FR-UK-IE Regional InitiativeCross-Border Balancing Procurement State of progress
SG 7 - 03 December 2008
John Prime - Claude Perret
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Summary
Main issues stated at last meeting
Interim solution : state of progress
Enduring solution : state of progress
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Main issues stated at last meeting
BALIT Project (Acronym for “Balancing Inter TSO”) Launched after the regulators’ approval of the NGET-RTE proposal Interim solution, based on current BASA Enduring solution, implementing complete process
Interim solution BASA contract evolution in progress The Interim solution will start after new French BM Rules approval by
CRE No practical solution to authorize NGET to formulate bids on the French
BM Target : New Rules should be approved Jan 2009 NB : these new Rules will be convenient also for Enduring solution
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Main issues stated at last meeting
Enduring solution NGET and RTE have started preliminary studies Enhanced planning should be available in Nov 2009 Remuneration of interconnector operators for use of infrastructure
needs to be considered
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Interim solution : state of progress
BASA contract evolution NG and RTE agreed on required changes Draft worked out by NG Ratification by RTE in progress
New French BM Rules The consultation of stakeholders is over The target for an approval by CRE in Jan 2009 remains relevant
TSO preparations on target for 01-Feb-09 commencement
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Enduring solution : state of progress
Technical solution for information exchanges BALIT platform
Collects TSO to TSO tenders Aggregates a Merit Order List Manages the tendering and allocation process Display results to each participant
Implementation guide for the BALIT Platform Based on ERRP V2.r0 Worked out by RTE, approved by NG
Invitation to tender for software development In progress
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Enduring solution : state of progress
IS modifications Analysis Phase in progress
Price generation (for each 50 MW bloc) Sending of offers to BALIT Platform Integration of offers received from BALIT Platform Acceptance communication managing
Settlement process Analysis Phase in progress
Operational process Being finalised
Gestionnairedu Réseau de Transport d 'Electricité
RTE(EDF)-CN2i 2002#RTE
Enduring solution : state of progress
Remaining to be doneDevelopment and coding PhaseContractual aspects
Revision of BASA Creation of TSO-TSO contract
Remuneration of interconnector operators A four parties meeting is scheduled in December
Implementation targeted for November 09