final paper reu summer2010
TRANSCRIPT
-
7/28/2019 Final Paper Reu Summer2010
1/34
1
PROJECT REPORT
NON-DESTRUCTIVE TESTING OF A BOX GIRDER BRIDGE
Submitted To
The 2010 Summer NSF REU Program in Engineering TomorrowPart of
NSF Type 1 STEP Grant
Sponsored By
The National Science Foundation
Grant ID No.: DUE-0756921
College of Engineering and Applied Science
University of Cincinnati
Cincinnati, Ohio
Prepared By:
Robert Golsby, Chemical Engineering, University of Cincinnati
Eliseo Iglesias, Mechanical Engineering, Trinity University
Kenechukwu Okoye, Biomedical Engineering, University of Cincinnati
Report Reviewed By:
_______(signature)______
Richard A. Miller, PhD, PE, FPCI
Professor
Department of Civil Engineering
University of Cincinnati
June 21-August 13, 2010
-
7/28/2019 Final Paper Reu Summer2010
2/34
2
AbstractThe scope of this project involved the examination, testing, and analysis of an adjacent
box girder bridge. The purpose of this project was initially to find a relationship between visual
damage of pre-stressed concrete box girders within the bridge and the actual performance of the
bridge. This relationship is important because any kind of correlation would serve for the benefitof officials in charge of rating the quality of these types of bridges. Due to time constraints, only
baseline tests were completed. The REU students in these baseline tests took data and video of
the experiment, which involved placing trucks on the test bridge (which was a bridge in Fayette
County). From these tests, the students (using models created in Visual Analysis) were able toapproximate the concrete strength and moment of inertia of the adjacent box girders. Also it was
found that the bridge is at least partially continuous; further testing is needed to confirm. These
baseline tests allowed for the examination of the bridge under loads; this sets up as a control for
future destructive tests.
-
7/28/2019 Final Paper Reu Summer2010
3/34
3
Acknowledgements
Research Contr ibutors
Research Experience for Undergraduates Site in Structural Engineering: Development of
Enhanced Materials and Structural Assemblages Used in Seismic Performance EvaluationStudies No. DUE-0756921 NSF REU Grant
University of Cincinnati Staff
Dr. Carlo Montemagno-Project Director
Dr. Anant R. Kukreti- Project Coordinator
Dr. Richard Miller-Faculty Mentor
Ms. Marlo Thigpen-Grant Coordinator
Phil Grosvenor- IT Coordinator
Ms. Mary Ann Schaefer- Senior Business Administrator
Dawit Alemayehu - Graduate Assistant
Tyler Stillings- Graduate Assistant
Sanooj Edalath Graduate Assistant Helper
Elie Hantouche- Graduate Assistant Helper Dr. Eric Steinburg- Associate Professor of Civil Engineering David R. Breheim, Research
Associate
Dr. Sam Khoury Research Engineer
Ohio University Graduate Studentso Jon Huffman, Clint Setty, Kyle Grupenhoff, Brendan Kelly and Santiago Camino
ODOT (Ohio Department of Transportation)
Steven G. Luebbe. P.E., P.S., Fayette County Engineer
REU Seminar Presentors
Andrea Burrows
Dr. Ron Millard
Kim Simmons
Dr. Raj Manglik Amber Erickson
Ted Baldwin
Jim Casper
Dr. Makram Sidan
Dr. Dorothy Air
Geoffery Pinski
Dr. Tim Keener
-
7/28/2019 Final Paper Reu Summer2010
4/34
4
Table of ContentsAbstract.......................................................................................................................................................................... 2
Acknowledgements ....................................................................................................................................................... 31. INTRODUCTION ............................................................................................................................................... 6
2. GOAL AND PROJECT OBJETIVES ............................................................................................................... 7
3. RESEARCH TASKS ........................................................................................................................................... 8
3.1. Literature Review....................................................................................................................................... 8
3.1.1. Types of Loads on Bridges .................................................................................................................... 8
3.1.2. Truck Loading ....................................................................................................................................... 8
3.1.3. Precast Concrete .................................................................................................................................... 8
3.1.4. Adjacent Box Girder Bridges ............................................................................................................... 9
3.1.5. Deformation and Deterioration ............................................................................................................ 9
3.2. Rudimentary Analysis of Bridge............................................................................................................... 9
3.2.1. Bridge Information ................................................................................................................................ 9
3.2.2. Determination of Calculated and Derived Values............................................................................. 11
3.2.3. Assumed and Approximated Values .................................................................................................. 11
3.2.4. AASHTO Specifications ...................................................................................................................... 12
3.3. Simulation of loading ............................................................................................................................... 13
3.3.1. Purpose of Simulating ......................................................................................................................... 13
3.3.2. Simulation Setup .................................................................................................................................. 14
3.3.3. Simulation Results ............................................................................................................................... 15
4. MEASURING INSTRUMENTS ...................................................................................................................... 17
4.1. Strain Gauges ........................................................................................................................................... 17
4.2. String Potentiometer ................................................................................................................................ 17
5. BENCHMARK TEST ....................................................................................................................................... 18
5.1. Initial Preparation.................................................................................................................................... 18
5.2. Placement of Instruments ........................................................................................................................ 19
5.3. Collection of Data..................................................................................................................................... 20
5.4. Results ....................................................................................................................................................... 21
6. ANALYSIS OF RESULTS ............................................................................................................................... 22
6.1. Finding the AASHTO specified Moment Distribution Factor ............................................................. 12
6.2. Tuning the Data to Find Experimental Physical Characteristics. ....................................................... 22
6.3. Tests for Continuity ................................................................................................................................. 23
7. CONCLUSION AND APPLICATION ............................................................................................................ 26
8. RECOMMENDATIONS .................................................................................................................................. 26
9. FUTURE WORK............................................................................................................................................... 27
APPENDIX I: NOMENCLATURE AND GLOSSARY OF TERMS ................................................................... 32
-
7/28/2019 Final Paper Reu Summer2010
5/34
5
Glossary ...................................................................................................................................................................... 32
Nomenclature ............................................................................................................................................................. 32
APPENDIX II: RESEARCH TIMELINE ............................................................................................................... 32
APPENDIX II: RESEARCH TIMELINE ............................................................................................................... 33
APPENDIX III: SAMPLE CALCULATIONS ....................................................................................................... 34
Table of F igures
Figure 1: Arial View of the Bridge
Figure 2: Cross-Sectional View of the Adjacent Box Girders with the lateral tie
Figure 3: Cross-Section of a Box Girder
Figure 4: Fayette County Bridge (Test Bridge)
Figure 5: Sketch of Bridge Supports
Figure 6: Simulation of Bridge Behavior under load
Figure 7: Visual AnalysisModel
Figure 8: Moment, Shear, and Displacement reactions from simulation
Figure 9: Instrumentation Position
Figure 10: Truck Position 1
Figure 11: Truck Position 2
Figure 12: Bridge DeflectionTest 3 Load
Figure 13: Bridge DeflectionsTest 4 Load
Figure 14: Dynamic Test
Figure 15: Test 4 LoadTuned Continuous Model (top) vs. Tuned Discontinuous Model (Bottom)
Figure 16: Test 3 LoadTuned Continuous Model vs. Tuned Discontinuous Model (Bottom)
Tables
Table 1: Bridge Facts and Figures
Table 2: Property Values of the Girders
Table 3: Simulation Results
Table 4: Strain Gauge Properties
Table 5: Wire Potentiometer Sensitivities
Table 6: Truck Dimensions and Weights
Table 7: Moment of Inertia
Table 8: Concrete Strength
Table 9: Comparison of the Tuned Continuous and Discontinuous Models
-
7/28/2019 Final Paper Reu Summer2010
6/34
6
1. INTRODUCTIONWhen bridges are designed, engineers must follow a set of constraints set by the
American Association of State Highway and Transportation Officials (AASHTO). These
guidelines are set primarily for safety reasons. They involve strict criteria for the strength of
materials, dimensions, and construction methods. Along with these design specifications, the
AASHTO provides engineers with formulas and equations of how to estimate and predict the
behavior of the bridge under its own weight, and under external loading conditions.
Unfortunately, despite regular visual inspection by government officials, in 2007 the I-35
Minnesota Bridge did just that, resulting in several casualties. In the disaster, nine people lost
their lives and sixty were injured. Twenty people turned up missing after the collapse. Two years
earlier, an adjacent box girder bridge suddenly collapsed in Lakeview, Pennsylvania. In this case,
no vehicles or people were on the bridge during the collapse. In both cases, there were
substantial financial losses, and people were inconvenienced while the bridges were being
rebuilt. While it is safe and often correct to assume that deterioration of certain features of
bridges cause these collapses, certain aspects of bridge behavior as a result of these
deteriorations still remains a mystery.
In Ohio, a large percentage of bridges are built in the same fashion as the Lakeview
bridge. This presents a possible concern that necessitates thourough inspection procedure for
these types of bridges. As noted in the Minnesota I-35 bridge collapse, visual inspection is not
sophisticated enough to predict the behavior of bridges. In order to get a better understanding of
box girder bridge behavior, researchers often conduct destructive and non-destructive testing of
the bridges and observe the reactions of the members that comprise the bridge and its supports.
Through the use of special instruments, the researchers can measure and record these reactions.
-
7/28/2019 Final Paper Reu Summer2010
7/34
7
From these observations, the researchers continue to try to draw conclusions about bridge
behavior.
2. GOAL AND PROJECT OBJETIVESThe main goal of this project is to collect data in a benchmark test on the behavior of an
adjacent box girder bridge through the use of live (external) loads, measuring instruments and
recording software. The objectives for this project are as follows:
Learning Material Strength theory with Dr. Miller
Gather Research and Understanding of the Project
Assist in the Benchmark (baseline) tests
Create Models of the Bridge in Visual Analysis and run simulations
Compare Benchmark Test Results with Simulation Results
Tune the Model (find the true E & I of the bridge)
Compare the Continuous Tuned model to Discontinuous model
Tabulate and Analyze Results
-
7/28/2019 Final Paper Reu Summer2010
8/34
-
7/28/2019 Final Paper Reu Summer2010
9/34
9
original un-tensioned length, they apply a compressive force. This pre-compression increases
load-carrying capacity to the beam and helps control cracking to specified limits allowed by
building codes (Precast/Pre-stressed Concrete Institute).
3.1.4. Adjacent Box Girder BridgesPre-stressed box beams are cast in pre-stressing plants. The beams are placed side by side
and held together by lateral tension rods. Grout and shear keys are then used to connect the
beams together (see Fig. 2) .
3.1.5. Deformation and DeteriorationDue to corrosion caused by water and heavy salt treatment during the winter time
corrosion can occur to the beams as well as the internal steel. Because of this the steel strands
begin to deteriorate and the bridge loses tensile support. As the deterioration level of these
strands increases pre-stress force decreases. This decreases the maximum load capacity and
could lead to total collapse of a beam or the bridge.
3.2. Preliminary Analysis of Bridge3.2.1. Bridge Information
The bridge that was tested was an adjacent box girder bridge with pre-stressed concrete
girders. The structure is located in Washington Court House in Fayette County in central Ohio.
The official number of the bridge is 36-17-6.80. The dimensions and material properties of the
bridge are as follows:
-
7/28/2019 Final Paper Reu Summer2010
10/34
10
Table 2: Bridge Facts and Figures
Property Value
Type: Adjacent Box GirderLocation: Washington Court House,
Fayette County, Ohio
Time Built: Approximately late 1960sSpans/Length: 3 spans, 48 feet each, 144 ft totalNumber of
Beams/Width:9 adjacent beams, each 3 feet
wide, 27 feet total widthDepth: 21 inchesSkew: 15 degrees left forwardMaterials used: Prestressed Concrete
Figure 1: Plan view of Bridge
Figure 2: Cross-Sectional View of the Adjacent Box Girders with the lateral tie
-
7/28/2019 Final Paper Reu Summer2010
11/34
11
3.2.2. Determination of Calculated and Derived ValuesFor the purpose of the preliminary analysis, the basic geometry of the cross-section was
taken into account when finding the moment of inertia (I) for the members. The formula for
determining this value is as follows:
(1)Also, the cross-sectional area of the girders itself was determined by basic geometry, using the
area formula for a rectangle.
3.2.3. Assumed and Approximated ValuesSome of the information of the bridge was either not readily available or subject to
unknown changes since the bridge's construction, or had to be determined experimentally. Such
values included the strength of the concrete, the modulus of elasticity of the concrete, the pre-
stressing tension in the steel strands, the diameter of the pre-stressing strands, and the level of
continuity of the bridge. The assumed values are as follows:
Property Initial value
Distribution Factor .11 (unitless)
Concrete strength 7 ksi
Moment of Inertia 23500 in
Cross Sectional Area 488 in
Strand Diameter 3/8 inch
Continuity Full continuity
Table 2: Property Values of the Girders
Figure 4: Fayette County Bridge (Test Bridge)Figure 3: Cross-Section of a Box Girder
-
7/28/2019 Final Paper Reu Summer2010
12/34
12
3.2.4. AASHTO Specifications: Finding the AASHTO specified Moment DistributionFactor
According to the following AASTHO specifications, bridges of this type must be design
with the appropriate distribution factor parameter. Based on the number of girders and several
other physical aspects of the design, AASTHOs equations give a distribution factor for design
only. The actual distribution factor of the bridge will be different since this is a design constraint
(these are usually over estimated). A comparison of between these two values would shed light
on how damaged the bridge is and how it performs according to its initial design.
(2)
Eq. 2 is the formula given by AASTHO for the Distribution factor of a bridge made of girders
that are Precast solid, voided, or Cellular Concrete Box, with Shear Keys and with or without
Transverse Post-Tensioning. All the mentioned physical characteristics coincide with the Fayette
County Bridge.
The following are formulas that facilitate the D.F. calculation (a sample of this calculation can be
found in Appendix III).
(3)
where
(4)
-
7/28/2019 Final Paper Reu Summer2010
13/34
13
Eq. 5 is a D.F. reduction factor for skewed bridges (the Fayette County Bridge is this type).
(5)where
When calculated with the appropriate values, the Distribution factor for design of this
type of bridge is 0.2413. This means that the interior girders of this bridge are designed to
distribute roughly 24% of any load to each girder.
3.3.
Simulation of loading
3.3.1. Purpose of SimulatingBefore conducting the on-site Benchmark tests, several simulations were run in order to
have an approximate estimate of how the bridge should behave under the given loads. These
simulations are designed to give internal moments, shear forces, and displacements at any point
along the modeled bridge. Once a model is designed and analyzed and the Benchmark test is
completed, a comparison between predicted and observed values can be done. Also, in the
model, several assumptions must be made regarding the physical characteristics of the bridge
itself (most of these are largely unknown). If the differences between these two values are too
dissimilar, a separate tuning procedure can be done in order to find the true characteristics of
the bridge. Using several iterations of a certain physical aspect of the bridge, the correct one can
be found that results in a displacement similar (within an acceptable error) to the displacement
observed in the Benchmark Test.
Visual Analysis V. 4 and V.7were used in this analysis. This software allowed for the
creation of a two-dimensional model of the Fayette County Bridge. The following section
-
7/28/2019 Final Paper Reu Summer2010
14/34
14
contains details on how the bridge was translated into a two-dimensional model, and how the
truck loadings were modeled.
3.3.2. Simulation SetupIn this setup, several steps had to be taken in order to adequately model the bridge in
Fayette County in Visual Analysis. First, since the model must be reduced to only one beam (2D
Model), the width of the bridge is disregarded. Also a distribution factor must be applied to any
real load on the bridge. For the purposes of this simulation a distribution factor of 11% was
applied. The assumption was made that since the bridge contains nine girders, ideally the weight
should be distributed evenly throughout the bridge (connecting grout in the shear keys and lateral
tie, as specified in the bridge plans, should facilitate this distribution, see Fig. 2). The model
contained the correct length and was separated into three spans (48 feet each). The model bridge
also has at one end, a pinned joint, and two roller joints (one at 48 feet and the second at 96 feet
from the leftmost end) that separate it into 3 spans (see Fig.5). The model was also treated as
continuous. As mentioned before, several physical characteristics of the bridge required
estimation for the purposes of this simulation. All of these estimated values were subject to
tuning later in the project.
The Benchmark Test involved six different loadings (trucks were used for this), and each
load comprised of different configuration to the truck locations on the bridge. In the Visual
Analysis model, each tire of the truck was treated as a point load, so if there were 4 trucks on a
particular loading configuration, there would be 24 point loads on the modeled beam (each truck
has 3 axles). These point loads would be located on the model based on their distance from the
abutment (the distance from the side guard rail edges of the bridge were disregarded for the
purposes of creating a 2D model). Figure 6 shows an example of this model and its point loads.
-
7/28/2019 Final Paper Reu Summer2010
15/34
15
The six different loadings were simulated, and the following section displays the results from
this analysis.
3.3.3. Simulation ResultsAs stated before, Visual Analysis shows the internal forces and moments throughout the
modeled bridge as well as displacements at every point of the bridge. The max value (in
magnitude) is 0.399 inches at 22 feet (this occurred in Run 3). This simulation does not take into
account the dead load the bridge experiences from its own weight. In light of this and the other
assumptions necessary in order to simulate the behavior of the bridge, the observed
displacements will not be exact.
144 ft
Figure 5: Sketch of Bridge Supports
-
7/28/2019 Final Paper Reu Summer2010
16/34
16
Table 3: Simulation Results
7 KSI Strength Concrete Simulation
I = 25300
in^4
A = 488 in^ 2
Max Negative Max Positive
Run Deflection (in) Location (ft) Deflection (in) Location (ft)
1 0.125 22.08 0.04 67.2
2 0.389 22.08 0.142 67.2
3 0.399 22.08 0.144 67.2
4 0.171 22.08 0.03 115.2
5 0.389 22.08 0.14 67.26 0.171 22.08 0.031 115.2
Figure 6: Simulation of Bridge Behavior under load
Figure 7: Visual AnalysisModel
Figure 8: Moment, Shear, and Displacement reactio
from simulation
-
7/28/2019 Final Paper Reu Summer2010
17/34
17
4. MEASURING INSTRUMENTS4.1. Strain Gauges
Strain gauges were used to measure and record the strain while the concrete girders
underwent in response to the external load of the ODOT trucks. The gauges that were used were
resistance gauges and measured two inches in length. They were manufactured in Japan, and
were affixed to the bridge using an epoxy solution.
Table 4:Strain Gauge Properties
Property Value
Type: WFLM-60-11-2LT
Gauge Length: 60mm
Gauge Resistance: 120 0.5
Temp Compensation For: 1110-6/oC
Transverse Sensitivity: -5.%
Quantity: 10
Gauge Factor: 1.96 1%
Test Condition: 23C 50%RH
Batch No.: IE28K
Lead Wires : 7/O.127 3W 2m
4.2. String PotentiometerString potentiometers (also known as "wire pots") are generally used to measure linear
displacement. For this project, they were put to use in measuring and recording the deflections of
the individual girders during the tests.
-
7/28/2019 Final Paper Reu Summer2010
18/34
18
Table 5: Wire Potentiometer Sensitivities
Beam Wire Pot Model Seal (Series) Sensitivity
(mV/V/inch)
1S A1 (W) PA-15 3708148 64.70
2 A2 PA-20 32010211 46.65
3 A3 PA-15 37080147 64.64
4 A4 PA-15 37080149 64.69
5 A5 PA-15 37080150 64.63
6 A6 PA-10A 9007-5885 97
7 A7 PT-10A 9007-5883 96.6
8 A8 PT-10A 9007-5886 96.8
9N A9 PT-10A 9007-5884 96.6
1S B1(E) PT-108 9007-5887 97.8
2 B2 PT101-0010-111-1110 B0952696 91.39
3 B3 PT101-0015-111-1110 H1003996 61.227
4 B4 PT101-0010-111-1110 J0962400 92.61
5 B5 PT101-0010-111-1110 J0962401 91.96
6 B6 PT101-0015-111-1110 H1003994 62.647
7 Not Applied8 B8 PT101-0010-111-1110 K0866500 91.83
9N Not Applied
5. BENCHMARK TEST5.1. Initial Preparation
The initial preparation of the benchmark test consisted of the following: marking all of
the key locations on the bridge (locations of instruments, span endpoints, origin location datum
Figure 9: Instrumentation Position
-
7/28/2019 Final Paper Reu Summer2010
19/34
19
(the southwest corner of the bridge where the bridge begins on the west abutment and on the
white traffic line), etc.), removing the top layer of asphalt at the location of the strain gauges,
setting up the frame for the wire pots below the bridge, gluing all of the strain gauges in place,
testing all of the instruments, and opening the recording software. Much of the aforementioned
preparation was carried out on July 14, 2010. The rest was completed on July 15, 2010.
5.2. Placement of InstrumentsThe location of the instruments was predetermined during the preliminary analysis
(where the location of maximum moment and displacement was found, using Visual Analyis).
Strain gauges were placed on top of the bridge along the midspan (22 ft from the leftmost edge
of the bridge) of the bridge; one located on the center of each beam, with the exception of the
northernmost beam. An additional line of gauges was set out an additional 14 feet 6 inches east
of the first set of strain gauges, which is location of the anticipated inflection point (see Figure
9). On this line, all of the beams had strain gauges affixed to them. Underneath the bridge on the
same lines as on the top, strain gauges were glued to the underside of the bridge, with a gauge on
each beam. Finally, supported by a wooden frame beneath the bridge, wire pots were arranged
along the aforementioned lines, with a wire pot on each beam on the midspan (22 ft from the
leftmost edge of the bridge) line and one on each beam on the inflection line, with the exception
of the northernmost beam and the third northernmost beam.
-
7/28/2019 Final Paper Reu Summer2010
20/34
20
5.3. Collection of DataThe collection of data involved applying external or "live" loads in the form of trucks
provided by the Ohio Department of Transportation. TCS for the MegaDec data acquisition
system was used to record the reading of the array of instruments over time in regular intervals.
For this test, the rate of collection was 1200 scans per second. The test involved six static tests
(see Figures 11 and 12), where the four trucks were placed in different locations to investigate
the different reactions. Following the static tests came two dynamic tests, each involving one of
the trucks traveling across the bridge, from west to east, first at 10 miles per hour, and again at
35 miles per hour. Testing began after all of the preparation on July 15, 2010.
Table 6: Truck Dimensions and Weights
License Plate: OF 1050 OF 5591 OG 2791 OD 6634
Number: 41 47 8 31
L R L R L R L R
Front Axle Weight
(lbs)
7500 6900 7250 7250 7350 7700 5400 6650
Middle Axle Weight
(lbs)
9450 10700 9150 9600 9800 11150 9800 11500
Rear Axle Weight
(lbs)
8850 10750 8950 9850 10050 11200 10000 11300
Distance - front axleto middle axle: 13-0 130 13-0 12-6
Distance - font axle to
rear axle:
17-8 178 17-8 1610
Front axle width*: 6-10 6-10 6-10 6-7
Middle and Rear axle
width**:
6-0 6-0 6-0 6-1
*(middle of tire to middle of tire)
** (space between tire pair to space between tire pair)
-
7/28/2019 Final Paper Reu Summer2010
21/34
21
5.4. ResultsThe following are figures displaying the displacements found in Test 3 and Test 4
(involving Truck positions 3 and 4). However, only the wire potentiometers in Row A (located at
22 ft) functioned properly.
Figure 12: Bridge DeflectionTest 3 Load
Beam 9
Beam 8 Beam 7 Beam 6 Beam 5 Beam 4 Beam 3 Beam 2Beam 1
-0.4
-0.35
-0.3
-0.25
-0.2
-0.15
-0.1
-0.05
0
Deflection(in)
Beam
Bridge Deflection - Test 3 Load
Row A
Figure 10: Truck Position 1 Figure 11:Truck Position 2
-
7/28/2019 Final Paper Reu Summer2010
22/34
22
Figure 13: Bridge DeflectionsTest 4 Load
6. ANALYSIS OF RESULTS6.1. Tuning the Data to Find Experimental Physical Characteristics.
The results from the Benchmark test showed that the displacements are slightly different
from the predicted values found using VisualAnalysis. This could be due to some of the
assumptions made for the physical characteristics being slightly inaccurate. For this reason
through the iteration of the moment of inertia, and the concrete strength and matching the
displacements produced in their simulations to those found in the Benchmark Test. Below are the
Tables that contain these displacements.
Beam 1
Beam 2 Beam 3 Beam 4 Beam 5 Beam 6 Beam 7 Beam 8Beam 9
-0.25
-0.2
-0.15
-0.1
-0.05
0
Deflections(in)
Beam
Bridge Deflections - Test 4 Load
Row A
-
7/28/2019 Final Paper Reu Summer2010
23/34
23
Table 7: Moment of Inertia
Iterations for I
Test 3 Test 4
I (in^4) Displacements
(in)
24800 -0.285 -0.17
24900 -0.284 -0.169
25000 -0.283 -0.169
25100 -0.282 -0.168
25150 -0.281 -0.168
25200 -0.281 -0.167
25300 -0.28 -0.167
Table 8: Concrete Strength
Test 3 Test 4
Strength
(PSI)
Displacement (in)
6800 -0.284 -0.169
6900 -0.282 -0.168
7000 -0.28 -0.167
7100 -0.278 -0.167
7200 -0.276 -0.165
7300 -0.274 -0.163
7400 -0.272 -0.162
7500 -0.27 -0.161
6.2. Tests for ContinuityBelow, Fig.15shows of the dynamic test done in the Benchmark Test. The graph displays
how strain in the first span changes as the truck moves along the bridge. One can infer that the
bridge is continuous due to the positive strain seen. Since the gauge is at the top of the beam of
the first span, when the truck is on the third span, the strain should read as negative (if it is
continuous) and positive when on the second span.
-
7/28/2019 Final Paper Reu Summer2010
24/34
24
In Figures 16 and 17,a comparison is done between a continuous tuned model of the
bridge versus a discontinuous tuned model. The discontinuous model has a displacement that is
much larger than the one observed in the Benchmark Test. Also the observed displacement is
within 5% of what the tuned model displays.
Figure 14: Dynamic Test
-1.40E+02
-1.20E+02
-1.00E+02
-8.00E+01
-6.00E+01
-4.00E+01
-2.00E+01
0.00E+00
2.00E+01
4.00E+01
1
549
1097
1645
2193
2741
3289
3837
4385
4933
5481
6029
6577
7125
7673
8221
8769
9317
9865
10413
10961
11509
12057
12605
13153
13701
microStrain
ms
-
7/28/2019 Final Paper Reu Summer2010
25/34
25
Figure 16: Test 3 LoadTuned Continuous Model vs. Tuned Discontinuous Model (Bottom)
Figure 15: Test 4 LoadTuned Continuous Model (top) vs. Tuned Discontinuous Model (Bottom)
-
7/28/2019 Final Paper Reu Summer2010
26/34
26
Table 9: Comparison of the Tuned Continuous and Discontinuous Models
Test 3 Test 4
Model Displacements (in)
Continuous -0.28 -0.168Observed -0.282 -0.167
Discontinuous -0.405 -0.356
% Difference 0.711744 0.597015
7. CONCLUSION AND APPLICATIONFrom the analysis of the wire-potentiometer data and the dynamic data (Fig. 14) from the
strain gauges most of the basic physical characteristics of the Fayette County Bridge. The
Moment of inertia can be approximated to be roughly 25300 in^4 and the Concrete Strength,
~7000PSI. However, the only way to confirm these two values is to first, take a look at the cross
section (when Dr. Miller and OU conduct the destructive test) to confirm the design from plans,
and second, take core sample and test for strength.
The bridge also seems to be at least partially continuous. The dynamic tests suggest this
and the continuous tuned models show the same displacement as the observed displacement from
the Benchmark Test.
8. RECOMMENDATIONSFirst, it is highly recommended that the cross sectional area and the concrete strength be
tested and recorded.
More testing is needed in order to confirm continuity by 1) observe behavior during the
destructive test 2) synchronize a timer along with the data acquisition to pinpoint exactly when
and where the truck is when positive displacement occurs on the first span (when the truck
-
7/28/2019 Final Paper Reu Summer2010
27/34
27
passes the third span) and 3) place truck on the third span and check for any kind of reaction in
the first span where the instruments are installed.
Instruments on the third and possibly second (middle span) should be considered.
Although on the middle span this would be difficult since it crosses the water and no kind of
support would be available for wire-potentiometers and strain gauge attaching, placing strain
gauges on the tops of the beams (after grinding off the asphalt) of the middle span would help in
observing behavior throughout the whole bridge and not just one span.
The strain gauge data did not allow for the examination of the distribution of the load
throughout the girders simply because of the nature of the test. In all tests a combination of four
trucks was used, making difficult to relate one truck to a specific displacement in a beam. To
explore this phenomenon, it is recommended that only truck be used. The location should be
varied so that the effect on displacement/strain in one beam can be observed.
9. FUTURE WORKThe bridge will be subject to further tests. The date and time of these tests is to be
determined. The aforementioned instruments will be used to collect data of the responses to live
loads, as in the benchmark test, but after the girders have sustained intentional damage. After
these series of tests, special equipment will be used to apply increasing loads until the bridge
fails. This will tell the researchers the ultimate load capacity of the bridge after damage. After all
of the tests, including the ones covered in this report, researchers shall have a better idea of the
distribution of forces among the adjacent members, establish a connection between apparent
damage and the effect on the ultimate load capacity, and use the findings to improve bridge
design and inspection methods.
-
7/28/2019 Final Paper Reu Summer2010
28/34
28
Bibliography
AASHTO. (2008).The Manual for Bridge Evaluation. Washington, DC: American Association
of State Highway and Transportation Officials, 1st
Edition.
AASHTO. (2007).LRFD Bridge Design Specifications. Washington, D.C.: American
Association of State Highway and Transportation Officials, 4th
Edition
AASHTO. (2002).Standard Specifications for Highway Bridges.Washington, D.C.: AmericanAssociation of State Highway and Transportation Officials, 17
thEdition
ACI Committee 345. (2006). Guide for Maintenance of Concrete Bridge Members. ACI 345.1R-06.
Bentz, E. 2000. Response-2000 Reinforced Concrete Sectional Analysis using the Modified
Compression Field Theory. Version 1.0.5.
ACI Committee 222 (2001),Protection of Metals in Concrete Against Corrosion, ACI
Publication No. 222R-01, American Concrete Institute, Farmington Hills, Michigan
ACI Committee. (2005), Building Code Requirements for Structural Concrete and Commentary,American Concrete Institute. ACI 318-05, American Concrete Institute, Farmington Hills,
Michigan.
American Association of State Highway Officials. (1965).Standard Specifications for Highway
Bridges, Washington DC, 6th
Edition.
American Association of State Highway and Transportation Officials.(2010).Section 4:
Structural Analysis and Evaluation.AASHTO LRFD Bridge Design Specifications, pp.29-39.
ASTM International.(2004).C39/C39 Compressive Strength of Cylindrical Concrete
Specimens, West Conshohocken, PA
ASTM International.(2004). C856,Petrographic Examination of Hardened Concrete, West
Conshohocken, PA
ASTM International.(2004). Microscopical Determination of Parameters of Air-Void System inHardened Concrete, West Conshohocken, PA
ASTM International.(2004). Acid-Soluble Chloride in Mortar and Concrete, WestConshohocken, PA
ASTM International.(2004). A370-97a Standard Test Methods and Definitions for Mechanical
Testing of Steel Products, West Conshohocken, PA
ASTM International.(2004). Aa16/A416M-99 Standard Specification for Steel Strand. ASTM
No. A416, Uncoated Seven-Wire for Prestressed Concrete, West Conshohocken, PA
-
7/28/2019 Final Paper Reu Summer2010
29/34
29
Billington, D. P. (2004). Historical Perspective on Prestressed Concrete.PCI Journal49,
No.1,pp.14-30.
Glass, G.K. and Buenfeld, N.R.(1997), The Presentation of the Chloride Threshold Level for
Corrosion of Steer in Concrete, Corrosion Science, Vol. 39, No. 5, pp 1001-1013.
Gulistani, Aziz A. March.(2010). Forensic Investigation of Prestressed Concrete Box Beams
from LIC-310 Bridge. A thesis presented to the faculty of the Russ College of Engineering and
Technology of Ohio University in partial fulfillment of the requirements for the degree Master ofScience.
Harries, K. A. (2009). Structural Testing of Prestressed Concrete Girders from the Lake View
Drive Bridge.Journal of Bridge Engineering14, No. 2, pp.78-92.
Harries, K. A., R. Gostautas, C. J. Earls, and C. Stull.(2006).Full-Scale Testing Program on De-
commissioned Girders from the Lake View Drive Bridge. The Pennsylvania Department ofTransportation, Dept. of Civil and Environmental Engineering, Univ. of Pittsburgh, Pittsburgh,
Rep. No. CE/ST 33.
Hartle, R.(2006), Field Inspection and Forensic Investigation of the SR 1014 Lake View DriveBridge over Interstate 70 Final Report, Michael Baker, Jr. Report, pp. 52.
Kassimali, Aslam.(2005). Structural Analysis. Cengage Learning, 4th
Edition, pp. 17-24, 330-374.
Kosmarka, S., H., Panarese, W., C.(1990), Design and Control of Concrete Mixtures,
!3th
Edition, Portland Cement Association, Skokie, III,pp.205.
Labia, Y., M. S. Saiidi, and B. Douglas. (1997). Full-Scale Testing and Analysis of 20-Year-Old
Pretensioned Concrete Box Girders.ACI Structural Journal94, No.5, pp. 471-82.
Macioce, T., Rogers H., Anderson, R., and Puzey, D., C.(2007), Prestressed Concrete Box
Beam Bridges- Two DOTS Experience, 2007 PCI-FHWA National Bridge ConferenceSession, pp. 83.
MDOT. September (2005). Box-Beam Concerns Found under the Bridge. Construction and
Technology Research Record, No.102, pp. 1-4.
Menn, C., and P. Gauvreau. (1990).Prestressed Concrete Bridges. Basel Switzerland; Boston:
Birkhuser Verlag.
Miller, R., and K. Parekh. (1994). Destructive Load Testing of a Damaged and Deteriorated
Prestressed Concrete Box Beam. MS Thesis.,University of Cincinnati.
-
7/28/2019 Final Paper Reu Summer2010
30/34
30
Miller, R., and K. Parekh. (1994). Destructive Testing of Deteriorated Prestressed Box Bridge
Beam. Transportation Research Record(1460), pp. 37-44.
Naito, C., R. Sause, I. Hodgson, S. Pessiki, and C. Desai. (2006).Forensic Evaluation ofPrestressed Box Beams from the Lake View Drive Bridge over I-70. Lehigh Univ., Lehigh, Pa.,
ATLSS Report No. 06-13.
Naito, C., R. Sause, and B. Thompson. (2008). Investigation of Damaged 12-Year Old
Prestressed Concrete Box Beams.Journal of Bridge Engineering13, No. 2, pp.139-48.
Nasser, G. D. (2008). The Legacy of the Walnut Lane Memorial Bridge. STRUCTURE Magazine
2008, (10), pp.27-31.
ODOT. (2007). Bridge Design Manual.Ohio Department of Transportation. January 2009Edition
PennDOT Bridge Quality Assurance Division,(2006), Superstructure, BMS Item E18,Condition Rating Guidelines for Prestressed Concrete for Prestressed Concrete Adjacent Box
Beams, Strike-offLetter 431-06-02.
PennDOT Bridge Quality Assurance Division.(2007), PennDOT Bureau of Design BridgeManagement System 2 Coding Manual, Publication 100A.
Pennsylvania Department of transportation.(2002), Bridge Safety Inspection Manual, PennDOTPublication 238, 2
thEdition
PCI.(2004).PCI Design Handbook. Background, PCI MNL- 120-04, 6th
Edition.
PCI.(2004).PCI Design Handbook. Features and General Principles, PCI MNL- 120-04, 6th
Edition.
PCI.(1989).Architectural Precast Concrete. Manual Contents and Concepts, PCI MNL-122-89,
2nd
Edition.
PCI.(2004).PCI Design Handbook. Common Products, PCI MNL-120-04,6th
Edition.
PCI.(2004). An Industry On The Rise, Visions Taking Shape: Celebrating 50 Years of the
Precast/Prestressed Concrete Industry; Chero Publishing Co.
PCI.(2006).Architectural Precast Concrete. Applications of Architectural Precast Concrete, PCI
MNL-122-06, 3rd
Edition.
PCI.(2006).Architectural Precast Concrete. Advantages of Architectural Precast Concrete,
Architectural Precast Concrete, 3rd
Edition.
-
7/28/2019 Final Paper Reu Summer2010
31/34
31
Precast/Prestressed Concrete Institute. (2004). PCI Design Handbook, Precast and Prestressed
Concrete, Chicago: Precast/Prestressed Concrete Institute, 6th
Edition.
Shenoy, C. V., and G. C. Frantz. (1991). Structural Tests of 27-Year-Old Prestressed Concrete
Bridge Beams.PCI Journal36, No.5, pp. 80-90.
Whiting, D., and B. G. Stejskal. (2004). Field Studies of Corrosion in Prestressed ConcreteBridges.Philip D. Cady International Symposium on Concrete Bridges in Aggressive
Environments, pp. 73-93.
-
7/28/2019 Final Paper Reu Summer2010
32/34
32
APPENDIX I: NOMENCLATURE AND GLOSSARY OF TERMS
Glossary
Moment of Inertia - A property, based on its geometry (most generally based on the
object's centroid or cross sectional area) of an object's (or member) resistance to bending.Usually expressed in units of length, i.e. in^4
Concrete Strength This is the compressive strength of concrete, determined
experimentally, and given in units of PSI. This value can be calculated from the Modulus ofElasticity
Modulus of Elasticity - A measure of an object's tendency to be deformed elastically
under an applied force.
Distribution Factor - A design parameter given by AASTHO (can be approximated by
dividing the number of lanes by the number of beams) that specifies the amount of load eachbeam experiences when the bridge is loaded.
Continuity or Discontinuity - If the bridge is separated into several spans, the beams in
each span could be connected to each other making the entire structure continuous. If theyare not, then the structure would be considered discontinuous. These two characteristics
change the response of the bridge from a load.
Tuning - Through several iterations of a simulation, the characteristics of the bridge are
changed until the response matches up with the response seen at the Fayette County Bridge.
This approximates or "tunes" the characteristic in question.
Cross-Sectional Area - This is the area of the inside cross section of a beam.
SkewThe amount of angle given to a bridge with respect to whatever it is over passing.For example if a bridge were placed perpendicular to a river, then there is no skew. However,
if the bridge is placed 15 off the perpendicular then is it considered a 15 degree skew.
Nomenclature
E = Youngs modulus of elasticity
I = Moment of InertiaJ = Polar Moment of Inertia
b = width of the beam (in)
d = depth of beam (in)
L = span of the beam (ft)Nb = number of beams or girders
= skew angle (degrees)
A*
= Area of the body (from parallel axis theorem)z = Distance from the centroid of the body to the axis (from parallel axis theorem)
-
7/28/2019 Final Paper Reu Summer2010
33/34
33
APPENDIX II: RESEARCH TIMELINE
Informational Session 06/21-22/2010
Information was provided an introduction to the research. This information told of previous tests
that were done from other research projects and why.
Literature and Lectures 06/24-28/2010
Lectures were given by Dr. Richard Miller and Mr. Dawit on the basics of the physics and
mechanics of bridge structures. Some homework and reading material was provided.
Procurement of Materials and Resources 06/30/2010 to 0713/2010
Materials needed for the experiment were gathered while researching was being done. These
materials consisted of available trucks, wire pots, gauges, etc.
Research Application to Bridge 07/02-07/2010
The information learned from the literature and lectures was then applied to the project bridge in
preparation for visual analysis simulations. This consisted of how the internal forces act in the
bridge such as moment and shear. Also, known characteristics and properties of the bridge were
obtained and documented.
Simulations 07/07-09/2010
Using known information and some assumptions simulations were done for maximizing
deflections on the bridge using Visual Analysis. This was done by finding the precise position to
place the trucks. Simulations were done for continuous and discontinuous cases to model
possible deflections and to obtain deflection results for comparison.
Benchmark Test 07/14-15/2010
This part of the project consisted of benchmark test set-up followed by the benchmark test. This
was a two day event at the bridge located in Washington Court House. Data was collected to be
analyzed at a future time (*see Benchmark Test).
Post-Benchmark Test Analysis 07/16-26/2010
Data was obtained and analyzed. After results for the actually benchmark test were found theses
results where then compared to the simulations to determine the continuity of the bridge. Other
useful Information which could possibly help with future tests were then documented by UC and
OU students and faculty. All possible errors experimental, electronic and environmental were
documented so that they could be fixed or prevented in future tests.
-
7/28/2019 Final Paper Reu Summer2010
34/34
Conclusion 08/02-06/2010
All Information for this project was then put together in a note book, report, poster and power
point for documentation and presentation needed in the future.
APPENDIX III: SAMPLE CALCULATIONS
AASTHOs Distribution Factor
b=36 in d=21 in
L=48 ft =9 beams
( )
( )