fish screen replacement project presentation to …

41
FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO ANGLER FRATERNITY TEMUKA DECEMBER 14 TH 2020

Upload: others

Post on 30-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN REPLACEMENT PROJECT

PRESENTATION TO ANGLER FRATERNITY

TEMUKA DECEMBER 14TH 2020

Page 2: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

PRESENTATION OVERVIEW

• Existing RDR and New Facility

• Background to Project

• Key Objectives

• Design Specifics

• Status and Programme

Page 3: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

RDR and NEW FISH SCREEN LOCATION

RDR Intake

see next slide for detail here

Page 4: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

RDR and NEW FISH SCREEN

Page 5: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

NEW FISH SCREEN – LAYOUT

new canal

existing RDR

new bypass

Page 6: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – LAYOUT

EARLY MODEL

Page 7: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – T-SCREENS

Page 8: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – T-SCREEN

Page 9: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FACILITY OVERVIEW

COMPUTER MODEL“Fish eye” view

looking downstream

Page 10: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FACILITY OVERVIEW

COMPUTER MODEL

One Tee Screen in maintenance

position

Page 11: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FACILITY OVERVIEW

COMPUTER MODEL

Flat screen section (bottom right)

Page 12: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – LAYOUTTHIS ONE”S

REAL!(Waitaki Dam)

Page 13: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

BACKGROUND TO PROJECT• Innovative fish barrier installed ~2007

• Bio-Acoustic Fish Fence (BAFF) proved ineffective in excluding fish from Race (4% - 97%; avg 30%)

• Numerous attempts to modify the installation to improve performance but with marginal success

• Jan 2016 – non-compliance notice from ECan

• Feb 2016 - Commitment by RDRML to replace BAFF

Page 14: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

BACKGROUND TO PROJECT• Sept 2016 – resource consents lodged for replacement with

Rock Bund Infiltration Gallery (RBIG)

• Submissions opposed the RBIG and an alternative design was investigated; April 2017 USA Study Tour

• Jan 2018 – new consent application for a rotary mechanical screen

• June 2018 – consents granted for rotary mechanical screen

• July 2018 – various consents appealed

• July 2019 – appeals on all fish screen consents resolved

Page 15: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

BACKGROUND TO PROJECT• Oct 2019 – construction contract tendered based on a

design and build basis (concept design tendered)

• January 2020 – no complying tenders received (design risk; contracting environment)

• RDRML Board agrees to alternative contracts – fully designed scheme to be tendered; separate screen supply; construct only contract

• Focus on full design of facility

Page 16: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

BACKGROUND TO PROJECT• Computer Fluid Dynamics (CFD) modelling results

identify velocity sensitivities – design revised

• Wider channel – limit on sweep velocities

• Flat screens required

• Baffles to moderate and balance flows through screens

• Enhancements to screen design by AWMA

• Further CFD modelling for confidence

Page 17: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – CFD MODELLING

Page 18: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – CFD MODELLING

Page 19: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

BACKGROUND TO PROJECT• COVID 19 - internet overload!

• July 2020 – fish screen supply contract with AWMA

• Sept 2020 – construction contract tendered

• Oct 2020 – Environment Court suggests consents haven’t commenced

• Nov 2020 – tenders closed

• Dec 2nd Designer advises some flow velocities exceed design

• Dec 9th Env Court Hearing re consents

Page 20: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

KEY OBJECTIVES• Resource Consent CRC182542 – conditions require:

• Exclude fish and return safely to the river

• Design to NIWA Guidelines or Schedule 2 LWRP

• Low Screen Approach Velocity (average <0.12 m/s)

• High Sweep Velocity (at least twice Approach Velocity)

• Testing Regime – initial and on-going to measure key velocities and to sample fish after the screen (in by-pass)

• Complete construction within 30 months (Jan 2021?)

Page 21: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

KEY OBJECTIVES• RDRML Objectives

• Build the right facility

• Meet or exceed consent conditions

• Flow capacity (~34 cumecs plus 10 cumecs)

• Manage sediment (maintain flow velocity through system)

• Budget control

It has to WORK!

Page 22: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

DESIGN SPECIFICS• Approach velocity < 0.12 m/s

• Enough screen area (374m2)• Need for flat screens

• Balance the flows (regulate through each screen)

• Sweep velocity• Seeking high sweep for fish and sediment (> 0.6 m/s)

• High sweep velocity (>1.0 m/s) impacts on screen effectiveness

• 0.9 m/s target

Page 23: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

DESIGN SPECIFICS• Fish Bypass effectiveness

• Safe fish passage back to river

• Testing facility to assess fish condition after the screen

• Use experience from BAFF where fish are caught in the by-pass channel

Page 24: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH BYPASS

Page 25: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH BYPASS CHANNEL – BAFF Photo shows fish by-pass channel in the existing BAFF fish screen. Structure is for sampling fish in the by-pass.

Page 26: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH BYPASStransition from fish screen into by-pass

Page 27: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH BYPASS – FLOW TRANSITION

Page 28: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

DISCHARGE via LAY FLAT GATE intoOPEN FISH BAYPASS CHANNEL

View looking upstream

Page 29: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH TRAP in BAFF BYPASS CHANNEL

Page 30: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

NEW FISH CAPTURE WEIR “PIANO KEY DESIGN”

Page 31: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

NEW FISH CAPTURE WEIR “PIANO KEY DESIGN”

View looking upstream(no fish capture traps shown)

Page 32: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

NEW FISH CAPTURE WEIR “PIANO KEY DESIGN”SCALE MODEL

Page 33: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

NEW FISH BYPASS CHANNEL – PROFILE AND VELOCITY

Black lines shows profile (vertical scale exaggerated)

Blue line indicates velocity along bypass channel

Location of testing weir

Page 34: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

STATUS AND PROGRAMME• Preferred contractor identified

• First screen shipped from AWMA

• Environment Court confirmed consents (awaiting written notice)

• Design changes required to moderate flows

• Original construction programme now very high risk

• Cutover and commissioning most likely May 2022

Page 35: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

DESIGN CHANGE DETAILS• Sweep velocities peaking at 1.3 m/s

• Tee screens become inefficient

• We are not convinced that there is sufficient understanding of why these flows are now evident

• Require confidence in proposed changes before committing to construction

Page 36: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

PROGRAMME - 2021• Pre-construction works (concrete elements)

• Supply of all fish screen elements

• Development of fish capture and testing methods

• Validation of design

• Construction start ~ August 2021

Page 37: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – UNDER CONSTRUCTIONMAIN BODY FABRICATION

Page 38: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – UNDER CONSTRUCTIONONE SCREEN CYLINDER

Page 39: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN – TESTING

Page 40: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

FISH SCREEN #1 – ON ITS WAY!

Page 41: FISH SCREEN REPLACEMENT PROJECT PRESENTATION TO …

RANGITATA DIVERSION RACE MANAGEMENT LTD

Thank you