final presentation
TRANSCRIPT
![Page 1: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/1.jpg)
END OF TERM PRESENTATION
Van Masterson-Summer & Fall 2014
![Page 2: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/2.jpg)
OVERVIEW• About Me
• Projects• TABBI 1 Roller Top Card
• TABBI Rewinder Thread Rope
• BK2 Quench Air Actuator Box
• BK4 Full Potential Spinning
• Other Projects
• Next Assignment
• Acknowledgements
• Questions
![Page 3: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/3.jpg)
ABOUT ME Hometown: Evansville, Indiana
School: Junior at Purdue University
Major: Electrical Engineering Technology
1st and 2nd terms at Berkeley Mentor: James Deloach
![Page 4: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/4.jpg)
TABBI 1 Roller Top CardPurpose
• to improve the basis weight uniformity of the light weight surge materials produced on TABBI
Tasks• Update TABBI 1 cable schedule
• Create new drawings and update existing drawings in DRCS and AutoCAD
• Verify accuracy of AutoCAD drawings
Actuator Panel
![Page 5: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/5.jpg)
TABBI Rewinder Thread Rope Purpose
• improve operator safety and ergonomics on the TABBI spoolers while performing the task of threading up.
Tasks
• Wrote ladder logic in RSLogix 5000 to control five motors using Powerflex 525 drives
• Created several RSView 32 screens that allow the operators to manually enable and disable the system
• Created a cable schedule for installation
• Created new drawings for the 525 drives and edited existing I/O drawings in AutoCAD
• Currently waiting on down time so that IMOCO can install pulleys and air control equipment.
![Page 6: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/6.jpg)
BK2 Quench Air Box Actuators Purpose
• ensure BK2 quench box movement does not require operator intervention to position and ensure geometry is repeatable by installing a robust quench air box actuator.
Tasks• Created new drawings in DRCS and
edited existing drawings in AutoCAD.
BWE Panel, Slot 14
BK2,POWER INTERFACE, CONTROL I/O, ETHERNET
![Page 7: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/7.jpg)
BK4 FULL POTENTIAL SPINNING
Purpose• support the Adult Care Cost Transformation
Initiative by providing Outercover at a competitive price while improving quality performance versus the current internally supplied material
Tasks• Edited tag names in RSLogix 5000 ladder logic for
the moving and fixed fans on BK4.
• Attended a vendor checkout in Lawrenceville, GA, to verify the functionality of the die heating and pipe heating panels for banks 1 & 2 of BK4 as well as the die cleaning panel
• Edited existing drawings and created new drawings in DRCS
![Page 8: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/8.jpg)
Other Projects• Mill Lighting – created an excel spreadsheet of lighting throughout
the mill
• TABBI Reclaim – Created a motor list for the fans and rolls for the TABBI reclaim card machine
• TABBI 2 Process Mapping – Documented the doffing process of TABBI 2 to determine if there were any inefficient steps in the process. This information might be used for a future project to improve the efficiency of the doffing process for TABBI 1 & 2
![Page 9: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/9.jpg)
41609 41640 41671 41699 41730 41760 41791 41821 41852 41883 41913 419440.00
50,000.00
100,000.00
150,000.00
200,000.00
250,000.00
300,000.00
350,000.00
400,000.00
450,000.00
500,000.00
Berkeley Energy Costs 2014
Renewable Energy RiderExtra FacilitiesEconomy DemandOn-Peak Billing Demand
Months
Total Cost
Note: total cost of energy from Dec. 2013 to Nov. 2014 was $4,235,626.11
Off-Peak Energy
![Page 10: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/10.jpg)
On-Peak Billing Demand
$1,213,755.7429%
On-Peak Energy$971,918.06
23%
Off-Peak Energy$2,016,967.36
47%
Extra Facilities$31,012.08
1%
Cost Breakdown Note: Not all categories are shown because they were so small they showed up as 0% on the chart.
Note: total cost of energy from Dec. 2013 to Nov. 2014 was $4,235,626.11
![Page 11: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/11.jpg)
Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14$200,000.00
$250,000.00
$300,000.00
$350,000.00
$400,000.00
$450,000.00
$500,000.00
$302,491.75
$305,302.34
$321,742.67
$315,442.15$303,709.72
$321,512.95
$433,815.01
$435,117.66
$448,052.54
$434,501.35
$317,067.23
$325,901.62
Berkeley Energy Cost Per Month
![Page 12: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/12.jpg)
Next Assignment: Loudon, TN
![Page 13: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/13.jpg)
• James Deloach
• Jason Hadley
• Lynn Hill & Criss Ward
• Kim Webb
• Susan Steenstra
• Dean Bonessi
• Josh Henri
• Tim Beeching
• Ernest Humphries
• Alma Lambert
• Edith Bayne
• Pete Covill
• Darryl Clark
• Tim Ducker
• Vikki May
• Ron Storm
• Wayne Jones
• Tracy Aldridge
![Page 14: Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022081605/58796a6c1a28ab37368b4adb/html5/thumbnails/14.jpg)
QUESTIONS?THREE-WAY LIGHT SWITCH
Single Pole, Double Throw
NOTE: Use only if Josh Henri asks how a three-way switch works.