eric strecker4
DESCRIPTION
TRANSCRIPT
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
1
Hydromodification ManagementHydromodification Management
Eric StreckerEric StreckerEric StreckerEric StreckerGeosyntec ConsultantsGeosyntec Consultants
Gary PalhegyiGary PalhegyiIndependent ConsultantIndependent Consultant
August 2008August 2008
AgendaAgenda
Overview of the Science
Management Strategies– Linking flow controls with channel processes– Integrating multiple stormwater control criteria– Roll of LID in hydromodification management
Project Examples– Contra Costa– LID Design for Hydromodification
HydromodificationHydromodificationModification of the Natural Hydrologic CycleModification of the Natural Hydrologic Cycle
Thompson Creek Flow Rates - Pre & Post Development(modeled for a 716 acre development using HEC-HMS)
140
160 Post-Urban @ 44% connectedimpervious coverPre-Urban, Infiltration = 0.16 in/hr
0
20
40
60
80
100
120
Time (hours)
Dis
char
ge (c
fs)
Critical Flow for Sediment Transport
2-Year Flood Flow - Pre-Urban
Increases Runoff Magnitude, Volume and Duration of Smaller Flows more then Larger Flows
Flow Duration Histogram
1500
2000
2500
3000
3500
eque
ncy
(cou
nt)
Post Condition
Existing Condition
20%
Flow Duration Histogram
quen
cy (c
ount
)
0
500
1000
70656055504540353025201510
Discharge (cfs)
Fre
Hollis (1975)
1 10 100
16%
Discharge (cfs)
Frequency (years)
Freq
Perc
ent C
hang
e
Physical Consequences of Physical Consequences of HydromodificationHydromodification
Intensified sediment transport and erosion processesObserved as excessive erosion, incision and widening
Thompson CreekThompson CreekSanta Clara ValleySanta Clara Valley
Ecological Consequences of Ecological Consequences of HydromodificationHydromodificationPredicted Increase in Average Monthly Stream Flow Volumes
200%
250%
ting
Con
ditio
ns
At Eagles Nest Road, LCC4
0%
50%
100%
150%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Perc
ent C
hang
e fro
m E
xist
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
2
Key ConceptsKey ConceptsFlow magnitude, volume, frequency of occurrence, duration and timing– are major driving forces that control the physical and ecological
processes in a riparian corridor
Sediment supply is also a key factor that is often not considered Channel stability – requires a balance among flow energy, sediment supply and
channel resilience
Analytical methods– must link watershed hydrology and land development with these
channel processes
Management strategies– must include the full range of geomorphically significant flows
Time integrated metrics (e.g., Erosion Potential)– provide the closest reproduction of these processes
Key Steps in the Key Steps in the Erosion Potential MethodologyErosion Potential Methodology
Characterize the Physical Setting
Perform Geomorphic Assessment
Conduct Continuous Hydrologic ModelingConduct Continuous Hydrologic ModelingConduct Hydraulic/Work & Sediment Transport ModelingEvaluate Sediment Supply ChangesEvaluate Potential Instability, Compliance and/or Design Parameters
Conceptual ModelConceptual Model
Hydrologic modelHydrologic model
Model ScenariosModel Scenarios1)1) PrePre--developeddeveloped2)2) Existing conditionsExisting conditions3)3) PostPost--developeddeveloped
Sediment transport / work modelSediment transport / work model(incl. hydraulics)(incl. hydraulics)
Erosion PotentialErosion PotentialQQss
QQff
Catchment boundary
preQspostQs
Ep∑∑
=
Hydrologic ModelingHydrologic Modeling
Land Use Scenarios– Pre, existing, and future
Climate– Long term continuous hourly records– Full probability distribution
Precipitation-Runoff– Soil moisture accounting– Where applicable snow melt
Calibrated & Verified
Hydraulic & Shear Stress ModelHydraulic & Shear Stress Model(Incorporates geometry, slope, & vegetation)
SKQ ⋅⋅= 49.1
∑ ⋅=
nRAK
3/2
96
Vegetation Vegetation densitydensity
SgRavgavg ρτ =
32
⎟⎟⎠
⎞⎜⎜⎝
⎛=
avg
bavgb n
nττ
87
88
89
90
91
92
93
94
95
0.0 10.0 20.0 30.0 40.0 50.0
P2
R2R1
P3
P4
A1 A2
n2
n3
n4
Boundary Material PropertiesBoundary Material Properties(determine critical shear stress for weakest boundary)
Jet Testing to field measureCritical Shear Stress (τc)
87
88
89
90
91
92
93
94
95
96
0.0 10.0 20.0 30.0 40.0 50.0
ττc bankc bank
ττc bedc bed
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
3
Effective Work & Sediment Effective Work & Sediment Transport ModelsTransport Models
( )ba cb
n
ττ −⋅= ∑1
( )cb
n
V ττ −⋅= ∑1
MacRae, C.R.
Andrew Simons, Ph.D., National Sedimentation Laboratory
Derek Booth, Ph.D., WSU
Cohesive
MaterialWorkWork
( ) 978.1
1cb
n
VVa −⋅= ∑
Wilcock-Crowe (2003)
b
c
bn
a ⎟⎠⎞⎜
⎝⎛⋅= ∑ ττ
1
TransportTransport
Brownlie (1981)Sand
Sand &Gravelmixtures
Gravel Parker (1990)( )[ ]∑ ⋅⋅⋅=n
DiDgGa
1 50φω
WorkWorkLaguna Creek, Laguna Creek, SacramentoSacramento Oso Canyon, Oso Canyon, TehachapiTehachapi
TransportTransport
Laurel Creek, Laurel Creek, FairfieldFairfield--SuisunSuisun Long Canyon, Long Canyon, Santa ClaritaSanta Clarita
InIn--StreamStreamManagement ObjectivesManagement Objectives
Maintain Baseline Conditions (MacRae, SCVURPPP)– Ep = 1 ± 20%
postWEp
∑=
Maintain Capacity / Supply Ratio (USACE, Soar & Thorne)– CSR = 1 ± 10%
preWEp
∑
supply
capacity
∑∑
=Qs
QsCSR
11
1010
22
55
EE 11
1010
22
55
EE 11
1010
22
55
EE
BaselineBaselinePost with Post with
increased flowsincreased flowsPost w/ 80% reduction in Post w/ 80% reduction in
sediment supplysediment supply
11
0.10.1
0.20.2
0.50.5
EpEp 11
0.10.1
0.20.2
0.50.5
EpEp 11
0.10.1
0.20.2
0.50.5
EpEp
Target EpTarget Ep Post EpPost Ep
AgendaAgenda
Overview of the Science
Management Strategies– Linking flow controls with channel processesLinking flow controls with channel processes
(ultimate objective)
– Integrating multiple stormwater control criteria
– Roll of LID in hydromodification management
Range of Management Strategies Range of Management Strategies being Used or Proposedbeing Used or Proposed
Stream classificationSite design, LIDPeak flow, velocityyTime of concentrationRunoff volume, groundwater rechargeFlow duration control Instream stabilizationWork & Erosion Potential (Ep)
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
4
What is Flow Duration Control and What is Flow Duration Control and Why is it Important?Why is it Important?
60
70
80
90
100
(hou
rs)
20
25
30Frequency of Flows
Effective Work Curve
Sediment Transport
Effective Discharge (lbs)
( )bττ
Work Curve (Leopold, 1964)
0
10
20
30
40
50
0 20 40 60 80 100 120 140 160 180 200 220 240
Flows Bin's (cfs)
Freq
uenc
y
0
5
10
15
Qs (lbs/sec)
Qc
( )bcb ττ −
Flow Duration Control Flow Duration Control Is a Design ConceptIs a Design Concept
Stream Discharge
Matched FDC Inflow
Infiltration(LID, diversion, by-pass, recycle)
Qcp
Volume Retained(50% to 90%)
AgendaAgenda
Overview of the Science
Management Strategies– Linking flow controls with channel processesLinking flow controls with channel processes
(ultimate objective)
– Integrating multiple stormwater control criteria
– Roll of LID in hydromodification management
FDC Integrates with Flood ControlFDC Integrates with Flood ControlCommercial developmentArea = 12.2 acres65% impervious surfacesInfiltration rate = 0.5 in/hrMAP = 20 inchesTc = 10 to 20 min
Example Flood Frequency ResultsExample Flood Frequency ResultsCommercial Development ExampleRecord: 1948 to 1990, 12.2 Acres, A/B Soils
8
10
12
e (c
fs)
Predeveloped
Postdeveloped
FDC Mitigated flow
Qcp
65% Impervious surfacesInfiltration = 0.5 in/hr
Flood Frequency Curves (Partial Duration Series)Showing Flood Control Results
10
12
14
16
18
20
rge
(cfs
)
Existing conditions - undeveloped
Proposed project @ 65% IMP
Discharge from FDC BasinPre-Project
Post-Project
Peak flow - design storm
0
2
4
6
1 10 100 1000 10000 100000
Cumulative Duration (hours)
Dis
char
ge
475 14th Street, Suite 400Oakland, CA 94612
FDC Depth = 2 feetFDC Area = 6.1% (0.74 ac)FDC Volume = 1.35 ac-ft
0
2
4
6
8
10
1 10 100Recurrance Interval (years)
Dis
char
475 14th Street, Suite 400Oakland, CA 94612
Peak Discharge from FDC Basin
100100--Year Storm Tested in FDC BasinYear Storm Tested in FDC Basin100-Year Design Storm Hydrographs showing FDC Basin Performance
15
20
25
ge (c
fs)
Post Project
Pre Project
FDC Basin Outflow
Pre-Project 100-Year = 15 cfs
0
5
10
0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00
Time (minutes)
Dis
char
g
475 14th Street, Suite 400Oakland, CA 94612
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
5
Outlet Structure ConfigurationOutlet Structure Configuration
Peak flow controlPeak flow control
1212--inch dia.inch dia.
Flow duration controlFlow duration control
22--inch dia.inch dia.
Not to ScaleNot to Scale
Integrating Water Quality, Flow Duration Integrating Water Quality, Flow Duration and Flood Controland Flood Control
Flow Duration Control Volume
Water Quality Volume Flood Control Volume
AgendaAgenda
Overview of the Science
Management Strategies– Linking flow controls with channel processesLinking flow controls with channel processes
(ultimate objective)
– Integrating multiple stormwater control criteria
– Roll of LID in hydromodification management
FDC BasinFDC Basin
Urban Urban RunoffRunoff
BioBio--infiltration infiltration SwaleSwale
FDCFDC
FDC Integrates with LID StrategiesFDC Integrates with LID Strategies
StreamStream
FDC FDC BasinBasin
BioBio--infiltration infiltration SwaleSwale
FDC FDC VaultVault
OnOn--Site BMPsSite BMPs
LIDLID
FDC is still met at discharge point
Technical Challenges with LIDTechnical Challenges with LID
Mimicking natural hydrologic functions?
Creating the right in-stream effects?– Maintain the correct work and transport conditions?– Any unforeseen physical or ecological consequences?
i.e. extended duration of low flowsIncreased receding hydrograph and/or base flows due to increased infiltration
Developing models that everyone can use and understand– BAHM, sizing factors, sizing charts
14-inches ponded water Infiltration at 2 in/hr
Actual Et
Modeling Bioretention for LID Modeling Bioretention for LID (Excel spreadsheet model)
24-inches amended soil
6-inches gravel layer
Deep percolation to underlying soils from drainable portion only
Drainable Portion
Field Capacity
100%
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
6
Bioretention Model ResultsBioretention Model ResultsBio-Retention Model with QCP Discharges
400
500
600
700
u-ft)
25000
30000
35000
40000
45000
orag
e (c
u-ft)
In-Flow
Deep Percolation
Out Flow
Surface Storage
Weir discharges
0
100
200
300
11/27 11/28 11/29 11/30 12/1 12/2 12/3 12/4 12/5 12/6
Time
Flow
(cu
0
5000
10000
15000
20000
25000
Pond
Sur
face
Sto
Qcp discharges
Field capacity fills
Bioretention Model ResultsBioretention Model ResultsBio-Retention Model
(Soil Moisture: drainable plus tension)
6.0
7.0
8.0
9.0
10.0
inch
es)
0.00025
0.00030
0.00035
0.00040
s)
Soil Storage
Et
Gra
vety
Dra
in
Drainable Storage
0.0
1.0
2.0
3.0
4.0
5.0
11/8 11/18 11/28 12/8 12/18 12/28 1/7 1/17 1/27 2/6 2/16 2/26 3/8 3/18 3/28 4/7 4/17 4/27 5/7 5/17
Time
Soil
Stor
age
(i
0.00000
0.00005
0.00010
0.00015
0.00020
Et (i
nche
s
Tens
sion
Zon
e
Field Capacity
Bioretention can achieve the Bioretention can achieve the Flow Duration CriteriaFlow Duration Criteria
Flow Duration Curves
2.5
3.0
3.5
4.00%imp at 0.16 in/hr
75%imp at 0.16 in/hr
Bioretention Results
0.0
0.5
1.0
1.5
2.0
1 10 100 1000 10000
Frequency (cfs)
Flow
s (c
fs)
Summary of AREA Sizing Summary of AREA Sizing Requirements to meet the FDCRequirements to meet the FDC
LocationLocationPond (3Pond (3--ft)ft) BioretentionBioretention
Percent of Catchment
L di tLaguna Creek
Low gradientHigh resilience
Qcp = 25% (2-yr peak)7% - 9% 12% - 14%
Fairfield-SuisunMedium resilience
Qcp = 20% (2-yr peak) 9% - 11% 17% - 21%
Southern California
Sandy soils Low resilience
Qcp = 0.0010% - 14% 18% - 28%
Range of sizes dependent on catchment soil infiltration rates
Flow Duration Control VOLUME Requirements for HydromodificationTehachapi Mountains, Southern Calif.
y = 0.09843x
8.0
10.0
12.0
olum
em
ent a
rea)
Volume requirements are dependent on the change in runoff between the pre and post condition, and thus are similar regardless of control measure.
Infil=0.0Qcp=0.004 cfs/acre
y = 0.02881x
0.0
2.0
4.0
6.0
0 10 20 30 40 50 60 70 80 90 100
Percent Imperviousness
Wat
er S
tora
ge V
o(in
ches
ove
r the
cat
chm
Infil=0.16 in/hrQcp=Zero
Land RequirementsLand Requirements
BMP TypeLAND USE Total
Impervious‐ness
Soil Infiltration
Total Volume
Surface Area
Sediment Reduction
Adjustment Factor
Total Volume
Surface Area
(acres) (%) (in/hr) (ac-ft) (acres) (%) (ac-ft) (acres)
Bioretention 1.5 AC DEVELOPABLE 40.95 19 0.26 7.72 5.14 30.1 1.60 12.39 8.24Bioretention 4DU/AC 81.56 57 0.26 46.14 30.70 1.60 74.04 49.26
Basin 6DU/AC 36.61 65 0.26 23.62 8.21 1.60 37.90 13.17Basin CONFERENCE HOTEL 12.33 46 0.26 5.63 1.96 1.60 9.03 3.14Swale Minor Road 0.27 12 0.26 0.03 0.03 1.60 0.05 0.05
0.42 0.5 0.26Open 0.37 0.5 0.26Pasture 211.2 0.5 0.26PRIVATE OPEN SPACE 25.64 0.5 0.26
Swale Road (RD) 12.39 90 0.26 11.07 9.70 1.60 17.76 15.57
SLOPE / OTHER GRADED 53.83 0.5 0.26
151.2 89.4
Application of Ecological Engineering Principals to Water Quality Management
Hydromodification MitigationEric Strecker
7
Hydromodification Control Hydromodification Control IssuesIssues
Land requirements for upland hydromodification controlSignificance of ET and resulting i i i filt ti t t h fincrease in infiltration to match surface hydrology– Habitat type changes
Instream measures are discouraged or not allowed, yet may be most effective (given land use considerations/sprawl)
“Greener Channels”“Greener Channels”
Addressing Stream Addressing Stream Stability by Working Stability by Working
with the Streamwith the StreamBoulder Bed Control Structure Boulder Bed Control Structure
(back)(back)
Timber Timber StepdownStepdown (front)(front)
Advantages: These directly Advantages: These directly address the issue and both address the issue and both
existing and future developmentexisting and future development
Disadvantage: Requires Disadvantage: Requires watershed planning and watershed planning and regulatory approvals are regulatory approvals are
difficultdifficult
Questions?Questions?
contact informationestrecker@ geosyntec.com