final examination semester i, session 2014/2015 · 2016. 11. 15. · semester i, session 2014/2015...

13
MAP 1053/MKAQ 1053 1 FINAL EXAMINATION SEMESTER I, SESSION 2014/2015 COURSE CODE : MAP 1053/MKAQ 1053 COURSE : PAVEMENT DESIGN AND CONSTRUCTION PROGRAMME : MAP/MKAQ DURATION : 2 HOURS 30 MINUTES DATE : DISEMBER 2014 INSTRUCTION TO CANDIDATES: 1. ANSWERS ALL QUESTIONS 2. NO REFERENCE IS ALLOWED 3. USE SEPARATE ANSWER BOOK FOR PART A AND PART B. ENCLOSE TABLE 1.7 WITH ANSWER BOOK PART A WARNING! Students caught copying/cheating during the examination will be liable for disciplinary actions and the faculty may recommend the student to be expelled from the study. This examination question consists of (13) printed pages only.

Upload: others

Post on 12-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • MAP 1053/MKAQ 1053 1

    FINAL EXAMINATION

    SEMESTER I, SESSION 2014/2015

    COURSE CODE : MAP 1053/MKAQ 1053

    COURSE : PAVEMENT DESIGN AND CONSTRUCTION

    PROGRAMME : MAP/MKAQ

    DURATION : 2 HOURS 30 MINUTES

    DATE : DISEMBER 2014

    INSTRUCTION TO CANDIDATES:

    1. ANSWERS ALL QUESTIONS

    2. NO REFERENCE IS ALLOWED

    3. USE SEPARATE ANSWER BOOK FOR PART A AND PART B.

    ENCLOSE TABLE 1.7 WITH ANSWER BOOK PART A

    WARNING!

    Students caught copying/cheating during the examination will be liable for

    disciplinary actions and the faculty may recommend the student to be expelled from

    the study.

    This examination question consists of (13) printed pages only.

  • MAP 1053/MKAQ 1053 2

    PART A:

    Q1. (a) A continuous reinforced concrete pavement (CRCP) has been designed

    with a trial thickness of 250mm. It was designed with a dowel joints and

    asphalt shoulder on top of 100mm unstabilized subbase. Based on PCA

    method, percentage of fatigue analysis and erosion analysis was found to

    be 108% and 95% respectively. As an engineer, please summarize the

    output of the design and suggest what are the steps or methods that can be

    done in order to improve the results.

    (8 marks)

    (b) A continues reinforced concrete pavement using gravel as coarse

    aggregate is subjected to 107 ESAL. This CRCP is a dual lane with a

    width of 12 ft per lane. Indirect tensile strength of the concrete at 28 days

    (ft) was found to be 650 psi. Design temperature drop (DTD) for the

    concrete pavement is expecting to be 55˚F and wheel load tensile stress is

    200 psi. With a 10 inches thickness of concrete slab, determine the

    longitudinal numbers of No 6 bars per lane required.

    Design tie bars along the longitudinal joints as well. Use billet steel with

    intermediate grade as tie bars. Use the tables and formulas given. Please

    state clearly your own assumption.

    (17 marks)

    (25 marks)

    αs = 5 x 106 /˚ F

    Nmin = 0.01273 Pmin WsD/ Ф2

    Nmax = 0.01273 Pmin WsD/ Ф2

    As= (γchLfa)/(fs)

    As= area of steel required per unit width

    fs= allowable stress

    γc = unit weight of concrete (0.0868 pci)

    h= thickness of the slab (in)

    L= distance from longitudinal joint to free edge

    where no tie bars exist (in)

    fa= average of coefficient of friction

  • MAP 1053/MKAQ 1053 3

    t= ½ ( fsd/ μ)

    t= length of tie bar

    fs= allowable stress

    d= diameter of tie bar

    μ= allowable bond stress (350 psi for deformed

    bars)

    Table 1.1 Approximate Relationship Between Shrinkage and Indirect Tensile

    Strength of PCC

    Indirect tensile strength (psi) Shrinkage (in./in.)

    300 or less 0.0008

    400 0.0006

    500 0.00045

    600 0.0003

    700 or greater 0.0002

    Table 1.2 Recommended Value of the Thermal Coefficient of PCC as a

    Function of Aggregate types

    Type of course aggregate Concrete thermal coefficient (10-6/˚F)

    Quartz 6.6

    Sandstone 6.5

    Gravel 6.0

    Granite 5.3

    Basalt 4.8

    Limestone 3.8

  • MAP 1053/MKAQ 1053 4

    Table 1.3 Allowable Steel Working Stress

    Indierct tensile strength of concrete at

    28 days (psi)

    Reinforcing bar size

    No. 4 No.5 No.6

    300 or less 65000 57000 54000

    400 67000 60000 55000

    500 67000 61000 56000

    600 67000 63000 58000

    700 67000 65000 59000

    800 or greater 67000 67000 60000

    Table 1.4 Recommended friction factors

    Types of Material Beneath Slab Friction factor (f)

    Surface treatment 2.2

    Lime stabilization 1.8

    Asphalt stabilization 1.8

    Cement stabilization 1.8

    River gravel 1.5

    Crushed stone 1.5

    Sandstone 1.2

    Natural subgrade 0.9

    Table 1.5 Yield strength and allowable stress for steel

    Type and grade of steel Yield strength

    (psi)

    Allowable stress (psi)

    Billet steel, intermediate grade 40 000 27 000

    Rail steel or hard grade of billet

    steel

    50 000 33 000

    Rail steel, special grade 60 000 40 000

    Billet steel, 60 000 psi

    miminum yield

    60 000 40 000

    Cold drawn wire (smooth) 65 000 43 000

    Cold drawn wire (deformed) 70 000 46 000

  • MAP 1053/MKAQ 1053 5

    Table 1.6 Weights and dimensions of standard reinforcing bars

  • MAP 1053/MKAQ 1053 6

    DESIGN INPUTS

    Input Variable Value Input variable Value

    Reinforcing

    Bar/Wire Diameter

    Ф (inches)

    Thermal

    Coefficient Ratio

    αs/αc (in./in.)

    Concrete Shrinkage

    , Z (in./in.)

    Design

    Temperature Drop

    DTD (˚F)

    Concrete Tensile

    Strength, ft (psi)

    Wheel Load Stress

    σw (psi)

    DESIGN CRITERIA AND REQUIRED STEEL PERCENTAGE

    Crack Spacing,

    x (feet)

    Allowable

    rack Width ,

    CWmax

    (inches)

    Allowable

    Steel Stress,

    (σs) max (ksi)

    Design steel

    range

    Value of

    Limiting

    Criteria

    Minimum

    Required Steel

    Percentage

    Maximum

    Allowable Steel

    Percentage

    Table 1.7 for Q1b

    Worksheet for Longitudinal Reinformecement Design

    Note: Please return this figure along with your answer book

  • MAP 1053/MKAQ 1053 7

    Figure 1.1 for Q1b: Percent steel to satisfy crack spacing criterion

  • MAP 1053/MKAQ 1053 8

    :

    Figure 1.2 for Q1b: Percent steel to satisfy crack width criterion

  • MAP 1053/MKAQ 1053 9

    Figure 1.3 for Q1b: Percent steel to satisfy steel stress criterion

  • MAP 1053/MKAQ 1053 10

    Q2. (a) AASHTO 1993 Design Guide used an empirical design approach in

    designing the thickness of structural layer. Recent development, ATJ 5/85

    (2013 revision) method was developed based on mechanistic-empirical

    design approach. By using this two types of design method (AASHTO

    1993 and ATJ 5/85 (2013)) as an example, explain in details the

    difference between empirical and mechanistic-empirical approach.

    (5 marks)

    (b) Determine the required structural thickness for a dual carriageway Rural

    Arterial using AASHTO 1993 Design Guide. The following data were

    given.

    Analysis period of 20 years

    ESAL for the first = 2 million

    Traffic growth rate of 4% per annum

    Directional spilt 60/40

    Lane distribution factor of 80%

    Standard deviation of 0.45

    Initial serviceability of 4.5

    Terminal serviceability of 2.5

    Soil will be exposed to six months of dry and 6 months of wet season.

    Both base and subbase materials are of good drainage quality and percent

    of pavement structure exposed to moisture levels approaching saturation

    is 10%.

    (20 marks)

    (25 marks)

    Growth factor= (1+r)n-1

    r

    ∆PSI= po - pt

    w18 = DD x DL x ŵ18

    SN=a1D1 + a2D2m2 + a3D3m3

    D1* ≥ SN1/a1

    SN1* = a1D1 * ≥ SN1

    D2*≥ (SN2 – SN1*)/(a2m2)

    SN1* + SN2 * ≥ SN2

    D3*≥ (SN3 – (SN1* + SN2* ))/ (a3m3)

    μf = 1.18 x 108 x MR-2.32

  • MAP 1053/MKAQ 1053 11

    Table 2.1 Suggested Levels of Reliability for Various

    Functional Classifications

    Functional Classification Recommended Level of

    Reliability

    Urban Rural

    Interstate and other Freeways 85-99.9 80-99.9

    Principle Arterials 80-99 75-95

    Collectors 80-95 75-95

    Local 50-80 50-80

    Layers Moduli:

    Asphalt Concrete : EAC= 400,000 psi

    Granular Base: EBS= 28,000 psi

    Granular Subbase: ESB= 13,000 psi

    a1 = 0.41

    a2 = 0.294(log10 EBS) – 0.977

    a3 = 0.227 (log10ESB) – 0.839

    Table 2.2 Recommended mi values for untreated Base and Subbase

    Percent of Time Pavement Structure is Exposed to Moisture Levels

    Approaching Saturation

    Quality of

    Drainage

    < 1% 1-5% 5-25% >25%

    Excellent 1.40-1.35 1.35-1.30 1.30-1.20 1.20

    Good 1.35-1.25 1.25-1.15 1.15-.100 1.00

    Fair 1.25-1.15 1.15-1.05 1.05-0.80 0.80

    Poor 1.15-1.05 1.05-0.80 0.80-0.60 0.60

    Very Poor 1.05-0.95 0.95-0.75 0.75-0.40 0.40

    Table 2.3 Effective Roadbed Soil Resilient Modulus

    Roadbed Moisture Condition Roadbed Soil Resilient Modulus

    (psi)

    Wet 5000

    Dry 6500

    Spring- Thaw 4000

    Frozen 20000

  • MAP 1053/MKAQ 1053 12

    Figure 2.1 for Q2b

  • MAP 1053/MKAQ 1053 13

    PART B

    Q3. A new big township is under construction and a monthly news bulletin is

    distributed monthly to everyone involved in the management and the

    construction of the township. An article on a certain construction aspect is

    highlighted every month. The article to be included in the next month’s

    bulletin is on road construction. The pavement for the roads in the town

    are of two types; asphalt pavement and concrete block pavement.

    Write a draft for the article to explain the various layers and components

    of the pavements. Good construction practices and various innovations

    should also be included to provide for an interesting and purposeful

    reading.

    (25 marks)

    Q4. (a) A full cut section of a road has failed during a raining season. The cut

    slopes which consist of simply constructed long and steep slopes without

    proper drainages and without proper erosion control have collapsed. The

    pavement has also failed because of water infiltration into the subgrade.

    Suggest how a reconstruction of this failed section should be done to

    provide for a permanent solution. The reconstruction should consist of the

    required drainages; both surface and subsurface and erosion control

    measures.

    (16 marks)

    (b) The use of rocks and large stones is a common feature in road

    construction. Differentiate between a rip rap, a stone mattress and a

    gabion in terms of their features and contributions.

    (9 marks)

    (25 marks)