Introduction History of utility: The Pohnpei system has a peak load of 6MW, served by a diesel fleet with a combined available capacity of 5850 kW ( of 14.5 MW nominally installed), 725 kW of run-of-river hydro, and 980 kW of grid-connected solar PV, including 600 kWp at the Pohnlangas solar farm Recent Pacific RE integration projects; 1. In March 2016, with a grant from the United Arab Emirates (UAE), 600kWp of solar PV was commissioned & integrated into PUC’s system 2. EU-SPC, North Rep 725kW Hydro electric Power plant rehabilitation. Oct 2014. 3. PEC Fund Projects – Nett Elementary School (200kW) – Commissioned 2014. 4.JICA Project – COMFSM (160kW) & FSM President’s office (20kW) – commissioned Dec 2012 Future Pacific RE integration road maps; PUC is currently seeking grant and low interest loans for a 9MW solar and 5.5 MW hydro electric to meet our goal of 100% renewable in 5 years. In line with national energy targets and in support of improved reliability and cost reduction objectives, PUC’s board adopted a vision & mission statement in August 2015 that calls for the development of 9 MW of solar PV and 5.5MW of hydroelectric capacity to reliably serve its 7000 customers w/reduced power generation costs while reducing PUC’s exposure high-fuel price volatility. [ Acknowledge important partners and stakeholders. UAE, SPC, EU, FSM Government, State Government, US Government, China Government & JICA

Upload: james-hamilton

Post on 10-Jan-2017

45 views

Category:

Engineering


2 download

TRANSCRIPT

Introduction • History of utility: The Pohnpei system has a peak load of 6MW, served by a diesel fleet with a combined available capacity of 5850 kW ( of 14.5 MW nominally installed), 725 kW of run-of-river hydro, and 980 kW of grid-connected solar PV, including 600 kWp at the Pohnlangas solar farm

• Recent Pacific RE integration projects; 1. In March 2016, with a grant from the United Arab Emirates (UAE), 600kWp of solar PV was commissioned & integrated into PUC’s system 2. EU-SPC, North Rep 725kW Hydro electric Power plant rehabilitation. Oct 2014. 3. PEC Fund Projects – Nett Elementary School (200kW) – Commissioned 2014. 4.JICA Project – COMFSM (160kW) & FSM President’s office (20kW) – commissioned Dec 2012

• Future Pacific RE integration road maps; PUC is currently seeking grant and low interest loans for a 9MW solar and 5.5 MW hydro electric to meet our goal of 100% renewable in 5 years. In line with national energy targets and in support of improved reliability and cost reduction objectives, PUC’s board adopted a vision & mission statement in August 2015 that calls for the development of 9 MW of solar PV and 5.5MW of hydroelectric capacity to reliably serve its 7000 customers w/reduced power generation costs while reducing PUC’s exposure high-fuel price volatility. [ • Acknowledge important partners and stakeholders. UAE, SPC, EU, FSM Government, State Government, US Government, China Government & JICA

Energy Issues Current energy issues relevant to the Pacific: •What isn’t working; Servicing and Maintenance of diesel generators units are difficult. Load shedding has to be conducted due to shortage of power supply. Hydro penetration is low (725kW Capacity). Actual is: 200-300 Kwh. •Why it isn’t working; 1. Solar works on day time w/good irradiance & hydro operates when water is available in the water reservoir. •Mistakes to avoid going forward; PUC has obtained a 50-year lease 100 acres of former agriculture land from Pohnpei State for the development of 9MW solar farm. And 2 sites will also be developed: Lehnmesi river (4.5MW) and Nankawad river (1 MW) for run-of-water hydro. •Which technologies or processes present solutions; Construction of a 5.5MW hydroelectric capacity at Lehnmesi (4.5MW) and Nankawad (1MW) to serve as base load and when generation is enough. Service of DEG can carried out.

Renewable Energy Integration Success Stories Introduction to any achievements in RE integration, cover: •What worked; - 980kW total solar-grid connected system - 725 KW total Hydro electrical Plant (only runs during high water flow) •Why it worked; - RE integration help support a reduction of PUC’s reliance on diesel generation and system stability. - Hydro operate full load – 1 DEG unit shuts down for service. •How it works; -All RE sources were connected to PUC main grid and are operated and maintained by PUC - Improve reliability and fuel cost reduction - decrease tariff •Which technologies were critical in the success - System is a grid tied. Future plans to include enabling technologies to stabilize. -Only monitoring and dispatching to main power plant. •Important partners and stakeholders.

-National and State Government, Utility Owner, Funding Agencies, Communities

Thankyou