facility preparedness: current facility and cleanroom
TRANSCRIPT
A Partnership of: US/DOEIndia/DAEItaly/INFNUK/UKRI-STFCFrance/CEA, CNRS/IN2P3Poland/WUST
S. K. Suhane/ RRCATPIP-II Technical Workshop02/12/2020
Facility Preparedness: Current facility and Cleanroom upgrade / Tooling and HPR
Movement of Cavity in the Cleanroom
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II2
Assembly and Vacuum Testing
HPR and Cleanroom Processing
HPR of cavity(3 Pass)Area ‘3’
Drying in the HPR station (Class 100)
Area ‘3’
Shift to HPR station for second
HPR
Shift inside class 100 cleanroom and assemble top flange, MC
&FP flange Area ‘4’
HPR of cavity(3 Pass)Area ‘3’
Shift inside class 100 cleanroom and
assemble End flange with vacuum
valve and burst disk
Area ‘4’
External HPR of cavity &
hardware
Shift to VTS Facility
Leak TestArea ‘4’
Vacuum Pump Down
Area ‘4’
Leak Test OK
Yes
No
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II3
HPR set up for HB650 cavity
HPR Set up detailsStructure support 304 SS Sq. Pipes
Wetted parts 316 S.S.
Nozzle material Hardended S.S.
Type of pump Reciprocating piston
Final Filter 0.05 micron
Cavity rotation Timing belt drive
Enclosure Polycarbonate
Cleanliness Class 100 (ISO-5)
Jacketed cavity rinsing • Wand adjustment• Mounting bracket
Bare Cavity HPR Jacketed Cavity HPR
External HPR Arrangement
Nozzle tip Filter Trigger Gun
Nozzle Holder
Nozzle Tip
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II4
High Pressure Rinsing Process
HPR Parameters
Jet pressure 80-100 bar
Pump Flow rate 8-10 LPM
Wand Rotation 2-5 RPM
Cavity verticaltravel
5-20 mm/min
Nozzles type 40° fan jet
Nozzlearrangement
Two oppositelyplaced nozzles
HPR duration (3+1+3) passes ofHPR after light EP,total duration of 7hours.
Q.C. in HPR processOnline monitoring of UPW parameters
Flushing of piping is done before every HPR cycle
HPR structure, fixtures, clean enclosure walls are thoroughly cleaned with
IPA using lint free cloth regularly
Water from rinsed cavity is collected and sent for microbial analysis
Wand filter cartridge is changed every year
Polisher unit is run in recirculation mode to maintain purity of UPW
Collection of water from rinsed cavity for particulate analysis (Planned in
new HPR set up)
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II5
Tooling for Cavity Handling in Cleanroom
S.S. cart with swivel castorsfor movement of cavity inthe cleanroom
Fixture with toggle clampsfor holding the cavity cage
Cleanroom compatible cart for cavity lifting and swivelling
Loading of cavity on HPR set up Holding fixture for jacketedcavity
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II6
Cleanroom Preparation of CavityCavity Assembly Process All tools and hardware cleaned with
ultrasonic cleaning before taking them insidethe cleanroom
Flanges and fasteners are rinsed withultrapure water and after drying, cleanedwith nitrogen using ionizing blow-off gun.
Particle count measured during each step ofcavity assembly
Torque wrench used for bolt tightening Aluminum seal and copper gasket carefully
checked and cleaned with IPA then purgedwith nitrogen blow-off gun
High purity nitrogen gas (99.9995 %) is usedfor purging
All movements and operations insidecleanroom are performed slowly andcautiously
Thorough cleaning of cleanroom walls, floorand furniture regularly Cleanroom assembly of Cavity
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II7
Cavity Vacuum Pumping
Cavity Pumping set up Pumping cart comprises of a combination of SIP
and TMP pum backed by a scroll pump, RGA, along with valves , gauges and associated fittings
All the flanges are CF type and sealed using copper gasket
Vacuum pumping is done slowly for evacuating the cavity. (Pump down rate 10 torr/min)
A by-pass line containing fine control leak valve is used in the pumping line for slow evacuation of cavity
Cavity is sealed at ultimate vacuum of 2xE-7 mbar
Bypass Line Leak Valve RGA
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II8
screen capture of RGA analog spectrum
Ultrapure Water Generation Plant
Parameter Value
Resistivity ≥ 18 MΩ-cm
TOC < 30 ppbTotal Bacteria Count < 1 cfu/100ml
Flow Rate 800 LPHFinal Storage Tank 2500 litreGasket PTFE
• Ultrapure water generation plant installed close to new mini cleanroom facility
• Storage tank made of virgin PP fitted with 0.22 micron PTFE vent filter
• Pump MOC: SS316
• Piping made of electropolished Stainless Steel grade 316
• Online Conductivity, Resistivity meter and TOC monitor
• Sample collection port for microbial analysis
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II9
Cavity Processing Facility Building
1
PLATFORM
D2
A
D4 D4 D4
D2
D2 D2
Large CleanroomAir conditioned envelope in PEB for housing Large Cleanroom
EP Set up CBP M/cUPW Plant
Mini Cleanroom
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II10
AHU for Large Cleanroom
AHU for Mini Cleanroom
New Mini Cleanroom
Personnel Entry
Cavity Entry
US Cleaner
SQUARE PIPE100x100
Air Lock(ANTE ROOM)
CHANNEL-100
1195CHANNEL-100 1195 1103
803
100
DO
OR
SIZ
E 10
00m
mIN
T O
PE 8
36m
mD
OO
R S
IZE
1500
mm
INT
OPE
130
2mm
975 975 975 975132
1195CORNER-100
1195 1103
165
935100
DOOR SIZE 1000mmINT OPE 836mm
CHANNEL-100
1195
975 975 975 975100
DO
OR
SIZ
E 15
00m
mIN
T O
PE 1
302m
m
975
CHANNEL-50
CH
ANN
EL-50
975
975
1005
140
666
CORNER-100
1195
1800
1202D2LH
Gowning Area
ANTE ROOM
76
0
DYN
AM
IC PA
SS B
OX-1
WALL M
OUNTED
INTER
NAL S
IZE:-6
00
X60
0X6
00
EXTERNAL S
IZE:-7
60
X67
0X1
05
0
670
AIR SHOWER
CH
ANN
EL-50
CH
ANN
EL-5
0
839
CHANNEL-50
DO
OR
SIZ
E 10
00m
mIN
T O
PE 8
57m
m
100 975 962
CH
ANN
EL-50
ISO Class-4 ISO Class-6 ISO Class-8
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II11
3.8
m
9.6 m
New Mini CleanroomFeatures of New Mini Cleanroom Required for High Pressure Rinsing, Drying,
Assembly and Evacuation of SCRF cavities Located in the vicinity of EP facility Floor area ~ 36 m2 , Room height - 4 m Cleanliness : ISO class 4 to class8 Temperature 20°C ± 2°C, RH 55% ± 5%. Flooring: Raised floor with perforated panels Air shower for entering ISO class 4 area Dynamic Pass Box for tool/component entry Portable particle counter with measuring range
range from 0.1 to 5.0 micron S.S. tubing for high purity gases and vacuum line Fire and smoke detectors Dedicated cleanroom garment laundry facility
Mini Cleanroom under construction
Expected to be operational byEarly next year
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II12
Proposed HPR set up in New Mini Cleanroom
The existing HPR set up will berelocated to the new cleanroom withcertain modifications in the structure
New cleanroom has raised floor in theISO 4 area. Base structure of HPRhas been modified for installation onthe raised floor.
Suitable opening shall be made in theraised floor for installing HPRstructure
Vertical frame has been suitablystiffened to support both the bare aswell as dressed cavity.
The existing high pressurereciprocating pump will be replacedwith a new diaphragm type pump.
PP/PVDF pipeline for ultrapure waterdistribution from the UPW plant will beinstalled
Triplex Diaphragm Pump
Support Structure for new HPR setup
Aerosol particle counter
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II13
Integrated Large Cleanroom Facility
ED1
D3
SLIDE
D3 D3
D3
CLASSISO-7
D3
D3
D3
D3
D2
SD1 SD1
SD2 SD2
CLASSISO-7
CLASSISO-8
CLASSISO-8
CLASSISO-7
CLASSISO-6
CLASSISO-7
CLASSISO-4
CLASSISO-4
CLASSISO-4
CLASSISO-4
CLASSISO-7
CLASSISO-6
CLASSISO-7
CLA
SSIS
O-7
CLASSISO-7
CLASSISO-4
CLASSISO-6
CLASSISO-7
ED1
D2
D2
D2
D2
D2
D2 D2
SLIDE
D3
D3
D3
CLASSISO-5
HAND HPR AREA
VACCART
HPRPUMP
Dimensions of Cleanrooms:Total Area of cleanrooms: 600 m2
Area of ISO class 4 rooms: 140 m2
HPR Room Height: 4 m
Raised Floor Height: 0.5 m
Final Assembly
HPR
String Assembly
HandHPR
Cavity Receiving
Ante-Room Cavity Tuning
ISO Class-4
ISO Class-5
ISO Class-6
ISO Class-7
High Vacuum Furnace
Legends:
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II14
Personnel Entry
Cavity Entry
Air Shower
Gowning Area
Salient Features of cleanrooms
Cleanrooms installed in a Pre-Engineered building having separate HVAC system for conditioning of the circulating air
Cleanroom design and construction as per ISO 14644 Perforated raised flooring in ISO 4 and 5 areas to maintain uniform unidirectional flow of air Supply air from ceiling mounted filter units and return air through side walls/ under the raised floor ISO class 4 areas have ceiling with physical filter coverage of 87-99 % with ACPH of 410 – 470 Room air pressure ranging from 6 Pa in Dynamic Air lock to 40 Pa in HPR area (ISO class 4) Static dissipative floor, wall and door materials to prevent charge buildup and resultant particle
attraction Two sets of floor mounted rails installed underneath the raised floor in string assembly area ISO class 4 rooms constructed using double walls at 250 mm inter-spacing for return air 60 mm thick double skin wall panels with 1 mm thick Stainless Steel 304 sheet on both sides and
PUF as infill are used in ISO class 4 walls Outer most walls constructed using 100 mm thick double skin wall panel with 1.6 mm thick
anodized aluminum sheet on both faces with inbuilt return air risers and PUF as infill
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II15
Salient Features of cleanrooms
HVAC system type: Ducted with positive plenum concept
Ducting from AHU to Cleanroom plenum are made of anodized aluminum
Individual filters connected to the plenum through flexible ducting
Filter type: ULPA-HEPA filter bank for ISO 4 and 5 Areas ; HEPA filters for ISO 6, 7, 8 Areas
HEPA and ULPA filters in SS box casing with full face gasket sealing
Personnel entry to cleanrooms through Air shower
Dynamic pass box for entry of tools and fittings
Sequential type particle monitoring system with 32 channel manifold. Particle size range of the monitor :
0.1 – 5.0 µm
Electropolished Stainless steel tubing with manifold for high purity gases and vacuum line
Analog Addressable Fire Alarm System with Dry-Sprinkler type Fire Suppression System
Cleanroom validation by a certified third party agency
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II16
Current Status
• Contract for design and construction has been awarded
• Site survey and measurement has been done by the contractor
• Cleanroom and HVAC design has been completed by the contractor
• Construction drawings have been completed
• Design documents and drawings have been reviewed by RRCAT
• Procurement of cleanroom systems, components and equipment by the contractor is
under progress
• Rails under raised floor for string assembly area are installed
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II17
HPR set up for large cleanroom A new HPR facility for HB 650 cavity is planned in the
integrated cleanroom. It will have a structure similar tothe new HPR stand in FNAL
The HPR structure will be installed on the raised floor ofcleanroom
Base support has been modified to suit the height ofraised floor.
Suitable opening shall be made in the raised floor forinstalling the structure
The facility can be used to rinse bare as well as jacketedcavity by adjusting the wand position
The cavity frame holding fixture on the HPR structure ismade common for both bare as well jacketed cavity
Components and sub-systems required for the new HPRset up are under procurement
Structure assembly is under fabrication For loading of cavity on the new HPR structure, suitable
cleanroom compatible lifting cart with wider legs openingis under procurement
Linear Actuator for Cavity Translation Cavity Loading Cart
Geared motor for wand rotation
Support Structures in fabrication
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II18
Conclusion and Future Plans
• Presently Cavity EP and HPR facility are at different locations.• New mini cleanroom for HPR and cavity assembly under construction in
the close proximity of EP facility.• HPR facility will be set up in the mini cleanroom• An integrated cleanroom facility for HPR, cavity assembly, string
assembly, tuning and high temperature degassing is under constructionin the cavity fabrication and processing facility building
• An improved HPR facility common for bare and jacketed HB650 cavity isunder construction and will be installed in the integrated cleanroom
2/12/2020 S. K. Suhane | Technical Workshop | PIP-II19