Facilities Project Management Monthly Report Friday, May 29, 2020 216 Approved Projects 9 BOIE, GREGG J Rudman Hall Clean Steam Generator Replacement 1.1PLAN/EST RR 5/28/20 Project Suspended due to the COVID19 3/23/20 Petersen Engineering is scheduled for site visit the 2nd week of March. Design Firm: Contractor: 20190067 Year Approved Funding: DMA PROJECT SUSPENDED Nesmith Hall Air Sourced Heat Pump suite 107 1.1PLAN/EST FCR 5/28/20 Project Suspended due to the COVID19 3/23/20 Design Firm: Contractor: 20190227 Year Approved Funding: COLLEGE / DEPT ALLOC PROJECT SUSPENDED Nesmith Hall Door Automation and Directional Signage 1.1PLAN/EST FCR 5/28/20 Project Suspended due to the COVID19 3/23/20Yates has PO for electrical will postpone Design Firm: Contractor: Yates And Portsmouth sign 20200008 Year Approved Funding: COLLEGE / DEPT ALLOC PROJECT SUSPENDED 2 Leavitt Lane new natural gas boiler 1.1PLAN/EST FCR 4/30/20 Project Suspended due to the COVID19 3/23/20 Design Firm: Contractor: 20200054 Year Approved Funding: COLLEGE / DEPT ALLOC PROJECT SUSPENDED Dimond Library Guidance on furniture & design 1.1PLAN/EST FCR 5/28/20 Project Suspended due to the COVID19 3/23/20 Design Firm: Contractor: 20200061 Year Approved Funding: COLLEGE / DEPT ALLOC PROJECT SUSPENDED Kingsbury Hall RM S311 Laboratory Ventilation 1.1PLAN/EST FCR 5/28/20 Project Suspended due to the COVID19 3/23/20 Design Firm: Contractor: 20200210 Year Approved Funding: COLLEGE / DEPT ALLOC PROJECT SUSPENDED McConnell Hall Roof Leak Investigation and Repair 1.1PLAN/EST RR 5/28/20 Project Suspended due to the COVID19 3/23/20 Careno and Building Envelope Specialists will review the Atrium..at a later date to be determined Design Firm: Contractor: 20200212 Year Approved 2020 Funding: DMA PROJECT SUSPENDED Friday, May 29, 2020 Page 1 of 29 University of New Hampshire Brenda Whitmore, Director Facilities Project Management

Upload: others

Post on 10-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Facilities Project Management Monthly Report 

Friday, May 29, 2020 216Approved Projects

9BOIE, GREGG J

Rudman Hall ‐ Clean Steam Generator Replacement1.1‐ PLAN/EST RR

5/28/20 Project Suspended due to the COVID‐19  3/23/20

  Petersen Engineering  is scheduled for site visit the 2nd week of March.

Design Firm: Contractor:

2019‐0067

Year Approved

Funding: DMA PROJECT SUSPENDED

Nesmith Hall ‐ Air Sourced Heat Pump suite 1071.1‐ PLAN/EST FCR

5/28/20  Project Suspended due to the COVID‐19  3/23/20

Design Firm: Contractor:

2019‐0227

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Nesmith Hall ‐ Door Automation and Directional Signage1.1‐ PLAN/EST FCR

5/28/20  Project Suspended due to the COVID‐19  3/23/20Yates has PO for electrical will postpone

Design Firm: Contractor: Yates  And Portsmouth sign

2020‐0008

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

2 Leavitt Lane ‐ new natural gas boiler1.1‐ PLAN/EST FCR

4/30/20  Project Suspended due to the COVID‐19  3/23/20

Design Firm: Contractor:

2020‐0054

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Dimond Library ‐ Guidance on furniture & design1.1‐ PLAN/EST FCR

5/28/20  Project Suspended due to the COVID‐19  3/23/20

Design Firm: Contractor:

2020‐0061

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Kingsbury Hall ‐ RM S311 Laboratory Ventilation1.1‐ PLAN/EST FCR

5/28/20 Project Suspended due to the COVID‐19  3/23/20

Design Firm: Contractor:

2020‐0210

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

McConnell Hall ‐ Roof Leak Investigation and Repair1.1‐ PLAN/EST RR

5/28/20 Project Suspended due to the COVID‐19  3/23/20 Careno and Building Envelope Specialists will 

review the Atrium..at a later date to be determined

Design Firm: Contractor:

2020‐0212

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Friday, May 29, 2020 Page 1 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 2: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Taylor Hall ‐ Communications and Marketing Relocation2‐ IN DESIGN SI

4/30/20  Project Suspended due to the COVID‐19  3/23/20Placework gave proposal and I filled out the PO just 

missing the fund number when the work from home started and will be on hold

Design Firm: Placework Contractor:

2019‐0146

Year Approved

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Parsons Hall ‐ Rm S128 Ammonia Gas Control System3‐ IN CONSTRUCTION FCR

5/28/20  Project Suspended due to the COVID‐19  3/23/20On hold until we return to the Campus .

Design Firm: Norris Contractor: Norris

2017‐0431

Year Approved2018

Funding: COLLEGE / 

DEPT ALLOC

7BRICKETT, ALEXANDER J

Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative3‐ IN CONSTRUCTION CP

CAPITAL PROJECT 5/28/2020 GMP 3‐ Phase I contract executed. Steel erection completed. Dtailing in progress. Exterior utility 

work in progress. Mechanical, electrical and plumbing work in Spaulding basement, Rudman basement, and 

Parsons basement underway.

Design Firm: Ellenzweig Contractor: Skanska USA Building

2016‐0278

Year Approved2016

Funding: SARRC 

ALLOC

Spaulding Hall ‐ Utility and Infrastructure3‐ IN CONSTRUCTION FCR

5/28/2020 ‐ Please see Project #2016‐0278 for updates.

Design Firm: Contractor:

2020‐0246

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Campus Wayfinding ‐ Phase 33.1‐ SUBSTANTIAL COMPLETION SI

5/28/2020 ‐ . Additional items to be added to scope pending funding availability. 101 Sign Repair Design in 

progress.

Design Firm: Contractor:

2016‐0156

Year Approved2019

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Morse Hall ‐ Third Floor Tepid Water Loop3.1‐ SUBSTANTIAL COMPLETION RR

5/28/2020  ‐  Final inspection to be completed with installation of connected eyewash station.

Design Firm: Contractor: GSPH

2017‐0004

Year Approved2017

Funding: DMA

Whittemore Center ‐ Arena ‐ Dehumidification System3.1‐ SUBSTANTIAL COMPLETION FCR

5/28/2020  ‐ New unit has been installed. Commissioning to wrap up fall 2020.

Design Firm: Harriman Contractor: Careno Construction

2017‐0308

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Parsons Hall ‐ Processed Chilled Water System Replacement3.1‐ SUBSTANTIAL COMPLETION RR

5/28/2020  ‐ Water berm installed. Controls programming for auto‐refill in progress.

Design Firm: Harriman Contractor: Northern Peabody

2018‐0048

Year Approved2019

Funding: DMA

Friday, May 29, 2020 Page 2 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 3: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Stoke Hall ‐ First Floor Renovation/Paul College Program3.1‐ SUBSTANTIAL COMPLETION FCR

5/28/2020 ‐ Main Door Replaced. Punchlist in progress.

Design Firm: Office Interiors Contractor: Milestone

2018‐0225

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

19GEUTHER, MARK E

Field House ‐ Women’s Team and General Locker Rooms – Design‐Only1.1‐ PLAN/EST SI

05‐28‐2020: Project suspended effective 3‐23‐2020 due to COVID‐19

Design Firm: Harriman Contractor: TBD

2019‐0163

Year Approved

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

10 West Edge Drive ‐ Roof and HVAC Replacement1.1‐ PLAN/EST RR

05‐28‐2020: Project suspended on 03‐23‐2020 due to COVID‐19.

Design Firm: Petersen Eng./Hoyle‐Tanner Contractor: TBD

2019‐0260

Year Approved

Funding: DMA PROJECT SUSPENDED

Whittemore Center ‐ Arena ‐ Ice and Arena Renovations1.1‐ PLAN/EST FCR

05‐28‐2020: Effective 3‐23‐2020 Project on hold due to Financial consideration related to the COVID‐19 

pandemic. It is anticipated that the project will move forward in April of 2021.

Design Firm: RFS Engineering Contractor: PC Construction

2020‐0001

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Field House ‐ Replacing office doors1.1‐ PLAN/EST FCR

05‐28‐2020: Project suspended on 3‐23‐2020 due to COVID‐19

Design Firm: N/A Contractor: Charters Brothers

2020‐0052

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Thermal Energy Storage Tank Feasibility Study1.1‐ PLAN/EST FCR

05‐28‐2020: Consultant close to publishing study report.

Design Firm: H.F. Lenz Company Contractor: TBD

2020‐0159

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Field House ‐ Volleyball Locker Room Renovation1.1‐ PLAN/EST FCR

05‐28‐2020: Project suspended effective 3‐23‐2020 due to COVID‐19

Design Firm: Contractor: TBD

2020‐0236

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Child Study & Development Center ‐ Decks1.1‐ PLAN/EST FCR

05‐28‐2020: Will follow up with client

Design Firm: Contractor: TBD

2020‐0250

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 3 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 4: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Field House ‐ Glass Wall, Outdoor Deck/Roof and Door Replacement Design Only2‐ IN DESIGN RR

05‐28‐2020: Meet with Design team on site. Design underway.

Design Firm: LaVallee Brensinger Contractor: TBD

2013‐1044

Year Approved2021

Funding: DMA

Child Study & Development Center ‐ Playground Repairs2‐ IN DESIGN FCR

05‐28‐2020: Pricing is over budget. Working thru prioritizing playground features

Design Firm: Ironwood Contractor: T&S Construction

2020‐0173

Year Approved2020

Funding:

Field House ‐ Pool Chemical Storage  ‐ Design Only2‐ IN DESIGN RR

05‐28‐2020: Design is continuing.

Design Firm: Weston & Sampson Contractor: TBD

2020‐0181

Year Approved2020

Funding: INST RR

Water Treatment Plant ‐ New Construction3‐ IN CONSTRUCTION SI

05‐28‐2020: FFE Installation complete. Site work and C of O corrections on going.

Design Firm: Woodard & Curran Contractor: Waterline Industries

2008‐0038

Year Approved2014

Funding: SARRC 

ALLOC

Field House ‐ 1st Floor AC Installation3‐ IN CONSTRUCTION SI

05‐28‐2020:  Project will start back up mid‐June. Athletic flooring on order.

Design Firm: Harriman Contractor: Charters Brothers

2011‐0653

Year Approved2019

Funding: SARRC 

ALLOC

Kendall Hall ‐ 3rd Floor Repurposing3‐ IN CONSTRUCTION SI

05‐28‐2020:  Finishes, balancing, and final inspections on going. Anticipate the project to be substantially 

complete mid‐June. FFE on order, early August installation anticipated.

Design Firm: Manypenny Murphy Contractor: Charters Brothers

2019‐0158

Year Approved2019

Funding: SARRC 

ALLOC

Kendall Hall ‐ 4th Floor Repurposing3‐ IN CONSTRUCTION SI

05‐28‐2020: See 2019‐0158

Design Firm: Manypenny Murphy Contractor: Charters Brothers

2019‐0161

Year Approved2019

Funding: SARRC 

ALLOC

Telecommunications Center ‐ Addition and Renovation3‐ IN CONSTRUCTION FCR

05‐28‐2020: Siding panels  and roofing substantially complete. Topping slab scheduled for 5‐29‐2020. curtain 

wall installation scheduled for late June.

Design Firm: Oak Point Contractor: Charters Brothers

2019‐0292

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 4 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 5: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Outdoor Facility ‐ New Soccer ‐ Lacrosse Field3.1‐ SUBSTANTIAL COMPLETION FCR

05‐28‐2020: Project is substantially complete. Waiting on close out documents

Design Firm: Tighe & Bond Contractor: R.A.D. Sports

2017‐0285

Year Approved2018

Funding: COLLEGE / 

DEPT ALLOC

Campus ‐ South Drive ‐ Temporary Connection to Colovos Road3.1‐ SUBSTANTIAL COMPLETION SI

05‐28‐2020: Substantially Complete. Need loops cut in for gate

Design Firm: Tighe & Bond Contractor: R.A.D. Sports

2018‐0267

Year Approved2019

Funding: SARRC 

ALLOC

Field House ‐ Football Locker Room Renovation – Phase II3.1‐ SUBSTANTIAL COMPLETION FCR

05‐28‐2020: Waiting on close out documents

Design Firm: Manypenny Murphy Contractor: Vantage Builders

2019‐0102

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Field House ‐ UV Filter Replacement3.1‐ SUBSTANTIAL COMPLETION RR

05‐28‐2020: Waiting on close out documents.

Design Firm: Weston & Sampson Contractor: Charters Brothers

2019‐0306

Year Approved2019

Funding: DMA

16HEISNER, MICHELE

Nesmith Hall ‐ Life Safety Review1.1‐ PLAN/EST RR

05/27/20 ‐ Report received on 04/15/20. Next steps to be determined.

Design Firm: Contractor:

2019‐0251

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Chase Ocean Engineering ‐ High Bay Lighting Replacement1.1‐ PLAN/EST FCR

05/27/20 ‐ Project suspended 3/23/20  due to Covid‐19. Schedule TBD.

Design Firm: Contractor:

2020‐0077

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Parsons Hall ‐ Convert room to 70‐seat TEAL Classroom1.1‐ PLAN/EST FCR

05/27/20‐ Project suspended 3/23/20 due to Covid‐19. Schedule TBD.

Design Firm: Contractor:

2020‐0171

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Putnam Hall ‐ Spaulding Hall Swing Space1.1‐ PLAN/EST SI

05/27/20 ‐ Space in Putnam Hall temporarily utilized for ʹbunk spaceʹ to support potential use of Hamel Rec 

as Covid 19 related overflow. Planning continues for move logistics of collections.

Design Firm: Contractor:

2020‐0204

Year Approved

Funding:

Friday, May 29, 2020 Page 5 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 6: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

HSI CHHS Modular Building1.1‐ PLAN/EST FCR

05/27/20‐ RFQ anticipated to be issued first week of June. RFP for design/build services to follow.  Continued 

discussion on modular construction logistics.

Design Firm: Contractor:

2020‐0231

Year Approved2020

Funding:

Hewitt Hall ‐ Rm G02 Sound Proof1.1‐ PLAN/EST FCR

05/27/20 ‐ Project suspended on 3/23 due to Covid‐19. Schedule TBD.

Design Firm: Contractor:

2020‐0243

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Spaulding Hall ‐ Move Coordination and Support1.1‐ PLAN/EST FCR

05/27/20 ‐Project is part of Spaulding and in support of swing space and move coordination. In planning

Design Firm: Contractor:

2020‐0249

Year Approved

Funding:

James Hall ‐ Suite 364 Fire Alarm Strobes1.1‐ PLAN/EST FCR

05/27/20 ‐ Fire Alarm strobes required in auxiliary cleanroom lab. Work to be performed along with 2020‐

0252 project.

Design Firm: Contractor:

2020‐0251

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

James Hall ‐ Suite 364 Lab Repairs1.1‐ PLAN/EST FCR

05/27/20‐ Details discussed with Kevan Carpenter. More information gathered from Lab users re: sink and 

eyewash location.

Design Firm: Contractor:

2020‐0252

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Campus ‐ USNH Zoom Capable Classrooms1.1‐ PLAN/EST FCR

05/27/20 ‐ First two phases of rooms identified. Walked through with Academic Technology; permitting 

process underway. Yates Electrical performing work.

Design Firm: Contractor: Yates Electrical

2020‐0274

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Hubbard Hall ‐ Bedroom Doors1.1‐ PLAN/EST FCR

05/27/20 ‐ Cost estimates finalized as of 05/27; to be forwarded to Housing for review and consideration.

Design Firm: Contractor:

2020‐0278

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Woodside Apts Community Building ‐ Air Handler Replacement2‐ IN DESIGN FCR

05/27/20  Project Suspended due to the COVID‐19

Design Firm: Petersen Engineering Contractor:

2019‐0307

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Friday, May 29, 2020 Page 6 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 7: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Morse Hall ‐ Rm 419 Adding New Equipment2‐ IN DESIGN FCR

05/27/20 ‐ 100% construction drawings to be issued on 05/29.

Design Firm: SMRT Contractor:

2020‐0190

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Congreve Hall ‐ Bathroom Retrofit2.5‐ IN PROCUREMENT FCR

05/27/20  Project Suspended due to the COVID‐19

Design Firm: SMRT Contractor:

2020‐0167

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

McLaughlin Hall ‐ Abatement and Carpeting2.5‐ IN PROCUREMENT FCR

05/27/20 ‐ suspended 3/23/20  Bids were received on 4/3/20. Procurement notified bidders that award 

determination was postponed due to Covid‐19. Project suspended due to Covid‐19. Schedule TBD.

Design Firm: Placework Contractor:

2020‐0179

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

James Hall ‐ Rm 185 Autoclave Replacement3‐ IN CONSTRUCTION RR

05/27/20 ‐ Testing of autoclave to occur in next two weeks.

Design Firm: Contractor:

2017‐0315

Year Approved2018

Funding: DMA

29HENRY, PAUL A

Health & Wellness ‐ COVID‐19 Testing Instrumentation1‐ ASSIGNED FCR

Design Firm: Contractor:

2020‐0281

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Huddleston Hall ‐ Creation of Offices within Carsey School1.1‐ PLAN/EST FCR

5‐28‐20  Project Suspended due to the COVID‐19  3/23/20

briniging entire project up to DD level to include MEP, deliverables are scheduled for August 2020

Design Firm: Harriman Contractor:

2017‐0402

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Stoke Hall ‐ Gas Code Violations1.1‐ PLAN/EST FCR

5‐28‐20  Laundry room fairly straight forward with a combinded tempered MUA system, lookeing further at 

the generator room, trying to verify date of installaiong to apply the correct year code.

Design Firm: Contractor:

2020‐0012

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 7 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 8: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Paul Creative Arts Center ‐ Johnson Theatre Renewal ‐ Design Only1.1‐ PLAN/EST RR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Working with Harriman for a design Proposal

Design Firm: Contractor:

2020‐0165

Year Approved2021

Funding: DMA PROJECT SUSPENDED

Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan2‐ IN DESIGN RR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20 

bringing entire project up to DD level to include MEP, deliverables are scheduled for August 2020    

Harriman has provided the Ballroom Occupancy Calcs to the SFMO this task is closed.

Design Firm: SFC Engineering Partnership Contractor:

2012‐0841

Year Approved2019

Funding: DMA PROJECT SUSPENDED

South Drive ‐ Design Advancement2‐ IN DESIGN SI

5‐28‐20 looking at moving the road to the existging Water Works Road location. Working on concept designs 

with Campus Plannign and Tighe & Bond

Design Firm: Tighe & Bond Contractor:

2013‐1115

Year Approved2013

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Huddleston Hall ‐ Design of Egress Modifications2‐ IN DESIGN RR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Bringing design up to DD, to included Roof, and Mechanical Systems. DD to be complete by end of summer 

tbd 

work on CDʹs to include selecting a CM for estimating and preconstruction pre site investigation of system 

routes and obstructions. Construction tentative schedule starting phases 2022‐2023.

Design Firm: Harriman Contractor: Harriman

2013‐1155

Year Approved2017

Funding: DMA PROJECT SUSPENDED

Paul Creative Arts Center ‐ Sprinkler Installation ‐ Design Only2‐ IN DESIGN RR

5‐28‐20  Issuing PO to Harriman to start desiign

Design Firm: Contractor:

2016‐0032

Year Approved2021

Funding: DMA

Huddleston Hall ‐ Roof Replacement Design Only2‐ IN DESIGN RR

5‐28‐20  Project Suspended due to the COVID‐19  3/23/20 

Bringing roof design up to DD by August 2020

Design Firm: ARM Contractor: Harriman

2016‐0165

Year Approved2017

Funding: DMA PROJECT SUSPENDED

Friday, May 29, 2020 Page 8 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 9: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Philbrook Hall ‐ Steam Study and Investigation2‐ IN DESIGN RR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

 Waiting for final Report, working with RFS & EF to install the boiler.

RFS provided three (3) options for steam study.  UNH has decided to proceed with using the steam boiler at 

Philbrook for hot water make up, this will allow the local steam boiler to operate between August ‐ May with 

continuation operation.  During Summer when Philbrook is not open the boiler will be put in dry layup with 

service assistance from Blake Engineering.  Intend to have local boiler online January 2019.

Design Firm: RFS Contractor: Eckhardt Johnson

2018‐0162

Year Approved2019

Funding: DMA

Utility Distribution ‐ Lee Circle Water Line Extension2‐ IN DESIGN FCR

5‐28‐20   Project to continue‐ did not appear on original list‐ Town Money

 Design is at DD, Project is +‐ 3 million over budget, working on Easements, Construction summer tbd

Design Firm: Underwood Eng Contractor: TBD

2018‐0256

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Paul Creative Arts Center ‐ Fire Alarm Design Only2‐ IN DESIGN RR

5‐28‐20  Issuing PO to Harriman for Design

Design Firm: TBD Contractor: TBD

2019‐0055

Year Approved2020

Funding: DMA

Paul Creative Arts Center ‐ Building Life Safety Report Update2‐ IN DESIGN RR

5‐28‐20  Have funding for design FY 2020

Addendum to Life Safety plan to be reviewed and approved with the SFMO.

Design Firm: Contractor:

2019‐0241

Year Approved2019

Funding: DMA

Concord ‐ UNH School of Law ‐ Student Services Consolidation2‐ IN DESIGN FCR

5‐28‐20  Project Suspended due to the COVID‐19  3/23/20 

UNH Law& HL Turner wrapping up design, DBB, construction summer tbd

Design Firm: CP Contractor:

2019‐0277

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Thompson Hall ‐ UNH Testing Center ‐ Phase 22‐ IN DESIGN SI

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Working on design, just had new input from Ted K. Placework are working on changes.

Design Firm: TBD Contractor: TBT

2019‐0322

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Elliott Alumni Center ‐ New Patio Stair Design Services2‐ IN DESIGN FCR

5‐28‐20  Project Suspended due to the COVID‐19  3/23/20

Funding Design PO Processed, presented budget information, waiting for direction.

Design Firm: MPM Contractor: TBD

2019‐0394

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Friday, May 29, 2020 Page 9 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 10: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Morse Hall ‐ Former Clean Rm Renovation2‐ IN DESIGN SI

5‐28‐20  Space to support Spaulding swing, final program has not been identified, First steps is to clean out 

the rooms, move existing freezer, and add door to corridor A375A. EOS will be primary occupant when 

finished. Have fundign for Design 2021 and Construction FY2022

Design Firm: Harriman Contractor: tbd

2020‐0189

Year Approved2020

Funding: SARRC 

ALLOC

Whittemore Center ‐ Arena ‐ Fire Alarm and Sound System Control Panel Repairs2‐ IN DESIGN FCR

5‐28‐20  Working with SFC to come up with a code complyant solution

Design Firm: SFC Eng. Contractor: Norris ‐ Scarponi

2020‐0229

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements2.5‐ IN PROCUREMENT FCR

5‐28‐20  Contract in signature circulation, working on budget issue with team. May have to remove scope of 

work to put back in the budget box.

Design Firm: Evan Mullen Contractor: Careno Const.

2017‐0447

Year Approved2018

Funding: GRANT

Holloway Commons ‐ Conference Area Carpeting Replacement2.5‐ IN PROCUREMENT FCR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Charter Brothers Low Bidder, construction tbd

Design Firm: Harriman Contractor: TBD

2018‐0195

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Paul Creative Arts Center – ADA Improvements – Music Wing Elevator2.5‐ IN PROCUREMENT SI

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20 

 2016 DD design to 2020 CD design. Selected Charter Brothers as CMAR. Construction tbd

Design Firm: Harriman Contractor: tbd

2018‐0273

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Campus ‐ Tennis Court Renovation2.5‐ IN PROCUREMENT FCR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20‐ 

 Bids in, Low bidder JTI, Processing FCR for PO & Project Costs, Contract pulled until further notice.

Design Firm: Tighe & Bond Contractor: TBD

2019‐0139

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Elliott Alumni Center ‐ 1925 Room2.5‐ IN PROCUREMENT FCR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Structuretone low bidder.

Design Firm: Manny Penny Murphy Contractor: TBD

2019‐0191

Year Approved2019

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Friday, May 29, 2020 Page 10 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 11: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Philbrook Hall ‐ Bathroom and Locker Room Renovation2.5‐ IN PROCUREMENT FCR

5‐28‐20   Project Suspended due to the COVID‐19  3/23/20

Selected Charter Brothers as CMAR, Looking to start Pre‐Construction services.

Design Firm: Harriman Contractor: Charter Brothers

2020‐0162

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Hood House ‐ Minor Renovation for Career and Professional Success Center3‐ IN CONSTRUCTION SI

5‐28‐20  Starting planting today, Yates running exterior receptical for LV lights.

Design Firm: Woodburn Landscaping Contractor: Belko Landscaping

2016‐0409

Year Approved2016

Funding: SARRC 

ALLOC

Elliott Alumni Center ‐ Building HVAC Modifications and Improvements3‐ IN CONSTRUCTION RR

5‐28‐20   Structuretone starting today to work on punch list and code compliant issues.

Design Firm: HARRIMAN Contractor: StructureTone

2019‐0048

Year Approved2020

Funding: DMA

Horton Social Science Center ‐ G04 Auditorium – Air Conditioning3.1‐ SUBSTANTIAL COMPLETION SI

5‐28‐20 Chasing down some balancing issues ‐waiting to return to campus

Design Firm: Harriman Contractor: Structuretone

2010‐0411

Year Approved2019

Funding: SARRC 

ALLOC

New England Center ‐ Boiler Replacement and BAS Controls3.1‐ SUBSTANTIAL COMPLETION RR

5‐28‐20  Boilers sequencing seems to be working after Factory rep spent the day on site, working on sump 

pumps, illicit discharge into sanitaryre‐piping to exterior catch basin on the North side of building in the 

process of scheduling

System is currently heating the building

Design Firm: Harriman Contractor:

2016‐0403

Year Approved2020

Funding: DMA

Philbrook Hall ‐ Boiler Replacement3.1‐ SUBSTANTIAL COMPLETION FCR

5‐28‐20   Still having issues with condensate pumps, Installed new float switch, have had mfg. rep on site 

trying to figure out the issues.

Design Firm: RFS Contractor: Eckardt & Johnson

2019‐0304

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

34HOUDE, DONALD A

Service Building ‐ Durham Fire Department Improvements1.1‐ PLAN/EST FCR

5‐28‐20 Project approved to move forward DFD has funding email sent to Don Houde 5/5/20 from Mike 

Mason/Chief Emanuel  5‐27‐20 I have notified B.W. that project2016‐0123 must be funded before I can 

proceed with this work.

Design Firm: McHenry Architecture Contractor:

2019‐0279

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 11 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 12: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Utility Distribution ‐ Morse Circle ‐ Circuit 111.1‐ PLAN/EST RR

5‐24‐20  No work here until at least after the Dual temp line installation.

Design Firm: Contractor: ICR

2020‐0019

Year Approved2021

Funding: DMA

1 Leavitt Lane ‐ Convert boiler to natural gas1.1‐ PLAN/EST FCR

5‐30‐20 Project Suspended on 3‐23‐20  ‐ Gas line is in place.

Design Firm: OPA Contractor:

2020‐0055

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

6 Leavitt Lane ‐ New Gas Line and Boiler1.1‐ PLAN/EST FCR

5‐28‐20  Conversion Project Suspended 3‐23‐20 But, N.U. has had NEUCCO co install all underground gas 

lines at the LL sites.

Design Firm: OPA Contractor:

2020‐0056

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

10 West Edge Drive ‐ Gas Piping1.1‐ PLAN/EST FCR

5‐28‐20 Project Suspended 3‐23‐20. Gas line is in place.

Design Firm: OPA Contractor:

2020‐0060

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Christensen Hall ‐ Relocate Electric panels1.1‐ PLAN/EST FCR

5‐28‐20 Project Suspended on 3‐23‐20.

Design Firm: Harriman Contractor:

2020‐0168

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Morse Hall ‐ Stand By Generator and Distribution ‐ Design ONLY1.1‐ PLAN/EST SI

5‐24‐2020  We are looking into all issues.I started by making contact with David Divins. I will be providing 

an encumbrance for logging of the generator loads.

Design Firm: Contractor:

2020‐0214

Year Approved2020

Funding: SARRC 

ALLOC

Demeritt Hall ‐ Research Lab Stand By Power Design1.1‐ PLAN/EST SI

5‐28‐20 Project Suspended on 3‐23‐20.

Design Firm: Contractor:

2020‐0215

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Conant Hall Transformer Upgrade1.1‐ PLAN/EST FCR

5‐28‐2020  Excavation and start of Utility conduit installation, this week.

Design Firm: Contractor: ICR‐Yates

2020‐0225

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 12 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 13: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Morse Hall ‐ Card Access for Lenharth Data Center1.1‐ PLAN/EST FCR

5‐30‐20 Project Suspended 3‐23‐20.

Design Firm: Contractor:

2020‐0240

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Field House ‐ Indoor Pool Electrical Service Replacement2‐ IN DESIGN RR

5‐28‐20 Project Suspended on 3‐23‐20.

Design Firm: Harriman Contractor:

2012‐0824

Year Approved2021

Funding: DMA PROJECT SUSPENDED

Paul Creative Arts Center ‐ High Voltage Electrical Service Replacement2‐ IN DESIGN RR

5‐26‐20  This project to bring Electrical power to the rear of PCAC to create a newMain Electrical Service 

room for the whole building. Our main objective is to be prepared to supply power to the new Elevator 

project this summer.. The HV contractor has a PO.

             5‐26‐20 I am prepairing to have the underground HV ductbank only installed from the Spaulding 

sector cabinet to the new PCAC transformer location.

Design Firm: Harriman Contractor:   ICR

2017‐0106

Year Approved2021

Funding: DMA

Combined Heat & Power Plant ‐ Steam to HW Heat Exchanger Replacements Phase 

Design Only2‐ IN DESIGN RR

5‐28‐20 Project suspended on 3‐23‐20.

Design Firm: Harriman Contractor:

2019‐0063

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Combined Heat & Power Plant ‐ Generator Replacement2‐ IN DESIGN RR

5‐30‐20 Project Susprnded on 3‐23‐20.

Design Firm: Harriman Contractor:

2020‐0034

Year Approved2021

Funding: DMA PROJECT SUSPENDED

Service Building ‐ Dispatch Center Keltron System2.5‐ IN PROCUREMENT FCR

5‐28‐20 ‐  Contractors have POʹs and incumbrances. Some work has been started. I thought this was on Hold, 

I am getting verification. On hold for now.

Design Firm: Contractor: Norris / UNH Telecom

2016‐0123

Year Approved2018

Funding: COLLEGE / 

DEPT ALLOC

Combined Heat & Power Plant ‐ Bring the catwalk & mezzanine to code2.5‐ IN PROCUREMENT FCR

5‐30‐20 project Suspended.

Design Firm: Harriman Contractor:

2017‐0188

Year Approved2017

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Spaulding Pedestrian Bridge Circuit 11 Conduit Replacement2.5‐ IN PROCUREMENT RR

5‐23‐20  ICR  has a PO and are planning this work in conjunction with Spaulding/Rudman shutdown . Start 

for this project is now, as soon as we coordinate with the Spaulding project.

Design Firm: Contractor: IC Reed and Sons

2019‐0123

Year Approved2020

Funding: DMA

Friday, May 29, 2020 Page 13 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 14: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Dimond Library ‐ Elevator Card Access2.5‐ IN PROCUREMENT FCR

5‐30‐20 Project Suspended.

Design Firm: Housing Contractor: Stanley , Yates, Housing

2019‐0270

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Keener Dairy Research Building ‐ Rm 127A Grinding Room Safety Improvements2.5‐ IN PROCUREMENT FCR

5‐28‐20 Project Suspended on 3‐23‐20.

Design Firm: McHenry Contractor:

2019‐0318

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Christensen Hall ‐ Lighting improvements2.5‐ IN PROCUREMENT FCR

5‐28‐20 Project Suspended on 3‐23‐20.

Design Firm: Contractor: Scarponi

2020‐0039

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Circuit 11‐12 Tie Cable Upgrade2.5‐ IN PROCUREMENT FCR

5‐24‐20  . Upgrade the conductors under the RR tracks that connect cirt 12 in A lor to cirt 11 by Woodside 

appts. This Summer.Contractor has PO. Waiting on the cable.

Design Firm: Contractor: I C Reed and Sons Inc.

2020‐0185

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Presidentʹs House ‐ Security Cameras2.5‐ IN PROCUREMENT FCR

5‐30‐20 Project Suspended on 3‐23‐20

Design Firm: Contractor: Yates, Burns, Telecom.

2020‐0211

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

MacFarlane Greenhouse ‐ Renovation/Improvements3‐ IN CONSTRUCTION FCR

5‐24‐20   This project is in construction. Project meetings will be on Tuesdays from 8:30AM to 10;AM.  

Footings and foundation in place. Vestibule Firewall in construction. .New greenhouse going up.

Design Firm: SMRT Contractor: Careno

2019‐0001

Year Approved2018

Funding: COLLEGE / 

DEPT ALLOC

Campus Lot‐F ‐ Pay & Display Unit3‐ IN CONSTRUCTION FCR

5‐24‐20    Working with T&S and Dirk Timmons. Some work is done, Waiting for material.and will finish B‐

lot in June.

Design Firm: Contractor: T&S

2019‐0358

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Ritzman Laboratory ‐ Electrical Work to Circuit 123‐ IN CONSTRUCTION FCR

5‐24‐20  This project is to demo cirt 1 and to tie Ritzman lab to circuit #12., in the Summer. Contractor has PO. 

Coordinating.

Design Firm: Contractor: I C Reed & Sons inc.

2020‐0184

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 14 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 15: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Utility Distribution ‐ Lot A circuit 8 to circuit  Tie3‐ IN CONSTRUCTION FCR

5‐24‐20  . Tap into circuit #8 at A Lot and connect all the way to Woodside and remove the fyying sub. 

Summer 2020 work. Pulling new cables in on Monday.

Design Firm: Contractor: I C Reed

2020‐0186

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Utility Distribution ‐ Gables Way to Lot‐A 5KV Underground Extension3‐ IN CONSTRUCTION FCR

5‐28‐20   This work may be completed next week.

Design Firm: Contractor: I C Reed ‐

2020‐0195

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Utility Distribution ‐ Eversource Transmission Line3.1‐ SUBSTANTIAL COMPLETION FCR

5‐25‐20  The installation of undergound ductbanks is complete and the areas disturbed have been restored. 

Eversource returning to install underground cable has been installed. . We are working with Eversource on a 

planting plan for 3 areas, Gregg, F.H. and Gables to be done next Spring. 2020. Completion of bumper 

installation in A‐Lot during Spring break. Eversource has picked up material by Gregg lot.

Design Firm: Contractor:

2016‐0277

Year Approved2019

Funding: SARRC 

ALLOC

Utility Distribution ‐ Sub Station 1 ‐ Transformer and Circuit Realignment3.1‐ SUBSTANTIAL COMPLETION FCR

5‐23‐20 This work substantially complete on punchlist.

Design Firm: Contractor: ICR

2019‐0243

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Kingsbury Hall ‐ Installation of Card Access and Wireless Door Openers3.1‐ SUBSTANTIAL COMPLETION FCR

5‐23‐20  This project is substantially complete. Waiting on Housing.

Design Firm: UNH Housing Contractor: Yates & NE door.

2019‐0353

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Combined Heat & Power Plant ‐ UNH CoGen Card Access3.1‐ SUBSTANTIAL COMPLETION FCR

5‐24‐20    New,Scope with the same PN. Installing low voltage lines to bring communication to the control 

center from 23 points. Contractor has funding. Contractor intalling pathways  complete. And cable 

installation was ompleted before the shutdown.

Design Firm: Contractor: Yates Electric.

2019‐0391

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

6 Leavitt Lane ‐ interior Panel board wiring3.1‐ SUBSTANTIAL COMPLETION FCR

5‐28‐20 Project substantially complete. Generator to be installed.

Design Firm: Contractor: Yates Electric Service

2020‐0031

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Friday, May 29, 2020 Page 15 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 16: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Utility Distribution ‐ Install Underground Duct Bank in Lot‐A3.1‐ SUBSTANTIAL COMPLETION FCR

5‐24‐20  This work is substantially complete. On Punchlist.

Design Firm: Contractor: Yates Electric.

2020‐0194

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

1 Leavitt Lane ‐ Electrical Distribution Circuits In Data Center3.1‐ SUBSTANTIAL COMPLETION FCR

5‐30‐20 This work was completed before suspension. The contractor is looking for direct payment from the 

department.

Design Firm: Contractor: Yates

2020‐0239

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

20MANCINI, MATTHEW E

Rudman Hall ‐ Vivarium Upgrades ‐ Phase II1.1‐ PLAN/EST SI

5/28/2020: Design to commence soon. Previously, this project was incorrectly associated with Phase I 

Vivarium Project.

Design Firm: Contractor:

2019‐0141

Year Approved2019

Funding: SARRC 

ALLOC

Barton Hall ‐ 2nd Floor Reno for Diagnostic Labs1.1‐ PLAN/EST SI

5/28/2020: Programming meetings with stakeholders have begun. Design to begin subsequent to progress of 

2020‐0092 Cole Hall Structural Space Improvements.

Design Firm: H.L. Turner Group Contractor:

2020‐0091

Year Approved2020

Funding: SARRC 

ALLOC

Dimond Library ‐ Interior Heating Distribution ‐ Design Only2‐ IN DESIGN RR

5/28/2020: BIM model in development. Schematic Design Issue expected mid‐June.

Design Firm: Harriman Contractor:

2010‐0281

Year Approved2021

Funding: DMA

Paul College ‐ HVAC and Control Modifications from Original Construction2‐ IN DESIGN FCR

5/28/2020: Project suspended.

Design Firm: Contractor: TBD

2016‐0295

Year Approved2016

Funding: SARRC 

ALLOC

Dimond Library ‐ Comprehensive Planning Effort2‐ IN DESIGN SI

5/28/2020: Assisting Campus Planning. To be coordinated with heating hot water system renovation project.

Design Firm: Perry Dean Rogers / 

Harriman

Contractor:

2019‐0160

Year Approved2020

Funding: SARRC 

ALLOC

Cole Hall ‐ Instructional Space Improvements2‐ IN DESIGN SI

5/28/2020: Final CDs under way. Architectrual portion of wrok is expected to proceed with coompletion by 

September ʹ20. HVAC scope will be defered.

Design Firm: John L Turner Contractor:

2020‐0092

Year Approved2020

Funding: SARRC 

ALLOC

Friday, May 29, 2020 Page 16 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 17: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Rudman Hall ‐ AHU‐3 Replacement2‐ IN DESIGN RR

5/28/2020: Design nearly complete for replacement of supply AHU‐3. Project to continue.

Design Firm: SMRT Contractor:

2020‐0128

Year Approved2021

Funding: DMA

Stoke Hall ‐ Conceptual Design of Lobby & Vending Machine Relocation2‐ IN DESIGN FCR

5/28/2020: Project has beem suspended effective 3/23/20.

Design Firm: Placework Contractor:

2020‐0192

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Elliott Alumni Center ‐ Renovate Restrooms 109 & 1112.5‐ IN PROCUREMENT FCR

5/28/2020:  Project has beem suspended effective 3/23/20.

Design Firm: Placeworks Contractor: Milestone

2019‐0386

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Christensen Hall ‐ A Tower Roof Replacement2.5‐ IN PROCUREMENT FCR

5/28/2020: Bid withdrawn.  Project to be re‐bid with planned construction for Summer ʹ21.

Design Firm: Manypenny Murphy ‐ ARM Contractor: Viking Roofing

2020‐0036

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Williamson Hall ‐ A Tower Roof Replacement2.5‐ IN PROCUREMENT FCR

5/28/2020: Bid withdrawn.  Project to be re‐bid with planned construction for Summer ʹ21.

Design Firm: Placework ‐ ARM Contractor: Viking Roofing

2020‐0037

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Rudman Hall ‐ Laboratory Fume Hood Control System Replacement3‐ IN CONSTRUCTION RR

5/28/2020: Project to continue.

Design Firm: SMRT Contractor: StructureTone

2010‐0479

Year Approved2017

Funding: DMA

Rudman Hall ‐ Conversion to DDC Controls3‐ IN CONSTRUCTION RR

5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.

Design Firm: SMRT Contractor: StructureTone

2015‐2336

Year Approved2018

Funding: DMA

Rudman Hall ‐ Fire Alarm Replacement3‐ IN CONSTRUCTION RR

5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.

Design Firm: SFC / SMRT Contractor: StructureTone

2015‐2352

Year Approved2016

Funding: DMA

Friday, May 29, 2020 Page 17 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 18: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System3‐ IN CONSTRUCTION FCR

5/28/2020: Reference ID 2010‐0479 for updates. Project to continue.

Design Firm: SMRT Contractor: Structuretone

2019‐0305

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Dimond Library ‐ Rm 421 Minor Renovation3‐ IN CONSTRUCTION FCR

5/28/2020: Phase II of project to resume 6/8/20. Two‐week duration expected for architecural renovations. AV 

upgrades to follow.

Design Firm: Contractor: Malthouse Construction

2019‐0357

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Rudman Hall ‐ AHU‐3 ‐ Make Ready Repairs and Modifications3‐ IN CONSTRUCTION RR

Emergency Repair 5/28/2020: Reference ID 2020‐0128 for updates. Work remains to replace isolation valves and chilled water 

valve. Project to continue.

Design Firm: SMRT Contractor: Grainte State Plumbing & 

Heating

2020‐0015

Year Approved2020

Funding: INST RR

Stoke Hall ‐ Lounge Updates3‐ IN CONSTRUCTION FCR

5/28/2020: Design has been provided. Work to be coordinated with 2020‐0192. Project has beem suspended 

effective 3/23/20.

Design Firm: Placework Contractor:

2020‐0191

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Rudman Hall ‐ AHU‐4 Condition Assessment and Repairs3.1‐ SUBSTANTIAL COMPLETION RR

5/28/2020: Project punch list.

Design Firm: SMRT Contractor: Granite State Plumbing & 

Heating

2020‐0043

Year Approved2020

Funding: DMA

Thompson Hall ‐ Presidentʹs Office Painting, Furniture and Window Treatments3.1‐ SUBSTANTIAL COMPLETION FCR

5/28/2020: Project to continue.

Design Firm: Contractor: APC Services of New 

England

2020‐0080

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

28PETERS, NICK E

Murkland Hall ‐ Slate Roof Repairs1.1‐ PLAN/EST RR

5/27/2020 ‐ Project suspended on 3/25 and resumed 5/1.  Reached out to contractor and Asset Management to 

being building requirements.  Confirmed no building permit required.  Contractor has material on hand, and 

is working with UNH for scheduling.  Project expected to begin mid‐June.

Design Firm: Contractor: Viking Roofing

2013‐1048

Year Approved2021

Funding: DMA

Friday, May 29, 2020 Page 18 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 19: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Memorial Union Building ‐ Roof Replacement Design and Planning1.1‐ PLAN/EST BAR

27 May 2020 ‐ Project suspended 1 May.  Awaiting information from stakeholders before proceeding.

Design Firm: ARM Contractor:

2018‐0337

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Murkland Hall ‐ Rooftop Mechanical Catwalks1.1‐ PLAN/EST RR

27 May 2020. Project suspended on 23 March.  Reaching out to customers and contractors to confirm scope.  

Identified engineer consultant to reach out too.

Design Firm: Contractor: Careno

2019‐0099

Year Approved2020

Funding: DMA PROJECT SUSPENDED

FY21 Campus Envelope and Interior Painting1.1‐ PLAN/EST RR

27 May 2020:  Received quote from contractor.  Soliciting to other contractors for additional quotes.  Expect to 

receive proposals back week of 25 May.

Design Firm: N/A Contractor: Milestone

2019‐0369

Year Approved2021

Funding: INST RR

Ambulance Corp Building ‐ Envelope and Interior Repairs1.1‐ PLAN/EST RR

Emergency Repair 27  May 2020:  Project is to abate mold issues from building, and remove damaged finishes.  No restoration 

will be accomplished under this project.

Design Firm: Contractor:

2020‐0196

Year Approved2020

Funding: INST RR

Kingsbury Hall ‐ Rms N101, S145 Classroom Repairs1.1‐ PLAN/EST RR

27 May 2020 ‐ Chairs tightened 26 March.  Contractor identified arms that need to be replaced, but are in 

stock.  Looking to perform next install once Covid Restrictions are removed.  Room S145 has been put on hold 

and will need to be readdressed as a separate project to replace all existing in the room.

Design Firm: N/A Contractor: K.I.

2020‐0222

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Rudman Hall ‐ Move Mass Spectrometer Wiring  from 326 to 3211.1‐ PLAN/EST FCR

27 May 2020 ‐ Project suspended on 23 Mar.  Awaiting further information from senior leadership.

Awaiting  Identified project requirements.  Mass Spectrometer must move because research team has 

relocated to room 326.  Heat load study on new room will need to be performed, and rebalanced to 

accommodate Mass Spectrometer.  Electrical requirements have been identified.  Received proposal and 

waiting for coronavirus to settle before continuing.

Design Firm: Contractor:

2020‐0230

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Handler Hall ‐ SERC Tile and Shower Base Repairs1.1‐ PLAN/EST FCR

27 May ‐ Project Suspended on 23 March.  Customer removed and investigated behind tile and drafted 

suggestions for solution.  Proposal received.  Discussing options with Housing.

Design Firm: N/A Contractor: Sprague Floor Covering

2020‐0233

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Friday, May 29, 2020 Page 19 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 20: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Memorial Union Building ‐ Consolidate Student Service Center1.1‐ PLAN/EST FCR

27 May 2020 ‐ Project suspended on 23 March.   Awaiting further direction from senior leadership.

 Met with Design team and customers to develop scope of work.  Awaiting Design team proposal.  Expecting 

delay to receive proposal back due to Coronavirus.

Design Firm: Placework Contractor: TBD

2020‐0235

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Hewitt Hall ‐ Rm 144 Install Dutch Door1.1‐ PLAN/EST FCR

27 May 2020 ‐ Project suspended on 23 March. Performed site visit.  Received proposal. Will reconnect with 

contractor when project resumes.

Design Firm: Contractor:

2020‐0237

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Nesmith Hall ‐ Rm 107 Install Power and Mount for AV1.1‐ PLAN/EST FCR

27 May 2020 ‐ Project suspended on 23 March.   Awaiting further direction from senior leadership.

 Reached out to customer to schedule site visit.  Waiting for good time to have site visit with customer.  Will 

try to coordinate a meeting when virus settles.

Design Firm: Contractor:

2020‐0238

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Field House ‐ Lundholm Sound System1.1‐ PLAN/EST FCR

27 May 2020 ‐ Project suspended on 23 March.   Awaiting further direction from senior leadership.

Met with customer at Gymnasium.  Developed project requirements.  Customer recommended a person in 

Academic Technologies to talk to about the Gymnasium [Andy Bruns].  Awaiting Coronavirus to settle before 

proceeding.

Design Firm: Contractor:

2020‐0241

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Holloway Commons / MUB ‐ Verizon Wireless In‐Building Antenna System1.1‐ PLAN/EST FCR

27 May 2020 ‐ Met with design team on 26 May.  Project has 100% CD and we are beginning the permit 

process while the project is bid for contractor selection.

Design Firm: Verizon Wireless Contractor: Verizon Wireless

2020‐0267

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Wildcat Stadium ‐ Verizon Wireless Distributed Antenna Installation1.1‐ PLAN/EST FCR

27 May 2020 ‐ Met with design team on 26 May.  Project has 100% CD and we are beginning the permit 

process while the project is bid for contractor selection.

Design Firm: Verizon Wireless Contractor: Verizon Wireless

2020‐0268

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Whittemore Center ‐ Verizon Wireless In‐Building Cellular Antenna System1.1‐ PLAN/EST FCR

27 May 2020 ‐ Met with design team on 26 May.  Project has 100% CD and we are beginning the permit 

process while the project is bid for contractor selection.

Design Firm: Contractor: Verizon Wireless

2020‐0269

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 20 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 21: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Verizon Wireless Head End Building ‐ Construction1.1‐ PLAN/EST FCR

27 May 2020 ‐ Met with design team on 26 May.  Project has 100% CD and we are beginning the permit 

process while the project is bid for contractor selection.

Design Firm: Verizon Wireless Contractor: Verizon Wireless

2020‐0270

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Campus Wide ‐ COVID Barrier Installatoins1.1‐ PLAN/EST FCR

28 May 2020 ‐ Awaiting plans from departments for requirements.

Design Firm: Contractor:

2020‐0279

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Presidentʹs House ‐ Replace Wood Trim1.1‐ PLAN/EST FCR

28 May 2020 ‐ Site walk at 8am on 1 June.

Design Firm: Contractor:

2020‐0280

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Memorial Union Building ‐ Granite State Room Chiller Replacement2‐ IN DESIGN FCR

27 May 2020 ‐ Project Suspended due to the COVID‐19  on 3/23/20.  Awaiting further direction from senior 

leadership.

Design Firm: SMRT Contractor:

2016‐0453

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Taylor Hall ‐ Flat and Shingle Roof Replacement2.5‐ IN PROCUREMENT RR

27 May 2020 ‐ NTP issued for 1 June.  Building permits, equipment/material staging in place.  Building will 

be vacant through August.

Design Firm: ARM Contractor: Skyline

2017‐0218

Year Approved2021

Funding: DMA

New Hampshire Hall ‐ Window Replacements and Exterior Painting2.5‐ IN PROCUREMENT RR

21 May 2020  Project Suspended due to the COVID‐19 until 1 November.

Design Firm: McHenry Architecture Contractor: Careno

2018‐0306

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Demeritt Hall ‐ Rm 112 Carpet Replacement and Chair Refurbishing2.5‐ IN PROCUREMENT RR

27 May 2020 ‐  Project Suspended due to the COVID‐19  on 3/23/20.

Design Firm: Harriman Contractor:

2019‐0384

Year Approved

Funding: DMA PROJECT SUSPENDED

Kingsbury Hall ‐ Career Services Design2.5‐ IN PROCUREMENT FCR

27 May 2020 ‐   Project design complete ‐ submitted to procurement to initiate bid process. Completing bid 

draft on 22 May.  Meeting with stakehold to discuss laydown locations.  Awaiting ACM sampling results 

before completing Draft 2 of bid documents.

Design Firm: Placework Contractor:

2020‐0216

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 21 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 22: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Morse Hall ‐ Emergency Eyewash Installation3‐ IN CONSTRUCTION FCR

27 May 2020 ‐ Construction completed. Final inspection scheduled for 4 June 2020.

Design Firm: N/A Contractor: Milestone Eng & Const, Inc

2020‐0150

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Campus ‐ Facilities Sit‐Stand Desks3.1‐ SUBSTANTIAL COMPLETION FCR

21 May 2020 ‐ Desks installed.  Performing closeout documents. Warranty received, and will submit to 

records team for completion.  Another chair is being procured for Jeff Prince.  Awaiting Rhonda for when 

chair can be purchased.

Design Firm: N/A Contractor: Summit Ergonomics

2020‐0161

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Morse Hall ‐ Humidification Tank System Replacement3.1‐ SUBSTANTIAL COMPLETION RR

Emergency Repair 27 May 2020 ‐  Project completed.  Boiler issues resolved through Operations.  Beginning project closeout.

Design Firm: Petersen Engineering Contractor: Granite State Plumbing and 

Heating

2020‐0221

Year Approved2020

Funding: INST RR

Christensen Hall ‐ MetroPCS ‐ T‐Mobile Antenna Upgrade3.1‐ SUBSTANTIAL COMPLETION FCR

27 May 2020 ‐   Work complete.  Awaiting closeout documents.

Design Firm: NB+C Contractor: NB+C

2020‐0228

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Pettee Hall ‐ Ceiling Light Fixture Repairs3.1‐ SUBSTANTIAL COMPLETION RR

Emergency Repair 27 May 2020 ‐ Construction complete.  Beginning closeout process.

Design Firm: N/A Contractor: Scarponi

2021‐0003

Year Approved2020

Funding: INST RR

33RINES, DANIEL M

Service Building ‐ Fire Department Sprinkler Installation1.1‐ PLAN/EST RR

5/26/20  ‐ . Confriming scope changes, budget revisions, with AM, once complete PM will confirm scope with 

A/E for design processes to begin. Project anticipated to be constructed in the Fall.

Design Firm: TBD Contractor:

2010‐0356

Year Approved2021

Funding: DMA

Train Station & Dairy Bar ‐ Transit Facility Improvements ‐ UNH ‐ Durham Rail 

Station1.1‐ PLAN/EST SI

5‐26‐20: Project suspended 3‐23‐20

Design Firm: Contractor:

2018‐0031

Year Approved

Funding: GRANT PROJECT SUSPENDED

121 Technology Drive ‐ Covid‐19 Construction Estimate1.1‐ PLAN/EST FCR

5‐26‐20: Project is in conceptual design waiting for landlord feedback.

Design Firm: Contractor:

2020‐0248

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 22 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 23: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Jessie Doe Hall ‐ Caps on Cement Wall1.1‐ PLAN/EST FCR

5‐26‐20: Reached out to term for budget pricing for minor repairs.

Design Firm: Contractor:

2020‐0275

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Field House ‐ West Parking Lot Repaving2‐ IN DESIGN FCR

5‐26‐20: Project suspended 3‐23‐20

Design Firm: Tighe & Bond Contractor:

2018‐0297

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Holloway Commons ‐ Front Stairs2‐ IN DESIGN FCR

5‐26‐20: Project suspended 3‐23‐20

Design Firm: HL Turner Contractor:

2020‐0024

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Service Building ‐ Storm Water / Building Envelope Design and Temporary Repairs2‐ IN DESIGN RR

5‐26‐20: Project suspended 3‐23‐30

Design Firm: Hoyle Tanner Contractor:

2020‐0047

Year Approved2020

Funding: DMA PROJECT SUSPENDED

College Road ‐ Extend Sidewalk2.5‐ IN PROCUREMENT SI

5‐26‐20: project suspended 3‐23‐20

Design Firm: Weston & Sampson Contractor: Gagnon Construction

2015‐2511

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Campus ‐ Main Street South Sidewalk2.5‐ IN PROCUREMENT SI

5‐26‐20:  Bids are due 5‐27. Project anticipated to kick off in June.

Design Firm: CMA Engineering Contractor:

2017‐0384

Year Approved2018

Funding: GRANT

Campus ‐ McDaniel Drive Extend Sidewalk2.5‐ IN PROCUREMENT SI

5‐26‐20:  Project suspended 3‐23‐20

Design Firm: Weston & Sampson Contractor:

2019‐0074

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Handler Hall ‐ Replacement of PVI Hot Water Tanks2.5‐ IN PROCUREMENT FCR

5/26/20  ‐ project moving forward, Contract is currently routing through USNH for signatures.

Design Firm: HL Turner Contractor: NPI

2019‐0324

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 23 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 24: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Utility Distribution ‐ Tunnel Repairs and Utility Line Replacement Leaving Central 

Plant ‐ Design Only2.5‐ IN PROCUREMENT RR

5‐26‐20: Design consulatant awarded to RMF. Contract is being reviewed by vendor.

Design Firm: Contractor:

2020‐0004

Year Approved2021

Funding: DMA

Campus ‐ STR0079 Strafford Ave ‐ NEC Stair Reconstruction2.5‐ IN PROCUREMENT RR

5‐26‐20: Project suspended 3‐23‐20

Design Firm: Tighe and Bond Contractor:

2020‐0009

Year Approved

Funding: DMA PROJECT SUSPENDED

McLaughlin Hall ‐ Repair exterior stair2.5‐ IN PROCUREMENT FCR

5‐26‐20: Project suspended 4‐30‐20 by BA

Design Firm: Hoyle Tanner Contractor: JTI Site Development

2020‐0040

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Woodside apts Community Building ‐  Drainage Improvement2.5‐ IN PROCUREMENT FCR

5‐26‐20: project suspended 3‐23‐30

Design Firm: Tighe and Bond Contractor: T&S Construction

2020‐0188

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Memorial Union Building ‐ Install New Hillside Stair on West Side ‐ Design Only3‐ IN CONSTRUCTION SI

5‐26‐20: Project suspended 3‐20‐20

Design Firm: Contractor: Piscataqua Landscaping

2008‐0120

Year Approved2019

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Edgewood Water Tank ‐ Decomissioning3‐ IN CONSTRUCTION SI

5/26/20  ‐ Project anticipated to kick off early June. Tank cleaning underway.

Design Firm: Contractor: Charter Brothers

2010‐0729

Year Approved2018

Funding: SARRC 

ALLOC

Pettee Hall ‐ Drainage Repairs and Stair Demo3‐ IN CONSTRUCTION RR

5‐26‐20: Project has been procured under the term agreement.

Design Firm: Hoyle Tanner Contractor: JTI Site Development

2017‐0146

Year Approved2021

Funding: DMA

FY21 Sidewalk and Walkway Repairs3‐ IN CONSTRUCTION RR

5‐26‐20: List has been identified, PM ready to move forward with term contractors

Design Firm: N/A Contractor: Top Quality Construction

2017‐0275

Year Approved2021

Funding: INST RR

Friday, May 29, 2020 Page 24 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 25: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Utility Distribution ‐ Piping Replacements from Heating Vault HVT086 to Handler 

Hall3‐ IN CONSTRUCTION RR

5‐26‐20: Project is underway, significant delays due to engineering and piping delivery. Steam shut down 

may need to be extended in order to complete.

Design Firm: Harriman Contractor: Anderson Welding

2018‐0362

Year Approved2021

Funding: DMA

Woodman Horticultural Barn ‐ Foundation Repair3‐ IN CONSTRUCTION FCR

5‐26‐20: . Veneer work is underway.

Design Firm: Hoyle Tanner Contractor: Careno Construction

2019‐0336

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

FY21 Site Stair Repairs3‐ IN CONSTRUCTION RR

5‐26‐20; list is being priced out via term contracts.

Design Firm: N/A Contractor: Top Quality Construction

2019‐0368

Year Approved2021

Funding: INST RR

FY21 Major Road Repairs ‐ Under Town of Durham Contract3‐ IN CONSTRUCTION RR

5‐26‐20: Bids have come back via the Towns resurfacing bid. Work to be reviewed with the town and low 

bidder, and scheduled for late summer.

Design Firm: Contractor:

2019‐0371

Year Approved2021

Funding: INST RR

Field House ‐ Indoor Pool Concrete Repairs3‐ IN CONSTRUCTION RR

5‐26‐20: Pre Con Meeting completed. Construction to begin week of 6‐8 with 5‐6 week duration anticipated.

Design Firm: Hoyle Tanner Contractor: Structural Preservation 

Systems

2020‐0129

Year Approved2021

Funding: DMA

Putnam Hall ‐ EMS ‐ Covid‐19 Preparations3‐ IN CONSTRUCTION FCR

5‐26‐20: project is substancially complete. PM looking into Air conditioning for occupants, vehicle heat/AC 

units have also been requested.

Design Firm: Contractor:

2020‐0244

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

Hamel Recreation Center ‐ Covid‐19 Surge Facility3‐ IN CONSTRUCTION FCR

5‐26‐20: Returned the generator, UNH to use in house 230KW generator for the time being. Fence and other 

items still on Rent.

Design Firm: Contractor:

2020‐0245

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Haaland Hall – PVI Tank Replacement3‐ IN CONSTRUCTION FCR

5‐26‐20: Project initiated, ETB confirmed, tank is ordered, and term contractor PO is complete.

Design Firm: N/A Contractor: United Mechanical

2020‐0253

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 25 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 26: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Campus ‐ Main Street Paving3‐ IN CONSTRUCTION FCR

5‐26‐20: Project is Via the TOD contract with Continental. Working on budget and scope currently.

Design Firm: Contractor:

2020‐0276

Year Approved

Funding:

Utility Distribution ‐ South Drive STSL ‐ CRL Piping Replacements HVT086 to 

Handler Hall Design Only3.1‐ SUBSTANTIAL COMPLETION RR

5‐26‐20:  This deisgn only project will be tracked with #2018‐0362

Design Firm: Harriman Associates Contractor:

2016‐0177

Year Approved2020

Funding: INST RR

Forest Park ‐ Decommissioning and Demolition3.1‐ SUBSTANTIAL COMPLETION FCR

5‐26‐20: 

Project is complete.

Design Firm: Harriman Contractor: AQE

2019‐0053

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In3.1‐ SUBSTANTIAL COMPLETION RR

5‐26‐20: Project to be commissioned week of 6‐1‐20. Final inspections pending after punchlist.

Design Firm: Harriman Contractor: Anderson Welding

2019‐0338

Year Approved2020

Funding: DMA

Field House ‐ G00CRB Concrete Spalling Investigation and Repair3.1‐ SUBSTANTIAL COMPLETION RR

5‐26‐20:  Project being tracked under the construction id # 2020‐0129

Design Firm: Hoyle Tanner Contractor:

2019‐0355

Year Approved2020

Funding: DMA

Zais Hall ‐ Water Infiltration Design and Investigation3.1‐ SUBSTANTIAL COMPLETION RR

5‐26‐20: Project design is complete. Project was not funded this year. Project will be closed out upon final 

invoicing.

Design Firm: Hoyle Tanner Contractor:

2019‐0402

Year Approved2020

Funding: DMA

21ROULEAU, RICHARD A

Thompson Hall ‐ Single Bottom Elevator Cylinder Replacement NHE 11021.1‐ PLAN/EST RR

5/26/2020 ‐ Project remains suspended due to COVID‐19.  When suspension is lifted, project bid package will 

need to be developed.

Design Firm: Contractor:

2015‐0091

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Thompson Hall ‐ Clock Tower and Envelope Assessment and Planning1.1‐ PLAN/EST RR

5/26/2020  ‐  Project remains suspended due to COVID‐19.  When suspension is lifted, this project will require 

a forensic RFQ/P to determine the cause and subsequent remedies.

Design Firm: Contractor:

2016‐0363

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Friday, May 29, 2020 Page 26 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 27: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Paul College ‐ Roof Membrane and Flashing Investigation  ‐ Corrective Plan/Design1.1‐ PLAN/EST RR

5/26/2020 ‐ ARM recommends water testing to determine where/how the water is getting in.  Proposal for 

testing is in hand.  P.O. request will be submitted now that Covid‐19 suspension has been lifted.  Depending 

on the results, we will pursue a warranty claim and/or involve PC Construction and the roofer.  Using 

remaining funds from original construction for this effort (ref. 2009‐0980 / 1XT955)

Design Firm: ARM, LLC (roofing 

consultant)

Contractor:

2019‐0331

Year Approved2019

Funding: DMA

Holloway Commons ‐ Main Entrance Door Repairs/Investigation1.1‐ PLAN/EST FCR

5/26/2020 ‐ Project remains suspended due to COVID‐19.  When suspension is lifted, the intent is to 

implement Granite State Glass recommendations with funding from Business Affairs.

Design Firm: Contractor: Granite State Glass

2019‐0337

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Hamilton Smith Hall ‐ Rms G13, G15 Water Infiltration Investigation and Repair2‐ IN DESIGN FCR

5/26/2020 ‐ Pending further investigation as to specifically where/how the water is entering.

Design Firm: BEA Contractor: Skanska?

2020‐0030

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Campus ‐ Academic Way Improvements2‐ IN DESIGN SI

5/26/2020 ‐ Construction documents being prepared under Project #2010‐0297.  SARCC funding in the 

amount of $1.5M had been approved but may be in jeopardy due to COVID‐19.  Work may be incorporated 

into Spaulding Hall project (2016‐0278) due to location being mostly within the limits of the Spaulding project.

Design Firm: Tighe & Bond with 

Woodburn Assoc.

Contractor: Skanska

2020‐0089

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Chase Ocean ‐ Rm S210 HVAC Recommendations and Repair2‐ IN DESIGN FCR

5/26/2020 Update ‐ Design ongoing.  Estimate preparation is ongoing.  Working with Energy Office on 

temporary solution for this summer making RTU‐1 primary for the server room and RTU‐2 secondary.  If the 

customer provides funding, intent is to replace RTU‐2 with smaller unit prior to heating season.  New RTU 

will be 100% recirc, able to stage and will have reheat.

Design Firm: H.L. Turner Group Contractor: TBD

2020‐0149

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Memorial Union Building ‐ Bookstore Water Infiltration Repairs2‐ IN DESIGN BAR

5/26/2020 ‐ Waiting for a proposal for Careno for application of siloxane water repellent.  It is being priced in 

conjunction with Nick Petersʹ similar projects at Chase, 10 West Edge and Library Storage.  Proposal expected 

week of 6/1.

Design Firm: SGH Engineering Contractor: Careno

2020‐0169

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

Morse Hall ‐ Interior Main Heating Line Connections2‐ IN DESIGN RR

05/26/2020 Update:  In design by Harriman.

Design Firm: Harriman Contractor: tbd

2020‐0271

Year Approved2021

Funding: DMA

Friday, May 29, 2020 Page 27 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 28: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

Service Building ‐ Interior Heating Main Connections2‐ IN DESIGN RR

05/26/2020 Update:  In design by Harriman.

Design Firm: Harriman Contractor: tbd

2020‐0272

Year Approved2021

Funding: DMA

Morse Hall ‐ Elevators NHE 1997 and 1998  Upgrades2.5‐ IN PROCUREMENT RR

5/28/2020  ‐ Project remains suspended due to COVID‐19.  Intent is to keep Structure Tone contract in place, 

re‐evaluate in November 2020, and hopefully resume spring 2021

Design Firm: Elevator Consulting 

Associates

Contractor: Structure Tone with Stanley 

as subcontractor

2013‐1225

Year Approved2020

Funding: DMA PROJECT SUSPENDED

Parsons Hall ‐ Classroom Renovation Iddles Lecture Halls2.5‐ IN PROCUREMENT RR

Static Update:  See project #2019‐0132 for all information relative to this project.

Design Firm: Contractor:

2014‐1780

Year Approved

Funding: DMA PROJECT SUSPENDED

Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design 

Only2.5‐ IN PROCUREMENT RR

5/28/2020 ‐ Project remains suspended due to COVID‐19.  Intent is to keep Chapman contract in place, re‐

evaluate in November 2020, and hopefully resume spring 2021.  Academic Technology to take lead on AV 

specifications, bidding, and implementation.

Design Firm: Harriman Contractor: Chapman 

Construction/Design

2018‐0145

Year Approved2019

Funding: DMA

James Hall ‐ HVAC Modifications Investigation and Design2.5‐ IN PROCUREMENT RR

05/28/2020 ‐ Repairs occurred on 5/18/2020; however, additional parts needed to be ordered.  Balance of work 

scheduled for 6/4/2020.

Design Firm: Contractor:

2018‐0270

Year Approved2018

Funding: DMA

Parsons Hall ‐ Iddles Auditorium Improvements2.5‐ IN PROCUREMENT SI

Static Update:  See project #2018‐0145 for all information relative to this project.

Design Firm: Harriman Contractor: Chapman Construction

2019‐0132

Year Approved2020

Funding: SARRC 

ALLOC

PROJECT SUSPENDED

Lord Hall ‐ Fire Alarm Replacement2.5‐ IN PROCUREMENT FCR

5/28/2020  ‐ Project remains suspended due to COVID‐19.  When suspension is lifted, intent is to seek an 

updated proposal from Norris.

Design Firm: SFC Engineering Contractor: Norris (if within term limits)

2020‐0038

Year Approved2020

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Utility Distribution ‐ Dual Temp Interconnection Plan3‐ IN CONSTRUCTION FCR

5/28/2020 ‐ Piping installation is ongoing in the Combined Heat & Power Plant (CHP).  In area between 

Morse Hall and Rudman Hall, dual‐temperature piping installation has commenced.  Excavation for new 

service to Morse Hall is complete.  Demo and earthwork in Morse Circle will commence week of June 1st.  

Pipe installation continues inside the Combined Heat & Power Plant.

Design Firm: Harriman Associates Contractor: Careno Construction

2019‐0022

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Friday, May 29, 2020 Page 28 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 29: Facilities Project Management Monthly...Facilities Project Management Monthly Report Friday, May 29, 2020 Approved Projects 216 BOIE, GREGG J 9 1.1‐ PLAN/EST RR Rudman Hall ‐ Clean

88 Commercial Street ‐ UNH Manchester ‐ Bio‐Manufacturing Innovation Center 

Tenant fit‐out3.1‐ SUBSTANTIAL COMPLETION FCR

5/28/2020 ‐ Construction is complete except for punchlist and miscellaneous extras.  Furniture is complete 

with exception of damage repair on recently delivered reception desk.  Lab casework punchlist is almost 

complete.  Audiovisual installation is complete.  Majority of the loose lab equipment has been received.  Use 

and occupancy of the space has slowed due to COVID‐19.

Design Firm: John Jordan Contractor: by landlord (using 

Milestone)

2018‐0210

Year Approved2019

Funding: COLLEGE / 

DEPT ALLOC

Coastal Marine Lab ‐ Fire Clean‐Up and Repairs3.1‐ SUBSTANTIAL COMPLETION FCR

5/28/2020 ‐ Project suspension due to COVID‐19 lifted on 4/27.  Next steps are to assemble roofing package for 

bidding and line up window repairs.

Design Firm: Contractor: Careno Construction

2018‐0336

Year Approved

Funding: COLLEGE / 

DEPT ALLOC

PROJECT SUSPENDED

Hamilton Smith Hall ‐ Major Renovation Project3.5‐ WARRANTY REPAIRS SI

5/28/2020 ‐ Some Skanska warranty work remains.  There are three water intrusion issues that we need to 

move forward.  A few furniture warranty items remain open.

Design Firm: DiMella Shaffer Associates Contractor: Skanska USA, Inc.

2012‐1851

Year Approved2013

Funding: SARRC 

ALLOC

Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation3.5‐ WARRANTY REPAIRS RR

5/28/2020 ‐ No change.  Complete pending equipment list update and O&M upload.

Design Firm: Harriman Associates Contractor: Charters Bros.

2018‐0249

Year Approved2019

Funding: DMA

Friday, May 29, 2020 Page 29 of 29University of New Hampshire

Brenda Whitmore, Director Facilities Project Management