Finch West LRT Project
Construction Liaison Committee Meeting
Tuesday, May 5, 2020
2FINCH WEST LRT PROJECT– CLC
Agenda
Agenda
FINCH WEST LRT PROJECT–CLC 3
• Safety Moment
• Work Update
• Construction Schedule
• Road and Utility Updates (East end)
• Finch West Station
• MSF
• Highway 400 Bridge Rehabilitation
• Humber College and Hwy. 27 Update
• Utility Work
• Communication and Community Engagement
FINCH WEST LRT PROJECT– CLC
Construction Schedule
High Level - Construction Schedule
FINCH WEST LRT PROJECT– CLC
FINCH WEST LRT PROJECT– CLC
Road and Utilities Update
Removal of Street Furniture– Ongoing
Activity Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Removal of street furniture
From the Black Creek to Tangiers Rd.
Ongoing as neededShort-term lane closures and pedestrian detours
Temporary Traffic Signal Installation- Ongoing
Activity Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Temporary traffic signal installation and
removal of existing signals
Finch Ave. W. and Jane St.
CompletedPartial lane closures
off-peak hours (9AM-3PM)
Finch Ave. W. and Signet Dr./Arrow Rd.
OngoingPartial lane closures
off-peak hours (9AM-3PM)
Road Widening – Completed
Activity Start and Duration
Location
FINCH WEST LRT PROJECT– CLC
Road widening (stripping grass and soil, excavation, and asphalt paving)
Stage 1:North side of Finch Ave. W. from Romfield Ln. to Tangiers Rd.
Completed
Stage 2:South side of Finch Ave W. from Romfield Ln. to Tangiers Rd.
Near completion
- Sidewalk closed or re-routed- At least one traffic lane in each direction - Bus stops closed and/or relocated- Access to emergency vehicles, businesses, schools, and churches maintained
Impact
N/A
Road Widening: Stages 2a -Ongoing Work
ActivityStart and Duration ImpactLocation
FINCH WEST LRT PROJECT– CLC
Stage 2a: watermain and storm sewers installation and ongoing road widening
South side of Finch Ave W. from east of Sentinel Rd. to RomfieldLn.
• March to May• 3 months.
• Pedestrians will be re-routed, if needed.
• Closure of the existing eastbound curb lane to create work zone
• At least one traffic lane in each direction
• Bus stops relocated• Access to emergency vehicles,
businesses, schools, and churches maintained
• Noise and dust caused by installation of the water pipes
Watermain and Storm Sewer Installation: Stages 2b - Ongoing Work
ActivityStart and Duration ImpactLocation
FINCH WEST LRT PROJECT– CLC
Stage 2b: Watermain and storm sewers installation
South side of Finch Ave W. from east of Tobermory Dr. to Romfield Ln.
• Late-March• 3 months.
• Pedestrians will be re-routed, if needed.
• At least one traffic lane in each direction
• Bus stops closed and/or relocated
• Access to emergency vehicles, businesses, schools, and churches maintained
Road Widening and Watermain Work: Stages 2a and 2b-Ongoing Work
FINCH WEST LRT PROJECT– CLC
Concrete Median Removal- Upcoming Work
ActivityStart and Duration ImpactLocation
FINCH WEST LRT PROJECT– CLC
Concrete medianremoval
• The Black Creek multi-use pedestrian crossing (Finch Ave. W. and Sentinel Rd)
• Keele St., north of Finch Ave (north side)
Spring 2020 Expect reduced lanes
Road Work and Wet Utility Pictures
FINCH WEST LRT PROJECT– CLC
Utilities– Completed
FINCH WEST LRT PROJECT– CLC-EAST 15
Activity Start and Duration
ImpactLocation
Relocation of hydro poles and duct works
Romfield Ln. to Keele St. Completed • Minimal• Working from
stage 1- road widening work area.
Stage 1: Excavate holes for hydro poles
Stage 2: Install hydro poles
Stage 3: Excavate open cut trench for underground duct structures
Stage 4: String overhead wires and install underground cables
Utilities – Ongoing Work
16
Activity Start and Duration
ImpactLocation
Preparatory work for duct structures and hydro pole relocation and Relocation of Hydro Poles
Finch Ave. W. from Signet Dr. to Jane St.
Preparatory work is ongoing. Five (5) months, approx.
• Short-term lane occupancy
• Some TTC bus stop relocations
• Some pedestrian detours
Stage 1: Excavate open cut trench for underground duct structures.
Stage 2: Excavate open cut trench for cable chambers
Stage 3: Install underground cables
FINCH WEST LRT PROJECT– CLC-EAST
1717
Finch West Station UpdateShahzeb Bhutto, Finch West Station Coordinator
FINCH WEST LRT PROJECT– CLC
Finch West Station Site – Ongoing And Upcoming Work
18
Activity Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Support of Excavation (SOE) and secant wall for the station box
Fenced areas (NE, NW, and SE corners of Finch Ave. at Keele St.)
Ongoing Noise and dust due to pile driving and heavy traffic in the area.
Support of Excavation (SOE) and secant wall for the station box
North side of Finch Ave. W. from Romfield Ln. to Keele St.
- Area has been fenced.- Traffic configuration is in place.- Equipment has been mobilized. - Drilling to start on May 6, 2020, approx.
- Noise and dust- Traffic disruptions- Lane reductions- TTC bus stop
closures- Sidewalk on north
side of Finch Ave. W. closed from Romfield Ln. to Keele St.
19FINCH WEST LRT PROJECT– CLC
Drilling Activity – First Phase - Ongoing
20FINCH WEST LRT PROJECT– CLC
Drilling Activity – Second phase - Ongoing
21FINCH WEST LRT PROJECT– CLC
Drilling Activity – Pictures
22
Maintenance andStorage Facility
Martine Buzingo Shariza – MSF Project Coordinator
FINCH WEST LRT PROJECT– CLC
MSF – Ongoing and Upcoming Work
FINCH WEST LRT PROJECT– CLCT 23
• Pouring footing foundation - Since October 2019
• Installation of steel structure begins Spring 2020
• Stripped, removed and hauled topsoil to TRCA lands - April 2020
24
Highway 400 BridgeRehabilitation UpdateSundip Multani, RBR (Rapid Bridge Replacement) Project Coordinator
FINCH WEST LRT PROJECT– CLC
HWY 400 Bridge Rehabilitation – Ongoing Work
FINCH WEST LRT PROJECT - CLC 25
Activity ImpactsLocation Start and duration
Concrete pour Completed. Curing cycle has commenced
Curing cycle has commenced
Southbound and northbound decks
Lane closures. Little traffic impacts with little volume on the road
Abutment refacing and rehabbing (i.e. chipping and removals
OngoingNE and SW quadrants
Approach Slab Shoulder Removal and Saw cutting
OngoingHwy 400
NB and SB structureAt night: Finch Ave. W. lane closure and Hwy 400 on-ramp lane closure
Finch Ave. W. Ongoing
Nightly work
FINCH WEST LRT PROJECT– CLC 26
Concrete barriers installation
Concrete barriers installation
HWY 400 Bridge Rehabilitation –
FINCH WEST LRT PROJECT– CLC 27
Concrete barriers installation
Concrete barriers installation
HWY 400 Bridge Rehabilitation –
28FINCH WEST LRT PROJECT– CLC
Humber College and Highway 27 Update
Road Work and Utility WorkMarcus Puchtinger, Project Coordinator, Humber College
Nicolas LeBlond, Project Coordinator, Civil Work
Humber College Stop – Ongoing Work
7
Activity
Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Removals (light pole, sign, etc.) removals
Ongoing until July 2020, approx.
• General noise from heavy equipment (excavators, loaders, dozers)
• Increase in truck traffic leaving the Humber College Station site during the excavation
Lot # 5 at Humber College Station
Excavation - Starting on the north side of the lot (south of Humber College Blvd)
Asphalt milling (remove and recycle asphalt)
Activity
Highway 27– Ongoing
7
Activity Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Median removals
• Hwy 27/Humber College Blvd. intersection
• Hwy. 27/Finch Ave. W.
Ongoing• Lane reductions• No TTC impacts• No impacts to pedestrians• Access to adjacent
properties maintained• Nightwork (for median
removal)• Temp. traffic signal work to
take place off-peak hours
Temporary traffic signal installation
• Finch Ave. W. and Westmore Dr. intersection
Ongoing • Hwy 27/Humber College Blvd. intersection
Completed
Watermain relocation• Southeast corner of Hwy
27 and Finch Ave. W.Ongoing. To be completed before May 31
• Lane reductions• No TTC impacts• Pedestrian traffic re-routed• Access to adjacent
properties maintained
Highway 27- Ongoing and Upcoming Work
7
Activity Start and Duration
ImpactLocation
FINCH WEST LRT PROJECT– CLC
Road widening • Lane reductions• No TTC impacts• Pedestrian traffic
re-routed• Access to adjacent
properties maintained
West of Hwy. 27, from the Humber River to 80 m. north of Finch Ave. W.
Early-May 2020 for five (5) weeks, approx.
Highway 27- Road Widening
7FINCH WEST LRT PROJECT– CLC
Utilities Relocation At Highway 27 Right Of Way
FINCH WEST LRT PROJECT– CLC 33
Installation of hydro poles,underground duct bank, cable chambers and road crossing
June 2020 for five (5) months
• Expect closure of lane closest to curb each day, which will re-open at end of each workday
• Pedestrian access
• Intermittent sidewalk closures
• Overnight work
• Two (2) lanes to be occupied during non-peak hours
On Hwy 27, from 200 m. south of Humber College Blvd. to 200 m. north of Finch Ave.
On Finch Ave, east of Hwy 27
Activity Start and Duration
ImpactLocation
Finch Ave. W., from 50 m. west of Hwy. 27 to 100 m. east of Westmore Dr.
Humber College Blvd., from Hwy. 27 to Arboretum Blvd.
Telecom Works at Highway 27 and Finch Ave. W. Area
FINCH WEST LRT PROJECT– CLC 34
Lowering of TelecomMay 8, 2020, for two (2) weeks, approx.
No impacts expectedLot # 5 (Humber College Station Site)
Activity Start and Duration
ImpactLocation
Telecom works:
Buried: Manhole rebuild and duck bank installation.
Aerial: Transfer/installation of new cable to new hydro poles
June 2020 for five (5) months, approx.
North side of Finch Ave. W. from west of Hwy. 27 to Damascus Dr. /Kiskadee Dr.
East side of Hwy. 27 from south of Humber College Blvd. to north of Finch Ave. W.
- Work on the boulevard
- Curb lane closures (9:00 am to 3:30 pm)
- Some bus stop relocations
35FINCH WEST LRT PROJECT– CLC
Communication and Community Engagement
Arantza Arias, Community Relations Specialist
Communication and Community Engagement Activities
36FINCH WEST LRT PROJECT– CLC
Canada Day Pop up
York University Parent and Family Orientation Service Fair
▪ April 28, 2020 – National Day of Mourning.
▪ Virtual Open House from May 13 – 20, 2020: An
interactive platform for participants to view Project update
video, read and download PowerPoint presentation, as
well as ask Project staff questions online.
▪ External Project Newsletter is being delivered by Canada
Post to more than 25,000 businesses/residences.
▪ In lieu of Earth Day/Volunteer Month activity in the
community, Mosaic donated funds to two local food banks
to help support residents laid off work
▪ Developing webinar to support local businesses access
COVID-19 funds
FINCH WEST LRT PROJECT– CLC 37
STAY IN TOUCH
Please sign-up to receive regular updates of construction activities and progress at:
www.metrolinx.com/finchwestlrt
Phone: 416-202-6500
Visit: www.metrolinx.com/finchwestlrt
Email: [email protected]
Follow: @finchwestlrt
3838FINCH WEST LRT PROJECT– CLC
Questions?