Property Location: Northeast corner of W. Church St. and Glenn Ln.. (±10.5 acres, District 5). Applicant’s Request: Planned Development request for a Major League Soccer stadium. Staff’s Recommendation: Approval of the request, subject to the con- ditions in this report. Public Comment Courtesy notices were mailed to property owners within 400 ft. of the subject property S UMMARY Location Map Subject Site Applicant Forrest Eber, CFO Orlando City Soccer Owner City of Orlando Project Planner Karl Wielecki, AICP Staff Report to the Municipal Planning Board December 16, 2014 O RLANDO S OCCER S TADIUM PD ZON2014-00028 I TEM #4B during the week of December 1, 2014. As of the published date of this report, staff has received no calls from the public concerning this request. Updated: December 11, 2014

Upload: others

Post on 21-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Property Location: Northeast corner of W. Church St. and Glenn Ln.. (±10.5 acres, District 5). Applicant’s Request: Planned Development request for a Major League Soccer stadium. Staff’s Recommendation: Approval of the request, subject to the con-ditions in this report. Public Comment Courtesy notices were mailed to property owners within 400 ft. of the subject property

S U M M A RY

Location Map Subject Site

Applicant

Forrest Eber, CFO Orlando City Soccer

Owner

City of Orlando

Project Planner

Karl Wielecki, AICP

Staff Report to the Municipal Planning Board December 16, 2014

ORLANDO SOCCER STADIUM PD

Z O N 2 0 1 4 - 0 0 0 2 8 I T E M # 4 B

during the week of December 1, 2014. As of the published date of this report, staff has received no calls from the public concerning this request.

Updated: December 11, 2014

Page 2: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 2

FU T U R E LA N D US E MA P

ZO N I N G MA P

Page 3: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 3

PD RE Z O N I N G MA P S

Page 4: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 4

PR O J E C T AN A LY S I S Project Description and Context The City of Orlando requests Planned Development approval for a new Major League Soccer stadium. The +/-10.5 acre subject property is bound on the north, west, and south by Central Blvd., Glenn Ln., and Church St. It extends over Parramore Ave. and a portion of Pine St. (both to be vacated by a concurrent abandonment application). Parramore Heritage Park, including the storm water pond, occupy the western 1/3 of the site. Fire Station #2 is at the southwest cor-ner of Parramore Ave. and Central Blvd. (to be relocated in the near future). The rest of the subject property (all City-owned) is va-cant. The stadium--Orlando’s second major league sports facility--features:

seating for 19,000 spectators (expandable to 22,900) in three levels, with the upper seating bowl cantilevered over the lower a supporters terrace overlooking Central and club seats and suites on west side a Score Board Room for 100 spectators and a bar open both to the inside of the stadium and Church St. playing field 8 ft. below street level a 16 ft. tall rotating lion statue at the main entrance

There will be four entrances: two along Church St., one at the northeast corner, and one at the terminus of Pine St on the east side of the stadium. One exit-only point will be at the north, to Central Blvd., secured from the street by a guardrail. The “front” of the stadium faces Church St. Beyond the entrances is an open plaza for gatherings and a stage. The interior concourse, four feet above grade, runs continuously around the stadium behind the lower bowl. The scoreboard will be centered at the south end of the stadium, between two 96 ft. tall stadium light poles. Below the scoreboard is a bar open to the stadium and Church St. side. At the southeast corner, there is a ticket booth and team store. This frontage allows for open views from Church St. of the field and the plaza. Locker rooms and food/beverage preparation areas, a kitchen, and areas for grounds keeping, maintenance and security staff are on the west side of the stadium. Office space in this location is 21,980 sq. ft. Along Glenn Lane is a 69-space surface parking lot includ-ing a drop off lane that can accommodate shuttles and limos. The existing Church Street “bridge” at the southwest corner of the site will remain. At the northwest corner of the site will be a service yard enclosed by 14 ft.-tall metal panel fence. It will house a three-bay loading dock, solid waste and recycling areas, media parking, and tunnel access to the field. This stadium will allow for an additional 3,900 seats. The preliminary plans show the extra seating installations at the southwest, northwest, and northeast corners of the upper bowl. As noted, there will be four pedestrian access points into the stadium. The following streetscape is proposed around the stadium:

Church St. - ranges from 14.5 ft. to 17 ft. Glenn Ln.- 6.5 ft. sidewalk Central Blvd. - streetscape ranges from 13.8 ft. to 21.3 ft., including 6 ft. street furniture/landscape zone and a pedestrian guardrail along Central Blvd.

Table 1—Project Context

Future Land Use Zoning Surrounding Use

North Urban Activity Center (UR-AC) PD/T/PH Coalition for the Homeless warehousing

East Urban Activity Center (UR-AC) AC-2/T/PH Faith Deliverance Church vacant

South Urban Activity Center (UR-AC) Public-Recreational-Inst. (PRI)

AC-2/T/PH P/T/PH

Retail Parramore Heritage Pond

West Urban Activity Center (UR-AC) AC-2/T/PH Christian Science Center warehousing

Page 5: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 5

East side- 15-25 ft. wide public plaza corridor area along entire east side, with raised landscaped planters. Pine St. east of the stadium will remain as is, with a sidewalk along the south side. Bollards may be installed at the terminus. A landscaped buffer with a fence is proposed along the southeast property line, abutting Faith Deliverance church.

During match days, the City anticipates closing Church St. to vehicular traffic from the stadium to Garland Ave. Conformance with the GMP and LDC The subject property has future land use designations of Public/Recreational and Institutional and Urban Activity Center. GMP2014-00036 is a small scale amendment to change the Urban Activity Center portion of the property to Public/Recreational and Institu-tional, in order to be consistent with the rest of the site. The subject property is zoned AC-2/T/PH and P/T/PH. The property is within the Traditional City and Parramore Heritage District Area. The eastern portion of the site is also within the Downtown Devel-opment of Regional Impact and the Downtown Community Redevelopment Area (CRA). The Public/ Recrea-tional and Institu-tional future land use designation has no maximum/ mini-mum density or in-tensity. The Future Land Use Element provides standards relating to the Public Recreational Institu-tional future land use designation within Policy 4.1.9. Allowed uses in-clude Public Safety Facilities; Community and Neighborhood Parks; Recreation Centers; Play Fields; Active and Passive Recreation Areas; Public Buildings; and all other uses associated with the City’s P Zoning district. There is no minimum or maximum intensity for develop-ment. The proposed stadium use is consistent with this future land use designation. The proposed development program is for a 18,000 seat MLS Stadium with 21,980 sq. ft. of office, 324,085 sq. ft. of commercial. This yields an intensity of 0.75 FAR. The subject property is within Future Land Use Element Subarea Policies S.6.3, S.6.4 and S.6.9, related to the Parramore area.

Subarea Policy S.6.3: The City’s Land Development Regulations shall protect the residential integrity of the Parramore Heritage area, and increase the opportunities for appropriately located neighborhood-serving retail development.

The subject property is compatible with S.6.3. The development of a new MLS stadium will increase the draw to the Par-ramore area. This will generate opportunities for new residents as well as new retail development.

Subarea Policy S.6.4: The City shall support façade improvements in this subarea in accordance with the Parramore Heri-

tage Urban Design Plan. The subject property is compatible with S.6.4. This project will be revitalizing the site with new development which has un-

dergone Appearance Review.

Subarea Policy S.6.9: The City of Orlando has determined that the over-concentration of social service uses in the Par-ramore Heritage Renovation Area has had a negative impact on the area’s stability and prosperity. Likewise, the City has determined that the establishment of adult entertainment facilities would further limit the revitalization of the area. In order to protect existing residential areas, encourage reinvestment and promote the fair distribution of social services throughout the region, the City’s Land Development Code shall include provisions to appropriately limit or prohibit the establishment, expansion, and relocation of such uses within Subarea 6.

The subject property is compatible with S.6.9. The future land use amendment is for Public/Recreational and Institutional designation in order to development a MLS Stadium and is not related to social services.

Table 3—Setback and Bufferyard Requirements

Yard

Building Setbacks Bufferyard

Min/Max Proposed Required Proposed

Front (Glenn Ln.) and Street Side (Church and Central)

0-15 ft. 3-12 ft. (100 ft. from Glenn)*

Interior Side n/a

Rear (east property line) 10 ft. min. 25 ft. None (PBU abut-ting a PBU)

4 ft. landscaping/hedge

* Parking lot between Glenn Ln. and the stadium; max. setback standard waived via PD.

n/a

PR O J E C T AN A LY S I S

Page 6: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 6

The eastern portion of the property is within the Downtown Development of Regional Impact (DRI) and the Downtown Community Redevelopment Area (CRA). The property is within the Parramore Heritage Planning Area in the CRA. The proposed mix of uses is compatible with the vision for this planning area; which is for stable residential areas will be accentuated by a significant arts, cul-tural and entertainment presence, while office and industrial developments will provide employment opportunities. The proposed PD amendment is consistent with the adopted and proposed (GMP2014-00036) future land use designations, the appli-cable subarea policies, the zoning designations and is compatible with the surrounding area. Alcohol sales. City code requires a separation of 1000 ft. between establishments selling alcoholic beverages and churches and schools. With this PD request, the applicant seeks exemption from this restriction. Signage. The submittal does not include any specific signs; these will be reviewed separately as a Planning Official’s Determination with City Council approval, and will also undergo Appearance Review Board review. The plans do identify a freestanding sign loca-tion at the southwest corner of the site. Also, the building elevations show sign panels on the east and west sides of the stadium and space for public art on the north and east. There is to be a team logo on the rear/Church St.-facing wall of the scoreboard. Impervious Surface Ratio (ISR). The underlying AC-2 district limits ISR to 0.90. The plans comply with this standard. Transportation Along with the stadium, the site will contain ancillary uses such as food vending and +/- 22,000 sq. ft. of office space for the Orlando City team offices. A 69-space parking lot will serve the day-to-day use of the office and will serve as premium parking and drop-off during games and events. This parking lot will be accessed from one driveway on Glenn Ln. Communication, general delivery, and field maintenance equipment will access the enclosed loading dock area located on the southeast corner of Glenn Ln and Central Blvd. via a driveway onto Central Blvd. Parking for the general public will not be on site but will be provided at existing garage and surface lot facilities predominately east of the subject site. Pedestrians will access the site via Church St, Central Blvd. and an im-proved Pine Street. Three patron entrance/exit gates will operate on the east side of the stadium and a fourth exit only gate will open onto Central Blvd. directly south of the Parramore Av intersection. Transit. LYNX operates multiple Links on the roads adjacent to the subject site with stops within short walking distances of the site. The LYMMO Grapefruit line has stops adjacent to the site. The LYMMO Lime line will have stops within one-quarter mile of the site. The site is also within 0.6 mile (walking distance) of the Church Street SunRail stations. Transportation Improvements. The subject site is within one half mile of the I-4 corridor which will be undergoing widening in the near future. Along with the abandonment of two blocks of Parramore Av, various roadway and sidewalk improvements will be con-structed concurrently with the stadium to provide safe pedestrian movement between the stadium and the parking areas. Bicycle/ Pedestrian Facilities. Sidewalks exist on all streets near the subject property. Some of these will be widened and improved as a part of this project. No bicycle only facilities exist immediately adjacent to the subject site. Trip Generation. The site previously contained Parramore Heritage Park, Orlando Fire Dept. Station #2, and several unused ware-houses. Recent vehicular trip generation was low and erratic for all uses. Typical daily use for the offices on the subject site is expected to be less than 200 trips. MLS games and other events planned for this site will generate up to 8,000 trips into the Downtown area, but the great majority of these vehicles will park at locations remote from the subject site. Stormwater Stormwater from this site is planned to go to the existing pond southwest of the subject property. This pond is proposed to be expanded by the City.

PR O J E C T AN A LY S I S

Page 7: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 7

EX I S T I N G SU RV E Y

Page 8: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 8

AE R I A L PH O TO

Faith Deliverance Church

Existing Parramore Heritage Park pond to be filled in

Existing Fire Station #2 (to be relocated)

City View apartments South pond to be enlarged

Page 9: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 9 ZON2014-00028—Orlando Soccer Stadium PD Page 9 ZON2014-00028—Orlando Soccer Stadium PD

S I T E P H O T O S

Pine St, view to east, showing Faith Deliver-ance Church and City View apartments

Church St., view to west along the south side of the subject property

Glenn Ln., view to north along the west side of the subject property

Southwest corner of the subject property, showing Church St. bridge

Page 10: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 10

PR O P O S E D SI T E PL A N

Premium parking

Lion statue

Ticket office and team store

Main entrances

Central Blvd. exit Central Blvd.

entrance Pine St. entrance

Service Yard

Scoreboard and bar

Page 11: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 11

STA D I U M EL E VAT I O N S

Page 12: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

ZON2014-00028—Orlando Soccer Stadium PD Page 12

STA D I U M RE N D E R I N G S

Page 13: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 13 ZON2014-00028—Orlando Soccer Stadium PD Page 13 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L Growth Management Plan Review The Comprehensive Planning Studio has no objections to the proposed PD zoning. For questions, contact Michelle Beamon at [email protected] or 407.246.3145. Land Development For questions, contact Karl Wielecki at [email protected] or 407.246.2726. 1. General Code Compliance. The proposed project shall be developed consistent with the conditions in this report, the attached

development plan, and all codes and ordinances of the City of Orlando, the State of Florida, and all other applicable regulatory agencies.

2. Conformance with PD Required. Construction and development shall conform to approved site plans, elevations, and land-scaping plans on file with the City Planning Division and all conditions contained in this report, or as modified by the Municipal Planning Board/City Council. When submitting plans to the Building Division for permitting, the applicant shall attach to each submittal a copy of this staff report, and the excerpts of the Municipal Planning Board minutes.

3. Default Zoning District. The default zoning district shall be AC-2/T/PH. For any requirements not specifically addressed in the PD ordinance, the regulations of that zoning district shall apply.

4. Modifications. Major modifications to the development plan or standards set forth herein shall follow the amendment proce-dures for Development Plans as set forth in Chapter 65, Part 2E, LDC. The Planning Official or his designee shall be authorized to permit minor changes to the Development Plan in conformance with the intent and purpose of the GMP and the LDC without further review by the Municipal Planning Board (MPB) or City Council. The changes shall not exceed the maximum standards of the GMP and LDC. These design changes include fences, accessory structures, signs, landscaping, interior alterations, and minor changes to the building.

4. Impervious Surface Ratio. The maximum ISR permitted for this development is 0.90. 5. Alcoholic Beverage Sales. The Orlando Soccer Stadium public venue shall be exempt from the provisions of Ch. 58, Part 4B. Urban Design For questions, contact Doug Metzger at [email protected] or 407.246.3414. 1. Appearance Review Board [ARB] Approval Required

a. This project is located in the Downtown Development Board/Community Redevelopment Area [DDB/CRA] Overlay Dis-trict, which requires review by the Appearance Review Board (ARB) for any new construction, substantial improvement and any major and/or minor exterior changes visible from the public ROW.

b. An ARB Major Certificate of Appearance Approval [CofAA], issued after an ARB Final Review, is required for this project prior to issuance of a Building Permit.

2. Streetscape a. Design Guidelines - All streetscape adjacent to the soccer stadium shall be designed and constructed in accordance with the

standards and specifications of the Downtown Orlando Streetscape Guidelines or as otherwise approved by the City. b. Maintenance – Unless approved through a separate agreement the Downtown Community Redevelopment Agency

[CRA] shall only maintain those portions of the soccer stadium improvements within the public right-of-way. The CRA shall not be responsible for nor maintain any section of streetscape not constructed in accordance with the Downtown Orlando Streetscape Design Guidelines or as otherwise approved by the City.

F I N D I N G S Findings Subject to the conditions contained herein, the proposal is consistent with the requirements for approval of Planned Development applications contained in Chapter 65 of the Land Development Code (LDC): 1. The proposed use will be consistent with the City’s Growth Management Plan. 2. The proposed use is consistent with the purpose and intent of the PD zoning district and all other requirements of the LDC. 3. The proposed use is compatible with surrounding land uses and the general character of the area. 4. The necessary public facilities will be adequate to serve the proposed use, or will be provided by the applicant as a condition of

this approval. Staff recommends approval of ZON2014-00028 subject to the conditions below:

Page 14: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 14 ZON2014-00028—Orlando Soccer Stadium PD Page 14 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L c. Minimum Width - At a minimum the streetscape zone on W. Church Street shall be 14-feet from back-of-curb and shall

include Streetscape Furniture and Street Tree Zone [Furniture Zone] combined with an unencumbered Pedestrian Clear Zone. The minimum streetscape width on W. Central Avenue shall be 13-feet and shall provide a Furniture and Streetscape Zone and an unencumbered Pedestrian Clear Zone. At a minimum Glenn Lane shall provide a 5-foot pedestrian clear zone or 6-feet if located on the back of curb.

d. Streetscape Finishes and Furniture – Streetscape treatments adjacent to the soccer stadium site should be consistent with the existing W. Church Street and W. Central Avenue streetscape treatments. This includes concrete sidewalks with saw cut joints; double-acorn LED street lights, the lights shall be perpendicular to the adjacent centerline; 4’x6’ street tree grates with a 1-foot concrete ribbon band for high-rise oak street trees. Construction standards and specifications shall be consis-tent with the requirements of the Downtown Orlando Streetscape Design Guidelines. Other streetscape treatments and al-ternatives may be approved through an ARB Minor Review.

e. Curbing - Unless otherwise approved all streets shall have Type “F” curb with gutter. f. Structural Soil - To minimize root damage to adjacent pavement areas structural soil or a Planning Official approved

equivalent shall be installed around all oak street trees consistent with Detail 3.4-O and 3.4-P of the Downtown Streetscape Guidelines.

g. Root Barriers - Where a canopy tree is installed within 10 ft. of any existing or proposed underground utility line a root bar-rier should be installed.

h. Utility Boxes—Utility boxes and covers in the streetscape zone shall be traffic bearing grade. i. Crosswalks – Decorative crosswalks shall be installed at the Glenn Lane and Service Yard driveway crossings as well as

pedestrian crossings in the Premium Parking and Drop-Off Area. Crosswalks at driveways shall be raised to be at the same grade as the sidewalk adjacent to the driveway in order to clearly define the pedestrian area. The driveway slope transition from street grade to the sidewalk grade shall occur in the Streetscape Furniture Zone. The crosswalk surface shall be treated with a material, color or texture that contrasts with the driveway surface. Reflective paint alone is not an acceptable treat-ment, however may be used in conjunction with pavers or other surfaces to define the pedestrian path for night time safety. Refer to Detail 3.2K of the streetscape guidelines for more information.

j. Sidewalk Café / Outdoor Dining - Outdoor dining areas exterior of the stadium walls that utilize street right-of-way will require a Sidewalk Café Permit [SWC Permit]. All outdoor dining areas, whether in or out of the right-of-way will require an ARB Minor Certificate of Appearance Approval for layout, furniture and stanchions prior to opening for business.

k. Outdoor Speaker Permit—Audio and/or speaker systems on the exterior of the stadium that project towards the right-of-way shall require and outdoor speaker permit that complies with the conditions of the LDC and City’s Noise Ordinance.

l. All above ground utility lines adjacent to the stadium should be placed underground during construction of the proposed streetscape improvements.

m. Glenn Lane Streetscape—Single acorn streetlights shall be added to the planting strip on Glenn Lane along the Premium Parking Area. The proposed tree spacing in the landscape plan shall be re-configured to accommodate the single acorn streetlights. Pedestrian level lighting, such as bollards shall be added in the Service Yard buffer planting strip or incorpo-rated into the design of the screen wall on Glenn Lane only.

n. Stadium Ingress and Egress Paving Treatments— At each stadium ingress and egress point colored concrete with unique scoring may be utilized from the entry to the back of curb provided those area are constructed to meet the construction stan-dards of the Downtown Streetscape Design Guidelines. All other pedestrian areas around the exterior of the stadium shall be saw cut concrete, or as otherwise approved.

o. Vehicle Hardening—Any streetscape sidewalks that may be used to support motorized vehicles, maintenance vehicles or loading and unloading, including the east side pedestrian path between Church Street and Central Avenue shall 6-inches thick in order to support the weight of motorized vehicles.

p. Central Avenue Egress—It is recommended that colored concrete with unique scoring should be added to the Central Ave-nue mid-stadium egress area.

q. ARB Approval – Final streetscape hardscape, landscape and furnishings plans shall be submitted for an ARB Minor [Staff] Review prior to submittal for final building permit.

3. Service Areas, Mechanical Equipment, Utilities, Venting a. Service Area/Utilities - All utilities, trash disposal pick-up, and other maintenance facilities should be located on the interior

of buildings, and not adjacent to the pedestrian sidewalks or streetscape zones to the fullest extent possible. b. Mechanical Equipment - All ground and roof mounted mechanical equipment shall be screened from view and meet the

conditions of the City Land Development Code [LDC] including transformers and other above ground utility structures and cabinets.

c. Telecommunications Equipment Screening - Buildings should be designed to accommodate future placement of telecom-munications equipment (including any communications equipment required by the police or fire department). It is recom-mend that screening areas be built into rooftop areas so that the placement and screening of the equipment does not become

Page 15: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 15 Page 15 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L an afterthought.

d. Streetscape - In no instance shall any above grade transformer, utility box, traffic signal control box, backflow preventer or vertical impediment be located in the Pedestrian Clear Zone.

e. Venting & Exhaust - All restaurant venting and restaurant exhaust shall be directed to the roof of the stadium structures, shall not be visible from the public right-of-way, and is not permitted on any façade of the stadium structures. All other venting and exhaust for mechanical equipment and utilities shall be a minimum of 12 ft. above grade, and shall be designed and integrated into the stadium structures so as to be seamless with the overall architecture of the structures. Venting shall not occur over or be directed towards primary pedestrian areas.

f. Backflow Preventer - backflow preventer/s shall be located so as not to be directly visible from the right-of-way and should be screened from view where necessary.

g. Dumpsters - All dumpsters and trash compactors shall be internal to buildings and screened with solid walls to match the principal structure. Decorative gates shall be installed to coordinate with the principal structure.

h. Fencing - All fencing on the site shall be an open, CPTED-approved fence, such as aluminum or wrought-iron picket fenc-ing. Chain link fences are prohibited except for construction fencing.

i. ARB Approval — The final location of exterior or rooftop mechanical equipment, utilities and vents shall be submitted for an ARB Minor [Staff] Review prior to submittal for final building permit.

4. Lighting a. Lighting Standards – Lighting shall comply with the City’s approved lighting ordinance [Ord. 2013-73]. A signed and

sealed lighting plan with photometrics consistent with the lighting ordinance or a photometric plan is subject to approval by the Planning Official and ARB Major Review. The submittal shall also include details of all proposed lighting fixtures on the exterior of the soccer stadium site. The final lighting and photometric plan shall be submitted for an ARB Minor [Staff] Review prior to submittal of final building permits.

b. Security Lighting - Security lighting shall not be substituted for parking or pedestrian area lighting fixtures. Security light-ing is restricted to lighting service, storage, loading and other similar uses. Security lighting shall not extend beyond the fascia or roofline of any building.

c. Light Shields - Shields for security lighting and pedestrian area lighting shall be fully shielded and similar in color with the surface to which the fixture is attached.

d. Service Areas - Lighting under awnings, canopies, and porte-cocheres should be recessed. If not recessed, the box type or other lighting fixture shall be opaque on all sides (no light shall emanate from any side of the fixture).

e. Pedestrian Areas – Pedestrian area lighting fixtures should be pedestrian in scale, as well as decorative in appearance, style and finish.

f. East Side Pedestrian Path—The pedestrian path on the east side of the stadium between Church Street and Central Avenue will be an important neighborhood pedestrian connection. Significant pedestrian level lighting of the walkway area that pro-vides a secure pedestrian environment after dark shall be provided and shall be in continuous night time operation.

5. Master Sign Program a. Intensified Entertainment District - The sign program for the Orlando Soccer Stadium should establish the district as a re-

gional entertainment destination. With its strategic location near the Amway Center, and the proposed Sports and Entertain-ment District the soccer stadium should utilize many of the sign concepts from the City’s Major Attraction Overlay District and Downtown Special Signage District; these special districts include digital signs and limited off-site signage rights that are oriented to the inside of the stadium.

b. Sign Master Plan - Prior to issuance of a Certificate of Occupancy for the soccer stadium a Sign Master Plan shall be ap-proved by the Planning Official thru an administrative determination, the City Council via ordnance and shall also receive a Major Certificate of Appearance Approval from the Appearance Review Board.

c. Maximum Copy Area - Maximum allowable copy area shall be established in the Master Sign Plan. d. Blended Maximums - Maximum allowable sign area shall be allocated and documented as part of the Master Sign Plan. e. Sign Program Guidelines - The Sign Master Plan shall establish a uniform sign format or program for the soccer stadium

site and include individual sign areas, design criteria, sign type, sign size and location of all exterior signs and sign spaces. The Sign Master Plan shall also include a wayfinding sign package and wayfinding system for the exterior of the stadium.

f. Exemptions – Inward facing Digital Screens and Roof Signs visible only to the sky shall not be deducted from the total sign allocation for the site, yet should be separately calculated and submitted as part of the Sign Master Plan.

g. Amendments - The Sign Master Plan may be amended as needed from time-to-time thru an Appearance Review Board Mi-nor Review.

h. Sign Permit – A sign permit is required for all permanent and individual signs. i. All permanent signage shall be subject to aesthetic and design review by the Appearance Review Board to ensure the over-

all theme and design criteria of the complex is maintained. 6. Vehicle Use Areas

Page 16: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 16 ZON2014-00028—Orlando Soccer Stadium PD Page 16 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L a. All vehicle use areas shall meet the requirements of the LDC including configuration, dimensional layout, and landscaping. b. The Premium Parking Area and Service Yard shall comply to Sec. 61.312 of the LDC. c. Landscape areas between vehicular use areas and rights-of-way or property lines shall be a minimum 7.5-feet wide. d. Vehicular Use Area Fencing – CPTED-style fencing and or walls shall be permitted in the required perimeter landscape

areas. Fencing details including style, color and gate locations shall be reviewed as part of the ARB Major [Final] Ap-proval.

7. Landscape and Hardscape Plans a. Church Buffer— provide a minimum 4 foot-wide landscape buffer along the western boundary of the church property that

includes a 4-foot tall CTED fence beginning at the W. Church St. right-of-way line for 25-feet. After the first 25-feet the fence height shall transition from a 4-foot tall fence to a 6-foot tall fence for the rest of the length of the bufferyard.

b. Service Yard Screening—A minimum 4-foot tall landscape buffer shall be provided along the Glenn Lane perimeter of the Service Yard.

c. Premium Parking Area Screening—a minimum 3-foot tall landscape buffer shall be provided along the perimeter of the Premium Parking Area.

d. East Façade Tree Plaintings— Four 4-foot by 6-foot tree grates with high rise oak canopy trees shall be added along the eastern edge of the pedestrian walkway north of the Pine Street stadium entry. The tree wells shall be centered between the pedestrian lighting fixture locations. Structural soil as specified in the Downtown Streetscape Design Guidelines shall be used in the tree grate and surrounding areas.

e. Landscape and Hardscape Plans—Final Landscape and hardscape plans shall be submitted for ARB Minor [Staff] Review prior to submittal for building permits.

8. Architecture a. Durable Materials – A durable material such as stone, brick, pre-cast concrete, polished concrete terrazzo block or thermo-

chromax that extends from finished grade to 8-ft. above finished grade shall be provided along the exterior facades of the stadium. Exposed, painted 8” by 16” concrete block and split-faced concrete block are not suitable materials. The use of stucco as an exterior building finish is permitted above 8-ft..

b. Principal Entrances – The principal pedestrian stadium entrances shall be architecturally treated and emphasized with cano-pies, awnings, enhanced hardscape, landscape or other material changes or architectural features.

c. Articulation – Not more than 30 ft. of any exterior façade shall be unbroken by architectural changes such as materials, col-ors, patterns, windows, columns, canopies, recesses, projections, pilasters, etc. Long single plane exterior walls should be avoided.

d. Transparency – It is understood that the functions and facilities of a stadium complex are unique and oriented inward how-ever providing 15% of transparency along the exterior ground floor of the stadium structures is strongly encouraged. Reflec-tive glass , spandrel glass and glass block are not considered transparent materials.

e. Glazing - All glass at the ground level should be clear. Minimum light transmittance shall be 80%. High performance or low-e glass may be considered as an alternative with a minimum transmittance of 60%. No windows shall be dry-walled, or have permanent partitions installed on the interior to block natural surveillance. Tinted or reflective glass shall not be per-mitted.

f. Exterior Doors – At a minimum a 4-inch by 6-inch view panel shall be provided in all exterior solid doors that provide in-gress or egress to the stadium in order to provide visibility for entering and exiting pedestrians. Mechanical and equipment room doors are exempt from this requirement.

g. Stormwater Run-off - Water shall not spill out onto the sidewalk or plaza areas from any downspout, nor shall any down-spout project into the public ROW. Canopies shall incorporate downspouts or other rain water management systems that prevent water spillage or drainage onto the pedestrian path or ROW.

m. Art Panels — Artwork for the fabric scrim art panels shall be reviewed and included in the Master Sign Plan. The artwork in the future may be changed as part of an ARB [Minor] Staff Review. The scrim panels shall be periodically replaced as needed in order to maintain and preserve the visual integrity and vibrancy of the artwork and the fabric scrim.

n. W. Pine Street [East] Façade — The recesses along east façade conflict with Crime Prevention Through Environmental Design [CPTED] principles and are a security concern during non-event times at the stadium. Additional lighting, surveil-lance options and/or additional barriers and buffers to increase pedestrian safety and security along the eastern pedestrian path should be considered.

o. Fencing—Security fencing between the stadium structures of the east façade shall be moved as far east as feasible to im-prove security and reduce potential hiding areas adjacent to the pedestrian pathway.

n. Appearance Approval – Final architectural elevations shall be provided for approval for ARB Minor [Staff] Review prior to submittal of building permits.

o. Model - Prior to permitting, a physical 1"= 100' model of the stadium should be provided for the DDB/CRA model in the Downtown Information Center on S. Orange Avenue.

Page 17: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 17 ZON2014-00028—Orlando Soccer Stadium PD Page 17 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L Transportation Planning Review For questions, contact John Rhoades at [email protected] or 407.246.2293. The Transportation Planning Division supports the owner/applicant’s request for an amendment to the existing Planned Develop-ment, provided the owner/applicant complies with the conditions listed below:

1. NUMBER OF BICYCLE PARKING SPACES REQUIRED: The proposed soccer stadium shall provide a minimum of eighty (80) short term bicycle parking spaces and fourteen (14) long-term bicycle parking spaces. Bicycle parking shall be provided as required in the Orlando Land Development Code (LDC), Chapter 61, Figure 28. .

2. BICYCLE PARKING LOCATION REQUIREMENTS: Short-term spaces shall be located within 120 ft. of and clearly visible from the Church Street, Pine Street, and Central Avenue stadium entrances; long-term spaces shall be located within 500 ft. of the office uses and employee entrances. The short term spaces may be evenly distributed among the various stadium en-trances. Covered bicycle parking is encouraged wherever the design of the building or use being served by the bicycle parking facility includes a covered area that could accommodate such facilities either as proposed or through economical redesign.

3. BICYCLE RACKS REQUIREMENTS: All standard bicycle racks shall comply with the following standards: a. Maximum rack height: 36 inches. b. Minimum depth for each row of parked bicycles: 72 inches. c. Minimum tube diameter: 1.9 inches. d. Minimum separation between horizontal rows: 30 inches on center to allow enough room for 2 bicycles to be secured to each rack element. e. Capacity: Designed to accommodate 2 bicycle parking spaces per rack. f. Finish: Powder coated or other weather-proof surface, as approved by the City Transportation Engineer.

4. BIKESHARE FACILITIES: The applicant shall consider the future implementation of a bike sharing service into this devel-opment proposal. A bike-sharing station area shall be no less than 10x20 ft., to be located within 120 ft. of one of the stadium entrances, should be implemented.

5. TRAFFIC CONTROL DEVICES AND MARKINGS: All driveways shall be marked and signed according to the cur-rent standards of the MUTCD. All driveway crosswalks shall be marked using ‘ladder’ type pavement markings using high-emphasis retro-reflective paint.

Transportation Engineering For questions, contact Lauren Torres at 407-246-3322 or [email protected]. Information regarding plan review, permit issuance, and inspections can be obtained by using our interactive voice response system PROMPT at 407-246-4444. The current design shows delivery vehicles backing into the delivery area from Central Blvd. Backing in from a major thor-

oughfare will not be approved. Show new delivery maneuver in Auto-Turn or other simulation software that provides an entry and exit for delivery vehicles where there is no backing-in within the ROW.

Engineering /Zoning Review For questions, contact Keith Grayson at 407.246.3234 or [email protected]. 1. The City Council Adopted the Engineering Standards Manual (ESM), Fourth Edition, on March 9, 2009. All plans must con-

form to the ESM and all construction must be accomplished in accordance to the ESM. 2. As per Section 61.225 of the Land Development Code and the Downtown Development Board, a 13 ft. wide concrete sidewalk

is required along all dedicated rights-of-way, unless other site specific specifications are given. Any existing sidewalk damaged or broken is to be repaired.

3. The final recorded plat shall contain the following note:"Development on the property depicted on this plat is subject to the re-quirements of Chapter 59, the Concurrency Management Ordinance of the City of Orlando, which governs the City's ability to issue building permits on this property. Approval of this application shall not be deemed to provide any vested rights, except as to those matters depicted hereon, that are consistent with the requirements of Chapter 177, Florida Statutes, or were required by the City of Orlando as a condition of platting."

4. Please be advised that the development of this project/property is subject to the terms and provisions of Concurrency Manage-ment Chapter 59 of the City Code and the Committed Trip Allocation Policy.

5. Construction activities including clearing, grading and excavating activities shall obtain an Environmental Protection Agency (EPA) National Pollution Discharge Elimination System (NPDES) permit, except: Operations that result in the disturbance of one acre total land area which are not part of a larger common plan of development or sale.

Page 18: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 18 ZON2014-00028—Orlando Soccer Stadium PD Page 18 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L 6. At the time of development, the owner/developer is required to pay an on-site inspection fee that is a percentage of the cost of

the on-site improvements , excluding the building, in accordance with City Land Development Code Section 65.604. 7. This property is required to plat in accordance with Section 65.401 of the City's Land Development Code prior to the issuance of

building permits. 8. In accordance with City Code Section 28.6 (f) 1-3, the Office of Permitting Services is authorized to make a determination of

approval/disapproval of refuse container sites. Approval/disapproval of the use of commercial hand pick-up of refuse from any non-residential entity shall be determined solely by the Refuse Collection Bureau Staff.

Police Dept. Review The Orlando Police Department has reviewed the plans for MLS-Orlando City Lions Soccer Stadium located at 655 W. Church St., utilizing CPTED (Crime Prevention Through Environmental Design) principles. CPTED emphasizes the proper design and effective use of the built environment to reduce crime and enhance the quality of life. There are four overlapping strategies in CPTED that apply to any development: Natural Surveillance, Natural Access Control, Territorial Reinforcement and Target Hardening. For questions regarding the Orlando Police Department plan review, please contact Audra Nordaby at 407.246.2454 or [email protected]. Natural Surveillance: Design the site to keep intruders easily observable. This is promoted by features that maximize visibility of people, parking areas and building entrances; doors and windows that look out onto streets and parking areas; pedestrian-friendly sidewalks and street; porches or patios and adequate nighttime lighting. Overall Project: · A lighting plan was not available at the time of this review. Lighting plays a very important role in CPTED. It is crucial that lighting sends the right messages to the public about the safe and appropriate use of space at different times of the day and night. o All lighting for this project shall meet or exceed the guidelines in Orlando City Code, Title II, Chapter 63, Part 2M. o In order to give staff and fans a sense of safety, pedestrian-scale lighting should be used in all high-pedestrian traffic areas espe-cially along main entrances, all common areas, pedestrian plazas and walkways throughout the project. o Appropriate lighting should be included in all areas anticipated to be utilized after-dark. This is especially true in and around the parking area, elevator lobbies, stairwells, public and private entrances, public corridors, the service yard and throughout any amenity areas and in all pedestrian plazas around the stadium. o The use of full cut-off or shielded light fixtures is strongly encouraged to direct light where it is intended while reducing light trespass, glare, and waste. · Landscaping is another crucial aspect of CPTED. Trees branches should be kept trimmed to no lower than 6 ft. from the ground and shrubs should be kept trimmed to no higher than 30 inches. Avoid conflicts between landscaping and lighting, especially lighting adjacent to canopy trees. Landscaping should not create blind spots or hiding places and should not block/cover windows. Open green spaces should be observable from multiple points. · Benches (or outdoor furniture) placed in common areas are a good way to increase surveillance and encourage interaction. Consider furniture designs that encourage stopping and resting but reduce opportunities for potential offenders (i.e. a ribbed design rather than solid and center rails or arm rests to discourage sleeping).

Bicycle parking pads (if installed) should be observable from entrances, securely fastened and not hidden behind landscap-ing. Ensure that any canopies do not interfere with lighting, especially pedestrian scale.

· Consider utilizing convex mirrors or reflective surfaces in any interior 90° corners to support surveillance around corners. · Public restrooms should be visible from the main customer areas, away from outside exits and of a zigzag design. · Special attention should be given to potential ambush points along the east side of the stadium. The use of mirrors or reflective material in these ‘coves’ are a good option to consider. · Benches or outdoor furniture placed in common areas are a good way to increase surveillance and encourage community inter-action. Consider furniture designs that encourage stopping and resting but reduce opportunities for potential offenders (i.e. a ribbed design rather than solid and center rails or arm rests to discourage sleeping). · Bicycle parking pads should be observable from building entrances, securely fastened and not hidden behind landscaping. · Trash receptacles should be made of a see through material to reduce the opportunity for someone to ‘hide’ any potential haz-ards within the containers. Offices, Locker rooms, Grounds keeping, Service, and Retail Spaces:

Since there is typically no natural surveillance around a dumpster, be sure this area is well-lit and that lighting is well main-tained.

Page 19: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 19 ZON2014-00028—Orlando Soccer Stadium PD Page 19 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L A security camera system (CCTV) capable of recording and retrieving an image to assist in offender identification and ap-prehension should be installed in areas without natural surveillance especially any place a shear wall may exist. Where possible, offices, reception areas, lobbies, or host stands should have exterior windows and furniture oriented to im-prove surveillance of public areas. All sides should have windows to observe walkways, parking areas and driving lanes. Advertisements and product displays should not be located in windows. If advertisements must be used, they should be small in size, cover no more than 15% of the window(s) and be located in an area that will not impede surveillance into and out of the building.

Natural Access Control: Design the site to decrease crime opportunity by denying access to crime targets and creating in offenders, a perception of risk. This can be accomplished by designing street, walkway, building and parking lot entrances to clearly indicate public routes and discourage access to private areas with structural and landscape elements.

Public entrances should be clearly defined by walkways, signs, and landscaping. Landscaping should create clear way-finding, be well lit and not block entrances or create ambush points. There should be no easy access to the roof of any buildings on property or the stadium itself. Way-finding located throughout the property should provide clear guidance for legitimate users while discouraging poten-tial offenders. Signage with hours of operation should be clearly visible at any public entrance. Traffic calming techniques as well as surface and gateway treatments around the project can promote safe vehicle speeds, reduce collision frequency and increase the safety and the perception of safety for non-motorized users. Walkways should be a minimum 6’ in width to enhance pedestrian flow.

Territorial Reinforcement: Design can create or extend a sphere of influence, where users develop a sense of territorial control, while potential offenders are discouraged. This is promoted by incorporating features that define property lines and distinguish private spaces from public spaces such as; landscape plantings, pavement designs, gateway treatments and CPTED open design (see-through) fences. · The property should be designed to encourage interaction between users. · If the office building will have a separate address, it should have an address that is clearly visible from the street and parking areas with numbers a minimum of five-inches high made of non-reflective material. · Fences may be considered around the premium parking area to add security, delineate property lines, allow transparency for surveillance, be unobtrusive, and create a sense of community. CPTED style fencing, up to 6-ft. in height, made of commercial grade steel is a good option to consider. Another option is landscape buffers, which include hostile vegetation, to delineate public from private spaces. The fencing and landscape buffer may be used together to further define and control spaces.

Maintenance is an important aspect of territorial reinforcement. A well-maintained area sends the message that people no-tice and care about what happens in an area. This in turn discourages vandalism and other crimes. The proposed pedestrian guardrails outside of the Central Avenue exit should be constructed in a way that will not allow patrons to go under or through the rail, thus defeating the purpose of the rails. On all of the proposed raised plant beds, retaining walls and terrace edges, consider including skate deterrents or architec-tural elements that encourage stopping and resting but reduce opportunities for potential offenders to sleep or hide in these areas.

Target Hardening: This can be accomplished by features that prohibit entry or access such as window locks, dead bolts for doors and interior door hinges. Overall Project: · We encourage the use of bollards as a means of delineating private from public spaces. Bollards that serve dual-purpose (i.e. bollards used for traffic or pedestrian control that also contain lights) are a good option to consider. · Door locks should be located a minimum of 40 inches from adjacent windows. · Air conditioner units should be caged and the cages should be securely locked. · An access control system should be considered throughout the project to secure private or restricted areas.

If an alarm or security system is installed, it should be regularly tested and maintained. During working hours, commercial alarm systems (to include any common or amenities areas) should be programmed so that a short beep is sounded if an exterior door opens.

· A security camera system (CCTVs) capable of recording and retrieving an image to assist in offender identification and appre-hension should be used throughout this project. Security cameras should be mounted at an optimal height to capture offender identi-

Page 20: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 20 ZON2014-00028—Orlando Soccer Stadium PD Page 20 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L fication (“aiming” down from the ceiling often results in images of the offender’s hat). CCTVs should also be placed in several loca-tions throughout the parking areas, service access areas, property access points and any areas with limited or no natural surveillance. · Back or side doors (non-public) should be kept locked from the outside at all times. Internal business policy should prohibit the “propping open” of exterior doors. · Large glass doors and windows should be made of impact resistant glass or a security film (such as Lexan™). If security film is utilized, ensure that the light transmittance of the security film is greater than or equal to the light transmittance of the window's glass. · Each retail and concession space should contain a drop safe or cash management device. Additional precautions, such as silent alarms, hold-up alarms and retail training (what to do during a robbery), should be discussed with OPD’s Crime Prevention Unit Officer Christopher Newton, 407.246.2093. Additional Recommendations: Orlando Police Department Public Safety Communications System Conditions: Distributed Antenna Systems (DAS): All buildings shall provide an adequate level of indoor coverage for public-safety radio service for the City of Orlando radio commu-nications system, including but not limited to police, firefighters, and other emergency responders. A DAS system will also improve commercial cellular service for building occupants. The system will enable all first responders to communicate with dispatch and other field units. Inadequate coverage not only puts first responders at risk but also the citizens they are protecting. Adequate indoor radio coverage shall include the following standards: · Inbound into the building: A minimum average in-building field strength of 10 dbm above the noise floor throughout ninety-five (95%) of the area on each floor of the building when transmitted from the city’s police dispatch center and the appropriate emer-gency service dispatch centers which are providing fire and emergency medical protection service to the building. · Outbound from the building: A minimum average outbound field strength of 10 dbm above the noise floor throughout ninety-five percent (95%) of the area on each floor of the building when transmitted from the field units portable radio to the appropriate emergency service dispatch centers which are providing fire and emergency medical protection service to the building. · The City’s Communications Unit with consideration of the appropriate police, fire and emergency medical department ser-vices shall determine the frequency range or ranges that must be supported. For the purpose of this section, adequate radio coverage shall constitute a successful communications test between the equipment in the building and the Communications Centers for all appropriate emergency service providers for the building. · If any part of the installed system or systems contains an electrically powered component, the system shall be capable of an independent battery or generator system for a period of at least twelve hours without external power input or maintenance. The bat-tery system shall automatically charge in the presence of external power. · FCC authorization: All amplification equipment must be FCC Type Accepted. · Developments must comply with NFPA 72-2010 – National Fire alarm and Signaling Code, Public Safety In-Building Re-quirements, as it pertains to emergency communications systems (ECS), and their components. If you have any questions regarding the requirements as listed above, it is suggested that you contact the OPD Radio Systems Ad-ministrator, Norm Poe at 321.235.5314 or email [email protected]. The OPD Technical Review Committee representa-tive, Audra Nordaby 407.246.2454, can assist the applicant in contacting the Emergency Communication Representatives. Construction Site Crime Prevention: Due to the continued trend of theft of building materials and equipment from construction sites, Orlando Police Department’s Crime Prevention Unit strongly recommends that the developer institute the following crime preven-tion/security measures at this project site: · Post signs at the site that theft from the site or trespassing on a construction site is a felony under Florida Law and that the de-veloper will prosecute. · To improve visibility of potential offenders by OPD patrol officers, perimeter lighting should be installed at a minimum of 150

Page 21: F L USE MAP - Orlando · 2017. 11. 4. · seating for 19,000 spectators (expandable to 22,900) ... East side- 15-25 ft. wide public plaza corridor area along entire east side, with

Page 21 ZON2014-00028—Orlando Soccer Stadium PD Page 21 ZON2014-00028—Orlando Soccer Stadium PD

CO N D I T I O N S O F AP P R O VA L ft. intervals and at a height not less than fifteen (15’) from the ground. The light source used should have a minimum light output of 2,000 lumens, shall be protected by a vandal resistant cover, and shall be lighted during the hours of darkness. · In addition to lighting, one of the following physical security measures should be installed: o Fencing, not less than six (6’) ft. in height, which is designed to preclude human intrusion, should be installed along the perimeter boundaries of the site and should be secured with chain and fire department padlocks for emergency vehicle access; post in a clear area, an emergency contact person and phones numbers for after hours, in case of an emergency; or o A uniformed security guard should be hired to continually patrol the construction site during the hours when construction work has ceased. · Valuable construction materials and tools should be protected in a secondary fenced, locked cage.

Post in a clean, open area, the name and numbers of an emergency contact person for OPD in case of a night-time emer-gency.

If you have any questions, please call the Crime Prevention Unit, Officer Christopher Newton, 407.246.2093. Innovative Response to Improve Safety (I.R.I.S.) Camera System: OPD recommends that the developer contact OPD in an effort to coordinate camera system technology. OPD has the ability to moni-tor specified external camera systems from private facilities at the will of the developer or building owner. OPD monitoring will be in addition to self- monitoring and will not replace building camera monitoring. OPD will not have the ability to interfere with or manipulate building camera systems, only view. The additional monitoring is beneficial to both the developer/owner and OPD as a crime prevention and overall public safety solution. IRIS questions should be directed to the Orlando Police Department, Sgt. Andy Brennan, at [email protected]. Mutualink© - Real-time interoperable communications multimedia sharing:

Mutualink© is an IP-based multimedia overlay network, designed to leverage the sharing of your existing radio, video, telephone, and IP-sensory equipment including disparate systems, as well as next-generation communication technology. Security and Public Safety agencies using Mutualink© have the dual benefit of maintaining full control of their radio, video, tele-phone, and IP-sensory related resources, while making them available for interoperable connection with other agencies' systems with the click of a mouse. Interconnection with the Mutualink© network is achieved without impacting the operation of existing console and remote control equipment. OPD recommends that the developer contact OPD in an effort to coordinate security and surveillance system technology. OPD has the ability to monitor specified camera systems from private facilities at the will of the developer or building owner. OPD monitoring will be in addition to self- monitoring and will not replace building camera monitoring. OPD will not have the ability to interfere with or manipulate building camera systems, only view. The additional monitoring is beneficial to both the developer/owner and OPD as a crime prevention and overall public safety solution. Mutualink© questions should be directed to the Orlando Police Department, Sgt. Andy Brennan, at [email protected].

Building Plan Review For questions, contact Don Fields at (407) 246-2654 or [email protected]. Building Plan Review is not applicable to this case at this time. The building design will be reviewed for code compliance during the design development and construction documents phase.

RE V I E W/AP P R O VA L PR O C E S S—NE X T ST E P S 1. MPB minutes scheduled for review and approval by City Council (currently scheduled for January 26, 2015 City

Council Meeting). 2. City Council review and approval of First reading of PD ordinance. 3. City Council review and approval of Second reading of PD ordinance. 4. Building permits issued.