experimental use of high-strength reinforcing...
TRANSCRIPT
Experimental Use of High-Strength Reinforcing Steel
by
Jere G. Newton formerly
Associate Designing Engineer
and
Larry G. Walker Supervising Design Engineer
Research Report Number 25-1 F
Experimental Use of High-Strength Reinforcing Steel Research Project 5-62-25
Conducted by
Bridge Division The Texas Highway Department
In Cooperation with the U. S. Department of Transportation
Federal Highway Administration Bureau of Public Roads
May 1967
The opinions, findings, and conclusions
expressed in this publication are those
of the authors and not necessarily those
of the Bureau of Public Roads.
ACKNOWLEDGEMENTS
The design and test of phases of this experimental
project were supervised by Mr. E. L. Hardeman, Senior Bridge
Engineer for District 9. Mr. W. R. Casbeer designed the ex
perimental structure and Mr. J. N. Newton was responsible for
field tests and data analysis. The research reported was
performed in cooperation with the Bureau of Public Roads.
The valuable assistance and cooperation of the Bureau
of Public Roads in planning and executing the field tests is
greatly appreciated, particularly the work of Mr. R. F. Varney
and Mr. C. F. Galambos who were in charge of live load
testing and equipment.
TABLE OF CONTENTS
LIST OF FIGURES AND TABLES • • • • • • · . ABSTRACT • • • • • • • • • • • • • • • • · . . . . I.
II.
INTRODUCTION • . . . . . . . . . . . . . . . . DETAILS OF THE EXPERIMENTAL STRUCTURE · . Description •••••••••• • • • • • Material . . . . . . . . . . . . . . . . . Des ign • • . .. . . • • • • • . . . . . . Construction • • • • • • • • • • • • •
III. FIELD TESTS AND EVALUATIONS · . . . . . .
IV.
Instrumentation •••••••••• Dynamic Live Load Tests •••••
. . . Dead Load and Time Dependent Deflections • Crack Width Measurements •••• • • •
• • · .
DISCUSSION OF RESULTS Dynamic Live Load Tests Dead Load and Time Dependent Crack Width Measurements • •
· . . . . . . · . . . . . . . . Deflections • · . . . . . . . .
V. CONCLUSIONS . . . . . . . . . . . . . . . . . APPENDIX • • • • . . . . .
References • • • • • • • • • • Figures and Tables • • • • • •
• • • · . . . . • • • · . . . .
Page No. ii
v
1
3 3 4 4 6
7 7
10 13 13
15 15 17 18
23
Figure No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
LIST OF FIGURES AND TABLES
Structure Layout
Structure Details
Structure Details
Structure Details
Strain Gage Installation
Deflection Gage
Axle Loads and Wheel Spacing
Stress Distribution
Stress Distribution
Stress Distribution
Stress Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Deflection Distribution
Peak Deflection vs. Truck Speed
Peak Deflection vs. Truck Speed
ii
Page No.
27
28
29
30
31
31
32
35
36
37
38
40
41
42
43
44
45
46
47
52
53
Figure No.
22
23
24
25
26
27
28
29
30
31
LIST OF FIGURES AND TABLES
Peak Deflection vs. Truck Speed
Peak Deflection vs. Truck Speed
Peak Deflection vs. Truck Speed
Peak Deflection vs. Truck Speed
Observed Deflection Due To Dead Load
Observed Deflection Due To Dead Load
Deviation From Predicted Crack Width vs. Occurence Frequency
Crack Width vs. Occurence Frequency For Each Bent (Before Traffic)
Crack width vs. Occurence Frequency For Eacy Bent (After Traffic)
Observed Crack Width vs. Occurence Frequency For Each Bent (Final Reading)
iii
Page No.
54
55
56
57
58
59
61
62
63
64
Table No.
1
2
3
4
5
6
7
8
LIST OF FIGURES AND TABLES
Steel Stress (PSI) In Bottom Of Girders Center of Span 2
Steel Stress (PSI) In Bottom Of Girders Center Of Span 4
Deflection Of Center Girder (Inches)
Observed Impact Factors
Observed Impact Factors
Vibration Frequency Of Test Vehicle During Test Runs (CPS)
Peak Double Amplitudes Of Vibration Measured On Truck Axles
Forced Vibration Frequency Of Bridge (CPS)
iv
Page No.
33
34
39
48
49
50
51
60
A B S T R ACT
The design, construction and study of a full scale ex
perimental overpass structure is reported.
A-432 reinforcing steel having a minimum yield strength
of 60,000 psi was used in the four span (55'-88'-88'-55')
continuous haunched concrete girder unit. Ultimate strength
theory was used in the desig~and stresses were also checked
by elastic methods.
Electrical strain gages were installed at selected
points on the reinforcing steel and deflection gages em
ploying electrical strain gages were mounted on the com
pleted structure. Oscillographic re~ords of strain and de
flection were taken for a series of live load tests.
A three axle truck was used in the live load tests.
Speed and lane position were varied for purposes of studying
impact, stress distribution, vibration characteristics and
deflection characteristics. Comparisons of observed and cal
culated stresses and deflections were made.
A study of crack width and distribution was made at
several times during the test program. Observed crack forma
tion is compared with various crack prediction methods.
Time dependant deflections were observed throughout the
test period and compared with deflection predictions.
v
The performance of the structure appears to be satis
factory. Crack formation is not considered excessive and
observed strains indicate an adequate factor of safety against
static failure.
vi
Report On
EXPERIMENTAL USE OF HIGH STRENGTH REINFORCING STEEL
I. INTRODUCTION
The successful use of high strength reinforcing steels
in Europe and in building construction in this country
prompted the Portland Cement Association and other agencies
to promote its use in bridges. Laboratory tests have indi-
cated that the high strength steels manufactured in this
country would perform satisfactorily under bridge loadings.
In an effort to gain experience in design and construction
with high strength steel and to evaluate its performance, the
Texas Highway Department initiated plans for a full scale
experimental structure. The crossroad structure over Inter-
state Highway 35 near Hillsboro, Texas,was built as a part
of the Interstate Highway Program and the experimental
phases of the project were accomplished in a research project
in cooperation with the Bureau of Public Roads.
Four structural requirements that must be satisfied by
all reinforced concrete bridges have been listed by Fountain
in an unpublished paper (Reference 1). These are:
1. Adequate safety against static failure
2. Adequate safety against fatigue failure
3. Satisfactory crack formation
4. Satisfactory deflections
It is the broad objective of the research reported to
evaluate the performance of the experimental structure with
respect to these requirements. However, no specific tests
were directed toward evaluation of safety against fatigue
failure.
2
3
I I. DETAILS OF THE EXPERIMENTAL STRUCTURE
Description
A four span continuous concrete T-Beam unit having span
lengths of 55 1 -88 1 -88 1 -55 1 was chosen for this study. The
6~" thick slab was cast monolithically with the parabolic
haunched girders. Three 21_4~" wide girders supported the 241
roadway. The total girder depth was 2 1 -3 11 in the uniform
depth sections and increased to 4 1-9" over supports. The
design loading was H15 for this 30 degree skew structuIE. A
general layout of the structure is shown in Figure 1 and
structural details are shown in Figures 2, 3 and 4.
The interior supports consisted of a single 30" round
column under each girder. Hinge action between columns and
girders was achieved by placing neoprene cushions on the outer
edges of the columns and by placing connecting dowels perpen
dicular to girders at the center of columns. The U-type
abutments and the 3~'' columns \lSre supported on drilled shafts
(cast-in-place piles) •
Several structures of this type and of conventional de
sign and reinforcing were constructed on the same project.
One of these, a four span continuous concrete T-Beam unit
having spans of 55 1-761_76'-55 1, was chosen as a control
structure for comparison purposes.
4
Material
High Strength A432 reinforcing steel with a minimum
yield point of 60,000 psi was chosen for the main steel in
the girders and deck slab. Regular strength A15 reinforcing
was used for stirrups and for column reinforcing. Concrete
with a minimum compressive strength of 3,000 psi and a mini
mum cement content of 5 sacks per cubic yard was specified.
Design
The continuous girder unit was designed by ultimate
strength theory. Load factors of 1.5 for dead load and 2.5
for live load were used except in the cases where dead load
and live load were of opposite sign. In these cases the
dead load factor used was 0.5. Moment distribution was based
on gross section moment of inertia. Lateral distribution of
wheel loads followed AASHO design criteria.
Comparison designs were made by elastic theory for both
30,000 psi and 20,000 psi working stress for reinforcing
steel. Tension steel requirements determined by ultimate
strength theory compared closely with those determined by the
elastic theory with 30,000 psi working stress. The major dif
ference in reinforcing steel requirements was in compression
reinforcement over supports. No compression steel was re
quired by ultimate theory; whereas, 14.62 sq. in. was required
5
by elastic theory. The conventional percentage of positive
moment steel was extended into supports, however. Bars in
girders were cut off as indicated by requirements and no bars
were bent up.
Ultimate strength theory was used for design of the deck
slab but shear stirrups were designed by conventional elastic
design methods.
Top girder steel was distributed over the full width of
girder flanges. Three dif nt bar sizes were used to satis-
fy the tension steel requirements over supports (#7 over the
first interior support, #8 over the center support and #9
over the third). This was done to evaluate the effect of
bar size on crack width. Crack width predictions were com
puted by several empirical formulas for comparison with ob
servations.
Deflection predictions based on gross moment of inertia
were compared with predictions based on transformed moments
of inertia. Both methods gave quite similar deflection pat
terns. The value of modulus of elasticity normally used in
determining construction camber for this type structure is
1.5xl06 • This value was intuitively decreased to 1.Oxl06
for this structure effectively increasing construction cam
ber.
construction
All forming and falsework for the superstructure was
completed prior to beginning concrete placement. All super
structure concrete was completed in seven placements during
the period June l8-June 28, 1963, and all forms were re
leased on July 8, 1963. The sequence of placement is shown
on Figure 2. Deck placements were finished by longitudinal
screeding. The average 28-day compressive concrete strength
was greater than 5,000 psi.
6
III. FIELD TESTS AND EVALUATIONS
Instrumentation
Electrical Strain Gages were bonded to selected rein
forcing bars prior to their placement in the forms. The
gages used in this test were Baldwin-Lima Hamilton A5-1S6,
FAP-50-12-S6, AS-9 and ES-9S gages. The A-5 and FAP-50
gages were temperature compensated for steel; the ES-9S
gages were temperature compensated for concrete. The gages
were mounted on bars ranging from #4 through #11 with the
ES-9S gages placed directly in concrete.
7
The bars were prepared by grinding the deformations off
of half the circumference of the bar for a length of four to
six inches. This area was then filed to remove surface
irregularities. Acetone was used to remove dirt and grease.
An epoxy and adhesive, formulated by the Texas Highway
Department Laboratories, was used to bond the gages to the
bars. This was a two component epoxy which was proportioned
on precise laboratory scales and stored in separate eight
ounce cups. The epoxy could then be field mixed with the
critical proportions needed for complete hardening.
Care was exercised in the handling of the gages to avoid
getting oil from the hands on the gages and breaking the
bond. The gage was glued to the bar and worked into place
carefully to avoid air pockets in the epoxy. The epoxy was
allowed to cure for 24 to 48 hours.
Four wire, 25 gauge cable was then soldered to the
8
gages using two leads to each gage wire. The ground wire
from the cable wag soldered to the reinforcing bar to facili
tate resistance to ground checks.
Di-jell wax was used to waterproof the gage and the
soldered joint. This wax was melted and applied by drops to
avoid air pockets.
The cables were epoxied to the reinforcing steel so that
forces applied to the cables would not be transmitted to the
delicate gage leads. A two component flexible epoxy, also
formulated by the Texas Highway Department Laboratories, was
applied over the area to protect the gage and soldered con
nection from mechanical damage.
Figure 5 shows the method of installation and protection
of gages. This method of installation did not prove entirely
satisfactory in protecting gages from mechanical damage
during steel and concrete placement. A number of gages were
damaged beyond repair. Also, the majority of the ES-9S gages
placed in the concrete were destroyed.
The installation of the strain gages was completed
several months before the actual construction of the
9
superstructure began. The gages were checked prior to the
beginning of construction and all bad gages were repaired or
replaced.
Lead cables were brought out of the superstructure at
the center column of each of the three interior bents. The
lead cables were taped to the reinforcing bars to minimize
possible damage from pouring and vibration.
Dummy or temperature compensating gages were mounted on
6" sections of reinforcing bars in the same manner as the
active gages. Extra coatings of flexible epoxy were applied
to the ends of these sections so that no stress would be
introduced through end bearing. These gages were then placed
as close as possible to their respective active gages so that
the temperature effect would be the same for both gages and
both lead wires.
The cables were brought down the columns into terminal
boxes strapped to the columns. The cables were soldered to
banana jacks mounted on a sheet of plexiglass. The ground
wires were shunted together to facilitate resistance to
ground tests.
Dynamic deflection measurements were accomplished with
devices consisting of cantilever arms clamped to the struc
ture and initially deflected by a wire attached to a fixed
10
ground reference {Figure 6} • Four strain gages were
attached to the arm to sense changes in deflection of the
arm. These assemblies were then calibrated to indicate
structure deflections. It was necessary to correct for
changes in the stress on the reference wire due to structure
movement.
Equipment for dynamic loading and for recording dynamic
strains and deflections was furnished and staffed by the
Bureau of Public Roads. Loading was accomplished with a
three axle truck which was equipped with instrumentation for
measuring dynamic axle loads. The physical dimensions of
the truck are shown in Figure 7. It could be loaded to ap
proximate either H15-S12 or H20-Sl6 loading.
The strain recording equipment had a capacity to
monitor over 50 strain gages and/or deflection indicators
simultaneously. Gage output was amplified to drive light
beam galvanometers which produced oscillographic records on
light sensitive paper. It was possible to adjust the ampli
fication and thereby control the amplitude of trace move
ments on the paper. This instrumentation was calibrated
periodically.
Dynamic Live Load Tests
The two-lane structure was divided into five test lanes.
Lanes 1 and 5 were along the east and west curbs re
spectively, with the tires of the truck approximately 8"
from the curbs. Lanes 2 and 4 were the regular traffic
lanes and Lane 3 was along the centerline of the structure
(Figure 1) .
The Bureau of Public Roads test truck made 620 test
passes over the five test lanes, each pass being called a
run. During these tests, six different sets of gages were
monitored. The runs for each set are referred to as a
series.
11
The loading for each series was constant, either H15-S12
or H20-S16. The speed and lanes were varied in each series.
Lanes 1 and 5 were used only for creep speed runs because of
their nearness to the curbs.
Test loading was done before the bridge approaches were
completed. Test runs were made downhill from north to south
over a temporary gravel fill, which appeared to cause exces_
sive bouncing of the truck. Severe impact was induced on 27
of the H20-S16 runs by placing ramps in the wheel paths
which elevated each axle and allowed it to drop 2" abruptly.
The impact ramps were alternately placed at the centerline
of the two middle spans, at the 0.6 point of the first span
and over each of the interior bents. Only one location was
used during anyone run.
12
Three air hoses were mounted perpendicular to the road
way at the beginning, center and end of the bridge to record
truck location on the oscillograph records. An event mark
was entered on the record as each axle passed over each hose.
These air hoses also actuated a digital time counter which
timed the passage of the truck to the nearest 1/1000 of a
second.
The lateral displacement of each run from the intended
test lane was measured by placing a series of pins at the be
ginning and end of the intended lane. An arm hanging from
the center of the truck tripped one of the pins as the truck
passed indicating lateral position of the truck.
Manual observations that were recorded for each run in
cluded time of day, truck speed, test lane, lateral displace
ment, and calibration data. Digital data reduction equipment
was used to transfer selected oscillographic trace readings
to punch cards. The oscillographic record rolls could be
mounted on the equipment and easily manipulated with the vari
able speed two directional chart drive. The setting of
vertical and horizontal indicators on a desired trace point
produced two analog outputs which were automatically con
verted to digital output and punched on cards along with
certain preset identification data. A computer program was
13
written to scale and convert digital trace readings to
stresses or deflections. The program output of stress or de
flection included tabulations by test runs and by individual
gages.
Dead Load and Time Dependent Deflections
Accurate levels were taken on the deck surface before
and after form removal and periodically thereafter to deter
mine initial dead load deflections and time dependent de
flections. The tenth points in each span were marked off
along five lines: the centerline, one foot from each curb
and the top of curb lines. Levels were taken at the same
points on each occasion.
Crack Width Measurements
Crack measurement was accomplished by use of a magni
fying comparator. This device is a microscopic viewer in
which lines of known width can be compared with cracks to
determine widths. By this method the crack width could be
measured to the nearest .001 inch at the point of measure
ment. Crack measurements were taken only at points of maxi
mum width. No measurements were made at points where edge
spalling of the crack had occurred since this was not con
sidered representative of the crack width below the surface.
The cracks were first marked by tracing each crack with
14
a felt marker. This trace followed the entire length of the
crack and was drawn as close to the crack as possible. This
permitted quick location and identification of each crack
and also enabled the crack pattern to be photographed.
Points of maximum-width were then located and marked so that
the same point would be measured each time. Measurement of
crack lengths was also made and a terminal reference mark
used so that crack extension would be readily visible.
The number system used to identify the cracks was sub
scripted so that primary, secondary and tertiary cracks could
be distinguished. primary cracks were marked before traffic
was placed on the bridge but after form release.
Secondary cracks were identified after a series of
"shake down" runs with an H1S and H20 truck. This included
some runs over the 2" impact ramps. Cracks were then marked
and measured at intervals during the test and after the last
run had been made.
Cracks were marked and measured on both top and bottom
of the slab in the negative moment area and on the bottom of
the girder in the positive moment area.
15
IV. DISCUSSION OF RESULTS
Dynamic Live Load Tests
Reinforcing Steel Stress. Significant results of live
load stress measurements are summarized in Tables 1 and 2.
Typical lateral distribution of stress level is shown in
Figures 8 through 11. The combination of stresses
(Figure 11) produced by test runs in lanes 2 and 4 most
nearly approximates design loading assumptions.
Maximum stresses occurred when the H20-S16 test truck
passed over the impact ramps. Even in this case, recorded
stresses combined with computed dead load stresses were less
than calculated values and less than the 30,000 psi value as
sumed for elastic design comparison. It should be noted
that the skew effect and the high concrete strengths would
produce a stiffer structure and that the design assumption
of cracked section was undoubtedly not present at all gages.
Deflections. Typical live load deflection measurements
are shown in Table 3. The effect of truck position on the
peak deflection of each girder is presented in Figures 12
through 17. The computed values shown on these figures were
determined by calculating the deflection due to one test
truck on one girder and distributing this effect to the
three girders in the average proportion of measured de
flections.
The accumulated effect of runs in Lanes 2 and 4 may be
seen in Figures 18 and 19. The skew effect and increased
concrete strength and modulus of elasticity (Ec observed =
5.5 x 106 ) contribute to reduction of deflections.
Impact and Vibration Characteristics. Measured impact
as indicated in Tables 4 and 5 was in general agreement
16
with values computed by A.A.S.H.O. design criteria although
it was highly inconsistent. This inconsistency can be
partly attributed to the oscillations of the test truck as
it came onto the structure. As was mentioned previously,
the approaches had not been completed at the time of testing
and a temporary gravel fill was used. The vibration fre
quency and peak double amplitude of vibration measured on
truck axles are presented in Tables 6 and 7.
The impact measurements in Lane 2 were consistently
high, which may be due to a rougher riding surface in that
area. There was no consistent trend of increased impact
with increase of speed. Speed had very little effect on
peak deflection, as may be seen in Figures 20 through 25.
No unusual vibration characteristics were revealed by
these tests. The forced frequency of vibration of the
structure ranged from 2.50 cps to 3.89 cps, as shown in
Table 8. The free vibration frequency was about 3.5 cps
for the interior spans.
The damping characteristics of the experimental struc-
17
ture were good. A log decrement of damping ranging from
.109 to .147 was observed. These values should be con
sidered as approximate since very low amplitudes were being
measured. The values of log decrement of damping given
above correspond to percentages of critical damping of 1.73%
i...;.td 2.33% respectively. This compares to a range of 1.4%
to 2.0% observed on the A.A.S.H.O. Road Test (Reference 2)
for conventionally reinforced concrete bridges.
Dead Load and Time Dependent Deflections
Deflections observed approximately two years after con
struction were less than the calculated values used in
setting construction camber. The calculated values were in
tuitively increased as described previously to adjust for re
duced reinforcing steel area. The adjusted calculation re
sulted in a predicted final interior span deflection of
0.234 ft., as compared to an observed value of 0.158 ft.
after two years. The observed increase in deflection from
April 1964 to June 1965 was 0.047 ft. Observed deflections
are presented in Figures 26 and 27.
18
As in live load tests, high concrete strengths and high
modul s of elasticity contributed to reduced deflections,
but it would appear that the effect of reduced steel per-
centage was overestimated in design calculations.
Crack width Measu~ements
The crack width study reported here is limited to the
negative moment area cracks only. The positive moment area
measurements were considered unreliable since the girders
were rubbed shortly after form removal. The cracks that did
reappear were not considered to be representative of the
actual crack pattern.
Observed crack widths were compared with theoretical
widths predicted by four crack width formulas. These formu-
las are given below:
(1) Watstein and Parsons with constants evaluated by
Clark (Reference 3)
W= 2.271110-8 h~d x p [fs-S6.6(i+ n >]
(2) Revised (1959) European Concrete Committee formula-
CEB (Reference 4)
(3) Jonsson, Osterman and Wastlund formula (for pure
bonding) 1 f 2/3
Wmox = KxD [*' xfs"]
(4) Kaar and Mattock formula (Reference 6)
W = 0,077 ~ fs x 10-6
Where: W = Average crack width (inches)
Wmax = Maximum crack width (inches)
h = OVerall depth (inches)
19
d = Compressive face to tensile steel (inches)
D = Bar diameter (inches)
p = As
Ac
fs = calculated steel stress (psi)
n = Es
p e
~
= As Ac (effective)
AC (effective) is the concrete surrounding the tensile bars having the same centroid as the tensile bars (usually = 2b x cover)
6 K2 = 47.5 x 10 for deformed bars
K = 0.23 for plain bars
K = .016 for deformed bars
Ic = Gross concrete moment of Inertia (in 4)
et = Distance from the neutral axis to the extreme fiber of the tension face (inches)
4D2 A = :r:rPe
20
The formulas of Watstein and Kaar are for average crack
width of the primary cracks, while the other two equations
are for the maximum crack width at any point. A factor of
1.5 was used to relate maximum to average values for purposes
of comparing the four equations. This factor was observed
by Hognestad for steel stresses of 30 to 40 Ksi (Refer-
ence 5). The dead load steel stresses here were not in this
range but no other data was found to correlate average and
maximum crack widths of lower steel stresses.
None of the formulas used gave a consistently reliable
picture of the average crack width. The formula of the
European Concrete Committee yielded the best values as it
consistently predicted wider crack widths than the other
formulas (Figures 29 through 31) •
The maximum crack widths were also closer to the CEB
formula. All formulas, however, gave low predictions of
maximum width. This is partly due to the presence of a live
load in the loading history of the bridge. None of the
formulas provide for the existence of short duration live
loads. However, even before the live load was applied, the
maximum theoretical widths were exceeded by 20 to 60 percent
of the observed cracks.
As can be seen from Figure 28, the formula of the CEB
21
yielded the lowest error. On the other hand, the formulas
of Watstein and Kaar have the lowest standard deviation of
error with .00122 and .00124 respectively. This compares
to the .00134 and .00138 in standard deviation of errors by
CEB and Jonssons· formulas.
Although attempts to predict crack width were not sat-
isfactory, the crack pattern and crack widths observed on
the structure indicate satisfactory performance. The maxi-
mum crack width observed after two years was .010 in. Only
two observations exceeded the European Concrete Committee
of .008 in. The average width after two years was .0055 in.
Average primary crack widths observed at various times are
tabulated below:
Date August, 1963 September, 1963 April, 1964 June, 1965
Bent 2 (#7 Bars)
.0037
.0041
.0031
.0062
Bent 3 (#9 Bars)
.0033
.0038
.0032
.0053
Bent 4 (#8 Bars)
.0046
.0046
.0025
.0049
The measurements in August 1963 were made before any traffic
had been placed on the structure. The measurements in
September 1963 were made a r all live load testing was
completed and the structure was opened to regular traffic.
As may be seen from the tabulation of crack widths a-
bove, the use of three different bar sizes did not show a
consistent trend as to their ability to control cracking.
22
Both the August and September 1963 readings yielded smaller
average crack widths in the area reinforced with #9 bars.
The last set of readings shows the largest crack width to be
in the area reinforced with #7 bars.
This is contrary to the performance demonstrated in a
number of laboratory tests which indicate that smaller bars
are superior in controlling crack widths. The final average
crack spacing for primary cracks was 1 1-6", 11-8" and 2'-0"
for Bents 2, 3 and 4 respectively. This is also contrary to
expectations.
Contributing factors to these discrepancies may include
variation in concrete quality and weather conditions, the
sequence of form release and the fact that most of the im
pact runs during live load testing were made on the first
two spans. It will also be noticed that the dead load de
flection of span 2 is greater than that in span 3 (Figure 2~.
The fact that forms were left in place longer than usual be
cause of unrelated construction scheduling factors may have
influenced crack formation. The concrete strengths were
high at the time of form release and this may have helped
to reduce crack width.
Observations of the control structure with regular rein
forcing steel revealed crack formation quite similar to that
on the test structure.
v. CONCLUSIONS
Based on the observations and data collected in this
study of a full scale experimental bridge constructed with
A-432 reinforcing steel, the following is concluded:
23
1. Measured live load stresses under overload conditions
indicate satisfactory working load performance. The
H15 designed structure was subjected to H20-S16
loading over impact ramps without causing excessive
stress.
2. Dead and live load deflections were smaller than
design predictions. This study indicates that the
reduced steel percentage resulting from the use of
high strength steel has little effect on deflections
in the working load range and that conventional
methods of calculating deflection are adequate.
3. Measured impact percentages were generally less than
A.A.S.H.O. design specification requirements.
4. Damping characteristics of the structure were good
and no unusual vibration characteristics were ob
served.
5. Observed crack pattern and widths indicate satis
factory performance.
6. Nothing in the observed behavior of this structure
24
, indicates unsatisfactory performance.
7. Cost experience on this project indicates consider-
able cost advantage in the use of high strength
steel in this type structure. An estimated 30 per-
cent reduction in reinforcing steel resulted. Some
reduction in concrete quantity was also possible due
to being able to reduce width of girder stems. The
contractor's unit price bid for A-432 steel was 9.8
cents per pound in place, which was the same as the
price for A15 steel. The cost of the structure in
place (excluding cost of drilled shafts, riprap,
railing and armour joints) was $4.32 per sq. ft.
The overall saving for the structure was estimated
at 10 percent.
APPENDIX
References
Figures and Tables
25
REFERENCES
1. Fountain, R. S. "High Strength Reinforcing Steel For Bridges," (Unpublished paper) •
26
2'. "Dynamic Studies of Bridges on the A.A.S.H.O. Road Test," Highway Research Board Special Report 71.
3. Clark, Arthur P. "Cracking in Reinforced Concrete Flexural Members." ACI Journal Vol. 27, No.8 (April 1956).
4. Gaston, J. R. and Hognestad, Eivind. "High Strength Bars As Concrete Reinforcement Part 3. Tests of Full Scale Roof Girder," PCA Journal Vol. 4, No.2, 10-23 (May 1962).
5. Hognestad, Eivind. IIHigh Strength Bars As Concrete Reinforcement, Part 2. Control of Flexural Cracking," Journal PCA Vol. 4, No.1, 46-63 (January 1962) •
6. Kaar, P. H. and Mattock, A. H. "High Strength Bars As Concrete Reinforcement, Part 4. Control of Cracking." Journal PCA, Vol. 5, No.1, 15-38 (January 1963) •
"\
:9 *' "C
S Id'e~ 1"
-..
E---------------
---:x--
--------
. -----
------
-----
--rr
--------------
------------
-------.~------
----
----
--.. -
--,r
---
----
-w --
----
--1
1--
--'"
"1--
-.,
---
----
---".-----~~----11-------~--
II
II
I,
\ tt
.1
~\.,
:. =-'=
'-:'::
: .. -:
..---
:: --i
f -:. :. -
,~-"::-'
:: :::. --
"i:.:
---..::
-:---:-
:. lr"::
-'::':: =
-t-=-=-
':::~;
:.= ..:: ::
=---.
.:-.::
-=-~~-------
-----....
~ .::-
~~ -::-
::. -::.::
. -::.-:
.-...::.
-I .. ---
-----
...... ---F
..... ---
--... --
------
---.... L
..--
----
\\.-
--.u
----
----
--.I
I---
---~ _
_ IL
_ _
_
-------
--
--
_ ....
_ -
__
__
__
__
u..
_ _
_ _
_ _
_ _
_ ..
_ _
_ _
_ _
... _
_ _
D _
__
__
__
__
__
__
__
__
_ ..
-_
__
-U
-_
__
__
__
__
__
_
._---_
._ .. _....
. ._ ..
_ ....
... _
-_
._._
..........
.... _
--_
.
.-
~2'
• .-
fS!.
o
88
'-0
' 8
S'-
0"
5S:'o~
PLA
N
VIE
W
rA
[I
t ,u
... --"
---"--"y
-----u-
uC-__
__ ~-~-:~~-----m--y-m-
l
BR
IDG
E
EL
EV
AT
ION
Test
Lan
es
1 2
3 4
2. q
. 'IR
OA
DIY
-,\Y
"C1)
.1
~ .....
......... "
.... ~
... ~ . .,-...
.. if
f·
" ~
·:::: .. ~ .. t
~ ... ' ..
~ .....
'~:.~.
.; .... ~.;
.,. ....
.. ;. ~
"t
&M
4'f
lAM
I z-.~
I :
S'-
/o-l
' SH
t. ~i",
•
SE
CT
ION
A-A
Fig
ure
1
STR
UC
TU
RE
LA
YO
UT
tv
-..J
.•. i
~'-
~?:~t1"~~~_~~.
HA
Lf'
P
LA
N
.. w
ilh
U
, s.
"."
M
?' 3
1.t1
b.
1 C~
uinu
ou.1
~~_L ~
::::p
=
##
"
Iii IJ"~ _
__
_ .~
.J
. A
rE,.
!"
1"'
~/'-<!l-
.6.or~!!,,~
:!, ..
i....t/
P..J
.19
:4"
.6..
:i;r
.!lU
:f_
~ ~
"1'''-
I ~~'l"M'.~~-".-"
-,-!
-•
.,-.
, -l-
ifN
i' Z;~:
m.
. :W
a: -E
li -I
.,_
*_
_ L
---I
Sfin
vpL!
N.w
-!J£
f~1'1
~""t
.r-(
}"·e
'-o·
2tJ~.h#"·~~':t!"
. I",~.ter..o~d;o~ i'r
.(~,
;?-.
~;~'~"l 14~rD""()*""I!I~()"
i!O~~. ""
'-'''''
-'(1*
.,.2
!l"'"
,:oo
I1lJ
3 "'0
/1,,
,°
AI>
/P:
"~.ti0n3 :J
},o,.."
fbr
It'J
c,I
t'W
<:¥
'Jdj
0/
kJ"8
1IU
dl,
..,1
"/H
!'I'
" h
olt
cm
"" Jl
irt:
1i.'!
'n J
/1N
!'""
""",
,,,,
,d ~ t
d'
8ir
dt!
n;
.tIf
ind.
e'7f
Cf~
tiff'
.Jim
il",.
Nr.
J I'
ml a
? "
"llh
Ifp
erp
IMd
rcu
/#r I.~
'-o
Fl"
"'d
tt'n
. ff
!ltct
rpfiJ
wr.
l F~""
~£h6
N"1/
!' loc8"a~-"'rlV)'I¥"4'CfI'O'Nt"AbtJh"U"'J/""'ck ... lt.
HA
LF
lO
MG
ITU
DIN
Al
SE
CT
ION
T
HR
U t
OF
GIR
D€
R
~,uiOn..t jJ
l}o
w"
l'o
r/Q
C.N
"6
(,!,1'J
d..J
01
' la
n,;
lr.1
dm
.lil
l .,l
tt ..
1 ;~
.Jk
Jh ~ m
ftJd
UlH
'lf'd
"t:'I/m
Ilk!
C D
I.JA
tr ..
. .d
di8
lJvm
., Jnt~
SU
I'ptN
'foll.
/)J
f7)tf
!'nJi
teuu
J/J
ow
n 'tlr
kIC
""m
8 S
nrn
"p
&n
£ l
fH'Wrme'estJti'Y"d8/~8 t
01'
dJrd
(!/!
r, <
!In
ti 6
tItr
.s£
61
rr p
/.s1
ctf
d ptfrp~hdlculliN" I'D
' 01' 8~~
~'''~~~~
t ~
2 ~
~ :
~ ~
: ~~l
li ~
~ 'a
:'II "
<:! Q
~
:::
:l ~
::? <>
<s
~~
'>11
"'I
<:>1
<>l
<>1
al ~_
"'I
Sj
<S
<:I
<:I
<l _
_ <:I
'"
>
<S
~
, •
t --r---l
f f
tii
'&-4
-
I '" ., ~~
No
I .. :
ND
p<
IIIr
l 0
1 lI
Nt' Idl,s~worA ~h."IJ ~NI"""",edli,JlfJ/il",lIo'
lhe
Ct:
IhC
rttl
. ,:
nIM
rJn
il/u
;S /
;of!!
'tfn
pO
UJ"
Wd
8h
d c~~
TE
XA
S
HIG
HW
AY
O
EP
,lR
TM
EN
T
28
6'-
0"
CO
NC
, G
IRD
ER
U
NIT
55
'-88
'-8
8-
55
' 2
4'-
0"
RO
AD
WA
Y
18"
CU
RB
S
3cf
22
' RT.
FRW
D. S
KE
W
OLD
H
WY
, 2
PO
UR
S
EO
UE
NC
E
I\.)
M
'>n
: Fu
ce
'orm
.s.
6IC
fju
.J'I
l'crm
trl
f!rr
/flfl
l'/(J
I').
61/1
0111
Ib
r d
/!'l'h
fClitl
n ~ 1
0
w4'
:"18
"1 o
f co
ncrt
rltr
.g
nd
r"'J4
!! fll
fOl'I
c Jt
f!II
JtrM
~nl.
_
_ ..
. 00
.£11
10
£9
'"''
JpIK
:<'_
'~':
:_fi
.~_
:,"-
';f'
$f
~:.,
. ~e
DE
AD
L
OA
D
D£
rLE
CT
ION
D
IAG
RA
M
9 H
ILL
""
..
. 1.
Fig
ure
2
STR
UC
TU
RE
D
ET
AIL
S
---<
>
---
---<
-,_
"
:i!!!,
" .. '
-rC~--
,~~
~L~s...~l __
_ _
____
._
, _
__
~[9.!
!~/~<I
!c'.~ .
. K,{~.
. ~ 5
EguJ
il/~
c~~
-__
_ . __
__
~"".tL_.
___ •.
--
. _
_ <i-"
". --
'':;''''
'''".1
>"->
1?'-
iJ" r~~
'!#
1:.:
l.~
.~-t:r._
:<-:0
'---1
r 1r ""
_. ./
:.';'-"'''
t R
d_
",
".,,$
D
1It
N'/
Al1
{h_
nJ;o
,u
~o-;.
.
~~---~
• H
AL
F'
LO
UG
ITU
Oll
J'.l
S
fCT
-Otl
'!
11
hU
t
Of
G1R:>~
J:;: J
.':V
""M
•• /~ItdwY.
CH
ON
N D
'AG
RA
AI;
,'::
;nn/
'CU
"tJU
lol
(~ C
,.,,
,,II
C
on
I'fH
"'tV
IoR
d",
!/ C
NW
i,
't'''''
~J
f!t
Jh
M
Q
$"
4t
6b
~
At
JI:
L't
~J
.::10
.\~ iti
:A ~
/ A
ft
A
4.t .. ~ .
At
f.:r
1 .~
I Jh
/.,'
::'
L 1
..3
l
AS"
-' I
' ... 't
a-
II
M
l II
I ~. A,
;/~ 6
,\E
l ~ !
A'
hi
I;t
:J::
Jli .
.. : ~\
~
,,_
__
•
,. PI
A::
L Ii:
!..
M (i
C
Or
Qt
-. ,1
/(1_
' J;!
. 0
i..
_ it
...
,..r
SE
CT
ION
A
T
SU
PP
OR
T ®
S
EC
TIO
N
AT
SU
PP
OR
T@
cJ!I
"''''
"""
eR
';"'!!
. r C
-f_
"",,
.Rd
""l C
""""
.
D
0 /
M
IM~
,-~
l¥o.::ll.LIIII~/J~L
,SE
CT
ION
AT
SU
PP
OR
T @
lj I
. ~'O
".
I ....
. ~1r~i"""
~~Sl
C
~t'L
H'Pt
J_
CU
RB
D
ET
AIl
.
fCd.
OE
TA
ILS
A
T
AB
uT
ME
NT
IN
TE
R lO
R
OlA
f R
AIo
l S
EC
_ S
EC
. A
T
SU
PP
OR
T
Fig
ure
3
STR
UC
TU
RE
D
ET
AIL
S
~~tJ
~.:~ ~~
;~r.q .. Z
~;~~!~
it.
"!':"
,t! ::
::-.
ft,-
r>'J
0/ :
0I.J
~'",
:.
."f'-IIU/..-.:."~;;t1"
~ ...
r r
_ .... 1
0'_ ...
/'<1"
/:...,
~.-t
~ ~, ••
t'
TE
XA
S
H'G
HW
AY
D
EP
AR
TM
E"T
28
6'·
0"
CO
NC
G
IRD
ER
U
NIT
5
5'·
8S"
8S"
55~
24
"0·
RO
AD
WA
Y
IS"
CU
RB
S
30
' 22
'RT
. F
RW
D.':
:'KE
W
OLD
H
WY
. 2
•• '4
1~7T
2. rl
li£
f
IV
\.0
{JA
KS
f',_
it..n '':''U .M
::.
t:A
NJ1
, ¥
. (;"
r-
--~:
--,
1#
0
C1
..
. "
a:C
l4lr
~!
:J "
IJ
AR
J ~
10-
r;-
lf~
t'f;J:i
>"!
,/~,~
q L*
JAR
S14
..
.. he
'~'-'
t;~/-'
2"
it"
BIL
L O
F
RE
IN
FO
RC
ING
S
TE
EL
~I
(FO
R
ON
E C
OL
IJM
NI
~,
I 'fl' ~ f
ib.
'Jir
,p be
",,;;;
'*'I
Ihi'
~I --.
• ,
)(
• "'i
,,: ""o
r ~''
'J
~~
_ 1'---
-,1
10
0-1 1 Y
! I
-3
~1;.i
tS 0
"
~~
~
I lSI
1",
~ 'j
1/
.$ (
r
aO
~'
1 <i.
&
"Z lI
R~ml
'(vc
~J1
SI""
;:,
LbL
! ~~'tJ
e.. -t
CC
l'Jd.
Jt.
ela
S;!
A c...dl'K·~ft_Cv.~t!J
BIL
L
OF
RE
INF
OR
CIN
G
ST
EE
L
Bil
L O
F R
EIN
FO
RC
ING
S
TE
EL
" .. -: ~~Jl~~ .. f'
h :W
e:~.
h .•
~ ,1
"9"'-J
"ii
i)
::-r
" ':
'~,,
-w,;
+_-~
?j
" __
.",
,I-'
(iii;"
IA-4
32
1
/3AR!JAtA/~
"~RJr"
1£
""
PS
T,,
b
AR
:JU
t ...
. ~~
:: _
ad
d4
7.t
5/b
s
¢e
l.l"j
l'or.
"'In
a ,
s1'fH
'/6In
d
~ '~_~~' -
P;:
:rlin
eg
r l'
ocI
Qih
imfl
l"""
OiI
fIN
"H;K
i<f
• •
,t/!?_,?~
;; -, "
;-;:1
... --
.:334
.~
_"'lo
!-1;
0' '" ..
":~~ ~ ~_-=~ .. a,
tfC
y:Y
d..
:r.
ul'C
on
crl/
!'lf
/If.
t"" ~
Rvb
ber
l'Jon
cl '1"
l8 (,
/ 9'
" ,.
. ~.
C""
"""I
rir
I,{,
"'_
._'''~
iii4
j~
,,!
bA
RJ e
( I!
, ...
.... '"
",' .
...., ~I
~~~~!
'.sl -.~~ &
N-:
tX
'':', ~j-
l,~"lj
.m y
...L.--",~_.
&"Z
'(:
'j] ~~~'.
~ '!
6A
RS
C"'
9
/JA
RJD
:i ~1
't1i
i111
"W'1
') f
op
Cb
ol1
bm
1
3A
RS
Y
:> -~'hl
f[f
2 r
:f :~L
.;~~:-
_f:; c~~
: ....
: -t
~)i I ~.
::->
-C
on
st.J
f.
Nca
pre
nl
ro~,I/!''''
Ho
tfIf
'Jn
eJ"
j"'
Th
lel«
.3 '. ~ ~ t;
;,---.:;'::~
e m
m. '"
,C d
41
!/.f
utO
N' b
t!in
8 ~
~ ~ ~ I ::;;-:
:: , . N
. __
(>#
ds ~ h
..,1
t ..
. in
pI.>
ot!
~ t:
~ t
~ ::~"~ I
di;
,.'*
urb
ed
hV
plo
£i4
8 J
up
«r-
)~y;r,m
.""'"
t ....
: <3
.... ~
_ .. 7"
:.~ ~
.31,.".c/~ '
ON
hS
c:
r C4ntC,.'tlft~
",,,:,,
'. j
J ..,r
t:".
~ ,.
':'!-.-
--'"
--
' P
tnvt
Hu
b""
,. &
,n.:
lihA
C'ftf
1ttI!
'nI'
-r:=M~=S
To
D;(!
i"d
u;;
ll<
d i
n lb
e (
C.n
-In
SU
C'h
.. )
ifIl
l/lu
ll Cj)'~
/3A1
?.J1
. !r
ae
l (.
Init
Pri
c#
! lJ
id p
er
Su
rl'#
C1
II w
il' '
10
1 b
it ."'.
,.".,
. //
nC
-d'
foo
l 01
' Dri
lltJ
d S
hil
l,.
.,; ..
. '':'
;t",
;
r·-::
/kit
!!: N
o d
irfA
Cl"
p.iil
ymen
l..;1
f,(,1
I be
/7't
IIdI!-
l'orHuhb~r tJo"~/n, C~cent; £,~
J()J
I"It
M6
"'~r
;";'
l.
or Neopr~l}e
P<
I1:6
; 0
,,1
.$1
18
11
be
i"clu
d,u
l in
1M
Cw
w""
Un
N P
,.ic
tT b
id 1
'01
" CI
8.:J
.!1 A
C<mc:rt!'#~
""R
SA
lI'
TY
PIC
AL
C
OL
UM
N
DE
TA
IL
",-"
-'t:.
lfii-
'_
t ~1{:
tt:.·_
~f#..r
.J!I.~
~;:
.,Jtpt
m .b
! C
.II Jt"
,..,
II· ...
... tw
o c~ ..
.Ioin
13
r---
-1'O
!:?-
~ __
_ +~~
O:""
,lt'
c';'
" _.
___ -
:6()~Q·. __
__ ~,,;
~.CtI'pl"'"
"ho,
.·1'1
--;;,.~~-,,!
~:
No
k -* -.6Jro~lI8"&vM:,~", ..
....
~/.'.i1t1.
.ld:o~
r'i'
7;~-
---;
,;.-
j .
~ --.-
--'"
.~~
---.
::;:
'::!
/j
AR
,sG
,
.... ':ll
"ti
ll-?-
/JA
RJF
c;
-lk
nf
. ~-
.Jy.7J
hJ_
<8/
;1.
t. M
-/~.
"",11"
1,:0
-, ~aN
"4""
• rS"~---=--7liJ
E_"""Ha..:;~), -
'1,;1
.
~.
.-,-
--_
. T
'''''
~.
:~---
.r!
Ti-'
'''N
~-I
"j4~
'M
" ,..
..,'-.
-::-v
-'"
_'~'/J!"'~
i ",
,'.7
' •
.sle
p!ll
' C~~I»J 10
HdW~
O-OWJ
'l~ ~~---
.. eA
"'-I
J,
. . -.
---~~~~.;
-~i
;,..
~,
t.;;
_,_~
·L_.
_.,.
.. '"
**
_~-
'",T~
/JA
RJG
,
j '~: ~~
l -f
tI(J
AM
I •• dJ_
J •
_
__
/-'':
1=
. ~
:=:::r:
.3: lt
d'
\sI:b~-~ ~~~" .~
,
I --. '_
. _
_ ~"'~
E""'
t""'
H"""
·1 i
f!i,
r,; Sp..K~.J a
2:0
"· :l
E'"
I(
_ ~:o"
~
tsb1ii1<'~,J ,
.4:0
"·/
0:0
· __
__
~1..."'fi'.
----
":!.
.~'£
.._-
,..
~ .. _~~, .. d$
.:.'
,~
1IA
LF
£
t£If
,AT
ION
----~,3
/jA~JoI,
l~1~
~~"t_""I~"
--~
t:. L.
,:,r
.,.~.:
,,/)
r ---"'/':i~
V
aA
RJ C~
No
",_
' T
bI!
'Arm
(;W
"t'$
IW
-# c
om
p/.
,hI jcinl'.,....~
cfA
I '0
CI"C"'''~
sh
ell b
it _'t:h~d f
tI.r
r"
(Mf/'~ M
.ff:
hrd
~s
bQ
N""
d '0
8""-1
" J
b,o
sh
ip", .
. ,,1
.
OE
TA
ILl>
O
F P
LA
T(
fOR
AR
MO
R
JOIN
T
Fig
ure
4
STR
UC
TU
RE
D
ET
AIL
S
GE
NE
RA
L N
OT
ES
; 0e~'1n:
HI5
l('-
Qd
i",
ill
octo
'''O
"(1
t _
ith
A.A
.S.t
t.O
. 1
95
7 S
h'.
do
...
S
pec",c
o.i
OIl
S.
An
CO
llcre
te
,hell
b
e e
fo'S
.. A
. C
ho
mfe
, oU
1
t1l9
0se
" co
ra_
e,.
, lI
4"u
nte
'"
Olh
e' _i
i,.
no
ted
. A
ll co
ncrel
.. _
".U
reeeh
e "
0
1".
,p"
t S
.rfo
ce
Fin
' ...
..
R"b
be,
8o
nd
in9
C
It.
en
' ,h
olt
b
e
Ou
tc.
ar.a
ct.
I ......
to(.
I ..
...
II b
, Jo
hn
"" ..
on
vil
le
0'"
o
l)p
rov
e" e."ol~
Aft
dj
irre
.-:
"io
n"
.. e1
oti
n9
10
re
t"fo
f'cin
fl
ate
e'
.r.
to
c ..
.. ~
Ie,.
"
o'
bo
t".
Po
ym
en
, fo
r t~i""O,.ci""
"'e
el
tho
r i"
,e
q"i .
. e"
to co
n'o
,mto
A
$i .
. O
es.i
,nah
on
'&
-4'2
,h
OIl
b
e
mo
lle
un
tl ..
. th
e b
i4 •
•••
Rei
....
SII
(A-4
32
1.
Av
tro
ge
co
'cu
lOle
d
foo
tift
9
p'r
e$
su
t.:
10
-Dt'U~6
Sh
oll
.:
24
.2
To
ns/
SQ
,fI,
T
f"A
S
HIG
HW
AY
D
EP
AR
TM
£N
T
28
6'-
0"
CO
r-.C
6
'lRD
ER
U
NIT
5
5'-
88
'-8
8'"
55
' 2
.("0
· R
OA
DW
AY
18
" C
UR
BS
3
d'2
2' R
T.
FRW
D,
SK
EW
O
LD
1fW
Y.
2
O"1
"C
iif4"it
1 •
13
5--
4(5
i).J
40
4
tI-4
"
~
,00
w
o
31
DI- JELL WAX GAUGE WIRE
FLEXIBLE EPOXY 4 CONDUCTOR CABLE
STRAIN GAGE -----,V'1'7?
\ \
/
Figure 5 STRAIN GAGE INSTALLATION
CONCRE TE GIRD rR CLAMP
. ,:_ ";" . t"~: .. ~'.~
GROUND WIRE
LEVE LING SCREW
I STRAIN GAGES ! L--CANTILEVER ARM
---'~,;--'--'!r--
GROUND REFE RENCE WEIGHT
Figure 6 DEFLECTION GAGE
C-+
-)
'~I I
C £
J
I
12
0.+
'
;/1
5-5
12
9.
821'
( 2
3.8
0"
32
.91
3 ....
fl
20
-5
/6
10
.27
' .oc
Fig
ure
7
AX
LE
LOA
DS
AN
D
WH
EEL
SPA
CIN
GS
21[
i)
( 4
-
( --
)
i24;
~O""
] A
XLE
LO
AD
S 2
9. 9~'"
W
N
LO
AD
ING
H1
5-S
12
H2
0-S
16
EA
ST
GIR
DE
R
SPE
ED
LA
NE
2 D
:AN
E 3
5 2
69
0
19
35
10
2
86
8
21
51
----
15
1
88
7
14
71
20
19
82
1
46
0
25
32
17
2
39
8
5 3
70
5
26
36
10
3
87
0
27
61
t-
---
15
3
82
3
29
26
20
43
18
3
04
4
---
---
25
43
42
3
32
8
IMPA
CT
5
95
0*
5
20
2*
TA
BL
E
1
ST
EE
L
STR
ESS
(P
SI)
IN
B
OTT
OM
O
F G
IRD
ER
S C
EN
TE
R
OF
SPA
N
2
SPA
N
2 W
EST
GIR
DE
R
LAN
E 4
LAN
E 2
&
4 LA
NE
2 LA
NE
3
13
57
4
04
7
--
10
56
3
92
4
--
--
-----
11
16
3
00
3
--
---
12
46
3
22
8
--
----- 17
81
4
99
8
--
19
24
5~29
27
90
1
11
4
21
71
6
04
1
27
90
3
77
1
-----
-----
23
12
6
13
5
27
91
3
30
6
22
89
6
60
7
7.91
9 3
58
5
24
54
6
79
7
--
41
69
*
10
11
9*
-
-
*Im
pact
bo
ard
s in
cen
ter
of
Sp
an
2
SPA
N
2
LAN
E 4
- - - - -
46
B7
45
34
45
30
47
23
-
70
74
*
LA
NE
2
&4
- .... - - -
~41~
73
24
73
21
76
42
- -
I
w
w
LO
AD
ING
H1
5-S
12
H2
0-S
16
TA
BL
E
2
ST
EE
L
ST
RE
SS
(P
SI)
IN
B
OTT
OM
O
F C
EN
TE
R
GIR
DE
R
SPA
N
4
CE
NT
ER
G
IRD
ER
SP
AN
4
SPE
ED
LA
NE
2 LA
NE
3 LA
NE
4 LA
NE
2 &
4
5 2
23
1
25
49
2
23
1
44
62
10
1
83
9
25
65
2
62
9
44
68
15
2
43
7
28
03
2
58
7
50
24
20
--
--
25
20
48
2
40
2
22
00
41
.48
5 2
96
1
34
35
3
12
5
60
86
10
2
87
9
34
28
3
19
5
60
74
---------------
15
3
11
2
35
28
3
47
8
65
90
20
27
46
3
42
8
29
79
5
7
25
28
45
3
52
8
32
11
---
IMPA
C'I
--
-I
w ~
60
00
50
00
I:
-'-
_
f.'f
IP--
-1
'---
::--
40
00
- H U,l
tlt
30
00
U
,l
U,l
A
VER
AG
E PE
AK
L
I Il:1
~
8 CI.l
STR
ESS
",N
B
OTT
O
LAN
E 2
20
00
H
20
-S1
6
10
00
o
--------~
--
=-=-
==-::
::.. -=
-.,-.=
f---
----
--~
"'--.:
::::::::
:: f----
__
_ -
<
,,', "'
-----..,
I----, ~~ .. "'
~~~ "-
~ ~~
~,
'''--..:::
:: 1'-....
.... ....
TE
LOA
D
TE
EL
~
1 O
F G
IRl )
ER
S SP
AN
3
.~
LOA
DIN
G
nt t
,· ... T
ruck
P
osit
ion
Fig
ure
8
STR
ESS
D
IST
RIB
UT
ION
p ~~
._
--
---4
5
MP
H
--
--
--
-0 1
0 M
PH
----0
15
MPH
-
----9
20
M
PH
---~25
MPH
-
---
---I
I IM
PAC
T
w
U1
60
00
50
00
40
00
- H CI)
A
I '-
"
CI)
3
00
0
CI)
~ 8 CI)
20
00
10
00
o
--~----
-1
---
----
-----
----
--
~ ~,
---/'~
..-.."
. ... -,
"---~
/'
----
::;
/'/'// ....
.."..
.--~ ~
" --
-~..-
~;>
-~
" ,,~
/'
---..-
/'
r:~/
t:::_-_
'-
~
~
:'P
--"
r--:...~
~\------------
.----~~ bb
--
-~ .. -
-------,-
-----
_._-
----
--.. -
-----,
--1
----
---
------
AV
ERA
GE
PEA
K
LI
TE
LOA
D
,TE
EL
ST
RES
S IN
B
OTT
OM
DF
G
IRD
E ~S
SPA
N 3
LA
NE
3
H2
0-S
16
L
OA
DIN
G
i-·
---.-
--
~I
* l
+ !
I P
U
U
U
A
5 M
PH
----
---0
10
MPH
----0
15
M
PH
Fig
ure
9
ST
RE
SS
D
IST
RIB
UT
ION
-
----
P 2
0 M
PH
---~ 25
M
PH
----
--p
IMPA
CT
w
(j
\
- H CIl ~
60
50
40
-3
0
CIl
CIl ~ 8 CIl
20
10
OC
O(
Ol rr
OJ
Ol
0
~~
--
..:::
r.----
-"
~
~--~ c..-
=. --
--:l~
~
Y
~---~ -
---
....... --
~
A
--~ f
/-
7_
........
--~ ~'-
AV
E RA
G 1
PEA
K
LI V
E LO
AD
~,
--,,-'
ST
EE
L
t;I
.,.,
/.,.
,'
ST
RE
SS
IN
B
OT
Te
M O
F G
IR D
ER
S LA
NE
4 SP
AN
3
c _
__
'
H2
0-S
16
~OADING
--
--
c:::;
! l
* J
P
, ---A
5
MPH
------~ 1
0 M
PH
----0
15
MPH
-
----
p 2
0
MPH
---~ 2
5
MPH
F
igu
re
10
S
TR
ES
S
DIS
TR
IBU
TIO
N
--
--
---j
f IM
PAC
T
W
-....I
12
00
0
10
00
0
80
00
H
U)
~
"-'
60
00
U
) U
)
rLl
P:::
E-t
U)
40
00
20
00
--1
--------
-----
--_
.-.-._
--
----_
. --
---
---
...-
~ ~
...-~
.e:::: b
:-:;;-
. -----~ ------~~
~
,..---
:::::.
-;.::. ~
_.-.
.....;
~-
~
-~ ~-::~
'---":
:: .....
........ '-
....."
-. -.
.I'-
'-""
'I P
' ,,~~
--._
----
----
-_
.-----------
--------------------
----
--
.. -
----
----
--.
-----------
.
AC
CU
MU
L \T
ED-r
,Iv. ~-
LO
AD
--------
STE
EL
S
"RE
SS
SP ~
3 TW
O
LAN
. ~S
LOA
DED
H
20
-S1
6
LO
AD
ING
----~-------
. --
--------
-
~I
II
! I
!!
~ l
Ip
U
U
U
AS
M
PH
----
---0
1
0
MPH
-----0
15
M
PH
Fig
ure
11
ST
RE
SS
DIS
TR
IBU
TIO
N
---
----
P 2
0 M
PH
---~ 25
M
PH
---
----
-P I
MPA
CT
w
(Xl
LO
AD
ING
SP
EE
D
5
10
H
15
-S1
2
15
20
25 5
10
H2
0_
S1
6
15
20
25
Imp
act
TA
BL
E
3
DE
FLE
CT
ION
O
F C
EN
TE
R
GIR
DE
R (
INC
HE
S)
span
3
LAN
E 2
LAN
E 3
LAN
E 4
LAN
E 2
+ 4
.24
8
.25
7
.26
5
.51
3
.30
2
.36
0
.36
0
.66
2
.29
5
.28
9
.28
2
.57
7
--~.
--
-
.30
0
.30
2
.28
7
.58
7
.35
6
.37
2
.36
3
.71
9
--
.39
5
.38
6
.36
9
.76
4
-----
--
.37
6
.38
5
.38
2
.75
8
.39
9
.39
2
.38
9
.78
8
.36
2
.38
2
.39
5
.76
7
1---
---
---
-.8
08
*
L.
-.8
16
*
-.7
43
*
-1.5
51
*Im
pact
bo
ard
s in
cen
ter
of
span
2
Sp
an
4
LAN
E 2
LAN
E 3
LAN
E 4
.08
6
.09
6
.08
7
--
.09
2
.09
9
.09
9
.09
7
.11
0
.10
4
.09
0
.09
2
.11
3
.09
4
.09
9
.10
1
--
----
--
-.1
41
.1
74
.1
47
---
.13
6
.16
2
.14
9
.14
7
.11
0
.11
1
--
-
LAN
E 2
+ 4
.17
3
.19
1
.20
1
.20
3
.19
5
.28
8
.28
5
.25
8 ~-.-.-
w
\.0
0. t:j
0.7
-U) 0.
6 rz:
l :r: ~ H
...... ~
0.5 -.
H
E-!
U
rz:l
..:l ~
OA
rz:l
Cl
0.3
0.2
I 1
I
PEA
K
DE
rLE
CT
ION
L
AN
E
4 SP
AN
2
H2
0-S
16
LO
AD
ING
-~
f..-
----i-
---
~----
"./
V
~
"."
. .... /
.... ".
~
"./
~
"' ....
JI'
f-----------
IV
~ ~
-~
----
--..
.-?
--::
~-:
...:
j
~
-----
~ r-.-
::-.:-.:--
:: :..----
-;:::...
.:::; --
-::.-=
=--
......
~--~
7~~
/'"
..------
-,.----
--.....
.....
--,: ....
/'~~ ~
..,.-/
d ~ ...
----J ~~
~ ----
i 1
t t
Fig
ure
1
2
DE
FL
EC
TIO
N
DIS
TR
IBU
TIO
N
Co
mp
ute
d
,;
,
Tru
ck
P
osit
ion
I
J I 5
MPH
--
----
-0 1
0
MPH
----0
15
M
PH
--
---
--P
20
M
PH
---~ 2
5
MPH
----~ I
MPA
Ccr
+=
"'" o
us
O.
........ r.n
O.
I"il :r: o z H 5
o. H
E-
! o I"il H ~
~
0"
0.
0. 7 5 5f-
--
!± 3 ~ ..
PE
AK
D
F
LE
CT
IO
LA
NE
3
SP
AN
2
H2
O-5
1 I>
L
OA
DIN
Ii
---------
~--
-------
----
-t---
-_
__
t---
__
~
, It---
---~
--.....
,
-----~-
_. -
------
_. --
' .
~
-+
•.
....
-
~
-
---
--.
--~.-.---".-
::=
-:;..:-~
.--
~-~
=---
~---..,
~ .
::;;-;
-?: ~-
...c;
:;:...
;. ~-
---:::
:--::-
-'
~~~~
---
---;
~.
r-_
_ ~
~-
I ~
~--
I-
.........,
._
. --
---.
-
L!
! !
[==J
LJ
U ~
A
5 M
PH
-----
--0
1
0
MPH
----0
15
M
PH
-----)1
20
M
PH
Fig
ure
1
3
DE
FL
EC
TIO
N
DIS
TR
IBU
TIO
N
---
42
5
MPH
----
-}f I
MP
AC
T
J:>.
I-'
0.8
0.7
-tJ) 0.6
ILl ::r: ()
z H
....... z
0.5
0 H
8 ()
ILl
H ~
ILl
0.4
CI
0.3
0.2
PEA
K
DE
FL
EC
T
ON
LA
NE
2 SP
AN
2
H2
0-S
6
LO
AD
H G
~'------
-----. -
----j ~--
-----
- -----
-1---
- -~ ...
I-~-
---
--
~ ~
~---------
-'l
Co
mp
ute
d
s~--
~-.
~
'----~~
--_
_
oj
--.
------"
':.::::..:
:::. ----:
: .::::...
: r=:.-
""""
----~
'-------
----:
::;-
~--~
~
--..
....
..
r-------
---.
-.-
~I
!!
~~
Ip
U
U
U
A
S
MPH
------~ 1
0
MPH
-----0
15
M
PH
----P
20
M
PH
Fig
ure
1
4
DE
FL
EC
TIO
N
DIS
TR
IBU
TIO
N
---~ 2
5
MP
H
----
--jf
IMPA
CT
,j::
>.
N
0.6
0.5
---
-o.
00
l
/il ::t: ~ H
- Z
0.3
0 H
8 U
/i
l H
~
0.2
/i
l Q
t$
<:L<
0
.1
o
I l
PEA
K
DE
FLE
CT
O
N
LAN
E 4
SPA
N
1 H
20
-8
16
LO
A D
ING
....
. f--
....
...
~
~
~
11
-,-
.-----r-
----
----
----
---
------;
--
-~~
l 1
t t
Fig
ure
1
5
DE
FL
EC
TIO
N
DIS
TR
IBU
TIO
N
.. -
rom
pu
tec
I I
---4
5
MPH
------~ 1
0 M
PH
----0
15
MPH
-
----
-P 2
0
MPH
--'
:!. 2
5
MPH
-
---
---I
f IM
PAC
T
,Jl.
LV
0.6
0.5
- til 0
.4
rx:I
II:
()
Z
H - Z
0.3
0 H
E-
t ()
rx:I
,..::t ~
0.2
rx:
I Q
L 0
.1
o
-----
--
PE
AK
D
E P
LE
CT
ION
L
AN
E
3 S
PA
N
1 H
20
-S1
6
LO
AD
ING
-
I
---
--
po--
l--
---
-! ~-
--~
compute~
--
- --
--
D
--
-=...
:::::
-:::...
..;
------
--
~
t +
.!
Ip
L
J L
J L
J ---A
5
MPH
-----
--0
1
0
MPH
----0
15
MPH
-
----
P 2
0
MPH
Fig
ure
16
D
EF
LE
CT
ION
D
IST
RIB
UT
ION
-
--
--'t!.
25
M
PH
---
--If
IMP
AC
T
~ ~
0.6
0.5
(fJ
0.4
~
tt: ~ H
- Z
0.3
0 H
E-t
U ~
H ~
0.2
~
Q
0.1
o
----
~--
----- PE
AK
D
FL
EC
TIO
LA
NE
2 SP
AN
1
H2
0-S
]1 L
OA
DIN
G
....
~ -
Ib
I --
r---::
---_
-
---~
~
-----~ ~
-- --~
f~---
---
Co
mp
ut 9
d -- ---~ ~
----_
._
-
~I
! J
i !
I r
U
U
U
AS
Fig
ure
1
7
DE
FLE
CT
ION
D
IST
RIB
UT
ION
-----
--0
1
0
MPH
M
PH
----0
15
M
PH
---
----P
20
MPH
---~ 2
5
MPH
-
--
---
--If
IM
PAC
T
,j:>.
(J
I
- Cf.l J:x:I :r:: ~ H - Z
0 H 8 u J:x:I H ~
J:x:I
Q
0.1
0.
0.9
,--
-.-
-_
.
0.8
-----
-----<
C;
-----
t---
----
-----
----
--.-
= ..
-------
--------
----
-_
--1
rr-
_ --
;:::
. 1--
----
~-=--
--..
r-.
--~-
--=
~...::-.::::-=
F--
-0
.6
_._"
-p
o-
0.4
A
CCU
MU
iA
TED
D
E L
EC
TIO
N
-._
---
.SPA
N
2 TW
OL.
4 ~S
LOA
l ED
H
2O
51
6
LOA
] IN
G
0.2
o
~I
I ~
J J
J *
I'
'r
U
0 U
A
S M
PH
------~ 1
0 M
PH
----0
15
MPH
-
----
-P 2
0 M
PH
Fig
ure
1
8
DE
FLE
CT
ION
D
IST
RIB
UT
ION
---~25
MPH
----
-Ii
IMPA
CT
,f;lo.
0\
0.6
0.5
-0
.4
til [;3 C'J
Z
H - ~
0.3
H 8 C'J ~ r.t..
0.2
ri
l Cl
0.1
o
----
--'""
~---
. -
~
-I-
--:.
~
j;-
---
r----
1---
-::.--=
----
. ~~
--..... .:::
t---
-, -~
--..
....
. -----
--,
,---
-A
CC
UM
UI i
ATE
D
DEF
LE
CT
ION
SP
AN
1
TWO
L
Al'
iEs
LOA
DE ~
H2
0-S
1E
L
OA
DIN
( I
...
=, I
I
I !
I l!
!=:
lu J r=
U
U
A
S
MPH
------~ 1
0
MPH
----0
15
MPH
-
---9
20
MPH
Fig
ure
1
9
DE
FL
EC
TIO
N
DIS
TR
IBU
TIO
N
---~ 25
M
PH
---
---
p IM
PAC
T
~
....:J
48
TABLE 4
OBSERVED IMPACT FACTORS
Based on Reinforcing Steel Stresses
Impact Factor * Impact
Gage Location ,-,ane # 10 MPH 15 MPH 20 MPH 25 MPH Boards Remarks Bottom of Girder Center of Span 3 2 1.00 1.02 1.00 1.19 - H20-S16 Loadings
It 3 .98 - .97 -It 4 .95 1.00 .99 1.22 -
Top of Slab over Bent 3 2 - 1.40 - - -
" 3 - 1.12 - -II 4 - 1.09 - - -
Top of Slab over Bent 4 2 1.26 - - -
II 3 .91 - - - -" 4 1.19 - - - -
Bottom of Girder 4/10 point Span 4 2 1.10 1.20 1.29 1.17 -
II 3 .98 .95 .93 .83 -" 4 1.03 .91 .89 .89 -
Top of Slab 1.13 1.19 1.86
Impact Boards over Bent 2 2 1.00 11.16 Center _.f.' ...
II 3 1.09 1.15 1.27 1.03 1. 78 " II 4 1.03 1.00 1.06 .97 1.66 "
*Impact Factor is defined as the ratio of stress at the speed indicated to the stress at crawl speed.
at -