final examination semester i, session 2014/2015 · 2016. 11. 15. · semester i, session 2014/2015...
TRANSCRIPT
-
MAP 1053/MKAQ 1053 1
FINAL EXAMINATION
SEMESTER I, SESSION 2014/2015
COURSE CODE : MAP 1053/MKAQ 1053
COURSE : PAVEMENT DESIGN AND CONSTRUCTION
PROGRAMME : MAP/MKAQ
DURATION : 2 HOURS 30 MINUTES
DATE : DISEMBER 2014
INSTRUCTION TO CANDIDATES:
1. ANSWERS ALL QUESTIONS
2. NO REFERENCE IS ALLOWED
3. USE SEPARATE ANSWER BOOK FOR PART A AND PART B.
ENCLOSE TABLE 1.7 WITH ANSWER BOOK PART A
WARNING!
Students caught copying/cheating during the examination will be liable for
disciplinary actions and the faculty may recommend the student to be expelled from
the study.
This examination question consists of (13) printed pages only.
-
MAP 1053/MKAQ 1053 2
PART A:
Q1. (a) A continuous reinforced concrete pavement (CRCP) has been designed
with a trial thickness of 250mm. It was designed with a dowel joints and
asphalt shoulder on top of 100mm unstabilized subbase. Based on PCA
method, percentage of fatigue analysis and erosion analysis was found to
be 108% and 95% respectively. As an engineer, please summarize the
output of the design and suggest what are the steps or methods that can be
done in order to improve the results.
(8 marks)
(b) A continues reinforced concrete pavement using gravel as coarse
aggregate is subjected to 107 ESAL. This CRCP is a dual lane with a
width of 12 ft per lane. Indirect tensile strength of the concrete at 28 days
(ft) was found to be 650 psi. Design temperature drop (DTD) for the
concrete pavement is expecting to be 55˚F and wheel load tensile stress is
200 psi. With a 10 inches thickness of concrete slab, determine the
longitudinal numbers of No 6 bars per lane required.
Design tie bars along the longitudinal joints as well. Use billet steel with
intermediate grade as tie bars. Use the tables and formulas given. Please
state clearly your own assumption.
(17 marks)
(25 marks)
αs = 5 x 106 /˚ F
Nmin = 0.01273 Pmin WsD/ Ф2
Nmax = 0.01273 Pmin WsD/ Ф2
As= (γchLfa)/(fs)
As= area of steel required per unit width
fs= allowable stress
γc = unit weight of concrete (0.0868 pci)
h= thickness of the slab (in)
L= distance from longitudinal joint to free edge
where no tie bars exist (in)
fa= average of coefficient of friction
-
MAP 1053/MKAQ 1053 3
t= ½ ( fsd/ μ)
t= length of tie bar
fs= allowable stress
d= diameter of tie bar
μ= allowable bond stress (350 psi for deformed
bars)
Table 1.1 Approximate Relationship Between Shrinkage and Indirect Tensile
Strength of PCC
Indirect tensile strength (psi) Shrinkage (in./in.)
300 or less 0.0008
400 0.0006
500 0.00045
600 0.0003
700 or greater 0.0002
Table 1.2 Recommended Value of the Thermal Coefficient of PCC as a
Function of Aggregate types
Type of course aggregate Concrete thermal coefficient (10-6/˚F)
Quartz 6.6
Sandstone 6.5
Gravel 6.0
Granite 5.3
Basalt 4.8
Limestone 3.8
-
MAP 1053/MKAQ 1053 4
Table 1.3 Allowable Steel Working Stress
Indierct tensile strength of concrete at
28 days (psi)
Reinforcing bar size
No. 4 No.5 No.6
300 or less 65000 57000 54000
400 67000 60000 55000
500 67000 61000 56000
600 67000 63000 58000
700 67000 65000 59000
800 or greater 67000 67000 60000
Table 1.4 Recommended friction factors
Types of Material Beneath Slab Friction factor (f)
Surface treatment 2.2
Lime stabilization 1.8
Asphalt stabilization 1.8
Cement stabilization 1.8
River gravel 1.5
Crushed stone 1.5
Sandstone 1.2
Natural subgrade 0.9
Table 1.5 Yield strength and allowable stress for steel
Type and grade of steel Yield strength
(psi)
Allowable stress (psi)
Billet steel, intermediate grade 40 000 27 000
Rail steel or hard grade of billet
steel
50 000 33 000
Rail steel, special grade 60 000 40 000
Billet steel, 60 000 psi
miminum yield
60 000 40 000
Cold drawn wire (smooth) 65 000 43 000
Cold drawn wire (deformed) 70 000 46 000
-
MAP 1053/MKAQ 1053 5
Table 1.6 Weights and dimensions of standard reinforcing bars
-
MAP 1053/MKAQ 1053 6
DESIGN INPUTS
Input Variable Value Input variable Value
Reinforcing
Bar/Wire Diameter
Ф (inches)
Thermal
Coefficient Ratio
αs/αc (in./in.)
Concrete Shrinkage
, Z (in./in.)
Design
Temperature Drop
DTD (˚F)
Concrete Tensile
Strength, ft (psi)
Wheel Load Stress
σw (psi)
DESIGN CRITERIA AND REQUIRED STEEL PERCENTAGE
Crack Spacing,
x (feet)
Allowable
rack Width ,
CWmax
(inches)
Allowable
Steel Stress,
(σs) max (ksi)
Design steel
range
Value of
Limiting
Criteria
Minimum
Required Steel
Percentage
Maximum
Allowable Steel
Percentage
Table 1.7 for Q1b
Worksheet for Longitudinal Reinformecement Design
Note: Please return this figure along with your answer book
-
MAP 1053/MKAQ 1053 7
Figure 1.1 for Q1b: Percent steel to satisfy crack spacing criterion
-
MAP 1053/MKAQ 1053 8
:
Figure 1.2 for Q1b: Percent steel to satisfy crack width criterion
-
MAP 1053/MKAQ 1053 9
Figure 1.3 for Q1b: Percent steel to satisfy steel stress criterion
-
MAP 1053/MKAQ 1053 10
Q2. (a) AASHTO 1993 Design Guide used an empirical design approach in
designing the thickness of structural layer. Recent development, ATJ 5/85
(2013 revision) method was developed based on mechanistic-empirical
design approach. By using this two types of design method (AASHTO
1993 and ATJ 5/85 (2013)) as an example, explain in details the
difference between empirical and mechanistic-empirical approach.
(5 marks)
(b) Determine the required structural thickness for a dual carriageway Rural
Arterial using AASHTO 1993 Design Guide. The following data were
given.
Analysis period of 20 years
ESAL for the first = 2 million
Traffic growth rate of 4% per annum
Directional spilt 60/40
Lane distribution factor of 80%
Standard deviation of 0.45
Initial serviceability of 4.5
Terminal serviceability of 2.5
Soil will be exposed to six months of dry and 6 months of wet season.
Both base and subbase materials are of good drainage quality and percent
of pavement structure exposed to moisture levels approaching saturation
is 10%.
(20 marks)
(25 marks)
Growth factor= (1+r)n-1
r
∆PSI= po - pt
w18 = DD x DL x ŵ18
SN=a1D1 + a2D2m2 + a3D3m3
D1* ≥ SN1/a1
SN1* = a1D1 * ≥ SN1
D2*≥ (SN2 – SN1*)/(a2m2)
SN1* + SN2 * ≥ SN2
D3*≥ (SN3 – (SN1* + SN2* ))/ (a3m3)
μf = 1.18 x 108 x MR-2.32
-
MAP 1053/MKAQ 1053 11
Table 2.1 Suggested Levels of Reliability for Various
Functional Classifications
Functional Classification Recommended Level of
Reliability
Urban Rural
Interstate and other Freeways 85-99.9 80-99.9
Principle Arterials 80-99 75-95
Collectors 80-95 75-95
Local 50-80 50-80
Layers Moduli:
Asphalt Concrete : EAC= 400,000 psi
Granular Base: EBS= 28,000 psi
Granular Subbase: ESB= 13,000 psi
a1 = 0.41
a2 = 0.294(log10 EBS) – 0.977
a3 = 0.227 (log10ESB) – 0.839
Table 2.2 Recommended mi values for untreated Base and Subbase
Percent of Time Pavement Structure is Exposed to Moisture Levels
Approaching Saturation
Quality of
Drainage
< 1% 1-5% 5-25% >25%
Excellent 1.40-1.35 1.35-1.30 1.30-1.20 1.20
Good 1.35-1.25 1.25-1.15 1.15-.100 1.00
Fair 1.25-1.15 1.15-1.05 1.05-0.80 0.80
Poor 1.15-1.05 1.05-0.80 0.80-0.60 0.60
Very Poor 1.05-0.95 0.95-0.75 0.75-0.40 0.40
Table 2.3 Effective Roadbed Soil Resilient Modulus
Roadbed Moisture Condition Roadbed Soil Resilient Modulus
(psi)
Wet 5000
Dry 6500
Spring- Thaw 4000
Frozen 20000
-
MAP 1053/MKAQ 1053 12
Figure 2.1 for Q2b
-
MAP 1053/MKAQ 1053 13
PART B
Q3. A new big township is under construction and a monthly news bulletin is
distributed monthly to everyone involved in the management and the
construction of the township. An article on a certain construction aspect is
highlighted every month. The article to be included in the next month’s
bulletin is on road construction. The pavement for the roads in the town
are of two types; asphalt pavement and concrete block pavement.
Write a draft for the article to explain the various layers and components
of the pavements. Good construction practices and various innovations
should also be included to provide for an interesting and purposeful
reading.
(25 marks)
Q4. (a) A full cut section of a road has failed during a raining season. The cut
slopes which consist of simply constructed long and steep slopes without
proper drainages and without proper erosion control have collapsed. The
pavement has also failed because of water infiltration into the subgrade.
Suggest how a reconstruction of this failed section should be done to
provide for a permanent solution. The reconstruction should consist of the
required drainages; both surface and subsurface and erosion control
measures.
(16 marks)
(b) The use of rocks and large stones is a common feature in road
construction. Differentiate between a rip rap, a stone mattress and a
gabion in terms of their features and contributions.
(9 marks)
(25 marks)