Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION February 2019 1

Upload: others

Post on 10-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 2: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

ADDITIONS AND RENOVATION

PROJECTS IN CONSTRUCTION

2

Page 3: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke Contract Amount - $32,014,460 Construction Period – June 2017 – January 2019 Construction Status – 97% Package 2 (Building) Project Scope – Fine Arts Building Replacement

Substantial Completion Interior January 11, 2019.

Rendering of New Auditorium 3

Page 4: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM

4

Page 5: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM

Bus Loop

Bandhall

Auditorium

Auditorium Lobby

5

Page 6: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

SAM RAYBURN MIDDLE SCHOOL Building Replacement

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction

Superstructure work in progress.

GMP Amount – $13,900,000Tentative Construction Period - June 2018 - August 2019Construction Status - 40%Project Scope - Building Replacement (Gym, Band and Library)

6

Page 7: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

SAM RAYBURN MIDDLE SCHOOL Building Replacement

New Library Location

Band Hall and Courtyard New Gym and Boys Lockers Location

7

Page 8: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

SAM RAYBURN MIDDLE SCHOOL Building Replacement

Gym Building - Lower Level StairwellGym Building lower level

New Library - Foundation Band Hall

8

Page 9: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy

Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – Breda Construction, Inc. Contract Amount - $468,095 Construction Period – June 2018 – March 2019 Construction Status – 60% Project Scope – Additional Student Canopy

Steel framing install in progress.

Rendering of Student Canopy 9

Page 10: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy

FlatworkCanopy Steel

Canopy Steel Canopy Steel

10

Page 11: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Thomas Curiel Contractor – WR Griggs Construction Co. Contract Amount - $2,671,000 Construction Period – June 2018 – February 2019 Construction Status – 95% Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades

Substantially Complete in February 4, 2019.

11

Page 12: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades

Kitchen Equipment Kitchen Equipment

Cafeteria - Serving Line Gates Serving Line

12

Page 13: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – CGC General Contractors, Inc. Contract Amount - $4,249,000 Construction Period – June 2018 – August 2019 Construction Status – 40% Project Scope – Cafeteria / Kitchen Renovation

Kitchen renovation work in progress. Underground utilities in progress.

Rendering of Caf eteria Interior 13

Page 14: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Aerial of Site

NEW KITCHEN ADDITION

RENOVATED

CAFETERIA

14

Page 15: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Kitchen Exterior Kitchen Exterior Kitchen Interior

15

Page 16: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Webber Commercial Construction Co. Contract Amount - $2,784,000 Construction Period – June 2018 – February 2019 Construction Status – 95% Project Scope – Fine Arts Addition, Bus Canopy & Drainage Upgrades

Fine Arts Classroom & Interior Substantial Completion Jan.15, 2019Exterior Canopies, landscape & irrigation underway.

Rendering of Band Room Addition at Fine Arts Classrooms 16

Page 17: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Aerial Vi ew of Campus17

Page 18: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Existing Front Entrance and Fine Arts Classrooms

Rendering of Band Room Addition at Fine Arts Classrooms

18

Page 19: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Fine Arts Building - Exterior Canopies

CanopiesFine Arts Building - Exterior

19

Page 20: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – Central Builders, Inc. Contract Amount - $3,892,000 Construction Period – June 2018 – February 2019 Construction Status – 92% Project Scope – Cafeteria / Kitchen Renovation

Kitchen Renovation punch inspections in progress.Completion scheduled February 18, 2019.

Renovated Cafeteria 20

Page 21: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation

Kitchen Area - Equipment Kitchen Area - Serving Lines

Office Area Kitchen Equipment

21

Page 22: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – WR Griggs Construction Contract Amount - $6,141,000 Construction Period – May 2018 – August 2019 Construction Status – 55% Project Scope – Science Classroom, Library Renovation and Classroom Addition

Plumbing, HVAC & Electrical in progress. Building Addition Framing & Masonry in progress.

22

Page 23: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Site Plan23

Page 24: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Classroom Addition Prep Room

Science Classroom Renovation Science Classroom Renovation

24

Page 25: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2018

25

Page 26: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

KALLISON RANCH AREA MIDDLE SCHOOL New Middle School

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke General Contractors, LLC Construction Budget - $48,000,000 Construction Period – July 2019 – May 2021 Status - Schematic Design in progress Project Scope – New Middle School

26

Page 27: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget – $23,000,000 Construction Period – March 2019 – May 2020 Status – Approval of Contractor to be recommended at February Board Project Scope – New Elementary School

Rendering of Rancho Del Lago Elementary School 27

Page 28: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

NORTHSIDE NATATORIUM Pool Replacement

Architect – Nextgen Architects

Contractor – Henock Construction, LLCContract Amount - $2,430,000

Construction Period – March 2019 – July 2019Status – Demolition (March 15, 2019)

Existing Pool

Project Scope – Pool Replacement

NISD Project Manager – James Evans

28

Page 29: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS

Flanking Steel Pylons

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – Spaw Glass Contract Amount - $350,000 Construction Period – March 2019 – April 2019 Status – Construction Project Scope – Plaza Pylons

29

Page 30: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2019

30

Page 31: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

JOHN MARSHALL HIGH SCHOOL Library Upgrades

Architect – Garza Bomberger & Associates

Contractor – TBD Construction Budget - $3,000,000 Construction Period – Spring 2019 – Spring 2020 Status – Construction Drawings in Progress

Project Scope – Library Addition & Renovation

Interior View

NISD Project Manager – James Evans

31

Page 32: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

NORTHSIDE ALTERNATIVE MIDDLE SCHOOL Science Classroom Addition

Architect – C.J. Lammers & Associates Project Architect – Chris Lammers NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $600,000 Construction Period – June 2019 – October 2019 Status - Bidding

Project Scope – Science Classroom Addition & Renovation

32

Page 33: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

NEW CONSTRUCTION

PROJECTS IN DESIGN2018 BOND PROJECT

33

Page 34: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

"GALM ROAD AREA" HIGH SCHOOL

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – James Berg Contractor – Joeris Contractors Construction Budget - $112,000,000 Construction Period – February 2020 – June 2022 Project Scope – New High School Schematic Design in progress

34

Page 35: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2018 BOND PROJECTS

ADDITIONS/RENOVATIONS

IN DESIGN

35

Page 36: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2019 SECURITY LOBBIES FOR 21 CAMPUSES

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $2,980,000 Construction Period – June 2019 – December 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope – Security Lobbies

Behlau ES Fisher ES Martin ESBurke ES Galm ES Murnin ESCarson ES Hatchett ES Oak Hills Terrace ESDriggers ES Langley ES Ott ESElrod ES Lewis ES Raba ESEvers ES Lieck ES Westwood ESFernandez ES Martin ES Northside Police Department

36

Page 37: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Contract Amount - $4,000,000 Construction Period – June 2019 – July 2020 Status – Bidding Project Scope – Library and Classroom Building

Library - Reading AreaFront Entry37

Page 38: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

NORTHWEST CROSSING ELEMENTARY SCHOOL Cafeteria / Kitchen Renovation

Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $2,000,000 Construction Period – June 2019 – December 2019 Status - Bidding

Project Scope – Cafeteria / Kitchen Renovation

Cafeteria Proscenium - Prespective View 38

Page 39: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

PAT NEFF MIDDLE SCHOOL Cafeteria Upgrades

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $3,200,000 Construction Period – June 2019 – February 2020 Status - Master Plan and Schematic Design in progress

Project Scope – Cafeteria Upgrades

39

Page 40: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

MEADOW VILLAGE ELEMENTARY SCHOOL ALE & Mechanical Upgrades

Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,400,000 Construction Period – June 2019 – November 2019 Status - Approval of Contractor to be recommended at February Board.

Project Scope – ALE and Mechanical Upgrades

40

Page 41: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

WILLIAM P. HOBBY MIDDLE SCHOOL Bus / Student Covered Walkway

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $2,800,000 Construction Period – June 2019 – December 2019 Status - Bidding

Project Scope – Bus / Student Covered Walkway and Front Entry

Canopy Rendering

41

Page 42: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

SANDRA DAY O'CONNOR HIGH SCHOOL Agricultural Facility Upgrade

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,275,000 Construction Period – March 2019 – July 2019 Status - Approval of Contractor to be recommended at February Board.

Project Scope – Agricultural Facility Upgrade

New Configuration of Building P 42

Page 43: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

SANDRA DAY O'CONNOR HIGH SCHOOL Flooring Replacement

Architect – Callins Watts Sendejo Architects Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $150,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.

Project Scope – Flooring Replacement

43

Page 44: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

OLIVER WENDELL HOLMES HS & JOHN JAY HS Paint Booth Replacement

Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $300,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.

Project Scope – Paint Booth Replacement

44

Page 45: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2019 DOOR HARDWARE PROJECT Various Campuses

Architect – Huckabee Associates Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $461,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.

Project Scope – Door Hardware

R.R. Cable ES Leon Valley ES Northwest Crossing ES

William J. Thornton ES Eduardo Villarreal ES Anson Jones MS

45

Page 46: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

ROOFING PROJECTS

46

Page 47: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2016 Hail Damage Roofing Projects

Phase IV - In Construction

Phase I - Complete

Beard Elementary School

Carnahan Elementary School

Clark High School

Stevenson Middle School

Carlos Coon Elementary School

Elrod Elementary School

Phase II – Complete

Esparza Elementary School (Closed out)

Nichols Elementary School (Closed out) Connally Middle School (Closed out)

Howsman Elementary School (2014 Bond) Leon Valley Elementary School (Closed out)

Scarborough Elementary School (Closed out)

Alternative ES & MS - North (Closed out)

Burke Elementary School (Closed out)

Brauchle Elementary School

Leon Springs Elementary School

Raba Elementary School

Phase III – In Construction

Burke Elementary School (2014 Bond)

Clark High School

Helotes Elementary School

O’Connor High School (1st Phase) Rhodes Elementary School

Sul Ross Middle School

Steubing Elementary School

Portable Roofs – Phase II (102)

Vale Middle School

Zachry Middle School Driggers Elementary School

Briscoe Middle School

Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Family Engagement Center

Northwest Crossing Elementary

Henderson Elementary School Knowlton Elementary School

Maintenance Building (2014 Bond)

LIST OF SC HOOLS

Portable Roofs -(Substantial Completion)

South Transportation Station Fernandez Elementary School

MEP Hail Damage -Various Campuses (54)

47

Page 48: Facilities Construction · 2019-12-13 · Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Superstructure work in progress

2016 Hail Damage Roofing Projects

Phase V - Design

O'Connor High School (2nd Phase)

Brandeis High School (1st Phase)

Stinson Middle School

Kuentz Elementary School

John Jay High School(2014/2018 Bond)

Hobby Middle School

Phase VI – Future

Support Services Center

Oak Hills Terrace Elementary School Kelly Smith Technology Center

Taft High School Northside Activity Center

North Transportation Station

Pease Middle School

Health Careers High School

Northside Tennis Center

Jefferson Middle School

John Glenn Elementary School(2014 Bond)

Mireles Elementary

Brennan High School Holmes High School

Rhodes Transportation Center Ward Elementary School

McDermott Elementary School

Mead Elementary School

Myers Elementary School

Adams Hill Elementary School(2018 Bond)