factory layout
DESCRIPTION
layoutTRANSCRIPT
MET-420, Semester I 2015-16
JPAN Tubular Components Pvt Ltd.
Sumit Soni2012ME10731
1
MET-420, Semester I 2015-16
Introduction
➔ Manufactures Tubing Components
➔ Started in 1998 with 400sqft of space and today having More than 80000sqft .
➔ ISO 9000::2008
➔ Sales in 2014 :13.44 milion$
2
MET-420, Semester I 2015-16
Project: Plant Equipment Layout
3
MET-420, Semester I 2015-16
Three line to be transfered to New Plant
4
MET-420, Semester I 2015-16
Plant area and its structure
5
MET-420, Semester I 2015-16
Line Equipment Planning
6
MET-420, Semester I 2015-16 7
SchematicDiagram
Line Equipment Planning
MET-420, Semester I 2015-16 8
Line Equipment Planning
MET-420, Semester I 2015-16
Machine Planning
9
MET-420, Semester I 2015-16
Machine Set up as per planning and line output
10
Line 1
Line 2
MET-420, Semester I 2015-16 11
Line 3
Machine Set up as per planning and line output
MET-420, Semester I 2015-16
Conveyor Length optimization:
➢ No of process and its space
➢ No of persons required to do the process
➢ Space to prevent piling of products and messing of
products into each other12
MET-420, Semester I 2015-16 13
Conveyor Length optimization:
MET-420, Semester I 2015-16
Conveyor length after optimisation
14
MET-420, Semester I 2015-16
Trolley Arrangement Plan
15
MET-420, Semester I 2015-16 16
Final Layout
MET-420, Semester I 2015-16 17
Final Layout
MET-420, Semester I 2015-16
Final Layout
18
MET-420, Semester I 2015-16
Takt Time
19
MET-420, Semester I 2015-16
Project: Thermal Insulator Design
20
Old Design
MET-420, Semester I 2015-16
New Design
21
Project: Thermal Insulator Design
MET-420, Semester I 2015-16
Workplace Organisation Method
22
MET-420, Semester I 2015-16 23