gas treatment plant
DESCRIPTION
Gas Treatment Plant. Chris, Stephanie, Mariam, Kyle Mentor: Jerry Palmer. Report Outline. Previous Questions Block Flow Diagram Detailed PFD's (stream #, components, P&T) for each process Energy sinks/loads, Equipment sizing, Cost in Aspen estimator for one process -- Hydrocarbon recovery . - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/1.jpg)
Gas Treatment PlantChris, Stephanie, Mariam, Kyle
Mentor: Jerry Palmer
![Page 2: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/2.jpg)
Report Outline
• Previous Questions
• Block Flow Diagram
• Detailed PFD's (stream #, components, P&T) for each process
• Energy sinks/loads, Equipment sizing, Cost in Aspen estimator for one process -- Hydrocarbon recovery
![Page 3: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/3.jpg)
Previous Questions1. Sending 97% Nitrogen and 3% methane from Nitrogen
rejection stream to NH3 plant.2.Using thermal swing adsorber instead of a pressure
swing adsorber.To prevent the loss of feed gas in the bed during
depressurization and also,the short time cycle in PSA can cause rapid re-pressurization that will lead to transient variation in the feed and product flow which will affect the operation of the plant
3. Using only one turboexpander for Hydrocarbon recovery.
![Page 4: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/4.jpg)
Basis : 310 MMSCFD
RevenuesMidrex : 103 kmol/day (Transfer Cost)Syn Gas:111 kmol/day (Transfer Cost) Nh3 PLant : 50.4 kmol/day (Transfer Cost)CHP :195.4 kmol/day (Transfer Cost)Pipeline:4.8 kmol/day ($3.80/MSCFD)LNG: 5000 BBL/day ($10.40/BBL)NGL: 48990 BBL/day (~$22/BBL)
![Page 5: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/5.jpg)
Block Flow Diagram
![Page 6: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/6.jpg)
![Page 7: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/7.jpg)
PFD-002
![Page 8: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/8.jpg)
PFD-003
![Page 9: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/9.jpg)
![Page 10: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/10.jpg)
![Page 11: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/11.jpg)
Aspen Estimate-Demethanizer in Hydrocarbon Recovery
Size:Tower:o Vessel Diameter: 8.5 fto Vessel Height 66 fto Liquid volume: 11,249.5 gallonso 33 Trayso 24 inches between trays
Condenser:o Area: 22,980.6 ft^2
Reboiler:o Area: 7,803.94 ft^2o Tube length: 20 ft
Reflux Pump:o Liquid flow rate: 1808.3 GPMo Efficiency: 70
![Page 12: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/12.jpg)
Aspen Estimate-Demethanizer in Hydrocarbon Recovery
Equipment Cost:o Tower: $3,059,300o Condenser: $419,000o Reboiler: $268,000o Reflux Pump: $17,200
Total equipment cost for one Demethanizer Column: $3,763,500
![Page 13: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/13.jpg)
Aspen Estimate-Demethanizer in Hydrocarbon Recovery
Energy:o Tower: 28.03 MMBTU/hro Condenser: 22.7 MMBTU/hro Reboiler: 5.3 MMBTU/hro Reflux ratio: .35
![Page 14: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/14.jpg)
Cost:o Total operation cost:
19,031,900 $/yearo Total capital cost:
$12,567,400
Aspen Estimate-Demethanizer in Hydrocarbon Recovery
![Page 15: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/15.jpg)
![Page 16: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/16.jpg)
![Page 17: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/17.jpg)
![Page 18: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/18.jpg)
Annotated Equipment ListEquipment Description Equipment Description Equipment Description Equipment Description
AC-001 AIR COOLER D-001 VAPOR-LIQUID SEPARATOR
HX-003 HEAT EXCHANGER
MS-001 MOLECULAR SIEVE BED
C-001 DEMETHANIZER
D-002 VAPOR-LIQUID SEPARATOR
HX-004 HEAT EXCHANGER
MS-002 MOLECULAR SIEVE BED
C-002 CRYOGENIC DISTILLATION COLUMN;ASTM A353
D-003 VAPOR-LIQUID SEPARATOR
HX-005 HEAT EXCHANGER
MS-003 MOLECULAR SIEVE BED
CMP-001 COMPRESSOR D-004 INLET- SEPARATOR
HX-006 HEAT EXCHANGER
MS-004 MOLECULAR SIEVE BED
CMP-002 COMPRESSOR D-005 VAPOR-LIQUID SEPARATOR
HX-007 HEATER MS-005 MOLECULAR SIEVE BED
CMP-003 COMPRESSOR D-006 VAPOR-LIQUID SEPARATOR
HX-008 BRAZED ALUMINIUM
MS-006 MOLECULAR SIEVE BED
CMP-004 COMPRESSOR D-007 VAPOR-LIQUID SEPARATOR
HX-009 BRAZED ALUMINIUM
PMP-001
CMP-005 COMPRESSOR D-008 PHASE SEPARATOR
JT-001 JOULE THOMPSONVALVE
R-001 CHILLER
CMP-006 COMPRESSOR D-009 VAPOR LIQUID SEPARATOR
JT-002 RB-001 REBOILER
CMP-007 COMPRESSOR HX-001 HEAT EXCHANGER
M-001 MEMBRANE
CMP-008 COMPRESSOR HX-002 HEAT EXCHANGER
M-002 MEMBRANE
![Page 19: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/19.jpg)
Energy Loads and Sinks• PFD-001: Compression = 6888 HP
Heating = 1.7MMBTU/HR
• PFD-002 and PFD-003: Estimated total of 139MMBTU/HR
• PFD-004:Air Cooling =3.4MMBTU/HR Compression = 880HP
Heating = 44.6MMBTU/HR
• PFD-005: Refrigeration = 56.3 MMBTU/HR
• PFD-006: Heating = 8 MMBTU/HR
• PFD-007: Compression = 1260 HPRefrigeration = 58 MMBTU/HR
• PFD-008: Compression = 920HP
![Page 20: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/20.jpg)
Major Equipment Costs
• 6 molecular sieve Adsorbers installed $ 6,690,000• 24 Tray Nitrogen Rejection Column Installed
$2,300,000• Absorbing and Stripping Columns for MDEA
treatment, approximately 25 trays each intstalled
$2,500,000
![Page 21: Gas Treatment Plant](https://reader036.vdocument.in/reader036/viewer/2022062222/568163d3550346895dd51c47/html5/thumbnails/21.jpg)
Q & A