Page 1: Final Year Project (ISP),Project Demo

Insurance Survey Portal

Final Year Project Proposal

Abdul Rehman Aslam9998

Yasir Mehmood9994

Supervised By

Ms. Rabia Latif

Submitted for the partial fulfillment of BS Software Engineering Degree to the Faculty of Engineering

NATIONAL UNIVERSITY OF MODERN LANGUAGESISLAMABAD

September 2012

3 | P a g e

Page 2: Final Year Project (ISP),Project Demo

Table of Contents

1. INTRODUCTION:..........................................................................................................52. BACKGROUND:............................................................................................................53. EXISTING SYSTEM:.....................................................................................................54. AIMS and objectives:......................................................................................................65. PROJECT SPECIFICATIONS:.......................................................................................6

5.1. Operations.................................................................................................................65.2. Roles.........................................................................................................................6

6.PROPOSED SYSTEM FEATURES................................................................................66.1 Use case diagrame.....................................................................................................66.2 System Prototypes.....................................................................................................76.3 Non Functional Requirements...................................................................................9

7. PROPOSED PLAN FOR IMPLEMENTATION:...........................................................97.1. System Requirement Specification...........................................................................97.2. Analysis:...................................................................................................................973. Documentation:..........................................................................................................97.4. Web Development..................................................................................................107.5. Testing....................................................................................................................107.6. Project Gantt chart..................................................................................................10

8. DELIVERABLE OUTCOME.......................................................................................109. RESOURCE REQUIRMENTS.....................................................................................10

9.1. Software Resource Requirements...........................................................................109.2. Hardware Resource Requirements.........................................................................10

10. REFERENCES............................................................................................................12I. www.igiinsurance.com.pk......................................................................................12II. www.agico.com.pk.................................................................................................12CERTIFICATION.............................................................................................................13

4

Page 3: Final Year Project (ISP),Project Demo

1. INTRODUCTION:The aim of a project is to develop an online web application and information system that maintains and manipulates insurance survey record for our valued customer named Saleem Siddiqui and Co., a leading insurance surveying company with four existing branches in major cities of Pakistan. The application will allow the company to automate the record of survey reports of its intended customers for different types of insurance

policies like motor, fire and marine Insurance.

2. BACKGROUND:In Pakistan, most of the surveying companies keep customer’s record manually and it is very difficult for them to manipulate or search a specific customer or claim incidence record. So it is quite a need to develop a system that efficiently handles this record keeping and manipulating problems.

3. EXISTING SYSTEM:For surveying companies, there is no such system available that can be used to keep and maintain record using a fully automated environment.

3.1 LimitationsThe company is spread over different branches all over the country, so manually keeping and maintaining records is limited to local branches of the company. In other words, no concept of a central record exist

4. AIMS and objectives:The aim of the proposed system is to automate the company in order to generate computerized reports of different categories of insurance like Fire, Motor and Marine Insurance.

5. PROJECT SPECIFICATIONS: The proposed system will maintains the data of the customers for following categories:

5.1. OperationsThe company will be able to insert, update and delete the record of a specific customer for given claims

5

Page 4: Final Year Project (ISP),Project Demo

Fire Insurance The company will be able to insert, update and delete the record of a specific customer for a Fire incidence claim

Motor Insurance The company will be able to insert, update and delete the record of a specific customer for Motor claim

Marine InsuranceThe company will be able to insert, update and delete the record of a specific customer for a Marine incidence claim.

5.2. RolesThe proposed system will be managed by different types of users with following rights

AdminThe admin will have complete rights i.e. to add users, delete users, view reports, delete reports and review his/her or subordinate’s work.

UsersThe user will be able to view all information related to the company. He can use a Login and password assigned to login into system, so he can generate ,view records.

6.PROPOSED SYSTEM FEATURES6.1 Use case diagrame

6

Page 5: Final Year Project (ISP),Project Demo

6.2 System Prototypes

General View

Admins View

Users View

7

Page 6: Final Year Project (ISP),Project Demo

6.3 Non Functional Requirements

7. PROPOSED PLAN FOR IMPLEMENTATION:Here is the complete proposed plan for implementation of our system

7.1. System Requirement Specification Requirements will be gathered within 40 days after starting the project.

7.2. Analysis:All the analysis will be done on the basis of the requirements gathered. Time required will be 15 days.

73. Documentation:Project progress reports will also be submitted and on the completion of the project, the final report and complete documentation will be submitted almost in a month.

8

Page 7: Final Year Project (ISP),Project Demo

7.4. Web DevelopmentAfter the web design phase, development phase will start and it will be completed within 4 months approximately.

7.5. TestingOur testing phase will start with development phase, unit testing will be done throughout the development and at the end we will perform system testing.

7.6. Project Gantt chartFollowing are the task and their time lines:

Figure 1: Project Gantt chart

8. DELIVERABLE OUTCOMEDeliverable outcome of the project will be in the form of a website, along with the detailed documentation of the project.

9. RESOURCE REQUIRMENTS Following are the resources require accomplishing our project

9.1. Software Resource Requirements

Dot Net frame The Microsoft Visual Studio 2010 will be used as Integrated Developing Environment (IDE) for the development of proposed system. Visual Studio 2010 is equipped with all essential tools that are required for the development of this system

9.2. Hardware Resource RequirementsA PC with a windows operating system will be used as hardware resource with following specifications

9

Page 8: Final Year Project (ISP),Project Demo

RAM: At least 2 GB of RAM will be required

Hard Drive 20GB of Physical Storage Required

Minimum CPU Requirement Intel Core2Due, with at least 2.4 GHz Dual Core Clock Speed

10

Page 9: Final Year Project (ISP),Project Demo

10. REFERENCES

I. www. igiinsurance .com.pk

II. www.agico.com.pk

11

Page 10: Final Year Project (ISP),Project Demo

CERTIFICATION

It is certified that final year project proposal submitted by Abdul-Rehman Aslam, and

Yasir Mehmood for the partial fulfillment of the requirement of “Bachelor’s Degree in

Software engineering is approved”.

Ms. Rabia Latif

Supervisor Signature ___________________

12