europa penetrator design and survivability testing ippw10 sanjay vijendran, esa estec marie-claire...

22
Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom Kennedy, University College London (Mullard Space Science Laboratory) Phillip Church, QinetiQ Jeremy Fielding, Rapid Space Technologies Nick Taylor, University of Cambridge (Cavendish Laboratory)

Upload: barnard-atkins

Post on 21-Jan-2016

213 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Europa Penetrator Design and Survivability TestingIPPW10Sanjay Vijendran, ESA ESTEC

Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium

Tom Kennedy, University College London (Mullard Space Science Laboratory)

Phillip Church, QinetiQ

Jeremy Fielding, Rapid Space Technologies

Nick Taylor, University of Cambridge (Cavendish Laboratory)

Page 2: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

19/06/2013 - 2

Mission Overview

Page 3: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Mission Science Goals Key science focus

astrobiology

Primary payloads Mass spectrometer Habitability package Microscope

Sampling system required drill through the shell and collect material for analysis

19/06/2013 - 3

Sampling Mechanism

Mass Spectrometer

Microscope

Page 4: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Penetrator Design

19/06/2013 - 4

EPAC front bay

Warm platform bay showing configuration

Rear plate

E-PAC

Central Bulkhead

Cold bay

Warm bay

Bay support system

Page 5: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Delivery System Design Function to deliver

the penetrator to the right location with the right impact conditions

PDS provides: attitude control descent timing large delta-V Penetrator release Orbiter interface

19/06/2013 - 5

Main engine

Attitude control thrusters

Bipropellant system

Avionics bay

Page 6: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

System Verification Current contract is focussed on maturing

technology and reducing risk for penetrator missions

Method applied: Impact Modelling for penetrator and critical components Small scale impact testing for critical components Functional testing for sampling mechanism Full scale impact testing to demonstrate mechanical system

performance and key items

19/06/2013 - 6

Page 7: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Small Scale Modelling Modelling of impact set up at

Cavendish Determine the speeds and materials

to be used for the small scale test flyer plates

Aim to reproduce the loading regime experience at full scale

Modelling of small scale test items

Small scale penetrator model Key electronics Torlon springs

19/06/2013 - 7

Page 8: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Small Scale Model Results

19/06/2013 - 8

Page 9: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Full Scale Modelling

Date - 9

Page 10: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Date - 10

Page 11: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Date - 11

Page 12: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Date - 12

Page 13: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Small Scale Tests Small scale testing

programme carried out at University of Cambridge Cavendish Labs

Following tests carried out: Batteries Data loggers Torlon leaf springs Drill components UHF critical components Scaled shells with Al plugged

apertures

Test outcomes largely successful

19/06/2013 - 13

Page 14: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Plugged Shell & Test Compartments

19/06/2013 - 14

Plugged Penetrator aperture

Page 15: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Torlon Spring Test Results (1)

19/06/2013 - 15

Page 16: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Torlon Spring Test Results (2)

19/06/2013 - 16

43 us

128 us

241 us

299 us

385 us

556 us

641 us

Page 17: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

19/06/2013 - 17

Page 18: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Functional Testing (1/2)

19/06/2013 - 18

Page 19: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Functional Testing (2/2)

19/06/2013 - 19

Page 20: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Full Scale Tests Full scale testing of the penetrator

planned for July 2013

Tests carried out at the QinetiQ operated MoD test range at Pendine

Rocket sled used to accelerate the Penetrator to a ~300m/s impact velocity

Two firings planned, one into sand, one into ice

Target dimensions 3 x 3 x 6 m

19/06/2013 - 20

Page 21: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Full Scale Breadboards

19/06/2013 - 21

Page 22: Europa Penetrator Design and Survivability Testing IPPW10 Sanjay Vijendran, ESA ESTEC Marie-Claire Perkinson, Lester Waugh, Mike Williams, Astrium Tom

Next Steps Complete full scale testing

Review outcomes

Plan for next steps: Potential follow on activities to be decided Battery and transceiver technologies to be addressed Inductive interface for power and data also of interest

19/06/2013 - 22