estimating the cost of novel (pre-commercial) systems for co2 capture - ed rubin, carnegie-mellon...
DESCRIPTION
A presentation from the 2013 CCS Costs Workshop.TRANSCRIPT
Estimating the Cost of Novel
(Pre-Commercial) Systems for CO2 Capture
Edward S. Rubin Department of Engineering and Public Policy
Department of Mechanical Engineering Carnegie Mellon University
Pittsburgh, Pennsylvania
Presentation to the
CCS Cost Workshop International Energy Agency (IEA)
Paris, France
November 6, 2013
E.S. Rubin, Carnegie Mellon
Characteristics of Novel
(Pre-Commercial) Capture Systems
• Includes any technology not yet deployed or available for purchase at a commercial scale
– Current stage of development may range from
concept to large pilot or demonstration project
• Process design details still preliminary or incomplete
• Process performance not yet validated at scale, or under a broad range of conditions
• May require new components and/or materials that are not yet manufactured or used commercially
E.S. Rubin, Carnegie Mellon
Examples of Pre-Commercial Systems: Everything beyond Present
Source: USDOE, 2010
Time to Commercialization
Advanced physical solvents
Advanced chemical solvents
Ammonia
CO2 com-pression
Amine solvents
Physical solvents
Cryogenic oxygen
Chemical looping
OTM boiler
Biological processes
CAR process
Ionic liquids
Metal organic frameworks
Enzymatic membranes
Present
Co
st
Re
du
cti
on
Be
ne
fit
5+ years 10+ years 15+ years 20+ years
PBI membranes
Solid sorbents
Membrane systems
ITMs
Biomass co-firing
Post-combustion (existing, new PC)
Pre-combustion (IGCC)
Oxycombustion (new PC)
CO2 compression (all)
Time to Commercialization
Advanced physical solvents
Advanced chemical solvents
Ammonia
CO2 com-pression
Amine solvents
Physical solvents
Cryogenic oxygen
Chemical looping
OTM boiler
Biological processes
CAR process
Ionic liquids
Metal organic frameworks
Enzymatic membranes
Present
Co
st
Re
du
cti
on
Be
ne
fit
5+ years 10+ years 15+ years 20+ years
PBI membranes
Solid sorbents
Membrane systems
ITMs
Biomass co-firing
Post-combustion (existing, new PC)
Pre-combustion (IGCC)
Oxycombustion (new PC)
CO2 compression (all)
Advanced physical solvents
Advanced chemical solvents
Ammonia
CO2 com-pression
Amine solvents
Physical solvents
Cryogenic oxygen
Chemical looping
OTM boiler
Biological processes
CAR process
Ionic liquids
Metal organic frameworks
Enzymatic membranes
Present
Co
st
Re
du
cti
on
Be
ne
fit
5+ years 10+ years 15+ years 20+ years
PBI membranes
Solid sorbents
Membrane systems
ITMs
Biomass co-firing
Post-combustion (existing, new PC)
Pre-combustion (IGCC)
Oxycombustion (new PC)
CO2 compression (all)
Post-combustion (existing, new PC)
Pre-combustion (IGCC)
Oxycombustion (new PC)
CO2 compression (all)
E.S. Rubin, Carnegie Mellon
Typical Cost Trend of a New Technology
Research Development Demonstration Deployment Mature TechnologyResearchResearch Development Development DemonstrationDemonstration DeploymentDeployment Mature TechnologyMature Technology
Time or Cumulative Capacity
Cap
ita
l C
ost
pe
r U
nit
of
Cap
ac
ity
Research Development Demonstration Deployment Mature TechnologyResearchResearch Development Development DemonstrationDemonstration DeploymentDeployment Mature TechnologyMature Technology
Time or Cumulative Capacity
Cap
ita
l C
ost
pe
r U
nit
of
Cap
ac
ity
Cap
ital C
ost
per
Un
it o
f C
ap
acit
y
Time or Cumulative Capacity
Research Development Demonstration Deployment Mature Technology
Adspted from EPRI TAG
E.S. Rubin, Carnegie Mellon
Historical Trends of FGD and SCR (DeSOx and DeNOx) Costs . . .
1968
1972
1974
1975
19761980
1982
1990
1995
0
50
100
150
200
250
300
0 10 20 30 40 50 60 70 80 90 100
Cumulative World Wet FGD Installed
Capacity (GW)
Cap
ital
Cos
ts ($
/kW
) in
1997
$
(1000 MW, eff =80-90%)
(200 MW, eff =87%) 1972
1975
1976
19801990
1995
1968
1974
1982
0
1
2
3
4
5
6
7
8
0 10 20 30 40 50 60 70 80 90 100
Cumulative World Wet FGD Installed
Capacity (GW)
O&
M C
osts
(199
7$/M
Wh)
(1000 MW, eff =80-90%)
(200 MW, eff =87%)
Source: Rubin et al. 2007
1983
1989
1993
19952000
-20 -10 0 10 20 30 40 50 60 70 80
Cumulative World SCR Installed Capacity (GW)
SC
R C
ap
ita
l C
ost
s ($
/kW
), 1
99
7$ First Japan commercial installation on a coal-fired power plant
← First German commercial installation
↓ First US commercial installation
←
1980
1983
1989
1993
19952000
40
50
60
70
80
90
100
110
120
1977
1978
1979
1980
All costs based on a standardized
500 MW coal-fired power plant
(except where noted)
. . . display the characteristics
seen in the previous slide
E.S. Rubin, Carnegie Mellon
Five Approaches to Cost Estimation for Novel Systems
• Conventional engineering-economic estimates
• Conventional with probabilistic inputs
• Application of learning (experience) curves
• Expert judgment /elicitations
• Don’t ask, don’t tell
Conventional engineering-
economic costing
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
Most novel processes use conventional costing methods
Many cost elements depend on the technical maturity of the process
E.S. Rubin, Carnegie Mellon
Cost estimates for novel processes often ignore “process contingency cost” guidelines
• Process Contingency Cost “factor applied to new technology … to quantify the uncertainty in the technical performance and cost of the commercial-scale equipment.” - EPRI TAG
Technology Status
Process
Contingency
Cost
(% of associated
process capital)
New concept with limited data 40+
Concept with bench-scale data 30-70
Small pilot plant data 20-35
Full-sized modules have been
operated 5-20
Process is used commercially 0-10
Source: EPRI, 1993; AACE, 2011
• Most studies of advanced capture systems for full-scale power plants (~500 MW) assume much smaller values than these guidelines call for, e.g.:
• 7% (IEAGHG, 2011)
• <20% (EPRI, 2011)
• 18% (USDOE, 2010)
• 10% (IECR, 2008)
E.S. Rubin, Carnegie Mellon
What system are we trying to cost?
• Early commercial deployment? (first of a kind), or
• Mature widely-deployed system? (Nth of a kind)
The major difference is usually in the system design (though some cost factors also may change)
Whichever case is chosen, process contingency cost
depends on the current state of technical
E.S. Rubin, Carnegie Mellon
Cost studies also commonly ignore guidelines for “project contingency cost”
• Project Contingency Cost “factor covering the cost of additional equipment or other costs that would result from a more detailed design of a definitive project at an actual site.” - EPRI TAG
EPRI Cost
Classification Design Effort
Project
Contingency (% of total process
capital, eng’g &home
office fees, and process
contingency)
Class I (~AACE Class 5/4)
Simplified 30–50
Class II (~AACE Class 3)
Preliminary 15–30
Class III (~ AACE Class 3/2)
Detailed 10–20
Class IV (~AACE Class 1)
Finalized 5–10
Source: EPRI, 1993
• Many Class I-III studies assume
≤10%
Conclusion:
• The total contingency cost for novel capture processes is grossly under-estimated in most cost estimates
• (e.g., totals of ~20-30% rather than ~40-100%)
E.S. Rubin, Carnegie Mellon
Example of Contingency Cost Impact on Total Cost
Process + Project Contingency Cost
for the CO2 capture process alone
Parameter 20% 50% 100%
Capture System Capital Cost
($/kW) 17% 42% 85%
Capture System COE
($/MWh) 8% 20% 40%
Total Plant Capital Cost
($/kW) 5% 13% 26%
Total Plant COE
($/MWh) 4% 11% 18%
Increase in Capital Cost and COE
(based on a 2-stage membrane capture system)
Conventional costing with
probabilistic variables
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
Case Study of PC Plant with a 2-Stage Membrane Capture System
Membrane System Parameter Unit Nominal Value Distribution Function
Ideal CO2 Permeance (S.T.P.) gpu 1000 triangular (500, 1000,5000)
Ideal CO2/N2 Selectivity (S.T.P.) ratio 50 triangular (40, 50, 75)
Feed-side Compressor Efficiency % 85 uniform (70, 85)
Vacuum Pump Efficiency % 85 uniform (70, 85)
Expander Efficiency % 85 uniform (70, 85)
CO2 Compressor Efficiency % 80 uniform (70, 85)
Cost Parameters
Membrane Module Cost $/sq ft 4.645 triangular (2.322, 4.645,18.58)
Total Indirect Capital Cost % PFC 37 uniform (20, 60)
CO2 T&S Costs $/ton 5 uniform (1,10)
Source: IECM v.8.0.2 (2013)
Probability
distributions
assigned to 6
performance
variables and 3
cost variables
E.S. Rubin, Carnegie Mellon
Case Study: SCPC-CCS (550 MWnet)
w/ 2-Stage Membrane Capture System
Conclusion:
• Explicit characterization of uncertainties can improve cost estimates by revealing risks as well as opportunities
95% CONFIDENCE INTERVALS=
COE:
DV +31/ -6 MWh (+51%/ -10%)
CO2 Avoidance Cost:
DV +49/ -8 $/ton= (+62%/ -10%)
0%
20%
40%
60%
80%
100%
0 30 60 90 120 150
Cum
ula
tive P
robabili
ty
Added Cost for CCS (Constant 2011 $/MWh)
Mean = $72 /MWh2.5% = $55 /MWh97.5% = $97 /MWh
Deterministic
Value (DV)
0%
20%
40%
60%
80%
100%
0 30 60 90 120 150 180
Cum
ula
tive P
robabili
ty
Cost of CO2 Avoided (Constant 2011 $/ton)
Mean = $94 /ton2.5% = $71 /ton97.5% = $128 /ton
Deterministic
Value (DV)
Cost estimates based on
learning curves
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
One-Factor Learning (Experience) Curves are the Most Prevalent
where, Ci = cost to produce the i th unit
xi = cumulative capacity thru period i
b = learning rate exponent
a = coefficient (constant)
Model equation:
Fractional cost reduction for a doubling of cumulative capacity (or production) is defined as
the learning rate: LR = 1 – 2b
Ci = a xi –b
20000
10000
5000
1000
10010 100 1000 10000 100000
1982
1987
1963
1980
Windmills (USA)
RD&D
Commercialization
USAJapan
Cumulative MW installed
19811983
500
Photovoltaics
Gas turbines (USA)
1995
1992
200
2000
Source: IIASA, 1996
• Most appropriate for projecting future cost of a current technology already commercially deployed
• Application to novel (pre-commercial) processes requires careful consideration of the “starting point” (cost and experience base) for future cost reductions
E.S. Rubin, Carnegie Mellon
Reported Learning Rates for Power Plant Technologies Vary a Lot
Table ES-1: Summary of studies characterizing historical learning rates for electric power
generation technologies.
Technology
Number
of studies
reviewed
Number
of studies
with one
factor
Number
of studies
with two
factors
Range of
learning rates
for “learning by
doing” (LBD)
Range of rates
for “learning by
researching”
(LBR)
Years
covered
across all
studies
Coal* PC 2 2 0 5.6% to 12%
1902-2006
IGCC 1 1 0 2.5% to 7.6%
Projections
Natural Gas* 8 6 2 -11% to 34% 2.38% to 17.7% 1980-1998
Nuclear 4 4 0 <0 to 6%
1975-1993
Wind (on-shore) 35 29 6 -3% to 32% 10% to 26.8% 1980-2010
Solar PV 24 22 2 10% to 53% 10% to 18% 1959-2001
BioPower Biomass production 4 4 0 12% to 45%
1971-2006
Power generation** 7 7 0 0% to 24%
1976-2005
Geothermal power 3 0 0
1980-2005
Hydropower 3 0 2 0.48% to 11.4% 2.63% to 20.6% 1980-2001
*Does not include plants with CCS. **Includes combined heat and power (CHP) and biodigesters.
0
1
2
3
-15% to -9%
-10% to -4%
-5% to -1%
0% to 4%
5% to 9%
10% to 14%
15% to 19%
20% to 24%
25% to 29%
30% to 34%
Fre
qu
en
cy
Learning RateDependent Variable = $/kW (n=9) Dependent Variable = $/kWh (n=2)
Mean = 14%Median = 13%Std Dev = 13%
Natural Gas-Fired Plants
0
2
4
6
8
10
12
-5% to -1%
0% to 4% 5% to 9% 10% to 14%
15% to 19%
20% to 24%
24% to 29%
30% to 34%
Co
un
t
Learning Rate
Histogram of Learning Rates in the Literature
Dependent Variable = $/kWh (n=12) Dependent Variable = $/kW (n=23)
Mean = 16%Median = 12%Std Dev = 14%
On-Shore Wind Plants
Source: Azevedo et al,2013
E.S. Rubin, Carnegie Mellon
Effect of Learning Curve Uncertainties
for Power Plants w/ CCS
0
5
10
15
20
25
30
Perc
en
t R
ed
ucti
on
in
CO
E
NGCC PC IGCC Oxyfuel
% COE REDUCTION AFTER
100 GW EXPERIENCE
• Projected reduction in cost of
electricity (COE) for each
plant type varies by a factor
of ~2 to 4
• Nonetheless, the judicious
use of learning curves can
suggest a pathway from
FOAK to NOAK costs for
novel technologies
Source: Rubin et al., 2007
Cost estimates based on
expert elicitations
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
Common Applications of Expert Judgment
• Estimating the future value of a parameter used in a model or cost calculation
• Direct estimates of the future value of a cost or other characteristic of interest
E.S. Rubin, Carnegie Mellon
One of four amine
system parameters
estimated by experts
and used to calculate
expected cost reductions
from advanced solvents
(below)
Example of Expert Elicitations (1)
E.S. Rubin, Carnegie Mellon
Absorption
Precombustion
Oxyfuel
Chemical Looping
$/tCO2
density
Scen.3: Minimum cost of CO2 avoided ($/tCO2) across 7 technologies
30 40 50 60 70 80 90 100 110 1200
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
Abs=0.20
Ads=0.03
Mem=0.02
Oth=0.04
Pre=0.30
Oxy=0.24
CLC=0.17
2025
Source: Jenni, K.E., Baker, E.D., Nemet, G.F. (2013).
IJGGC, 12, 136-145.
Source: Nemet, G.F., Baker, E., Jenni, K.E. (2013).
Energy, 56, 218–228.
Example of Expert Elicitations (2)
Elicitations by Nemet et al. of future energy penalty and avoidance cost
for seven capture technologies as a function of three policy scenarios
E.S. Rubin, Carnegie Mellon
How does expert judgment compare to costs projected using learning rates ?
950
1,000
1,050
1,100
1,150
1,200
2015 2020 2025 2030 2035 2040 2045 2050
Co
st ($
/kW
)
NGCC w/o CCS
Original EPRI
Base Case
ALT 1 - CES
ALT 2 - CTAX20
ALT Base Case
4,600
4,700
4,800
4,900
5,000
5,100
5,200
5,300
5,400
2015 2020 2025 2030 2035 2040 2045 2050
Co
st ($
/kW
)
Nuclear
Original EPRI
Base Case
ALT 1 - CES
ALT 2 - CTAX20
ALT Base Case
0
500
1,000
1,500
2,000
2,500
2015 2020 2025 2030 2035 2040 2045 2050
Co
st ($
/kW
)
On Shore Wind
Original EPRI
Base Case
ALT 1 - CES
ALT 2 - CTAX20
ALT Base Case
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2015 2020 2025 2030 2035 2040 2045 2050
Co
st ($
/kW
)
Solar PV (Rooftop)
Original EPRI
Base Case
ALT 1 - CES
ALT 2 - CTAX20
ALT Base Case
EXPERTS
EXPERTS
EXPERTS
EXPERTS
Conclusion:
• Expert judgment is often inconsistent with learning curve projections
Source: Azevedo et al,2013
Don’t ask, don’t tell
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
Avoid Cost Estimates for Processes at Early Stages of Development
• This approach favors the use of performance metrics, rather that cost estimates, to evaluate and screen novel components or process designs in the early stages of development (e.g., TRL levels 1-3 or higher)
• For novel CO2 capture processes, projected reductions in the power plant energy penalty is a favored metric
• No guarantee, however, that improvements in key performance metrics will necessarily result in lower overall cost (e.g., COE) for the novel system
So where does this leave us ?
E.S. Rubin, Carnegie Mellon
E.S. Rubin, Carnegie Mellon
Conclusions and Recommendations
Conclusions
• A variety of methods are available to estimate the future
cost of new, pre-commercial capture systems; but …
• Some methods are not commonly used; others are often
used inappropriately; no clear consistency across method
Recommendation
• Establish a task force to develop improved guidelines,
emphasizing needs for transparency and incorporation
of uncertainties in cost estimates for novel processes
E.S. Rubin, Carnegie Mellon
A Final Word of Wisdom
“It’s tough to make predictions,
especially about the future”
- Yogi Berra
Future
CCS
Costs