executive summaryenvironmentclearance.nic.in/writereaddata/online/tor/06...project : construction of...

36
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter : Airports Authority of India Gaurang Environmental Solutions Pvt. Ltd. EIA Coordinator Airports Authority of India Authorized Signatory EXECUTIVE SUMMARY 1.1. Identification of Project: Sardar Vallabhbhai Patel International Airport (SVPIA) (IATA: AMD, ICAO: VAAH) is an international airport serving the cities of Ahmedabad and Gandhinagar in Gujarat, India. It is named after Sardar Vallabhbhai Patel, the 1 st Deputy Prime Minister of India. In fiscal year 2017-18, it handled about 9.2 million passengers making it the eighth-busiest airport in terms of passenger traffic in India. The airport is an operating hub for Air Odisha and Blue Dart Aviation. The airport also serves as a focus city for Air India, GoAir, IndiGo and Jet Airways. As part of the airport modernization process, the AAI proposed to construct a new air traffic control (ATC) tower cum technical block. The same will be done due to operational requirement as approach funnel of runway (23) is not clearly visible from existing ATC Tower The area earmarked for the proposed construction is about 9840.00 m 2 within the existing airport premises. There is no additional requirement of land for the proposed construction works. The construction work will be done in the land abutting the existing airport. Thus, the same requires prior Environmental Clearance under the provisions of EIA Notification, 2006 and subsequent amendments. The same shall be categorized under item 7 (a) of Schedule - Gazette Notification as Category A project. 1.2. Project Brief: The project involves construction of new ATC tower cum technical block. The old ATC building will be dismantled. The total area of the existing SVPI airport is 928.59 acres, while the area earmarked for the proposed construction is 9840 sq. m. The details of the proposed building are summarized as under: Table 1.1: Project summary for new ATC tower cum technical block S No. Description Details 1. Project cost Rs. 166.47 Cr. 2. Location Latitude: 23° 04' 42.44" N Longitude: 72° 37' 12.15" E

Upload: others

Post on 24-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

EXECUTIVE SUMMARY

1.1. Identification of Project:

Sardar Vallabhbhai Patel International Airport (SVPIA) (IATA: AMD, ICAO: VAAH) is an

international airport serving the cities of Ahmedabad and Gandhinagar in Gujarat, India. It

is named after Sardar Vallabhbhai Patel, the 1st Deputy Prime Minister of India.

In fiscal year 2017-18, it handled about 9.2 million passengers making it the eighth-busiest

airport in terms of passenger traffic in India. The airport is an operating hub for Air Odisha

and Blue Dart Aviation. The airport also serves as a focus city for Air India, GoAir, IndiGo

and Jet Airways.

As part of the airport modernization process, the AAI proposed to construct a new air

traffic control (ATC) tower cum technical block. The same will be done due to operational

requirement as approach funnel of runway (23) is not clearly visible from existing ATC

Tower

The area earmarked for the proposed construction is about 9840.00 m2 within the existing

airport premises. There is no additional requirement of land for the proposed construction

works. The construction work will be done in the land abutting the existing airport. Thus,

the same requires prior Environmental Clearance under the provisions of EIA Notification,

2006 and subsequent amendments. The same shall be categorized under item 7 (a) of

Schedule - Gazette Notification as Category A project.

1.2. Project Brief:

The project involves construction of new ATC tower cum technical block. The old ATC

building will be dismantled. The total area of the existing SVPI airport is 928.59 acres,

while the area earmarked for the proposed construction is 9840 sq. m. The details of the

proposed building are summarized as under:

Table 1.1: Project summary for new ATC tower cum technical block

S No. Description Details

1. Project cost Rs. 166.47 Cr.

2. Location Latitude: 23° 04' 42.44" N

Longitude: 72° 37' 12.15" E

Page 2: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

3. ARP coordinates Latitude : 23° 04' 16.28" N

Longitude : 72° 37' 35.15" E

4. Plot area 9840 sq. m.

5. Ground Coverage (achieved) 1512.25 sq. m.

6. Total Built Up Area (including

Headroom & core of Tower)

10520.5 sq. m.

7. Green Area 3338.5 sq. m. (33.92 %)

8. Road and Open Area (excluding surface

parking area)

3466.65 sq. m.

9. Surface parking Area 1522.595 sq. m. (32 Cars & 64 Scooters)

10. No. of Floors 15

11. Height of Tower 72.4 m

12. Population {Staff (ATC cum Technical

Block)

125 Persons (Peak)

13. Water demand 12 KLD (Domestic)

14. Power requirement 1000 KW

Source: 132 kV GSS of Torrent Power

15. Back up source 750 kVA (2 nos.)

16. Solid waste generation 57 kg/day

Table 1.2: Existing Airport Data

S.

no Particulars Details Particulars Details

A. General Information

1. Airport Owner/Operator Airports Authority of India

2. State Gujarat

3. Location Hansol, Ahmedabad. Gujarat

4. Latitude & Longitude of Aerodrome

Reference Point (ARP–WGS 84)

23°04'16.28"N 72°37'35.15"E

5. Suitability Code E Aircraft

6. Aircraft operations

(Scheduled/Non-scheduled)

Destination:

Domestic: Delhi, Kolkata, Mumbai, Chennai, Goa, Pune, Hyderabad, Bangalore, Jaipur, Indore, Bhopal International: Singapore, Abu Dhabi, Muscat, Dubai, Sharjah, Doha, Kuwait, London, Newark

Page 3: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Operators :

Domestic: Air India, Air Vistara, Jet Airways, Spice jet, Go Air, Indigo, Air Costa, Jet Lite International: Air Arabia, Emirates, Spice jet, Fly Dubai, Jet Airways, Etihad, Singapore, Qatar, Air India Frequency :

Domestic : 124 per day International : 24 per day

7. Other Airports in the vicinity

(within 150 Km radius)

Vadodara Airport : 100.00 km towards SE

B. Airport land area & utilization

1. Total land area (Acres) 928.59 Acres

C. Aerodrome Data (Air side)

1. Aerodrome elevation / Reference Temperature

57.5 m /42°C

2. Aerodrome Reference Code (ARC) 4E

3. Aerodrome traffic density Medium

4. Type of traffic permitted VFR/IFR (with night operation)

5. Aerodrome rescue & fire fighting category (ARFF)

Cat-IX

D. Runway

1. Runway operations 05/23

2. Runway Dimension 3505 m x 45 m

3. Runway strip dimension 3625 m x 150 m

4. Runway Strength (PCN) Rigid Portion - 83/R/B/W/T Flexible / Composite portion ---94/F/B/W/T

5. Runway surface Flexible Pavement

6. Runway shoulder 10.5 M

7. Runway End Safety area (RESA) 90 m x 90 m at both end of runway

E Terminal Building

1. Area Domestic Side: 31000 sq.m International Side: 39000 sq.m

2. PEAK HOUR CAPACITY (PHP) DEPARTURE/ARRIVAL/TRANSIT PAX

Domestic: 1600

International: 1400

3. Car Parking Area Domestic: 10786.55 Sq.m

International: 17621.59 Sq.m

F. Apron Details

1. Dimension Apron 1: 750 m x 200 m

Page 4: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Apron 2: 363 m x 135 m

2. Capacity Apron 1- 24 (Code A & B: 12, Code C :7, D & E : 5) Apron 2- 06 (Code C: 2 and Code D & E: 4)

3. PCN

APRON-1 Bay 1 to 7 88/R/A/W/T Bays 8 to 12 59/R/A/W/T Bays 13 82/R/A/W/T Bay 14 to 21 98/R/B/W/T Bay 22 to 24 59/R/A/W/T APRON-2 Bay 31 to 36 63/R/B/W/T

G Taxiway Details

1. Width Taxiways Length (m)

Width (m)

Surface Type

Strength

ALPHA 308.45 23 Rigid (Concrete)

72/R/B/W/T

BRAVO 337 23 Flexible (Asphalt)

58/R/B/W/T (Rigid ) 101/F/B/W/T (Flexible)

CHARLIE 297 23 Rigid (Concrete)

77/R/B/W/T

DELTA 320 23 Rigid (Concrete)

84/R/B/W/T

FOXTROT 262 23 Rigid (Concrete)

---

GOLF 152.25 23 Rigid (Concrete)

65/R/B/W/T

HOTEL 152.25 23 Rigid (Concrete)

65/R/B/W/T

2. PARALLEL TWY (Width/Strength)

Taxiways Length (m)

Width (m)

Surface Type

Strength

PAPA 1455.60

23

Rigid (Concrete)

Between TWY B & TWY C) 84/R/B/W/T (Between TWY A & TWY B) 81/R/B/W

3. Shoulder All Twy having shoulders of 10.5 m each side

H. Navigation Aids

1. DVOR Available

2. PAPI PAPI for both ends have been installed to accommodate Cat-E Aircraft; Glide Angle Rwy 05 - 3 degree / Rwy 23 – 3 degree

I AAI Staff Accommodation

Residential Colony Type of Quarters Available Quarters

Page 5: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

TYPE I (A) 3 TYPE II (A) 33 TYPEIII (B) 42 TYPEIV (C) 13 TYPEV (D) 6 TYPEVI (E) 1 TOTAL 98

CISF Barrack Accommodation 2 Male barrack accommodation 1 Female barrack accommodation

J. Other Facilities

1. Instrumental Landing system Available

2. Runway Light Facilities Available

3. Approach Lighting System (ALS) Runway 05- SALS Runway 23- Abridged Cat - I Approach Lights (Length 750 m)

H. Solar Panels

1. Area for Solar panels 12 acres in front of Radar in ops area

********************

Page 6: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

INTRODUCTION OF THE PROJECT

2.1 Identification of Project and Project Proponent Ahmedabad district is located in the central Gujarat. Ahmedabad is the largest city in

Gujarat and seventh largest urban agglomeration in India located on the banks of the

Sabarmati River, 30 km from the state capital Gandhinagar. Ahmedabad is an industrial

hub for textiles and was popularly known as the ‘Manchester of India’.

Sardar Vallabhbhai Patel International Airport (S.V.P.I.) is spread over an area of 928.59

acres. Presently 774 acres of land has been used on airside (operational area) while 142.93

acres earmarked on city side (in use 45 acres + future development 97.93 acres). Airports

Authority of India (AAI) proposes to construct new ATC Tower cum Technical Block at

S.V.P.I. at an area of 9840.00 m2 (2.43 Acres).

The proposal is to construct new ATC Tower cum Technical Block at S.V.P.I. Airport,

Ahmedabad to make approach funnel of runway (23) visible, as from existing ATC Tower

cum Technical Block approach funnel (23) is not clearly visible.

Airports Authority of India (AAI) was constituted by an Act of Parliament and came into

being on 1st April 1995. AAI under the Ministry of Civil Aviation is responsible for

creating, upgrading, maintaining and managing civil aviation infrastructure in India.

Airports Authority of India (AAI).

AAI is planning to take up the works of construction of new ATC Tower and other allied

works. The proposed construction of new ATC tower cum Technical Block of Airport is

categorized under item 7 (a) of Schedule - Gazette Notification dated Sept. 14th, 2006 and

its subsequent amendment thereafter.

The existing facility & other details are as follows:

S.N. Particulars Details Particulars Details

A. General Information

1. Airport Owner/Operator Airports Authority of India

2. State Gujarat

3. Location Hansol, Ahmedabad. Gujarat

4. Latitude & Longitude of 23°04'16.28"N 72°37'35.15"E

Page 7: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Aerodrome Reference Point

(ARP–WGS 84)

5. Suitability Code E Aircraft

6. Aircraft operations

(Scheduled/Non-scheduled)

Destination:

Domestic: Delhi, Kolkata, Mumbai, Chennai, Goa, Pune, Hyderabad, Bangalore, Jaipur, Indore, Bhopal International: Singapore, Abu Dhabi, Muscat, Dubai, Sharjah,

Doha, Kuwait, London, Newark

Operators :

Domestic: Air India, Air Vistara, Jet Airways, Spice jet, Go Air, Indigo, Air Costa, Jet Lite International: Air Arabia, Emirates, Spice jet, Fly Dubai, Jet

Airways, Etihad, Singapore, Qatar, Air India

Frequency :

Domestic : 124 per day International : 24 per day

7. Other Airports in the vicinity

(within 150 Km radius)

Vadodara Airport : 100.00 km towards SE

B. Airport land area & utilization

1. Total land area (Acres) 928.59 Acres

C. Aerodrome Data (Air side)

1. Aerodrome elevation / Reference Temperature

57.5 m /42°C

2. Aerodrome Reference Code (ARC)

4E

3. Aerodrome traffic density Medium

4. Type of traffic permitted VFR/IFR (with night operation)

5. Aerodrome rescue & fire fighting category (ARFF)

Cat-IX

D. Runway

1. Runway operations 05/23

2. Runway Dimension 3505 m x 45 m

3. Runway strip dimension 3625 m x 150 m

4. Runway Strength (PCN) Rigid Portion - 83/R/B/W/T Flexible / Composite portion ---94/F/B/W/T

5. Runway surface Flexible Pavement

6. Runway shoulder 10.5 M

7. Runway End Safety area (RESA) 90 m x 90 m at both end of runway

Page 8: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

E Terminal Building

1. Area Domestic Side: 31000 sq.m International Side: 39000 sq.m

2. PEAK HOUR CAPACITY (PHP) DEPARTURE/ARRIVAL/TRANSIT PAX

Domestic: 1600

International: 1400

3. Car Parking Area Domestic: 10786.55 Sq.m

International: 17621.59 Sq.m

F. Apron Details

1. Dimension Apron 1: 750 m x 200 m Apron 2: 363 m x 135 m

2. Capacity Apron 1- 24 (Code A & B: 12, Code C :7, D & E : 5) Apron 2- 06 (Code C: 2 and Code D & E: 4)

3. PCN

APRON-1 Bay 1 to 7 88/R/A/W/T Bays 8 to 12 59/R/A/W/T Bays 13 82/R/A/W/T Bay 14 to 21 98/R/B/W/T Bay 22 to 24 59/R/A/W/T APRON-2 Bay 31 to 36 63/R/B/W/T

G Taxiway Details

1. Width Taxiways Length (m)

Width (m)

Surface Type

Strength

ALPHA 308.45 23 Rigid (Concrete)

72/R/B/W/T

BRAVO 337 23 Flexible (Asphalt)

58/R/B/W/T (Rigid ) 101/F/B/W/T (Flexible)

CHARLIE 297 23 Rigid (Concrete)

77/R/B/W/T

DELTA 320 23 Rigid (Concrete)

84/R/B/W/T

FOXTROT 262 23 Rigid (Concrete)

---

GOLF 152.25 23 Rigid (Concrete)

65/R/B/W/T

HOTEL 152.25 23 Rigid (Concrete)

65/R/B/W/T

2. PARALLEL TWY (Width/Strength)

Taxiways Length (m)

Width (m)

Surface Type

Strength

PAPA 1455.60

23

Rigid (Concrete)

Between TWY B & TWY C) 84/R/B/W/T (Between TWY A & TWY B) 81/R/B/W

3. Shoulder All Twy having shoulders of 10.5 m each side

Page 9: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

H. Navigation Aids

1. DVOR Available

2. PAPI PAPI for both ends have been installed to accommodate Cat-E Aircraft; Glide Angle Rwy 05 - 3 degree / Rwy 23 – 3 degree

I AAI Staff Accommodation

Residential Colony Type of Quarters Numbers TYPE I (A) 3 TYPE II (A) 33 TYPEIII (B) 42 TYPEIV (C) 13 TYPEV (D) 6 TYPEVI (E) 1 TOTAL 98

CISF Barrack Accommodation 2 Male barrack accommodation 1 Female barrack accommodation

J. Other Facilities

1. Instrumental Landing system Available

2. Runway Light Facilities Available

3. Approach Lighting System (ALS) Runway 05- SALS Runway 23- Abridged Cat - I Approach Lights (Length 750 m)

H. Solar Panels

1. Area for Solar panels 12 Acres in front of Radar in ops area

2.2 Brief Description of Nature of the Project AAI is planning to construct ATC Tower cum Technical Block at S.V.P.I. Airport,

Ahmedabad due to operational requirement as approach funnel of runway (23) is not

visible.

Type of project: The proposed expansion of Airport is categorized as category A under item 7 (a) of

Schedule - Gazette Notification dated Sept. 14th, 2006 and its subsequent amendment for

preparation of Environment Impact Assessment study and Environment Management

Plan. However general condition is not applicable to this project. This project is

independent and is not linked with other project which may attract directly or indirectly

any provisions of schedule of EIA notification 2006 amended to date.

Page 10: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

2.3 Need for the project & its Importance The ATC Tower controls all movements such as takeoff, landing and ground traffic. The

Purpose of ATC Tower is to prevent collisions, organize and expedite the flow of air

traffic, and provide information and other support for pilots. ATC provides services to all

private, military, and commercial aircraft operating within its airspace.

The existing ATC Tower cum Technical Block needs to relocate due to operational

requirement as approach funnel of runway (23) is not clearly visible. To meet the proper

and smooth movement of Aircrafts at the S.V.P.I. Airport, Ahmedabad it is required to

relocate the ATC Tower cum Technical Block.

Improvements in connectivity will effectively contribute to the economic performance of

the wider economy through enhancing its overall level of productivity. Table 1.1 shows

the quantum of passengers handled at SVPI airports in last few years:

Table 1-1: Passenger Handled at Major Airports in India (in millions)

S. N. Particulars 2014-15 (FY) 2015-16 (FY) 2016-17 (FY) 2017-18 (FY)

Dom Inlt. Dom Inlt. Dom Inlt. Dom Inlt.

1. Aircraft Movement 41529 41529 43697 10416 38762 12345 49987 13142

2. Passenger 3571559 3571559 6483641 1568535 7323471 1785909 5619373 1850954

3. Cargo (in tones) 35932 35932 44317 23457 45552 31050 50367 41266

Source: Airports Authority of India, APAO, New Delhi

2.4 Demand Supply Gap

The existing ATC Tower cum Technical Block needs to relocate due to operational

requirement as approach funnel of runway (23) is not clearly visible. To meet the proper

and smooth movement of Aircrafts at the S.V.P.I. Airport, Ahmedabad it is required to

relocate the ATC Tower cum Technical Block.

2.5 Imports vs. Indigenous production

Not Applicable as the project is construction of new ATC tower cum Technical Block at

SVPI Airport, Ahmedabad.

Page 11: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

2.6 Export Possibility

Not Applicable as the project is construction of new ATC tower cum Technical Block at

SVPI Airport, Ahmedabad.

2.7 Domestic/ export Markets

Not Applicable as the project is construction of new ATC tower cum Technical Block at SVPI Airport, Ahmedabad.

2.8 Employment Generation (Direct and Indirect) due to the project

The proposed project will provide direct employment during construction & operation

phase. Local workers will be hired from the nearby areas during construction

phase/workers will be sourced by construction contractor. During operation phase

employees from existing ATC Tower will be shifted in new ATC Tower cum Technical

Block.

*********

Page 12: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

PROJECT DESCRIPTION

3.1 Type of Project: AAI is planning to construct ATC Tower cum Technical Block at S.V.P.I. Airport,

Ahmedabad due to operational requirement as approach funnel of runway (23) is not

visible.

Project falls under Category “A”, under schedule ‘7(a)’ of EIA Notification dated 14th

September, 2006 & amendment made thereafter.

3.2 Location:

The project is situated at Hansol, Ahmedabad, Gujarat. The airports reference point is

located at latitude 23°04'16.28"N and longitude 72°37'35.15"E. The Google map is

given in Figure.

Figure: Google Map

Page 13: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

S.V.P.I. Airport Environmental Setting: S. No Particulars Details

1. Present Land use at Airport Industrial Commercial

2. Nearest Highway/Major Road • NH-8: 5.5 km towards NE

• NH-8C: 12.0 km towards NNW

• NH-59: 1.7 km towards SE

• NH-228: 13.88 km towards SSW

• SH-41: 4.1 km towards W

3. Nearest Railway Station Ahmedabad Railway Station : 6.8 km towards sw

4. Nearest Town/village • Ahmedabad (As the proposed project site lies within

S.V.P.I. Airport, Ahmedabad).

5. Major Water Bodies • Sabarmati River : 1.5 km towards N

• Khairicut Canal : 3.0 km towards E

• Narmada Main Canal : 5.2 km towards N

• Bera Nala : 6.5 km towards NE

• Kankariya Talav : 8.3 km towards SSW

• Khari Nadi : 8.7 km towards E

• Chandola Talav : 10.7 km towards SSW

• Vaheva Nadi : 11.6 km towards S

6. Seismic Zone Zone III (Moderate Seismic Hazard)

3.3 Details of alternative site:

The proposed project involves construction of new ATC Building cum Technical Block

at S.V.P.I. Airport Ahmedabad. The construction work will be done in the land abutting

the existing airport. Hence, no alternative sites were examined.

3.4 Size or magnitude of operation: S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land has

been used on airside (operational area) while 142.93 acres earmarked on city side (in use

45 acres + future development 97.93 acres). Airports Authority of India (AAI) proposes

Page 14: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

to construct new ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2

(2.43 Acres) out of which 1512.25 m2 shall be utilized as ground coverage. The total

Built up area envisaged for the proposed tower 10520.5 m2.

Details of proposed Facility are as under:

S No. Description Details

1. Coordinates (ATC Tower) Latitude: 23° 04' 42.44" N

Longitude: 72° 37' 12.15" E

2. ARP coordinates Latitude : 23° 04' 16.28" N

Longitude : 72° 37' 35.15" E

3. Plot area 9840 sq. m.

4. Ground Coverage (achieved) 1512.25 sq. m.

5. Total Built Up Area (including

Headroom & core of Tower)

10520.5 sq. m.

6. Green Area 3338.5 sq. m. (33.92 %)

7. Road and Open Area (excluding surface

parking area)

3466.65 sq. m.

8. Surface parking Area 1522.595 sq. m. (32 Cars & 64 Scooters)

9. No. of Floors 15

10. Height of Tower 72.4 m

11. Population {Staff (ATC cum Technical

Block)}

125 Persons (Peak)

Page 15: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Fig: Layout Plan of New ATC Tower cum Technical Block

Page 16: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Fig: Master Plan of SVPI Airport, Ahmedabad

3.5 Raw Material required (Quantity & Source), Product & Mode of Transport: Airport being a service industry doesn’t process any raw material or deal in production

of products. The proposed project is construction of new ATC tower cum Technical

Bock which requires general construction materials viz. sand, aggregates, bricks, etc.

Page 17: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

will be used for infrastructure (roads, service areas, ATC tower) development. The raw

materials will be procured from nearby markets as per requirements and transportation

facilities will be provided by construction contractor.

3.6 Resource optimization/recycling & Reuse envisaged in the Project: 1. Use of fly ash will be considered as a part of resource optimization, recycling & reuse as per

engineering and operational requirements.

2. During construction phase, material will be used as per requirements with the focus of resources

conservation.

3. During operational phase, the input resources such as Drinking Water, Energy & Fuels will be

used as per requirements with the focus of resources conservation & resource

Optimizations.

4. During operation Municipal wastes will be managed as per MSW Rules, 2016; two bin systems

will be followed. All the recyclable wastes collected will be recycled by the service provider and

biological wastes will be composted away from the airport by municipal authorized facilities.

5. ISO 50001- Energy Management System is in place, energy conservation, energy efficiency will

be considered as a part of resources conservation & resource optimizations.

6. Use of renewable energy and capacity enhancement will be considered for energy resource

optimization.

3.7 Availability of Water, Energy / Power Requirement & Source:

3.7.1 Population :

S. No. Population Details

1. Staff ( Control Tower cum Technical Block) Peak Intensity 125

2. Visitors 50

3.7.2 Water requirement:

The daily consumption of water for new ATC tower cum Technical Block during

operation phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh

Page 18: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

water and 5 KLD will be recycled/treated water. The water requirement for Landscaping,

HVAC & DG cooling will be about 32 KLD (treated water). The water will be met

through Ahmedabad Municipal Corporation (AMC) water supply. The details of water

requirement and wastewater generation for operation phase are as follows:

A. Construction phase:

Domestic Water

Domestic water during construction phase for approx 100 nos. of workers will be 5

KLD, which will be met through the construction contractor / from the supply line of

AMC as specified in the contract award.

The potable water supplied for construction workers will be treated to meet the potable

water specification by the contractor as per AMC water quality norms / IS10500.

Domestic wastewater will be generated, collected and retained in the bio toilets provided

by construction contractor.

B. Operational Phase:

S. No.

Particulars Population* Fresh water

demand

Treated water Demand

Total water Demand

1. Staff’s 125 @40 LPCD: 5 KLD @30 LPCD: 4 KLD 9 KLD

2. Visitors 50 @25 LPCD: 2 KLD @20 LPCD: 1 KLD 3 KLD

3. Landscape @5L/m2 17 KLD 17 KLD

4. HVAC & DG cooling 50 KL One Time Requirement

and 15 KLD Daily requirement

15 KLD 15 KLD

Total 7 KLD 37 KLD 44 KLD

Source: NBC 2016 *Maximum Footfall

Page 19: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Water Balance

Fresh water

7 KLD

Staff’s5 KLD

STP treated

water

37 KLD

6 KLD

Waste water

S

T

P

Capacity

10 KLD

Sludge &

evaporation

losses

1 KLD

Recycled/ reused for flushing, landscaping

Daily water demand: 44 KLD {7 KLD (fresh) + 37 KLD (recycled/ reused water)}

HVAC & DG Cooling 50 KL

4 KLD

Visitors -2 KLD

Landscape17 KLD

2 KLD

5 KLDFlushing 5 KLD

Treated water from AMC

32 KLD

35 KLD Re-circulated

15 KLD

5 KLD

3.7.3 Power Demand

The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport,

Ahmedabad is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of

Torrent Power.

There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in

case of power cut or failure. DG set will be provided with an effective safe stack height

for proper dispersion of pollutants that will keep the emissions within the permissible

limit. The fuel requirement will be about 240 lit/hr of HSD (as and when used).

3.7.4 STORM WATER MANAGEMENT:

Construction phase

Contaminant Sources Impact Mitigation Sediment & Floatables

Streets, lawns, driveways, roads, construction

During construction, sediment fencing or other erosion control devices will be used to mitigate the short-term

Page 20: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

activities, adverse impacts of sedimentation.

Oil & Grease Roads, driveways, parking lots etc.

Oil & Grease trap will be provided to remove oil & grease, suspended matter, and ensure the quality of water.

Storm water control and rain water harvesting will be done as per the standards laid

down by CGWA & BIS. Following measure will be adopted for the same:

Construction Sequencing: Construction sequencing (involves disturbing only part of a

site at a time to prevent erosion from dormant parts) has been done at site. Grading

activities and construction are completed and soils are effectively stabilized on one part

of the site before grading and construction commence at another part.

Compost Blankets: A compost blanket is a layer of loosely applied composted material

placed on the soil in disturbed areas to reduce storm water runoff and erosion. This

material fills in small rills and voids to limit channelized flow, provides a more

permeable surface to facilitate storm water infiltration, and promotes re-vegetation.

Post Construction Phase:

a. Design:

For good design of rainwater harvesting, following points are to be kept under

consideration:

• Ideal location with good ground slope.

• The location has adequate subsurface permeability of the aquifer to accommodate

maximum recharge of rainwater through injection well.

• Rate of filtration should exceed average rainfall intensity.

• Clogging of filtration media should be cleaned periodically.

• Ground water pollution does not take place.

b. Baseline:

The average annual rainfall (based on last 5 years rainfall data) at Ahmedabad station is

623 mm.

Page 21: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Rain Fall Data (last 5 years):

S. No. Year Annual Average Rainfall

1 2017 734.5

2 2016 436.1

3 2015 315.7

4 2014 698.2

5 2013 929

Total 3113.5 say 3114

Average 622.8 say 623

Source: IMD, Ahmedabad

c. Calculation of No. of RWH Structures:

The rain water harvesting structures are calculated on the basis of peak intensity of

rainfall recorded as 40 mm/hr considering 15 minutes of peak rainfall. The same has

been done to avoid flooding of the area.

S.

No

Type of

Structure/ Surface

Area [A]

(sq. m.)

Run off

Coefficient

[C]

Intensity

of rainfall

(m/hour) [I]

Total Recharge

[Q = CIA]

(m3/hr)

1. Roof Top 1512.25 0.9 0.04 54.441

2. Landscape 3338.5 0.3 0.04 40.062

3. Road &Paved area 4989.25 0.75 0.04 149.677

Grand Total (1-3) 9840 244.18

Total Rain Water Flow : 244.18 m3/hr

Considering 15 minutes of peak rainfall,

Runoff volume : 61.04 m3/hr

Volume of each pit : 27 m3 (3 m x 3 m x 3 m)

Total no. of rain water harvesting pits required

: Total run-off volume/volume of each pit

Page 22: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

: 61.04/27

: 2.26 say 2 nos.

Therefore, 2 Nos. rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with

PVC slotted pipe upto minimum depth of 30 m.

d. Design of Rain Water Harvesting Structure:

The dimensional parameters of Desilting/Settlement chamber would be 3 m (length) x 3

m (width) x 1.30 (depth). In Desilting chamber, 0.30 m depth below outflow is kept for

silt deposition. The filtration tank dimension would be 3 m (length) x 3 m (width) x 1 m

(depth) with 0.15 m dia recharge well of 30 m depth depending upon the formation for

recharge in aquifer through vadose zone.

e. Calculation of annual recharge:

S.

No

Type of

Structure/ Surface

Area [A]

(sq. m.)

Run off

Coefficient

[C]

Intensity

of rainfall [I]

(m/annum)

Total Recharge

[Q= CIA]

(m3/ annum)

1. Roof Top 1512.25 0.9 0.623 847.91

2. Landscape 3338.5 0.3 0.623 623.96

3. Paved area 4989.25 0.75 0.623 2331.22

Grand Total (1-3) 9840 3803.09

Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting

structure would be 3803.09 m3/ annum.

3.8 Waste Generation & Management Solid Waste management:

Solid waste generated from the airport mainly comprises of food waste and garbage

waste. Further, small quantities of sludge from STP and other waste are being generated.

Page 23: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

The solid waste generated will be first segregated as plastic, glass, paper, and other waste

separately and disposed off as per applicable Rules.

Solid Waste Calculation:

Particulars Population Basis Quantity of waste generated (in kg/day)

Staffs 125 @0.40 kg/day 50

Visitors 50 @0.12 kg/day 6

Landscaping 0.824 acres @0.2kg/acre/day 0.16

Total 56.16 Say 57 kg/day *Source: NBC 2016

Break Up of Residential Solid Waste:-

Particulars Quantity (kg/day) % Percentage

Biodegradable 27 47.43

Paper 5 8.13

Plastic/rubber 5 9.22

Metal 1 0.5

Glass 1 1.01

Rags 2 4.49

Other 2 4.02

Inerts 14 25.16

Total 57 100

Source: Municipal Solid Waste Management Manual-Part-II, CPHEEEO, MOUD, 2016

Page 24: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

Bins Particulars Treatment Disposal Green Compostable waste Collected in green colored bins and sent

to the OWC Will be sent to municipality disposal site

White Dry/ recyclable waste:

No in-situ treatment. Collected in white colored bins and sent to solid waste collection point. Segregated waste will be

handed over to authorized waste pickers or waste collectors.

Black Other waste/ Domestic hazardous waste

No in-situ treatment. Collected in Black colored bins and sent to solid waste collection point

Source: Municipal Solid Waste Management Manual, CPHEEEO, MOUD, 2016

Waste water treatment & management:

During operation phase, wastewater generated from ATC Tower cum Technical Block will

be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary

treatment facilities.

3.9 Schematic representations of the Feasibility drawing which give information of

EIA purpose:

As per the EIA notification dated 14th September, 2006, it is mandatory for the proposed

activity to get Environmental Clearance (EC) before setting up any project or

expansion/modernization of any project. The detailed chart delineating the process is

given below:

Environmental Impact Assessment (EIA) is a well planned process to predict the

environmental consequences of any kind of development, which is a result of human

activities and to suggest appropriate measures in order to reduce adverse effects and also

to augment positive effects. The EIA procures a rational and ethical approach for

sustainable development. However, it is more scientific process because it not only tells

the past, present and the future consequences of on-going developments, but also

predicts the future events which are likely to change due to various reasons.

In terms of the EIA notification of the MoE&F dated 14th September 2006, the generic

structure of EIA documents shall be as under:-

Page 25: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

• Introduction

• Project Description

• Analysis of Alternatives (Technology & Site)

• Description of the Environment

• Anticipated Environmental Impact & mitigation Measures

• Environmental Monitoring Programme

• Additional studies

• Project benefits

• Environmental Cost benefits Analysis

• EMP

• Summary & Conclusion

• Disclosure of Consultant Engaged

*************

Page 26: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

SITE ANALYSIS

4.1 Connectivity: S.V.P.I. Airport is an international airport serving the cities of Ahmedabad and

Gandhinagar in Gujarat, India. The airport is located in Hansol, 9 km (5.6 mi) north of

central Ahmedabad.

Particular Details

Nearest Highway/Major Road, • NH-8: 5.5 km towards NE

• NH-8C: 12.0 km towards NNW

• NH-59: 1.7 km towards SE

• NH-228: 13.88 km towards SSW

• SH-41: 4.1 km towards W

Railway Station Ahmedabad Railway Station : 6.8 km towards sw

Public Transport

Plenty of tourist buses, taxis and luxury coaches are available

to and from important cities of the state and that of the

country.

4.2 Land Form, Land Use & Land Ownership

Presently, the airport is situated on 928.59 acres of land and the airport was set up in

1937, while international operations began on 26/01/1991 and currently operates about

148 flights per month. Currently, 774 acres of land is available on airside and 142.93 acres

of land is available on city side (45 acres present in use & 97.93 acres for future development).

The land ownership of 928.59 acres is reserved with Airport Authority of India.

4.3 Topography

Geomorphologically the district can be divided into two zones, the major portion of it

forms a flat planar topography except for a few rocky features in the extreme southern

portion.

Page 27: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

22

Source: http://en-in.topographic-map.com/places/Ahmedabad-7809992 Fig: Topographical Map of S.V.P.I. Airport, Ahmedabad

4.4 Existing Land use Pattern The land use pattern of the existing airport remains same. The additional construction

of new ATC tower will be converted into industrial commercial category.

4.5 Existing Infrastructure of Site

Existing infrastructure details are given in Section-2.1.

4.6 Soil Classification The soils in the district can broadly be classified as: they are Black soils, Goradu

soils, Kyari soils & Rocky soils. Alluvial sandy loam to sandy clay soils are found in

the Kheda, Gandhinagar, Ahmadabad and Mehsana district and the western part of the

Vadodara district. These soils are the most productive soils in the state and contains

fairly good amount of potassium. (Source:- Ground Water Brochure Ahmedabad

District Gujarat & http://www.gujenvis.nic.in/PDF/soil.pdf)

Page 28: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

4.7 Climate Data from Secondary Sources The climate of the district is characterized by hot summer and general dryness except

during the southwest monsoon seasons. The year can be divided into four seasons.

The period from March to May is the hot season (summer) followed by southwest

monsoon from June to September. October and November constitute the post-

monsoon or retreating monsoon season. The cold season (winter) starts from

December and ends in February. The mean maximum temperature ranges between

28.4ºC during January to 41.8ºC during May and the mean minimum temperatures

vary between 11.7ºC during January and 27ºC during June. Long-term average annual

rainfall recorded by IMD station at Ahmedabad is 799.6 mm. Most of the rainfall

(about 766 mm) is received from south-west monsoon between June to September.

(Source: Ground Water Brochure Ahmedabad District Gujarat).

4.8 Social Infrastructure Available The existing social infrastructure in the Shillong which is located at about 10 km from

the airport are:

Hospital with ambulance;

Banks;

Post office;

Bus station;

Fire station;

Secondary school;

Police station;

Shopping complex;

Sports infrastructure (Stadium & Camps etc);

Community halls;

Cinema halls; and

Primary health care centers

**************

Page 29: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd. EIA Coordinator 24

Airports Authority of India

Authorized Signatory

PLANNING BRIEF

5.1 Planning Concept This is a planned airport development project to cater aviation demand as per Master Plan.

The construction of new ATC building cum Technical block is proposed. Other facilities such

as power, transportation and communication, social infrastructure facilities are already

available at project site as the proposed project lies within S.V.P.I. Airport, Ahmedabad.

5.2 Population Projection The general public at S.V.P.I airport, Ahmedabad will not be having any impact as this

building is to be used by only staff of existing ATC office.

5.3 Land use planning Land use has been categorized based on the following functional groups:

Airfield Dependent: Land uses with the highest location and area priority include those that

are fully within the airfield, or overlapping the airside-landside boundary.

Airport Supporting: Land uses with functional priority include those that are required for

the airport to function. Their location may be on the airside or landside but preferably within

the airport boundary.

Commercial: Land uses that are fully provide non-aviation revenues. These uses have

flexibility of location but should not interfere with the functional operation of Airfield

Dependent or Airport Supporting Land Uses.

Infrastructure & Open Space: These land use areas are determined by the needs of all the

land uses above. Since supporting infrastructure must be within the development areas the

first three groups determine the area required for this group. Open space includes those areas

remaining which cannot be developed.

5.4 Assessment of Infrastructure Demand (Physical & Social) Social Demand

On the basis of the preliminary site visit, the infrastructure demand in the nearby area is

assessed on the basis of need and priority:

The assessment will be identified in the socio economic survey, after the grant of TOR and

will be submitted at the time of final presentation regarding Environmental Clearance.

Page 30: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd. EIA Coordinator 25

Airports Authority of India

Authorized Signatory

Physical infrastructure Physical infrastructure is an important aspect of the site. It determines the quality of life to a

large extent. Physical infrastructure deals with:

• Water supply

• Electricity

• Waste management & treatment

Water supply The daily consumption of water for new ATC tower cum Technical Block during operation

phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh water and 5

KLD will be recycled/treated water. The water requirement for Landscaping, HVAC & DG

cooling will be about 32 KLD (treated water). The water will be met through AMC water

supply.

Electricity

The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport, Ahmedabad

is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of Torrent Power.

There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in case of

power cut or failure. DG set will be provided with an effective safe stack height for proper

dispersion of pollutants that will keep the emissions within the permissible limit. The fuel

requirement will be about 240 lit/hr of HSD (as and when used).

Solid Waste management:

Solid waste generated from the airport mainly comprises of food waste and garbage waste.

Further, small quantities of sludge from STP and other waste are being generated. Collection

and handling of domestic solid waste is being done in line with the provisions of the Solid

Waste Management Rules 2016. Waste water treatment & management:

During operation phase, wastewater generated from ATC Tower cum Technical Block will

be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary

treatment facilities.

*********

Page 31: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

PROPOSED INFRASTRUCTURE

6.1 Industrial Area (processing area) S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land has been

used on airside (operational area) while 142.93 acres earmarked on city side (in use 45 acres +

future development 97.93 acres). Airports Authority of India (AAI) proposes to construct new

ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2 (2.43 Acres) out of

which 1512.25 m2 shall be utilized as ground coverage. The total built up area envisaged for

the proposed tower 10520.5 m2.

The Brief details are as under:

S No. Description Details

1. Project cost Rs. 166.47 Cr.

2. Location Latitude: 23° 04' 42.44" N

Longitude: 72° 37' 12.15" E

3. ARP coordinates Latitude : 23° 04' 16.28" N

Longitude : 72° 37' 35.15" E

4. Plot area 9840 sq. m.

5. Ground Coverage (achieved) 1512.25 sq. m.

6. Total Built Up Area (including

Headroom & core of Tower)

10520.5 sq. m.

7. Green Area 3338.5 sq. m. (33.92 %)

8. Road and Open Area (excluding surface

parking area)

3466.65 sq. m.

9. Surface parking Area 1522.595 sq. m.

10. No. of Floors 15

11. Height of Tower 72.4 m

12. Population {Staff (ATC cum Technical

Block)

125 Persons (Peak)

13. Water demand 12 KLD (domestic)

6.2 Residential Area (non-processing area) Not Applicable as the project is construction of new ATC tower cum Technical Block at

SVPI Airport, Ahmedabad.

Page 32: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

6.3 Green Belt Approximately 33.92 % of the total project area will be under green belt and plantation.

Entire landscaping is irrigated with treated waste water having drip irrigation and automatic

water efficient water dispensing system.

6.4 Social Infrastructure The proposed infrastructure will be identified in the socio-economic survey, after the grant of

ToR and will be submitted at the time of final presentation regarding Environmental

Clearance.

6.5 Connectivity S.V.P.I. Airport is an international airport serving the cities of Ahmedabad and Gandhinagar

in Gujarat, India. The airport is located in Hansol, 9 km (5.6 mi) north of central Ahmedabad.

The connectivity details are as below:

Particular Details

Nearest Highway/Major Road, • NH-8: 5.5 km towards NE

• NH-8C: 12.0 km towards NNW

• NH-59: 1.7 km towards SE

• NH-228: 13.88 km towards SSW

• SH-41: 4.1 km towards W

Railway Station Ahmedabad Railway Station : 6.8 km towards SW

Public Transport

Plenty of tourist buses, taxis and luxury coaches are available

to and from important cities of the state and that of the

country.

6.6 Drinking Water Management (Source & Supply of Water) The daily consumption of water for new ATC tower cum Technical Block during

operation phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh

water and 5 KLD will be recycled/treated water. The water requirement for Landscaping,

HVAC & DG cooling will be about 32 KLD (treated water). The water will be met

through by AMC water supply.

6.7 Sewerage System For the treatment of domestic sewerage, STP will be installed in the project site.

Page 33: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

6.8 Industrial Waste Management No Industrial waste will be generated from the project.

6.9 Solid waste Management Solid waste generated from the airport mainly comprises of food waste and garbage waste.

Further, small quantities of sludge from STP and other waste are being generated. Collection

and handling of domestic solid waste is being done in line with the provisions of the Solid

Waste Management Rules 2016.

6.10 Waste water treatment & management During operation phase, wastewater generated from ATC Tower cum Technical Block will

be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary

treatment facilities. The treated wastewater from the STP will be used for flushing.

6.11 Power Requirement & Supply/ Source The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport, Ahmedabad

is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of Torrent Power.

There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in case of

power cut or failure. DG set will be provided with an effective safe stack height for proper

dispersion of pollutants that will keep the emissions within the permissible limit. The fuel

requirement will be about 240 lit/hr of HSD (as and when used).

**************

Page 34: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

REHABILITATION & RESETTLEMENT (R&R) PLAN

7.1. Rehabilitation & Resettlement (R&R) Plan

Introduction:

Airport Authority of India (AAI) proposes to construct new ATC Tower cum Technical

Block as the approach funnel of runway (23) is out of visual coverage from existing ATC

Tower. S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land

has been used on airside (operational area) while 142.93 acres earmarked on city side (in use

45 acres + future development 97.93 acres). Airports Authority of India (AAI) proposes to

construct new ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2 (2.43

Acres) out of which 1512.25 m2 shall be utilized as ground coverage. The total Built up area

envisaged for the proposed tower 10520.5 m2. The land ownership of 928.59 acres is reserved

with Airport Authority of India.

Therefore Rehabilitation and Resettlement (R&R) is not applicable for proposed project.

************

Page 35: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

PROJECT SCHEDULE & COST ESTIMATES

8.1. Project Schedule & Cost Estimates Estimated cost of work for the construction of new ATC Tower cum Technical Block &

allied works is worked out to be Rs. 166.47 Crores.

*************

Page 36: EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/06...Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR Promoter :

Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR

Promoter : Airports Authority of India

Gaurang Environmental Solutions Pvt. Ltd.

EIA Coordinator

Airports Authority of India

Authorized Signatory

ANALYSIS OF PROPOSAL

9.1. Analysis of the Proposal The present proposal of construction of new ATC tower cum Technical Block will

help to meet the proper and smooth movement of Aircrafts at the S.V.P.I. Airport,

Ahmedabad. Improvements in connectivity will effectively contribute to the economic

performance of the wider economy through enhancing its overall level of productivity. The

project will boast economic growth benefitting the whole region through the

generation of both direct and indirect economic value. Airport operations will have a

considerable economic and social impact in surrounding regions.

These benefits extend far beyond the direct effect of an airport’s operation on its

community development to the wider benefits that air service accessibility brings to

business interests and to consumers. The construction and operation of airport will

generate direct employment opportunity, indirectly contributed jobs through supply

chain, enhance induced impact through tourism. Thus the project will prove beneficial

to the area.

. *********