foundations purpose – to transfer weight of structure (including live loads) to the ground within...
TRANSCRIPT
Foundations
Purpose – To transfer weight of structure (including live loads) to the ground within allowable settlement criteria
Foundation Shape & Size
• Dependant on type of structure, weight, soil bearing capacity & sensitivity of structure
• Pressure under foundation
= structure weight + imposed loads
area of foundation * F.O.S
Note effect of wind or horizontal loading
ReplacementDisplacement
Driven castinsitu
Permanentcasing
Temporarycasing
Pre-Formed
Concrete Timber Steel
UnsupportedSupported
Permanent
Temporarysupport
CasingDrilling mud
Or water
Types of Bearing Pile
Replacement - Rotary Bored Piling• 300mm to 2400mm
diameter• Up to 50M depth• Auger ‘screws’ into
ground, breaking up soil• Auger withdrawn with
soil• Back spun to release • May require temporary
casing
Continuous Flight Auger (CFA)
• Auger not removed during drilling – supports bore sides
• When design depth reached concrete delivered through centre of auger to base of bore and auger removed at same rate as concrete infill
• Reinforcement cage added to wet concrete• Quiet• Excavated soil to be disposed of
Auger Pile Walling1. Contiguous Piling – small gap between piles
2. Secant Piling – piles interlocked
Reinforced Non Reinforced
Vibro Replacement• 1. Vibrator penetrates weak soils under action
of vibrations and 'compressed air' jetting medium and forms a hole to design
• 2. After being held at depth for a short time, the vibrator is withdrawn and a charge of stone is placed into the hole.
• 3. The vibrator is reintroduced into the hole, the stone is compacted, forced out and tightly interlocked with the surrounding ground.
• 4. by adding successive charges of stone and compacting each one, a column of very compact stone is built up to ground level.
Dynamic Deep Compaction• With DDC, the ground is subjected to repeated
surface tamping using a heavy steel and concrete weight.
• Typically the tamper weighs between 5 and 20 tonnes, dropping in free fall from heights of up to 25 metres.
• The tamper is dropped a set number of times on a grid pattern over the site to form a pass. Two to five passes on a site, dependent on soil type and condition, can be required.
• The imprints formed at each drop position are infilled with granular material after each pass.
Health & Safety Issues
• Heavy plant manoeuvring on site – use banksman
• Other plant eg concrete deliveries need to work close by
• Overhead working on many applications• Noise of driven piles• Deep excavations to be protected• Piles designed on basis of site investigation