final - nebt 2018-02-24 workshop presentation … · final - nebt 2018-02-24 workshop presentation...

27
District of Columbia Water and Sewer Authority David L. Gadis, CEO and General Manager March 14, 2019 WELCOME NEIGHBORS! Clean Rivers Project Northeast Boundary Tunnel Tunnel Forum Meeting

Upload: others

Post on 15-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

0

District of Columbia Water and Sewer AuthorityDavid L. Gadis, CEO and General Manager

March 14, 2019

WELCOME NEIGHBORS!

Clean Rivers Project

Northeast Boundary Tunnel

Tunnel Forum Meeting

Page 2: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

1

Community Welcome –

Page 3: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

2

Agenda

Welcome

Construction Sites Schedule

First Street NW Pumping Station Construction Site

Florida Avenue NW Construction Site

Local Business Partnership with North Capitol Main Street

NEBT Outreach and Tunnel Forum Recruitment

Questions

Page 4: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

3

Northeast Boundary Tunnel Project Overview

This is a Federal Consent Decree Project

Between DC Water, the District of Columbia, the U.S. Environmental Protection Agency, and the U.S.

Department of Justice. Salini-Impregilo/Healy Joint Venture (SIH) is the design-builder selected for the

work.

Mitigate chronic flooding

For decades during heavy rainfalls, the neighborhoods of LeDroit Park and Bloomingdale, the Rhode

Island Metro Station area, other neighborhoods near Rhode Island Avenue, and Mount Olivet Road, NE

experienced chronic flooding. The Northeast Boundary Tunnel, being mined by Chris the Tunnel Boring

Machine, will significantly mitigate sewer flooding while improving the water quality of the Anacostia River.

Reduce untreated combined sewage overflows to Anacostia and Potomac Rivers

and Rock Creek

Currently 88% (?) of the CSO discharging to the Anacostia prior to the Clean Rivers project, now go to

Blue Plains for treatment. It will go up to 98% after NEBT. 300 tons of floatables were captured in Blue

Plains last year.

Page 5: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

4

Construction Site Schedule

Page 6: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

5

Construction Site Schedule

R Street NW

MAY 2019 – JUNE 2019

Mobilization on Site

Install Geotechnical and Monitoring

Instrumentation

Site Preparation

T Street NW

Completed Utility Relocation

OCTOBER 2019 – DECEMBER 2019

Mobilization on Site/Site Preparation

Install Geotechnical and Monitoring

Instrumentation T Street NW

Construction Site

R Street NW

Construction Site

Page 7: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

6

First Street NW Pumping Station Construction Site –

Page 8: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

7

First Street NW Pumping Station Construction SiteConstruction Site Work Sequencing Overview

FEBRUARY 2019 – MARCH 2019 Mobilization on Site/Site Preparation

Bryant Street Alternate Parking Area (APA)

Install Geotechnical and Monitoring

Instrumentation

Median Removal

MARCH 2019 – NOVEMBER 2019 Jet Grout / Ground Improvement

Page 9: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

8

First Street NW Pumping Station Construction SiteRhode Island Avenue NW Median Removal

MEDIAN REMOVAL Purpose

Safely move motorists, pedestrians, bicyclists

around construction work. Assure the safety of

our workers.

Minimize impact on traffic due to our

construction work

• Maintain 2 lanes-- 11-feet wide-- in each

direction and at all times on Rhode Island

Avenue NW

Designed to meet DDOT Maintenance of Traffic

standards

Parking Restrictions

Page 10: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

9

Update on Bryant Street Alternative Parking Area

Letters mailed to residents eligible to

park in the APA

Welcome packages to include the

parking tags will be mailed this week

Security guards will be posted at the

APA

Page 11: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

10

First Street NW Pumping Station Construction Site Median Removal Plan

The First Street Tunnel and the Northeast

Boundary Tunnel will be connected at the

intersection of First Street NW and Rhode

Island Avenue NW.

Jet grouting is a construction method for

ground improvement or soil stabilization.

Page 12: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

11

Jet Grouting

Page 13: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

12

First Street NW Pumping Station Construction Site Tree Replanting Plan

© Robert O’Brien

Willow Oak

Legend

Trees

Page 14: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

13

First Street NW Pumping Station Construction Site Monitoring Noise and Vibration

24-hour noise and vibration meter continuously

uploads data to our server for review

The noise and vibration specialist checks meter

regularly

Meters are programmed with an alarm that when

triggered, the specialist and others on the team,

receive a notification

Determine if alternative construction methods or

additional mitigation is required based on meter

readings

A portable meter is available if a resident informs us of

excessive noise or vibration impacts

Page 15: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

14

Florida Avenue NW Construction Site –

Page 16: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

15

Florida Avenue Construction SiteConstruction Site Work Sequencing Overview

FEBRUARY 2019 – APRIL 2019 Mobilization on Site

Install Geotechnical and Monitoring Instrumentation

Site Preparation

APRIL 2019 – JANUARY 2020 Install Secant Piles for Shaft

Ground Stabilization: Ground Freezing and Jet Grouting

Drop Shaft Excavation, Final Lining, and Hydraulics

Page 17: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

16

Florida Avenue Construction SiteAlternative Route

Florida Avenue NW

Page 18: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

17

Florida Avenue NW Construction SiteTree Removal Plan

S Street NW

3rdS

tree

t N

W

Page 19: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

18

Florida Avenue NW Construction SiteTree Planting Plan

© Robert O’Brien

Bur Oak

S Street NW

3rdS

tree

t N

W

Page 20: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

19

Local Business Partnership with North Capitol Main Street –

Page 21: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

20

North Capitol Main Street Partnership

Service Description

Business Impact Mitigation Assistance • Construction Impact Mitigation Plan

• Wayfinding Signage and Beautification Plan

• Needs Assistance and Health Check

Economic Vitality • Web, Social Media, and Mobil Delivery

• Marketing and Branding

• Negotiation Assistance

Design • Storefront Enhancement

• Storefront Signage

Page 22: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

21

NEBT Outreach and Tunnel Forum Recruitment –

Page 23: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

22

Tunnel Forum Recruitment

Sign up today to participate!

Contact Us:NEBT Outreach Team: [email protected] Northeast Boundary Tunnel Project: dcwater.com/NEBT24/7 NEBT Hotline: 1-800-988-6151

Tunnel Forums are reoccurring, collaborative meetings to share

information about the project, gather community input, and

collectively resolve issues while building relationships.

Participants Drive Solutions!

Get Involved to:

• Learn about what is happening

• Ask questions

• Provide feedback

• Get results!

Drives

Solutions!

Tunnel Forums

DC WaterContractor

SIHCommunity

Page 24: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

23

Questions?

Page 25: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

24

R Street NW Construction Site Restoration Plan

Restoration Plan and

Renderings

of Cooper/Gordon Park

Page 26: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

25

T Street NW Construction SiteTree Removal Plan

Page 27: Final - NEBT 2018-02-24 Workshop Presentation … · Final - NEBT 2018-02-24 Workshop Presentation Author: Cassidy, John Created Date: 3/14/2019 3:13:34 PM

26

T Street NW Construction SiteTree Replanting Plan