring spot Date Data,Leg,dB(A)

[dB(A)] Standard Limit

Value

1# Gangkou District Administration

2016-03-12 52.0

70 2016-03-13 51.5

2016-06-12 52.5

31

2016-06-13 51.8

2# Wanxin Building Materials

Factory

2016-03-12 56.8

2016-03-13 58.2

2016-06-12 57.6

2016-06-13 58.9

3# Gangkou District

Procuratorate

2016-03-12 51.0

2016-03-13 52.6

2016-06-12 50.8

2016-06-13 52.6

4# Hongxing Village

2016-03-12 43.6

2016-03-13 44.8

2016-06-12 44.2

2016-06-13 43.8

5# Gangkou District Police

Office

2016-03-12 47.2

2016-03-13 48.6

2016-06-12 48.0

2016-06-13 49.0

6# Gangkou District Traffic

Police

2016-03-12 48.0

2016-03-13 49.3

2016-06-12 47.6

2016-06-13 48.8

7# Gangkou District real

estate agency

2016-03-12 52.6

2016-03-13 53.5

2016-06-12 53.2

2016-06-13 52.8

.

As presented in Table 10, noise level of Component F2 has met the standard.

c. Sea water quality

Table 11: Water quality data of Component F2 (Jan. – Jun. 2016)

32

Parameter Date

Monitoring spot

Standard LimitationClass III,GB3097-

1997

1# 2

# 3

#

Temperature ℃

2016-03-12 17.6 17.5 17.6

/ 2016-03-13 17.7 17.6 17.7

2016-06-12 30.9 31.3 30.2

2016-06-13 30.6 30.9 30.5

PH

2016-03-12 7.84 7.86 7.86

6.8~8.8 2016-03-13 7.82 7.84 7.85

2016-06-12 7.84 7.78 7.84

2016-06-13 7.82 7.74 7.81

Suspended Solids

2016-03-12 15.7 14.7 15.0

Man-made

increment≤100

2016-03-13 16.2 14.3 15.0

2016-06-12 15.3 15.4 15.0

2016-06-13 15.3 14.8 14.5

DO

2016-03-12 7.30 7.40 7.37

>4 2016-03-13 7.33 7.44 7.41

2016-06-12 7.05 7.25 7.28

2016-06-13 7.10 7.25 7.31

COD

2016-03-12 1.86 1.81 1.83

≤. 2016-03-13 1.88 1.78 1.81

2016-06-12 1.99 1.82 1.92

2016-06-13 1.99 1.75 1.87

BOD5

2016-03-12 1.1 1.2 1.3

≤.

2016-03-13 1.3 1.3 1.3

2016-06-12 1.4 1.3 1.4

2016-06-13 1.4 1.2 1.3

inorganic

nitrogen

ammonia nitrogen

2016-03-12 0.121 0.119 0.114 ≤.11

2016-03-13 0.127 0.122 0.119

33

2016-06-12 0.127 0.107 0.118

2016-06-13 0.126 0.111 0.123

nitrate nitrogen

2016-03-12 0.261 0.253 0.258

2016-03-13 0.260 0.263 0.262

2016-06-12 0.266 0.232 0.246

2016-06-13 0.271 0.241 0.252

nitrite nitrogen

2016-03-12 0.023 0.020 0.025

2016-03-13 0.025 0.024 0.026

2016-06-12 0.022 0.025 0.028

2016-06-13 0.024 0.029 0.032

reactive phosphate

2016-03-12 0.026 0.031 0.030

≤.030 2016-03-13 0.029 0.034 0.034

2016-06-12 0.025 0.028 0.025

2016-06-13 0.026 0.033 0.028

Petroleum organic

compound

2016-03-12 0.024 0.025 0.026

<0.3 2016-03-13 0.025 0.024 0.026

2016-06-12 0.022 0.024 0.025

2016-06-13 0.022 0.023 0.026

The concentration of reactive phosphate was slightly above the standard level at location #2 and #3 in March, and at location #2 in June. According to local environmental protection agency, it is due to the environmental background value of local sea water quality, which was not impacted by the projects.

. 3. Component C1:Urban Road Networkand Related MunicipalInfrastructure for Chongzuo

City

C1-1.Chengnanjiu Road and Liancheng Road

a. Air quality

Table 12: Air quality monitoring result of Component C1-1 (Jan. – Jun. 2016)

Sampling time Parameter

Concentration mg/m3

Class II, air quality

standard (GB3095-

1996)

1#Tai village

resettlement spot

2#Business

Administrative

34

Agency of Chongzuo

2016 1stQuarter

TSP

0.131 0.161

≤0.30

2016 2nd

Quarter 0.138 0.171

2016 1

st Quarter

NO2

0.022 0.022

≤0.12

2016 2nd

Quarter 0.021 0.021

Note: The data of 1

st quarter was the average value of data on Jan. 11-15, Feb. 15-19 and Mar. 7-11. The data of 2

nd quarter

was the average value of data on Apr. 10-14, May 9-13, and Jun. 6-10.

The air quality parameters were all in compliance with regulation.

b. Noise

Table 13: Noise monitoring of component C1-1(Jan.–Jun. 2016)

Location Noise source

2016 1st Quarter 2016 2

nd Quarter [dB(A)]

Standard Limit Value Day time

Night

time Day time Night time

Eastern boundary of construction site

Excavator, crane 58.7 43.6 58.6 43.2

70

Southern boundary of

construction site Excavator, crane 56.5 43.4 58.3 42.8

Western boundary of

construction site Excavator, crane 57.7 43.6 57.6 43.3

Northern boundary of

construction site Excavator, crane 58.3 44.3 58.4 43.6

The closest sensitive

spot to construction

site

construction noise,

daily noise 57.4 43.6 58.3 43.0

Note: The data of 1st quarter was the average value of data on Jan. 11-12, Feb. 15-16 and Mar. 7-8. The data of 2

nd quarter

was the average value of data on Apr. 10-11, May 9-10, and Jun. 6-7.

The noise level was all in compliance with regulation.

35

c. Surface water

Table 14: Surface water quality monitoring results (Jan.-Jun. 2016)

Monitoring spot Time pH DO BOD5 COD ammonia nitrogen

Suspended solids

Petroleum organic

compound

Total phosphorou

s

Total nitroge

n

1#

Chengnanjiu Road bridge

crosssection(50m upstream of Moshui river)

2016

1st

Quarte

r

7.6

9

7.0

8 1.16 13.11 0.19 11.33 0.01L 0.08 2.80

2016

2nd

Quarte

r

7.6

8

7.3

0 1.13 13.56 0.15 10.11 0.01L 0.08 2.61

2#

Chengnanjiu Road bridge

crosssection(50m lower stream of Moshui river)

2016

1st

Quarte

r

7.6

0

6.7

4 1.24 13.56 0.14 10.00 0.01L 0.09 2.59

2016

2nd

Quarte

r

7.5

5

6.9

3 1.19 12.22 0.15 11.44 0.01L 0.08 2.61

3#

Lianchengnan Road (50m upstream of Moshui river)

2016

1st

Quarte

r

7.4

0

7.0

2 1.07 12.00 0.12 10.22 0.01L 0.09 2.91

2016

2nd

Quarte

r

7.5

3

7.0

8 0.98 13.22 0.14 9.33 0.01L 0.09 2.74

4#

Lianchengnan Road (50m lower

stream of Moshui river)

2016

1st

Quarte

r

7.5

8

7.1

2 1.08 16.22 0.13 10.67 0.01L 0.10 2.66

2016

2nd

7.5 6.9 1.07 14.56 0.13 9.67 0.01L 0.09 2.52

36

Quarte

r

3 7

Standard limit value(

,GB3838-2002) 6-9 ≥5 ≤4 ≤20 ≤1.0 / ≤0.05 ≤0.2 ≤1.0

Note: L means lower than detection limit. The data of 1

st quarter was the average value of data on Jan. 11-13, Feb. 15-17 and Mar. 7-9. The data of 2

nd quarter was the

average value of data on Apr. 10-12, May 9-11 and Jun. 6-8.

Total nitrogen was found above the standard concentration in both 1st and 2nd quarter.According to local environmental protection agency, it is due to the environmental background value of local sea water quality, which is nothing to do with theconstruction of the project.

d. Dust

Table 15: Dust monitoring results of Component C1-1 (Jan.-Jun.2016)

Time Monitoring spot

Concentration mg/m3

1#Upwind

direction

2#Downwind

direction 3

# Downwind direction

2016 1st Quarter

Southern Liancheng Road 0.148 0.192 0.196

Chengnanjiu Road 0.136 0.181 0.190

2016 2nd

Quarter Southern Liancheng Road 0.139 0.192 0.192

Chengnanjiu Road 0.134 0.186 0.190

Note: The data of 1st quarter was the average value of data on Jan. 11-12, Feb. 15-16 and Mar. 7-8. The data of 2nd quarter was the average value of data on Apr. 10-11, May 9-10, and Jun. 6-7.

C1-2.Beiweier Road

a. Air quality

Table 16: Air quality monitoring result of Component C1-2 (Jan. – Jun. 2016)

Sampling time Parameter

Concentration

mg/m3

Class II, air quality standard (GB3095-1996)

1#Maan Village

2016 1st

Quarter

TSP

0.163

≤0.30

2016 2nd

Quarter 0.172

2016 1

st Quarter NO2 0.022

37

2016 2

nd Quarter 0.021

≤0.12

Note: The data of 1

st quarter was the average value of data on Jan. 11-15, Feb. 15-19 and Mar. 7-11. The data of 2

nd quarter

was the average value of data on Apr. 10-14, May 9-13, and Jun. 6-10.

The air quality parameters were all in compliance with regulation.

b. Noise

Table 17: Noise monitoring of component C1-2(Jan.–Jun. 2016)

Location Noise source 2016 1

st Quarter 2016 2

nd Quarter [dB(A)]

Standard Limit Value Day time

Night time

Day time Night time

Eastern boundary of construction site

Excavator, crane

58.8

44.0

59.1

43.8

70

Southern boundary of construction site

Excavator, crane

57.6

43.8

57.4

43.9

Western boundary of construction site

Excavator, crane

58.5

43.9

57.6

43.4

Northern boundary of construction site

Excavator, crane

57.7

43.7

58.0

43.8

The closest sensitive spot to construction

site

construction noise, daily noise

58.5

43.1

57.9

42.8

Note: The data of 1st quarter was the average value of data on Jan. 11-12, Feb. 15-16 and Mar. 7-8. The data of 2

nd quarter

was the average value of data on Apr. 10-11, May 9-10, and Jun. 6-7.

The noise level was all in compliance with regulation.

c. Dust

Table 18: Dust monitoring results of Component C1-2 (Jan.-Jun.2016)

Time Monitoring spot Concentration mg/m

3

1#Upwind

direction 2

#Downwind direction

3# Downwind direction

2016 1st Quarter

Beiweier Road

0.147

0.195

0.200

2016 2nd

Quarter

0.146

0.199

0.195

Note: The data of 1st quarter was the average value of data on Jan. 11-12, Feb. 15-16 and Mar. 7-8. The data of 2nd quarter was the average value of data on Apr. 10-11, May 9-10, and Jun. 6-7.

38

4. Component C2:Shuikou LakeEnvironmentalImprovement for Chongzuo City

a. Air quality

Table 19: Air quality monitoring result of Component C2 (Mar. – Jun. 2016)

Sampling time Parameter

Concentration mg/m3

Class II, air quality

standard (GB3095-

1996)

1#Chongzuo College

2#Jiangnan 3

rd

elementary

schoolofJiangzhouDi

strict,Chongzuo City

2016 1st

Quarter TSP

0.127

0.141

≤0.30 2016 2

nd Quarter

0.133

0.136

2016 1

st Quarter NO2

0.020

0.021

≤0.12

2016 2nd

Quarter

0.020

0.020

Note: The data of 1

st quarter was the average value of data on Jan. 11-15, Feb. 15-19 and Mar. 7-11. The data of 2

nd quarter

was the average value of data on Apr. 10-14, May 9-13, and Jun. 6-10.

The air quality parameters were all in compliance with regulation.

b. Noise

Table 20: Noise monitoring of component C2 (Mar.–Jun. 2016)

Location Noise source

2016 1st Quarter 2016 2

nd Quarter

[dB(A)] Standard Limit

Value Day time

Night

time Day time Night time

1. Military base at Shuikou Lake eastern shore

Living,

transportation and

natural background

noise

58.7 43.4 58.4 43.8

70 2. Chongzuo

College

Living,

transportation and 56.3 44.1 57.1 43.9

39

natural background

noise

3. Jiangnan 3rd

elementary

school of

Jiangzhou

District,

Chongzuo City

Living,

transportation and

natural background

noise

58.3 43.4 58.8 43.2

Note: The data of 1st quarter was the average value of data on Jan. 11-12, Feb. 15-16 and Mar. 7-8. The data of 2

nd quarter

was the average value of data on Apr. 10-11, May 9-10, and Jun. 6-7.

The noise level was all in compliance with regulation.

c. Surface water

Table 21: Surface water quality monitoring results (Mar.-Jun. 2016)

Monitoring spot

Time

Parameter

Temperature (℃)

pH DO KMnO4

COD

Ammonia

nitrogen

Total phosphor

ous

Total nitrog

en

BOD5

Petroleum

organic compou

nd

Suspended solids

1#

Input of ShuikouL

ake

2016 1st

Quarter 20.37

7.81

6.77

2.50 10.6

7 0.17 0.07 2.35 1.87 0.04 10.00

2016 2nd

Quarter

22.56 7.65

7.12

2.29 10.2

2 0.18 0.07 2.59 2.03 0.06 9.78

2#

Output of Shuikou

Lake

2016 1st

Quarter 19.97

7.79

7.10

2.30 11.0

0 0.17 0.08 2.51 2.40 0.04 8.67

2016 2nd

Quarter

22.23 7.71

7.44

2.36 12.5

6 0.17 0.08 2.64 2.24 0.06 8.67

3#

Shuikou Lake

central area (left)

2016 1st

Quarter 20.00

7.73

7.10

2.40 16.3

3 0.21 0.07 2.61 2.37 0.04 9.00

2016 2nd

Quarter

22.08 7.60

6.91

2.46 12.8

9 0.21 0.09 2.34 2.21 0.06 10.44

4#

Shuikou Lake

central area

(right)

2016 1st

Quarter 20.77

7.66

6.70

2.93 19.0

0 0.26 0.07 3.04 2.93 0.04 9.67

2016 2nd

Quarter

22.38 7.57

7.16

2.93 12.7

8 0.26 0.08 2.61 2.82 0.06 10.78

Standard limit value(,GB3838-2002)

/ 6-9 ≥5 ≤6 ≤20 ≤1.0 ≤0.2 ≤1.0 ≤4 ≤0.05 /

Note: The data of 1st quarter was the average value of data on Jan. 11-13, Feb. 15-17 and Mar. 7-9. The data of 2

nd quarter

was the average value of data on Apr. 10-12, May 9-11 and Jun. 6-8.

40

Total nitrogen was found above the standard concentration in both 1st and 2ndquarter.According to local environmental protection agency, it is due to the environmental background value of local sea water quality, but not because the project., which was not impacted by the ongoing projects. It also showed that Petroleum organic compound was slightly above the standard concentration level.

d. Dredged sludge

Table 22: Monitoring results of dredged sludge of Component C2 (Mar.-Jun.2016)

Monitoring spot

Time

Sulfide Cr6⁺ Pb Cd Zn Cu volatile phenol

1#

Input of Shuikou Lake

2016 1st Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

2016 2nd

Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

2#

Output of Shuikou Lake

2016 1st Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

2016 2nd

Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

3#

Shuikou Lake central area

(left)

2016 1st Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

2016 2nd

Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

4#

Shuikou Lake central area

(right)

2016 1st Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

2016 2nd

Quarter 0.005L 0.004L 0.01L 0.001L 0.02L 0.05L 0.0003L

Note: The data of 1st quarter was the average value of data on Jan. 11-13, Feb. 15-17 and Mar. 7-9. The data of 2

nd quarter

was the average value of data on Apr. 10-12, May 9-11 and Jun. 6-8.

According to Table 22, Sulfide, Cr6⁺, Pb, Cd,Zn, Cu and volatile phenol were under detection limit, which means that there were only trace concentration of those pollutants in dredges sludge.

5. Component B1 and B2: Urban Road Networkand RelatedInfrastructure for Baise City, and Longwang Bridge for Baise City Air quality

Table 23:Air quality Monitoring Data of Baise City (Jan. – Jun. 2016)

Date PM10 Class II, air quality standard (GB3095-

1996)

41

Jan. – Jul. 2016 59 ≤70

The general air quality of Baise city during January to July has reached the standard.

42

VI. PUBLIC CONSULTATION

Public consultation has been implemented by PICs during the design and construction of ongoing components as per the public consultation program developed during project preparation, as detailed in the table below.

Table24: Implementation of Public Consultation Program (by June 2016)

Organizer Approach/Times Subjects Participants Implementation Status

(Y/N/NA)

A. Project Preparation

GPMO, PICs,design institutes,EIA institutes, resettlement

plan institutes,

EPBs

EIA public opinion surveys:

once for each component

Priority, design, environmentalbenefits and impacts, social benefits and impacts, mitigationmeasures, attitudes toward project component, and suggestions

GPMO, PICs,design institutes,EIA institutes,EPBs, otherprovincial andmunicipalgovernmentstakeholders,community representatives

Y for six components

Expert panel review: once for each component

Y for six components

Socioeconomic and AP surveys

Y for six components

Public consultation meeting and

questionnaire: once for overall

project

Y for six components

Site visits: multiple times

Y for six components

B. Construction

GPMO, PICs,EMC,

IEM

Public consultation and site visits: at least

once per year

Adjusting mitigation measures if necessary, constructionimpacts, commentsand suggestions

Residents withinconstructionarea

Y for six components

For dredging at ShuikouLake,

lakeside residents will be

consulted through

community visits on a monthly

basis

Collecting public commentsand suggestionsand adjustingmitigation measures accordingly

Lakeside residents Y by C2 PIC

Expert workshop or press

conference: at least once

Comments and suggestions on mitigation measures, public opinions; adjusting mitigationmeasures accordingly

Experts from varioussectors, media

N

43

Organizer Approach/Times Subjects Participants Implementation Status

(Y/N/NA)

Public information

session: at least once per year

Adjusting mitigation measures if necessary, constructionimpacts, commentsand suggestions

Representatives of residentsand social sectors

Y for six components

Survey on resettlement:

as required per resettlement

plans

Comments and suggestions

People affected by landacquisition and resettlement

Y for six components

C、 Commissioning period

GPMO, PICs,EMC, IEM

Questionnaire:at least once in the

commission period

Operational impact on the opinions and suggestions, and recommendations for corrective action public

Residence and social representative, EPA

Y the completed component B1

and B2.

Site inspection: many times, it is according to the environmental inspection result of the project

completion

Y the completed component B1 and B2

Note: Y-Yes; N-No; NA-Not applicable.

As indicated above, the established public consultation program has been generally implemented as scheduled, except that no expert workshop or press conference has been organizedwithout identifying any major environmental issue and any major change of mitigation measures for all the ongoing components. After a recent site visit of EED experts,Baise project now running wellwithout any public comments.

44

VII. INSTITUTIONAL STRENGTHENING AND TRAINING

To strengthen the capacity of PICs in environmental management and monitoring, the training program proposed during project preparation has been implemented based on current project progress, as detailed in the table below.

Table25: Implementation of Institutional Strengthening and Training (by June 2016)

Activities Targeted

Agencies/Attendees Contents Timing

Implementation Status (Y/N/NA)

Institutional Strengthening

Institutional Strengthening

GPMO, PICs,POCs, GEPD,EPBs

Defining institutional arrangements for environmental management, monitoring, and supervision During project

preparation

Y for six components

Defining positions and responsibilities

Y for six components

Appointing and recruiting personnel

Y for six components

EMC

Recruiting and contracting EMC for internal environmental management consultancy and monitoring

Prior to project implementation

Y for six components

IEM

Recruiting and contracting an IEM for the overall project, through international competitive bidding, for the environmental management consultancy and independent external monitoring

Prior to project implementation

Y with one individual

environmental specialist

recruited for this purpose in Aug. 2013 for

the whole project.

Environmentalmanagementclauses andprotocols

PICs, POCs, EMC

Developing environmental management clauses and incorporating them into construction and operational contracts

During project preparation

Y for six components

Developing and refining environmental monitoring protocols

Y for six components

45

Activities Targeted

Agencies/Attendees Contents Timing

Implementation Status (Y/N/NA)

Developing environmental emergency response procedures

Y for six components

Training

Environmentallaws,regulations,and policies

GPMO, PICs,POCs, contractors

Environmental laws and regulations;

Environmental policies and plans;

Basic environmental management;

Environmental emergency response

Prior to project implementation

Y for six components

EMPimplementation GPMO, EMC,PICs, POCs,contractors

Responsibility and duties for projectconstruction, management and environmental protection;

Environmental protection tasks in project construction;

Key environmental protection measures during construction;

EMP improvement and corrective actions

Prior to and during project

implementation

Y for six components

Environmentalmonitoring,inspection,and reporting

PICs, POCs,EMC, contractors

Monitoring and inspection methods, data collection and processing, interpretation of data, reporting system

Environmental reporting requirements

Prior to and during project

implementation

Y for six components

46

Activities Targeted

Agencies/Attendees Contents Timing

Implementation Status (Y/N/NA)

Awareness building Road networkPOCs

Awareness building and educational activities will be carried out to promote compliance with relevant regulations regarding the road transport of toxic and hazardous substances

NA

Note: Y-Yes; N-No; NA-Not applicable. EMC = environmental management company and/or consultant, EMP = environmental management plan, EPB =environmental protection bureau at the city level, GEPD = Guangxi Environmental Protection Department, GPMO =Guangxi Project Management Office, IEM = independent environmental monitor (as part of the implementation consultancy), PIC = project implementing company, POC = project operating company.

As presented above, the proposed institutional strengthening and training program for GSCDP has been well implemented during this reporting period.

47

VIII. KEY ENVIRONMENTAL ISSUES

In terms of environmental management, the Urban Road Network and Related Municipal Infrastructure for Fangchenggang City: Most of the mitigation measures were implemented efficiently in 1#, 2#, 3# roads, and Anbujiang Bridge construction sites. It was observed that there has potential safety risk on construction site at 2# Road. Following mitigation measure was suggested: (a) all electricity facilities should be secured in closed boxes and (b) the wires should be protected by enough covers.

Chongzuo component: Urban Road Network and Related Municipal Infrastructure for Chongzuo City: No significant environmental issues were observed. To avoid potential impact on air quality, it is suggested to cover the construction materials at project sites. Shuikou Lake Environmental Improvement for Chongzuo City: Net cages have been cleared, and good wetland ecosystem has been built with project intervention. But there have potential safety issue for local residents and unclear environmental management system establishment. It is suggested protection and warning facilities be set and clear environment management system be established. Garbage at certain parts of the construction site should be cleaned and dumped in time to keep city area clean and tidy.

Baise component: Currently two subcomponents are completed and have come into the operational stage. But the monitoring based on environmental management plan in the operation stage for these two subcomponents is not completely in place. During the operation of the project, air quality monitoring was conducted based on the requirement of environmental management plan, which showed good air quality in general. Continuous monitoring on different environmental parameters should be reinforced to make sure that environmental management plan is implemented effectively.

48

IX. CONCLUSION

The environmental reports from the PICs of ongoing components during this reporting period have shown that the component EMPs developed during project preparation have been well implemented in the following aspect:

- Mitigation measures have been implemented based on component progress with satisfactory effectiveness;

- The results of environmental monitoring implemented during this reporting period for the two ongoing components (F1, F2) also show general compliance with applicable Chinese standards.For F1, the reactive phosphate content of F1 in the reporting period is, and according to the local environmental protection bureau, it is because the baseline of water quality, but not influenced by the project.

- For C1 and C2, Chongzuo Environmental Monitoring Agency monitored air quality, noise and surface water quality of C1 and C2 area. In general all the parameters were in compliance with Chinese government standards except for the concentration of total nitrogen in surface water. According to local environmental protection bureau, it is because of environmental background value of local water quality, which means it was not affected by the conduction of the project. No complaintwas received during the implement of C1 and C2 from January to June, 2016. No environmental accident occurred during this period of time.

- Both public consultation program and institutional strengthening and training program have been well implemented as scheduled so far.

- The results of environmental monitoring implemented during this reporting period for the two ongoing components (B1, B2) also show general compliance with applicable Chinese standards.

For next step, based on current achievements, the focus should be tracking the environmental mitigation measures. Shuikou Lake Environmental Improvement for Chongzuo City: Required actions were identified as following: (i) Chongzuo PMO should collect information about the environmental monitoring equipment installation and maintenance under the loan, responsibilities should be clearly setup for each stakeholders; (ii) warning and information boards should be set to avoid unauthorized fishing and swimming activities by local residents to ensure their safety; and (iii) During operational period, Jiangnan Street Committee will be responsible for the maintenance of Shuikou Lake. Clearly operational guidance should be prepared on environment management.