facility photo tour

68
Fire Control System no parts available, little support from Symplex for maintenance. Needs to be replaced.

Upload: rachelle-johnson

Post on 06-Mar-2016

219 views

Category:

Documents


4 download

DESCRIPTION

Photos of Montezuma School's facility outlining needed upgrades and replacements

TRANSCRIPT

Page 1: Facility Photo Tour

Fire Control System – no parts available, little support from Symplex for maintenance. Needs to be replaced.

Page 2: Facility Photo Tour

HS clock/bell system. Needs to be replaced. Bell system does not work. Clock system works for some clocks not all. No parts nor maintenance support available.

Page 3: Facility Photo Tour

Example of a hallway clock that broke and was not replaced.

Page 4: Facility Photo Tour

Phone intercom also serves as the PA system for the building. There are no external hallway speakers or room speakers for PA.

Page 5: Facility Photo Tour

Building was hit by lightening in 2007. Phone voice mail was knocked out at that time. Company that current phone system was purchased from (Impression Comdial) is no longer in business. No parts, support maintenance available.

Page 6: Facility Photo Tour

Many door closers are broke. No parts available. Fire Marshall has ordered that door closers cannot hold a door open.

Page 7: Facility Photo Tour

HS Gym Doors- There are 10 doors into the gym. closers are broke, doors don’t fit in the frames, frames needs painting, locks don’t work, push bars need replacing, doors need refinishing.

Page 8: Facility Photo Tour

Junior High girl’s bathroom door. Door does not completely shut and needs to be refinished.

Page 9: Facility Photo Tour

Junior High Gym door. Needs to be replaced. They don’t shut properly, can’t be locked.

Page 10: Facility Photo Tour

Elementary door. Needs to be refinished, louver covered and door is not to be standing open.

Page 11: Facility Photo Tour

Elementary fire doors. There doors do not qualify as fire doors and need to be replaced.

Page 12: Facility Photo Tour

Metal HS hallway ceiling is stained and discolored.

Page 13: Facility Photo Tour

There are 18 sky lights in the high school hallway that have all been covered up.

Page 14: Facility Photo Tour

Broken and covered up sky light in high boy’s locker room.

Page 15: Facility Photo Tour

Old light fixture, electrical outlet and stained ceiling outside the elementary office.

Page 16: Facility Photo Tour

Elementary Classroom Ceiling – Not just the stained tile but that many are adhered with screws.

Page 17: Facility Photo Tour

Ceiling in JH boy’s locker room that has (is) sustaining water damage. Source of the leak has not been determined.

Page 18: Facility Photo Tour

Junior High Boy’s Locker Room Ceiling – more water and moisture damage caused by roof leak.

Page 19: Facility Photo Tour

HS floor tile are in constant need of replacement and repair.

Page 20: Facility Photo Tour

Broken floor tile at North East door of HS.

Page 21: Facility Photo Tour

Elementary Classroom Flooring – mismatched colors, tile constantly coming off.

Page 22: Facility Photo Tour

HS Gym basket motors don’t work. You can see that the electrical wires for this motor have been unhooked. Motors are large enough to lift glass backboards. New motors needed.

Page 23: Facility Photo Tour

Gym Bleachers are in constant need of repair. Replacement parts are scarce. Bleachers do not meet ADA requirements. Need stairs, hand rails and wheel chair access. Bleachers are not motorized and need to be taken in and out by hand or with mechanical mule.

Page 24: Facility Photo Tour

Gym needs updated lights, bleachers, doors, backboards and basket motors. There is still some life left in the floor but will need to be replaced sometime.

Page 25: Facility Photo Tour

HS univent that needs to be replaced.

Page 26: Facility Photo Tour

Univent located at the South East entrance of the Elementary. Does not work.

Page 27: Facility Photo Tour

Manual control for radiator. There are no automatic radiator controls that function properly in the JH portion of the building.

Page 28: Facility Photo Tour

Covered register in Pre-School room – not an appropriate heating system for young children.

Page 29: Facility Photo Tour

2nd floor JH classroom. Non-working controls to univent and example of deterioration of plaster on wall.

Page 30: Facility Photo Tour

One of two boilers in JH section of the building. Installed in 1950. One works fine, the other is working but not in as good of shape. We have been warned that it could fail at any time.

Page 31: Facility Photo Tour

Loose brick on chimney from inside the boiler room.

Page 32: Facility Photo Tour

Water leaking onto floor of JH boiler room from base of chimney.

Page 33: Facility Photo Tour

Entrance to high school tunnel system. Abatement of tunnels will be necessary to do work on infrastructure issues.

Page 34: Facility Photo Tour

JH boy’s locker shower room. Limited or no hot water available.

Page 35: Facility Photo Tour

Mechanical access point in Junior High area of the building.

Page 36: Facility Photo Tour

Same pipe, different angle.

Page 37: Facility Photo Tour

Interior of 2nd floor JH janitor closet located inside boy’s bathroom. Other side of wall is boy’s bathroom.

Page 38: Facility Photo Tour

Old electrical box in JH boiler room.

Page 39: Facility Photo Tour

Electrical panel located in JH boiler room.

Page 40: Facility Photo Tour

Light switch in Junior High hallway. Some of these switches still work, many do not and have been bypassed.

Page 41: Facility Photo Tour

Elementary Classroom Outlet- added to the room, can’t keep the cover on it.

Page 42: Facility Photo Tour

HS library is general need of a complete update; lights, furniture, flooring and ceiling. It could also use additional space to handle more than one group in the library at a time.

Page 43: Facility Photo Tour

Elementary library. Needs updated lights, new flooring, new furniture.

Page 44: Facility Photo Tour

Sidewalk at East Breezeway entrance is cracked and falling away from the building.

Page 45: Facility Photo Tour

Area of tuck pointing needed on JH building.

Page 46: Facility Photo Tour

More tuck pointing needed on Junior High building.

Page 47: Facility Photo Tour

High School Boiler Chimney

Page 48: Facility Photo Tour

Junior High Boiler Chimney

Page 49: Facility Photo Tour

East wall of Elementary. The wall is bowing out and needs to be repaired and possible replaced. Bowing is due to settling of the footing from water draining down the interior of the wall. The connection of the wall and roof system has failed.

Page 50: Facility Photo Tour

South side of Elementary. Problems with the windows and screens.

Page 51: Facility Photo Tour

Interior view of Junior High gym north windows. The windows leak and the water has caused damage to the gym floor. Windows have been sealed from the exterior.

Page 52: Facility Photo Tour

Elementary classroom. In need of proper storage of student gear.

Page 53: Facility Photo Tour

Elementary classroom. In need of updated lighting, flooring, desks and other furnture.

Page 54: Facility Photo Tour

Interior elementary classroom – No windows. Inadequate ventilation.

Page 55: Facility Photo Tour

Elementary classroom. In need of new cabinets that are in constant need of repair.

Page 56: Facility Photo Tour

Elementary Cabinet with laminate coming off.

Page 57: Facility Photo Tour

Each elementary room has a cabinet with a sink. Each has plumbing issues and cabinets are damaged and broken.

Page 58: Facility Photo Tour

Deteriorating wall plaster in 2nd floor JH counselor office.

Page 59: Facility Photo Tour

More deterioration of wall plaster in counselor office. Root of the problem is water coming into the building from the outside. Mold has been found when plaster falls off the wall.

Page 60: Facility Photo Tour

Paint and wall board deteriorating in 1st floor Junior High classroom.

Page 61: Facility Photo Tour

More plaster problems in 2nd floor JH classroom (TAG).

Page 62: Facility Photo Tour

JH bathroom stalls with no doors. Not ADA compliant.

Page 63: Facility Photo Tour

Plaster peeling on wall in downstairs JH boy’s bathroom. A constant issue in the JH portion of the building. Often mold is associated with this problem.

Page 64: Facility Photo Tour

JH boy’s bathroom floor urinals that were boxed in due to water leaking into 1st floor bathroom and ruining ceiling. Urinals need to be replaced as well as floor.

Page 65: Facility Photo Tour

Junior High stairs are not compliant with current fire code. Should be removed and relocated.

Page 66: Facility Photo Tour

2nd floor JH needs a straight and connected hallway for fire exit.

Page 67: Facility Photo Tour

Wrestling/Ag Room Roof. Same roof as on the Junior High building. Roof membrane has not come loose but seems are in constant need of repair. Needs to be replaced.

Page 68: Facility Photo Tour

Junior High Roof. The black roof membrane has come loose and cement blocks and sand bags were added several years ago to keep the roof membrane from rippling in the wind. Roof needs to be replaced.