environmental monitoring report · yunnan pu’er regional integrated road network development...

186
Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. 6 th Semestral Report Project Number: 46040-003 December 2018 PRC: Yunnan Pu’er Regional Integrated Road Network Development Project Prepared by Pu’er Municipal Transport Bureau for the Yunnan Pu’er Municipal Government and the Asian Development Bank

Upload: others

Post on 03-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Environmental Monitoring Report

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily

represent those of ADB’s Board of Director, Management or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference

to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make

any judgments as to the legal or other status of any territory or area.

6th Semestral Report Project Number: 46040-003 December 2018

PRC: Yunnan Pu’er Regional Integrated Road Network Development Project

Prepared by Pu’er Municipal Transport Bureau for the Yunnan Pu’er Municipal Government and the Asian Development Bank

Page 2: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

People’s Republic of China Yunnan Pu’er Regional Integrated Road NetworkDevelopment Project

ADB LOAN 3217‐PRC

Environmental Monitoring Report #6 Semi-annual Report

For The Period Ending

31 December 2018

Pu’er Municipal Government

Pu’er Municipal Transport Bureau

Page 3: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief
Page 4: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

5th Semi-annual Environmental Monitoring Report

ABBREVIATIONS ADB Asian Development Bank CO2 Carbon Dioxide CODCr Chemical Oxygen Demand DO Dissolved Oxygen dB(A) Unit of the equivalent continuous sound level A(Decibel) EA Executing Agency EARF Environmental Assessment And Review Framework EEMA External Environmental Monitoring Agency EHS Environmental, Health & Safety EIA Environmental Impact Assessment EIR Environmental Impact Report EMDP Ethnic Minority Development Plan EMP Environmental Management Plan FSR Feasibility Study Report GRM Grievance Redress Mechanism GTRI Guangxi Transportation Research Institute ha Hectare IA Implementing Agency ICB International Competitive Bidding km Kilometre L Litre LIEC Loan Implementation Environmental Consultant m3 Cubic metre mg Milligrame MMR Menglian-Menga Road MTC Meng’A Material Transit Centre NCB National Competitive Bidding NJLR Ning’er-Jiangcheng-Longfu Road NO2 Nitrogen Dioxide O&M Operation And Maintenance PEMS Pu’Er Environmental Monitoring Station PEPB Pu’Er Environmental Protection Bureau PMG Pu’Er Municipal Government PMTB Pu’Er Municipal Transport Bureau PPMO Pu’Er Project Management Office PRC Project Completion Report PRC People’S Republic Of China PS Project Supervisor PWRB Pu’Er Water Resources Bureau RP Resettlement Plan SO2 Sulfur Dioxide SS Suspended Solid SWCR Soil And Water Conservation Repor TPH Total Petroleum Hydrocarbons TSP Total Suspended Particle YEPB Yunnan Environmental Protection Bureau YNFY Yunnan Fangyuan Technology Co., Ltd.

Page 5: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

5th Semi-annual Environmental Monitoring Report

Map 1 TheLocationg of Yunnan Pu’er Regional Integrated Road Network Development Project

Page 6: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

5th Semi-annual Environmental Monitoring Report

CONTENTS

I. INTRODUCTION ............................................................................................................................. 1

A. Report Purpose and Rationale ..................................................................................................... 1 B. Project Objective and Components ............................................................................................. 1 C. Project Implementation Progress ................................................................................................. 3

II. INSTITUTIONAL ORGANISATION AND RESPONSIBILITIES FOR EMP IMPLEMENTATION ... 4

A. Institutional responsibilities .......................................................................................................... 4 B. Incorporation of Environmental Requirements into Project Contractual Arrangements .............. 7

III. COMPLIANCE WITH ENVIRONMENTAL PROTECTION TERMS OF AGREEMENTS CONCERNING THE PROJECT .................................................................................................... 10

IV. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD ....................................................................................................................11

V. SUMMARY OF ENVIRONMENTAL MONITORING ...................................................................... 27

A. Monitoring Plan and Responsibilities ......................................................................................... 27 B. Environmental Quality Objectives and Sampling Analysis Method ........................................... 29 C. Environmental Monitoring Results ............................................................................................. 30 D. Monitoring Result of Soil Erosion Protection ............................................................................. 45

VI. PUBLIC CONSULTATION ........................................................................................................... 165

VII. INSTITUTIONAL STRENGTHENING AND TRAINING .............................................................. 166

A. Institutional strengthening ........................................................................................................ 166 B. Training .................................................................................................................................... 166

VIII. KEY ENVIRONMENTAL ISSUES ............................................................................................... 169

A. Key Issues Identified ................................................................................................................ 169 B. Solutions and Actions ............................................................................................................... 170

IX. APPENDICES .............................................................................................................................. 171

Appendix 1 Environmental Impact Mitigation and Monitoring Structure Diagram ........................ 172 Appendix 2 The Qualifications of the External Environmental Monitoring Agencies .................... 173 Appendix 3 Proposed Grievance Redress Mechanism ................................................................ 178 Appendix 4 Responsible Person and Complaints Hotline of GRM Access Points ....................... 179 Appendix 5 Environmental Management Training Record ........................................................... 180

Page 7: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

1/178 6th Semi-annual Environmental Monitoring Report

I. INTRODUCTION

A. Report Purpose and Rationale

The purpose of the Environmental Monitoring Report(EMR) is to document the environmental management activities and compliance with the EMP.This report is 6th semi-annual EMR for the period from July to December, 2018. As 6th semi-annual EMR, it demonstrates compliance with the EMP for the design, bidding, and construction preparation stages.

The EMRcovers: (i) Implementation progress of the project; (ii) Implementation status of the Environmental Management Plan(EMP) and layout of the environmental supervisory institutions; (iii) Implementation of measures to lessen environmental impacts of the project; (iv) Findings of environmental monitoring; (v) Public consultation; (vi) Building and training of institutions; (vii) Major environmental problems during the current phase, countermeasures and suggestions.

The EMR is prepared by the External Environmental Monitoring Agency (Guangxi Transportation Research Institute, Yunnan Fangyuan Science and Technology Co., Ltd, Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd, Kunming Longhui Engineering Design Consulting Co., Ltd). It based on the environmental supervision reports, the external environmental monitoring reports and theSoil Erosion Protection monitoring reports, submitted by the External Environmental Monitoring Agencies. Some information provided by the PPMO and other management departments. The field survey carried out by the PPMO.

B. Project Objective and Components

B-1.Project Scope and Objectives

The principal objective of the project is to improve rural transport situation in Pu’er and regional road network, and to strengthen regional integration of Pu’er and boarder areas of neighboring countries the trade development among them. The project is designed to accomplish these objectives through three discrete components.

Output 1: Regional roads development. This output comprises: (i) upgrading and new construction for a total of 228.078 km of Class III highway between Ning’er–Jiangcheng–Longfu; (ii) upgrading and new construction for the 44.739 km Menglian to Meng’a section of the existing Lancang–Menglian–Meng’a Class III / IV border road to a predominantly Class II road; (iii) the development of trade facilities at the MTC; and (iv) improving the safety of the roads by introducing safety measures determined by the ChinaRAP road safety design decision making tool.

Output 2: Rural access improvements. This output comprises: (i) the upgrading of about 600 km of village earthen or gravel roads to concrete Class IV standard; (ii) spot improvements on up to 1,200 km (or CNY24 million investment) of connecting lower level village roads; (iii) introduction of five new village bus service routes on a pilot basis, and (iv) a gender focused rural road maintenance program. The primary objective of the roads is to provide all weather access to administrative villages or to link with higher level roads.

Output 3: Institutional development. This output will address the limited implementation capacity of PMG. A project management consultant will be recruited to assist the PMG to implement and monitor the project in accordance with ADB procedures. The project will finance a 3-year training program ($400,000 for 40 person-months) for international and domestic training in financial and project management, road maintenance engineering, road maintenance practices, road safety, environmental management, social safeguards management, and wildlife trafficking and human and drugs trafficking enforcement.

Page 8: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

2/178 6th Semi-annual Environmental Monitoring Report

B-2.Engineering Brief

Output 1: Regional Roads

Menglian-Meng’a Road:The Road starts from Menglian at K54+900,goes through Mengma, ends at Meng’a Port, chainage of K99+744.3. There are three broken chainages, so the actual length is 44.7km. The technical standard is highway Class II with design speed of 60 km/h. The standard width is 12m from K54+900 to K95+594.8, only at the end section from K95+585.04 to K99+744.29, ending at Meng’a Port the road width of 23m applies.

Ning’er–Jiangcheng–Longfu Road:The Road starts at Ningjing Highway K3+800, north side of Ning’er Township, Ning’er County, ends at Jiangcheng No.3 China-Vietnam border marker, 228.0km in length. The technical standard is highway Class III, with the design speed of 40 km/h, the width of 8.5m from the start point to Laozhaozhai, 25.136km in length, and the design speed of 30 km/h, the width of 7.5m from the Laozhaozhai to the end point, 202.9km in length (12m in width for the section of K231+706.30~K234+069.52).

Output 2: Rural Access Improvements

The rural access improvement plan is to provide all-weather Class IV, thirty-one paved rural roads, 600km in total length in seven counties in Pu’er municipality, and provide spot improvements on the village roads, 1200km in total length linking the remote villages with these rural roads. The latest adjustment has basically confirmed thatthirty rural roads, 537.12km in total length will receive the improvements, including three rural roads, 73.7km in total length in Mojiang County, two roads, 70.75km in Jinggu, seven roads, 126.94km in Zhenyuan, two roads, 56.3km in Jiangcheng, five roads, 59.65km in Lancang, six roads, 66.3km in Ximeng and five roads, 73.48km in Jingdong. Most of these rural roads will be paved with cement concrete. The site investigations on the village roads for the spot improvements will be conducted late; the scope will be finalized accordingly.

Table 1-1:The Engineering Features

Engineering Name Menglian-Meng’a Road

Ning’er–Jiangcheng–Longfu Road

Rural Access Improvements

Total Length 44.7km 228.0km 537.12km

Road Class: Class Ⅱ- 2 lanes,

undivided; uncontrolled access

Class Ⅲ - 2 lanes, undivided; uncontrolled

access

Class Ⅱ- 1 lane; uncontrolled access

Design Speed 60km/h 30、40km/h 20km/h Loading Class 2 2 2

Earthquake Zone: IX VII,VIII Ⅷ、IX

Design Flood large bridge, 100 years, other 50

years; roadway 50 years

large and mediumbridge, 50 years, other 25 years; roadway

25 years

small bridge,50years

Subgrade Width integrated 2 lanes 12 m, 23 m

integrated 2 lanes 7.5 m, 8.5 m 4.5~6.5m

Land area occupied 121.384 ha 147.949 ha — Terrain mountain area mountain area mountain area

Horizontal alignment

Curve 90 1673 — Minimum

radius 162.97m 15m 15m

Curve length 59.67% 60.62% —

Vertical alignment

Steepest gradient 6% 12% 9%

Minimum crest 2,200 m crest 300m —

Page 9: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

3/178 6th Semi-annual Environmental Monitoring Report

curve radius sag 2,874.341 m sag 300m

C. Project Implementation Progress

Output 1: Regional Roads

Menglian - Meng’a Road:The two contractors started mobilization in March 2016, the constructions began work in the second quarter. Due to the delay of the construction works for two contractors, the Pu’er municipal transport bureau and two contractors made an agreement on the extension of the construction contract. The revised contract completion date will be 28th April 2019. The progress to date of still less than expected with 89% of contract time passed on both contracts and CNY319million or only 70% of the estimated final value of the work completed. The bidding document of the MM-Sub1 was approved by the ADB on the 12 September 2018. The letter of bidding was advertised on 18 September 2018. The bidding evaluation report was approved and the PCSS number was issue out by the ADB on the 24 December 2018.The contract was signed on the 28 December 2018. The performance of security was provided to the employer on the 17 January 2019.Construction of the MM-Pavement works is expected to commence in the first quarter of 2019.

Ning'er - Jiangcheng - Longfu Road:The works commenced in October 2016 except for package NJL-Sub5 which commenced in December. Due to the delay of the construction works for ten contractors, the Pu’er municipal transport bureau and ten contractors made an agreement on the extension of the construction contract. The revised contract completion date for ten contracts are varied based on the progress of each contract. With effectively average of 89% of time passed the accumulative progress on all ten contracts stands at CNY324million or 36%. NJL-Sub1 and NJL-Sub10 show greatest progress at respectively 62% and 63% while NJL-Sub5 is still lagging at 12%. All others packages show progress between 19 and 38%. For all packages, but NJL-Sub1 and NJLSub10, there is few chance that lost time can be made up during the remaining contract duration. The contractor of NJL-Sub8 is envisaged to be terminated due to lack of progress, or site inactivity, despite frequent warnings from Project Supervisor. The bidding documents of the pavements works for Ning’er – Jiangcheng – Longfu Road will submitted to ADB in the first quarter of the 2019.

Output 2: Rural Access Improvements

As of the end of the reporting period all of the contracts have been tendered. All the construction works have been commenced by the end of the period. Due to the slight delay of the construction works for 15 contractors, each county transport bureau and contractors made an agreement on the extension of the construction contract. The average value of works completion is 93%. All packages show between 78 and 99% progress.

Page 10: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

4/178 6th Semi-annual Environmental Monitoring Report

II. INSTITUTIONAL ORGANISATION AND RESPONSIBILITIES FOR EMP IMPLEMENTATION

A. Institutional responsibilities

The Pu’er Municipal Government is the Executing Agency (EA) who has overall responsibility for project implementation. The EA has established the Pu’er Project Management Office (PPMO), which has been delegated overall responsibility for day-to-day management of the project, supervising the implementation of the EMP, coordinating the project environmental grievance redress mechanism and reporting to ADB.

The Pu’er Municipal Transport Bureau(PMTB) is the Implementing Agency (IA) responsible for implementing project components, administering and monitoring contractors and suppliers, construction supervision, quality control and EMP implementation. The IA will prepare bid documents and ensure that bids are responsive to environmental requirements and budgets and contracts include environmental clauses from the EIA, and the full EMP.

The PPMO and the IA have both assigned environmental staff to manage, coordinate, oversee and verify EMP implementation.

Mitigation measures (including, road alignment avoiding sensitive or protected areas) have been built into the detailed design by theengineeing design consultants.

PMTB has contracted the Yunnan Fangyuan Science and Technology Co., Ltd, Guangxi Transportation Research Institute, Kunming Longhui Engineering Design Consulting Co., Ltd, and Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd, who shall carry out environmental monitoring at the construction stage according to the EMP .These four agencies are the External Environmental Monitoring Agency(EEMA).

PMTB has contracted Yunnan Shengmeng Engineering Consulting Co., Ltd, Shandong Ping’an Road and Bridge Engineering Consulting Co., Ltd, and Yunnan Yuantu Engineering Supervision Co., Ltd, to supervise the construction of the Menglian-Meng’a Road and the Ning’er-Jiangcheng-Longfu Road, supervise the environment simultaneously during engineering supervision, and submit the environmental supervision report on monthly basis.

A Loan Implementation Environmental Consultant (LIEC) is included through the project Management Consulting services. They will assist the PPMO and the IA with EMP implementation including environmental training and reporting. The semi-annual EMRs will be preared by the External Environmental Monitoring Agency.

Contractors will be responsible for implementing the mitigation measures during construction under the supervision of PPMO through the Supervision Office, and LIEC.

In their bids, contractors are required to respond to the environmental management and monitoring requirements defined in the EMP. Each contractor is required to develop site specific EMPs and will assign a person responsible for environment, health and safety.

See the Appendix 1 for the environmental management institutions of the project.

Page 11: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

5/178 6th Semi-annual Environmental Monitoring Report

Table 2-1TheCompliance Status ofInstitutional Responsibilities for Eenvironmental Management

Responsible Entity Project Stage Environmental Responsibility Compliance

with EMP PMG All Stages The Executing Agency (EA) for the project

responsible for overall implementation and compliance with loan assurances and the EMP.

Being complied with

PPMO Project Preparation

• Engage design institutes on FSR, EIR, RP and SWCR

• Complied with

Engineering Detailed Design

• Engage design institutes • Review updated EMP, confirm that mitigation

measures have been included in engineering detail design

• Complied with

Tendering & Pre-construction

• Appoint at least one environmental specialist on staff

• Complied with

• Incorporate EIA/EMP clauses in tender documents and contracts

• Complied with

• Prepare EIAs for replacement rural roads according to the EARF and submit to ADB

• Being complied with

Construction • Supervise the effective implementation of the EMP

• Being complied with

• Establish and operate the project public complaint s center and coordinate the project environment GRM.

• Being complied with

• Prepare quarterly project progress reports and semi-annual environment monitoring reports and submit them to ADB

• Being complied with

• Conduct information disclosure and public consultation

• Being complied with

• Inspect implementation of mitigation measures. • Being complied with

PMTB Tendering & Pre-construction

• Manage the procurement process • Complied with • Incorporate EIA/EMP clauses in tender

documents and contracts • Complied with

• Appoint at least one environmental specialist on staff

• Complied with

• Engage LIEC as part of the Loan Implementation Project Management Consulting Services

• Complied with

• Engage EEMA for environmental monitoring • Complied with • Engage EEMA for independent compliance

monitoring • Complied with

Construction • Supervise contractors and ensure compliance with the EMP

• Being complied with

• Approve method statements • Being complied with

• Coordinate construction supervision and quality control

• Being complied with

• Coordinate environmental monitoring according to the environmental monitoring program in the approved EMP

• Being complied with

• Act as a local entry point for the project GRM • Being complied with

• Submit quarterly monitoring results to PPMO, PEPB.

• Being complied with

Page 12: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

6/178 6th Semi-annual Environmental Monitoring Report

Responsible Entity Project Stage Environmental Responsibility Compliance

with EMP Design institutes

Project Preparation

• Prepare project FSRs, EIRs, RPs, SWCRs • Complied with • Conduct public consultation • Complied with

Engineering Detailed Design

• Incorporate mitigation measures defined in the EMP into engineering detail designs

• Complied with

• Update the EMP in cooperation with the LIEC • Being complied with

YEPD Project Preparation

• Review and approve the project EIRs • Complied with

PEPB/PWRB

Construction • Conduct inspections of construction sites and activities to monitor compliance with PRC regulations and standards

• Being complied with

PPTA consultant

Project Preparation

• Provide technical assistance • Complied with • Review EIRs • Complied with • Prepare EIA report and EMP • Complied with

LIEC Engineering Detailed Design

• Review updated EMP, confirm that mitigation measures have been included in engineering detailed design

• Complied with

Tendering & Pre-construction

• Review bidding documents to ensure that the EIA/EMP clauses are incorporated

• Complied with

• Confirm project’s readiness in respect of environmental management.

• Complied with

Construction • Advise on mitigation measures • Being complied with

• Provide technical support to PPMO and PMTB for environmental management

• Being complied with

• Conduct environmental training • Being complied with

• Conduct semi-annual EMP compliance review • Being complied with

• Support PPMO in preparing quarterly project progress reports and semi-annual environmental monitoring reports.

• Being complied with

• Review domestic environmental acceptance reports

• Being complied with

• Prepare environmental completion report. • To be complied with

Contractors

Tendering & Pre-construction

• Ensure sufficient funding and human resources for proper and timely implementation of required mitigation and monitoring measures in the EMP throughout the construction phase

• Complied with

Construction • Appoint an environment, health and safety (EHS) officer to oversee EMP implementation related to environmental, occupational health and safety on construction site

• Complied with

• Ensure health and safety • Being complied with

• Implement mitigation measures • Being complied with

• Prepare method statements on the implementation of pollution control and mitigation measures listed in Table 2 of EMP, and submit to PMTB and EEMA for review

• Being complied with

• Act as a local entry point for the project GRM • Being complied with

Page 13: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

7/178 6th Semi-annual Environmental Monitoring Report

Responsible Entity Project Stage Environmental Responsibility Compliance

with EMP EEMA

Construction

• Undertake environmental monitoring according to the environmental monitoring program in the approved EMP (contracted by PMTB)

• Being complied with

• Report monitoring data to PMTB monthly • Being complied with

• Conduct independent verification of project’s environment performance and compliance with the EMP (contracted by PMTB)

• Being complied with

• Review monthly monitoring data submitted and conduct compliance checking against applicable environmental standards

• Being complied with

• Provide advice to contractors for resolving on-site environmental problems when monitoring data show non-compliance.

• Being complied with

• Submit quarterly compliance monitoring results to PPMO, PMTB and PEPB

• Being complied with

B. Incorporation of Environmental Requirements into Project Contractual Arrangements

The main items of the EIA and all the contents of the EMP have been included in the bidding documents and construction contracts.

B-1. Output 1: Regional Roads

The environmental engineering is clearly defined as one of the main contents in the bidding documents for regional roads and all the requirements concerning environmental protection are included in the special terms of related contracts:

Menglian-Meng’a Road:

Table2-2: Environmental Requirements of Menglian-Meng’a Road Construction Contract

Terms Environmental Requirements 4.18 Environmental Protection

The Contractor shall execute environmental monitoring procedures and mitigation measures to minimize adverse impacts of the project to the environment. The aforesaid mitigation measures shall cover the design, construction and management of the project and the maintenance and operation of equipments used here, and shall be implemented strictly.

The Contractor shall guarantee that the emissions, disposed items and sewage generated during the construction of the project will not go beyond related limits defined by related laws and regulations. (1) For the purpose of protecting health of the construction workers, the Contractor

shall, as for the control of noises generated by construction machinery and transport vehicles, observe the Noise Pollution Control Law of the People’s Republic of China and the Emission Standard of Environmental Noise within the Boundary of Construction Site (GB12523-2011) and arrange the working machinery rationally so that to minimize the duration of exposure of workers in the intensive environmental noises, or arrange periodic intensive noise work, or provide protective devices (like safety shoes and helmets, goggles, breathing masks or take other effective measures, which including definitely, shorter work hours. Furthermore, importance shall be paid to maintain the machinery so that to minimize possible noises. For the purpose of protecting residents nearby, no night construction activities shall be arranged, or earlier approval from the residents shall be obtained or use low-noise machinery if night construction is required. Loud-noise equipments, such as the stone breaker and the concrete mixer, shall be kept at least 1km away from the noise sensitive objects.

Page 14: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

8/178 6th Semi-annual Environmental Monitoring Report

Terms Environmental Requirements (2) Pollutants during road construction mainly come from the lime-soil dust generated

from the running and transportation of construction vehicles and machines. In this regard, effective measures shall be taken to mitigate air pollution on the construction site so that to protect health of the workers. These measures include: a. Choose sealed dustproof electronic equipments; b. Water the machines for channel building and the concrete mixing plants at

regular intervals to lower the dust; c. For by-stage works, certain moisture shall be kept to avoid dust; d. Treat the sludge in the drilled pile with correct method when erecting bridges

so that to prevent directly dumping the sludge into the rivers or farmlands; e. Spoils can be dumped only at approved site.

(3) Reliable measures shall be taken to guarantee unblocked traffic, water supply for domestic use and irrigation, power supply, communication, and normal living and production conditions of nearby urban and rural resident.

(4) The preparatory area for construction, work shed, storing area for fuel and other materials, and the fueling and maintenance areas shall be at least 500m away from the water source.

(5) The Contractor shall comply with related national and local environmental laws and regulations to A) Set up an operating mechanism to control environmental impacts; B) Adopt and implement the environmental supervision, EIA and EMP. The Contract shall report the implementation of such environmental supervision, EIA and EMP to the Owner on quarterly or half-yearly basis. The Contractor shall comply with related national, provincial and local

environmental laws and regulations and the EMP. In addition, the Contractor shall: (1) Set up the environmental impact control system; (2) include in the EIA and the EMP the measures to control and mitigate environmental impacts; (3) Distribute budget according to related requirements so that to guarantee implementation of related measures. The Contractor is required to report to the Owner the implementation of these measures on half-yearly basis.

What’s more, the Contractor shall comply with (i) The measures and requirements proposed in the EIA and the EMP, see the Appendix [2] for details; (ii) The Employer shall be always ready to monitor the implementation of the EMP and carry out all the correction or prevention presented in the security monitoring report.

The Contractor shall follow these measures, requirements and actions to distribute the cost.

Work Contents MM-Sub1: Roadbed, bridge and culverts, greening and environmental protection, etc; MM-Sub2: Roadbed, bridge and culverts, greening and environmental protection, etc;

Ning’er-Jiangcheng-Longfu Road:

Table2-3: Environmental Requirements of Ning’er-Jiangcheng-Longfu Road Construction Contract

Terms Environmental Requirements General terms 1.1 (36)

Work contents: NJL-Sub1: Roadbed, bridge and culverts, greening and environmental protection, etc ; NJL-Sub2: Roadbed, bridge and culverts, greening and environmental protection, etc; NJL-Sub3: Roadbed, bridge and culverts, greening and environmental protection, etc; NJL-Sub4: Roadbed, bridge and culverts, greening and environmental protection, etc; NJL-Sub5: Roadbed, bridge and culverts, greening and environmental protection, etc;

General terms 2.3 (9)

Following documents are part of the contract: 1. Resettlement plan (RP); 2. Environmental Impact Assessment (EIA);

Page 15: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

9/178 6th Semi-annual Environmental Monitoring Report

Terms Environmental Requirements 3. Environmental Management Plan (EMP); 4. Gender Action Plan (GAP); 5. Ethnic Minority Development Plan(EMDP);

Special terms 65

The Contractor shall comply with the national, provincial and local environmental laws and regulations; The Contractor shall: (a) Set up a running system for environmental impact management; (b) Take monitoring and mitigation measures over the EIA, EMP, RP and EMDP

(focus on the environmental protection, the non-voluntary resettlement guarantee measures and indigenous people guarantee, during construction);

(c) Comply with all the corrective and preventive measures, including: (i) the guarantee supervision report; or (ii) follow-up agreements between the Asian Development Bank and the People’s Government of Pu’er;

(d) Take all the necessary measures to minimize damage to religious trees and religious remains during construction;

(e) Allcate budget for guarantee the implementation of all the above measures. The Contractor shall fulfill related responsibilities concerning the non-voluntary resettlement guarantee before settling the final payment. The Contractor shall submit to the IA reports on the implementation of all the above measures on quarterly basis.

B-2. Output 2: Rural Roads

As of the end of the reporting period all of the contracts have been tendered, and the environmental protection requirements are incorporated into the special terms of related contracts.

Page 16: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

10/178 6th Semi-annual Environmental Monitoring Report

III. COMPLIANCE WITH ENVIRONMENTAL PROTECTION TERMS OF AGREEMENTS CONCERNING THE PROJECT

Up to now, the EA and IA of the project have fully implemented or are implementing all the due environmental terms defined in the loan agreement, and have get well prepared to implement all the undue environmental terms. See the following table for compliance with environmental terms defined in Appendix B of the Loan Agreement.

Table3-1: Compliance with Environmental Protection Terms of Agreements

Environmental Relevant Covenant Status of Compliance 2. PMG shall ensure or cause to ensure that the preparation, design,construction implementation, operation and decommissioning of the project and all project facilities comply with (a) all applicable laws and regulations of the Borrower relating toenvironment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the EIA, the EMP, and any corrective or preventative actions (i) set forth in a Safeguards Monitoring Report , or (ii) which are subsequently agreed between ADB and PMG.

The executing institution and the implementing institution have strictly taken measures and observed requirements defined in the EIA and the EMP. • Being complied with.

3. PMG shall ensure that permanent and temporary land take for the MenglianMeng'a Road shall avoid intact woodlands at road sections as specified and agreed in the EMP.

Design and current construction of the Menglian-Meng’a Road have avoided the whole forest land along the road. • Being complied with.

4. PMG shall ensure CO2 emissions monitoring and annual reporting to ADB during the operation of the Project Rural Roads and Project Regional Roads up to year 2020, by conducting traffic counts annually and calculating CO2 emissions, for comparison with ADB's CO2 emission threshold of 100,000 tons annually for all the project roads combined.

• To be complied during operation

5. PMG shall ensure that the design of the project roads takes into consideration climate change adaptation recommendations from the ADB funded climate change assessment study.

• Complied with.

6. PMG shall ensure that the road section as specified and agreed in the EMP shall not traverse through Protection Zones 1 and 2 of the Wenquan Reservoir.

The location of Wenquanhe Reservoir have been changed. The section K25+200~K45+200 of Ning’er- Jiangcheng-Longfu Road don’t cut through the runoff area of Wenquanhe Reservoir. This section don’t need to be redesigned. • Complied with.

7. PMG shall ensure that there is no tree felling and siting of asphalt mixing and concrete batching station within the road section as specified and agreed in the EMP during its construction.

Up to now, the asphalt mixing and concrete batching stations have been located on the grassland and cropland. There is no tree felling. • Being complied with.

8. PMG shall ensure that the protected tree species at locations along the Ning'er-Longfu Road as specified under the EMP shall be marked, tagged and fenced off before commencement of the construction

• The contractors of Ning'er-Longfu Roadare marking and fencing off the protected tree species.

• Being complied with; 9.PMG shall ensure that noise mitigation measures are implemented. Such measures shall include road side noise barriers and provision of double-glazed windows at locations specified in the approved domestic Environmental Impact Assessment for the Menglian-Meng'a Road and the Ning'er-Longfu Road.

The corresponding noise reducing measures will be included in the engineering design; • To be complied at the late stage of

construction.

Page 17: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

11/178 6th Semi-annual Environmental Monitoring Report

IV. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD

Investigation is made on changes in the engineering contents during the current report period and results are as follows:

Adjustments have been made to 28 line positions along the Menglian-Meng’a Road, increasing the earthwork by 43,500m3 and the requisitioned forest land by 5.2474ha. The change of Menglian-Meng’a Road has been approved by Pu’Er Development and Reform Bureau(Document No-普发改基础【2016】361号),this change was evaluated comprehensively by experts organized by Pu’er Municipal Transport Bureau. The earthwork was increased because some section of the road was extended based on the topography, and because of the unexpected landslide happened during the heavy rainy season.

According to the survey,The location of Wenquanhe Reservoir have been changed. The section K25+200~K45+200 of Ning’er-Jiangcheng-Longfu Road don’t cut through the runoff area of Wenquanhe Reservoir. This section don’t need to be redesigned.

A few sections of Menglian-Meng’a Road and Ning’er-Jiangcheng-Longfu Road have been adjusted by unilateral vibration based on the original line positions. The stake number of sensitive points have been changed, and some sensitive points need to increase or decrease.Because there are security risks for the downstream residents, the spoil disposal area (K185+300) in Contract Section 9 have been changed to the work zone of highway maintenance. The EMP will be updated.

The implementation status of measures to mitigate environmental impacts of the project up to now is listed below according to the EMP. During the current report period, measures to be implemented to mitigate the environmental impacts have been implemented.

Page 18: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

12/178 6th Semi-annual Environmental Monitoring Report

Table4-1: Implementation Status of Measures to Mitigate Potential Environmental Impacts

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

A. Potential environmental impacts and countermeasures existing in and applicable to the Ning’er-Jiangcheng-Longfu Road, Menglian-Meng’a Road and rural roads The Design Stage

Soil resources

Loss of land and topsoil and increased risk of erosion

➢ Minimize permanent and temporary land take for both highways, especially cultivated land and basic farmland.

➢ Retain/incorporate landscape features of interest in design. ➢ Optimize balance between cut and fill and avoid deep cuts

and high embankments to minimize earthworks. ➢ Maximize reuse of spoil within the construction or adjacent

construction works. ➢ Agree borrow and spoil disposal sites, management and

rehabilitation plan with PEPB if these sites are different from those specified in the Soil and Water Conservation Report.

➢ Remove and store topsoil (10-30cm) for restoration works prior to main earthworks.

➢ Specify landscape species that serve a specific bioengineering function, are in keeping with natural habitats and landscape and of local provenance.

➢ Design appropriate retention and drainage systems for slopes to reduce soil erosion.

Design Institute

PPMO; PMTB

The dedicated Design Proposal for Water and Soil Conservation is prepared and this proposal will be followed for engineering construction here. ➢ Complied with

Extreme weather events due to climate change

Road surface cracking due to extreme hot or cold weather, landslide and flooding due to torrential rainfall

➢ Consider potential impacts from extreme weather events due to climate change in designing road subgrade, pavement, road-side slopes, drainage system, bridges and culverts.

➢ Adopt appropriate protective measures such as vegetation cover, geotextiles, settling basins, permeable paving, infiltration ditches, stepped slopes, riprap, crib walls, retaining walls and intercepting ditches to reduce the speed of surface run-off.

Design Institute

PPMO; PMTB

Potential impacts from extreme weather events are taken into consideration during the design stage. See the designed flood frequency set forth in Table 1-1 herein. ➢ Complied with

Water quality

Bridge construction across water

➢ All construction staging areas, construction camps, fuel and materials storage, re-fuelling and maintenance areas to be located at least 500m from watercourses.

Design Institute

PPMO; PMTB

All the designed interim facilities during construction stage of the project are far away from the surface

Page 19: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

13/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

bodies ➢ Design of these construction staging areas and construction camps must ensure proper collection and treatment of wastewater and site runoff.

water; sewage collection and treatment facilities are designed for all the construction areas and living quarters. ➢ Complied with

Health and safety

Promotion of pedestrian safety, protection of vulnerable road users

➢ Design must ensure public health and safety. ➢ Design must ensure safety of pedestrians and agricultural

traffic. ➢ Adopt universal design principles for where appropriate.

Design Institute

PPMO; PMTB

Dedicated public health and safety design are made during design of the project ➢ Complied with

Air emissions

Construction transport emissions

Specify local materials from licensed providers that minimize transport distance.

Design Institute

PPMO; PMTB

Most of materials used for construction of the project are purchased from local markets according to the principle of “purchase nearby”; ➢ Complied with

GHG emissions

Energy efficiency

Consider energy efficient machinery and operational equipment Design Institute

PPMO; PMTB

All the machines and equipments used for the project satisfy related energy efficiency standard of China. ➢ Complied with

Pre-construction Stage Institutional strengthening

Lack of environment management capacity within PPMO

➢ Appoint qualified environment specialist to PPMO staff. ➢ Include LIEC in loan implementation project management

consulting services. ➢ LIEC to conduct environment management training for

PPMO staff and environmental specialist.

PPMO, LIEC, PEPB

ADB PPMO has appointed the environment specialist and the LIEC. ➢ Being complied with

Lack of environment management and monitoring capacity within PMTB

➢ Appoint qualified environmental specialist to PMTB staff. ➢ Contract EEMA to conduct environment monitoring ➢ Contract qualified EEMA to conduct external compliance

monitoring and verification of EMP implementation ➢ LIEC to conduct environment management training for PMTB

staff and their environmental specialist.

PMTB, LIEC, PEPB

PPMO, ADB

PMTB has appointed the environment specialist and signed a contract with the external environmental monitoring institutions to carry out legal compliance supervision for environmental monitoring and the EM. The LIEC hasn’t organized related training activities yet.

Page 20: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

14/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

➢ Being complied with EMP update

- ➢ Review mitigation measures defined in this EMP and update as required to reflect detailed design.

➢ Submit to ADB/PPMO for approval and disclose updated EMP on ADB website.

➢ Prepare a revised environmental compliance monitoring plan as required to meet the environmental requirements in the updated EIA and EMP.

PMTB, LIEC

PPMO, ADB

Reviewing shows that the EMP requires no upgrading now. ➢ Complied with

EIA for replacement rural roads

⚫ Prepare EIA (including EMP) for replacement rural roads according to the EARF and submit to ADB

PPMO ADB The EIA for replacement rural roads has been approved.It will be submitted to the ADB. ➢ Being complied with

Air quality Dust (TSP) impact to sensitive receptors

Put into tender documents dust suppression measures: ➢ Frequent watering of unpaved areas, backfill areas and haul

roads to suppress dust; ➢ Erect hoarding around dusty activities to contain emissions; ➢ Manage stockpile areas with frequent watering or covering

with tarpaulin; ➢ Minimize the storage time of construction and demolition

wastes on site by regularly removing them off site; ➢ Do not overload trucks when transporting earth materials to

avoid spilling dusty materials onto public roads; ➢ Equip trucks for transporting earth materials with covers or

tarpaulin to cover up the earthy materials during transport; ➢ Install wheel washing equipment or conduct wheel washing

manually at each exit of each works area to prevent trucks from carrying muddy or dusty substance onto public roads;

➢ Immediately cleanup all muddy or dusty materials on public roads outside the exits of the works areas;

➢ Sensibly plan the transport routes and time to avoid busy traffic and heavily populated areas when transporting earthy materials; and

➢ Immediately plant vegetation in all temporary land take areas upon completion of construction to prevent dust and soil erosion.

Design Institute

PPMO; PMTB

Some measures (see the special term 4.18) in the EMP are included in the tender documents for the Menglian-Meng’a Road; no detailed measures are included in the tender documents for the Ning’er-Jiangcheng-Longfu Road but the EIA and the EMP are included are part of the contract (General term 2.3 (9)). ➢ Being complied with

Page 21: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

15/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

Fumes and particulate matter from asphalt mixing plant and concrete batching plant

Put into tender documents that ⚫ These plants must be enclosed and equipped with bag

house filter or similar air pollution control equipment. ⚫ Locate asphalt mixing plants and concrete batching plants

at least 300m downwind from residential areas and other sensitive receptors.

Design Institute

PPMO; PMTB

Noise Power mechanical equipment noise impact to sensitive receptors

Put into tender documents the following noise mitigation measures: ➢ Use quiet equipment; ➢ Adopt good O&M of machinery; ➢ Use temporary hoardings or noise barriers to shield off noise

sources; ➢ Avoid nighttime construction between 2200 and 0600 hours; ➢ If nighttime construction needed, consult nearby residents

beforehand for their consensus; ➢ If nighttime construction needed, avoid using noisy

equipment; and ➢ Maintain continual communication with the schools along the

road alignments to avoid noisy activities near the schools during examination periods.

Design Institute

PPMO; PMTB

Water quality

Construction site wastewater impact on water bodies

Put into tender documents the following measures to treat wastewater and runoff from construction sites and to prevent pollution to nearby water channels:: ➢ All construction camps, fuel and materials storage, re-fuelling

and maintenance areas to be located at least 500m from watercourses

➢ Provide portable toilets and small package WWTPs for workers and canteens; and

➢ Install sedimentation tanks on-site to treat process water and muddy runoff.

Design Institute

PPMO; PMTB

Ecology Protection of flora and fauna

Put into tender documents: ➢ All project personnel, including construction workers, are

prohibited from catching or trading in flora or fauna ➢ Project personnel will immediately report to the PMTB and

Design Institute

PPMO; PMTB

Page 22: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

16/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

EEMA any fauna found trapped within project sites e.g. in ditches or pits

Solid waste Disposal or storage of excavated spoil

Specify in tender documents the spoil disposal or storage sites and that only these sites could be used.

Design Institute

PPMO; PMTB

Health & safety

Occupational health & safety of workers

Specify in tender documents the provision of personal safety and protective equipment such as safety hats and shoes, eye goggles, respiratory masks, etc. to all construction workers;

Design Institute

PPMO; PMTB

Social and environmental

Handling and resolving complaints received during project implementation

➢ PPMO to establish a project Complaint Center with hotline ➢ PPMO to publicize local access points (contractors, PMTB)

for the GRM ➢ PPMO to establish grievance redress mechanism

procedures for resolving, documenting and reporting complaints according to the EMP

PPMO ADB PPMO has set up the GRM. ➢ Complied with

Traffic Construction vehicles causing traffic congestion

Plan transport routes for construction vehicles and specify in tender documents to forbid vehicles from using other roads during peak traffic hours.

Design Institute, Local traffic police

PPMO; PMTB

It is clearly defined in the tender documents that the Contractors shall “take reliable measures to guarantee unblocked traffic”. ➢ Complied with

Construction Stage Soil resources

Spoil disposal ➢ Strip and store topsoil in a stockpile for reuse in restoration. ➢ Use spoil disposal sites approved by PEPB and manage in

accordance with approved plan. ➢ Avoid side casting of spoil on slopes. ➢ Co-ordinate with water resources bureau monitoring station

on effectiveness of soil erosion prevention measures and any need for remedial action.

➢ Rehabilitate and restore spoil disposal sites in accordance with agreed plan.

➢ Conduct project completion audit to confirm that spoil disposal site rehabilitation meets required standard, contractor liable in case of non-compliance.

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, the surface soil, spoils and waste are treated strictly according to the design and the EMP. ➢ Being complied with

Page 23: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

17/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

Soil erosion • Implement soil erosion protection measures as defined in the Soil and Water Conservation Report

• Confirm location of the borrow pits and spoil storage and disposal sites; if these are different from those specified in the Soil and Water Conservation Report.

• Construct intercepting ditches and drains to prevent runoff entering construction sites, and diverting runoff from sites to existing drainage;

• Construct hoardings and sedimentation ponds to contain soil loss and runoff from the construction sites

• Limit construction and material handling during periods of rains and high winds;

• Stabilize all cut slopes, embankments, and other erosion-prone working areas while works are ongoing;

• Stockpiles shall be short-term, placed in sheltered and guarded areas near the actual construction sites, covered with clean tarpaulins when not in use, and sprayed with water during dry and windy weather conditions;

• All cut areas shall be stabilized with thatch cover within 30 days after earthworks have ceased at the sites;

• Immediately restore and landscape temporarily occupied land upon completion of construction works.

• Unauthorized extraction or disposal at other sites would be subject to penalties.

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, measures proposed in the SWCR are implemented in the road sections under construction now and monitoring on thesoil erosion protection is carried out. The details of monitoring results show in section V. ➢ Being complied with

Page 24: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

18/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

Soil contamination

➢ Properly store petroleum products, hazardous materials and wastes on an impervious surface.

➢ Develop spill response plan. Keep a stock of absorbent materials (e.g. sand, earth or commercial products) on site to deal with spillages and train staff in their use.

➢ If there is a spill take immediate action to prevent entering drains, watercourses, unmade ground or porous surfaces. Do not hose the spillage down or use any detergents. Use oil absorbent materials and dispose at a licensed waste management facility.

➢ Record any spill events and actions taken in environmental monitoring logs and report to LIEC.

➢ Properly store petroleum products, hazardous materials and waste in clearly labeled containers on an impermeable surface in secure and covered areas, preferably with bund and/or containment tray for any leaks.

➢ Remove all construction waste from the site to approved waste disposal sites.

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, the petroleum products on the road under construction are all kept according to related regulations. All hazardous substances and waste materials are treated appropriately without leakage. Construction wastes are delivered to designated place for disposal. ➢ Being complied with

Air quality Dust (TSP) during construction

➢ Frequent watering of unpaved areas, backfill areas and haul roads to suppress dust.

➢ Pave frequently used haul roads ➢ Limit the speed of vehicles travelling on unpaved areas and

haul roads ➢ Pay particular attention to dust suppression near sensitive

receptors such as schools, hospitals, residential areas and natural areas.

➢ Erect hoarding/screens around dusty activities such as demolition.

➢ Manage stockpile areas to avoid mobilization of fine material, cover with tarpaulin and/or spray with water.

➢ Do not overload trucks transporting earth materials. ➢ Equip trucks transporting earth materials with covers or

tarpaulin to cover loads during transport. ➢ Install wheel washing equipment or conduct wheel washing

manually at each exit of each works area to prevent trucks

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, one watering truck is provided for the each section contractor; the watering truck waters once per three non-rainy days. No excess load is found on any haulage truck and all the trucks are covered during transportation. Traffic rush hours and areas with intensive population are avoided. No wheel-washing facilities are configured at the exit of the construction area. ➢ Being complied with

Page 25: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

19/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

from carrying muddy or dusty substance onto public roads. ➢ Immediately cleanup all muddy or dusty materials on public

roads outside the exits of the works areas. ➢ Plan the transport routes and time to avoid busy traffic and

heavily populated areas when transporting earthy materials. ➢ Immediately plant vegetation in all temporary land take areas

upon completion of construction to prevent dust and soil erosion.

Fumes and particulate matter from asphalt mixing plant, concrete batching plant and other equipment and machinery

➢ Locate asphalt mixing plants and concrete batching plants at least 300m downwind from residential areas and other sensitive receptors.

➢ Enclose these plants and equip them with bag house filter or similar air pollution control equipment.

➢ Regularly inspect and certify vehicle and equipment emissions and maintain to a high standard.

Contractor PMTB; EEMA; LIEC

The central mixing station of Menglian-Meng’a Road at K84+800 has been completed. The location is far from residential areas and other sensitive receptors. This station has been equiped the air pollution control equipments. The other asphalt mixing and concrete batching stations haven’t started construction yet. ➢ Being complied with

Noise Noise from power mechanical equipment and vehicles

➢ Sensibly schedule construction activities, avoid noisy equipment working concurrently.

➢ Select advanced quiet equipment and construction method, and tightly control the use of self-provided generators.

➢ Comply with local requirements in areas with sensitive receptors very close by,

➢ Avoid construction works, particularly noisy activities such as piling and compaction from 22:00 to 06:00 hr.

➢ If nighttime construction needed, consult nearby residents beforehand for their consensus.

➢ If nighttime construction needed, avoid using noisy equipment

➢ If necessary, set up temporary noise barriers. ➢ Control speed of bulldozer, excavator, crusher and other

transport vehicles travelling on site. ➢ Specify equipment and machinery that conforms to PRC

Contractor

PMTB; EEMA; LIEC

At present, the Ning’er-Jiangcheng-Longfu Road and the Menglian-Meng’a Road is at the stage of excavation and embankment work.All the contractors comply with related requirements to reduce noises. Noise within the boundary of construction site meets GB12523-2011 and no adverse impacts are generated to local residents. ➢ Being complied with

Page 26: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

20/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

noise standard GB12523-90 and ensure regular maintenance.

➢ Adopt noise reduction devices and measures for works in proximity to sensitive noise receptors to ensure required standards are maintained.

➢ Locate sites for rock crushing, concrete mixing and other noisy activities at least 1km away from sensitive noise receptors.

➢ Limit the speed of vehicles travelling on site and on haul roads (less than 8 km/hr).

➢ Minimize the use of whistles and horns. ➢ Maintain continual communication with schools along the

road alignments to avoid noisy activities near the schools during examination periods and other noise-sensitive activities.

Water quality

Management of works in and adjacent to watercourses

➢ If possible, carry out bridge pier construction during the dry season.

➢ Erect berms or sandbags during bridge foundation works if necessary to contain runoff polluting the rivers.

➢ Maintain adequate flood flow during the rainy season. ➢ All construction camps, fuel and materials storage, refueling

and maintenance areas to be located at least 500m from watercourses.

➢ Take all necessary measures to prevent construction materials and waste from entering drains and water bodies.

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, all the interim facilities are far away from the water source. The water environment protection measures and flood control measures have been taken on the under construction bridge. ➢ Being complied with

Water quality

Construction site wastewater discharge

➢ All construction wastewater to be treated to appropriate PRC standard prior to discharge.

➢ Ensure timely cleanup of scattered materials on site, stockpiles must adopt measures to prevent being washed into water bodies by rain water.

➢ Reuse equipment and wheel wash wastewater for dust suppression.

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, all the sewage from construction is treated according to related requirements. ➢ Being complied with

Solid waste Construction site refuse

➢ Prepare a waste management plan including waste minimization and re-use

➢ Prepare a spill management plan for hazardous materials on

Contractor PMTB; EEMA; LIEC

At present, contractors of all road sections haven’t prepared the Waste Management Plan and the Spillage

Page 27: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

21/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

construction sites ➢ Set up centralized domestic waste collection point and

transport offsite for disposal at licensed municipal waste facility;

➢ Prohibit burning of waste.

and Leakage Control Plan yet. All the construction wastes are treated jointly according to related regulations. ➢ Partially compliant

Ecology Protection of vegetation and fauna, and restoration of disturbed areas

➢ Demarcate the construction working area to prevent encroachment and damage to adjacent areas.

➢ Ensure sufficient aftercare for landscape planting to maximize survival.

➢ Agree compensation planting for any forestry losses in line with PRC forestry laws.

➢ All project personnel, including construction workers, are prohibited from catching or trading in flora or fauna

➢ Project personnel will immediately report to the PMTB and EEMA any fauna found trapped within project sites e.g. in ditches or pits

Contractor PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, all the construction areas are within the boundary and no hunting or picking of plants are founded. ➢ Being complied with

Physical cultural resources

Destruction of cultural relics in river bed and soil

Contractor must comply with PRC's Cultural Relics Protection Law and Cultural Relics Protection Law Implementation Regulations if such relics are discovered, stop work immediately and notify the relevant authorities, adopt protection measures and notify the local Cultural Bureau to protect the site.

Contractor Cultural Relics Bureau; PMTB; EEMA; LIEC

During the construction stage of Ning’er-Jiangcheng-Longfu Road and Menglian-Meng’a Road, no historical relics are found in the construction area. ➢ Complied with

Occupational health and safety

Construction site sanitation

➢ Effectively clean and disinfect the site. ➢ During site formation, spray with phenolated water for

disinfection. ➢ Disinfect toilets and refuse piles and ensure timely removal of

solid waste; ➢ Exterminate rodents on site at least once every 3 months,

and exterminate mosquitoes and flies at least twice each year;

➢ Provide public toilets in accordance with the requirements of labor management and sanitation departments in the living areas on construction site,

➢ Appoint designated staff responsible for cleaning and disinfection.

Contractor PMTB; EEMA; LIEC

The layout of the living quarters on the construction site is irrational, no disinfection work or cleaning work is carried out. ➢ Being complied with

Page 28: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

22/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

Occupational safety

➢ Appoint Environment, Health and Safety Officer to develop and implement environmental, health and safety management plan, maintain records concerning health, safety and welfare and regularly report on accidents, incidents and near misses.

➢ Train all construction workers in general health and safety matters and on emergency preparedness and response procedures.

➢ Provide personal protective equipment (hard hats, shoes and high visibility vests) to all construction workers and enforce their use.

➢ Provide goggles and respiratory masks to workers doing asphalt road paving.

➢ Provide ear plugs to workers working near noisy powered mechanical equipment (PME), especially during piling of bridge foundations.

➢ Ensure safe handling, transport, storage and application of explosives for tunnel construction.

➢ Implement special measures to ensure worker safety in confined spaces during tunnel construction.

➢ Provide a clean and sufficient supply of fresh, potable water for all camps and work sites.

➢ Provide an adequate number of latrines and other sanitary arrangements at the site and work areas and ensure that they are cleaned and maintained in a hygienic state.

➢ Provide adequate waste receptacles and ensure regular collection and disposal.

➢ Ensure that Contractors have adequate worker and third party insurance cover.

➢ No children (less than 14 years of age) to work on any contract.

Contractor PMTB; EEMA; LIEC

The contractors have prepared corresponding environmental health and safety control plan and carried out related training. Personal protective appliances are distributed to workers. Safe drinking water is available on the construction site. WC (with ordinary sanitary conditions) and waste collecting facilities are made available. There is no child labor. ➢ Being complied with

Page 29: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

23/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

Food safety ➢ Inspect and supervise food hygiene in cafeteria on site regularly.

➢ Cafeteria workers must have valid health permits. ➢ Once food poisoning is discovered, implement effective

control measures immediately to prevent it from spreading

Contractor PMTB; EEMA; LIEC

At present, the food and sanitary conditions of the dining hall on the construction site are good. No food poisoning events have taken place during the report period. ➢ Being complied with

Disease prevention and safety awareness

➢ Construction workers must have physical examination before start working on site.

➢ If infectious disease is found, the patient must be isolated for treatment to prevent the disease from spreading.

➢ From the second year onwards, conduct physical examination on 20% of the workers every year.

➢ Establish health clinic at location where workers are concentrated, which should be equipped with common medical supplies and medication for simple treatment and emergency treatment for accidents.

➢ Specify the person responsible for health and epidemic prevention responsible for the education and propaganda on food hygiene and disease prevention to raise the awareness of workers.

➢ Regularly inspect works to ensure there are no areas of stagnant water that could provide breeding grounds for malaria, encephalitis and dengue fever mosquitoes.

Contractor PMTB; EEMA; LIEC

Annual health checks are required by Chinese regulate. All cons construction workers have been examined. No infectious diseases have been reported during the report period. ➢ Complied with

Community health and safety

Temporary traffic management

➢ A traffic control and operation plan will be prepared together with the local traffic management authority prior to any construction. The plan shall include provisions for diverting or scheduling construction traffic to avoid morning and afternoon peak traffic hours, regulating traffic at road crossings with an emphasis on ensuring public safety through clear signs, controls and planning in advance.

➢ As much as possible, schedule delivery of construction materials and equipment during non-peak hours.

Contractor, local traffic police

PMTB; EEMA; LIEC

The contractors have prepared traffic control and implementation plan.Specific workers are appointed to guide the traffic at road intersections and signboards are erected. ➢ Complied with

Information disclosure

Residents and businesses will be informed in advance through publicity about the construction activities and provided with the dates and duration of expected disruption and alternative routes,

Contractor, PMTB

PPMO, LIEC

Bulletin boards are set up at the construction area of each section to publicize information concerning

Page 30: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

24/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

as required. construction of the project. ➢ Complied with

Access to construction sites

➢ Clear signs will be placed at construction sites in view of the public, warning people of potential dangers such as moving vehicles, hazardous materials, excavations and raising awareness on safety issues.

➢ All sites will be made secure, discouraging access by members of the public through fencing or security personnel, as appropriate.

Contractor PMTB; EEMA; LIEC

Safety warning boards are set up at the construction area of each section. ➢ Complied with

Utility services interruptions

➢ Assess construction locations in advance for potential disruption to services and identify risks before starting construction.

➢ If temporary disruption is unavoidable, develop a plan to minimize the disruption in collaboration with relevant local authorities such as power company, water supply company and communication company.

➢ Communicate the dates and duration in advance to all affected people.

Contractor, local service providers

PMTB; EEMA; LIEC

All the electrical power, telecommunication and water supply facilities within the construction site are relocated when the contractors move in. No interruption or adverse impacts to the public service facilities have taken place during the report period. ➢ Complied with

Social & environmental

Handling and resolving complaints

⚫ Appoint a GRM coordinator within PPMO. ⚫ Brief and provide training on GRM access points (PMTB,

contractors). ⚫ Disclose GRM to affected people before construction begins

at the main entrance to each construction site. ⚫ Maintain and update a Complaints Register to document all

complaints and their resolution. Report on GRM in quarterly project progress reports and semi-annual environmental monitoring reports..

PPMO, PMTB, Contractor

ADB PPMO has set up the GRM. Specific workers at all the road sections are appointed to handle and solve complaints and announcement will be made on the construction site. No related complaints are reported during the report period. ➢ Complied with

Operational Stage Traffic Road

condition Regularly inspect and maintain the road surface, drains and verges.

O&M units PPMO ➢ To be complied at operational stage

Road safety and traffic accidents

Strictly enforce traffic law to improve road safety and reduce traffic accidents.

Pu’er Traffic Police

PMG ➢ To be complied at operational stage

Collisions Monitor incidence and type of wildlife fatality and install warning O&M units PPMO/PM ➢ To be complied at operational

Page 31: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

25/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

with wildlife signs or other preventative measures, as required. G stage B.Specific potential impacts and mitigation measures for Ning’er-Jiangcheng-Longfu Road Detailed Design Stage Drinking water source – Wenquan Reservoir

Alignment near the reservoir at section K25+200 to K45+200.

• Alignment design of road section K25+200 to K45+200 must not traverse through Protection Zone 1 of the Wenquan Reservoir

• Drainage design of road section K25+200 to K45+200 traversing through Protection Zone 2 of the Wenquan Reservoir must have collection, containment and treatment systems for the road runoff.

Design Institute

PPMO; PMTB

The location of Wenquanhe Reservoir have been changed. The section K25+200~K45+200 of Ning’er-Jiangcheng-Longfu Road don’t cut through the runoff area of Wenquanhe Reservoir. This section don’t need to be redesigned. ➢ Complied with

Social, environmental health

Traffic noise impact to sensitive receptors

➢ Design road side noise barriers at the following 6 locations as indicated in the domestic EIR: ◼ Banhai Village – 2.5 m high x 100 m long ◼ Manlian Village – 2.5 m high x 90 m long ◼ Sanjia Village – 2.5 m high x 50 m long ◼ Longtangba – 2.5 m high x 50 m long ◼ Xishitou Village – 2.5 m high x 100 m long ◼ Baozang Township – 2.5 m high x 250 m long

Design Institute

PPMO; PMTB

The road side noise barriers at the following 6 locations are designing. ➢ Complied with

Pre-construction Stage Trees native to Yunnan

Damage to protected tree species native to Yunnan by construction workers and machinery

Trees at the following locations shall be tagged, conspicuously marked and fenced off prior to commencement of construction activities ➢ Panaxzingiberensis 姜状三七: 20 trees in Liming Township

along chainage K80 to K85 ➢ Phoebe nanmu 滇楠: 3 trees in Liming Township

approximately 200 m to the right of road center line at chainage K85+100 and in Qushui Township approximately 55 m to the right of road center line at chainage K200+800

➢ Dalbergiaretusa 黑黄檀: 1 tree in Mengxian Township approximately 100 m to the left of road center line at chainage K48+800.

➢ Aesculuswangii 云南七叶树: 5 trees in Qushui Township approximately 50 m to the right of road center line at chainage

PMTB environmental specialist

PPMO At present, contractors of detailed sections have moved in. They will mark and separate the protected plants with fences after the location of the trees are confirmed by the local forestry authorities. ➢ To be complied with

Page 32: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

26/178 6th Semi-annual Environmental Monitoring Report

Impact Factor

Potential Impacts and/or Issues

Mitigation Measures defined in the EMP Impleme

nting Entity

Supervising Entity

Implementation status and compliance with EMP

K215+800. C.Specific potential impacts and mitigation measures for Menglian-Meng’a Road Detailed Design Stage Social, environmental health

Traffic noise impact to sensitive receptors

Design road side barrier at the following one location as indicated in the domestic EIR: Menghai Primary School – 3 m high x 200 m long

Design Institute

PPMO; PMTB

Menghai Primary School has been changed to the local rehab. And the route of this section has been adjusted to 150m from the building. The road side barrier hasn‘t need to design. ➢ Complied with

Landscape Preservation of trees and woodlands

Permanent and temporary land-take to avoid intact woodlands at sections K55+200-K65+500、K70+100-K72+300、K75+300-K77+200

Design Institute

PPMO; PMTB

The whole forest land along the line is avoided during design of the Menglian-Meng’a Road. ➢ Being complied with

Operational Stage Social, environmental health

Traffic noise impact to sensitive receptors

Install 140 m2 of double-glazed windows on first row of non-commercial buildings facing the road at the following 3 locations as indicated in the domestic EIR (CNY1,000/m2). Total cost = $23,000 • Mengma Township at K79+800 • Manglang at K95+200 • Anma at K97+350

PPMO PMG, PEPB

➢ To be complied during the operation stage

Page 33: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

27/178 6th Semi-annual Environmental Monitoring Report

V. SUMMARY OF ENVIRONMENTAL MONITORING

A. Monitoring Plan and Responsibilities

This Environmental Monitoring Report is prepared by the External Environmental Monitoring Agency (Guangxi Transportation Research Institute, Yunnan Fangyuan Science and Technology Co., Ltd, Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd, Kunming Longhui Engineering Design Consulting Co., Ltd). It based on the environmental supervision reports, the external environmental monitoring reports and theSoil Erosion Protection monitoring reports, submitted by the External Environmental Monitoring Agencies. Some information provided by the PPMO and other management departments. The field survey carried out by the PPMO and EEMA. This Report covers for the period from July to December, 2018.

For the regional roads, the monitoring plan during the construction period is defined in the EMP. Environmental monitoring on Menglian - Meng’a Road in construction period is undertaken by Guangxi Transportation Research Institute, and soil erosion protection monitoring is undertaken by Yunna Jin Yu Ecological Engineering Consulting Co., Ltd. Environmental monitoring on Ning'er - Jiangcheng - Longfu Road in construction period is undertaken by Yunnan Fangyuan Technology Co., Ltd., and water conservation monitoring is undertaken by Kunming Longhui Engineering Design Consultation Co., Ltd.

Through field verification by EMMA, this report has corrected the stake number of all monitoring points and replaced a few of monitoring points which is far away from the project, but not modified the monitoring frequency and duration which have been confirmed by EMP.

Table 5-1:Monitoring Plan during Construction Period for the Regional Roads

Item Monitoring Parameter Monitoring Location

Monitoring Frequency &

Duration Implementing Entity

Supervising Entity

Menglian-Meng’a Road Construction Stage Air quality

TSP; (SO2& NO2 only if there is asphalt mixing within 500 m)

10 locations that are within 20 m of the alignment: 1. Pajingchachang(K64+500) 2. Hegelaozhai (K68+300) 3. Hegexinzhai (K71+400) 4. Health center of Mengma(K79+900) 5. Hehaxinzhai (K83+100) 6. Guangsan (K87+700) 7. Bingsuo (K89+300) 8. Manglang (K92+400) 9. Anma (K97+350) 10. Menga(K98+700)

1 day (24-hr) per month (Monitor only when road section has construction activities within 500 m)

GXTRI PMTB, PPMO

Noise LAeq 10 locations that are within 20 m of the alignment: 1. Pajingchachang(K64+500) 2. Hegelaozhai (K68+300) 3. Hegexinzhai (K71+400) 4. Health center of Mengma(K79+900) 5. Hehaxinzhai (K83+100) 6. Guangsan (K87+700) 7. Bingsuo (K89+300) 8. Manglang (K92+400) 9. Anma (K97+350) 10. Menga(K98+700)

2 times per day (daytime and nighttime); 1 day per month (Monitor only when road section has construction activities within 500 m)

GXTRI PMTB, PPMO

Water DO, SS, TPH 3 locations during bridge construction 1 time per day; 1 GXTRI PMTB,

Page 34: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

28/178 6th Semi-annual Environmental Monitoring Report

Item Monitoring Parameter Monitoring Location

Monitoring Frequency &

Duration Implementing Entity

Supervising Entity

quality at the following road sections: 1. Nancha River(K56+803) 2. Nanma River(K74+950) 3. Nanma River(K96+300) Set up 2 stations for water quality monitoring at each of the 3 locations as follows: 1. Control station: 50 m upstream of

the bridge alignment 2. Impact station 100m downstream of

the bridge alignment (Note: if downstream impact station data > 130% of upstream control station data (DO <130%), mitigation measures are needed)

day per month during bridge construction

PPMO

Ning’er-Jiangcheng-Longfu Road Construction Stage Air quality

TSP; (SO2& NO2 only if there is asphalt mixing within 500 m)

11 locations that are within 20 m of the alignment 1. Dazhai (K1+350) 2. Xishitou (K21+160) 3. Mengxian Primary School(K47+900) 4. Anning (K54+100) 5. Xuande (K60+600) 6. Xianren (K92+900) 7. Liming Township (K109+900) 8. Baozang Township (K140+300) 9. Banhe Primary School(K152+300) 10. Qiyiqiao (K159+450) 11. Niuluohe (K183+500)

1 day (24-hr) per month (Monitor only when road section has construction activities within 500 m)

YNFY PMTB, PPMO

Noise LAeq 11 locations that are within 20 m of the alignment 1. Dazhai(K1+350) 2. Xishitou (K21+160) 3. Mengxian Primary School(K47+900) 4. Anning (K54+100) 5. Xuande (K60+600) 6. Xianren (K92+900) 7. Liming Township (K109+900) 8. Baozang Town ship(K140+300) 9. Banhe Primary School(K152+300) 10. Qiyiqiao (K159+450) 11. Niuluohe (K183+500) [Note: nighttime monitoring not needed at the school locations]

2 times per day (daytime and nighttime); 1 day per month (Monitor only when road section has construction activities within 500 m)

YNFY PMTB, PPMO

Water quality

DO, SS, TPH 7 rivers during bridge construction at the following road sections: 1. Mengxian River (K58+875) 2. Manxian River (K95+200) 3. Manbangtian River (K109+405) 4. Mengye River (K139+340) 5. Lahu River (K194+700) 6. Longdong River (K221+400) 7. Shili River (K227+240) Set up 2 stations for water quality monitoring at each of the 7 rivers as follows::

1 time per day; 1 day per month during bridge construction

YNFY PMTB, PPMO

Page 35: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

29/178 6th Semi-annual Environmental Monitoring Report

Item Monitoring Parameter Monitoring Location

Monitoring Frequency &

Duration Implementing Entity

Supervising Entity

1. Control station: 50 m upstream of the bridge alignment

2. Impact station 100m downstream of the bridge alignment

(Note: if downstream impact station data > 130% of upstream control station data (DO <130%), mitigation measures are needed)

B. Environmental Quality Objectives and Sampling Analysis Method

B-1. Environmental quality objectives

The environmental monitoring results of the project are evaluated according to the environmental quality objectives defined in the EMP. In which, the latest GB3095-2012 is adopted for the Ambient Air Quality Standard. See the table below for applicable standards.

Table 5-2: Applicable Standards for Monitoring Indexes

Period Indicator Standard

Construction

TSP Ambient Air Quality Standard (GB3095-2012)ClassⅡ Fume from asphalt mixing plant (SO2, NO2) Integrated emission standard of air pollutants(GB 16297-1996)

Noise limits of PME at boundary of construction site

Emission standard of environment noise for boundary of construction site(GB 12523-2011)

Discharge of wastewater from construction sites

Integrated Wastwater Discharge Standard(GB 8978-1996)ClassⅠ

DO, SS and TPH levels in river during bridge construction works

SS and TPH at downstream impact station <130% of the upstream control station. DO at downstream impact station >70% of the upstream control station and must not be < 2mg/L

Operation

Traffic noise at sensitive receptor within 35 m of road red line

Environmental Quality Standard for Noise (GB3096-2008) Category 4a Functional Area

Traffic noise at sensitive receptor beyond 35 m of road red line

Environmental Quality Standard for Noise (GB3096-2008) Category 1 and Category 2 Functional Areas

B-2. Sampling analysis method

The sampling analysis methods and the samples taking procedure of monitoring parameters are subject to related national standards.

See the following table for details. Table5-3:Sampling Analysis Methods of the Indicators

Indicator Sampling analysis method Detection Limit

CODCr Water Quality-Determination of the Chemical Oxygen Demand-Dichromate Method (HJ 828-2017) 4 mg/L

SS Water Quality-Determination of Suspended Substance-Gravimetric Method (GB11901-89) 4 mg/L

TPH Water Quality-Determination of Petroleum Oil, Animal and Vegetable Oils-Infrared Photometric Method (HJ637-2012) 0.01 mg/L

DO Water Quality-Determination of Dissolved Oxygen-Iodometric Method (GB 7489-1987) 0.2mg/L

Noise(LAeq) Environmental Quality Standard for Noise (GB3096-2008) /

Page 36: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

30/178 6th Semi-annual Environmental Monitoring Report

Indicator Sampling analysis method Detection Limit

TSP Ambient Air-Determination of Total Suspended Particulates--Gravimetric Method (GB/T15432-1995) 0.001mg/m3

C. Environmental Monitoring Results

C-1. Project Implementation Progress at Environmental Monitoring Points

Menglian - Meng’a Road: Table 5-4 shows project implementation progress at each monitoring points of Menglian - Meng'a Road by 31 December, 2018.

Table 5-4:Project Progress at Monitoring Points of Menglian - Meng'a Road

S/N Monitored Objects Stake No. Name of the

Monitoring Point Progress of works

1

Noise

K64+500 Pajingchachang Subgrade works in progress 2 K68+300 Hegelaozhai Subgrade works in progress 3 K71+400 Hegexinzhai During this report period not in progress

4 K76+100 Health center of Mengma

During this report period not in progress

5 K83+100 Hehaxinzhai During this report period not in progress

6 K87+700 Guangsan Subgrade works in progress 7 K89+300 Bingsuo Subgrade works in progress 8 K92+400 Manglang During this report period not in progress

9 K94+600 Anma Subgrade works in progress

10 K98+700 Menga Subgrade works in progress

1

Ambient air quality

K64+500 Pajingchachang Subgrade works in progress 2 K68+300 Hegelaozhai Subgrade works in progress 3 K71+400 Hegexinzhai During this report period not in progress

4 K76+100 Health center of Mengma

During this report period not in progress

5 K83+100 Hehaxinzhai During this report period not in progress

6 K87+700 Guangsan Subgrade works in progress 7 K89+300 Bingsuo Subgrade works in progress 8 K92+400 Manglang During this report period not in progress

9 K94+600 Anma Subgrade works in progress

10 K98+700 Menga Subgrade works in progress

1 Surface water

K56+803 Nancha River River-crossing bridge works in progress

2 K74+950 Nanma River River-crossing bridge works in progress

3 K96+300 Nanma River River-crossing bridge works in progress

Page 37: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

31/178 6th Semi-annual Environmental Monitoring Report

Ning'er - Jiangcheng - Longfu Road:Table 5-5 shows theproject progress at each monitoring points of Ning'er - Jiangcheng - Longfu Road by 31 December, 2018.

Table 5-5: Project Progress at Monitoring Points of Ning'er-Jiangcheng-Longfu Road

S/N Monitored Objects Stake No. Name of the

Monitoring Point Progress of works

1

Noise

K1+350 Dazhai During this report period not in progress

2 K21+160 Xishitou During this report period not in progress

3 K47+900 Mengxian Primary School During this report period not in progress

4 K54+100 Anning During this report period not in progress 5 K60+600 Xuande During this report period not in progress 6 K92+900 Xianren During this report period not in progress 7 K109+900 Liming Township During this report period not in progress 8 K140+300 Baozang Township During this report period not in progress

9 K152+300 Banhe Primary School During this report period not in progress

10 K159+450 Qiyiqiao Subgrade works in progress 11 K183+500 Niuluohe During this report period not in progress 1

Ambient air quality

K1+350 Dazhai During this report period not in progress

2 K21+160 Xishitou During this report period not in progress

3 K47+900 Mengxian Primary School During this report period not in progress

4 K54+100 Anning During this report period not in progress 5 K60+600 Xuande During this report period not in progress 6 K92+900 Xianren During this report period not in progress 7 K109+900 Liming Town During this report period not in progress 8 K140+300 Baozang Town During this report period not in progress

9 K152+300 Banhe Primary School During this report period not in progress

10 K159+450 Qiyiqiao Subgrade works in progress 11 K183+500 Niuluohe During this report period not in progress 1

Surface water

K58+875 Mengxian River During this report period not in progress 2 K95+200 Manxian River During this report period not in progress 3 K109+405 Manbangtian River During this report period not in progress 4 K139+340 Mengye River River-crossing bridge works in progress 5 K194+700 Lahu River During this report period not in progress

6 K221+400 Longdong River River-crossing bridge works in progress

7 K227+240 Shili River River-crossing bridge works in progress

C-2. Monitoring Results of Noise

The monthly monitoring plan for monitoring points have been formulated according to the construction conditions provided by the Engineering Command. During this monitoring period, some monitoring points have completed subgrade construction, and there was no construction activity near some monitoring points during the entry of monitors.

Menglian - Meng’a Road:

The environmental noise monitoring data is from July to December 2018. During this

Page 38: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

32/178 6th Semi-annual Environmental Monitoring Report

report period, just part of sections are in construction. EEMA have monitored the noise of six construction points for one day per month, which are Pajingchachang(K64+500), Hegelaozhai (K68+300), Guangsan(K87+700), Bingsuo(K89+300), Anma(K94+600), Menga(K98+700). All project sections haven’t constructed at nighttime, so all monitoring points haven’t monitored the noise of nighttime. Table 5-6 shows monitoring results.

The monitoring values at these points range from 54.5 dB (A) to 58.7dB (A) at daytime. The all monitoring values satisfy the limit value given in GB3096-2008.

Ning'er - Jiangcheng - Longfu Road:

The environmental noise monitoring data is from July to December 2018. During this report period, the most part of sections aren‘t in construction. EEMA have monitored the noise of construction point for one day per month, only Qiyiqiao(K159+450). All project sections haven’t constructed at nighttime, so all monitoring points haven’t monitored the noise of nighttime. Table 5-7 shows monitoring results.

The monitoring values at these points range from 54.6dB (A) to 55.4dB (A) at daytime. The all monitoring values satisfy the limit value given in GB3096-2008.

The Sampling technicians of Environmental Monitoring Agencies have took the photos for every monitoring point when they obtained water sample. The follow photos show some situations of noise sample.

Menglian - Meng’a Road

Page 39: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

33/178 6th Semi-annual Environmental Monitoring Report

Ning'er - Jiangcheng - Longfu Road

Page 40: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

34/178 6th Semi-annual Environmental Monitoring Report

Table5-6: Noise Monitoring Results in Construction Period of Menglian - Meng’a Road Unit: dB (A)

Name of the Monitoring Point

Monitoring Time

Standard Limit

Monitoring Results July August September October November December

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Pajingchachang (K64+500)

Daytime 70 17 56.8 19 59.1 14 54.5 21 55.7 22 56.8 18 57.3

Nighttime 55 / / / / / / / / / / / /

Hegelaozhai (K68+300)

Daytime 70 17 55.2 19 60.2 14 56.9 21 56.4 22 57.1 19 58.5

Nighttime 55 / / / / / / / / / / / /

Hegexinzhai (K71+400)

Daytime 70 / / / / / / / / / / / /

Nighttime 55 / / / / / / / / / / / /

Health center of Mengma(K79+900)

Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Hehaxinzhai (K83+100)

Daytime 70 / / / / / / / / / / / /

Nighttime 55 / / / / / / / / / / / /

Guangsan (K87+700)

Daytime 70 17 55.6 19 55.0 14 56.7 / / / / / /

Nighttime 55 / / / / / / / / / / / /

Bingsuo (K89+300)

Daytime 70 17 56.5 19 57.1 14 55.4 / / / / / /

Nighttime 55 / / / / / / / / / / / /

Manglang (K92+400)

Daytime 70 / / / / / / / / / / / /

Nighttime 55 / / / / / / / / / / / /

An’ma (K97+350)

Daytime 70 17 57.4 19 59.1 14 58.5 / / / / / /

Nighttime 55 / / / / / / / / / / / /

Menga(K98+700) Daytime 70 17 58.1 19 57.5 14 58.7 22 57.6 / / / /

Nighttime 55 / / / / / / / / / / / /

Page 41: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

35/178 6th Semi-annual Environmental Monitoring Report

Table 5-7:Noise Monitoring Results in Construction Period of Ning’er - Jiangcheng - Longfu Road Unit: dB (A)

Name of the Monitoring Point

Monitoring Time

Standard Limit

Monitoring Results July August September October November December

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Dazhai(K1+350) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Xishitou(K21+160) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Mengxian Primary School(K47+900)

Daytime 60 / / / / / / / / / / / /

Nighttime / / / / / / / / / / / / /

Anning(K54+100) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Xuande(K60+600) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Xianren(K92+900) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Liming Town(K109+900)

Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Baozang Town(K140+300)

Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Banhe Primary School(K152+300)

Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Qiyiqiao(K159+450) Daytime 60 / / / / / / / / 20 55.4 28 54.6

Nighttime 50 / / / / / / / / / / / /

Niuluohe(K183+500) Daytime 60 / / / / / / / / / / / /

Nighttime 50 / / / / / / / / / / / /

Page 42: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

36/178 6th Semi-annual Environmental Monitoring Report

C-3. Monitoring Results of Ambient Air Quality

Menglian - Meng’a Road:

The ambient air quality monitoring data is from July to December 2018. During this report period, just part of sections are in construction. EEMA have monitored the ambient air quality of six construction points for one day per month, which are Pajingchachang(K64+500), Hegelaozhai (K68+300), Guangsan(K87+700), Bingsuo(K89+300), Anma(K94+600), Menga(K98+700).. Table 5-8 shows monitoring results.

During the period from July to December 2018, as show in Table 5-8 that the monitoring results of all monitoring points is 100% within requirements. The TSP daily mean value of these seven monitoring points, where subgrade works have been under construction, ranges from 0.064 to 0.158mg/m3, which satisfie the limit of Class II in Ambient Air Quality Standard (GB3095-2012).

Ning'er - Jiangcheng - Longfu Road:

The ambient air quality monitoring data is from from July to December 2018. During this report period, the most part of sections aren‘t in construction, especially during April to June. EEMA have monitored the ambient air quality of construction points for one day per month, only Qiyiqiao(K159+450). Table 5-9 shows monitoring results.

During the period from July to December 2018, as show in Table 5-9 that the monitoring results of all monitoring points is 100% within requirements. The TSP daily mean value of these seven monitoring points, where subgrade works have been under construction, ranges from 0.053 to 0.062mg/m3, which satisfie the limit of Class II in Ambient Air Quality Standard (GB3095-2012).

The Sampling technicians of Environmental Monitoring Agencies have took the photos for every monitoring point when they obtained water sample. The follow photos show some situations of noise sample.

Menglian - Meng’a Road

Page 43: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

37/178 6th Semi-annual Environmental Monitoring Report

Ning'er - Jiangcheng - Longfu Road

Page 44: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

38/178 6th Semi-annual Environmental Monitoring Report

Table 5-8: Ambient Air Quality Monitoring Results in Construction Period of Menglian - Meng’a Road Unit: mg/m3

Location of the Monitoring Point

Standard Limit

Monitoring Results July August September October November December

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Pajingchachang (K64+500) 0.3 17 0.097 19 0.103 14 0.098 21 0.091 22 0.078 18 0.069

Hegelaozhai (K68+300) 0.3 17 0.085 19 0.098 14 0.108 21 0.083 22 0.080 19 0.064

Hegexinzhai (K71+400) 0.3 / / / / / / / / / / / /

Health center of Mengma

(K79+900) 0.3 / / / / / / / / / / / /

Hehaxinzhai (K83+100)

0.3 / / / / / / / / / / / /

Guangsan (K87+700) 0.3 17 0.085 19 0.094 14 0.127 / / / / / /

Bingsuo (K89+300)

0.3 17 0.080 19 0.076 14 0.125 / / / / / /

Manglang (K92+400)

0.3 / / / / / / / / / / / /

An’ma (K97+350)

0.3 17 0.077 19 0.081 14 0.158 / / / / / /

Menga (K98+700) 0.3 17 0.067 19 0.071 14 0.119 22 0.074 / / / /

Page 45: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

39/178 6th Semi-annual Environmental Monitoring Report

Table5-9: Ambient Air Quality Monitoring Results in Construction Period of Ning’er - Jiangcheng - Longfu Road Unit: mg/m3

Location of the Monitoring

Point

Standard

Limit

Monitoring Results July August September October November December

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Sampling Date

Monitoring Value

Dazhai (K1+350) 0.3 / / / / / / / / / / / /

Xishitou (K21+160) 0.3 / / / / / / / / / / / /

Mengxain Primary school

(K47+900)

0.3 / / / / / / / / / / / /

Anning (K54+100) 0.3 / / / / / / / / / / / /

Xuande (K60+600) 0.3 / / / / / / / / / / / /

Xianren (K92+900) 0.3 / / / / / / / / / / / /

Liming Townshiip

(K109+900) 0.3 / / / / / / / / / / / /

Baozang Township

(K140+300) 0.3 / / / / / / / / / / / /

Banhe Primary

School(K152+300)

0.3 / / / / / / / / / / / /

Qiyiqiao (K159+450) 0.3 / / / / / / / / 20 0.053 28 0.062

Niuluohe (K183+500) 0.3 / / / / / / / / / / / /

Page 46: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

40/178 6th Semi-annual Environmental Monitoring Report

C-4. Monitoring Results of Surface Water

Menglian - Meng’a Road:

During this report period, part project sections haven’t constructed. EEMA have monitored water monthly quality in river reach near three river-crossing bridges, when they were in constructiong. Table 5-10 shows monitoring results.

According to evaluation for monitoring results, the monitoring indexe of river reach near Nancha River K56+803, Nanma River K74+950, Nanma River K96+300 during July to December, CODCr, DO and TPH can satisfy the water quality standard of category III in Environmental Quality Standard for Surface Water (GB3838 - 2002). For suspended solids (SS), no up-to-standard evaluation is performed because no corresponding water environmental quality standard exists in China at present.

The monitoring results of the three bridge works at July to December shows that the bridges construction didn’t have a significant impact on water quality. The CODCr and SS dates of the impact station(100m downstream of the bridge alignment) aren’t more than 130% of control station(50m upstream of the bridge alignment), the DO dates aren’t less than 70%.

The value of TPH monitoring results are low for Nanma River K74+950 and K96+300 in July and September. Affected by sampling and analysis deviation, dates of the impact station were more than 130% of control station, but the dates can satisfy the water quality standard of category III in Environmental Quality Standard for Surface Water (GB3838 - 2002).

Table5-10: Surface Water Monitoring Results and Evaluation in Construction Period of Menglian - Meng’a Road Unit: mg/L

River Name and Stake Number

Sampling Date

Sampling stations

Monitoring Results

CODCr DO SS TPH

Environment Quality Standard of Surface Water (GB3838—2002) Class III ≤20 ≥5 — ≤0.05

Nancha River K56+803

Jul. Control station / / / /

Impact station / / / /

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Impact station / / / /

Nov. 22 Control station 7 7.9 86 0.02

Impact station 8 8.0 88 0.01

Dec. 18 Control station 6 8.1 98 0.02

Impact station <4 8.8 96 0.02

Nanma River K74+950

Jul. Control station / / / /

Impact station / / / /

Aug. 19 Control station 10 7.8 23 0.03

Impact station 9 7.8 28 0.03

Sep. 14 Control station 7 7.8 16 0.02

Impact station 8 7.7 15 0.02

Oct. 21 Control station 9 8.1 48 0.03

Page 47: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

41/178 6th Semi-annual Environmental Monitoring Report

River Name and Stake Number

Sampling Date

Sampling stations

Monitoring Results

CODCr DO SS TPH

Impact station 10 8.0 52 0.02

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

Nanma River K96+300

Jul. 17 Control station 11 7.6 54 0.02

Impact station 12 8.0 49 0.03

Aug. Control station / / / /

Impact station / / / /

Sep. 14 Control station 8 7.5 14 0.01

Impact station 9 7.6 16 0.02

Oct. Control station / / / /

Impact station / / / /

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

Ning'er - Jiangcheng - Longfu Road:

During this report period, part project sections haven’t constructed. EEMA have monitored water monthly quality in river reach near five river-crossing bridges, when they were in constructiong. Table 5-11shows monitoring results.

According to evaluation for monitoring results, the monitoring indexe of river reach near Mengye River K139+340, Longdong River K221+400, Shili River K227+240 during July to December, CODCr, DO and TPH from July to December 2018 can satisfy the water quality standard of Class III or Ⅳ in Environmental Quality Standard for Surface Water (GB3838 - 2002). For suspended solids (SS), no up-to-standard evaluation is performed because no corresponding water environmental quality standard exists in China at present.

The monitoring results of the three bridge works at July to December shows that the bridges construction didn’t have a significant impact on water quality. The CODCr and SS dates of the impact station(100m downstream of the bridge alignment) aren’t more than 130% of control station(50m upstream of the bridge alignment), the DO dates aren’t less than 70%.

The value of TPH monitoring results are low for Shili River K227+240 in July. Affected by sampling and analysis deviation, dates of the impact station were more than 130% of control station, but the dates can satisfy the water quality standard of category III in Environmental Quality Standard for Surface Water (GB3838 - 2002).

Table 5-11: Surface Water Monitoring Results before Construction of Ning’er - Jiangcheng - Longfu Road Unit: mg/L

River Name and Stake Number

Sampling Date Sampling Station Monitoring Results

CODCr DO SS TPH Environment Quality Standard of Surface Water

(GB3838—2002) ClassⅢ ≤20 ≥5 — ≤0.05

1.Mengxian River K58+875

Jul. Control station / / / /

Impact station / / / /

Aug. Control station / / / /

Page 48: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

42/178 6th Semi-annual Environmental Monitoring Report

River Name and Stake Number

Sampling Date Sampling Station Monitoring Results

CODCr DO SS TPH Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station

Impact station

Nov. Control station

Impact station

Dec. Control station / / / /

Impact station / / / /

6.Longdong River K221+400

Jul. 19 Control station 11 6.4 28 0.03

Impact station 13 6.3 44 0.03

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Impact station / / / /

Nov. 20 Control station 4 8.8 14 <0.01

Impact station 5 8.8 16 0.01

Dec. 28 Control station 7 8.4 15 0.01

Impact station 8 8.1 18 0.01

7.Shili River K227+240

Jul. 19 Control station 13 6.7 36 0.03

Impact station 17 6.4 49 0.04

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Impact station / / / /

Nov. 20 Control station <4 9.6 7 <0.01

Impact station <4 9.3 7 <0.01

Dec. 28 Control station 5 9.1 6 <0.01

Impact station 7 8.8 7 <0.01

Environment Quality Standard of Surface Water (GB3838—2002) Class Ⅳ ≤30 ≥3 - ≤0.5

2.Manxian River K95+200

Jul. Control station / / / /

Impact station / / / /

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Page 49: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

43/178 6th Semi-annual Environmental Monitoring Report

River Name and Stake Number

Sampling Date Sampling Station Monitoring Results

CODCr DO SS TPH Impact station / / / /

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

3.Manbangtian River K109+405

Jul. Control station / / / /

Impact station / / / /

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Impact station / / / /

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

4.Mengye River K139+340

Jul. Control station / / / /

Impact station / / / /

Aug. 21 Control station 8 8.1 34 0.01

Impact station 14 7.6 42 0.01

Sep. 16 Control station 5 9.0 31 0.02

Impact station 11 8.0 38 0.02

Oct. 19 Control station 10 7.8 34 0.01

Impact station 16 7.0 39 0.01

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

5.Lahu River K194+700

Jul. Control station / / / /

Impact station / / / /

Aug. Control station / / / /

Impact station / / / /

Sep. Control station / / / /

Impact station / / / /

Oct. Control station / / / /

Impact station / / / /

Nov. Control station / / / /

Impact station / / / /

Dec. Control station / / / /

Impact station / / / /

Page 50: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

44/178 6th Semi-annual Environmental Monitoring Report

The Sampling technicians of Environmental Monitoring Agencies have took the photos for every monitoring point when they obtained water sample. The follow photos show some situations of water sample.

Menglian - Meng’a Road

Nanma River K96+300

Control Station Nanma River K96+300

Impact Station

Nancha River K56+803

Control Station Nancha River K56+803

Impact Station Ning'er - Jiangcheng - Longfu Road

Shili River K227+240

Control Station Shili River K227+240

Impact Station

Page 51: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

45/178 6th Semi-annual Environmental Monitoring Report

Longdong River K221+400

Control Station Longdong River K221+400

Impact Station

D. Monitoring Result of Soil Erosion Protection

D-1. Menglian - Meng’a Road

(1)Monitoring situation

Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd. accepted the monitoring commission for soil and water conservation of highway works for Langcang, Pu’er City - Menglian - Meng’a in November 2013, and its monitoring of soil and water conservation for highway works in Lancang - Menglian - Meng’a started from March 2014. The Monitoring Report for Soil and Water Conservation of Highway Works in Canglan, Pu’er - Menglian - Meng’a was submitted quarterly. However, the construction of Menglian - Meng’a section had not started, therefore no soil and water conservation monitoring has been applied to Menglian - Meng’a Road.

In March 2016, to satisfy the requirements of EMP, the supplemental agreement attached to monitoring contract of water and soil conservation was signed by and between Pu’er Transportation Investment Group Co., Ltd. and Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd. In June 2016, workgroup of water and soil conservation monitoring made a site survey and data collection along the whole Menglian - Meng’a Road and developed a monitoring plan for water and soil conservation along Menglian - Meng’a Road on the basis of original Monitoring Design and Implementation Plan for Water and Soil Conservation of Menglian - Meng’a Road. During this report period, the monitoring team conducted the sixteenth filed monitoring on October 18 to 21.

K75+325 Manglie River October 19, 2018

K96+300 Nanma River October 19, 2018

Page 52: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

46/178 6th Semi-annual Environmental Monitoring Report

(2)Implementation of Soil and Water Conservation Measures

Main project area: The excavation of soil and stone for subgrade and the construction of pile foundations of bridges are underway.

Gravel-soil-taken field: The one for this project hasn’t yet been enabled.

Spoil disposal area: There are 9 spoil yards designed for the entire route, covering an area of 18.09 ha, with design capacity of 2.29 million m3 of spoils. Up to now, the actual quantity of spoils is about 1.219 million m3. A total of 9 spoil yards have been put into use, of which, 5 yards have been constructed with retaining walls. The conditions of spoil yards are detailed in Table 5-12.

Table 5-12: Conditions of Spoil Yards

Yard Name Location

Actual Floor Area

Design Capacity

Current Occupancy Remarks

(ha) (mil. m3) (mil. m3) 20# spoil yard K58+000 0.70 0.05 0.03 New spoil yard under service,

structures to be constructed. 21# spoil yard K60+520 0.94 0.03 0.20 Under service, with structures to be

constructed. 22# spoil yard K61+400 1.23 0.07 0.005 Under service, with structures to be

constructed. 23# spoil yard K61+900 0.57 0.02 0.005 Under service, with retaining wall

constructed. 24# spoil yard K63+200 0.24 0.01 0.008 Under service; platform divided;

structures to be constructed. 25# spoil yard K63+350 1.79 0.02 0.005 Under service, with retaining wall

constructed.

26# spoil yard K64+400 4.18 1.06 0.424

7# spoil yard in Lot 1 at Paliang Village Committee; retaining wall constructed.

27# spoil yard K82+340 5.97 0.76 0.38 Under service, with retaining wall

constructed. 28# spoil yard K89+645 2.47 0.27 0.162 Under service, with retaining wall

constructed.

Total 18.09 2.29 1.219

Construction site area: Seven construction camps are planned to be enabled for this project and all have been used now.

Construction camp area: Six construction camps are planned to be enabled for this project and all have been used now.

Table 5-13: Statistics of the Use of Construction Camp Area

No. Bid Section

Construction Camp Name

Pile No. and Location

Land Area (m2)

Later Disposal Direction

Remarks

1

Contract Section 1

Construction site(Renting houses)

K56+550 right side (0.13) Return and

retain Being used

2 Construction site K57+200 left side

0.33 Vegetation restoration

Being used

3 Mixing Station and

Component Prefabrication Yard

K57+200 right side

1.47 Vegetation restoration

Being used

4 Contract Construction site K83+860 (0.28) Return and Being

Page 53: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

47/178 6th Semi-annual Environmental Monitoring Report

No. Bid Section

Construction Camp Name

Pile No. and Location

Land Area (m2)

Later Disposal Direction

Remarks

Section 2 (Renting houses) right side retain used

5 1# Mixing Station K84+800 right side

cultivated land restoration

Being used

6 1# Component

Prefabrication Yard (Using Subgrade)

K96+140 right side

(1.07) Subgrade Being

used

Total 15.45

Construction road area: Construction road of this project is planned to be constructed 2.2 km. he construction is undergoing along with construction demand.

Topsoil piling area: No such yard is divided separately for storage of topsoil which has been stored on one side of the spoil yard to facilitate collection during construction.

The next photos show the implementation situation of soil and water conservation measures.

Current State of Section at K56+300 Retaining Wall Constructed at 23# Spoil Yard at

K61+900

Retaining wall constructed.

Subgrade drainage ditch constructed.

Page 54: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

48/178 6th Semi-annual Environmental Monitoring Report

Current State of 26# Spoil Yard at K64+400

Subgrade Excavation at K71+400 Current State of Subgrade Drainage Ditch at K73+600

Retaining wall constructed.

Page 55: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

49/178 6th Semi-annual Environmental Monitoring Report

Construction of Bridge Pile Foundation at

K74+990 Drainage Ditch of Section at K76+000

27# Spoil Yard at K82+340 with Retaining Wall and Drainage Ditch Constructed

Intercepting Ditch of Subgrade at K83+500 Current State of 27# Spoil Yard at K82+340

Retaining wall constructed.

Drainage ditch constructed.

Intercepting ditch constructed.

Page 56: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

50/178 6th Semi-annual Environmental Monitoring Report

Subgrade Drainage Ditch Surrounding K88+100 Subgrade Drainage Ditch Surrounding K89+200

28# Spoil Yard at K89+645 with Retaining Wall and Drainage Ditch Constructed

Drainage ditch constructed.

Drainage ditch constructed.

Retaining wall and drainage ditch constructed.

Page 57: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

51/178 6th Semi-annual Environmental Monitoring Report

Current State of 28# Spoil Yard at K89+645 Drainage Ditch of Section at K93+220

Current State of Section at K90+200

Page 58: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

52/178 6th Semi-annual Environmental Monitoring Report

Current State of Project’s Ending Point at Meng’a

(3)Existing Problems and Suggestions

According to this site monitoring, Lancang – Meng'a Highway project is under peak construction period, the implementation of soil and water conservation to be strengthened and further improved.

Combined with the "three simultaneous" system of soil and water conservation in development and construction projects, the following suggestions for the Employer are proposed according to the existing problems in soil and water conservation of Lancang – Meng'a Highway Project.

1) The procedures for earth-rock excavation are in progress, but topsoil stripping and collection is not seriously conducted and the water and soil conservation measures are delayed; see the following figures.

Suggestions for improvement: Please adhere to the “three simultaneous” system for water and soil conservation. During construction, the follow-up of water and soil conservation measures shall be strengthened, and multiple forms of water and soil conservation measures can be implemented at the current earth-rock excavation stage, e.g., temporary drainage, temporary cover, temporary protection with woven bags of soil, use of timber piles, provision of protective fence and so on; topsoil stripping and reutilization shall be strictly implemented.

Page 59: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

53/178 6th Semi-annual Environmental Monitoring Report

K64+000 Subgrade Excavation K76+000 Subgrade

Current Situation of K90+200 Section

2) During excavation of earth and rocks, the excavated earth and rocks are not removed and disposed to the spoil disposal area. The water and soil loss caused by the lateral spoil is most serious and has big impact on the surrounding environment.

Suggestions for improvement: the spoil shall not be disposed laterally, while instead it shall be transferred to the spoil disposal area to stack and store properly. For the construction sections along the river, retaining protection shall be strengthened, and the spoil shall be transferred promptly so as to avoid it entering the river. It is prohibited to dump the spoil into the river. At present, water and soil conservation measures like temporary drainage, temporary cover, temporary filling with woven bags of soil, use of timber piles and so on can be adopted.

Topsoil stripping and reutilization

Strengthen the retaining protection for the construction sections along the river, and pay attention to the simultaneous follow-up of water and soil conservation measures!

Page 60: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

54/178 6th Semi-annual Environmental Monitoring Report

Nancha River Section near K56+000

Nancha River Section near K56+000 Nancha River Section near K58+000

3) Package I: For the 26# spoil yard (K64+400), retaining measures have been provided, but the water cut-off measures are not completely implemented and the muck is not compacted stage by stage. Therefore, due to abundant local rainfall, obvious surface and gully erosion phenomena as well as sludge along the water scouring have occurred under the rain wash and effect of gravity.

Forbid to dispose the spoil laterally; implement temporary measures!

Remove the muck of the river

Page 61: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

55/178 6th Semi-annual Environmental Monitoring Report

26# Spoil Disposal Area (K64+400) in Package I of Paliang Village

Improve water cut-off and drainage measures, and compact the stacked spoil stage by stage.

Page 62: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

56/178 6th Semi-annual Environmental Monitoring Report

Suggestions for improvement: please timely improve the measures for external water cut-off and internal drainage. At present, on the outer side of the scope of spoil stacking in the spoil disposal area, temporary drainage ditches can be firstly used to divert water flow so as to control the flushing of spoil stacking. When construction conditions are met in the later stage, permanent drainage ditches are used to cut off and divert the peripheral catchments and the spoil stacking catchments. Besides, the stacked spoil shall be compacted stage by stage according to the design requirements.

4) The package I K68+500 Hege old stockade comprehensive utilization, the waste residue stacking is not reasonable, the lack of drainage measures, due to the local rainfall, under the action of rainwater scour, it is very easy to produce obvious soil erosion phenomenon.

Suggestion for improvement: fully reserve the drainage channel of seasonal gully, and make use of land improvement in a comprehensive way to restore the land in time, cover soil and plough, and restore the ability of land cultivation as soon as possible.

Hege old village K68+500

Reserving the drainage channel, covering the soil and returning the ploughing

Page 63: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

57/178 6th Semi-annual Environmental Monitoring Report

5) In terms of the 27# spoil yard (K82+340) in Package II, retaining barricades and drainage ditches have been constructed, while the stacked spoil is not compacted stage by stage, which does harm to the stability of spoil. Besides, there are farm lands in the peripheral area, so the environment will be influenced if the disposal area is under poor management.

Suggestion for improvement: improve relevant measures as per the design requirements; compact the stacked spoil; strengthen the retaining protection so as to stop the spoil from sliding outward.

27# Spoil Disposal Area (K82+340) Retaining Barricades and Drainage Ditches Constructed

Compact the stacked spoil; strengthen management and protection; second plowing is recommended in the later stage

Page 64: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

58/178 6th Semi-annual Environmental Monitoring Report

6) In terms of the 28# spoil yard (K89+645) in Package II, retaining barricades and drainage ditches have been constructed, but the stacked spoil is not compacted stage by stage, which does harm to the stability of spoil. Besides, there are farm lands in the peripheral area, so the stacked spoil may slide outward and thus influence the environment if the disposal area is under poor management.

Suggestion for improvement: improve relevant measures as per the design requirements; compact the stacked spoil; strengthen the retaining protection so as to stop the spoil from sliding outward.

27# Spoil Disposal Area (K89+645) Retaining Barricades and Drainage Ditches Constructed

Compact the stacked spoil; strengthen management and protection; second plowing is recommended in the later stage

Page 65: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

59/178 6th Semi-annual Environmental Monitoring Report

(4) Other recommendations:

i. The above problems and suggestions thereof are typical of the project site. For similar situations not mentioned in the project, please implement correspondingly;

ii. On April 19, 2017, the Yunnan Provincial Water Conservancy Department carried out supervision and inspection for the water and soil conservation of the project. Please implement all the work regarding water and soil conservation as per the inspection guidance and comments;

iii. In respect of the spoil disposal area, temporary soil stacking yard and borrow pit that need to be transferred for comprehensive utilization, a transfer agreement shall be signed, in which the responsibilities for safety, prevention and control of soil and water loss, as well as subsequent acceptance shall be defined and assigned;

iv. Retaining and barricading measures shall be provided for the spoil disposal area by adhering to the principle of “Retaining before Disposal”; the spoil shall be stacked stage by stage, and the established retaining barricades and drainage measures shall be managed and protected in a timely manner; the stability of muck shall be put into consideration in muck stacking and measures implementation;

v. During construction, if other units and local villagers borrow earth and rocks from this project or make comprehensive utilization of the topsoil, please implement the soil borrowing agreement to specify and assign the responsibilities for safety, prevention and control of soil and water conservation;

vi. Please pay attention to the follow-up of the measures for temporary drainage ditches, temporary retaining and barricades, as well as the greening measures of grass planting on slope in the construction areas;

vii. In the construction during dry season, please sprinkle water to lower dust, and during raining season, pay attention to the drainage, dredging and slurry clearing works for the muddy sections;

viii. Carry out greening recovery in a timely manner in the borrow pit;

ix. Avoid the spoil dispose behaviors that cause potential safety hazards. In case of any possibilities of hazards, handle the potential dangers promptly;

x. It is required to strengthen the retaining protection for the construction sections along the river to avoid the muck flowing into river; clear the muck near the river on the side slope and timely implement the greening recovery measures.

D-2. Ning'er - Jiangcheng - Longfu Road:

(1)Monitoring situation

Kunming Longhui Engineering Design Consulting Co., Ltd. undertakethe monitoring work of water and soil conservation for construction project along Ning’er - Jiangcheng - Longfu Road in May 2016.After receiving the task, our company has organized and established the soil and water conservation monitoring team and carried out the monitoring preparatory work of the project in25~29May, 2016. The monitoring will use the survey, patrol inspection and other monitoring methods to conduct monitoring for comprehensive understanding and data collection over the currently actual construction situations of the route. Currently, the monitoring team has carried out the preparation work of the Soil and water conservation Monitoring Implementation Plan of the Pu’erNing’er County-Jiangcheng - Sino-Vietnam No.3 Boundary Monument Highway Project according to the actual site situation and the relevant information collected.

The monitoring team conducted the filed monitoring on June, using survey, patrol and

Page 66: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

60/178 6th Semi-annual Environmental Monitoring Report

other monitoring methods to cover the main works, spoil disposal areas, borrow areas, construction camp sites, temporary stockyard, access road and other areas. Up to December 30, 2018, the earth-rock excavation for subgrade along the line was almost completed and mortar rubble retaining wall protection and subgrade drainage ditch had been performed for some road sections.

(2)Implementation of Soil and Water Conservation Measures

Disturbed surface area:Up to December 2018, earth-rock excavation was underway along the line; earth-rock excavation in some sections was completed, ready for placement of subgrade and pavement. The cumulative disturbed area was 865.98ha.

Sand stocking field:According to the site survey by the monitoring team, the sand quarries have not been put into use.

Gravel-soil-taken field: According to the site survey by the monitoring team, the gravel-soil-taken field have not been put into use.

Road area:Most of the road sections in this line had been disturbed and were in earth-rock excavation upon monitoring group's arrival on site, and it is shown from field investigation and comparison by monitoring group that there is no factor restricting water and soil conservation for construction line for the project. The following photos show the details of some sections during this report period.

The starting section of the Ning River Road

Page 67: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

61/178 6th Semi-annual Environmental Monitoring Report

Starting Point of the Road Connected with

Ning’er-Jinggu Highway Current Situation near K5+000 Banhai

K10+000 Longtangba K12+000 Ximenyanzi

Road Section near K8+200 Manlian Village

Page 68: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

62/178 6th Semi-annual Environmental Monitoring Report

K18+000 Ning’er Loop Line K19+700 Current Situation

Current Situation near K17+200 Babaoshu

Current Situation near K23+000 Wenquan Village and LaoxuZhai

Page 69: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

63/178 6th Semi-annual Environmental Monitoring Report

K23+847 Laoxu Stockaded Village 2# Bridge

Current Situation K26+000 Dalutang Current Situation

Current Situation near K29+800 Dalutang

K45+300 Shanshen Temple Pass K50+000 Mengxian Township

Page 70: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

64/178 6th Semi-annual Environmental Monitoring Report

Current Situation near K45+000 Kesa

K60+000 Xuande Current Situation K65+500 Lanniqing Current Situation

Current Situation near K78+000 Tiechang River

Page 71: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

65/178 6th Semi-annual Environmental Monitoring Report

K75+000 Tiechanghe Current Situation K80+000 Caizidi Pass Current Situation

Current Situation near K80+000 Caizidi Pass

K90+000 Xianren Commune Current Situation K110+000 Liming Current Situation

Page 72: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

66/178 6th Semi-annual Environmental Monitoring Report

K115+000 Muhua Stockaded Village Road

Current Situation K125+000 Baka (Nanyin River) Current Situation

K138+000 Nanyin River Current Situation

K138+000 Nanyin River Current Situation K141+000 Baozang Township Current Situation

Page 73: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

67/178 6th Semi-annual Environmental Monitoring Report

Current Situation near K141+000 Baozang Township

Current Situation of Road Section at K146+000 Mengye River

Page 74: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

68/178 6th Semi-annual Environmental Monitoring Report

Current Situation near K153+000 Banhe

Township K161+000 Qiyi Bridge Current Situation

Current Situation of Road Section at K148+000 Mengye River

Current Situation of Road Section at K167+000 Lahu River

Page 75: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

69/178 6th Semi-annual Environmental Monitoring Report

Current Situation of road Section at K178+000 Ganmazhai Tuanpo

Current Situation of Road Section at K180+000 Ganmazhai Tuanpo

Page 76: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

70/178 6th Semi-annual Environmental Monitoring Report

K171+000 Lahu River Current Situation K184+000 Road Current Situation

Current Situation of Road Section at K185+000 Niuluo River

Current Situation of K191+000 Road Section

Page 77: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

71/178 6th Semi-annual Environmental Monitoring Report

K189+000 Niuluo River Current Situation K202+000 Mingzi Mountain Current Situation

Current Situation of Road Section near K207+000

Current Situation of Road Section near K207+000~K211+000 Dazhupeng

Page 78: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

72/178 6th Semi-annual Environmental Monitoring Report

Current Situation of Road Section near K215+100 Liangzitian

Current Situation of Road Section near K217+000 Liangzitian

Page 79: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

73/178 6th Semi-annual Environmental Monitoring Report

K211+000 Dazhupeng Current Situation K227+000 Longfu Current Situation

Current Situation of Road Section near K221+000 Longdong River

Page 80: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

74/178 6th Semi-annual Environmental Monitoring Report

Current Situation of K244+500 Project Ending Point

K230+000 Current Situation K244+799.25 Project Ending Point (No. 3

Sino-Vietnam Boundary Monument)

Spoil disposal area::According to Owner-supplied data and field survey, up to December 31, 2018, 56 spoil disposal areas are used, cover the total field of 103.07ha, with a design capacity of 13.175 million m³. To date, the cumulative spoil is about 11.038 million m³

Vietnam boundary

Page 81: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

75/178 6th Semi-annual Environmental Monitoring Report

Table 5-14: Project Waste Slags Characteristic and Piling Slags Conditions

Contract Section Spoil

Disposal Area No.

Center Station Location Landform

Type and Area of Occupied Land (ha) Spoil Volume

(mil. m³)

Capacity (mil. m³)

Spoil Elevation

Max. Stacking Height

Catchment Area Remarks

Woodland Meadow Wasteland Water Area Terrace Subtotal (m) (m) (km2)

Contract Section 1 (K0+000~K18+140)

Q1 K0+380 100m to the left Mild slope 0.75 0.23 0.98 0.12 0.15 1413-1428 15 0.01 Under

service, with retaining wall constructed.

Q2 K7+400 250m to the left Gully 2.84 1.21 4.05 0.18 0.2 1454-1469 15 0.02 Under

service, Measure lag.

Q3 K14+600 160m to the left Gully 1.60 1.60 0.155 0.18 1420-1437 17 0.03 Under

service, with retaining wall constructed.

Q4 K17+200 5m to the left Gully 4.22 2.81 7.03 0.225 0.25 1311-1316 5 0.01

End of service, using

for local building

materials storage.

Contract Section 2 (K18+140~K35+000)

Q5 K24+500 100m to the left Gully 2.47 1.06 3.53 0.321 0.35 1386-1399 13 0.06

Under service, with retaining wall and drainage

ditch constructed.

Q6 K29+960 50m to the left Gully 5.14 1.28 6.42 0.654 0.7 1473-1489 16 0.10 Under

service, Measure lag.

Q7 K32+340 650m to the left Gully 7.98 2.01 9.99 1.724 1.9 1480-1521 41 0.12 Under

service, Measure lag.

Contract Section 3 (K35+000~K52+000) Q8 K35+300 190m to the left Gully 2.75 2.75 0.411 0.45 1544-1564 20 0.08

Under service,

Measure lag.

Contract Section 4 (K52+000~K72+000)

Q9 K56+500 100m to the left Mild slope 0.89 0.89 0.12 0.15 1299-1317 18 0.03 Under

service, with retaining wall constructed.

Q10 K57+400 60m to the left Mild slope 0.62 0.62 0.06 0.1 1291-1302 11 0.01 Under

service, Measure lag.

Q11 K62+300 50m to the right Gully 1.08 0.46 1.54 0.1 0.13 1290-1298 8 0.03 Under

service, with retaining wall constructed.

Q12 K65+440 130m to the right Mild slope 0.61 1.44 2.05 0.17 0.2 1254-1267 13 0.01 Under

service, Measure lag.

Contract Section 5 (K72+000~K101+000)

Q13 K75+260 190m to the right Mild slope 1.29 1.29 0.12 0.16 1916-1928 12 0.01 Under

service, Measure lag.

Q14 K80+280 20m to the right Gully 1.45 1.45 0.153 0.2 1780-1795 15 0.10 Under

service, Measure lag.

Q15 K82+700 200m to the right Gully 0.76 0.76 0.084 0.12 1710-1724 14 0.07 Under

service, Measure lag.

Q16 K88+320 120m to the left Mild slope 1.03 1.03 0.077 0.11 1288-1300 12 0.06 Under

service, Measure lag.

Page 82: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

76/178 6th Semi-annual Environmental Monitoring Report

Contract Section Spoil

Disposal Area No.

Center Station Location Landform

Type and Area of Occupied Land (ha) Spoil Volume

(mil. m³)

Capacity (mil. m³)

Spoil Elevation

Max. Stacking Height

Catchment Area Remarks

Woodland Meadow Wasteland Water Area Terrace Subtotal (m) (m) (km2)

Q17 K99+000 20m to the left Gully 2.00 2.00 0.44 0.48 1076-1106 30 0.08 Under

service, Measure lag.

Contract Section 6 (K101+000~K129+500)

Q18 K104+640 20m to the left Gully 1.28 1.28 0.351 0.39 1148-1178 30 0.07 Under

service, Measure lag.

Q19 K114+500 20m to the left Gully 2.01 2.01 0.306 0.35 1248-1266 18 0.06 Under

service, Measure lag.

Contract Section 7 (K129+500~K158+000)

Q20 K126+550 10m to the right Mild slope 0.75 0.75 0.045 0.08 1026-1035 9 0.03 Under

service, with retaining wall constructed.

Q21 K127+850 30m to the left Gully 1.25 1.25 0.2 0.26 1088-1108 20 0.05 Stop service, measure lag.

Q22 K130+480 50m to the right Gully 5.37 5.37 0.55 0.6 971-986 15 0.06 Stop service, measure lag.

Q23 K139+180 45m to the left Mild slope 4.75 4.75 0.52 0.57 769-783 14 0.10 Under

service, with retaining wall constructed.

Q24 K141+600 20m to the right Mild slope 0.86 0.86 0.088 0.12 780-791 11 0.05 Under

service, with retaining wall constructed.

Q25 K152+800 20m to the right Mild slope 3.49 3.49 0.675 0.7 808-829 21 0.06 End of

service,with retaining wall constructed.

Q26 K155+860 20m to the right Mild slope 0.87 0.87 0.13 0.16 828-844 16 0.05 Under

service, with retaining wall constructed.

Contract Section 8 (K158+000~K185+000)

Q27 K159+120 20m to the right Mild slope 0.27 0.27 0.025 0.04 838-851 13 0.02 Under

service, with retaining wall constructed.

Q28 K162+200 30m to the right Mild slope 0.51 0.51 0.047 0.07 840-852 12 0.02 Under

service, with retaining wall constructed.

Q29 K165+000 30m to the right Mild slope 0.45 0.45 0.025 0.04 857-865 8 0.02 Under

service, Measure lag.

Q30 K167+000 100m to the left Mild slope 0.20 0.47 0.67 0.05 0.08 847-858 11 0.02 Under

service, with retaining wall constructed.

Q31 K171+200 20m to the right Mild slope 0.36 0.36 0.03 0.06 852-863 11 0.02 Under

service, Measure lag.

Q32 K174+000 20m to the right Mild slope 1.90 1.90 0.16 0.2 910-922 12 0.04

Under service, with temporary

block constructed.

Q33 K177+550 30m to the left Gully 2.53 2.53 0.3 0.34 975-992 17 0.06 Under

service, Measure lag.

Page 83: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

77/178 6th Semi-annual Environmental Monitoring Report

Contract Section Spoil

Disposal Area No.

Center Station Location Landform

Type and Area of Occupied Land (ha) Spoil Volume

(mil. m³)

Capacity (mil. m³)

Spoil Elevation

Max. Stacking Height

Catchment Area Remarks

Woodland Meadow Wasteland Water Area Terrace Subtotal (m) (m) (km2)

Q34 K179+200 60m to the left Mild slope 0.68 0.68 0.05 0.075 1038-1048 10 0.05

Under service, with temporary

block constructed.

Q35 K181+200 40m to the left Mild slope 1.89 1.89 0.11 0.16 1015-1025 10 0.03 Under

service, with retaining wall constructed.

Q36 K184+400 80m to the right Mild slope 0.83 0.83 0.064 0.1 919-929 10 0.03 Under

service, retaining wall constructing。

Contract Section 9 (K185+000~K212+000)

Q37 K187+000 20m to the right Mild slope 1.77 1.77 0.15 0.2 893-908 15 0.05 Under

service, with retaining wall constructed.

Q38 K188+200 50m to the right Gully 1.23 1.23 0.225 0.27 920-942 22 0.08 Under

service, Measure lag.

Q39 K192+000 20m to the right Mild slope 3.27 3.27 0.36 0.4 910-925 15 0.05 Under

service, with retaining wall constructed.

Q40 K193+460 50m to the right Mild slope 0.64 0.64 0.045 0.07 912-922 10 0.04 Under

service, Measure lag.

Q41 K194+760 30m to the right Mild slope 0.55 1.28 1.83 0.15 0.2 933-945 12 0.08 Under

service, Measure lag.

Q42 K196+750 20m to the right Mild slope 0.84 1.27 2.11 0.106 0.15 951-959 8 0.10 Under

service, Measure lag.

Q43 K204+880 10m to the right Gully 1.02 1.02 0.093 0.14 1124-1136 12 0.06 Under

service, with retaining wall constructed.

Q44 K209+960 20m to the right Gully 0.67 0.67 0.12 0.17 1233-1255 22 0.10 Under

service, Measure lag.

Q45 K210+420 20m to the right Gully 0.60 0.60 0.12 0.17 1190-1212 22 0.11 Under

service, Measure lag.

Q46 K210+760 20m to the right Mild slope 0.47 0.47 0.08 0.12 1171-1192 21 0.11 Under

service, Measure lag.

Contract Section 10 (K212+000~K234+069.52)

Q47 K215+100 10m to the right Mild slope 1.00 1.00 0.09 0.13 973-983 10 0.05 Under

service, Measure lag.

Q48 K215+400 15m to the right Mild slope 1.62 1.62 0.105 0.14 950-959 9 0.05 Under

service, Measure lag.

Q49 K216+350 10m to the right Mild slope 0.70 0.70 0.025 0.04 900-905 5 0.02 Under

service, Measure lag.

Q50 K217+600 20m to the right Mild slope 0.55 0.55 0.021 0.04 850-856 6 0.03 Under

service, with retaining wall constructed.

Page 84: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

78/178 6th Semi-annual Environmental Monitoring Report

Contract Section Spoil

Disposal Area No.

Center Station Location Landform

Type and Area of Occupied Land (ha) Spoil Volume

(mil. m³)

Capacity (mil. m³)

Spoil Elevation

Max. Stacking Height

Catchment Area Remarks

Woodland Meadow Wasteland Water Area Terrace Subtotal (m) (m) (km2)

Q51 K218+700 30m to the right Mild slope 0.99 0.43 1.42 0.121 0.16 815-828 13 0.10 Under

service, Measure lag.

Q52 K219+700 20m to the right Mild slope 0.47 0.47 0.028 0.05 782-790 8 0.02 Under

service, Measure lag.

Q53 K220+220 15m to the right Mild slope 0.69 0.69 0.03 0.05 769-775 6 0.02 Under

service, Measure lag.

Q54 K223+100 20m to the right Mild slope 1.80 1.80 0.113 0.16 704-714 10 0.04 Under

service, with retaining wall constructed.

Q55 K224+700 20m to the left Mild slope 1.17 1.17 0.059 0.09 664-672 8 0.05 Under

service, with retaining wall constructed.

Q56 K234+300 20m to the left Mild slope 0.53 0.81 1.34 0.157 0.2 680-695 15 0.07 Under

service, Measure lag.

Total 80.8 7.83 4.58 4.02 5.84 103.07 11.038 13.175

Page 85: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

79/178 6th Semi-annual Environmental Monitoring Report

K14+600 Spoil Disposal Area

K24+500 Spoil Disposal Area

Constructed intercepting ditch

Constructed retaining facility

Page 86: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

80/178 6th Semi-annual Environmental Monitoring Report

K29+960 Spoil Disposal Area

K32+340 Spoil Disposal Area

Page 87: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

81/178 6th Semi-annual Environmental Monitoring Report

K45+000 Spoil Disposal Area

K56+500 Spoil Disposal Area

Constructed retaining facility

Page 88: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

82/178 6th Semi-annual Environmental Monitoring Report

K62+300 Spoil Disposal Area

K99+000 Spoil Disposal Area

Page 89: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

83/178 6th Semi-annual Environmental Monitoring Report

K104+640 Spoil Disposal Area

K126+550 Spoil Disposal Area

Page 90: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

84/178 6th Semi-annual Environmental Monitoring Report

K130+480 Spoil Disposal Area

K139+180 Spoil Disposal Area

Page 91: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

85/178 6th Semi-annual Environmental Monitoring Report

K141+600 Spoil Disposal Area

K152+800 Spoil Disposal Area

Constructed retaining facility

Page 92: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

86/178 6th Semi-annual Environmental Monitoring Report

K155+860 Spoil Disposal Area

K162+200 Spoil Disposal Area

Constructed retaining facility

Page 93: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

87/178 6th Semi-annual Environmental Monitoring Report

K174+000 Spoil Disposal Area

K177+500 Spoil Disposal Area

Page 94: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

88/178 6th Semi-annual Environmental Monitoring Report

K179+200 Spoil Disposal Area

K181+200 Spoil Disposal Area

Page 95: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

89/178 6th Semi-annual Environmental Monitoring Report

K184+400 Spoil Disposal Area

K185+300 Spoil Disposal Area(Comprehensive utilization of the highway maintenance area)

Constructed retaining facility

Page 96: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

90/178 6th Semi-annual Environmental Monitoring Report

K187+000 Spoil Disposal Area

K188+200 waste residue field

Page 97: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

91/178 6th Semi-annual Environmental Monitoring Report

K192+000 Spoil Disposal Area

K193+460 Spoil Disposal Area

Page 98: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

92/178 6th Semi-annual Environmental Monitoring Report

K215+100

K215+400 Spoil Disposal Area

Page 99: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

93/178 6th Semi-annual Environmental Monitoring Report

K223+100 Spoil Disposal Area

K224+700 Spoil Disposal Area

Constructed retaining facility

Page 100: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

94/178 6th Semi-annual Environmental Monitoring Report

K234+300 Spoil Disposal Area

Construction camp area: It is shown from field investigation by monitoring group that since the Project is now in construction, construction site is set as needed. Table 5-14 show the details.

Construction camp area: According to the site survey of the monitoring team, since the project is now in construction, construction site is set as needed, and twenty-nine construction camp areas are put in use. The following photos and table show the details.

Construction Camp Area at K3+160 Construction Site at K220+150

Page 101: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

95/178 6th Semi-annual Environmental Monitoring Report

Table 5-15: Statistics of the Use of Construction Camp Area

No. Bid Section

Pile No. and Location

Number of Persons in the

Camp Land

Area (m2) Environmental

Health on Construction Site

Whether There is Water Source in

Peripheral Range of 500m

Geological Conditions

(Collapse and Landslide Area as

well as Debris Flow Area)

① Domestic Sewage Treatment Measures

② Domestic Waste Disposal Measures

③ Remarks

1

Contract Section 1

Weiguo Forestry Bureau of Ninger

County 20 2000 Good No Safety

a. Restaurant wastewater treatment: It is suggested to transfer the wastewater to

peasant households for cultivation; b. fecal sewage; Build water closet

Cover into local domestic waste treatment system

Residence leasing

2 K3+160 25 900 Good None Safety

a. Restaurant wastewater treatment: It is suggested to transfer the wastewater to

peasant households for cultivation; b. fecal sewage; Build water closet

Cover into local domestic waste treatment system

Residence leasing

3 K12+600 25 1100 Good None Safety

a. Restaurant wastewater treatment: It is suggested to transfer the wastewater to

peasant households for cultivation; b. fecal sewage; Build water closet

Cover into local domestic waste treatment system

Residence leasing

4 Contract Section 2 K19+150 40 1230

Good health conditions, with

disinfection measures taken

Domestic water source Good Discharge into sedimentation and

treatment tank of the village/township Cover into local domestic waste treatment system

Residence leasing

5 Contract Section 3 K47+200 25 2000 Good None Good geological

conditions Transfer to peasant households for

cultivation

Village/township-level domestic waste treatment

system

Residence leasing

6

Contract Section 4

K58+875 11 250 Good Available Good Discharge into sedimentation tank Put into designated dump pit Self-erection

7 K60+875 15 150 Good Available Good Discharge into sedimentation tank Put into designated dump pit Self-erection

8 K58+900 8 90 Good None Good Discharge into sedimentation tank Put into designated dump pit Leasing

9 K55+660 15 110 Good None Good Discharge into sedimentation tank Put into designated dump pit Leasing

10 Contract Section 5

Project site at K88+800 23 1500 Good None Good geological

conditions Transfer to peasant households for

cultivation

Village/township-level domestic waste treatment

system Self-erection

11

Contract Section 6

1km at the right side of K110+800 (Liming

Township) 40 1000 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

12 1km at the left side of

K108+980 (Liming Township)

23 300 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

13 The left side of

K116+530 (beside the highway)

15 200 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

14 The left side of

K119+100 (beside the highway)

10 150 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

Page 102: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

96/178 6th Semi-annual Environmental Monitoring Report

No. Bid Section

Pile No. and Location

Number of Persons in the

Camp Land

Area (m2) Environmental

Health on Construction Site

Whether There is Water Source in

Peripheral Range of 500m

Geological Conditions

(Collapse and Landslide Area as

well as Debris Flow Area)

① Domestic Sewage Treatment Measures

② Domestic Waste Disposal Measures

③ Remarks

15 The left side of

K120+380 (beside the highway)

15 300 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

16

Contract Section 7

The right side of K140+800 (Baozang

Town) 40 600 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

17 The right side of

K153+980 (beside the highway)

19 300 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

18 The right side of

K137+800 (beside the highway)

15 250 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

19 The right side of

K129+600 (beside the highway)

20 300 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build water closet and septic tank for treatment to meet

standards before discharge.

Cover into local domestic waste treatment system

Residence leasing

20

Contract Section 8

K162+760~K162+900 13 400 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Cover into local domestic waste treatment system

Residence leasing

21 K168+300 8 350 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Cover into local domestic waste treatment system

Residence leasing

22 K168+600 13 450 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Cover into local domestic waste treatment system

Residence leasing

23 K175+620 8 300 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Cover into local domestic waste treatment system

Residence leasing

Page 103: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

97/178 6th Semi-annual Environmental Monitoring Report

No. Bid Section

Pile No. and Location

Number of Persons in the

Camp Land

Area (m2) Environmental

Health on Construction Site

Whether There is Water Source in

Peripheral Range of 500m

Geological Conditions

(Collapse and Landslide Area as

well as Debris Flow Area)

① Domestic Sewage Treatment Measures

② Domestic Waste Disposal Measures

③ Remarks

24 K185+000 12 400 Good No Good

a. Restaurant wastewater treatment: Transfer to peasant households for

cultivation; b. fecal sewage: Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Cover into local domestic waste treatment system

Residence leasing

25

Contract Section 9

K205+300 40 500 Good None Good It is suggested to transfer to peasant households for cultivation Built water closet Residence

leasing

26 K185+100 20 100 Good None Good It is suggested to transfer to peasant households for cultivation

Build pit toilet and take out and transfer fecal sewage

regularly to peasant households as fertilizer.

Residence leasing

27

Contract Section 10

K215+600 10 200 Good No Good Domestic Sewage: For cultivation fecal sewage: Build water closet

Sanitary landfill in the place far from water body and village/township upon

incineration

Residence leasing

28 K220+150 30 600 Good No Good Domestic Sewage: For cultivation fecal sewage: Build water closet

Sanitary landfill in the place far from water body and village/township upon

incineration

New portable house

29 K230+200 12 200 Good No Good Domestic Sewage: For cultivation fecal sewage: Build water closet

Sanitary landfill in the place far from water body and village/township upon

incineration

Residence leasing

Total 363 16230

Page 104: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

98/178 6th Semi-annual Environmental Monitoring Report

Construction road area: According to the site survey of the monitoring team, since the project is in construction, seventeen construction roads have been planned with the total length of 7.6km to cover field of 5.32ha. The works mainly refer to reconstruction and extension, and there are many available peripheral roads; additional part is mainly in bare state, with obvious water loss and soil erosion.

Utilization of Access Road near K10+000

Longtangba Nanyin River Access Road at K139+000 (Peripheral Area and Subgrade Used)

Topsoil piling area: According to the site survey of the monitoring team, since topsoil stripped in construction is stacked at a corner of spoil disposal area, and stacked at nearby subgrade in some road sections, and there is no topsoil yard set independently.

(3)Implementation of water and soil conservation measures

According to monitoring survey and analysis of project construction data, water and soil conservation measures already implemented include:

Engineering measures: 200,000m³ topsoil stripping and collection; 1,838m/21,867m³ retaining wall; 25,900m/44,030m³ intercepting and drainage ditches.

Vegetation measures: planting 64,832.83m² grass.

Temporary measures: using bagged soil to protect a length of 4,927m; temporary drain ditch 52,285m.

The following photos show the implemented measures of water and soil conservation.

Topsoil stripping in K3+500 Dazhai section

Subgrade drain ditch and topsoil stripping at K10+000 Longtangba

Page 105: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

99/178 6th Semi-annual Environmental Monitoring Report

Retaining wall completed at K56+500 spoil

disposal area Retaining wall completed at K152+800 spoil

disposal area

Retaining wall completed at K162+200 spoil

disposal area K221+000 subgrade drain ditch

Slope landscaping Slope landscaping

Disturbed area landscaping Disturbed area landscaping

Page 106: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

100/178 6th Semi-annual Environmental Monitoring Report

Disturbed area landscaping Disturbed area landscaping

(4)Existing Problems and Suggestions

1) Road area

The main existing problems include: spoil is not stacked reasonably after main line excavation, there is transverse spoil in some road sections, transverse spoil mass indicates hazard of landslide and debris flow, bare surface suffers from visible erosion upon rainwater scouring, and water and soil conservation measures for main line are behind schedule.

Suggestions on Perfection:

i. Collectible topsoil in project area shall be stripped and stacked in centralized mode for greening in the future;

ii. Spoil shall be moved to spoil disposal area and compacted and stacked by platform, transverse spoil is prohibited, and the spoil not stacked in subgrade backfilling area and spoil disposal area shall be cleaned, and greening and restoration shall be provided for the area occupied by transverse spoil;

iii. "Three-simultaneous" system for water and soil conservation shall be implemented to strengthen simultaneous implementation of water and soil conservation measures; in case permanent measures cannot be implemented at the moment during construction, temporary measures shall be strengthened, such as temporary retaining by woven bag filled with soil, temporary covering and temporary drainage;

iv. In case of any individual or unit in need to borrow spoil from the Project for comprehensive utilization during construction, it is necessary to sign borrow agreement to confirm spoil direction, purpose as well as responsibilities for safety, water and soil conservation, prevention and control;

v. Patrol shall be intensified for the road section along the river, construction process shall be optimized, and retaining wall shall be strengthened to prevent spoil from the river and the influence on flood discharge of river course; for construction for the road section in mountain land, drainage channel shall be reserved adequately in natural gully, and the gully may not be buried or occupied by spoil to prevent the genration of man-made factors for landslide, torrential flood and debris flow.

Page 107: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

101/178 6th Semi-annual Environmental Monitoring Report

Transverse Spoil and Stacking at Will in Road Section near K3+160

Road Section near K45+000 Kesa

Spoil shall be moved to spoil disposal area and stacked by standards; in case of local need for spoil for comprehensive utilization, relevant agreement shall be signed to confirm spoil direction, purpose as well as the responsibilities for safety, water and soil conservation, prevention and control; in earth-rock excavation stage, water and soil conservation measures may be taken, such as temporary drainage ditch, temporary covering and woven bag filled with soil may be taken for temporary retaining.

Spoil shall be moved to spoil disposal area and stacked by standards; in case of local need for spoil for comprehensive utilization, relevant agreement shall be signed to confirm spoil direction, purpose as well as the responsibilities for safety, water and soil conservation, prevention and control; in earth-rock excavation stage, water and soil conservation measures may be taken, such as temporary drainage ditch, temporary covering and woven bag filled with soil may be taken for temporary retaining.

Page 108: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

102/178 6th Semi-annual Environmental Monitoring Report

K60+000 Xuande Current Situation K92+000 Xianren Commune Current Situation

Road Section near K101+000 Manmushuliangzi

Transverse Spoil in Road Section near K102+500 Road Section in the Vicinity of K105+000

Temporary drainage ditch may be excavated to discharge water flow in rain season.

Spoil shall be moved to spoil disposal area and stacked by standards; the spoil in natural gully shall be cleaned to dredge water flow in the gully; water and soil conservation measures may be taken, such as temporary drainage ditch, temporary covering, woven bag filled with soil, and timber pile may be set for temporary retaining.

Spoil shall be moved to spoil

disposal area and stacked by

standards

Page 109: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

103/178 6th Semi-annual Environmental Monitoring Report

Road Section near K141+000 Baozang Township

Mengye River Road Section at K146+000 Mengye River Road Section at K151+000

Spoil shall be moved to spoil disposal area and stacked by standards; retaining wall shall be strengthened for the road section in construction along the river, and spoil shall be removed in time to prevent being fallen into the river, and it is prohibited to dump spoil into river course.

Page 110: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

104/178 6th Semi-annual Environmental Monitoring Report

Current Situation of Road Section at K178+000 Ganmazhai Tuanpo

Current Situation of Road Section at K178+000

Ganmazhai Tuanpo Current Situation of K180+000 Road Section

In case of local need for spoil for comprehensive utilization, it is necessary to sign relevant agreement to confirm spoil direction, purpose as well as responsibilities for safety, water and soil conservation, prevention and control; the residual spoil upon backfilling shall be moved to spoil disposal area in time and may not be dumped transversely for the reason that transverse spoil has poor stability, indicating obvious water loss and soil erosion, landslide hazard and obvious damage to surrounding vegetation in the influence of rainfall and gravity conditions. The ground shall be restored after spoil cleaning.

Timber pile fence may be erected, woven bag filled with soil may be taken for temporary retaining, and bare surface shall be restored in time.

Page 111: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

105/178 6th Semi-annual Environmental Monitoring Report

Current Situation of K191+000 Road Section

Current Situation of Road Section at K178+000

Ganmazhai Tuanpo Current Situation of Road Section at K184+600

Niuluo River

In case of local need for spoil for comprehensive utilization, it is necessary to sign relevant agreement to confirm spoil direction, purpose as well as responsibilities for safety, water and soil conservation, prevention and control; the residual spoil upon backfilling shall be moved to spoil disposal area in time and may not be dumped transversely; retaining wall shall be strengthened for the road section in construction along the river, and spoil shall be removed in time to prevent being fallen into the river, and it is prohibited to dump spoil into river course.

Page 112: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

106/178 6th Semi-annual Environmental Monitoring Report

Current Situation of Road Section near K217+000 Liangzitian

Spoil Fallen Into River Course From Road Slope

Near K220+000 Transverse Spoil in Road Section near K235+000

2) Spoil disposal area

Such conditions as lagging for water retaining, intercepting and drainage measures, unreasonable slag stacking technology, greater slag stacking area gradient, easy generation for water and soil loss due to rainwater erosion and no beneficial slag body stability; for some spoil disposal area, spoil-related safety problems still exist. The next photos and tables show the problem and suggestions of spoil disposal areas.

Spoil shall be moved to spoil disposal area and stacked by standards; retaining wall shall be strengthened for the road section in construction along the river, and spoil shall be removed in time to prevent being fallen into the river, and it is prohibited to dump spoil into river course.

Clear the muck into the spoil disposal area and implement the reasonable stockpiling.

The spoil in river course shall be cleaned in time to avoid influence on flood drainage of river course

Page 113: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

107/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K14+600 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.05ha

Volume of Spoil 9.65×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities

A 300m of soil intercepting/drainage ditch has already been built at the upstream of the spoil disposal area.

Problems There is no retaining facility at the downstream of the spoil; the spoil surface is rough; the drainage in the spoil disposal area is disordered; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; retaining facilities shall be constructed at the downstream; the spoil surface shall be leveled, and then inside drainage ditches shall be arranged; slope cutting and stepping shall be conducted, and the overall slope ratio shall be less than 1:2.

Conditions of Downstream of Spoil Disposal Area

Temporary retaining facilities shall be added asap.

The temporary intercepting ditch has already been constructed. After the rainy season,

the follow-up design shall be followed to construct permanent retaining facilities asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

Downstream of Spoil Disposal Area

Page 114: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

108/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K14+600

Page 115: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

109/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K24+500 Type of Spoil Disposal Area Valley type Disturbed Surface

Area 2.73ha

Volume of Spoil 21.68×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? No

Constructed Facilities A 30m of temporary retaining facility has already been constructed at the downstream.

Problems The retaining facility at the downstream of the spoil cannot meet the requirements; there is no intercepting/drainage facility at the upstream of the spoil disposal area; the spoil surface is rough; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged, and timely site restoration shall be conducted.

Conditions of Downstream of Spoil Disposal Area

Temporary retaining facilities shall be added asap.

Temporary drainage facilities shall be constructed in the spoil disposal area asap according to the topography.

The temporary retaining facility has already been constructed.

After the rainy season, the follow-up design shall be followed to construct permanent facilities asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

Downstream of Spoil Disposal Area

Page 116: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

110/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K24+500

Page 117: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

111/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K29+960 Type of Spoil Disposal Area Valley type Disturbed Surface

Area 3.73ha

Volume of Spoil 52.89×104 m3 Original design

or not? No Continue to be used for spoil disposal or

not? Yes

Constructed Facilities A 500m of temporary drainage ditch has already been arranged.

Problems The temporary drainage ditch has already been arranged, but due to the great catchment area at the upstream of the spoil disposal area, it cannot meet the requirements, and thus severe spoil surface scouring is caused; no slope stepping has been conducted; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed asap.

The temporary drainage facility has already been arranged.

The scattered spoil shall be cleared.

Temporary retaining facilities shall be built asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent facilities asap.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Downstream of Spoil Disposal Area

Page 118: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

112/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K29+960

Page 119: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

113/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K32+340 Type of Spoil Disposal Area Valley type Disturbed

Surface Area 4.48ha

Volume of Spoil 71.96×104 m3 Original design

or not? Following 7#

Continue to be used for spoil

disposal or not?

Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the spoil surface is rough; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Intercepting/drainage facilities shall be constructed asap.

The spoil surface shall be leveled.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Downstream of Spoil Disposal Area

Page 120: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

114/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K32+340

Page 121: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

115/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K45+000 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 4.16ha

Volume of Spoil 22.86×104 m3 Original design

or not? No

Continue to be used for spoil

disposal or not?

Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; there is no retaining facility at the downstream; the drainage in the spoil disposal area is disordered; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Temporary retaining facilities shall be arranged asap.

Intercepting/drainage facilities shall be constructed. After the rainy season,

the follow-up design shall be followed to construct permanent retaining facilities asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Page 122: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

116/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K45+000

Page 123: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

117/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K56+500 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.87ha

Volume of Spoil 11.50×104 m3 Original design

or not? Following 10# Continue to be used for spoil

disposal or not? No

Constructed Facilities A 300m of mortar masonry retaining wall.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged, and timely site restoration shall be conducted.

Conditions of Downstream of Spoil Disposal Area

The retaining facility has been provided.

Intercepting/drainage facilities shall be constructed.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

Downstream of Spoil Disposal Area

Page 124: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

118/178 6th Semi-annual Environmental Monitoring Report

Boundary of Spoil Disposal Area

3D Rendering of Spoil Disposal Area at K56+500

Page 125: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

119/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K62+300 Type of Spoil Disposal Area Valley type Disturbed

Surface Area 1.04ha

Volume of Spoil 6.50×104 m3 Original design or

not? Following

11#

Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the spoil surface is rough; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; bridleway and inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Downstream of Spoil Disposal Area

Page 126: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

120/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K62+300

Boundary of Spoil Disposal Area

Page 127: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

121/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K99+000 Type of Spoil Disposal Area Valley type Disturbed

Surface Area 0.40ha

Volume of Spoil 8.25×104 m3 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Downstream of Spoil Disposal Area

Page 128: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

122/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K99+000

Boundary of Spoil Disposal Area

Page 129: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

123/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K104+640 Type of Spoil Disposal Area Valley type Disturbed

Surface Area 0.46ha

Volume of Spoil 5.63×104 m3 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Downstream of Spoil Disposal Area

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Page 130: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

124/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K104+460

Boundary of Spoil Disposal Area

Page 131: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

125/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K126+550 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.23ha

Volume of Spoil 3.60×104 m3 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

The house has been relocated.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Downstream of Spoil Disposal Area

Page 132: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

126/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K126+550

Boundary of Spoil Disposal Area

Page 133: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

127/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K130+480 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.03ha

Volume of Spoil 11.00×104 m3 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Intercepting/drainage facilities shall be constructed.

Temporary retaining facilities shall be arranged asap.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Page 134: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

128/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K130+480

Boundary of Spoil Disposal Area

Page 135: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

129/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K139+180 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 2.56ha

Volume of Spoil 3.68×104 m3 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems The drainage in the spoil disposal area is disordered; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

The spoil surface shall be leveled.

The scattered spoil shall be cleared.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 136: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

130/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K139+180

Boundary of Spoil Disposal Area

Page 137: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

131/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K141+600 Type of Spoil Disposal Area Valley type Disturbed

Surface Area 1.13ha

Volume of Spoil 9.80×104 m3 Original design

or not? Following

24#

Continue to be used for spoil

disposal or not? No

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream, and timely site restoration shall be conducted.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 138: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

132/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K141+600

Boundary of Spoil Disposal Area

Page 139: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

133/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K152+800 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.76ha

Volume of Spoil 56.80×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? No

Constructed Facilities A 350m of mortar masonry retaining wall.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; there is not complete retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream, and timely site restoration shall be conducted.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 140: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

134/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K152+800

Boundary of Spoil Disposal Area

Page 141: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

135/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K155+860 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.65ha

Volume of Spoil 6.58×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? No

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be added at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Downstream of Spoil Disposal Area

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Temporary retaining facilities shall be arranged asap.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 142: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

136/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K155+860

Boundary of Spoil Disposal Area

Page 143: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

137/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K162+200 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.58ha

Volume of Spoil 4.81×104 m3 Original design

or not? Following 27# Continue to be used for spoil

disposal or not? No

Constructed Facilities

A 50m of mortar masonry retaining facility and a 40m of temporary retaining facility have been arranged.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is not complete retaining facility in the spoil disposal area; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream, and timely site restoration shall be conducted.

The spoil surface shall be leveled.

Intercepting/drainage facilities shall be constructed.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 144: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

138/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K162+200

Boundary of Spoil Disposal Area

Page 145: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

139/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K174+000 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.51ha

Volume of Spoil 10.21×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 146: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

140/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K174+000

Boundary of Spoil Disposal Area

Page 147: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

141/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K177+500 Type of Spoil Disposal Area

Valley type

Disturbed Surface Area 1.30ha

Volume of Spoil 24.41×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 148: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

142/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K177+500

Boundary of Spoil Disposal Area

Page 149: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

143/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K179+200 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.69ha

Volume of Spoil 8.45×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Intercepting/drainage facilities shall be constructed.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Temporary retaining facilities shall be arranged asap.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 150: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

144/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K179+200

Boundary of Spoil Disposal Area

Page 151: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

145/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K184+400 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.14ha

Volume of Spoil 10.74 Original design or

not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 152: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

146/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K184+400

Boundary of Spoil Disposal Area

Page 153: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

147/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K187+000 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.72ha

Volume of Spoil 16.41×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Intercepting/drainage facilities shall be constructed.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 154: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

148/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K187+000

Boundary of Spoil Disposal Area

Page 155: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

149/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K188+200 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.30ha

Volume of Spoil 11.57×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

The lateral spoil shall be cleared, and site restoration shall be conducted.

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 156: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

150/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K188+200

Boundary of Spoil Disposal Area

Page 157: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

151/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K192+000 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 2.61ha

Volume of Spoil 15.23×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Intercepting/drainage facilities shall be constructed.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Temporary retaining facilities shall be arranged asap.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 158: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

152/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K192+000

Boundary of Spoil Disposal Area

Page 159: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

153/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K193+460 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.56ha

Volume of Spoil 11.51×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

Downstream of Spoil Disposal Area

Temporary retaining facilities shall be arranged asap.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 160: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

154/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K193+460

Boundary of Spoil Disposal Area

Page 161: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

155/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K215+100 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.47ha

Volume of Spoil 2.48×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed. The spoil surface

shall be leveled.

Downstream of Spoil Disposal Area

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Temporary retaining facilities shall be arranged asap.

Page 162: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

156/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K215+100

Boundary of Spoil Disposal Area

Page 163: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

157/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K215+400 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.67ha

Volume of Spoil 4.51×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream, and timely site restoration shall be conducted.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Downstream of Spoil Disposal Area

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Temporary retaining facilities shall be arranged asap.

Page 164: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

158/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K215+400

Boundary of Spoil Disposal Area

Page 165: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

159/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K223+100 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 0.80ha

Volume of Spoil 8.87×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Conditions of Downstream of Spoil Disposal Area

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Downstream of Spoil Disposal Area

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Temporary retaining facilities shall be arranged asap.

Page 166: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

160/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K223+100

Boundary of Spoil Disposal Area

Page 167: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

161/178 6th Semi-annual Environmental Monitoring Report

Location of

Spoil Disposal Area

K234+300 Type of Spoil Disposal Area

Gentle-slope type

Disturbed Surface Area 1.33ha

Volume of Spoil 10.11×104 m3 Original design

or not? No Continue to be used for spoil

disposal or not? Yes

Constructed Facilities None.

Problems There is no intercepting/drainage facility at the upstream of the spoil disposal area; the drainage in the spoil disposal area is disordered; no slope stepping has been conducted; there is no retaining facility at the downstream; the follow-up design has not been implemented.

Suggestions for

Improvement

The follow-up design for the spoil disposal area shall be implemented as soon as possible; intercepting facilities shall be constructed at the upstream; the spoil surface shall be leveled, and then slope cutting and stepping shall be carried out, with the overall slope ratio less than 1:2; inside drainage ditches shall be arranged; retaining facilities shall be constructed at the downstream.

Intercepting/drainage facilities shall be constructed.

The spoil surface shall be leveled.

Slope cutting and stepping shall be carried out, and the overall slope ratio shall be less than 1:2; bridleway drainage ditches shall also be arranged.

It is recommended to add protection for subgrade slopes, intercepting ditches for areas with rich catchment at the upstream of slopes, and comprehensive protection for slopes higher than 10m.

Temporary retaining facilities shall be arranged asap.

After the rainy season, the follow-up design shall be followed to construct permanent retaining facilities asap.

Page 168: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

162/178 6th Semi-annual Environmental Monitoring Report

3D Rendering of Spoil Disposal Area at K234+300

Boundary of Spoil Disposal Area

Page 169: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

163/178 6th Semi-annual Environmental Monitoring Report

Suggestions on Perfection:

i. The principle of "retaining before dumping" shall be followed for spoil disposal area, retaining measures shall be improved in time for spoil disposal area, and spoil shall be moved to spoil disposal area and stacked reasonably;

ii. For the spoil disposal area on flood land, the Owner shall verify with local river course administration to check whether river course management range is occupied, and it is specified in river course management regulations to prohibit occupation of river course management range to prevent influence on flood discharge capacity of the river; relevant measures shall be improved by design requirements, and spoil shall be stacked by standards;

iii. In case of any individual or unit in need to borrow spoil from the Project for comprehensive utilization during construction, it is necessary to sign borrow agreement to confirm spoil direction, purpose as well as responsibilities for safety, water and soil conservation, prevention and control.

iv. Discarding behavior with potential safety hazards should be eliminated in time, such as K120+500, K181+200 and K185+300. Restrictive factors should be excluded when new spoil disposal area have to be added. Local water and soil conservation management departments should be consulted for the area selection.

v. Description of the spoil disposal yard near K185+300: According to the second soil and water conservation check of NJLR conducted by PWRB on February 9, 2018. There are residential areas downstream of NJL-Sub 9 1# spoil disposal yard near K185+300, which is near Niuluohe Village in Jiangcheng. There are potential safety hazards for this spoil disposal yard. PWRB suggested that the spoil disposal yard could be changed into a comprehensive using land or the road maintenance land after the drainage system was improved. But the change requires the transportation administration department to issue relevant approval documents and consent. At present, the spoil disposal yard has been changed into a road maintenance land.

(4) Other recommendations: The Project is now in earth-rock excavation; since it is in rain season, a lot of bare

surfaces will suffer from water loss and soil erosion obviously in case water and soil conservation measures are not taken; to better implement water and soil conservation for Ning’er - Jiangcheng Highway, and ensure that relevant specifications for water and soil conservation can be met during project implementation and acceptance requirements can be met finally, the following suggestions are hereby raised:

(1) The above problems are typical of the project site and given recommendations, and the places not mentioned in the project please refer to the improvement; (2) To carefully organize and implement “three-simultaneous” system in accordance with the approval of water conservation scheme;

(3) To follow the principle of “blocking first and then spoiling” in spoil disposal area;

(4) To avoid spoiling behavior with hidden dangers;

(5) To implement topsoil stripping, collection and reutilization;

(6) To optimize the construction process and strengthen the guarding for construction along the river to prevent residue from entering the river and forbid all spoiling behavior that occupying the scope for river course management.

(7) To pay attention to the follow-up of temporary measures (temporary drainage ditch, woven bag filling, temporary blocking by inserting piles and temporary cover, etc.)

(8) In case of request to borrow spoil from the Project for utilization and for temporary land occupation for utilization, written agreement shall be signed to confirm responsibilities for prevention and control of water loss and soil erosion;

Page 170: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

164/178 6th Semi-annual Environmental Monitoring Report

(9) In case of deviation in peg position, headquarters may refer to construction drawings and on-site conditions of bid sections for correction and then urge rectification, and we will perform modification in time and track rectification implementation in the future;

(10) In the actual construction process, spoil disposal areas may be adjusted from time to time due to the impacts of such factors as land occupation and construction conditions. According to Article 3 of 3.1.1 of the Technical code on soil and water conservation of development and construction projects (GB50433-2008), the spoil should be comprehensively utilized; spoil that cannot be utilized should be stacked at special place of storage, with blocking measures taken on the principle of “blocking first and then spoiling”. According to relevant requirements, spoil disposal areas shall not be arranged in the scope of rivers, slopes and built reservoir and the scope of river management. The monitoring team suggests the Employer to timely improve and adjust the spoil disposal areas under requirements; local administrative departments should be timely asked for opinions on the selection and planning of new spoil disposal areas. The suggestions on the selection and arrangement of new spoil disposal areas should comply with the Technical code on soil and water conservation of development and construction projects (GB50433-2008); the selection of spoil disposal areas shall comply with the following provisions: i. Bring no harm to the safety of the surrounding utilities, industries and enterprises and residential sites.

ii. For the spoil disposal areas near the river course, the Project shall conform to the planning of soil and water conservation and rules for flood control and flood discharge without soil (rock and spoil) disposal areas arranged within the river and lake management scope.

iii. The arrangement of spoil disposal areas in regions, where significant impacts may be imposed on important infrastructure, the safety of people's lives and property and flood flowing safety, shall be forbidden.

iv. It is not suitable to arrange them in the ditches with large flow rate, or else, flood control demonstration shall be carried out.

v. Waste gully, concave ground or branch ditch shall be selected in hilly areas and concave ground or wasteland on plains; wind gap or the places where wind erosion may easily happen shall be avoided in sandy area.

Page 171: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

165/178 6th Semi-annual Environmental Monitoring Report

VI. PUBLIC CONSULTATION

The EMP has defined the public consultation plan during the construction and operation stage of the project. The EMP consists of public participation in the following aspects: (i) Monitor the impacts and countermeasures during the construction and operation stage; (ii) Assess the environmental and economic benefits and social influences; and (iii) have interview with the public after completion of the project. The following types of public participation are included in the EMP: field survey, seminar, investigation into problems, interview and public hearings, etc. The following table details implementation of the public consultation plan.

Table 6-1:Public Consultation Plan

Organizer Format No. of Times Subject Attendees Construction Stage

PPMO Public consultation & site visit

4 times: 1 time before construction commences and 1 time each year during construction

Adjusting of mitigation measures, if necessary; construction impact; comments and suggestions

Residents adjacent to project sites, representatives of social sectors

PPMO, PMTB

Expert workshop or press conference

As needed based on public consultation

Comments and suggestions on mitigation measures, public opinions

Experts of various sectors, media

The public consultation before construction of the project has been implemented at the EIA stage. In the EIA stage, field investigation and questionnaire are organized and carried out among local residents by the responsible body to carry out the EIA. The results of public consultation before the construction of each sub-project is included in the EIA report of such sub-project.

Public consultation during the construction stage (annual): During this reporting period, Menglian-Meng’a Road and Ning’er-Jiangcheng-Longfu Road haven’t carried out the once-per-year public consultation during the construction period. The construction of rural roads have started, but the public consultation isn’t carried out on schedule.

Page 172: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

166/178 6th Semi-annual Environmental Monitoring Report

VII. INSTITUTIONAL STRENGTHENING AND TRAINING

According to EMP,The capacity of the PPMO, PMTB and contractors’ staff responsible for EMP implementation and supervision will be strengthened. All parties involved in implementing and supervising the EMP must have an understanding of the goals, methods, and practices of project environmental management. The project will enhance capacity and expertise in environmental management through (i) institutional capacity building and (ii) training.

A. Institutional strengthening

The EMP defines corresponding measures concerning the development of environmental management ability of the executing institution (PPMO) and the implementing institution (PMTB) of the project. The implementation status of these measures is listed below.

Table7-1:Implementation status of Institutional strengthening

Implementing Entity Mitigation Measures defined in the EMP Supervising

Entity Implementation status

and compliance with EMP

PPMO

➢ Appoint qualified environment specialist to PPMO staff.

➢ Include LIEC in loan implementation project management consulting services.

➢ LIEC to conduct environment management training for PPMO staff and environmental specialist.

ADB

PPMO has appointed the environment specialist and LIEC. However, no related training activities have yet been done by LIEC. ⚫ Partly complied with

PMTB

➢ Appoint qualified environmental specialist to PMTB staff.

➢ Contract EEMA to conduct environment monitoring

➢ Contract qualified EEMA to conduct external compliance monitoring and verification of EMP implementation

➢ LIEC to conduct environment management training for PMTB staff and their environmental specialist.

PPMO、ADB

PMTB has appointed the environmental specialist and contractedEEMA to conduct environment monitoring. PMTB has contracted EEMA to conduct external compliance monitoring and verification of EMP implementation. LIEC has organized part of training activities. ➢ Partly complied with

B. Training

According to EMP,The PPMO, PMTB, contractors and O&M units will receive training in EMP implementation, supervision, and reporting, and on the Grievance Redress Mechanism. Training will be facilitated by the LIEC with support of other experts (e.g. the Engineers of EEMA) under the loan implementation project management consulting services.

Table7-2: Implementation status of Training Plan

Training Attendees Contents No. of Times Implementation Status Plan EMP adjustment and implementation

PPMO, PMTB, contractors

Development and adjustment of the EMP, roles and responsibilities, monitoring, supervision

Once prior to

The Menglian-Meng’a Road has carried out training on the environmental management in April 2016 by the supervisory institution;In March 2017, PPMO have organized LIEC to carry out the technical training for the project headquarters and contractors

——

Page 173: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

167/178 6th Semi-annual Environmental Monitoring Report

Training Attendees Contents No. of Times Implementation Status Plan and reporting procedures, review of experience (after 12 months)

about the EMP, roles and responsibilities, monitoring, supervision and reporting procedures.

once after one year of project To be implemented

Will be organized in 2019 as scheduled.

Grievance Redress Mechanism

PPMO, PMTB, contractors, PEPB

Roles and responsibilities, procedures, review of experience (after 12 months)

Once prior to To be implemented

Will be organized in 2019 as scheduled by LIEC

once after one year of project To be implemented

Will be organized in 2019 as scheduled.

Environmental technologies and processes

PPMO, PMTB, contractors, O&M units

Engineering and pollution control technologies, equipment selection and procurements,

Once (during project implementation)

To be implemented

Will be organized in 2019 as scheduled by LIEC

Environmental quality monitoring

PPMO, PMTB, contractors, O&M units

Monitoring methods, data collection and processing, reporting systems

Once (at beginning of project construction)

In March 2017, PPMO have organized LIEC to carry out the technical training for the project headquarters, contractors, General Supervision Office, EEMA about monitoring methods, data collection and processing, reporting systems

Has executed

Roads and traffic

PMTB, O&M units

Traffic management and traffic safety

Once (during project implementation)

In March 2017, PPMO have hired the expert to carry out the traffic management and safety training for the concerned personnel of the municipal transport bureaus of counties in Pu’er, the project headquarters, contractors, the general supervision offices, the design institutes.

Has executed

Customs Bureau

Wildlife trafficking

Once (during project implementation)

In August 2017, PPMO have entrusted the external consultative agency to carry out the fighting wildlife traffiching training for the forest policemen,. customs officers, border policemen, traffic policemen, quarantine and inspection officers, township transport managers in Pu’er

Has executed

Page 174: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

168/178 6th Semi-annual Environmental Monitoring Report

C. Grievance Redress Mechanism

Menglian - Meng’a Road:During this reporting period, no complaints were received.

Ning'er - Jiangcheng - Longfu Road:During this reporting period, eighteen complaints were received. Complaints mainly include pavement water accumulation, construction dust, wet slippery road and water pipe damage. All complaints have been satisfactorily settled.

Page 175: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

169/178 6th Semi-annual Environmental Monitoring Report

VIII. KEY ENVIRONMENTAL ISSUES

A. Key Issues Identified

By 31 December 2018, the subgrade of most sections of Menglian-Meng’a Road have been near compled, slope protection construction, pavement construction and bridge foundation construction are being carried out. About Ning’er - Jiangcheng - Longfu Road, the most subgrade of ten bid sections have been compled, slope protection construction and bridge foundation construction are being carried out. During this monitoring period, the environmental monitoring has been carried out on the sensitive points along the road according to the project construction progress.

According to the monitoring results, the construction of Menglian-Meng’a Road and Ning’er-Jiangcheng-Longfu Road have not obvious impact on the environmental quality of sensitive sites along the roads,and haven’t led the environmental quality to exceed the corresponding standards.

During this reporting period, the following key environmental issues have been identified.

(1) Menglian-Meng’a Road, Ning’er-Jiangcheng-Longfu Road and the Rural Access haven’t carried out the once-per-year public consultation on schedule.

(2) The part progress of institutional strengthening and training has delayed the schedule.

(3) The part of water and soil conservation measures of Menglian-Meng’a Road have been delayed. The main problenms are following.

i. Topsoil stripping and collection is not seriously conducted before the earth-rock excavation.

ii. Near the sections of K56 and K58, the excavated earth and rocks are not removed and disposed to the spoil disposal area. The transverse spoil caused water and soil seriously loss.

iii. The water cut-off measures are not completely implemented and the muck is not compacted stage by stage, in the 26th spoil disposal area near K64+400 of section I. Obvious surface and gully erosion phenomena have been produced.

iv. In the spoil stockade comprehensive utilization area near Hege Old Village (K68+500) of section I, the waste residue stacking is not reasonable, and there is no the drainage measures.

v. In the 27th and 28th spoil disposal areas of section II, the stacked spoil is not compacted stage by stage, which does harm to the stability of spoil.

(4) The part of water and soil conservation measures of Ning’er - Jiangcheng - Longfu Road have been delayed. The main problenms are following.

i. Road area: Spoil is not stacked reasonably after main line excavation, there is transverse spoil in some road sections, transverse spoil mass indicates hazard of landslide and debris flow, bare surface suffers from visible erosion upon rainwater scouring, and water and soil conservation measures for main line are behind schedule.

Page 176: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

170/178 6th Semi-annual Environmental Monitoring Report

ii. Spoil disposal area: Such conditions as lagging for water retaining, intercepting and drainage measures, unreasonable slag stacking technology, greater slag stacking area gradient, easy generation for water and soil loss due to rainwater erosion and no beneficial slag body stability; for some spoil disposal area, spoil-related safety problems still exist.

B. Solutions and Actions

The above issues have been reported to PPMO, the project headquarters and the corresponding contractors. PPMO and the project headquarters have supervised and urged the corresponding contractors to improve. According to the key environmental issues have been identified, the following suggestions and measures have been put forward.

(1) PPMO needs to organize the once-per-year public consultation about Menglian-Meng’a Road, Ning’er-Jiangcheng-Longfu Road and Rural Roads in 2018. And PPMO needs to complete the training according to EMP in 2018.

(2) PMO has required the project headquarters,the project supervision agencies and the contractors jointly formulate the improvement measures for the soil erosion impact issues based on the advices raised up in the monitoring report. The advices see Chapter “D. Monitoring Result of Soil Erosion Protection” for details.

Page 177: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

171/178 6th Semi-annual Environmental Monitoring Report

IX. APPENDICES

Appendix 1 Environmental Impact Mitigation and Monitoring Structure Diagram Appendix 2 The Qualifications of the External Environmental Monitoring Agencies Appendix 3 Proposed Grievance Redress Mechanism (GRM) Appendix 4 Responsible Person and Complaints Hotline of GRM Access Points Appendix 5 Environmental Management Training Record

Page 178: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

172/178 6th Semi-annual Environmental Monitoring Report

Appendix 1 Environmental Impact Mitigation and Monitoring Structure Diagram

Page 179: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

173/178 6th Semi-annual Environmental Monitoring Report

Appendix 2 The Qualifications of the External Environmental Monitoring Agencies

The Qualification of Yunnan Fangyuan Science and Technology Co., Ltd.

Page 180: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

174/178 6th Semi-annual Environmental Monitoring Report

The Qualification of Guangxi Transportation Research Institute

Page 181: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

175/178 6th Semi-annual Environmental Monitoring Report

The Qualification of Kunming Longhui Engineering Design Consulting Co., Ltd.

Page 182: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

176/178 6th Semi-annual Environmental Monitoring Report

The Qualification of Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd.

Page 183: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

177/178 6th Semi-annual Environmental Monitoring Report

The Engineers’ Qualifications of the External Environmental Monitoring Agencies

The Agency The Engineers for the Project The Engineers’ Qualification

Yunnan Fangyuan Science and Technology Co., Ltd.

He Yan (The Project Leader) Engineer of Environmental Monitoring

Wang Runtian Engineer of Environmental Monitoring Cha Jianqiang Engineer of Environmental Monitoring Zhu Ronggang Engineer of Environmental Monitoring Xu Yanbo Assistant Engineer of Environmental Monitoring BaoChengfei Assistant Engineer of Environmental Monitoring Lei Fengliang Assistant Engineer of Environmental Monitoring

Guangxi Transportation Research Institute

Huang Guangyu (The Project Leader) Senior Engineer of Environmental Monitoring

ZhongGuang Senior Engineer of Environmental Monitoring Pan Changwei Engineer of Environmental Monitoring Huang Rui Engineer of Environmental Monitoring Ma Zengxing Engineer of Environmental Monitoring Ding Xiaojuan Assistant Engineer of Environmental Monitoring Su He Assistant Engineer of Environmental Monitoring

Kunming Longhui Engineering Design Consulting Co., Ltd.

Hu Yufang (The Project Leader)

Senior Engineer of Water and Soil ConservationMonitoring

Wang Zhi Engineer of Water and Soil ConservationMonitoring Yin Qidong Engineer of Water and Soil ConservationMonitoring DuanXiaoli Engineer of Water and Soil ConservationMonitoring

Lu Yanli AssistantEngineer of Water and Soil ConservationMonitoring

Wang Haoran Assistant Engineer of Water and Soil ConservationMonitoring

Yunnan Jin Yu Ecological Engineering Consulting Co., Ltd.

Zhang Jiabing (The Project Leader) Engineer of Water and Soil Conservation Monitoring

Wang Bin Senior Engineer of Water and Soil Conservation Monitoring

Zhou Xiang Senior Engineer of Water and Soil Conservation Monitoring

Wang Shigui Engineer of Water and Soil Conservation Monitoring

Huang Jiajian Assistant Engineer of Water and Soil Conservation Monitoring

Wang Yong Assistant Engineer of Water and Soil Conservation Monitoring

Page 184: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

178/178 6th Semi-annual Environmental Monitoring Report

Appendix 3 Proposed Grievance Redress Mechanism

Affected Persons

PPMO Complaints

Center Hotline

Contractor Complaint

Register

Complaint

Register

Complaint

Register PMTB/PEPB

PPMO

ADB

satisfactory

satisfactory

satisfactory

complain

unsatisfactory

unsatisfactory

com

pla

in

com

pla

in

Ste

p 1

(1 w

ee

k)

Ste

p 2

(2 w

ee

ks)

Ste

p 3

(2 w

ee

ks)

GRM entry point

environmental

com

pla

in

resettlement Resettlement GRM

Page 185: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

179/178 6th Semi-annual Environmental Monitoring Report

Appendix 4 Responsible Person and Complaints Hotline of GRM Access Points

Implementing Entity Responsible Person Complaints Hotline

PPMO Zhou Tianshuangni +86 879 2819198 PMTB Zhao Shifa +86 879 2163793

PEPB

Pu’er Municipal Environmental Monitoring Detachment

+86 879 12369

Menglian - Meng’a Road:

MM-Sub1 CCCC Fourth Highway Engineering Co., Ltd. Zhang Wenbo +86 18002139751

MM-Sub2 Yunnan Highway & Bridge Co., Ltd. Zhou Jian +86 18587156683 MM-Pav1 Contract not awarded yet Not yet specified Not yet specified Ning'er-Jiangcheng-Longfu Road

NJL-Sub 1 Liaoning Communication Construction Engineering Co., Ltd. Huang Shukai +86 13577111275

NJL-Sub 2* Sheng Di Communication Engineering Co., Ltd. Wu Daoyong +86 13888777822

NJL-Sub 3* Yunnan Jin’guang Construction Engineering Co., Ltd. DuanLinsheng +86 13577201605

NJL-Sub 4* ShenmuYuliang Construction Engineering Co., Ltd. Wang Zenghai +86 13908794917

NJL-Sub 5* Jiangxi Hongfa Road & Bridge Construction Engineering Co., Ltd. Wang Yongneng +86 15877731185

NJL-Sub 6 HeiLongjiangHualong Construction Co., Ltd. Wang Rongbo +86 15812040596

NJL-Sub 7 Maoming Transport Construction Engineering Co., Ltd. Zhou Tiejun +86 15987969999

NJL-Sub 8 Dongxiang County GanDongLuqiao Engineering co., LTD. Deng Qichang +86 13896153403

NJL-Sub 9 Jiangxi province Guyue Engineering Co., Ltd. Yuan Lin +86 18187947739

NJL-Sub 10 Hunan foreign Construction group co., LTD. Huang Jinchang +86 13888391612

NJL-Pav1 Contract not awarded yet Not yet specified Not yet specified NJL-Pav2 Contract not awarded yet Not yet specified Not yet specified NJL-Pav3 Contract not awarded yet Not yet specified Not yet specified

Page 186: Environmental Monitoring Report · Yunnan Pu’er Regional Integrated Road Network Development Project 2/178 6th Semi-annual Environmental Monitoring Report B-2.Engineering Brief

Yunnan Pu’er Regional Integrated Road Network Development Project

180/178 6th Semi-annual Environmental Monitoring Report

Appendix 5 Environmental Management Training Record

Topic Trainer(s) Attendees Date ADB financed project management & implementation ADB PMTB 1 2014/3/31~4/3

ADB financed project management & implementation

Chuxiong PMO Longrui PMO PMTB 4 2015/3/24~

3/26

Project management PMG PMTB 1 2015/4/29

Disbursement & financial management, procurement, social safeguards, and environmental management (Shangxi Xi'an)

ADB PMTB 3 2015/9/23~9/25

Disbursement & financial management, procurement, social safeguards, and environmental management (Yunnan Mangshi)

Dehong TransportBureau PMTB 3 2016/1/13~

1/14

Disbursement & financial management, procurement, social safeguards, and environmental management (Yunnan Pu'er)

ADB PMTB & CTB 100 2016/4/11~4/13

Environmental supervision training

MMR General Supervision Office

Supervision Engineer 13 2016/4

Environmental supervision and Implementation of EMP training PPMO General Supervision

Office, Constractors 30 2017/03/08

Traffic management and safety training PPMO

Municipal Transport Bureaus of counties in

Pu’er, Project Headquarters,

Contractors, General Supervision Offices,

Design Institutes

46 2017/3/20~3/21

Fighting wildlife traffiching training PPMO

Relevant organizations of the countries in Pu’er

(Forest Police,. Customs Office, Border Police, Traffic Police,

Quarantine and Inspection Office, Township Transport

Management)

88 2017/8/15~8/17

Environmental protection, soil and water conservation training

The contractor of NJL-Sub 3 The site builders 28 2018/3/1

Environmental protection, soil and water conservation training

The contractor of NJL-Sub 3 The site builders 35 2018/4/1