final paper reu summer2010

Upload: kenechukwu-okoye

Post on 03-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Final Paper Reu Summer2010

    1/34

    1

    PROJECT REPORT

    NON-DESTRUCTIVE TESTING OF A BOX GIRDER BRIDGE

    Submitted To

    The 2010 Summer NSF REU Program in Engineering TomorrowPart of

    NSF Type 1 STEP Grant

    Sponsored By

    The National Science Foundation

    Grant ID No.: DUE-0756921

    College of Engineering and Applied Science

    University of Cincinnati

    Cincinnati, Ohio

    Prepared By:

    Robert Golsby, Chemical Engineering, University of Cincinnati

    Eliseo Iglesias, Mechanical Engineering, Trinity University

    Kenechukwu Okoye, Biomedical Engineering, University of Cincinnati

    Report Reviewed By:

    _______(signature)______

    Richard A. Miller, PhD, PE, FPCI

    Professor

    Department of Civil Engineering

    University of Cincinnati

    June 21-August 13, 2010

  • 7/28/2019 Final Paper Reu Summer2010

    2/34

    2

    AbstractThe scope of this project involved the examination, testing, and analysis of an adjacent

    box girder bridge. The purpose of this project was initially to find a relationship between visual

    damage of pre-stressed concrete box girders within the bridge and the actual performance of the

    bridge. This relationship is important because any kind of correlation would serve for the benefitof officials in charge of rating the quality of these types of bridges. Due to time constraints, only

    baseline tests were completed. The REU students in these baseline tests took data and video of

    the experiment, which involved placing trucks on the test bridge (which was a bridge in Fayette

    County). From these tests, the students (using models created in Visual Analysis) were able toapproximate the concrete strength and moment of inertia of the adjacent box girders. Also it was

    found that the bridge is at least partially continuous; further testing is needed to confirm. These

    baseline tests allowed for the examination of the bridge under loads; this sets up as a control for

    future destructive tests.

  • 7/28/2019 Final Paper Reu Summer2010

    3/34

    3

    Acknowledgements

    Research Contr ibutors

    Research Experience for Undergraduates Site in Structural Engineering: Development of

    Enhanced Materials and Structural Assemblages Used in Seismic Performance EvaluationStudies No. DUE-0756921 NSF REU Grant

    University of Cincinnati Staff

    Dr. Carlo Montemagno-Project Director

    Dr. Anant R. Kukreti- Project Coordinator

    Dr. Richard Miller-Faculty Mentor

    Ms. Marlo Thigpen-Grant Coordinator

    Phil Grosvenor- IT Coordinator

    Ms. Mary Ann Schaefer- Senior Business Administrator

    Dawit Alemayehu - Graduate Assistant

    Tyler Stillings- Graduate Assistant

    Sanooj Edalath Graduate Assistant Helper

    Elie Hantouche- Graduate Assistant Helper Dr. Eric Steinburg- Associate Professor of Civil Engineering David R. Breheim, Research

    Associate

    Dr. Sam Khoury Research Engineer

    Ohio University Graduate Studentso Jon Huffman, Clint Setty, Kyle Grupenhoff, Brendan Kelly and Santiago Camino

    ODOT (Ohio Department of Transportation)

    Steven G. Luebbe. P.E., P.S., Fayette County Engineer

    REU Seminar Presentors

    Andrea Burrows

    Dr. Ron Millard

    Kim Simmons

    Dr. Raj Manglik Amber Erickson

    Ted Baldwin

    Jim Casper

    Dr. Makram Sidan

    Dr. Dorothy Air

    Geoffery Pinski

    Dr. Tim Keener

  • 7/28/2019 Final Paper Reu Summer2010

    4/34

    4

    Table of ContentsAbstract.......................................................................................................................................................................... 2

    Acknowledgements ....................................................................................................................................................... 31. INTRODUCTION ............................................................................................................................................... 6

    2. GOAL AND PROJECT OBJETIVES ............................................................................................................... 7

    3. RESEARCH TASKS ........................................................................................................................................... 8

    3.1. Literature Review....................................................................................................................................... 8

    3.1.1. Types of Loads on Bridges .................................................................................................................... 8

    3.1.2. Truck Loading ....................................................................................................................................... 8

    3.1.3. Precast Concrete .................................................................................................................................... 8

    3.1.4. Adjacent Box Girder Bridges ............................................................................................................... 9

    3.1.5. Deformation and Deterioration ............................................................................................................ 9

    3.2. Rudimentary Analysis of Bridge............................................................................................................... 9

    3.2.1. Bridge Information ................................................................................................................................ 9

    3.2.2. Determination of Calculated and Derived Values............................................................................. 11

    3.2.3. Assumed and Approximated Values .................................................................................................. 11

    3.2.4. AASHTO Specifications ...................................................................................................................... 12

    3.3. Simulation of loading ............................................................................................................................... 13

    3.3.1. Purpose of Simulating ......................................................................................................................... 13

    3.3.2. Simulation Setup .................................................................................................................................. 14

    3.3.3. Simulation Results ............................................................................................................................... 15

    4. MEASURING INSTRUMENTS ...................................................................................................................... 17

    4.1. Strain Gauges ........................................................................................................................................... 17

    4.2. String Potentiometer ................................................................................................................................ 17

    5. BENCHMARK TEST ....................................................................................................................................... 18

    5.1. Initial Preparation.................................................................................................................................... 18

    5.2. Placement of Instruments ........................................................................................................................ 19

    5.3. Collection of Data..................................................................................................................................... 20

    5.4. Results ....................................................................................................................................................... 21

    6. ANALYSIS OF RESULTS ............................................................................................................................... 22

    6.1. Finding the AASHTO specified Moment Distribution Factor ............................................................. 12

    6.2. Tuning the Data to Find Experimental Physical Characteristics. ....................................................... 22

    6.3. Tests for Continuity ................................................................................................................................. 23

    7. CONCLUSION AND APPLICATION ............................................................................................................ 26

    8. RECOMMENDATIONS .................................................................................................................................. 26

    9. FUTURE WORK............................................................................................................................................... 27

    APPENDIX I: NOMENCLATURE AND GLOSSARY OF TERMS ................................................................... 32

  • 7/28/2019 Final Paper Reu Summer2010

    5/34

    5

    Glossary ...................................................................................................................................................................... 32

    Nomenclature ............................................................................................................................................................. 32

    APPENDIX II: RESEARCH TIMELINE ............................................................................................................... 32

    APPENDIX II: RESEARCH TIMELINE ............................................................................................................... 33

    APPENDIX III: SAMPLE CALCULATIONS ....................................................................................................... 34

    Table of F igures

    Figure 1: Arial View of the Bridge

    Figure 2: Cross-Sectional View of the Adjacent Box Girders with the lateral tie

    Figure 3: Cross-Section of a Box Girder

    Figure 4: Fayette County Bridge (Test Bridge)

    Figure 5: Sketch of Bridge Supports

    Figure 6: Simulation of Bridge Behavior under load

    Figure 7: Visual AnalysisModel

    Figure 8: Moment, Shear, and Displacement reactions from simulation

    Figure 9: Instrumentation Position

    Figure 10: Truck Position 1

    Figure 11: Truck Position 2

    Figure 12: Bridge DeflectionTest 3 Load

    Figure 13: Bridge DeflectionsTest 4 Load

    Figure 14: Dynamic Test

    Figure 15: Test 4 LoadTuned Continuous Model (top) vs. Tuned Discontinuous Model (Bottom)

    Figure 16: Test 3 LoadTuned Continuous Model vs. Tuned Discontinuous Model (Bottom)

    Tables

    Table 1: Bridge Facts and Figures

    Table 2: Property Values of the Girders

    Table 3: Simulation Results

    Table 4: Strain Gauge Properties

    Table 5: Wire Potentiometer Sensitivities

    Table 6: Truck Dimensions and Weights

    Table 7: Moment of Inertia

    Table 8: Concrete Strength

    Table 9: Comparison of the Tuned Continuous and Discontinuous Models

  • 7/28/2019 Final Paper Reu Summer2010

    6/34

    6

    1. INTRODUCTIONWhen bridges are designed, engineers must follow a set of constraints set by the

    American Association of State Highway and Transportation Officials (AASHTO). These

    guidelines are set primarily for safety reasons. They involve strict criteria for the strength of

    materials, dimensions, and construction methods. Along with these design specifications, the

    AASHTO provides engineers with formulas and equations of how to estimate and predict the

    behavior of the bridge under its own weight, and under external loading conditions.

    Unfortunately, despite regular visual inspection by government officials, in 2007 the I-35

    Minnesota Bridge did just that, resulting in several casualties. In the disaster, nine people lost

    their lives and sixty were injured. Twenty people turned up missing after the collapse. Two years

    earlier, an adjacent box girder bridge suddenly collapsed in Lakeview, Pennsylvania. In this case,

    no vehicles or people were on the bridge during the collapse. In both cases, there were

    substantial financial losses, and people were inconvenienced while the bridges were being

    rebuilt. While it is safe and often correct to assume that deterioration of certain features of

    bridges cause these collapses, certain aspects of bridge behavior as a result of these

    deteriorations still remains a mystery.

    In Ohio, a large percentage of bridges are built in the same fashion as the Lakeview

    bridge. This presents a possible concern that necessitates thourough inspection procedure for

    these types of bridges. As noted in the Minnesota I-35 bridge collapse, visual inspection is not

    sophisticated enough to predict the behavior of bridges. In order to get a better understanding of

    box girder bridge behavior, researchers often conduct destructive and non-destructive testing of

    the bridges and observe the reactions of the members that comprise the bridge and its supports.

    Through the use of special instruments, the researchers can measure and record these reactions.

  • 7/28/2019 Final Paper Reu Summer2010

    7/34

    7

    From these observations, the researchers continue to try to draw conclusions about bridge

    behavior.

    2. GOAL AND PROJECT OBJETIVESThe main goal of this project is to collect data in a benchmark test on the behavior of an

    adjacent box girder bridge through the use of live (external) loads, measuring instruments and

    recording software. The objectives for this project are as follows:

    Learning Material Strength theory with Dr. Miller

    Gather Research and Understanding of the Project

    Assist in the Benchmark (baseline) tests

    Create Models of the Bridge in Visual Analysis and run simulations

    Compare Benchmark Test Results with Simulation Results

    Tune the Model (find the true E & I of the bridge)

    Compare the Continuous Tuned model to Discontinuous model

    Tabulate and Analyze Results

  • 7/28/2019 Final Paper Reu Summer2010

    8/34

  • 7/28/2019 Final Paper Reu Summer2010

    9/34

    9

    original un-tensioned length, they apply a compressive force. This pre-compression increases

    load-carrying capacity to the beam and helps control cracking to specified limits allowed by

    building codes (Precast/Pre-stressed Concrete Institute).

    3.1.4. Adjacent Box Girder BridgesPre-stressed box beams are cast in pre-stressing plants. The beams are placed side by side

    and held together by lateral tension rods. Grout and shear keys are then used to connect the

    beams together (see Fig. 2) .

    3.1.5. Deformation and DeteriorationDue to corrosion caused by water and heavy salt treatment during the winter time

    corrosion can occur to the beams as well as the internal steel. Because of this the steel strands

    begin to deteriorate and the bridge loses tensile support. As the deterioration level of these

    strands increases pre-stress force decreases. This decreases the maximum load capacity and

    could lead to total collapse of a beam or the bridge.

    3.2. Preliminary Analysis of Bridge3.2.1. Bridge Information

    The bridge that was tested was an adjacent box girder bridge with pre-stressed concrete

    girders. The structure is located in Washington Court House in Fayette County in central Ohio.

    The official number of the bridge is 36-17-6.80. The dimensions and material properties of the

    bridge are as follows:

  • 7/28/2019 Final Paper Reu Summer2010

    10/34

    10

    Table 2: Bridge Facts and Figures

    Property Value

    Type: Adjacent Box GirderLocation: Washington Court House,

    Fayette County, Ohio

    Time Built: Approximately late 1960sSpans/Length: 3 spans, 48 feet each, 144 ft totalNumber of

    Beams/Width:9 adjacent beams, each 3 feet

    wide, 27 feet total widthDepth: 21 inchesSkew: 15 degrees left forwardMaterials used: Prestressed Concrete

    Figure 1: Plan view of Bridge

    Figure 2: Cross-Sectional View of the Adjacent Box Girders with the lateral tie

  • 7/28/2019 Final Paper Reu Summer2010

    11/34

    11

    3.2.2. Determination of Calculated and Derived ValuesFor the purpose of the preliminary analysis, the basic geometry of the cross-section was

    taken into account when finding the moment of inertia (I) for the members. The formula for

    determining this value is as follows:

    (1)Also, the cross-sectional area of the girders itself was determined by basic geometry, using the

    area formula for a rectangle.

    3.2.3. Assumed and Approximated ValuesSome of the information of the bridge was either not readily available or subject to

    unknown changes since the bridge's construction, or had to be determined experimentally. Such

    values included the strength of the concrete, the modulus of elasticity of the concrete, the pre-

    stressing tension in the steel strands, the diameter of the pre-stressing strands, and the level of

    continuity of the bridge. The assumed values are as follows:

    Property Initial value

    Distribution Factor .11 (unitless)

    Concrete strength 7 ksi

    Moment of Inertia 23500 in

    Cross Sectional Area 488 in

    Strand Diameter 3/8 inch

    Continuity Full continuity

    Table 2: Property Values of the Girders

    Figure 4: Fayette County Bridge (Test Bridge)Figure 3: Cross-Section of a Box Girder

  • 7/28/2019 Final Paper Reu Summer2010

    12/34

    12

    3.2.4. AASHTO Specifications: Finding the AASHTO specified Moment DistributionFactor

    According to the following AASTHO specifications, bridges of this type must be design

    with the appropriate distribution factor parameter. Based on the number of girders and several

    other physical aspects of the design, AASTHOs equations give a distribution factor for design

    only. The actual distribution factor of the bridge will be different since this is a design constraint

    (these are usually over estimated). A comparison of between these two values would shed light

    on how damaged the bridge is and how it performs according to its initial design.

    (2)

    Eq. 2 is the formula given by AASTHO for the Distribution factor of a bridge made of girders

    that are Precast solid, voided, or Cellular Concrete Box, with Shear Keys and with or without

    Transverse Post-Tensioning. All the mentioned physical characteristics coincide with the Fayette

    County Bridge.

    The following are formulas that facilitate the D.F. calculation (a sample of this calculation can be

    found in Appendix III).

    (3)

    where

    (4)

  • 7/28/2019 Final Paper Reu Summer2010

    13/34

    13

    Eq. 5 is a D.F. reduction factor for skewed bridges (the Fayette County Bridge is this type).

    (5)where

    When calculated with the appropriate values, the Distribution factor for design of this

    type of bridge is 0.2413. This means that the interior girders of this bridge are designed to

    distribute roughly 24% of any load to each girder.

    3.3.

    Simulation of loading

    3.3.1. Purpose of SimulatingBefore conducting the on-site Benchmark tests, several simulations were run in order to

    have an approximate estimate of how the bridge should behave under the given loads. These

    simulations are designed to give internal moments, shear forces, and displacements at any point

    along the modeled bridge. Once a model is designed and analyzed and the Benchmark test is

    completed, a comparison between predicted and observed values can be done. Also, in the

    model, several assumptions must be made regarding the physical characteristics of the bridge

    itself (most of these are largely unknown). If the differences between these two values are too

    dissimilar, a separate tuning procedure can be done in order to find the true characteristics of

    the bridge. Using several iterations of a certain physical aspect of the bridge, the correct one can

    be found that results in a displacement similar (within an acceptable error) to the displacement

    observed in the Benchmark Test.

    Visual Analysis V. 4 and V.7were used in this analysis. This software allowed for the

    creation of a two-dimensional model of the Fayette County Bridge. The following section

  • 7/28/2019 Final Paper Reu Summer2010

    14/34

    14

    contains details on how the bridge was translated into a two-dimensional model, and how the

    truck loadings were modeled.

    3.3.2. Simulation SetupIn this setup, several steps had to be taken in order to adequately model the bridge in

    Fayette County in Visual Analysis. First, since the model must be reduced to only one beam (2D

    Model), the width of the bridge is disregarded. Also a distribution factor must be applied to any

    real load on the bridge. For the purposes of this simulation a distribution factor of 11% was

    applied. The assumption was made that since the bridge contains nine girders, ideally the weight

    should be distributed evenly throughout the bridge (connecting grout in the shear keys and lateral

    tie, as specified in the bridge plans, should facilitate this distribution, see Fig. 2). The model

    contained the correct length and was separated into three spans (48 feet each). The model bridge

    also has at one end, a pinned joint, and two roller joints (one at 48 feet and the second at 96 feet

    from the leftmost end) that separate it into 3 spans (see Fig.5). The model was also treated as

    continuous. As mentioned before, several physical characteristics of the bridge required

    estimation for the purposes of this simulation. All of these estimated values were subject to

    tuning later in the project.

    The Benchmark Test involved six different loadings (trucks were used for this), and each

    load comprised of different configuration to the truck locations on the bridge. In the Visual

    Analysis model, each tire of the truck was treated as a point load, so if there were 4 trucks on a

    particular loading configuration, there would be 24 point loads on the modeled beam (each truck

    has 3 axles). These point loads would be located on the model based on their distance from the

    abutment (the distance from the side guard rail edges of the bridge were disregarded for the

    purposes of creating a 2D model). Figure 6 shows an example of this model and its point loads.

  • 7/28/2019 Final Paper Reu Summer2010

    15/34

    15

    The six different loadings were simulated, and the following section displays the results from

    this analysis.

    3.3.3. Simulation ResultsAs stated before, Visual Analysis shows the internal forces and moments throughout the

    modeled bridge as well as displacements at every point of the bridge. The max value (in

    magnitude) is 0.399 inches at 22 feet (this occurred in Run 3). This simulation does not take into

    account the dead load the bridge experiences from its own weight. In light of this and the other

    assumptions necessary in order to simulate the behavior of the bridge, the observed

    displacements will not be exact.

    144 ft

    Figure 5: Sketch of Bridge Supports

  • 7/28/2019 Final Paper Reu Summer2010

    16/34

    16

    Table 3: Simulation Results

    7 KSI Strength Concrete Simulation

    I = 25300

    in^4

    A = 488 in^ 2

    Max Negative Max Positive

    Run Deflection (in) Location (ft) Deflection (in) Location (ft)

    1 0.125 22.08 0.04 67.2

    2 0.389 22.08 0.142 67.2

    3 0.399 22.08 0.144 67.2

    4 0.171 22.08 0.03 115.2

    5 0.389 22.08 0.14 67.26 0.171 22.08 0.031 115.2

    Figure 6: Simulation of Bridge Behavior under load

    Figure 7: Visual AnalysisModel

    Figure 8: Moment, Shear, and Displacement reactio

    from simulation

  • 7/28/2019 Final Paper Reu Summer2010

    17/34

    17

    4. MEASURING INSTRUMENTS4.1. Strain Gauges

    Strain gauges were used to measure and record the strain while the concrete girders

    underwent in response to the external load of the ODOT trucks. The gauges that were used were

    resistance gauges and measured two inches in length. They were manufactured in Japan, and

    were affixed to the bridge using an epoxy solution.

    Table 4:Strain Gauge Properties

    Property Value

    Type: WFLM-60-11-2LT

    Gauge Length: 60mm

    Gauge Resistance: 120 0.5

    Temp Compensation For: 1110-6/oC

    Transverse Sensitivity: -5.%

    Quantity: 10

    Gauge Factor: 1.96 1%

    Test Condition: 23C 50%RH

    Batch No.: IE28K

    Lead Wires : 7/O.127 3W 2m

    4.2. String PotentiometerString potentiometers (also known as "wire pots") are generally used to measure linear

    displacement. For this project, they were put to use in measuring and recording the deflections of

    the individual girders during the tests.

  • 7/28/2019 Final Paper Reu Summer2010

    18/34

    18

    Table 5: Wire Potentiometer Sensitivities

    Beam Wire Pot Model Seal (Series) Sensitivity

    (mV/V/inch)

    1S A1 (W) PA-15 3708148 64.70

    2 A2 PA-20 32010211 46.65

    3 A3 PA-15 37080147 64.64

    4 A4 PA-15 37080149 64.69

    5 A5 PA-15 37080150 64.63

    6 A6 PA-10A 9007-5885 97

    7 A7 PT-10A 9007-5883 96.6

    8 A8 PT-10A 9007-5886 96.8

    9N A9 PT-10A 9007-5884 96.6

    1S B1(E) PT-108 9007-5887 97.8

    2 B2 PT101-0010-111-1110 B0952696 91.39

    3 B3 PT101-0015-111-1110 H1003996 61.227

    4 B4 PT101-0010-111-1110 J0962400 92.61

    5 B5 PT101-0010-111-1110 J0962401 91.96

    6 B6 PT101-0015-111-1110 H1003994 62.647

    7 Not Applied8 B8 PT101-0010-111-1110 K0866500 91.83

    9N Not Applied

    5. BENCHMARK TEST5.1. Initial Preparation

    The initial preparation of the benchmark test consisted of the following: marking all of

    the key locations on the bridge (locations of instruments, span endpoints, origin location datum

    Figure 9: Instrumentation Position

  • 7/28/2019 Final Paper Reu Summer2010

    19/34

    19

    (the southwest corner of the bridge where the bridge begins on the west abutment and on the

    white traffic line), etc.), removing the top layer of asphalt at the location of the strain gauges,

    setting up the frame for the wire pots below the bridge, gluing all of the strain gauges in place,

    testing all of the instruments, and opening the recording software. Much of the aforementioned

    preparation was carried out on July 14, 2010. The rest was completed on July 15, 2010.

    5.2. Placement of InstrumentsThe location of the instruments was predetermined during the preliminary analysis

    (where the location of maximum moment and displacement was found, using Visual Analyis).

    Strain gauges were placed on top of the bridge along the midspan (22 ft from the leftmost edge

    of the bridge) of the bridge; one located on the center of each beam, with the exception of the

    northernmost beam. An additional line of gauges was set out an additional 14 feet 6 inches east

    of the first set of strain gauges, which is location of the anticipated inflection point (see Figure

    9). On this line, all of the beams had strain gauges affixed to them. Underneath the bridge on the

    same lines as on the top, strain gauges were glued to the underside of the bridge, with a gauge on

    each beam. Finally, supported by a wooden frame beneath the bridge, wire pots were arranged

    along the aforementioned lines, with a wire pot on each beam on the midspan (22 ft from the

    leftmost edge of the bridge) line and one on each beam on the inflection line, with the exception

    of the northernmost beam and the third northernmost beam.

  • 7/28/2019 Final Paper Reu Summer2010

    20/34

    20

    5.3. Collection of DataThe collection of data involved applying external or "live" loads in the form of trucks

    provided by the Ohio Department of Transportation. TCS for the MegaDec data acquisition

    system was used to record the reading of the array of instruments over time in regular intervals.

    For this test, the rate of collection was 1200 scans per second. The test involved six static tests

    (see Figures 11 and 12), where the four trucks were placed in different locations to investigate

    the different reactions. Following the static tests came two dynamic tests, each involving one of

    the trucks traveling across the bridge, from west to east, first at 10 miles per hour, and again at

    35 miles per hour. Testing began after all of the preparation on July 15, 2010.

    Table 6: Truck Dimensions and Weights

    License Plate: OF 1050 OF 5591 OG 2791 OD 6634

    Number: 41 47 8 31

    L R L R L R L R

    Front Axle Weight

    (lbs)

    7500 6900 7250 7250 7350 7700 5400 6650

    Middle Axle Weight

    (lbs)

    9450 10700 9150 9600 9800 11150 9800 11500

    Rear Axle Weight

    (lbs)

    8850 10750 8950 9850 10050 11200 10000 11300

    Distance - front axleto middle axle: 13-0 130 13-0 12-6

    Distance - font axle to

    rear axle:

    17-8 178 17-8 1610

    Front axle width*: 6-10 6-10 6-10 6-7

    Middle and Rear axle

    width**:

    6-0 6-0 6-0 6-1

    *(middle of tire to middle of tire)

    ** (space between tire pair to space between tire pair)

  • 7/28/2019 Final Paper Reu Summer2010

    21/34

    21

    5.4. ResultsThe following are figures displaying the displacements found in Test 3 and Test 4

    (involving Truck positions 3 and 4). However, only the wire potentiometers in Row A (located at

    22 ft) functioned properly.

    Figure 12: Bridge DeflectionTest 3 Load

    Beam 9

    Beam 8 Beam 7 Beam 6 Beam 5 Beam 4 Beam 3 Beam 2Beam 1

    -0.4

    -0.35

    -0.3

    -0.25

    -0.2

    -0.15

    -0.1

    -0.05

    0

    Deflection(in)

    Beam

    Bridge Deflection - Test 3 Load

    Row A

    Figure 10: Truck Position 1 Figure 11:Truck Position 2

  • 7/28/2019 Final Paper Reu Summer2010

    22/34

    22

    Figure 13: Bridge DeflectionsTest 4 Load

    6. ANALYSIS OF RESULTS6.1. Tuning the Data to Find Experimental Physical Characteristics.

    The results from the Benchmark test showed that the displacements are slightly different

    from the predicted values found using VisualAnalysis. This could be due to some of the

    assumptions made for the physical characteristics being slightly inaccurate. For this reason

    through the iteration of the moment of inertia, and the concrete strength and matching the

    displacements produced in their simulations to those found in the Benchmark Test. Below are the

    Tables that contain these displacements.

    Beam 1

    Beam 2 Beam 3 Beam 4 Beam 5 Beam 6 Beam 7 Beam 8Beam 9

    -0.25

    -0.2

    -0.15

    -0.1

    -0.05

    0

    Deflections(in)

    Beam

    Bridge Deflections - Test 4 Load

    Row A

  • 7/28/2019 Final Paper Reu Summer2010

    23/34

    23

    Table 7: Moment of Inertia

    Iterations for I

    Test 3 Test 4

    I (in^4) Displacements

    (in)

    24800 -0.285 -0.17

    24900 -0.284 -0.169

    25000 -0.283 -0.169

    25100 -0.282 -0.168

    25150 -0.281 -0.168

    25200 -0.281 -0.167

    25300 -0.28 -0.167

    Table 8: Concrete Strength

    Test 3 Test 4

    Strength

    (PSI)

    Displacement (in)

    6800 -0.284 -0.169

    6900 -0.282 -0.168

    7000 -0.28 -0.167

    7100 -0.278 -0.167

    7200 -0.276 -0.165

    7300 -0.274 -0.163

    7400 -0.272 -0.162

    7500 -0.27 -0.161

    6.2. Tests for ContinuityBelow, Fig.15shows of the dynamic test done in the Benchmark Test. The graph displays

    how strain in the first span changes as the truck moves along the bridge. One can infer that the

    bridge is continuous due to the positive strain seen. Since the gauge is at the top of the beam of

    the first span, when the truck is on the third span, the strain should read as negative (if it is

    continuous) and positive when on the second span.

  • 7/28/2019 Final Paper Reu Summer2010

    24/34

    24

    In Figures 16 and 17,a comparison is done between a continuous tuned model of the

    bridge versus a discontinuous tuned model. The discontinuous model has a displacement that is

    much larger than the one observed in the Benchmark Test. Also the observed displacement is

    within 5% of what the tuned model displays.

    Figure 14: Dynamic Test

    -1.40E+02

    -1.20E+02

    -1.00E+02

    -8.00E+01

    -6.00E+01

    -4.00E+01

    -2.00E+01

    0.00E+00

    2.00E+01

    4.00E+01

    1

    549

    1097

    1645

    2193

    2741

    3289

    3837

    4385

    4933

    5481

    6029

    6577

    7125

    7673

    8221

    8769

    9317

    9865

    10413

    10961

    11509

    12057

    12605

    13153

    13701

    microStrain

    ms

  • 7/28/2019 Final Paper Reu Summer2010

    25/34

    25

    Figure 16: Test 3 LoadTuned Continuous Model vs. Tuned Discontinuous Model (Bottom)

    Figure 15: Test 4 LoadTuned Continuous Model (top) vs. Tuned Discontinuous Model (Bottom)

  • 7/28/2019 Final Paper Reu Summer2010

    26/34

    26

    Table 9: Comparison of the Tuned Continuous and Discontinuous Models

    Test 3 Test 4

    Model Displacements (in)

    Continuous -0.28 -0.168Observed -0.282 -0.167

    Discontinuous -0.405 -0.356

    % Difference 0.711744 0.597015

    7. CONCLUSION AND APPLICATIONFrom the analysis of the wire-potentiometer data and the dynamic data (Fig. 14) from the

    strain gauges most of the basic physical characteristics of the Fayette County Bridge. The

    Moment of inertia can be approximated to be roughly 25300 in^4 and the Concrete Strength,

    ~7000PSI. However, the only way to confirm these two values is to first, take a look at the cross

    section (when Dr. Miller and OU conduct the destructive test) to confirm the design from plans,

    and second, take core sample and test for strength.

    The bridge also seems to be at least partially continuous. The dynamic tests suggest this

    and the continuous tuned models show the same displacement as the observed displacement from

    the Benchmark Test.

    8. RECOMMENDATIONSFirst, it is highly recommended that the cross sectional area and the concrete strength be

    tested and recorded.

    More testing is needed in order to confirm continuity by 1) observe behavior during the

    destructive test 2) synchronize a timer along with the data acquisition to pinpoint exactly when

    and where the truck is when positive displacement occurs on the first span (when the truck

  • 7/28/2019 Final Paper Reu Summer2010

    27/34

    27

    passes the third span) and 3) place truck on the third span and check for any kind of reaction in

    the first span where the instruments are installed.

    Instruments on the third and possibly second (middle span) should be considered.

    Although on the middle span this would be difficult since it crosses the water and no kind of

    support would be available for wire-potentiometers and strain gauge attaching, placing strain

    gauges on the tops of the beams (after grinding off the asphalt) of the middle span would help in

    observing behavior throughout the whole bridge and not just one span.

    The strain gauge data did not allow for the examination of the distribution of the load

    throughout the girders simply because of the nature of the test. In all tests a combination of four

    trucks was used, making difficult to relate one truck to a specific displacement in a beam. To

    explore this phenomenon, it is recommended that only truck be used. The location should be

    varied so that the effect on displacement/strain in one beam can be observed.

    9. FUTURE WORKThe bridge will be subject to further tests. The date and time of these tests is to be

    determined. The aforementioned instruments will be used to collect data of the responses to live

    loads, as in the benchmark test, but after the girders have sustained intentional damage. After

    these series of tests, special equipment will be used to apply increasing loads until the bridge

    fails. This will tell the researchers the ultimate load capacity of the bridge after damage. After all

    of the tests, including the ones covered in this report, researchers shall have a better idea of the

    distribution of forces among the adjacent members, establish a connection between apparent

    damage and the effect on the ultimate load capacity, and use the findings to improve bridge

    design and inspection methods.

  • 7/28/2019 Final Paper Reu Summer2010

    28/34

    28

    Bibliography

    AASHTO. (2008).The Manual for Bridge Evaluation. Washington, DC: American Association

    of State Highway and Transportation Officials, 1st

    Edition.

    AASHTO. (2007).LRFD Bridge Design Specifications. Washington, D.C.: American

    Association of State Highway and Transportation Officials, 4th

    Edition

    AASHTO. (2002).Standard Specifications for Highway Bridges.Washington, D.C.: AmericanAssociation of State Highway and Transportation Officials, 17

    thEdition

    ACI Committee 345. (2006). Guide for Maintenance of Concrete Bridge Members. ACI 345.1R-06.

    Bentz, E. 2000. Response-2000 Reinforced Concrete Sectional Analysis using the Modified

    Compression Field Theory. Version 1.0.5.

    ACI Committee 222 (2001),Protection of Metals in Concrete Against Corrosion, ACI

    Publication No. 222R-01, American Concrete Institute, Farmington Hills, Michigan

    ACI Committee. (2005), Building Code Requirements for Structural Concrete and Commentary,American Concrete Institute. ACI 318-05, American Concrete Institute, Farmington Hills,

    Michigan.

    American Association of State Highway Officials. (1965).Standard Specifications for Highway

    Bridges, Washington DC, 6th

    Edition.

    American Association of State Highway and Transportation Officials.(2010).Section 4:

    Structural Analysis and Evaluation.AASHTO LRFD Bridge Design Specifications, pp.29-39.

    ASTM International.(2004).C39/C39 Compressive Strength of Cylindrical Concrete

    Specimens, West Conshohocken, PA

    ASTM International.(2004). C856,Petrographic Examination of Hardened Concrete, West

    Conshohocken, PA

    ASTM International.(2004). Microscopical Determination of Parameters of Air-Void System inHardened Concrete, West Conshohocken, PA

    ASTM International.(2004). Acid-Soluble Chloride in Mortar and Concrete, WestConshohocken, PA

    ASTM International.(2004). A370-97a Standard Test Methods and Definitions for Mechanical

    Testing of Steel Products, West Conshohocken, PA

    ASTM International.(2004). Aa16/A416M-99 Standard Specification for Steel Strand. ASTM

    No. A416, Uncoated Seven-Wire for Prestressed Concrete, West Conshohocken, PA

  • 7/28/2019 Final Paper Reu Summer2010

    29/34

    29

    Billington, D. P. (2004). Historical Perspective on Prestressed Concrete.PCI Journal49,

    No.1,pp.14-30.

    Glass, G.K. and Buenfeld, N.R.(1997), The Presentation of the Chloride Threshold Level for

    Corrosion of Steer in Concrete, Corrosion Science, Vol. 39, No. 5, pp 1001-1013.

    Gulistani, Aziz A. March.(2010). Forensic Investigation of Prestressed Concrete Box Beams

    from LIC-310 Bridge. A thesis presented to the faculty of the Russ College of Engineering and

    Technology of Ohio University in partial fulfillment of the requirements for the degree Master ofScience.

    Harries, K. A. (2009). Structural Testing of Prestressed Concrete Girders from the Lake View

    Drive Bridge.Journal of Bridge Engineering14, No. 2, pp.78-92.

    Harries, K. A., R. Gostautas, C. J. Earls, and C. Stull.(2006).Full-Scale Testing Program on De-

    commissioned Girders from the Lake View Drive Bridge. The Pennsylvania Department ofTransportation, Dept. of Civil and Environmental Engineering, Univ. of Pittsburgh, Pittsburgh,

    Rep. No. CE/ST 33.

    Hartle, R.(2006), Field Inspection and Forensic Investigation of the SR 1014 Lake View DriveBridge over Interstate 70 Final Report, Michael Baker, Jr. Report, pp. 52.

    Kassimali, Aslam.(2005). Structural Analysis. Cengage Learning, 4th

    Edition, pp. 17-24, 330-374.

    Kosmarka, S., H., Panarese, W., C.(1990), Design and Control of Concrete Mixtures,

    !3th

    Edition, Portland Cement Association, Skokie, III,pp.205.

    Labia, Y., M. S. Saiidi, and B. Douglas. (1997). Full-Scale Testing and Analysis of 20-Year-Old

    Pretensioned Concrete Box Girders.ACI Structural Journal94, No.5, pp. 471-82.

    Macioce, T., Rogers H., Anderson, R., and Puzey, D., C.(2007), Prestressed Concrete Box

    Beam Bridges- Two DOTS Experience, 2007 PCI-FHWA National Bridge ConferenceSession, pp. 83.

    MDOT. September (2005). Box-Beam Concerns Found under the Bridge. Construction and

    Technology Research Record, No.102, pp. 1-4.

    Menn, C., and P. Gauvreau. (1990).Prestressed Concrete Bridges. Basel Switzerland; Boston:

    Birkhuser Verlag.

    Miller, R., and K. Parekh. (1994). Destructive Load Testing of a Damaged and Deteriorated

    Prestressed Concrete Box Beam. MS Thesis.,University of Cincinnati.

  • 7/28/2019 Final Paper Reu Summer2010

    30/34

    30

    Miller, R., and K. Parekh. (1994). Destructive Testing of Deteriorated Prestressed Box Bridge

    Beam. Transportation Research Record(1460), pp. 37-44.

    Naito, C., R. Sause, I. Hodgson, S. Pessiki, and C. Desai. (2006).Forensic Evaluation ofPrestressed Box Beams from the Lake View Drive Bridge over I-70. Lehigh Univ., Lehigh, Pa.,

    ATLSS Report No. 06-13.

    Naito, C., R. Sause, and B. Thompson. (2008). Investigation of Damaged 12-Year Old

    Prestressed Concrete Box Beams.Journal of Bridge Engineering13, No. 2, pp.139-48.

    Nasser, G. D. (2008). The Legacy of the Walnut Lane Memorial Bridge. STRUCTURE Magazine

    2008, (10), pp.27-31.

    ODOT. (2007). Bridge Design Manual.Ohio Department of Transportation. January 2009Edition

    PennDOT Bridge Quality Assurance Division,(2006), Superstructure, BMS Item E18,Condition Rating Guidelines for Prestressed Concrete for Prestressed Concrete Adjacent Box

    Beams, Strike-offLetter 431-06-02.

    PennDOT Bridge Quality Assurance Division.(2007), PennDOT Bureau of Design BridgeManagement System 2 Coding Manual, Publication 100A.

    Pennsylvania Department of transportation.(2002), Bridge Safety Inspection Manual, PennDOTPublication 238, 2

    thEdition

    PCI.(2004).PCI Design Handbook. Background, PCI MNL- 120-04, 6th

    Edition.

    PCI.(2004).PCI Design Handbook. Features and General Principles, PCI MNL- 120-04, 6th

    Edition.

    PCI.(1989).Architectural Precast Concrete. Manual Contents and Concepts, PCI MNL-122-89,

    2nd

    Edition.

    PCI.(2004).PCI Design Handbook. Common Products, PCI MNL-120-04,6th

    Edition.

    PCI.(2004). An Industry On The Rise, Visions Taking Shape: Celebrating 50 Years of the

    Precast/Prestressed Concrete Industry; Chero Publishing Co.

    PCI.(2006).Architectural Precast Concrete. Applications of Architectural Precast Concrete, PCI

    MNL-122-06, 3rd

    Edition.

    PCI.(2006).Architectural Precast Concrete. Advantages of Architectural Precast Concrete,

    Architectural Precast Concrete, 3rd

    Edition.

  • 7/28/2019 Final Paper Reu Summer2010

    31/34

    31

    Precast/Prestressed Concrete Institute. (2004). PCI Design Handbook, Precast and Prestressed

    Concrete, Chicago: Precast/Prestressed Concrete Institute, 6th

    Edition.

    Shenoy, C. V., and G. C. Frantz. (1991). Structural Tests of 27-Year-Old Prestressed Concrete

    Bridge Beams.PCI Journal36, No.5, pp. 80-90.

    Whiting, D., and B. G. Stejskal. (2004). Field Studies of Corrosion in Prestressed ConcreteBridges.Philip D. Cady International Symposium on Concrete Bridges in Aggressive

    Environments, pp. 73-93.

  • 7/28/2019 Final Paper Reu Summer2010

    32/34

    32

    APPENDIX I: NOMENCLATURE AND GLOSSARY OF TERMS

    Glossary

    Moment of Inertia - A property, based on its geometry (most generally based on the

    object's centroid or cross sectional area) of an object's (or member) resistance to bending.Usually expressed in units of length, i.e. in^4

    Concrete Strength This is the compressive strength of concrete, determined

    experimentally, and given in units of PSI. This value can be calculated from the Modulus ofElasticity

    Modulus of Elasticity - A measure of an object's tendency to be deformed elastically

    under an applied force.

    Distribution Factor - A design parameter given by AASTHO (can be approximated by

    dividing the number of lanes by the number of beams) that specifies the amount of load eachbeam experiences when the bridge is loaded.

    Continuity or Discontinuity - If the bridge is separated into several spans, the beams in

    each span could be connected to each other making the entire structure continuous. If theyare not, then the structure would be considered discontinuous. These two characteristics

    change the response of the bridge from a load.

    Tuning - Through several iterations of a simulation, the characteristics of the bridge are

    changed until the response matches up with the response seen at the Fayette County Bridge.

    This approximates or "tunes" the characteristic in question.

    Cross-Sectional Area - This is the area of the inside cross section of a beam.

    SkewThe amount of angle given to a bridge with respect to whatever it is over passing.For example if a bridge were placed perpendicular to a river, then there is no skew. However,

    if the bridge is placed 15 off the perpendicular then is it considered a 15 degree skew.

    Nomenclature

    E = Youngs modulus of elasticity

    I = Moment of InertiaJ = Polar Moment of Inertia

    b = width of the beam (in)

    d = depth of beam (in)

    L = span of the beam (ft)Nb = number of beams or girders

    = skew angle (degrees)

    A*

    = Area of the body (from parallel axis theorem)z = Distance from the centroid of the body to the axis (from parallel axis theorem)

  • 7/28/2019 Final Paper Reu Summer2010

    33/34

    33

    APPENDIX II: RESEARCH TIMELINE

    Informational Session 06/21-22/2010

    Information was provided an introduction to the research. This information told of previous tests

    that were done from other research projects and why.

    Literature and Lectures 06/24-28/2010

    Lectures were given by Dr. Richard Miller and Mr. Dawit on the basics of the physics and

    mechanics of bridge structures. Some homework and reading material was provided.

    Procurement of Materials and Resources 06/30/2010 to 0713/2010

    Materials needed for the experiment were gathered while researching was being done. These

    materials consisted of available trucks, wire pots, gauges, etc.

    Research Application to Bridge 07/02-07/2010

    The information learned from the literature and lectures was then applied to the project bridge in

    preparation for visual analysis simulations. This consisted of how the internal forces act in the

    bridge such as moment and shear. Also, known characteristics and properties of the bridge were

    obtained and documented.

    Simulations 07/07-09/2010

    Using known information and some assumptions simulations were done for maximizing

    deflections on the bridge using Visual Analysis. This was done by finding the precise position to

    place the trucks. Simulations were done for continuous and discontinuous cases to model

    possible deflections and to obtain deflection results for comparison.

    Benchmark Test 07/14-15/2010

    This part of the project consisted of benchmark test set-up followed by the benchmark test. This

    was a two day event at the bridge located in Washington Court House. Data was collected to be

    analyzed at a future time (*see Benchmark Test).

    Post-Benchmark Test Analysis 07/16-26/2010

    Data was obtained and analyzed. After results for the actually benchmark test were found theses

    results where then compared to the simulations to determine the continuity of the bridge. Other

    useful Information which could possibly help with future tests were then documented by UC and

    OU students and faculty. All possible errors experimental, electronic and environmental were

    documented so that they could be fixed or prevented in future tests.

  • 7/28/2019 Final Paper Reu Summer2010

    34/34

    Conclusion 08/02-06/2010

    All Information for this project was then put together in a note book, report, poster and power

    point for documentation and presentation needed in the future.

    APPENDIX III: SAMPLE CALCULATIONS

    AASTHOs Distribution Factor

    b=36 in d=21 in

    L=48 ft =9 beams

    ( )

    ( )