evaluation of an industrial microgrid using ......u.p.b. sci. bull., series c, vol. 79, iss. 4, 2017...
TRANSCRIPT
U.P.B. Sci. Bull., Series C, Vol. 79, Iss. 4, 2017 ISSN 2286-3540
EVALUATION OF AN INDUSTRIAL MICROGRID USING
HOMER SOFTWARE
Andrei HORHOIANU1, Mircea EREMIA
2
The paper highlights the technical, economic and environmental aspects
related to the development of a microgrid at an industrial oil field level. Microgrid
simulation based on HOMER software has two main objectives. The first objective is
to determine the feasibility of the microgrid. HOMER considers the microgrid being feasible if it is able to meet the electricity and heat demand, as well as other
restrictions imposed by the user. The second goal is to estimate the life cycle cost of
the microgrid, represented by the installation and lifetime operating costs. The
availability of renewable energy resources strongly affects the behavior and
financial aspects of microgrids based on such energies, because the amount of
energy and generating duration are two functions strictly dependent upon the
availability of primary energy resources.
Keywords: HOMER, microgrid, renewable energy, load demand
1. Introduction
The technical and economic analysis of a microgrid is a difficult process
due to the number of design options and the uncertainty of key parameters, such
as demand profiles of thermal or electrical loads or fuel prices. Moreover,
renewables, by their intermittent nature and non-dispatchable seasonal production,
add additional complexity. To overcome all challenges mentioned above, a series
of software applications such as HOMER, RETScreen or DER-CAM can be used
for the technical and economic analyzes. In this paper, we opted to use HOMER
(Hybrid Optimization Model for Energy Resources) as it allows the user to carry
out the simulation, optimization and sensitivity analysis of a microgrid model. To
determine the microgrid’s feasibility and life cycle cost, HOMER examines, in the
simulation step, its hourly performances for the duration of one year. In the
optimization phase, HOMER simulates a series of possible configurations for the
microgrid, in order to determine the solution that satisfies all technical restrictions
at a minimum life cycle cost. In the sensitivity analysis stage, HOMER performs a
series of optimizations to smooth out uncertainties or changes in the assumptions
considered. The optimization process determines the optimal values of design
variables such as type, size and number of microgrid components, while the
1 PhD student, Dept. of Electrical Power Systems, University POLITEHNICA of Bucharest,
Romania, e-mail: [email protected] 2 Professor Emeritus, Dept. of Electrical Power Systems, University POLITEHNICA of Bucharest,
Romania, e-mail: [email protected]
194 Andrei Horhoianu, Mircea Eremia
sensitivity analysis assesses the effects of uncertainties or changes on microgrid
parameters such as average wind speed or the future fuel price. To limit the
complexity of input data and allow for a fast and practical calculation, the
simulation logic used by HOMER is less detailed than other simulation software
such as DesignPro or Hybrid2 [1] used in technical and economic analysis of
microgrids. On the other hand, HOMER is more detailed and advanced than
software such as RETScreen, which does not allow time series simulations [2].
2. Microgrid characteristics
To highlight the technical, economic and environmental aspects of an
industrial microgrid, we consider a microgrid developed on an existing oil field
site. As shown in Fig. 1, it is assumed that the microgrid is interconnected to a
public distribution network (20 kV) and it includes a series of production
equipment and distributed energy sources for efficient and safe operation of the
oil field resources.
Fig. 1. The microgrid architecture analyzed using HOMER
In terms of energy resources, required for exploitation of the oil field, the
microgrid includes two cogeneration units with gas turbines, one high capacity
boiler, two wind turbines and a photovoltaic system with a battery string for
Evaluation of an industrial microgrid using HOMER software 195
ensuring power supply of critical equipment. The optimum capacity of each
distributed generation unit is determined in the following sections using HOMER
software.
3. Microgrid components modeling
In HOMER simulation, the microgrid must include at least one electrical
and/or one thermal power source, and one destination of the generated energy
(e.g. electrical and/or thermal loads) or it must have the possibility of selling the
generated energy to the network. In the following sections, we present the way
microgrid components are modeled, using HOMER, as well as the technical and
economic aspects related to their common operation.
A. Load modeling
HOMER defines the term load, as an electrical or thermal energy demand.
The microgrid under review encompasses a number of electrical and thermal loads
spread over a relatively small area ( 50 𝑘𝑚2) at all levels of oil production within
the oil field. To simulate all these loads, HOMER requires the hourly values of
electricity demand registered at point of common coupling (PCC) as well as the
hourly values of thermal demand registered at the oil deposit and gathering and
treatment station.
Considering typical demand profiles for electricity and thermal usage
within an oil field from the North-East of Romania, we have set out in HOMER
the daily profiles of the electrical (Fig. 2.a) and thermal loads (Fig. 2 b). These
load profiles are dictated by the technological processes occurring at the oil field
under review.
a) b)
Fig. 2. Daily load profiles: (a) electrical (b) thermal
Analyzing the load profiles highlighted in Fig. 2 above, we can conclude
that at the point of common coupling, the total electrical demand of the microgrid
196 Andrei Horhoianu, Mircea Eremia
has a daily average of 22.000 kWh/day and records two peak times (8:00 – 1200
kW and 23:00 – 1500 kW), while the thermal demand of the oil deposit and
gathering and treatment station presents a daily average of 7200 kWh/day and a
peak of 500 kWh/day every 3 hours. Based on the specified daily load profiles,
HOMER determines the monthly and annually load profiles of the microgrid
(Figs. 3 a and b).
a) b)
Fig. 3. Monthly and annual load profiles: (a) electrical (b) thermal
B. Energy resources modeling
In HOMER simulation, the term energy resource refers to any form of
energy used by the microgrid to generate electrical power or heat. The energy
resources available within the HOMER software include four forms of renewable
energy ( solar, wind hydro and biomass) as well as fossil fuel based systems.
Renewable energy resources vary greatly depending on geographic location. For
example: solar energy is strictly dependent on climate and latitude; wind power
varies depending on weather fronts and landscaping; hydropower depends on
landscaping topology and rain while the biomass resources depend on local
biological productivity. Moreover, in any geographical areas, each renewable
energy source presents seasonal or even hourly variations.
The availability of renewable energy resources strongly affects the
behavior and financial aspects of a production system based on such energies
because the amount of energy and production duration are two functions, strictly
dependent upon the availability of primary energy resources. Therefore, the
Evaluation of an industrial microgrid using HOMER software 197
appropriate modeling of renewable energy is an important aspect of any program
of technical and economic analysis.
For modeling the photovoltaic system, HOMER requires the geographical
coordinates of the system. Therfore, it is considered that the analyzed microgrid is
developed at an industrial oil field located in Moinesti, in the north-west of
Romania. After selecting the geographic location, HOMER generates statistic data
regarding the available solar energy in the selected area, using NASA database
and an algorithm developed by Graham and Hollands [3]. The obtained statistics
are presented in Fig. 4.
Fig. 4. Average values of solar radiation in Moinesti, Romania
As seen in Fig. 4, the horizontal solar radiation poses to the area under
consideration, an annual average of 3.25 kWh/m2/day and an average annual
clarity index of 0.41. Clearness index, defined as a subunitary ratio between solar
radiation at the ground level and the solar radiation at the atmosphere level, is a
measure of atmosphere clarity. With regards to the photovoltaic system, this is
modeled in HOMER as a device that produces electricity directly proportional to
the incident solar radiation from its surface, and independently of temperature and
voltage to which it is exposed.
HOMER calculates the energy produced by the photovoltaic system, using
the following equation [6]:
𝑃𝑃𝑉 = 𝑓𝑃𝑉 ∙ 𝑌𝑃𝑉 ∙𝐼𝑇
𝐼𝑠 (1)
where: 𝑃𝑃𝑉 – power generated by the photovoltaic system (kW)
𝑓𝑃𝑉 – correction factor of the nominal capacity
𝑌𝑃𝑉 – nominal capacity of the photovoltaic system (kW)
𝐼𝑇 – global solar radiation incident on the system surface (𝑘𝑊/𝑚2)
198 Andrei Horhoianu, Mircea Eremia
𝐼𝑠 – standard amount of solar radiation used for specifying the nominal capacity of the PV system
(1 𝑘𝑊/𝑚2)
The nominal capacity of a photovoltaic system represents the power
generated under standard test conditions. In HOMER, the power generated by the
PV system is always specified as the nominal capacity. For every hour of the year,
HOMER calculates the global solar radiation, incident on the surface of the PV
system using HDKR model developed by Duffie and Beckmann [4]. This model
takes into account: the amount of solar radiation global incidents in an open area;
orientation of the PV system; geographic location, and time of the year and day.
The correction factor (𝑓𝑃𝑉) highlights the effects of dust, losses in cables,
temperature and other factors that may cause deviations on the power generated
by the photovoltaic system from the values recorded under standard test. HOMER
does not consider the effect of temperature on the power generated by the
photovoltaic system, but the correction factor can be reduced to take account of
this aspect.
In reality, the power generated by the photovoltaic system depends
strongly and nonlinearly on the voltage to which is exposed. The peak power
(voltage level at which maximum power is generated) depends on solar radiation
and temperature. If the photovoltaic system is connected directly to d.c. load or a
battery system, then the voltage differs from the maximum point and system
performance will suffer. To address this deficiency, a device called maximum
power point tracker, is installed between the photovoltaic system and the other
components so that the voltage to which the photovoltaic system is exposed,
coincide with maximum value. HOMER considers that the simulated photovoltaic
system has a maximum power point tracker by default. To carry out the economic
calculations with HOMER, the user will have to specify the cost of initial
investment ($), the replacement cost ($) and annual operating and maintenance
costs ($/year). By default, the replacement cost is considered equal to the cost of
initial investment.
To define the search space of the optimal solution, in terms of technical
and economic aspects, we consider as standard values the following parameters:
Initial investment cost for a 25 kW photovoltaic system - 75.000 $;
Replacemnt cost for a 25 kW photovoltaic system - 75.000 $
Annual operating and maintenance costs for a 25 kW photovoltaic
system - 250 $/year
Liftetime of 25 kW photovoltaic system - 25 years
Correction factor - 80%
Considering these span values, the average value of solar energy in the
selected geographic area, the load profiles and the features and restrictions on
other elements of the microgrid (detailed in the following sections), HOMER
Evaluation of an industrial microgrid using HOMER software 199
generates a series of possible configurations to identify the optimal solution,
characterized by a minimum net present cost. The characteristics of the
photovoltaic system obtained for the optimal solution, are presented in Fig. 5.
Fig. 5. Photovoltaic system characteristics obtained in the optimal solution
With regards to simulation of wind turbine systems in HOMER, the first
step is to generate data on the wind energy, available in the selected geographical
location. This data relates to the wind speeds encountered by the turbine during a
year and can be specified by the user or automatically generated by HOMER
using nASA database. In addition, HOMER generates four additional statistic
parameters: Weibull form factor, autocorrelation factor, daily power pattern and
peak hourly wind speed value. The characteristics of the wind speed, obtained by
HOMER for the geographical location of our microgrid, are presented in Fig. 6
and 7.
Fig. 6. Average wind speed values Fig. 7. Variation with altitude of wind speed
200 Andrei Horhoianu, Mircea Eremia
Analysing the above figures, we can observe that the wind speed has an
average value of 4.9 m/s and a logarithmic profile with respect to the variation of
the altitude. The wind speed additional parameters generated by HOMER are
presented in Table 1. Table 1
Wind speed parameters generated by HOMER
Parameter Value
Weibull form factor 2
Autocorrelation factor 0.85
Daily load pattern 0.25
Peak hourly wind speed 15
The Weibull form factor is a measure of the wind speed distortion over the
year. The autocorrelation factor highlights the dependence of wind speed at a
certain hour on the wind speed recorded in the previous hour. The daily load
pattern and peak hourly wind speed indicate the magnitude and phase of the daily
wind speed model. The wind turbine is modeled in HOMER as a device that
converts the kinetic wind energy into electricity after a power curve defined as a
variation of the power generated by the wind velocity. To perform the
simulations, HOMER considers a standard air density of 1.225 𝑘𝑔/𝑚3.
For each hour, HOMER calculates the power generated by the wind
turbine, following a four-step process. Thus, in a first stage HOMER determines
the average wind speed for the time considered on the basis of characteristic data
previously generated for wind energy. In the second step, HOMER determines the
average wind speed at the turbine nacelle using a function of speed variation with
altitude (Fig. 9). In the third stage, based on the turbine power curve (Fig. 8)
HOMER determines the power generated by the wind turbine considering the air
standard density. In the final step, the power calculated in step 3 is multiplied with
the ratio between the current air density and standard density.
Fig. 8. Wind turbine power curve
Evaluation of an industrial microgrid using HOMER software 201
To define the search space of the optimal solution, in terms of technical
and economic aspects, we consider as standard values the following parameters:
Initial investment cost for a 1500 kW wind turbine - 3 M $
Replacement cost for a 1500 kW wind turbine - 3 M $
Annual operating and maintenance costs - 0.03 M $/year
Lifetime of the wind turbine - 20 years
The nacelle height - 80 m
Considering these span values, the average value of wind energy in the
selected geographic area, the load profiles and the features and restrictions on
other elements of the microgrid (detailed in the following sections), HOMER
generates a series of possible configurations to identify the optimal solution,
characterized by a minimum net present cost. The characteristics of the wind
turbine obtained for the optimal solution, are presented in Fig. 9.
Fig. 9. Wind turbine characteristics obtained in the optimal solution
With regards to cogeneration plants, HOMER defines these as equipment
used for generating electricity and heat from fossil fuels or biomass. The main
physical parameters defined by HOMER user, refer to generated electricity
(minimum and maximum), equipment lifetime in hours of operation, type of fuel
used and consumption curve. To serve the electricity and heat demand of the oil
field, we consider that the microgrid encloses two cogeneration plants with a
capacity of 2000 kW each. The parameters specified in HOMER, are presented in
Table 2.
202 Andrei Horhoianu, Mircea Eremia
Table 2
Parameters of cogeneration plants
Cogeneration
plant Parameter Value
CG01, CG02
Capacity ( kW) 2000
Initial investment cost ($) 1.200.000
Replacement cost ($) 1.200.000
Annual operating and maintenance cost ($/year) 30.000
Minimum loading (%) 10
Lifetime (hours) 15.000.000
Thermal energy recovery ratio (%) 40
Minimum operating time ( minutes) 120
As shown in Table 2, the two cogeneration plants have same technical
characteristics and can operate alternately or simultaneously in order to satisfy the
electricity and heat demand. We consider that the natural gas extracted in the oil
field represents the fuel used by the cogeneration plants following the
consumption curve presented in Fig. 10.
Fig. 10. Fuel consumption curves of cogeneration plants
The properties of the gas produced within the oil field and used within the
cogeneration plants, are presented in Table 3. Table 3
Fuel parameters
Parameter Value
Higher heating value ( MJ/kg) 43.2
Density (kg/𝑚3) 820
Carbon content (%) 88
Sulf content (%) 0.33
HOMER defines the fuel consumption curve using the following equation [6]:
𝐹 = 𝐹0𝑌𝑔𝑒𝑛 + 𝐹1𝑃𝑔𝑒𝑛 (2)
where:
Evaluation of an industrial microgrid using HOMER software 203
𝐹0 – consumption curve interception coefficient, in l/hr/kW
𝐹1 – consumption curve slope, in l/hr/kW
𝑌𝑔𝑒𝑛 – nominal capacity of the cogeneration unit, in kW
𝑃𝑔𝑒𝑛 – electrical energy produced by the cogeneration unit, in kW
The emissions of pollutants are also taken into consideration in the
microgrid simulation. The emissions values considered for each of the two
cogeneration plants, are presented in Table 4. Table 4
Pollutants emissions values
Pollutant Value
Carbon monoxide ( g/l) 6.5
Incompletely burned hydrocarbons (g/l) 0.72
Solide particles (g/l) 0.49
Sulfur based compounds (g/l) 2.2
Nitrogen oxides ( g/l) 58
Based the on economic parameters defined in Table 2, HOMER calculates
the fixed and marginal cost of generating energy. These values are then used in
the simulation phase to determine the optimal economic and technical solution.
HOMER calculates the fixed cost of producing energy using the following
equation [6]:
𝑐𝑔𝑒𝑛,𝑓𝑖𝑥 = 𝑐𝑜𝑚,𝑔𝑒𝑛 +𝐶𝑟𝑒𝑝,𝑔𝑒𝑛
𝑅𝑔𝑒𝑛+ 𝐹0𝑌𝑔𝑒𝑛 ∙ 𝑐𝑓𝑢𝑒𝑙,𝑒𝑓𝑓 (3)
where:
𝑐𝑜𝑚,𝑔𝑒𝑛 –operating and maintenance costs, in $/hour
𝐶𝑟𝑒𝑝,𝑔𝑒𝑛 – replacement cost, in $
𝑅𝑔𝑒𝑛 – lifetime, in hrs
𝐹0 – consumption curve interception coefficient, in L/hr/kW
𝑌𝑔𝑒𝑛 – nomial capacity of the cogeneration unit, in kW
𝑐𝑓𝑢𝑒𝑙,𝑒𝑓𝑓 –fuel cost (including penalties due to pulluants), in $/l
HOMER calculates the marginal cost of producing energy using the
equation [6]:
𝑐𝑔𝑒𝑛,𝑚𝑎𝑟 = 𝐹1 ∙ 𝑐𝑓𝑢𝑒𝑙,𝑒𝑓𝑓 (4)
where:
𝐹1 – consumption curve slope, in l/hr/kW
𝑐𝑓𝑢𝑒𝑙,𝑒𝑓𝑓 – fuel cost (including penalties due to pulluants), in $/l
Taking into account all the above, the HOMER generates a series of
possible configurations to identify the optimal solution, characterized by a net
204 Andrei Horhoianu, Mircea Eremia
present cost. The characteristics of the cogeneration plants for the optimal
solution, are presented in Fig. 11.
Fig. 11. Cogeneration plants characteristics obtained in the optimal solution
The battery system enclosed within the microgrid is modeled in HOMER
as a device capable of storing a certain amount of energy at a reasonable
efficiency with a number of restrictions in terms of duration of loading,
discharging and lifetime. It is assumed that the properties of the battery system,
remain constant throughout its lifetime and are not affected by external factors
such as temperature.
The main physical parameters of the battery system, specified by HOMER
user are: rated voltage, rated power, lifetime, initial charge status, minimum
charging status and efficiency. The values of these parameters for the battery
system enclosed within the microgrid are summarized in Table 5. Table 5
Battery system parameters
Parameter Value
Nominal voltage (V) 48
Nominal power (kWh) 70
Initial charging status (%) 100
Minimum charging status (%) 40
Efficiency (%) 64
Lifetime (years) 20
In order to calculate the maximum degree of loading or unloading of the
battery system, HOMER considers the battery kinetic model [5], wherein the
battery is regarded as a system of two containers, as shown in Fig. 12.
Evaluation of an industrial microgrid using HOMER software 205
Fig. 12. Battery kinetic model
According to the kinetic model, some of the energy stored in the battery is
immediately available for loading / unloading and the rest depends on the nature
of chemical bonds in the battery energy. The conversion rate of this type of
energy depends on the "height" of the two tanks. In this model, the battery is
described using the following parameters:
maximum capacity - the total size of the two tanks
capacity rate - the ratio between the available energy the bound
energy
constant conversion rate - the dimension of pipeline between the
two tanks
The battery kinetic model explains the typical capacity curve (Fig. 13) for
a battery system modeled in HOMER. Therefore, for high discharge rates, the
tank is draining quickly the available energy and only a small fraction of the
bound energy can be transferred to the reservoir of available energy, before it is
discharged. At this point of time, the battery can no longer cope with the demand
and behave like a completely empty tank.
Fig. 13. Typical capacity curve for a US-250 battery (www.usbattery.com)
Simulating the battery as a system of two reservoirs, allows emphasizing
the following two specific aspects:
206 Andrei Horhoianu, Mircea Eremia
The battery cannot charge/discharge fast; a full charge requires an
infinite amount of time for a given load current, which tends to zero.
The battery’s ability to charge/discharge, depends not only on the
charging status but also in the history of recent charge/discharge
cycle.
Therefore, a charged battery to 80% state of charge, will face higher
discharge rates, compared to a battery with a quick discharge to 80% because it
has a higher level in the reservoir of available energy. HOMER allows modeling
of both aspects outlined above, using kinetic model.
To perform the economic calculation using HOMER, the user has to
specify the cost of the battery system, the replacement cost and the annual cost of
operation and maintenance. The costs considered for the battery system enclosed
within our microgrid are presented in Table 6. Table 6
Specific costs for a 70 kWh battery system
Cost Value
Initial investment cost ($) 3.500
Replacement cost ($) 3.500
Annual maintenance and operation cost ($/year) 20
Due to the fact that the battery system is modeled as a dispatchable
energy source, HOMER calculates both fixed marginal costs, in order to make the
necessary comparisons with the other dispatchable systems and to determine the
optimal solution. Unlike cogeneration systems, the battery system is available
immediately for electricity production and therefore it is considered that the fixed
cost of energy is zero. The marginal cost consists of the deterioration cost of the
battery system (cost / kWh of energy required to charge the battery system) and
the average cost of energy stored in the battery.
The deterioration cost of the battery system, is determined using equation
[6]:
𝑐𝑏𝑤 =𝐶𝑟𝑒𝑝,𝑏𝑎𝑡𝑡
𝑁𝑏𝑎𝑡𝑡𝑄𝑙𝑖𝑓𝑒𝑡𝑖𝑚𝑒√𝜂𝑟𝑡 (5)
where:
𝐶𝑟𝑒𝑝,𝑏𝑎𝑡𝑡 – replacement cost of the battery system, in $
𝑁𝑏𝑎𝑡𝑡 – number of batteries enclosed in the system
𝑄𝑙𝑖𝑓𝑒𝑡𝑖𝑚𝑒 – battery lifetime, in kWh
𝜂𝑟𝑡– efficiency of the battery system
The characteristics of the battery system obtained in the optimal solution,
are presented in Fig. 14.
Evaluation of an industrial microgrid using HOMER software 207
Fig. 14. Battery system characteristics obtained in the optimal solution
4. Simulation economic results
In the following paragraphs we present the economic results for the
optimal microgrid architecture obtained using HOMER. The optimal solution is
characterized by a minimum lifecycle cost and includes the following
components: a photovoltaic system, two wind generators, two cogeneration units
and a battery system equipped with a reversible AC/DC converter. The life cycle
cost elements of the microgrid are graphically summarized in Table 7. Table 7
Life cycle cost elements
System/Equipment
Investment
Cost
[MM $]
Replacement
Cost
[MM $]
O&M
Cost
[MM $]
Fuel
Cost
[MM $]
Residual
Value
[MM $]
Total
[MM $]
Photovoltaic System PV01
45 0 2.1 0 0 47.1
Wind Turbine GE01
3 1 0.5 0 -0.6 3.9
Wind Turbine
GE02 3 1 0.5 0 -0.6 3.9
Cogeneration Unit
CG01 0.06 0 61 2.5 -0.01 63.55
Cogeneration Unit
CG02 0.06 0.01 61 2.5 -0.01 63.55
Distribution Network 0 0 6 0 0 6
Battery System 0.03 0.01 0.01 0 0 0.05
AC/DC Converter 0.01 0.01 0 0 0 0.02
Contingency 0 0 5 0 0 5
Microgrid 52.24 2.03 136.11 5 1.22 193.07
208 Andrei Horhoianu, Mircea Eremia
The life cycle cost of the equipment / system represents the present value
of all costs of installing and operating it for the entire life of the project
(considered 25) minus the present value of all revenue generated by the equipment
/ system throughout the life of the project. HOMER calculates the life cycle cost
of each microgrid component and also for the whole microgrid. The discount rate
used is 6%. To determine the life cycle cost, HOMER generates a cash flow
chart (Fig. 57) in which all the cash flows are costs and appear as negative
numbers, excluding the residual value, which appears at the end of the project.
Fig. 15. Microgrid cash flow
The residual value of the equipment / energy system is defined as the
remaining value of the equipment at the end of the project. HOMER considers a
linear depreciation of equipment, which means that residual value is directly
proportional to the remaining life. It is also assumed that the residual value
depends on the replacement cost and not on the cost of the initial investment.
HOMER calculates the residual value using the following equations [6]:
𝑆 = 𝐶𝑟𝑒𝑝 ∙𝑅𝑟𝑒𝑚
𝑅𝑐𝑜𝑚𝑝 (6)
where, 𝑅𝑟𝑒𝑚 = 𝑅𝑐𝑜𝑚𝑝 − (𝑅𝑝𝑟𝑜𝑗 − 𝑅𝑟𝑒𝑝) (7)
and, 𝑅𝑟𝑒𝑝 = 𝑅𝑐𝑜𝑚𝑝 ∙ 𝐼𝑁𝑇(𝑅𝑝𝑟𝑜𝑗
𝑅𝑐𝑜𝑚𝑝
) (8)
The terms of the above equations, have the following meaning:
Evaluation of an industrial microgrid using HOMER software 209
S – residual value [$]
𝐶𝑟𝑒𝑝 – replacement cost [$]
𝑅𝑐𝑜𝑚𝑝 – equipment lifetime [years]
𝑅𝑝𝑟𝑜𝑗 – project life [years]
𝐼𝑁𝑇() – integer function
5. Pollutant emissions evaluation
The main systems enclosed within the microgrid that generate emissions
are the two cogeneration units (CG01 and CG02). The quantities and types of
emissions determined by HOMER for these systems, are presented in Table 8.
Table 8
Microgrid pollutant emissions
Pollutant Quantity
[kg/year]
Carbon dioxide 3559660
Carbon monoxide 4692
Unburned hydrocarbons 520
Particulate matter 354
Sulf dioxide 11009
Nitrogen oxides 45382
HOMER considers by default, a penalty cost of $10 / tonne for each type
of pollutant specified in Table 8. This cost penalty is reflected in the composition
of the costs of operation and maintenance (O & M) specified in Table 7.
6. Conclusion
HOMER is a software application that simulates all possible microgrid
configurations for which the user wants to analyze the technical and economic
aspects. Simulated systems can be sorted and filtered into the optimization phase
depending on criteria set by the user in order to determine the optimal solution.
Although fundamentally HOMER is an economic optimization software, it can be
used to minimize fuel consumption or sensitivities analysis such as wind speed,
sunlight, fuel cost, etc.
Implementation of a microgrid at an oil field is a difficult process due to
the number of design options and the uncertainty of key parameters, such as
thermal or electrical load profiles and fuel prices. Moreover, renewables by their
intermittent nature and nondispatchable seasonal production, add additional
complexity.
The particularity of the processes undertaken at an oil field impose the
entrainment of dispatchable power sources to ensure the flexibility required to
210 Andrei Horhoianu, Mircea Eremia
satisfy the electricity and heat demand. However, the dispatchable power sources
are generally based on fossil fuel and have a negative impact on the microgrid life
cycle cost. In addition, penalties related to air pollution significantly increase the
opreating and maintenance costs.
R E F E R E N C E S
[1] J. F. Manwell and J. G. McGowan, “A combined probabilistic/time series model for wind diesel
systems simulation”, Solar Energy, Vol. 53, pp. 481–490, 2014
[2] RETScreen International http://www.retscreen.net [3] V. A. Graham and K. G. T. Hollands, “A method to generate synthetic hourly solar radiation
globally”, Solar Energy, Vol. 44, No. 6, pp. 333–341, 2012
[4] J. A. Duffie and W. A. Beckman, “Solar Engineering of Thermal Processes” 2nd ed., Wiley,
New York, 2013
[5] J. F. Manwell and J. G. McGowan, “Lead acid battery storage model for hybrid energy
systems”, Solar Energy, Vol. 50, pp. 399–405, 2012.
[6] “Homer Energy”, Homer Help Manual, 2015
[7] M. A. M. Ramli, A. Hiendro, S. Twaha, “Economic analysis of PV/diesel hybrid system with
flywheel energy storage”, Renew. Energy, vol. 78, pp. 398-405, 2015.
[8] B. Tudu, K. K. Mandal, N. Chakraborty, “Optimal design and performance evaluation of a grid
independent hybrid micro hydro-solar-wind-fuel cell energy system using meta-heuristic techniques”, 2014 1st International Conference on Non-Conventional Energy (ICONCE
2014), Jan. 2014.
[9] M. J. Khan, M. T. Iqbal, "Pre-feasibility study of stand-alone hybrid energy systems for
applications in Newfoundland", Renewable Energy, vol. 30, no. 6, pp. 835-854, May 2015.