Page 1: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

Fullerton College Bond Fund Projects Update

Fullerton College Athletics ProjectFullerton College Athletics Project

Fullerton College Athletics Project

Scope Overview

Schedule

Parking

Page 2: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

N. BERKELEY AVE.

N.

BE

RK

EL

EY

AV

E.

N.

LE

MO

N S

T.

E. CHAPMAN AVE.

Fullerton College Athletics ProjectFullerton College Athletics Project

Page 3: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

N. BERKELEY AVE.

N.

BE

RK

EL

EY

AV

E.

N.

LE

MO

N S

T.

E. CHAPMAN AVE.

Phase 1Olympic Pool•50 meter pool replaces old 25 meter pool•1 meter and 3 meter spring boards•Pool pump house building•Fire pump building•Serves as additional fire protection to campusTennis Courts•RefurbishedNew Fire Lane

FIR

E L

AN

E

Fullerton College Athletics ProjectFullerton College Athletics Project

Page 4: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

N. BERKELEY AVE.

N.

BE

RK

EL

EY

AV

E.

N.

LE

MO

N S

T.

E. CHAPMAN AVE.

Phase 2A Artificial Turf Fields•Football, soccer and track and field per NCAA standards•1,500 seat home bleacher & pressbox•500 seat visitors bleacher•Six 100 ft. light poles withdirectional reflectors76.6 footcandles for games (30 footcandles for simple use)0.6 footcandles at 100 ft east (1.5 footcandles on vertical)0.16 footcandles at 150 ft east ( 0.5 footcandles on vertical)

Fieldhouse•20,000 sf / 2 stories•Locker rooms/Training•Field support services•3 Classrooms•10 Offices•6 workstations•Roof plaza assembly space (1,800 sf)•60 new parking stalls

Fullerton College Athletics ProjectFullerton College Athletics Project

Level 2

Level 1

Light Pole Reflectors

Page 5: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

Phase 2C Dance Studio•New lighting and A/C•Refinished floors and paintCorridors•New lighting, floors, and paintRestroomsStorage

Phase 2B South Gym•New lighting and A/C•Refinished floors, paint•Refurbished basketball equipmentWomen’s Locker Room•New lighting and ventilation•Refurbished and new showers•New Dedicated team rooms•New bathroomsCoaches locker roomsOfficials changing roomsEquipment storage

Fullerton College Athletics ProjectFullerton College Athletics Project

Page 6: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

Phase 2DNorth Gym•New power retractable bleachers w/ assistive listening•Refinished floors•New lighting and A/CMezzanines•Renovated for multi-purpose use•New lights, A/C & paint•(16) Offices & (2) Meeting Spaces•New Storage

Men’s locker room•New lighting and ventilation•New lockers•Refurbished and new showers•New Dedicated team rooms•New bathrooms

Phase 2E Outdoor Sports Court•New Sand volleyball pit•New Basketball half-court•Refurbished strength lab•Expanded Training Facilities•New circuit lab

Fullerton College Athletics ProjectFullerton College Athletics Project

Page 7: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

N. BERKELEY AVE.

N.

BE

RK

EL

EY

AV

E.

N.

LE

MO

N S

T.

E. CHAPMAN AVE.

Additional WorkPlaying Field•Bleachers/Pressbox•Jump Events•Signage•Throwing FieldDoors•Security•Access hardware•Value engineeringDance Studio•Floor repair•Ballet barsSouth Gym •Bleachers

Fullerton College Athletics ProjectFullerton College Athletics Project

Page 8: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

Original SchedulePool – 8 MonthsStart Date December 21, 2007Substantial Completion August 22, 2008Current SchedulePool – 16 MonthsStart Date December 27, 2007Substantial Completion April 30, 2009

Original SchedulePE/Field House – 13 MonthsStart Date January 25, 2008Substantial Completion March 9, 2009Current SchedulePE/Field House – 21 MonthsStart Date September 2, 2008Substantial Completion May 18, 2010

Schedule

Fullerton College Athletics ProjectFullerton College Athletics Project

Phase 1Phase 1Phase 1

Phase 2

Page 9: Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking

Fullerton College Athletics ProjectFullerton College Athletics Project

Parking

• Number of parking spaces at the beginning of our program – 3,314

• Number of parking spaces at the present time – 3,554 or gain of 240 spaces

• Number of parking spaces expected after our last approved project (Technology Complex) – 3,774 or gain of 460 spaces