gas systems for gif++ 14/02/2015 ernesto regaño 1
TRANSCRIPT
14/02/2015Ernesto Regaño2
Summary: Status and plan Detailed status.Future growth of the systems’ facility.
Overview
29.06.2012
Summary
3
Preferred installation periods and Duration W08 (false floor) 1week. W09 (complete piping) 3 days. W16 (closed loop connection) 3-5 days
Specific needs Need to open the false floor and limit the access to avoid any
falling accident. RP vacuum cleaner.
Present status. Temporary Lack of false floor due to hard work needed to
prepared and because was completely different from all other experimental zones in EHN1.
Gas available from w10 ( for RPC, TGC)
14/02/2015Ernesto Regaño4
System Status To be done
Panels Validated Nothing
RPC-TGC Mixers On hold for the spill retention tray
Supply pipe work with welding, Connection to analysis rack, two pipe lines between Atex and not Atex rack , connection of T for RPC mixture, Plastic exhaust connections. Electrical work form MFCs, and humidifier , functional test.
Gas service zone
Waiting for aluminium profiles.Spill retention tray To be welded and installed
Install aluminium profile for suport the false floor. False floor already cut and in traspor to GIF++, (Minor cuts in the false floor tiles needed).
IR Analisis rack Waiting for 1 pipe work 1 Pipe work ,electrical work, Funtional test and RUN, Permanent 24v Power supply needed
H2O-O2 Analisis
Being leak tested Leak testing, Transport, Electrical work, Permanent 24v Power supply needed
Pipe cable tray and exhaust pipe support
Pipe cable Tray instaled, Exhaust pipe to be anchored to the wall properly.
Detailed Actual Status.
14/02/2015Ernesto Regaño8
H2O-O2 Analisis rack to be instaledClosed loop (RPC cosmic trigger) ready to
be instaled, calibrated and used. W16.Several Mixers (paied by the users) will be
build and Instaled.Small closed loop racks (paied by the
users) will be build and Instaled.Control rack to be discussed and defined.Other Users needs.
Coming upgrades