executive summary bhaiyathan sarguja/executive summar… · pollution control research institute,...
TRANSCRIPT
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar i
EXECUTIVE SUMMARY
Energy is a critical success factor in the economic development process of any
country. It is well known that our commitment for the cause of development requires
assured supply of affordable and reliable energy. The demand for energy has grown
rapidly with the development of society. In spite of the increase in electricity
generation a wide gap still persists in the supply and demand.
Chhattisgarh State Electricity Board (CSEB) is responsible for meeting the entire
power demand of the consumers within the State of Chhattisgarh. Presently, CSEB
has a total installed generation capacity of 1423.85 MW of which 137.85 MW is
hydel and 6 MW from cogen based on cane bagasse and rice husk. In addition to the
installed capacity of 1423.85 MW, Chhattisgarh has Central Sector Share (from
Korba Thermal Power Station, Vindhyachal Thermal Power Station, Kakarapar
Nuclear Power Plant, NTPC's Kawas CCPP & Gandhar CCP) to the State presently
as 306 MW and CPP power availability as 300 MW.
The installed capacity in the state of Chhattisgarh is insufficient to meet the demand
for power. At present (2006-07), the Power Availability in the State is 1660 MW only
against Power Demand of 2300 MW. It is estimated that the peak power demand
would rise to 3700 MW by 2011 – 12. Based on the data, peaking power availability in
Chhattisgarh State will be surplus from 2010 - 11 on the projected demand, only with
the help of existing and proposed power projects of State and Central Sector.
However, with the rapidly increasing industrial development, the per capita energy
consumption level is an aspect of importance in the standards of living in both Urban
and rural areas, agricultural growth etc. which will increase the power demand to a
greater extent.
In view of the above projections, it is clear that the State of Chhattisgarh would face
shortage of power in the years to come, if power projects are not implemented. Hence,
an addition in generating capacity is mandatory to reduce power shortage. It can be
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar ii
achieved through setting up new power plant and augmentation of generating capacity
of existing power plants. The proposed project of 3 x 500 MW Coal based Thermal
Power Project at Bhaiyathan will help in bridging the gap between supply and demand
of power in the State of Chhattisgarh & Western region.
In order to assess the environmental implications due to the setting up of the proposed
thermal power plant, Chhattisgarh State Electricity Board retained Pollution
Control Research Institute, BHEL, Haridwar as consultants to carry out Rapid
Environmental Impact Assessment (EIA) for proposed thermal power plant at
Bhaiyathan, District Surguja (Chhattisgarh). The study has been carried out based on
the Base line data collection covering one season of three months duration during
September - December, 2005.
Site Selection
In order to establish a power generating station close to the coal source, Chhattisgarh
State Electricity Board has explored the feasibility at Bhaiyathan, Baikunthpur,
Premnagar, Korba Risdi, Korba - FCI Complex locations. The relative merits of each
site have also been considered regarding environmental issues. It was concluded that
site near Bhaiyathan in District Surguja is favourable in view of :
• Adequate un-inhabited land availability
• No reserve forest/protected forest in the plant area
• General soil characteristics are suitable
• The length of approach road to be constructed is minimum
• Availability of water from Rehar river and Gobri Nalla
• Proximity to coal mines/coal resource of SECL
• Proximity to rail link of South Eastern Central Railway
Site and its Salient Features
The proposed power project would be located in Bhaiyathan block of Surajpur Tehsil,
District Surguja. The proposed power plant site is located at latitude of 23°19' N,
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar iii
longitude of 83°53' E at an altitude of 525 m above MSL. The distance of proposed
project by road from Surajpur is about 10 km and from that of Ambikapur is 52 km.
National Highway No.78 is at a distance of about 10 km. The district road i.e. Surajpur
- Bhaiyathan Road which connects the site to highway is close to the site.
The proposed site for main plant is located near to villages Mohanpur (Masira) &
Lodhima and ash disposal area will be between Ragda, Sirsi and Chopan villages
about 3 km from main power plant site. Water intake system will be installed near the
proposed anicut/dam on Rehar River at around 5 kms downstream from plant site. For
staff colony, land has been identified at Newra village 4 km from main plant site near
to Surajpur Road Railway Station. It may be seen from toposheet that most of the
nearby area is inhabitant, very few villages are in the region and there is no forest area
in the near vicinity.
Climatic Conditions
The climate of district is characterized by hot summer and well distributed rainfall
during the monsoon season. The location near to tropic of cancer results in tropical
climate with high pressure belt throughout the year, but due to its height above MSL
controls its high temperature. The climatic condition of Surguja district is
characterized by hot dry summer and a cold winter. The average rainfall in the district
is around 1474 mm. The nearest Indian Meteorological Department (IMD)
Observatory from the proposed power project site at Bhaiyathan is at Ambikapur.
Minerals
The proposed project site is towards West to district headquarter Ambikapur. Coal
deposits of South Eastern Coalfields Ltd. are present near Bishrampur area. The
mineral exploration studies carried out by South Eastern Coalfields Ltd., CMPDIL and
available geological information indicate that proposed project sites are situated over
non-coal bearing area.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar iv
Sanctuary, National Park, Wild Life & Forests
The area within 10 Kms of proposed power project site covers no National Park and
Wild life Sanctuaries. However, hills towards North of the site is protected forest area
with no mining, residential or industrial activities permitted. There is no endangered
species of animals existing within a radius of 10 kms of proposed project site.
The proposed project site does not fall under forest area. No major forest area is at
proposed project site, however small patches of revenue forests are present on the
proposed site. The forest area is around 8 - 10 kms towards North to the proposed
project site.
Socio - Economics of the Area
Around 84% of the total workers are engaged in agriculture activities and only a small
percentage of around 2% is engaged in family enterprise in the development block.
Out of this total work force, only 63.03% are main workers and balance 36.97% are
marginal workers which are employed for agriculture work as per requirements. Also,
majority of population, 56.41% in the region is non-worker, which indicates under-
developed conditions of the region. The proposed project will help in development of
the region through better job opportunities in services and infrastructure improvement.
Thus the comparatively thin population at and around the proposed site may be an
advantage from Resettlement & Rehabilitation point of view.
Major Industries
Surguja is an industrially undeveloped district of the State. There are no major
industries in the region. There is no medium and large scale industry within 25 kms of
the proposed project site. However, coal mining activities are reported in the region.
Coal mining projects of South Eastern Coal Fields Limited (SECL) at Bhatgaon,
Bishrampur and Rehar - Gayatri region are present in the region. All these mining
blocks of SECL are not within 10 kms of the proposed project site, however these
blocks fall within 25 kms region. Bhatgaon is towards North - East, Bishrampur
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar v
towards South - East and Rehar - Gayatri towards South - South East from the
proposed project site.
Selection of Technology & Unit Size
The plant is proposed to be established on the basis of unitized system. Super Thermal
Power station of 1500 MW capacity is proposed to be built up by 3 units of 500 MW
due to following reasons :
a. Economy of scale to achieve least per MW installed cost.
b. Better efficiency of large sized boiler, steam turbine and lower overall heat rate.
c. Lower land requirement/MW
d. Lower Operation & Maintenance cost and staff requirement
e. Higher net saleable power due to higher efficiency and lower auxiliary power
consumption due to use of steam turbine driven boiler feed pumps.
As the unit capacities of 500 MW are under consideration for the project, the
technology proposed to be used is pulverized fuel fired boilers.
Environmental Aspects
The various measures proposed to be adopted to minimize the pollution from the
proposed Power Project are as follows :
Air Pollution Control System
High efficiency (99.89 %) Electrostatic precipitators (ESP) would be installed to
control the emission of ash particles. The ESP would be designed to limit the
particulate emission to 100 mg/Nm3. Also, State of Art system like Ammonia
injection, is planned to be envisaged to maintain desired particulate emissions from the
stack. To facilitate wider dispersion of pollutants and in accordance with the
regulatory requirement, chimneys of 275 m height above plant grade level are
envisaged for this project.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar vi
Space will be provided for retrofitting the Flue Gas De-sulphurisation (FGD) system.
The design and layout of steam generator and its auxiliaries would be such that a
wet/dry FGD system can be installed in future, if required.
Water Pollution Control System
An effluent management scheme would be implemented with the objective of
optimization of various water systems so as to reduce intake water requirement, which
would result in lesser waste water discharge. The effluent management scheme would
essentially involve collection, treatment and recirculation/disposal of various effluents.
Adequate treatment facilities would be provided to all the waste streams emanating
from the power plant to control water pollution. This would include physico-chemical
treatment for plant effluent and biological treatment for sanitary effluents.
Efficient operation of treatment plants would be ensured so that the quality of effluents
conforms to the relevant standards prescribed by the Regulatory Agencies. All the
treated effluents would be discharged through a single point outlet from Central
Monitoring Basin (CMB) for Green Belt Development.
Ash Pond Effluent
A dry extraction and wet disposal system has been envisaged for fly ash disposal. The
bottom ash, however, will be collected and disposed in wet form. An ash water re-
circulation system for ash pond effluent has been envisaged. The ash slurry discharged
into the lagoons will be allowed to stagnate where most of the ash particles will settle
and almost clear water will be collected at the top. This water will be re-circulated to
the plant area for re-use after further clarification/sedimentation. Thus, there will be no
discharge of ash pond effluent.
Noise Pollution
The major noise generating sources are turbines, generators, compressors, pumps,
fans, coal handling plant etc. Acoustic enclosures shall be provided to control the
noise level below 90 dB(A). Personal protective equipments shall be provided to the
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar vii
persons working in high noise area. Noise level of 75 dB(A) will not be exceeded at
the plant boundary.
Afforestation and Green Belt Development
An area of around 33 % of all components of total plant has been earmarked for Green
Belt Development which also includes a green belt of 100 m width all around the
project. Extensive afforestation within the plant and township areas would be
undertaken. All available spaces in the plant and township will be afforestated through
appropriate species. The species selected will be a mixture of endemic pollution
resistant and pollution indicators.
Ash Utilisation
CSEB shall consider utilization of ash produced by its coal based power stations as a
thrust area of its activities. At the project site, various avenues for utilization of ash in
various application areas such as issue to cement and asbestos industries, brick
manufacturing, low lying area filling, wasteland development, road embankment
construction etc. shall also be explored.
Land Requirement
Total 635.55 hectares of land would be required for the proposed project. Out of
which, 275.02 hectares of land for the Main Plant area including Green Belt &
Switchyard, 180.77 hectares of land for ash disposal area, 127.60 hectare of land for
township, 31.16 hectare of land for water intake pump house, water & ash pipe line
corridors etc. and 21.00 hectare for railway corridor is identified by Chhattisgarh State
Electricity Board (CSEB). For staff colony, land has been identified at Newra villages
4 km from main plant site near to Surajpur Road Railway Station. Ash disposal area
will be developed at Ragda, Sirsi and Chopan villages about 3 km from power plant.
Collector, Surguja vide letter No.93 dated 29.04.2005 confirmed that land will be
made available for Bhaiyathan Thermal Power Project as per Govt. rules and Land
Acquisition Act.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar viii
It is proposed to construct a Permanent Township comprising 1196 dwelling units, with
all necessary infrastructural facilities in the proposed township, to cater to the
requirements of operation & maintenance personnel and other supporting staff of the
project. The infrastructure support facilities in the township would include different
types of accommodation alongwith armoury for Security staff, 25 bedded General
Hospital with support facilities, Estate office, Union/Association offices, Nursery,
Senior Secondary School, Shopping centre, Bank, Post office, Telephone exchange,
Petrol pump, Parks, Welfare Association Club, Bal bhawan, Ladies Club, Community
centre, Swimming pool, Sports complex with play fields, Auditorium, Guest house,
Field hostel facilities and space for religious places etc.
Rehabilitation of Displaced Population
The area identified for Main plant, Township complex is mainly agricultural land with
Single crop pattern in the area, while proposed ash disposal area is mainly barren land.
The land is fairly undulated terrain with rocky soil. Minimum revenue forest/PF land
(1.76%) falls within the proposed project sites.
The land proposed to be acquired for project presently belongs to around 949 farmers.
The lands for the proposed project sites involve minimum displacement of persons.
Appropriate rehabilitation and resettlement plan will be implemented for the project
affected persons in consultation with State Govt. and as per “State Model
Rehabilitation Policy – 2005 and as amended in 2007 ” of Chhattisgarh Govt. so that
this issue can be taken care appropriately.
Impact during Construction Phase
The construction of a new power plant usually involves significant changes in
land use, which may be accompanied by direct social and ecological impacts.
The proposed 3 x 500 MW Coal based Thermal Power Project at Bhaiyathan is to be
located at about 10 Km North of Surajpur town. The project site is approachable
through National Highway (NH - 78) connecting Ambikapur and Baikunthpur via
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar ix
Surajpur and all the infrastructure are already available there. Surajpur - Bhaiyathan
road exists close to proposed project site. The existing road will be utilised for
movement of construction material, construction machineries and transportation of
power plant equipment. There is no requirement of additional land for development of
infrastructural facilities since the site is connected by roads and Highway (NH 78) lies
just about 10 kms. away. The site is also closely located to Surajpur Road Railway
Station (South Eastern Central Railway) at about 4 kms from the proposed project site.
All these existing infrastructure will significantly reduce the impacts during
construction phase of these units for the proposed plant.
The environmental impact during construction will be localized and short term with no
changes in use of the surrounding land as compared to the current conditions. Impacts
will primarily relate to the civil works period and less intensive impact is expected
during erection of the equipment and trial operation. The time schedule for the main
civil works (foundations for steam generators and turbine units, transformers and
condensers) is about 36 months.
The construction phase of the project will have some impacts on the environment.
These impacts will be minimised/neutralized with the help of State of Art construction
equipments and appropriate environmental management practices.
Air Quality
Ambient air monitoring was carried out to assess the air quality in the vicinity of the
proposed power project. Ambient air monitoring sites at 10 locations were selected
covering all four directions with respect to proposed project site and also existence of
sensitive locations like hospitals, schools etc. within a radius of 10 km. from the
proposed coal based power plant site. It was ensured that the monitoring sites are free
from any obstructions, availability of power and easy accessibility to the
village/locations while selecting the monitoring sites.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar x
These stations were selected so as to provide representative ambient air quality data on
Background Air Pollution Level in the vicinity of the proposed power plant site. Due
consideration was given to the meteorological parameters and local conditions (e.g.
local sources of pollution) while selecting these sites.
Various statistical parameters like 98 percentile, average, maximum and minimum
values have been computed from the observed raw data for all the Ambient Air
Quality Monitoring Stations. The obtained values are compared with the standard
prescribed by Central Pollution Control Board (CPCB) for rural and residential Zone.
The interpretation of these data is as follows :
Suspended Particulate Matter
24 hourly average arithmetic mean concentration of SPM at various locations around
the proposed power plant site varied from 102 to 134 µg/m3. The lowest and the
highest mean values were found at Kaskela and Basdei village respectively.
98th percentile concentration values of SPM varied from 130 µg/m3 (at Kaskela) to
160 µg/m3 (at Ragda Village) which is below the standard value for Residential areas.
Higher value at Ragda was found due to reverine loose soil near the village on the
bank of Gobri Nalla (river).
Respirable Suspended Particulate Matter (RSPM)
24 hourly average arithmetic mean concentrations of RSPM at various locations varied
between 40 to 54 µg/m3. The lowest and the highest mean values were observed at
Kaskela and Basdei respectively. 98th percentile concentration values of RSPM varied
from 50 µg/m3 (at Kaskela) to 69 µg/m3 at Bhaiyathan.
Sulphur Dioxide
24 hourly average arithmetic mean concentrations of SO2 at various locations varied
between 4 to 6 µg/m3. The highest mean value was observed at Bhaiyathan and
lowest mean value which is 6 µg/m3 was observed at various locations such as
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xi
Uchhdih, Ragda, Ramnagar, Karonji, Khopa and Kaskela villages. 98th percentile
concentration values of SO2 varied from 7 µg/m3 (at Bhaiyathan and Karkoli) to 11
µg/m3 (at Khopa) which are well within the corresponding NAAQS allowable limit of
80 µg/m3 for residential area.
Oxides of Nitrogen
The 24 hourly average arithmetic mean of NOx concentrations at the monitored
locations varied from 6 to 9 µg/m3. The highest mean values were found at Ramnagar,
Karonji, Khopa villages whereas lowest mean value was observed at Doomaria
village. 98th percentile concentrations for NOx varied from 11 µg/m3 to 18 µg/m3. The
maximum 98 percentile value i.e. 18 µg/m3 was observed at various places such as
Ramnagar, Karonji and Khopa villages. The values observed in all the monitoring
locations are well within the corresponding NAAQS allowable limit of 80 µg/m3 for
residential area.
Air Quality Impact Assessment by means of Computer Modeling (ISCST3 Model)
The impact due to operation of proposed power plant on ambient air quality in the
surrounding region has been predicted through mathematical modeling. The change in
the incremental concentrations in SPM, SO2 and NOx were computed through
computer dispersion model.
The monitoring station equipped with monitoring equipment to record hourly wind
speed, direction, relative humidity and temperature was set up at the project site. The
data logger attached with the station recorded the observations and the data was down
loaded from it from time to time. The maximum temperature during the post monsoon
study period was recorded as 32.5 oC and the minimum 5.6 oC.
24-hour, second highest concentration has been computed from the meteorological
data recorded through PCRI Meteorological Station installed at Bishrampur for the
period 26.09.2005 to 25.12.2005 using the EPA-ISCST3 model.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xii
Model Output
The output of model provides ground level concentration of pollutants due to the
proposed 3 x 500 MW coal fired power plant. Impact on ambient air quality due to the
proposed thermal power project has been assessed by superimposing predicted
concentrations on background air pollution level. Baseline ambient air quality data
indicated that maximum 98th percentile concentration of SPM, SO2 and NOx was
observed 160, 11 and 18 µg/m3 respectively and these concentrations have been
considered as background level of pollutants. The maximum incremental
concentrations of SPM, SO2 and NOx are expected to be 1.3 µg/m3, 27.8 µg/m3 and
20.9 µg/m3, respectively due to thermal power project operation. These concentrations
are expected to occur at a distance of 4.2 Km South west with respect to source.
Maximum total concentrations of SPM, SO2 and NOx, after superimposition of
background level would be 161.3 µg/m3, 38.8 µg/m and 38.9 µg/m3, respectively.
The total concentrations are compared with National Ambient Air Quality Standards
prescribed for residential areas as specified under National Ambient Air Quality
Standards as notified by Central Pollution Control Board. It is concluded that total
concentrations of pollutants would be below the allowable limits for residential areas.
Water Availability
Water resources department of Chhattisgarh has confirmed the allocation of 50 million
cum of water for the proposed project. WRD committed total 60 million cum per year
water in the meeting dated 02.08.2007Though during 09 months of year from July to
March, monthly requirement will be met by the natural flow available in the Rehar
river, but for the months of April to June, the shortfall in the inflow will be
supplemented by construction of two storage weir/barrage on the tributaries of Gobri
river and one weir at the junction of Gobri river and Rehar river.
The cooling towers have been envisaged for the proposed power project. Make up
water requirement for this project would be 5380 m3/hr with ash water re-circulation
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xiii
system. Total water requirement for the proposed power plant (5380 m3/hr) would be
drawn from river Rehar storages. Make up water for cooling towers would be 3455
m3/hr. Part of the clarified water after passing through pressure filter will be sent to
De-Mineralisation (DM) plant.
Water Quality
During the operation of the thermal power plant, waste water would also be generated
from various sources viz. cooling tower blow down, blow down from raw water
treatment plant, waste from DM plant during regeneration of columns and ash pond
overflow etc. Therefore, it is necessary to assess the water availability, existing quality
of the water body around the proposed plant, quality of the raw water and the
assessment due to the impact of the power plant on the near-by water bodies.
Water Quality Assessment Methodology
For the purpose of Water Quality Assessment, sampling points were selected for
Surface water and Ground water within the area of study. The proposed power project
site is presently single crop agricultural land. Ground water is the major source of
water for use in the nearby villages of the proposed power plant. The sampling points
were selected in these villages in order to assess the existing quality of the ground
water. There are only two surface water sources, i.e., Gobri Nalla and Rehar River
near the proposed site and quality of water at these sources was also assessed as the
surface water in the nearby area.
It may seen from analysis results that some of the parameters fall in Class “B” and
some in Class “C” as per Best Designated uses as specified by Central Pollution
Control Board. Therefore, the overall surface water quality may be put in class “C”
water. A part of the water of these surface water sources are presently being used for
agricultural purposes. The water quality of both these sources is suitable for
agricultural activities. The water quality is also suitable for power plant operations
after treatment. As no water is planned to be discharged into Gobri Nala and Rehar
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xiv
River from the proposed power project site, no impact is envisaged on the surface
water quality due to proposed power project.
Assessment of Ground Water Quality
The ground water in the district is mainly developed by dug wells for domestic and
irrigation purposes. The dug cum bore wells are also used for irrigation. The borewells
fitted with hand pumps are used for the rural drinking water supply requirements of
the village community. The average ground water depth in the district during pre-
monsoon (May-June) varies from 6.17 m to 7.32 m, while during post monsoon these
levels vary from 2.75 m to 4.01 m.
Ground water is also the major source of drinking water in the region. The ground
water samples were collected from various existing sources around the proposed
power project site.
On comparing the water quality analysis results with IS:10500, it is observed that the
values of Alkalinity, Aluminium, Copper, Fluoride, Manganese, Iron, Total Dissolved
Solids and Zinc are higher than desirable limits but within the permissible limits in
some of the villages. But all the parameters are well below the permissible limit values
as per Indian Standard. All other parameters are within the desirable limits. Therefore
it could be concluded that Ground Water is safe for drinking and other purposes.
The surface water and ground water sample analysis shows that there is not much
source of pollution in the region and base line data for surface water and ground water
is well within the limits prescribed in “Primary Water Quality Criteria” laid down by
CPCB and IS:10500 (Specifications for Drinking Water) respectively.
Water Management System
Water is one of the important requirements for power generation. The main
requirement of water in coal based power plant is for cooling and ash disposal. The
proposed project will adopt circulating type Cooling Water system with cooling
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xv
towers. The cooling water requirement will be only for make up water for evaporation
losses and blow down quantity.
The proposed units will have dry evacuation and wet ash disposal system. The bottom
ash will be disposed in wet form but the ash water recovery system will substantially
reduce the quantity of water required for ash disposal. Since the quantity of water
taken from Rehar and Gobri River is low as compared to water availability, it will not
have any adverse impact on water availability to down stream users. As ash water
recirculation system is planned to be provided at thermal power project, there will be
no effect due to power plant on quality of surface water.
Keeping into consideration the amount of water required and effluent discharged after
treatment, it can be concluded that proposed project will neither affect the availability
of water nor the surface/ground water quality in the region. However, detailed
ground/surface water monitoring schedule would be developed for monitoring of
water quality around the proposed power project site.
Soil Quality
For studying soil profile of the region, sampling locations were selected to assess the
existing soil conditions in and around the proposed project area representing various
land use conditions. The physical, chemical parameters and heavy metal
concentrations in soil samples were determined.
Soil samples were collected from different places based on survey conducted around
the site. At each location, soil samples were collected from three different depths viz.
50 cm, 100 cm and 150 cm below the surface. The samples were then packed in
polythene plastic bags and sealed. The samples from three different depths were
homogenized. Large stones, gravels and plant roots were removed from the soil. The
soil was then crushed and passed through 100 mesh sieve. Sieved soil was used for
analysis. The present study on the soil profile establishes the baseline characteristics
around the proposed project site.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xvi
Single crop agriculture is the main activity in the surrounding area of proposed power
project. The soil samples were collected from various villages around the proposed
power project site. As the proposed project is not likely to generate any material which
will affect the soil quality, therefore no adverse impact is envisaged due to proposed
power plant site.
Coal & Ash
The daily raw coal requirement for 3 x 500 MW units shall be about 24,165 tonnes
based on average Gross Calorific Value of 3650 Kcal/kg, 100% plant load factor and
2450 Kcal/Kwh unit heat rate. The coal requirement for Bhaiyathan Thermal Power
Project shall be met from captive coal mine blocks at Paturia and Gidhmuri already
allotted to Chhattisgarh State Electricity Board (CSEB) by Ministry of Coal. These
mining blocks are about 90 kms from the proposed project site. Mining plan for these
coal blocks have been approved by Ministry of Coal.
The bottom ash shall be extracted and disposed off in wet form. The fly ash shall be
extracted in dry form from the electrostatic precipitator hoppers. This dry ash can
either be taken to buffer hoppers for its onward transportation in dry form or can be
slurrified in wetting units for its disposal in wet form to ash disposal area.
Ash Water System
Initially water for ash handling system shall be available from plant make up water
system. Thereafter, it is proposed to re-circulate the ash water from the ash dyke area
to the plant area for its reuse in the ash handling system. For this purpose required
number of ash water pumps shall be provided which shall take suction from the
retention basin associated with the ash water re-circulation system. The effluent
generated during operational phase will be treated to meet the permissible norms and
will be utilized for green belt development.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xvii
Fly Ash Management
The fly ash and bottom ash from the plant is proposed to be collected and used for
various applications. CSEB will explore various other avenues for utilisation of ash in
value added products such as cement, fly ash bricks etc.
In order to provide quality dry fly ash to users such as, manufacturers of cement,
concrete and its allied products like Cellular Concrete etc., the plant shall provide
systems and facilities for 100% extraction of dry fly ash.
Noise
The noise monitoring stations were selected for measurement of Ambient Noise
Levels to establish the base line status of noise level in and around the proposed power
plant site. It has been observed that in all the locations, the noise level during day time
and night time is well within limit specified for Residential areas during post monsoon
season.
However, appropriate measures would be taken at the design stage itself to attenuate
noise level to the acceptable limit during operation stage of the power plant. Moreover,
provision would be made within the power plant to insulate areas such as the control
rooms from the turbine hall noise. The control rooms and adjacent offices would have
double glazed windows facing to the turbine hall with wide spacing for better sound
attenuation. Besides, ear muffs/plugs will be provided to the workers in the close
vicinity of noise sources. Also effort will be made to use special construction
equipment having low noise generation during construction stage. The generated noise
would be controlled to reduce it to an acceptable level at the project site boundary by
means of isolation and as a further mitigation measure planting of trees along the plant
boundary as well as within the plant premises would be done to form a sound barrier.
These measures would be adequate to limit the incremental change in background
noise level to a minimal. It is expected that the setting up of coal based thermal power
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xviii
project at Bhaiyathan would not have any major adverse impact on community noise
level.
Impact Assessment
Thermal power plants invariably have potential environmental effects during both the
construction and operational phases including effects on air, water, noise & land
environments as well as socioeconomic conditions during construction phase. The
significance of construction impacts will be limited, however the mitigation measures
will be taken for traffic management, appropriate timing and routing of materials,
delivery etc.
The probable environmental impacts during construction as well operational phase of
the proposed 3 x 500 MW coal based thermal power project have been identified. The
impacts during the construction/development phase may be regarded as temporary or
short term; while during the operation phase the impact has to be taken as long-term
effects. The overall impacts during construction and operation phase of proposed coal
based power plant have been assessed and are as given below :
Air Quality
Ambient air quality studies within 10 kms. radius of proposed power plant at
Bhaiyathan indicate that the 98 percentile concentration of Suspended Particulates
(SPM), Sulphur Di-oxides (SO2) and Oxides of Nitrogen (NOx) are well within
permissible limits of National Ambient Air Quality Standards for Residential & Mix
Use areas as prescribed by Central Pollution Control Board.
The emission from the proposed power project will mainly consist of Suspended
Particulate Matters (SPM) and SO2. In order to control SPM from the power plant,
High efficiency Electrostatic precipitators (ESP) would be installed. The ESP would
be designed to limit the particulate emission to 100 mg/Nm3. To facilitate wider
dispersion of pollutants and in accordance with the regulatory requirement, chimneys
of 275 m height above plant grade level are envisaged for this project. Emissions
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xix
through these tall stacks will help in effective dispersion of gaseous pollutants in the
atmosphere and thereby minimising effect on ground level concentration of pollutants.
The chimneys shall be provided with sampling points for continuous online
monitoring system for stack emissions.
Space will be provided for retrofitting the Flue Gas De-sulphurisation (FGD) system.
The design and layout of steam generator and its auxiliaries would be such that a
wet/dry FGD system can be installed in future, if required.
Fugitive dust emission at coal handling, other vulnerable areas of the plant will be
controlled by regular sprinkling of water and Green Belt development.
Current baseline air quality study indicated that background concentrations of
Suspended Particulate Matters (SPM), SO2 and NOx are within limits for residential
areas. The air dispersion prediction model shows that during normal operation with
two stacks (one twin flue and one single flue) of 275 meter height, maximum ground
level concentration of SPM, SO2 and NOx will not exceed the permissible norms of
National Ambient Air Quality for residential & mix use areas.
ISCST-3 model indicates that the maximum ground level concentration after
commissioning of the plant will be within specified limits at site and incremental
change in concentration in all other parameters will be negligible. The maximum
impact would be at a distance of 4.2 kms from source under normal operation.
There will be marginal impact on ambient air quality in and around the proposed
project site due to construction activities, transportation, handling and storage of
construction materials. However, the impact on air quality will not have long term
effect in the region.
The air quality impact of operation of proposed power project would be within
allowable limits for Residential and Rural areas. Thus, there will not be significant
impact on air quality due to emission of Suspended Particulate Matters, Suplhur Di-
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xx
oxides and Oxides of Nitrogen due to operation of coal based thermal power project at
Bhaiyathan.
Water Pollution
Water is one of the important requirements for power generation. Total water
requirement for the proposed power plant (5380 m3/hr) would be drawn from river
Rehar and stored in a water reservoir.
The surface water through reservoir will be sent to water treatment plant. The clarified
water from the clarifier will then be sent to cooling towers as make up water. The main
requirement of water in Power Plant would be make-up water for cooling tower. Make
up water for cooling towers would be 3455 m3/hr. Part of the clarified water after
passing through pressure filter will be sent to De-Mineralisation (DM) plant.
During the operation of the thermal power plant, waste water would also be generated
from various sources viz. cooling tower blow down, blow down from raw water
treatment plant, waste from DM plant during regeneration of columns and ash pond
overflow etc.
It is proposed to provide ash water re-circulation system to meet the requirements of
environmental authority. Decanted water from ash pond shall be led to the plant area
through pumps. This water will be used further in the ash handling system. Normal
make up to the ash water system shall be from CW blow down water. Provision to
supply treated plant effluent from central monitoring basin to ash handling shall also
be kept.
The effluent management scheme would essentially involve collection, treatment and
recirculation/disposal of various effluents. Adequate treatment facilities would be
provided to all the waste streams emanating from the power plant to control water
pollution. This would include physico-chemical treatment for plant effluent and
biological treatment for sanitary effluents.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xxi
Efficient operation of treatment plants would be ensured so that the quality of effluents
conforms to the relevant standards prescribed by the Regulatory Agencies. All the
treated effluents would be discharged through a single point outlet from Central
Monitoring Basin (CMB) and will be used for Green Belt Development in the plant
premises.
The discharged effluent quality will meet the norms laid down by Chhattisgarh State
Pollution Control Board for discharge on land. Hence, there will be no significant
impact due to discharge of waste water on the environment.
Employment
The installation of proposed power project will generate employment opportunities
during construction as well as operation phase and thus will provide direct and indirect
jobs to the local population. The project will not disturb the existing social pattern of
the area and due to the employment opportunities generated; it will have beneficial
economic impact on the area.
Aesthetics
The effective pollution control equipment helps to maintain the visual quality of air
and water environment. Natural vegetation and its diversity will increase due to green
belt development. The aesthetics of the area is expected to improve after installation of
proposed 3 x 500 MW thermal power project.
Socio-Economic Environment
The impacts on socio-economic status of the project area are predominantly positive
and no adverse changes are expected.
The proposed project at Bhaiyathan will generate employment opportunities during
construction as well as operation phase and thus will provide direct and indirect jobs to
the local population. The project will not disturb the existing social pattern of the area
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xxii
and due to the employment opportunities generated in the society where majority of
population has no regular job, it will have beneficial economic impact on the area.
The additional power generated would lead to availability of power to the area and
state. This would result in increased power supply to rural areas. An increase in
sanitation, education and transportation facilities is expected due to proposed project.
The economic output due to proposed project would be positive besides enhancement
of community services.
The proposed project will lead to development of the area. Hence, it will have
beneficial effect on the society.
Ecology
The proposed project site does not fall under forest area. No major forest area is at
proposed project site, however small patches of revenue forests are present on the
proposed site. The forest area is around 8 - 10 kms towards North to the proposed
project site.
The area within 25 Kms of proposed project site covers no National Park, Wild life
Sanctuaries. However, hills towards North of the site are reserved forest area. There
are no endangered species of animals existing within study area.
There may be some negative impacts on terrestrial ecosystem namely crops and
vegetation due to dispersion of fly ash. However, with efficient control systems for
particulate and tall stacks for gases, no significant adverse impacts are foreseen which
can disturb the ecological balance of the area.
There are no major water bodies or aquatic biosystems in the study area. The only
water bodies in the region include Rehar river and Gobri nalla. However, the aquatic
life will not be affected because of low water requirement, no effluent discharge from
proposed thermal power project and closed cycle system for cooling water.
-
Rapid Environmental Impact Assessment Study for proposed 3 x 500 MW Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh)
Pollution Control Research Institute, BHEL Haridwar xxiii
Hence, the proposed plant will not have any significant detrimental impacts on plants,
animals, soil and other ecological targets around the proposed site as a whole.
Education & Health
The infrastructure support facilities would be developed in the proposed township
which would also include 25 bedded General Hospital with support facilities and
Senior Secondary School. Hence there will be positive impact on education & health
services in the area due to the proposed power plant.
Environmental Impact Matrix
The overall environmental impact of the project can be quantitatively assessed through
environmental impact matrix by assigning weightages to various environmental
parameters in the matrix. The weightage values are subjective but have been achieved
after considering inter-disciplinary judgment based on the type of the project.
The assessment indicates that with the adoption of the mitigation measures established
by the Environment Impact assessment process, the overall environmental impacts of
construction and operation of the proposed project, there will be Impact on
environment but not injurious in general. However, mitigation measures are important
during the construction as well as operation stage of Proposed Thermal Power project.
The changes in air, water quality with the introduction of proposed mitigation
measures would allow compliance with appropriate standards and confine negative
effects within acceptable limits. The green belt development plan envisaged in and
around the power plant will improve the surrounding environment.
On the whole it can be concluded that installation of 3 x 500 MW Coal Fired
Thermal Power Project at Bhaiyathan, District Surguja (Chhattisgarh) will be an
environment friendly project.