The key to successful testing is effective and timely planning. Rick Craig introduces proven test planning methods and techniques, including the Master Test Plan and level-specific test plans for acceptance, system, integration, and unit testing. Rick explains how to customize an IEEE-829-style test plan and test summary report to fit your organization’s needs. Learn how to manage test activities, estimate test efforts, and achieve buy-in. Discover a practical risk analysis technique to prioritize your testing and become more effective with limited resources. Rick offers test measurement and reporting recommendations for monitoring the testing process. Discover new methods and develop renewed energy for taking your organization’s test management to the next level.TRANSCRIPT
![Page 2: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/2.jpg)
4
Administrivia
· Course timing · Breaks
© 2013 SQE Training V3.1
![Page 3: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/3.jpg)
© 2013 SQE Training V3.1 5
Course Agenda
1. The Culture of Testing and Quality2. Introduction to STEP and Preventive
Testing3. Test Levels4. Master Test Plan5. The Test Summary Report
![Page 4: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/4.jpg)
1THE CULTURE OF TESTING AND QUALITY
![Page 5: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/5.jpg)
© 2013 SQE Training V3.1 7
What are your problems?
· What are your testing challenges?
![Page 6: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/6.jpg)
© 2013 SQE Training V3.1 8
What is quality?
• Meeting requirements(stated and/or
implied)
·Quality
![Page 7: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/7.jpg)
© 2013 SQE Training V3.1 9
What is testing?
• The process of determining conformance to requirements—stated
and/or implied
·Testing
![Page 8: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/8.jpg)
© 2013 SQE Training V3.1 10
Class Questionnaire
• The overall quality of the software systems/products at my organization is:
Outstanding - one of the best Acceptable - OK Poor - must be improved Unknown - a mystery to me
![Page 9: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/9.jpg)
© 2013 SQE Training V3.1 11
Class Questionnaire
• The time, effort, and money that my organization spends trying to achieve high software quality is:
Too much - needs to be reduced
About right - OK Too little - needs to be increased Unknown - a mystery to me
![Page 10: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/10.jpg)
© 2013 SQE Training V3.1 12
Corporate Culture• Them and Us vs. One Team • Early vs. Late
![Page 11: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/11.jpg)
© 2013 SQE Training V3.1 13
Economics of Test and Failure• The cost of testing• The cost of failure• The savings of preventive
testing and defect prevention
ProductionDesignRequirements
Cost toCorrect in 1970s $
Code Test
Time
$139 $455 $977
$7,136
$14,102
TRW, IBM, and Rockwell Landmark Study
![Page 12: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/12.jpg)
© 2013 SQE Training V3.1 14
Software PsychologyWhat is “good enough”?
Time
# of Bugs
![Page 13: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/13.jpg)
2INTRODUCTION TO STEP AND PREVENTIVE TESTING
![Page 14: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/14.jpg)
© 2013 SQE Training V3.1 16
Select a Method/Process
• Systematic Test and Evaluation Process (STEP™) – SQE
• MS Test Process – Microsoft• TMap®
• Exploratory Testing
· Example testing
methodologies
1.10
1.20
1.24
1.22
1.30
![Page 15: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/15.jpg)
© 2013 SQE Training V3.1 17
STEP™• Level Plans
– Acceptance – System – Integration – Unit
...
U nit
. . .
P lan
A n a lyze D es ig n Im p lem en t
A qu ire
. . .
M easu re
Integration
...
System
...
Acceptance
Project Testing
![Page 16: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/16.jpg)
© 2013 SQE Training V3.1 18
STEP™ Activities
• P1. Establish master test plan• P2. Develop detailed test
plans
· Plan strategy
• A1. Analyze test objectives• A2. Design tests
• A3. Implement plans and designs
· Acquire testware
• M1. Execute tests• M2. Check test set adequacy•M3. Evaluate software and process
· Measure software and
testware
![Page 17: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/17.jpg)
19
Level Timing
Master Test Planning
and
Methodology
Standards
Guidelines
Projectplan
Requirementsspecification
High-leveldesign
ImplementationDetaileddesign
Acceptance
Unit
Integration
System
Plan
Plan
Plan
Plan
Acquire
Acquire
Acquire
Acquire
Measure
Measure
Measure
Measure
© 2013 SQE Training V3.1
![Page 18: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/18.jpg)
© 2013 SQE Training V3.1 20
Preventive Testing
• Testing begins early (i.e., during requirements) and test cases are used as requirements models
• Testware design leads to software design
• Defects are detected earlier or prevented altogether
• Defects are analyzed systematically • Testers and developers work together
![Page 19: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/19.jpg)
21
Opportunities for Defects
Business Needs
Requirements
Design
Coding
Installation
Operation
© 2013 SQE Training V3.1
![Page 20: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/20.jpg)
© 2013 SQE Training V3.1 22
Testers Improve Requirements
• Testers ask:– What does this mean?– Are there any unspecified situations?– How can this requirement be adequately
demonstrated?– What problems might occur?
• Tests define and help specify requirements– “A function/method or constraint specification
is unfinished until its test is defined”
![Page 21: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/21.jpg)
© 2013 SQE Training V3.1 23
Two Views·Food and Drug Administration (FDA):“You CAN’T test quality into your software.”
·SQE:“You MUST test quality into your software.”
![Page 22: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/22.jpg)
3TEST LEVELS
![Page 23: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/23.jpg)
© 2013 SQE Training V3.1 25
What is a Level?
· A level is defined by the environment
· An environment is the collection of
• Hardware• System Software• Application Software• Documentation• People• Interfaces• Data
![Page 24: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/24.jpg)
26
The “V” Model
Plan
Plan
Plan
Plan
Requirements
High-level design
Detailed design
Coding
· Acceptance
· System
· Integration
· Unit
·
·
·
·
© 2013 SQE Training V3.1
![Page 25: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/25.jpg)
© 2013 SQE Training V3.1 27
What determines the number of levels?
·Risk
·Politics
·Organization
·Objectives
![Page 26: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/26.jpg)
© 2013 SQE Training V3.1 28
Acceptance Testing
· Objective: To demonstrate a system’s readiness for operational use and customer acceptance
• Focuses on user requirements• Follows systems testing and is expected to work
• Is a final stage of confidence building• Provides protection to ensure production readiness• Allows customers to “sign off” on the product
· Ends: When the system is approved for use
![Page 27: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/27.jpg)
© 2013 SQE Training V3.1 29
System Testing
· Objective: To develop confidence that a system is ready for acceptance testing. It forms the basis of a regression test set and often represents the bulk of the testing effort
• Most comprehensive testing• Usually tests software design and requirements
• Usually consumes most test resources
· Ends: When a system is turned over for acceptance testing or moved into production
![Page 28: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/28.jpg)
© 2013 SQE Training V3.1 30
Integration Testing
· Objective: To progressively test the interfaces between units and modules
• Focuses on interfaces• Can be top-down, bottom-up, or functional
· Ends: When the entire system has been integrated and stability has been demonstrated
![Page 29: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/29.jpg)
© 2013 SQE Training V3.1 31
Unit Testing
· Objective: To determine that each unit meets its requirements (program specification) and that internal consistency has been achieved
• Can be black-box as well as white-box• Primary means of code coverage
· Ends: When each unit has met its exit criteria
![Page 30: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/30.jpg)
4MASTER TEST PLAN
![Page 31: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/31.jpg)
33
Master Test Plan
Master Test Plan
UnitTest Plan
AcceptanceTest Plan
IntegrationTest Plan
SystemTest Plan
Test Cases
© 2013 SQE Training V3.1
![Page 32: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/32.jpg)
© 2013 SQE Training V3.1 34
Process vs. DocumentationThe process may be more important
than the product (i.e., paper)
![Page 33: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/33.jpg)
© 2013 SQE Training V3.1 35
Audience
Who will read a Master Test Plan?
![Page 34: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/34.jpg)
36
IEEE Style Master Test Plan (2008)
1. Introduction– Document identifier– Scope– References– System overview and
key features– Test overview
• Organization• Master test schedule• Integrity level
schema• Resources summary• Responsibilities• Tools, techniques,
methods, and metrics
2. Details of the MTP– Test processes including
definition of test levels• Management• Acquisition• Supply• Development• Operation• Maintenance
– Test documentation requirements
– Test administration– Test reporting
3. General– Glossary– Document change
procedures and history© 2013 SQE Training V3.1
![Page 35: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/35.jpg)
© 2013 SQE Training V3.1 37
Master Test Plan Sections1. Test Plan Identifier2. Introduction3. Test Items4. Features to be tested5. Features not to be tested6. Software Risks7. Planning Risks and Contingencies 8. Approach9. Item Pass/Fail Criteria10. Suspension Criteria/Resumption Requirements11. Test Deliverables12. Testing Tasks13. Environmental Needs14. Responsibilities15. Staffing and Training Needs16. Schedule17. Approvals
![Page 36: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/36.jpg)
© 2013 SQE Training V3.1 38
1. Test Plan Identifier / 2. Introduction
• Test Plan Identifier
• Introduction– Scope of project– Scope of plan (functional)
![Page 37: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/37.jpg)
© 2013 SQE Training V3.1 39
3. Test Items• What is to be tested, from the library
management perspective• Which build/version of:
– Application software– Documentation– Databases– etc.
Version 2.1
![Page 38: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/38.jpg)
40
To test or not to test? That is the question!
4. Features to Be Tested / 5. Not to Be Tested
© 2013 SQE Training V3.1
![Page 39: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/39.jpg)
42
6. Risk Analysis
Software/product
Project /planning
Two kinds of risk
Testing priority
Contingencies andrisk mitigation
© 2013 SQE Training V3.1
![Page 40: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/40.jpg)
43
6. Example Software/Product Risks
· Scalability· Scope of use· Environment· Accessibility· Usability· Interface complexity· Technical complexity
· Functional complexity· Performance · Reliability· Third-party products· Data integrity· Recoverability· New technology
© 2013 SQE Training V3.1
![Page 41: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/41.jpg)
© 2013 SQE Training V3.1 44
6. Inventory Features and Attributes
Features
• Upload a file• Add a record• Logon to the system• Update a user profile• Generate a report
Attributes
Accessibility Reliability
SecurityPerformance
Backward compatibility
![Page 42: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/42.jpg)
45
6. Risk Likelihood and Impact
· Likelihood• High• Medium• Low
· Impact• High
• Medium• Low
© 2013 SQE Training V3.1
![Page 43: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/43.jpg)
46
6. Initial Risk Priority
LikelihoodHigh (3)Medium (2)Low (1)
ImpactHigh (3)Medium (2)Low (1)
X
= Potential $ Loss
Risk (Test) Priority 1 2 3Impact
Lik
elih
oo
d
12
3
1 2 3
2 4 6
3 6 9
© 2013 SQE Training V3.1
![Page 44: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/44.jpg)
47
6. Risk Inventory ― Example
SpellingInvalid mail-toEmail virusesWrong tel #sSlow performancePoor usabilityUgly siteDoes not work with
Browser XHacker spam attackSite intrusion
Web Site Attribute Likelihood Impact Priority
HighLowMediumLowHighMediumLowMedium
LowLow
LowMediumMediumHighHighMediumMediumHigh
MediumHigh
32439426
23
© 2013 SQE Training V3.1
![Page 45: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/45.jpg)
48
6. Risk Inventory ― Example (cont.)
Slow performanceDoes not work with
Browser XPoor usabilityEmail virusesSpellingWrong tel #sSite intrusionInvalid mail-toUgly siteHacker spam attack
Web Site Attribute Likelihood Impact Priority
HighMedium
MediumMediumHighLowLowLowLowLow
HighHigh
MediumMediumLowHighHighMediumMediumMedium
96
44333222
© 2013 SQE Training V3.1
![Page 46: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/46.jpg)
49
6. Risk Inventory ― Example (cont.)
Slow performanceDoes not work with
Browser XPoor usabilityEmail virusesSpellingWrong tel #sSite intrusionInvalid mail-toUgly siteHacker spam attack
Web Site Attribute Likelihood Impact Priority
HighMedium
MediumMediumHighLowLowLowLowLow
HighHigh
MediumMediumLowHighHighMediumMediumMedium
96
44333222
© 2013 SQE Training V3.1
![Page 47: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/47.jpg)
50
7. Class Questionnaire
1) _________________________________2) _________________________________3) _________________________________4) _________________________________
1) _________________________________2) _________________________________3) _________________________________4) _________________________________
What are your greatest planning risks?
What are your contingencies?
© 2013 SQE Training V3.1
![Page 48: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/48.jpg)
51
7. Example Planning Risk Checklist
• Delivery dates• Staff availability• Budget• Environment options• Tool inventory• Acquisition schedule• Participant buy-in/
marketing• Training needs • Scope of testing
• Lack of product Requirements
• Risk assumptions• Usage assumptions• Resource
availabilityCheck Listxxxxxxxx xxxxxxxx xxxxxxxx xxxxxxxx xxxxxxxx xxxxxxxx xxxxxxxx
X
X
//
/
//
© 2013 SQE Training V3.1
![Page 49: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/49.jpg)
52
7. Contingencies
Contingency Options:
+ Time- Scope/Size+ Resources- Quality/Risk
© 2013 SQE Training V3.1
![Page 50: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/50.jpg)
© 2013 SQE Training V3.1 54
8. Approach / Strategy
· The set of directions that has a major impact on the effectiveness or efficiency of the testing effort (i.e., forks in the road)
![Page 51: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/51.jpg)
© 2013 SQE Training V3.1 56
8. Methodology (Political) Decisions• When will testers become involved in the
project?• What testing levels will be employed?
– Acceptance– System– Integration– Unit
• How many (if any) beta sites will be used?• Will there be a pilot?• What testing techniques will be utilized?
– Inspections– Walkthroughs
![Page 52: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/52.jpg)
57
8. Entrance and Exit Criteria Decisions
• What criteria will be used?• Are the criteria flexible/negotiable?• Who decides?
© 2013 SQE Training V3.1
![Page 53: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/53.jpg)
© 2013 SQE Training V3.1 58
8. Smoke Tests as Entrance Criteria
· Smoke tests are often used to evaluate whether or not a release is REALLY ready for system testing
![Page 54: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/54.jpg)
© 2013 SQE Training V3.1 59
8. Test Coverage Decisions
• Functional coverage should be measured– For every test domain
• Program-based coverage should be used– On all code written (given sufficient
resources)– As a criteria for finishing unit testing
What strategy should be used for determining “where to make the cut”?
![Page 55: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/55.jpg)
© 2013 SQE Training V3.1 60
8. S/W Config Management Decisions
• Who owns/is responsible for each component?
• How many environments will be used, and what will each be used for?
• How often will the SUT be updated?• How much regression testing is required
for each build?– Full– Partial
• Who controls changes to the test environment?
![Page 56: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/56.jpg)
61
8. Full Regression Strategy ― Arguments
Full regression usually requires maintenance of full, effective test sets
· For
• Easy to manage (one test set
per level)• Lowest risk
· Against
• Heavy and often impractical
resource requirements (time
and dollars)
© 2013 SQE Training V3.1
![Page 57: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/57.jpg)
62
8. Partial Regression Strategy ― Arguments
· For
•Solves execution resource problem
• Only viable strategy for emergency
· Against
• Must develop and maintain adequate relationship
information between functions and tests and functions and
components• Must know which components
have changed• Must decide which features
need to be re-tested and assemble subsets
• Adds risk for features not re-tested
© 2013 SQE Training V3.1
![Page 58: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/58.jpg)
© 2013 SQE Training V3.1 64
8. Test Environment(s) Decisions
• Will multiple platforms be needed?• What hardware will be used?• Data
– Where will it come from?– How much volume will be needed?– How fresh (fragility) must it be?– How inter-dependent (referential integrity)
does it need to be?
• What user profiles will be used?• Are simulators or other “test” software
required?
![Page 59: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/59.jpg)
© 2013 SQE Training V3.1 65
8. Automation Decisions
• The four questions– What?– When?– Who?– How?
![Page 60: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/60.jpg)
© 2013 SQE Training V3.1 66
Automated TestingTools are not THE answer
![Page 61: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/61.jpg)
© 2013 SQE Training V3.1 67
9. Item Pass/Fail Criteria• Pass/fail criteria can be expressed using
a number of different measurements:– % of test cases passed/failed– Number of bugs
• Type of bugs• Severity of bugs• Location of bugs
– Overall usability– Overall stability
Bugs and/or test cases may be “weighted”
![Page 62: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/62.jpg)
© 2013 SQE Training V3.1 68
10. Suspension and Resumption Criteria
·Examples of suspension criteria include
· Blocking bugs
· Test case failures > 10%
· GUI response > 5 seconds
· Requirements < 80% complete
· Environmental problems
![Page 63: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/63.jpg)
69
11. Testing Deliverables
Test Plan Test Log
Test Procedure
Specification
Test Design Specification
Test Case Specification
Test Summary
Report
Test Incident Report
© 2013 SQE Training V3.1
![Page 64: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/64.jpg)
70
12. Testing Tasks
To do listaaaabbbbccccddddeeee
© 2013 SQE Training V3.1
![Page 65: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/65.jpg)
© 2013 SQE Training V3.1 71
13. Environmental Needs
• Hardware configuration• Data• Interfaces• Facilities• Publications• Security access• System software• Documentation
![Page 66: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/66.jpg)
72
14. Responsibilities
Development Manager(Jennifer)
Library Manager(Alison)
Test Lead 1(Dale)
Test Lead 2 (Steve)
Tool Coordinator (Karen)
Test Manager(Rick)
Cre
ate
MT
P
Un
it T
est
Exi
t C
rite
ria
Cre
ate
Bu
ild
s
Dev
elo
p T
DS
fo
r F
eatu
re A
Au
tom
ate
Scr
ipts
1-2
2
Dev
elo
p T
DS
fo
r F
eatu
re B
Dev
elo
p T
DS
fo
r F
eatu
re C
Dev
elo
p T
DS
fo
r F
eatu
re D
X
X
X X
X X
X
X
Dev
elo
p T
DS
fo
r F
eatu
re E
X
© 2013 SQE Training V3.1
![Page 67: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/67.jpg)
73
15. Staffing and Training Needs
Successful Testing Recipe
Take 1 experienced project leader
Add 5 senior testers, plus a handful of novice testers
Throw-in liberal amounts of training
Allow to mix and then add tools to taste
Garnish with appropriate amounts of hardware
© 2013 SQE Training V3.1
![Page 68: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/68.jpg)
© 2013 SQE Training V3.1 74
16. Schedule
A timeline with milestones
![Page 69: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/69.jpg)
© 2013 SQE Training V3.1 75
16. Class Discussion
·Where do milestones come from?•Marketing business decision•Wishful thinking•Estimates/guesstimates•Politics•WAGs
I need it today!
![Page 70: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/70.jpg)
76
17. ApprovalsWho calls the shots?
Users?
Product manager?
Development manager?
Test manager?
© 2013 SQE Training V3.1
![Page 71: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/71.jpg)
77
Test Summary Report• Report Identifier• References
– Test items (with revision #s)
– Environments– Test Plan
• Variances (Deviations)– From test plan or
requirements– Reasons for deviations
• Summary of Incidents– Resolved incidents– Defect patterns– Unresolved incidents
• Adequacy Assessment– Evaluation of coverage– Identify uncovered
attributes
• Summary of Activities– System/CPU usage– Staff time– Elapsed time
• Software Evaluation – Limitations– Failure likelihood
• Approvals
© 2013 SQE Training V3.1
![Page 72: Essential Test Management](https://reader033.vdocument.in/reader033/viewer/2022052600/5587d8c5d8b42a14408b4654/html5/thumbnails/72.jpg)
78