final version economic design of vsi x-bar control charts for correlated non-normal case (1)

32
1 Economic Design of Variable Sampling Interval X-Bar Control Charts for Monitoring Correlated Non-Normal Samples Seyed Taghi Akhavan Niaki, Ph.D. 1 Professor of Industrial Engineering, Sharif University of Technology P.O. Box 11155-9414 Azadi Ave., Tehran 1458889694 Iran Phone: (+9821) 66165740, Fax: (+9821) 66022702, E-Mail: [email protected] Fazlollah Masoumi Gazaneh, M.Sc. Department of Industrial Engineering, Islamic Azad University (South-Tehran Branch), Tehran, Iran, E-Mail: [email protected] Moslem Toosheghanian, M.Sc. Department of Industrial Engineering, Iran University of Science and Technology [email protected] Abstract Recent studies have shown the X-bar control chart with variable sampling interval detects shifts in the process mean faster than the traditional X-bar chart. These studies are usually based on the assumption that the process data are independently and normally distributed. However, many situations in practice violate these assumptions. In this study, a methodology is developed to economically design a variable sampling interval X-bar control chart that takes into consideration correlated non-normal sample data. An example is provided to illustrate the solution procedure. A sensitivity analysis on the input parameters (i.e., the cost and the process parameters) is performed taking into account the non-normality and the correlation on the optimal design of the chart. Keywords: X-bar control chart; Economic design; Variable sampling interval; Non-normality; Correlated process data; Genetic algorithms 1 Corresponding author

Upload: mohamed-farag-mostafa

Post on 08-Nov-2015

216 views

Category:

Documents


2 download

DESCRIPTION

economic X bar chart

TRANSCRIPT

  • 1

    Economic Design of Variable Sampling Interval X-Bar Control Charts for Monitoring Correlated Non-Normal Samples

    Seyed Taghi Akhavan Niaki, Ph.D.1 Professor of Industrial Engineering, Sharif University of Technology

    P.O. Box 11155-9414 Azadi Ave., Tehran 1458889694 Iran Phone: (+9821) 66165740, Fax: (+9821) 66022702, E-Mail: [email protected]

    Fazlollah Masoumi Gazaneh, M.Sc.

    Department of Industrial Engineering, Islamic Azad University (South-Tehran Branch), Tehran, Iran, E-Mail: [email protected]

    Moslem Toosheghanian, M.Sc.

    Department of Industrial Engineering, Iran University of Science and Technology [email protected]

    Abstract

    Recent studies have shown the X-barcontrol chart with variable sampling interval detects shifts in the process mean faster than the traditional X-barchart.These studies are usually based on the assumption that the process data are independently and normally distributed. However, many situations in practice violate these assumptions. In this study, a methodology is developed to

    economically design a variable sampling interval X-barcontrol chart that takes into consideration correlated non-normal sample data. An example is provided to illustrate the solution procedure.A sensitivity analysis on the input parameters (i.e., the cost and the process parameters) is

    performed taking into account the non-normality and the correlation on the optimal design of the

    chart.

    Keywords: X-bar control chart; Economic design; Variable sampling interval; Non-normality;

    Correlated process data; Genetic algorithms

    1 Corresponding author

  • 2

    1. Introduction and literature survey

    Control charts are the most important tools in statistical quality control environments for

    continuous improvement of the quality of the items being produced and the X chart is the first

    that was originally introduced by Shewhart in 1924 (Shewhart 1931). The design of the Shewhart

    X control charts requires the determination of three designparameters: the sample size ( n ), the

    sampling interval ( h ), and the control limits width ( k ). Shewhart considered these parameters

    fixed, however recent studies have shown that varying the sampling interval (VSI), the sample

    size (VSS), the sampling interval jointly with the sample size (VSSI), or all design parameters at

    the same time, including k , (VP) reduce the detection time of process changes (see for example,

    Reynolds et al., 1988; Baxley, 1996; Prabhu et al., 1993,1994; Costa, 1994, 1997, 1999). Further,

    a survey of studies on VSR charts is presented in Tagaras (1998).

    Duncan (1956) proposed the first economic model to determine the optimal values of n ,

    h , and k of an X chart. Since then, the economical design of control charts has received

    increasing attention in the literature (e.g., Montgomery, 1980; Vance, 1983; Woodall, 1986;

    Pignatiello and Tsai, 1988; Niaki et al. 2010). The usual approach in an economical design is to

    develop a cost model for a special type of industrial process, and then derive the optimal

    parameters by minimizing the expected cost per unit of time.While Duncans (1956) and Chius

    (1975) models for the economic design of control charts have been widely studied in practice, in

    the former the process remains in operation during the period of search for the assignable cause

    and in the latter the process is ceased.

    In the design process of the Shewhart X control chart, one assumes the measurements

    (observations) within the subgroups are independently and normally distributed. However, these

    assumptions may not hold in many practices. For example, when a production process consists of

  • 3

    multiple but similar units on a single part, such as several cavities on a single casting, multiple

    pins on an integrated circuit chip, or multiple contact pads on a single machine mount, the

    collected measurements within a subgroup are usually correlated (Grant and Leavenworth 1988).

    Neuhardt (1987) considered the effect of correlation within a subgroup on the performances of

    control charts. Yang and Hancock (1990) employed Neuhardts idea to conduct simulation

    studies to specify the effect of correlated data on the performances of X , R, S and S2 charts. Liu

    et al. (2002) used the correlation model of Yang and Hancock (1990) to develop a minimum-loss

    design of fixed sample size and sampling interval (FSI) charts for correlated data. Chen and

    Chiou (2005) combined Yang and Hancocks correlation model (1990) with the cost model of

    Bai and Lee (1998) to make the economic design of the VSI charts for correlated data. Recently,

    Chen et al. (2007) incorporated the Yang Hancocks correlation model (1990) with the cost

    model of Costa (2001) to develop an economic design of the VSSI charts for correlated data.

    If the size of subgroups (sample size) is large enough, the statistic X is approximately

    normal based on the central limit theorem. However, when a control chart is applied to monitor

    the process, unfortunately the sample size is usually not sufficiently large due to the sampling

    cost. As a result, due to non-normality, the traditional method of designing the control chart may

    decrease the ability of detecting assignable causes. Yourstone and Zimmer (1992) considered the

    Burr distribution to represent the non-normal distributions and statistically designed the X chart.

    Chen (2004) presented the economic design of VSI X control charts for non-normal data. Lin

    and Chou (2005) employed the Burr distribution to design both symmetric and asymmetric-limit

    VSSI X chart under non-normality. Recently, Lin and Chou (2007) studied the effect of non-

    normality on the performances of adaptive X control charts (i.e., variable sample size, sampling

    intervals, and and/or action limit coefficients) and concluded the VP X control chart is more

  • 4

    effective than the other adaptive charts in detecting small process mean shifts under non-normal

    process data.

    In this research, the economic model of the VSI X chart for correlated non-normal

    process data is developed using Burr distribution and the correlation model presented in Yang

    and Hancock (1990). The FSI and VSI schemes are compared in terms of the long-run expected

    cost per hour and statistical performances for various levels of correlation.

    The remainder of the paper are as follows. In the next section, the concept of the VSI

    control charts is briefly discussed. The Burr distribution representing the various types of non-

    normal distributions is introduced in section 3. The economic model based on the Burr

    distribution that works under correlated process data is developed in section 4. A solution

    method to find the optimal values of the design parameters of an asymmetric VSI X chart is

    presented in section 5. Sensitivity analysis on the process parameters and correlation coefficients

    are conducted in section 6. Finally, conclusions make up the last section.

    2. The VSI X control chart

    Consider a process involving a single quality characteristic following a normal

    distribution with in-control mean 0 and in-control known variance 2 . To monitor the process

    mean using an X control chart, traditionally at a given sample point a sample of n independent

    observations ( ; 1, 2,..., )ix i n are taken and the sample mean 1

    1n

    ii

    x n x

    is calculated accordingly. If the plotted x falls within the interval 0 k n , ( 0 is the centerline and k is the control limit width) the process is considered in-control and the next sample is taken in a

    fixed interval of 1h time. Otherwise, a signal is sent to inform the operator to search for an

  • 5

    assignable cause. This control chart is said to operate in a fixed sample-size ( )n and fixed

    sampling interval 1( )h (FSI) condition.

    When the VSI scheme is in use, the waiting time h until the next sampling point is a

    function of the current x value. In other words, if ; 1, 2ix I i , then ih h where

    ' '1 0 1 0 2 0 2 0 1

    '2 0 2 0 2

    , ,

    ,

    I k k k kn n n n

    I k kn n

    (1)

    with 2 10 k k , ' '2 10 k k , and 2 1 0h h . According to Chen (2004), the slight cost savings

    offered by the VSI schemes with more than two sampling interval sizes does not justify their use.

    As an example, Fig. 1 depicts a VSI X chart using two interval lengths of 1h and 2h .

    0

  • 6

    The sample means in Fig.1 are plotted against the time on the horizontal axis. The first

    sample mean falls within 2I , so the next sampling interval is 2h . The second one falls within 1I ,

    which is close to the control limits. Hence, a shorter sampling interval is adopted to take the third

    sample and so on.

    The way the VSI X control charts work can improve the detection ability of FSI charts

    by shortening the length of time until a signal is occurred. Nonetheless, the complexity will

    increase when the number of divided areas becomes large. Further, traditional symmetric VSI

    charts can be easily obtained by setting '1 1k k .

    3. The Burr distribution

    In this study, the Burr distribution is used to model non-normal process data. Burr (1942)

    proposed a simple probability distribution function that was capable to model various types of

    non-normal data. The cumulative distribution function of the two-parameter Burr distribution is

    11 y 0

    1

    0 y

  • 7

    Burr (1942) tabulated the first two moments (given in a Table numbered 2) and the

    coefficients of skewness and kurtosis (given in another Table numbered 3) for the family of the

    Burr distribution. These tables allow users to make a standardized transformation between the

    variable of the Burr distribution (Y ) and any other random variable ( X ) when they have the

    same coefficients of skewness and kurtosis. The standardized transformation between Y and

    X is defined as follows:

    x

    X X Y MS S (3)

    Where S and M are the sample mean and standard deviation of the Burr distribution,

    respectively and X and xS are the sample mean and standard deviation of the data set (as a

    random variable).

    Different combinations of the parameters 1c and 1k can cover an extensive range of skewness and kurtosis coefficients of various probability density functions (e.g., Normal,

    Gamma, Beta, etc.). For instance, when c = 4.8621 and k = 6.3412, the Burr distribution

    approximates the normal distribution (Yourstone and Zimmer 1992). Further, the first four

    moments of the empirical distribution can be used to determine c and k . Burr (1967) used this

    distribution to study the impact of non-normality on constant coefficients of the X and R control

    charts. Tsai (1990) employed the Burr distribution to design the probabilistic tolerance for a

    subsystem. Yourstone and Zimmer (1992) used the Burr distribution to design the control limits

    of X control charts for non-normal data. Chou et al. (2000) employed the Burr distribution for

    the economic design of X charts under the presence of non-normal process data.

  • 8

    4. The economic model of the VSI X control chart

    The economic design of the VSI X control chart is developed employing a cost function

    and searching for the optimal design parameters that minimizes the cost function during a

    production cycle. The derivation of the cost function comes in the next subsection.

    4.1. The cost function

    In the derivation of the cost function, the process is initially assumed in-control 0 . The process will then be disturbed by a single assignable cause that makes a shift of in the mean (i.e., the out-of-control process mean becomes 0 ),where is the magnitude of the shift. After the shift, the process remains out-of-control until the assignable cause is removed.

    The inter-arrival time of the assignable cause is assumed to follow an exponential distribution

    with a mean of 1 . For monitoring purposes, a sample of size n is taken at each sampling point. If the

    calculated sample mean falls inside the two control limits, its position inside the control region

    will be used to specify the next sampling point; making sampling interval variable. If the sample

    mean goes beyond the two control limits, the process is ceased and a search starts to find a

    possible assignable cause and if necessary to adjust the process.

    As in Chen (2004), the length of a production cycle is the time between the instant the

    process starts in control to the time the process is stopped for adjustments. Fig. 2 shows a

    production cycle ( )T that is divided into four intervals including the in-control period 1( )T , the

    out-of-control period 2( )T , the searching period due to a false alarm 3( )T , and the period for

    identifying and correcting the assignable cause 4( )T .

  • 9

    Fig 2. Production cycle considered in the cost model

    The individual periods are now illustrated before they are grouped together.

    1( )T : Based on the assumptions the expected length of the in-control period is 1 .

    2( )T : Let A be the length of the sampling interval in which an assignable cause occurs,

    and Y be the time interval between sample points just prior to the occurrence of the assignable

    cause and the occurrence itself (see Fig. 2). Then, Reynolds et al. (1988) showed that

    2 1 11

    1m

    j jJ

    E T E A E Y S h P

    (4) Where 1S represents the expected number of samples required to detect the assignable cause and

    1 jP represents the conditional probability that X falls within jI , given that X falls inside the

    two control limits when 0 . Moreover, the number of samples in detecting the

    assignable cause can be modeled by a geometric distribution with parameter 1q , (i.e., 1 11S q ),

    Last Sample before process mean shift

    Cycle ends

    Process mean

    Shift

    First Sampleafterprocessmeanshift

    Assignable

    Cause

    Assignable

    Cause Out-of-control

    Detected

    (T1) in control period +

    (T3) Searching period due to false alarm

    (T2) out- of-control period

    (T4) Time period for identifying and correcting assignable cause

    Y

    A

    Cycle

    Start

  • 10

    where 1q is the probability of detecting an assignable cause in a sample. Reynolds et al. (1988)

    also assumed that the probability of the length of A being jh is

    0 01

    Pr( )m

    j j j j jj

    A h h P h P

    (5) Where 0 jP is the conditional probability that X falls within jI , given that X falls inside the

    control limits when 0 . Then from the result of Duncan (1956), the conditional expected value of Y given jA h is

    1 1

    1

    j

    j

    hj

    j h

    h eE Y A h

    e

    (6)

    Therefore, the expected length of the out-of control period is reached using (4)(6) as:

    0

    2 1 11 101

    11 11

    j

    j

    hm mj j j

    j jm hj jj jj

    P h h eE T S h P

    h P e

    (7)

    3( )T : Let 0S be the expected number of samples in the in-control state. Then, Bai and

    Lee (1998) showed that

    01

    0 021

    01

    11

    j

    j

    j

    m hmj hj

    jm h jjj

    P eS P e

    P e

    (8)

    The expected searching period due to false alarm becomes

    1 0 0t q S (9)

    where 0q is the false alarm rate and that an average of 1t hours is spent if the signal is a false

    alarm.

  • 11

    4( )T : The time to identify and correct the assignable cause following an action signal is

    assumed a constant 2t .

    Thus, the expected length of a production cycle can be aggregately represented by

    1 2 3 4

    01 1 1 0 0 2

    1 101

    ( ) ( )

    11 1 11

    j

    j

    hm mj j j

    j jm hj jj jj

    E T E T T T T

    P h h eS h P t q S t

    h P e

    (10)

    The expected cost of a production cycle includes (a) the cost of false alarms; (b) the cost

    of detecting and eliminating the assignable cause; (c) the cost associated with production in the

    out-of-control condition; and (d) the cost of sampling and testing. Defining 1c the average search

    cost of a false signal, 2c the average cost to discover the assignable cause and adjust the process

    to in-control state, 3c the hourly cost associated with production in an out-of-control state, 4c the

    fixed sampling cost for each sample, and 5c the variable cost of sampling and testing in each

    sample, the expected cost of a production cycle, ( )E C , becomes:

    1 0 0 2 3 2 4 5 0 1( )E C c q S c c E T c c n S S (11) The aim of the economic design of a VSI X control chart with generalized control limits

    is to determine the appropriate values of design parameters ' '1 2 1 2 1 2, , , , , ,n k k k k h h such that the expected cost per hour, ECT , given in (12) is minimized

    1 0 0 2 3 2 4 5 0 1

    2 1 0 0 2

    ( )1( )

    c q S c c E T c c n S SE CECTE T E T t q S t

    (12)

    Note that ECT is a function of both the process and the cost parameters.

    Since the objective of this research is to develop an economical design of the VSI X

    control chart under correlated non-normal process data, in the next section, correlated data is first

  • 12

    considered. Then we take advantage of the Burr distribution to model non-normal data in section

    4.3. These modeling can help determine the values of 0 jP and 1 jP used in (12).

    4.2. The case of correlated process data

    Yang and Hancock (1990) assumed each subgroup a realization of the random vector

    1 2[ , ,..., ]T

    nX X XX following a multivariate normal distribution ( )N ,V , where

    1[ ( ),..., ( )]T

    nE X E X is the mean vector and { ( , ); 1,..., , 1,... }ij i jv Cov X X i n j n V is

    the covariance matrix. Assuming e , where e is a vector of all 1s, i.e., ( )iE X , and 2V R , where { ; 1,..., , 1,..., }ijr i n j n R is the correlation matrix, the sample mean X

    can be shown to be normally distributed with mean and variance as follows:

    E( ) X (13)

    2V( ) 1 1X nn (14)

    Where

    #

    1

    iji j

    r

    n n

    (15)

    The mean and variance of X are still valid even if the measurements are not normally

    distributed.

    Now, let 0O and 1O be the conditional probabilities that any sample mean X falls outside

    the control limits, given that the process is in control ( 0 ) and out of control ( 0 ), respectively. The conditional probabilities 0O and 1O are also called the false alarm rate and the

  • 13

    failure-detection power of a control chart, respectively. Then by denoting the upper and the

    lower control limits of the X chart by UCL and LCL , respectively, we have

    0 1

    '0 1

    UCL k n

    LCL k n

    (16)

    As a result 0O can be obtained as

    0 0

    0 0

    1 Pr

    Pr Pr

    O LCL X UCL

    X UCL X LCL

    Then by replacing UCL and LCL given in (16), we have

    1

    0 10 0

    '0

    0

    Pr 1 1 1 1

    Pr 1 1 1 1

    X kOn n n

    kXn n n

    (17)

    Similarly 1O becomes

    1

    1 0

    '0 1

    =1 Pr

    1 Pr1 1 1 1

    O LCL X UCL

    k n X k nnn n

    (18)

    4.3. The case on non-normal process data

    The skewness and kurtosis coefficients of the sample mean X (based on a sample of size

    n ) according to Dodge and Rousson (1999) are, respectively,

    3 43 4 3 , = +3X X nn (19)

  • 14

    In which 3 and 4 denote the skewness and kurtosis coefficients of the random variable

    X (modeling the population). Using the values of 3 4( ) and ( )X X and the tables of the Burr distribution (1942), one can obtain the values of , , , and M S c k for the distribution with

    skewness and kurtosis values close to the 3 4( ) and ( )X X through the interpolation. Now, using the Burr transformation given in (2) and (3), expressions for 0O , 1O , 0 jP ,

    0mP , 1 jP , and 1mP are derived in the equations A.1 to A.6 of the appendix, respectively.

    5. An example and a solution procedure

    An examination of the probability components in (12) reveals that finding the optimal

    values of the parameters * * * '* ' * * *1 2 1 2 1 2, , , , , ,n k k k k h h of the VSI X chart using a conventional optimization method is not simple. As a result, to describe the nature of the solutions obtained

    for the economic design of the VSI X control chart under correlated non-normal process data, a

    numerical example is provided and a parameter-tuned genetic algorithm (GA) is developed to

    search for a near optimal solution. The numerical example is borrowed from Chou et al. (2002)

    and is modified to demonstrate the methodology. In this example, the input based on the

    historical data is:

    0.01 , 1 10c , 2 30c , 3 100c , 4 0.5c , 5 0.1c , 1 , 1 0.1t , and 2 0.3t . Previous data also indicate the skewness and kurtosis coefficients of the tang dimension are

    approximately 3 1.4322 and 4 7.3558 , respectively, which may be approximated by the Burr distribution with 2c and 4k .

    The recent 60 successive parts are viewed as a random sample from a multivariate non-

    normal distribution. The sample average is 0.66, 0.59, 0.69, 0.54 TT and the corresponding sample covariance matrix is

  • 15

    1.05 05 8.40 06 7.80 06 6.90 068.40 06 1.07 05 9.90 06 7.70 067.80 06 9.90 06 1.07 05 9.00 066.90 06 7.70 06 9.00 06 1.10 05

    E E E EE E E EE E E EE E E E

    V

    that results in an average correlation coefficient of 0.77 . Now, suppose a set of data is collected and the sample mean and sample standard

    deviation are computed 0.5x and 0.001xS , respectively. For a given sample size, in order to calculate the probabilities ijP and ultimately ECT we first find the skewness and kurtosis

    coefficients of the process data (3 and 4 ). Then, we obtain 3 X and 4 X using Equation (19). Next, using the Burr (1942) Tables II and III the values of M , S , c , and k that correspond

    to 3 X and 4 X are obtained using interpolation. Finally, equations (A.1)-(A.6) are used to determine the probabilities 0 jP , 0mP , 1 jP , and 1mP that are required to evaluate ECT in (12). The

    solution procedure is carried out using a parameter-tuned GA to obtain the near optimal values of

    * * * '* ' * * *1 2 1 2 1 2, , , , , ,n k k k k h h that minimize ECT . The proposed GA was coded in MATLAB (version 7.8) environment, in which except

    the integer sample size n , decimal coding is applied. The initial population contains 40 feasible

    chromosomes that are randomly generated. The fitness value of each solution in the initial

    population is evaluated by ECT in (12) and the chromosome with the lowest cost replaces the

    one with the highest cost. The best 20% of the chromosomes are the survivors for the next

    generation. For the crossover operation, among the second 20% of the chromosomes, the parents

    are selected using the Rolette-Wheel method, in which the crossover point is randomly selected

    and the crossover operation on the parents are performed with the probability of 0.5. In this step,

    if a gene does not satisfy its corresponding constraints, its value is transformed to an acceptable

  • 16

    value within the range uniformly. Moreover, the mutation is performed with a probability of 0.3.

    These steps are continued until the stopping condition, 1500 generations, is achieved.

    By employing the proposed GA on the economic designs of both the FSI and VSI X-bar

    charts, the near optimal solutions along with the minimum costs are obtained as given in Table

    (1). As shown in this table, the cost function ETC of Equation (12) gives a minimum of $4.748

    if the sample size, the sampling interval, and the control limit coefficient are fixed (FSI).

    However, a minimum cost of $3.335 is obtained when the sample size and the control limit

    coefficient are fixed and the sampling intervals change (VSI), resulting in 29.76% cost savings.

    Table (1): The optimal designs of the FSI and VSI X-Bar control chart

    X-Bar n 1h 2h 1k 2k '1k '2k ETC % decrease

    FSI 2 0.520 2.457 2.796 4.748

    VSI 2 0.010 1.361 2.456 0.0004 2.622 2.622 3.335 29.76

    In the operations of the GA,the quality of the solution obtained depends on the setting of

    its control parameters: the population size (PS), the crossover probability (CP), the mutation rate

    (MR), and the generation number (GN) (Chen 2006). In order to find the optimal setting of these

    parameters, an orthogonal array experiment is performed on three different levels of the

    parameters. Based on three replicates and the smaller-the-better criterion on the signal-to-noise

    ratio, the optimal combination level of the control parameters is obtained as PS=40, CP=0.5,

    MR=0.3, GN=1500.

  • 17

    6. Sensitivity analyses

    In this section, a sensitivity analysis is conducted to understand how typical the given

    numerical example is and to explore the effect of the model parameters on the solution of the

    proposed economic design of the VSI X control chart under correlated non-normal process data.

    Since the chart is designed without knowing the shift direction, the optimization should

    consider the overall better performance taking into account process mean increases and process

    mean decreases. As a result, different cost parameter settings are considered for each of which

    the near optimal solution of the economic model of both the FSI and VSI X-Bar control chart

    along with its expected cost per hour is obtained for positive and negative mean shifts in Tables

    (2) and (3), respectively. In these tables, is the false alarm risk. Further, similar to the tables given in Chen (2004), we set 1 2 0

    ' 'k k ; for (and 1 2 0k k ; for ) and added them to the constraints in the optimization model. By this way, the chart is designed without lower

    (upper) limits in case of increase (decrease) in the process mean. Moreover, a constraint in the

    optimization model was added to avoid false alarm risks of bigger that 0.05, and another

    constraint was added to avoid 1h smaller than 0.01.

    While previous research works (Bai and Lee 1998, Chen 2004, Chen and Chiou 2005,

    and Chen et al. 2007) only considered positive mean shifts, a careful examination of the results

    in Table (3) reveals that the optimal sample size of "one" has been obtained in all cases in which

    negative mean shifts are considered. Based on Equations (A.2)-(A.6), this means the correlation

    should not have any effect on the probabilities obtained to reach the near optimal solution.

    Moreover, Table (4) summarizes the performances of the economic design of X control charts

    for process data with different levels of correlation coefficients and Table (5) shows the

    percentage reductions in cost obtained using the VSI X-Bar chart.

  • 18

    The results given in Tables (2) and (5) reveal the following findings:

    1. For positive mean shifts, the expected cost per hour of the VSI control schemes are

    consistently smaller than that of the FSI control scheme over the 15 parameter

    combination sets.

    2. Compared with the FSI schemes, in most cases the corresponding VSI scheme tends to

    operate with a larger upper control limit ( 1k ) and the same (or sometimes smaller)

    sample size.

    3. The percent reduction in ECT is reduced when small or intermediate mean shifts ( = 0.5 or 1) are encountered.

    4. The percentage reduction in ECT is significantly increased due to higher searching cost

    (involving 1c and 2c ), lower sampling cost (involving 4c and 5c ), when the production

    cost in the out-of-control state is large and when is small. Other parameters such as 1t and 2t do not significantly affect the ECT.

    5. In most cases, false alarm rate () of the X control chart for the VSI scheme is smaller than the FSI scheme.

    Further, the results in Tables (3) and (5) indicate the following

    1- For negative mean shifts, the expected cost per hour of the VSI control schemes are

    consistently smaller than that of the FSI control scheme over the 15 parameter

    combination sets.

    2- The percent reduction in ECT is significantly increased when the mean shifts are = -0.5 or -1.

  • 19

    3- The percentage reduction in ECT is increased due to lower searching cost (involving 1c

    and 2c ), lower sampling cost (involving 4c and 5c ), and when is small. Other

    parameters such as 1t and 2t do not significantly affect the ECT

    From Table (4), several findings can be spelled out as follows:

    1. As the measurements in the sample are positively or negatively correlated, both VSI and

    FSI charts for highly correlated data require less frequent sampling with small sample

    size and narrow width of the control limits.

    2. Monitoring the process data by the VSI chart results in an evident improvement in

    ECT when a high positive correlation is considered. On the contrary, when the

    measurements in the sample are negatively correlated, the obvious improvement only

    sounds to be the case for intermediatehighly correlated data .8.05.0 3. The sample sizes taken in VSI schemes are slightly smaller than the corresponding one in

    the FSI scheme.

    4. As compared with the FSI charts, the VSI chart takes the next sample more slowly for

    positively correlated data and more quickly for the most of negatively correlated data.

    5. In this study, the percentages of the cost reduction with 2c , 4k , and different values of (Table 4) are consistently more significant than the corresponding percentages of the cost reduction (Table 3) obtained by Chen and Chiou (2005), where

    the process data is distributed normality.

    It should be noted that when 0 the expected cost per hour obtained for the FSI and VSI charts are 2.398 and 2.163, respectively. These figures are similar to the ones in Chen (2004), in

    which he obtained them as 2.440 and 2.145, respectively. The difference is due to different

  • 20

    computer codes written to solve the problem. In fact, while Chen (2004) employed the

    EVOLVER coding to solve the problem, we solved the problem in MATLAB environment.

    7. Conclusions and recommendation for future research

    In this paper, we first took advantages of the Bai and Lees (1998 ) cost model, the Yang

    and Hancocks (1990 ) correlation model, along with the Burr distribution modeling of non-

    normal data to develop the economic design of the VSI X-Bar control chart for monitoring the

    mean of correlated non-normal process data. An illustrative example to demonstrate the

    application of the proposed methodology was then provided and comparisons were made

    between the FSI and VSI schemes in terms of the expected cost per hour. To do this a parameter-

    tuned genetic algorithm was developed to search for the near optimal solution of the economic

    designs. Sensitivity analyses were next carried to determine the influences of the input

    parameters on the solutions of the economic design. Based on the results in the sensitivity

    analyses, we have the following findings:

    1. Over the 15 different combination sets of the model parameters indicated for positive

    mean shifts given in Chen and Chiou (2005) the average percentage reduction in the

    expected cost per hour ( ECT ) of the VSI scheme under correlated non-normal process

    data is about 26.76%, which is more than that for correlated normal process data.

    2. For positive mean shifts, the improvements in the VSI scheme in terms of ECT become

    evident when the average wasted costs associated with false alarms and the detection and

    elimination of the assignable cause after a true alarm are large. Moreover, when the

    sampling cost is low, the improvement is also important for both positive and negative

    mean shifts.

  • 21

    3. When the sample measurements are correlated, the improvement in ECT is apparent for

    process data with a high degree of positive correlation or with an intermediatehigh

    degree of negative correlation.

    4. As compared with the FSI charts, the VSI chart takes the next sample more slowly for

    positively correlated data and more quickly for the most of negatively correlated data.

    5. For monitoring the correlated data, the FSI and VSI chart use a smaller sample than that

    for monitoring uncorrelated data.

    6. In most cases, false alarm rate () of the X control chart for the VSI scheme is smaller than the FSI scheme.

    While a single assignable cause was assumed throughout this research, it would be

    interesting to conduct a research on the optimal design of VSI X control charts to monitor

    correlated non-normal process data under the consideration of multiple assignable causes in the

    future.

    8. Acknowledgement

    The authors are thankful for constructive comments of the reviewers that helped better

    presentation of this paper.

  • 22

    Table 2. The optimum design of FSI and VSI X charts for positive mean shifts under the Burr distributions ( 2 and 4c k ) FSI VSI

    No t1 t2 c1 c2 c3 c4 c5 n h1 k1 k'1 ECT n h1 h2 k1 k2 k'1 k'2 ECT 1 0.01 2 0.1 0.3 10 30 100 0.5 0.1 2 0.9438 2.4560 2.8659 0.0500 2.6952 1 0.0103 1.3600 2.9815 0.3796 1.8453 1.8453 0.0120 1.8038

    2 0.05 2 0.1 0.3 10 30 100 0.5 0.1 2 0.4644 2.4624 2.8732 0.0496 6.6443 1 0.0101 0.6327 2.6656 0.3989 2.9600 2.9600 0.0179 4.9277

    3 0.01 2 0.1 0.3 10 30 10 0.5 0.1 2 3.2542 2.4561 2.6753 0.0500 1.0331 1 0.0101 4.7090 2.8331 0.3844 2.0326 2.0326 0.0145 0.7752

    4 0.01 2 0.1 0.3 10 30 1000 0.5 0.1 2 0.3115 2.4560 2.6526 0.0500 7.8436 1 0.0100 0.4641 2.6538 0.3879 2.2658 2.2658 0.0182 5.2736

    5 0.01 2 0.1 0.3 25 75 100 0.5 0.1 2 1.2166 2.4596 2.6683 0.0498 3.7817 1 0.0103 1.5817 3.0000 0.3704 2.8698 2.8698 0.0117 2.4090

    6 0.01 2 0.5 1.5 10 30 100 0.5 0.1 2 0.9626 2.4569 2.8347 0.0499 2.6102 1 0.0101 1.4578 2.9281 0.3749 2.7379 2.7379 0.0128 1.7727

    7 0.01 2 0.1 2.1 10 210 100 0.5 0.1 2 1.0957 2.4559 2.7048 0.0500 4.3896 1 0.0100 1.4379 2.9699 0.3717 2.6024 2.6024 0.0122 3.5173

    8 0.01 2 0.1 0.3 1 3 100 0.5 0.1 2 0.7160 2.4584 2.8515 0.0499 1.9395 1 0.0118 1.2941 1.8632 0.4692 1.7030 1.7030 0.0499 1.3475

    9 0.01 2 0.1 0.3 10 30 100 5 0.1 2 2.1940 2.4562 2.8601 0.0500 5.5069 1 0.0101 3.7610 1.8617 0.4794 2.0574 2.0574 0.0500 4.1687

    10 0.01 2 0.1 0.3 10 30 100 0.5 1 1 1.1107 1.8614 2.7378 0.0500 3.7594 1 0.0110 2.1792 2.5370 0.4040 2.0408 2.0408 0.0211 2.5344

    11 0.01 1 0.1 0.3 10 30 100 0.5 0.1 2 0.5202 2.4572 2.7956 0.0499 4.7479 2 0.0102 1.3613 2.4563 0.0004 2.6219 2.6219 0.0500 3.3351

    12 0.01 1 0.1 0.3 10 30 20 0.5 0.1 2 1.2372 2.4560 2.7481 0.0500 2.2451 2 0.0102 3.1640 2.4570 0.0018 2.9970 2.9970 0.0499 1.6415

    13 0.05 1 0.1 0.3 10 30 100 0.5 0.1 2 0.2405 2.4561 2.8830 0.0500 10.9347 2 0.0100 0.7009 2.4565 0.0009 2.9828 2.9828 0.0500 8.1413

    14 0.01 0.5 0.1 0.3 10 30 100 0.5 0.1 1 0.3430 1.8616 2.1894 0.0500 6.6988 2 0.0106 0.7823 2.4581 0.0001 2.8878 2.8878 0.0499 5.6334

    15 0.01 0.5 0.1 0.3 10 30 5 0.5 0.1 2 2.0035 2.4560 2.6434 0.0500 1.5727 2 0.0105 3.9988 2.4559 0.0009 2.9479 2.9479 0.0500 1.3989

    0.77

  • 23

    Table 3. The optimum design of FSI and VSI X charts for negative mean shifts under the Burr distributions ( 2 and 4c k ) FSI VSI

    No t1 t2 c1 c2 c3 c4 c5 n h1 k1 k'1 ECT n h1 h2 k1 k2 k'1 k'2 ECT 1 0.01 2 0.1 0.3 10 30 100 0.5 0.1 1 0.9000 2.9988 1.5996 0.0137 1.9121 1 0.0100 1.0260 2.9997 2.9997 1.6585 1.1122 0.0118 1.8202

    2 0.05 2 0.1 0.3 10 30 100 0.5 0.1 1 0.3933 2.9998 1.5963 0.0139 4.9941 1 0.0100 0.4954 2.9957 2.9957 1.6559 1.0701 0.0119 4.8011

    3 0.01 2 0.1 0.3 10 30 10 0.5 0.1 1 2.9803 2.9995 1.6009 0.0137 0.7974 1 0.0104 3.3745 2.9995 2.9995 1.6585 1.1139 0.0118 0.7701

    4 0.01 2 0.1 0.3 10 30 1000 0.5 0.1 1 0.2558 2.9994 1.6137 0.0131 5.4336 1 0.0100 0.3256 2.9975 2.9975 1.6606 1.0979 0.0118 5.1187

    5 0.01 2 0.1 0.3 25 75 100 0.5 0.1 1 1.0320 2.9997 1.6352 0.0123 2.5528 1 0.0107 1.1484 2.9989 2.9989 1.6688 1.1110 0.0118 2.4391

    6 0.01 2 0.5 1.5 10 30 100 0.5 0.1 1 0.9013 3.0000 1.5963 0.0139 1.8783 1 0.0137 1.0344 2.9971 2.9971 1.6546 1.1041 0.0119 1.7904

    7 0.01 2 0.1 2.1 10 210 100 0.5 0.1 1 0.9144 2.9995 1.5990 0.0138 3.6248 1 0.0116 1.0439 2.9994 2.9994 1.6579 1.1055 0.0119 3.5358

    8 0.01 2 0.1 0.3 1 3 100 0.5 0.1 1 0.9599 2.9996 1.3325 0.0499 1.4305 1 0.5122 1.0320 2.9983 2.9983 1.3328 0.8591 0.0499 1.4126

    9 0.01 2 0.1 0.3 10 30 100 5 0.1 1 2.7436 2.9999 1.3322 0.0500 4.3864 1 1.5009 2.9897 2.9937 2.9937 1.3326 0.9011 0.0500 4.3394

    10 0.01 2 0.1 0.3 10 30 100 0.5 1 1 1.4055 2.9986 1.5178 0.0201 2.6823 1 0.0114 1.5800 2.9999 2.9999 1.6303 1.1062 0.0125 2.5792

    11 0.01 1 0.1 0.3 10 30 100 0.5 0.1 1 0.6331 2.9996 1.4686 0.0260 2.9988 1 0.0105 0.9782 2.9993 2.9993 1.5558 0.5244 0.0166 2.7255

    12 0.01 1 0.1 0.3 10 30 20 0.5 0.1 1 1.4326 2.9996 1.4688 0.0259 1.4881 1 0.0105 2.0278 2.9986 2.9986 1.5594 0.6150 0.0163 1.3705

    13 0.05 1 0.1 0.3 10 30 100 0.5 0.1 1 0.3142 2.9999 1.4364 0.0306 7.3119 1 0.0101 0.3615 2.9997 2.9997 1.5470 0.6871 0.0173 6.7761

    14 0.01 0.5 0.1 0.3 10 30 100 0.5 0.1 1 0.5109 2.9984 1.3325 0.0499 4.4881 1 0.0109 0.9183 2.9988 2.9988 1.3555 0.3117 0.0451 4.2459

    15 0.01 0.5 0.1 0.3 10 30 5 0.5 0.1 1 2.5710 2.9983 1.3331 0.0498 1.1636 1 0.0113 4.0903 2.9918 2.9918 1.3354 0.4842 0.0494 1.1204

    0.77

  • 24

    Table 4. Effect of correlation coefficients on the optimal design of the FSI and VSI X charts under the Burr distributions ( 2 and 4c k ) FSI VSI

    n h1 k1 k'1 ECT n h1 h2 k1 k2 k'1 k'2 ECT % 0.9 2 0.42696 2.54506 2.96068 0.04997 4.93567 1 0.01000 1.14443 1.86145 0.00106 1.68205 1.68205 0.04997 3.36725 31.77724

    0.8 2 0.53618 2.47706 2.81296 0.04997 4.77219 1 0.01068 1.18143 1.86118 0.00113 1.98587 1.98587 0.04999 3.36713 29.44267

    0.7 2 0.54953 2.41360 2.68994 0.04963 4.69388 2 0.01023 1.12432 2.48025 0.00245 2.93573 2.93573 0.04609 3.34272 28.78554

    0.6 3 0.62383 2.71990 2.99961 0.04997 4.53213 2 0.01057 1.49458 2.34295 0.00492 2.92305 2.92305 0.04955 3.18791 29.65975

    0.5 3 0.62306 2.58229 2.99907 0.04999 4.36052 3 0.01026 1.65146 2.58918 0.00052 2.99608 2.99608 0.04963 3.07956 29.37639

    0.4 4 0.69670 2.72072 2.99993 0.04982 4.19957 3 0.01101 1.65987 2.56365 0.00098 2.92944 2.92944 0.04388 2.94890 29.78085

    0.3 4 0.70525 2.48929 2.99993 0.04998 3.91435 3 0.01047 1.60831 2.58609 0.00396 2.79143 2.79143 0.03563 2.80881 28.24321

    0.2 5 0.91768 2.39362 2.99997 0.04985 3.54721 4 0.01022 1.77758 2.84457 0.00388 2.99874 2.99874 0.02411 2.62885 25.88951

    0.1 9 1.45073 2.38232 2.99533 0.04986 3.01286 5 0.01013 1.70928 2.78880 0.31280 2.84947 2.84947 0.01873 2.42983 19.35140

    0 11 1.86872 1.91101 2.80768 0.03639 2.39795 7 0.01222 1.72507 2.66818 0.85559 2.99931 2.99931 0.00947 2.16310 9.79352

    -0.1 8 1.65198 1.67679 1.92691 0.00423 1.93348 7 0.01001 1.57608 2.24190 1.27358 1.90720 1.90720 0.00173 1.88589 2.46151

    -0.2 5 1.43798 1.37049 1.08825 0.00521 1.74940 5 0.01005 1.41908 1.82256 1.23673 2.66754 2.32316 0.00079 1.71984 1.68937

    -0.3 4 1.36257 1.31588 2.31656 0.00080 1.63784 4 0.01116 1.35429 1.51731 1.29000 1.72271 1.72271 0.00025 1.63485 0.18278

    -0.4 3 1.36355 1.08033 1.38650 0.01966 1.75917 3 0.01073 1.29067 1.64592 0.85457 2.52335 2.52335 0.00235 1.61942 7.94401

    -0.5 2 0.92253 1.30626 2.57480 0.04990 2.85462 2 0.01018 1.57398 1.99290 0.18527 2.55298 2.55298 0.01172 1.98012 30.63450

    -0.6 2 1.03912 1.16751 2.51285 0.04999 2.56525 2 0.01061 1.43037 1.87324 0.30548 1.53344 1.53344 0.00941 1.86062 27.46810

    -0.7 2 1.21410 1.01146 2.99077 0.04995 2.24150 2 0.01016 1.37357 1.72249 0.43533 2.10534 2.10534 0.00711 1.73396 22.64305

    -0.8 2 1.36156 0.88854 2.17417 0.04076 1.91192 2 0.01023 1.28667 1.53854 0.59497 2.44292 2.44292 0.00453 1.61081 15.74925

    -0.9 2 1.25857 0.90606 1.36369 0.01091 1.58033 2 0.01007 1.19620 1.29985 0.81036 1.48247 1.48247 0.00164 1.50857 4.54048

    Fixed cost parameters: =0.01, =1, t1=0.1, t2= 0.3, c1= 10, c2=30, c3=100, c4=0.5, c5=0.1

  • 25

    Table (5): Cost Reductions when instead of FSI, the VSI X-Bar chart is employed

    Percentages of Cost Reduction

    No. Positive Mean Shifts Negative Mean Shifts

    1 33.074 4.806

    2 25.836 3.863

    3 24.962 3.419

    4 32.766 5.797

    5 36.298 4.456

    6 32.086 4.682

    7 19.872 2.454

    8 30.522 1.251

    9 24.300 1.073

    10 32.585 3.844

    11 29.758 9.112

    12 26.883 7.906

    13 25.546 7.329

    14 15.905 5.396

    15 11.050 3.714

  • 26

    References

    Bai, D.S., Lee, K.T. (1998). An economic design of variable sampling interval X control

    chart. International Journal of Production Economics 54: 57-64.

    Baxley Jr., R.V. (1996). An application of variable sampling interval control charts. Journal

    of Quality Technology 27: 275282.

    Burr, I.W. (1942). Cumulative frequency distribution. Annals of Mathematical Statistics 13:

    215-232.

    Burr, I.W. (1967). The effect of non-normality on constants for X and R charts. Industrial

    Quality Control 22: 563569.

    Chen, Y.K. (2004). Economic design of X control chart for Non-normal data using variable

    sampling policy. International Journal of Production Economics 92: 61-74.

    Chen, Y.K., Chiou, K.C. (2005). Optimal design of VSI X control charts for monitoring

    correlated sample. Quality and Reliability Engineering International 21: 757768.

    Chen, Y.K., Chiou, K.C., Hsieh, K.L., Chang, C.C. (2007). Economic design of the VSSI X

    control charts for correlated data. International Journal of Production Economics 107:

    528539.

    Chiu, W.K. (1975). Economic design of attribute control charts. Technometrics 17: 8187.

    Chiu, W.K., Cheung, K.C. (1977). An economic study of X charts with warning limits.

    Journal of Quality Technology 9: 166171.

    Chou, C.Y., Chang, C.L., Chen, C.H. (2002). Minimum-loss design of X-Bar control

    charts for Non-normally correlated data. Journal of the Chinese Institute of

    Industrial Engineers 19: 16-24.

    Chou, C.Y., Chen, C.H., Liu, H.R. (2000). Economic-statistical design of X charts for non-

    normal data by considering quality loss. Journal of Applied Statistics 27: 939951.

  • 27

    Costa, A.F.B. (1994). X-BAR chart with run rule and variable sample size. Journal of Quality

    Technology 26: 155-163.

    Costa, A.F.B. (1997). X-BAR chart with variable sample size and sampling interval. Journal

    of Quality Technology 29: 197-204.

    Costa, A.F.B. (1999). X charts with variable parameters. Journal of Quality Technology 31:

    408416.

    Costa, A.F.B. (2001). Economic design of X charts with variable parameter: the Markov

    chain approach. Journal of Applied Statistics 28: 875885.

    Dodge, Y., Rousson, V. (1999). The complications of the fourth central moment. The

    American Statistician 53: 267269

    Duncan, A.J. (1956). The economic design of X charts used to maintain current control of a

    process. Journal of American Statistical Association 51: 228-242.

    Grant, E.L., Leavenworth, R.H. (1988). Statistical Quality Control. McGraw-Hill Book

    Company, Singapore.

    Lin, Y.C., Chou, C.Y. (2005). On the design of variable sample size and sampling intervals

    X charts under non-normality. International Journal of Production Economics 96: 249

    261.

    Lin, Y.C., Chou, C.Y. (2007). Non-normality and the variable parameters X control charts.

    European Journal of Operational Research 176: 361-373.

    Liu, H.R., Chou, C.Y., Chen, C.H. (2002). Minimum-loss design of X charts for correlated

    data. Journal of Loss Prevention in the Process Industries 15: 405411.

    Montgomery, D.C. (1980). The economic design of control charts: A review and literature

    survey. Journal of Quality Technology 1: 24-32.

  • 28

    Niaki, S.T.A., Ershadi, M.J., Malaki, M. (2010). Economic and economic-statistical designs

    of MEWMA control charts, A hybrid Taguchi loss, Markov chain and genetic algorithm

    approach. International Journal of Advanced Manufacturing Technology 48: 283-296.

    Neuhardt, J.B. (1987). Effect of correlated sub-samples in statistical process control. IIE

    Transactions 19: 208-214.

    Pignatiello, J.J., Tsai, A. (1988). Optimal economic design of control chart when cost model

    parameters are not known. IIE Transactions 20: 103110.

    Prabhu, S.S., Montgomery, D.C., Runger, G.C. (1994). A combined adaptive sample size and

    sampling interval X control scheme. Journal of Quality Technology 26: 16-76.

    Prabhu, S.S., Runger, G.C., Keats, J.B. (1993). An adaptive sample size X chart.

    International Journal of Production Research 31: 28952909.

    Reynolds Jr., M.R., Arnolds, J.C., Amin, R.W., Nachlas, J.A. (1988). X chart with variable

    sampling interval. Technometrics 30: 181-192.

    Shewhart, W.A.T. (1931). Economic control of quality of manufactured product. Van

    Nostrand, New York, USA.

    Tagaras, G. (1998). A Survey of recent developments in the design of adaptive control charts.

    Journal of Quality Technology 30:.37-62.

    Taguchi, G. (1987). System of experimental design: Engineering method to optimize quality

    and minimize costs. UNIPU , New York.

    Tsai, H.T. (1990). Probabilistic tolerance design for a subsystem under Burr distribution

    using Taguchis quadratic loss function. Communications in Statistics: Theory and

    Methods 19: 4679-4696.

    Vance, L.C. (1983). A bibliography of statistical quality control chart techniques, 1970

    1980. Journal of Quality Technology 15: 5962.

  • 29

    Woodall, W.H. (1986). Weakness of the economic design of control charts. Technometrics

    28: 408409.

    Yang K., Hancock W.M. (1990). Statistical quality control for correlated samples.

    International Journal of Production Research 28: 595608.

    Yourstone, S.A., Zimmer, W.J. (1992). Non-normality and the design of control charts for

    averages. Decision Sciences 23: 1099-1113.

  • 30

    Appendix

    Using the Burr transformation given in (2) and (3), equation (17) becomes

    1

    1

    '1

    0

    '1

    1

    = Pr Pr1 1 1 1

    Pr Pr (A.1)1 1 1 1

    1 1 1

    1 0, 1 01 1

    kc

    kkY M Y MOS Sn n

    kkY M S Y M Sn n

    kMax M S Maxn

    1

    '

    ,1 1

    kck

    M Sn

    Likewise, 1O in equation (18) can be represented by

    1

    1

    '1

    1

    '1

    1

    O 1 Pr1 1 1 1

    1 Pr (A.2)1 1 1 1

    1 1 1

    1 0, 11 1

    kc

    k n k nY MSn n

    k n k nM S Y M Sn n

    k nMax M S Maxn

    1

    '

    0,1 1

    kck n

    M Sn

    As a result, the conditional probabilities 0 jP , 0mP , 1 jP , and 1mP are obtained as

    0 0 1 0 0

    ' '0 0 1 0

    Pr ,

    + Pr ,

    j j j

    j j

    P k X k LCL X UCLn n

    k X k LCL X UCLn n

  • 31

    0

    1

    1 1 1 = 1

    1+Max 0,M 1+Max 0,M1 1 1 1

    k kc c

    j j

    Ok k

    S Sn n

    1

    ' '

    1 1

    1 0, 1 0,1 1 1 1

    for 1, 2, ..., -1 (A.3)

    j j

    k kc ck k

    Max M S Max M Sn n

    j m

    '0 0 0 0

    0 '

    Pr ,

    1 1 1 (A.4) 1

    1 0, 1 0,1 1 1 1

    m m m

    k kc c

    m m

    P k X k LCL X UCLn n

    Ok kMax M S Max M Sn n

    1 0 1 0 0

    ' '0 0 1 0

    Pr ,

    Pr ,

    j j j

    j j

    P k X k LCL X UCLn n

    k X k LCL X UCLn n

    1

    1

    1 1 1 1

    1 0, 1 0,1 1 1 1

    k kc c

    j j

    Ok n k n

    Max M S Max M Sn n

  • 32

    1

    ' '

    1 1

    1 0, 1 0,1 1 1 1

    for 1, 2, ..., -1

    j j

    k kc ck n k n

    Max M S Max M Sn n

    j m

    (A.5)

    '1 0 0 0

    1 '

    Pr , (A.6)

    1 1 1 1

    1 0, 1 0,1 1 1 1

    m m m

    k kc c

    m m

    P k X k LCL X UCLn n

    Ok n k nMax M S Max M S

    n n