ESKOM South Africa CSP Augmentation Conference PE2 – operational experience. August 2013. Puerto Errado 2 Project Overview Project Profile and milestones. Puerto Errado 2 Milestones. Dec 2008:Due Diligence of EBL on PE1 June 2009: Signing Investment Agreement - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

1

ESKOM South Africa CSP Augmentation ConferencePE2 – operational experience

August 2013

Page 2: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Puerto Errado 2 Project Overview Project Profile and milestones

Puerto Errado 2 Key data

EPC Contractor Novatec Solar

Net Aperture Area 302,000m²

Turbine 2x 15 MW turbines GE Termodyne

Cooling Air cooled condensers

Solar share 100%

Operating Temperature

Up to 270°C

Operating Pressure Up to 55bar

Peak Thermal Output

150MWth

Peak Electrical Output

30MWel

2

Dec 2008: Due Diligence of EBL on PE1

June 2009: Signing Investment Agreement

April 2010: Start of Site Activities

April 2011: Financial Close

April 2012: Completion of Construction

Aug 2012: Start of Operations

June 2013: Final Acceptance Tests

Puerto Errado 2 Milestones

confidential

Page 3: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Use of NOVATEC´s guaranteed performance valuesGuaranteed key performance indicators are used for performance modelling all along the project development chain

GUARANTEED KEY PERFORMANCE INDICATORS

Project Development Solar Field Erection Solar Field Operation

Energy Yield Calculation

Contract

Technical specifications

Technical AcceptanceActual versus guaranteed performance

Availability Monitoring

Performance MonitoringActual versus

target performance

3

Page 4: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

PE2 performance guarantees

4confidential

• Conversion of Direct Solar Radiation to Net Thermal Energy Output depending on Sun Angle Position

Conversion of Net Thermal Energy in Net Electrical Output

Start up & Restart Times

Average Mirror Cleanliness & Plant Availability

Final Acceptence Tests: Target versus Actual Performance Comparison on 1 minute Time Step Basis over 20 day Tests in 4 Seasons

Page 5: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

First FAT 20 Day Test (Summer 13)

5

Page 6: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Target versus actual on 23/06/2013

6

Page 7: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

PE2 Plant Availability 99,8%

7

Page 8: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Low HR Requirement

Cleaning Performance

(4000 m² per Hour => 2 MWth)

Very low Water Consumption

(~ 2 Liter per m² an year)

Propietary low cost cleaning machines

8

Page 9: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

PE 2 Solar Field Cleanliness (monthly average based on daily measurements)

9

Page 10: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

NOVATEC´s Receiver Designs

Vacuum Tubes are being used in Sections >300°C

10

NOVA-1 Receiver SUPERNOVA / DMS Receiver

- confidential -

Primary Reflector Design remains the same for all Receivers

Page 11: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Supernova – Constant high steam temperatures

11

Control of Outlet Temperature via Focusing/Defocusing

- confidential -

Page 12: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Constant superheated steam temperature despite Fluctuating DNI

12

Fluctuating DNI and stable temperatures - confidential -

Page 13: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

Conclusion

13confidential

• NOVATEC´s transparent and detailed Performance Guarantees are Key for a successful Aquisiton of Equity and Debt Providers

• Final Acceptance Tests of PE2 so far Proof NOVATEC´s Overperformance

• PE2 Success is a solid Basis for the Market Introduction of NOVATEC´s new Technologies Supernova and DMS

Page 14: ESKOM South Africa  CSP Augmentation Conference PE2 – operational  experience

14

Liddell solar augmentation, Australia 2012Puerto Errado 1, Spain 2009

Puerto Errado 2, Spain 2012