foul drainage and sewer line

Upload: clement-song-hua-ong

Post on 09-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Foul Drainage and Sewer Line

    1/8

  • 8/8/2019 Foul Drainage and Sewer Line

    2/8

    jointers but beyond these requirements the width must be kept to a

    minimum.

    Before any work commences the sewer trace shall be set out. The

    manhole centres shall be marked by a centre peg whose location shall be

    tied to 3 pegs situated outside the working area.

    Sight rails shall be set up painted black and white to mark the centre line

    of the sewer, and boning rods shall be used to give the distance from the

    sight rails to the invert of the sewer. It is desirable that no fewer than 3

    sight rails be set up on each line so that if one is disturbed it would be

    obvious. The maximum distance between sight rails should be 23m.

    The Contractor shall maintain the setting up of pipelines not less than

    460m in advance of pipelying and shall carry such exploratory excavation

    as may be required by Employer.

    For the length of the pipelines which are curved on plan or in elevation the

    curve shall be obtained by deflecting the pipes at each joint.

    Strongly constructed, clearly painted boning rods shall be provided at

    each length where work is in progress. Such boning rods shall be designed

    to show the pipeline invert level below the sight rails.

    When excavation is complete and before any further work commences

    wooden pegs are to be driven into the formation at not more than 5 m

    centres the level of each peg being adjusted to the proposed sewer invertby the use of the sight rails and boning rods.

    6. PIPE BEDDING WITH GRANULAR MATERIAL

    The bedding for the pipes shall be thoroughly compacted. The pipes shall

    be laid evenly on the barrel at the required level. There should be no

    hollows, voids or foreign material under the pipe. Any concrete blocks or

    wedges should be removed on completion of bedding. The bedding

    should be completed to the correct profile as shown in the drawing.

    The bedding should at all stages of the construction be well compacted.

    Water shall be added to the granular material as laid to obtain optimum

    moisture content for compaction and sufficient mechanical tampers,

    vibrators or other approved method of compaction shall be employed at

    all times.

  • 8/8/2019 Foul Drainage and Sewer Line

    3/8

    Particular care must be taken to ensure that proper bedding is obtained at

    and on either side of the pipe joints. Where pipe jointing holes are left the

    bedding particular care must be taken to ensure complete and proper

    filling of the holes after pipe testing.

    7. CONCRETE BED, HAUNCHING AND SURROUND TO PIPE

    The concrete bed foundation and Type Section for the pipes shall consist

    of the concrete or reinforced concrete as shown in details on the Contract

    drawings.

    In all cases the concrete shall be well rammed or vibrated and worked

    under and around the pipes. No concrete shall be placed around the

    pipes until the pipe joints have been inspected and approved.

    At approximately every four pipes or 6m whichever is the less interval the

    Contractor shall form a joint in the concrete bed or surround with 25mm

    thick fibreboard, timber or other approved material. The shuttering

    material shall be left in to form a permanent joint. Where the concrete

    bed is required to be reinforced all reinforcement shall stop on either side

    of the joint.

    In placing the concrete in surround the Contractor is required to concreteright against the side of the trench excavation. Where the excavation has

    been carried out to a greater width than the required Type Section or

    approved width, the Contractor will be required to provide the additional

    concrete necessary to the sides of the excavation.

    8. HANDLING PIPES

    At every point of loading or unloading pipes or castings must be handle by

    approved lifting tackle. Unloading by rolling down planks or any other

    form of inclined ramp will not be allowed. Pies are to be carefully stacked

    on site with timber packings under and between the pipes. Where pipesare stacked, the height shall never exceed 2m.

    9. PIPELAYING

    All pipes shall be carefully brushed out inside and shall be tested for

    soundness before being laid. The pipes shall be laid separately to true

    inverts, straight lines and falls, each pipe being separately boned between

  • 8/8/2019 Foul Drainage and Sewer Line

    4/8

    sight rails and bearing evenly upon the solid ground or concrete for its full

    length.

    Where pipes are laid without a concrete bed, holes shall be cut in the

    bottom of the trench os such size and depth as to allow the joints to be

    properly made and the barrel of the pipe to bear evenly on the solidground for its full length.

    Where pipes are to be laid on rock formation the excavation shall be taken

    down to 1.2 m below bed level and great care shall be taken to ensure

    that there are no projecting pieces of rock on which the pipe will ride. The

    bed will then be made up to its true line and level by refilling with either

    100mm of consolidated selected material from the excavation well

    rammed, and watered if necessary, or with 100 mm of concrete 1:3:6 or

    as per contact drawings.

    The Contractor shall be responsible for ensuring that all blocks and

    wedges are of sufficient size and strength to prevent settlement of the

    pipes.

    The excavation of the bottom 150mm of the trench and laying of screed

    or any other surface preparation shall be done immediately in advance of

    pipe laying but no pipes shall be laid until a distance of at least 10m along

    the trench has been prepared and bottomed up to the receive the pipes.

    The trenches and joint holes shall be kept free from water until the pipes

    are laid, jointed and surrounded with concrete. No water from the

    trenches shall be allowed to endter the new pipes and no re-filling of

    trenches will be allowed until the joints of the pipes have been tested,inspected and approved.

    Properly fitted stoppers shall be provided and constantly used to close the

    ends of all uncompleted pipe lines. The stoppers are only to be removed

    when necessary.

    10.REINFORCED CONCRETE MANHOLES

    Reinforced concrete (Grade 30-20 mm aggregates) manholes shall each

    be of the internal plan sizes and depths indicated on the drawing. Unless

    otherwise specified, manholes not exceeding 1.0m deep from cover toinvert are to be 450mmx690mm on plan internally and those exceeding

    915mm deep are to be 600mmx1000mm, the length being increased of

    necessary to accommodate the branch drains. All reinforced concrete

    bases, walls and cover slabs shall be 150mm thick as shown and

    reinforced with mild steel rod reinforcement.

  • 8/8/2019 Foul Drainage and Sewer Line

    5/8

    Form rebated opening in cover slab for manhole cover and frame. The

    manhole shall be benched with plain concrete (Grade 25) by using

    sulphate resisting cement and with half round or three quarter section

    salt-glazed ware channels bedded on. Provide galvanized malleable step

    irons to all man holes exceeding 915mm deep.

    11.MANHOLE

    Where detailed R.C manholes are to be built in the positions shown on in

    accordance with the details in the approved Drawings.

    The chamber and shaft rings may be supplied in different lengths and

    each section will be provided with lifting holes. The joints between the

    sections shall be of an ogee joint with cement mortar to form a watertight

    joint. Before completion of the manhole all the lifting holes, ogee and

    other joints shall be neatly pointed.

    The reinforced concrete slabs covering the chambers and the shafts of the

    manholes shall be set and pointed in cement mortar to form watertight

    joints.

    The reinforced concrete slabs covering the chambers and the shafts of the

    manholes shall be set and pointed in cement mortar to form watertight

    joints.

    At all points where pipes are built into walls, or floors, great care shall be

    taken that the joint is watertight joint. If found to be otherwise, the

    concrete shall be cut away and replaced with concrete, to make a

    watertight joint.

    Manhole covers and frames are to be set in cement mortar and

    surrounded with Grade B concrete and covers left flush with the

    surrounding ground or road surface as the case may be and shall be set

    on two courses of 225mm brickwork. The fine adjustment of cover levels

    shall be effected by creasing courses of hard burnt tile. Care shall be

    taken to ensure that the cover is level with and sloped to any fall or grade

    to the surrounding surfaces.

    12.BACKDROPS AND TUMBLING BAY

    Where detailed, tumbling bay, or backdrop are to be constructed in

    accordance with the details on the approved drawings.

  • 8/8/2019 Foul Drainage and Sewer Line

    6/8

    Special spigot and socket, tumbling bay, or backdrop junctions shall be

    used in the junction between the two lines of pipes.

    Tumbling bay backdrop pipes are to be built in the walls of the man hle by

    cutting a neat hole in the precast concrete rings sufficient for building in

    the pipes and pointed in cement mortar. The joint shall be finished flushwith the inside of the manhole and neatly splayed on the outside to form a

    watertight joint.

    13.MANHOLE COVERS AND FRAMES

    The manhole covers and frames shall be of the cast iron machines type

    and of approved size, weight and pattern. The heavy duty type shall be

    used in roadways and paved area.

    Manhole covers and frames shall comply with BS 497 and be of the

    standard type and size and shall be accordance with the drawings. The

    cover and frame shall be cast from a mixture of cast iron scrap and a

    suitable grade of pig iron. The mixture of the resultant metal shall be free

    from air and sand holes and from cold shuts. They shall be neatly dressed

    and carefully fettled. All casting shall be free from voids, whether due to

    shrinkage, gas inclusion or other causes.

    Manhole covers and frames shall be supplied coated with a black

    bituminous composition. They shall be well fitted, flush at the top and

    should not rock.

    14.TESTING TO BRITISH CODE OF PRACTICE 301:1971

    After the sewers have been laid they shall be inspected by the Employer

    for grade, line and level and appearance of inner surface. Any sewers

    inaccurately laid to grade, line and depth, or if the interior shows open

    joints, ragged edges or protruding mortar, or which are not alignment,

    shall be made good and relaid so as to conform to the drawings and

    specification and at the Contractors expenses.

    Sewers shall then be subjected to water or air test, at the discretion of the

    Employer, for which the Contractor shall provide all necessary testingapparatus, including expanding plugs, flexible bag stoppers, smoke

    cartridges, etc. together with any other apparatus and labour which may

    be required for the proper testing of the sewers. These tests shall be

    carried out before backfilling and again after completion of backfilling and

    reinstatement.

  • 8/8/2019 Foul Drainage and Sewer Line

    7/8

    Sewer with caulked joints shall not be tested until at least 24 hours after

    jointing.

    The sewer or drain shall be tested in sections consisting of the length of

    pipe between two adjacent manholes.

    Water test

    The test before backfilling shall be commenced as soon as practical after

    laying but the sewer or drain shall have been filled for approximately one

    hour before test readings are taken.

    A test pressure of 1.2m head above the soffit of sewer or drain shall be

    applied at the high end but no more than 2.4m at the low end. Steeply

    graded sewers or drains shall be tested in stages where the above

    maximum head would be exceeded if the whole section were tested at

    once.

    The loss of water over a period of 30minutes shall be measured by adding

    water from a measuring vessel at regular intervals of 10 minutes and

    noting the quantity required to maintain the original water level in the

    stand pipe. The average quantity of water added for sewers or drains up

    to 300mm nominal bore shall not exceed 0.1 gallon per hour per 30 linear

    metre per 25mm of nominal bore of the sewer and drain.

    The test after completion of backfilling shall be described above.

    The length of sewer or drain shall be effectively plugged with suitable

    expanding plugs between manholes, and the air pumped in with an

    approved air testing machine until a pressure of 100mm head of water is

    indicated in U-tube connected to the system. The air pressure shall not

    fall to less than 75mm head of water during a period of 5 minutes, without

    further pumping, after a period for requisite stabilization drains which

    incorporate traps shall be tested to 50mm head of water and the

    permissible loss shall be 12mm head of water in 5 minutes.

    Should the pressure not be maintained for the required time a smoke testshall applied for the purpose of locating the fault.

    15.CLEARING PIPELINE OF OBSTRUCTION

    After testing of the pipelines as specified, the interior of the pipelines shall

    be inspected to ascertain that the pipes are entirely clear of obstruction

    and that the invert is smooth.

  • 8/8/2019 Foul Drainage and Sewer Line

    8/8

    In the case of pipes which cannot be inspected from the inside, generally

    under 600mm in diameter, a loose plug shall be passed through each

    pipeline to ensure that the pipes are entirely clear of obstruction and that

    the invert is smooth. The loose plug shall be in the form of a cylinder with

    solid ends made of timber not less than 25mm in thickness.

    The outside diameter of the ends of the plug shall not be smaller than

    25mm less than the diameter of the pipe through which it is to be passed

    and its length shall not less than its diameter.

    Any obstruction in the pipelines shall be removed and any unevenness of

    the invert shall be made good.

    16.FRACTURE OF PIPE

    In the event of pipes being fractured after properly laid whether due to

    imperfect beds having been formed or the material for refilling having

    been improperly selected or to any other causes, the Contractor in every

    instance, will be held responsible and he will be called upon to replace

    such defective pipes at his won cost, if such defect appears before the

    expiration of the period of maintenance.

    Any pipe or length of pipes found to be defective shall be immediately

    removed and replaced at the Contractors expense and leaking joints shall

    be remade; the inspections and test shall then be repeated as often as

    necessary until the whole lines under inspection or test is accepted by theEmployer.