geo lrfd jeffh

Upload: jamie-moore

Post on 01-Jun-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/9/2019 Geo Lrfd Jeffh

    1/51

    LRFD and Geotechnical Design andConstruction

    September 6, 2007

    Jeff Horsfall

    Wisconsin Department of Transportation

  • 8/9/2019 Geo Lrfd Jeffh

    2/51

    Discussion Topics

    •WisDOT Geotechnical guidelinesand variances from AASHTO code

    •Process Description•Plan Documents

    •New Pile Driving Specification

  • 8/9/2019 Geo Lrfd Jeffh

    3/51

    Session Goals:

    How the WisDOT Policies vary from

    the AASHTO Code and Guidelines

    Process for WisDOT to evaluatebridge foundations using LRFD

    What to put on the Bridge PlansWhat is the new pile specification

  • 8/9/2019 Geo Lrfd Jeffh

    4/51

    “ The Code is more what you call guidelinesthan an actual rule.”

    Captain Barbosa to Miss Swan

     aboard the Black Pearl 

  • 8/9/2019 Geo Lrfd Jeffh

    5/51

    WisDOT Geotechnical

    Guidelines, variances from AASHTO

    code and the old Bridge Manual

    Old Bridge Manual•Chapter 10 Substructures - General

    •Chapter 11 Piling

    Revised Bridge Manual•Chapter 10 Geotechnical Investigation

    •Chapter 11 Foundation Support

  • 8/9/2019 Geo Lrfd Jeffh

    6/51

    Revised Bridge Manual

    Chapter 10 Geotechnical Investigation•Geotechnical Bulletin #1

    • AASHTO Table 10.4.2-1

  • 8/9/2019 Geo Lrfd Jeffh

    7/51

  • 8/9/2019 Geo Lrfd Jeffh

    8/51

    WisDOT Policy and

    exceptions to the AASHTO

    •Shallow Foundations

  • 8/9/2019 Geo Lrfd Jeffh

    9/51

    WisDOT exception to AASHTO:

    It is WisDOT’s current policy to designshallow foundations using the Allowable

    Stress Design (ASD) method.

    Wi DOT li i

  • 8/9/2019 Geo Lrfd Jeffh

    10/51

    WisDOT policy item:

    It is WisDOT’s policy to place the bottom ofshallow foundations at embedment depths of

    4 feet unless founded on competent bedrock.

    Wi DOT li it

  • 8/9/2019 Geo Lrfd Jeffh

    11/51

    WisDOT policy item:

    It is WisDOT’s policy to permit a maximum of1 inch of horizontal movement at top of

    substructure unit and 1.5 inches of totalestimated settlement.

    Wi DOT li it

  • 8/9/2019 Geo Lrfd Jeffh

    12/51

    WisDOT policy item:

    The normal ground water level is used todetermine the allowable bearing capacity of

    footings.

    At stream crossings, the mean annual high

    water level is used to compute a factor ofsafety for bearing capacity. This factor of

    safety must be reasonable, but can be lessthan that specified for design (FS=3).

  • 8/9/2019 Geo Lrfd Jeffh

    13/51

    WisDOT Policy and

    exceptions to the AASHTO

    •Deep Foundations

    Wi DOT li it

  • 8/9/2019 Geo Lrfd Jeffh

    14/51

    WisDOT policy item:

    WisDOT’s minimum pile spacing is 2’-6” or 2.5pile diameters, whichever is greater.

    WisDOT’s maximum pile spacing is 8’-0” ,

    based on abutment or pier structural designs.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    15/51

    WisDOT policy item:

    It is WisDOT’s policy to use a minimum 6-inchpile embedment in the footings, but there are

    conditions where more embedment is

    required.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    16/51

    WisDOT policy item:

    It is WisDOT’s policy to place the bottom ofpile-supported footings below the final

    ground surface at a minimum depth of 2.5 feetfor sill abutments and at a minimum depth of

    4 feet for piers and other types of abutments.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    17/51

    WisDOT policy item:

    It is WisDOT policy to limit the yield strengthto 36 ksi for steel piles.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    18/51

    WisDOT policy item:

    It is WisDOT’s policy to limit the horizontalmovement at top of substructure unit to 0.5

    inch or less at the service limit state.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    19/51

    WisDOT policy item:

    WisDOT requires at least four (4) piles pergroup to support each substructure unit,

    including each column for multi-columnbents.

    WisDOT does not reduce geotechnicalresistance factors to satisfy redundancy

    requirements to determine axial pileresistance. Hence, redundancy of resistance

    factors in LRFD [10.5.5.2.3] is not applicable

    to WisDOT structures.

    WisDOT exception to AASHTO:

  • 8/9/2019 Geo Lrfd Jeffh

    20/51

    WisDOT exception to AASHTO:

    Recommended values of nominal lateralresistance for battered or vertical piles used

    by the Structures Design Office, are asfollows:

    • A detailed analysis

    • A minimum value based on pile type• A table of typical values

  • 8/9/2019 Geo Lrfd Jeffh

    21/51

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    22/51

    WisDOT policy item:

    It is WisDOT policy to initially compute adesign resistance capacity for piling and then

    to drive the piles such that the drivenresistance capacity meets or exceeds the

    design capacity.

    Hence for piles prone to scour, the driven pile

    capacity will exceed the design capacity tocompensate for extreme events when a

    portion of the embedded pile length is

    exposed.

    WisDOT policy item:

  • 8/9/2019 Geo Lrfd Jeffh

    23/51

    WisDOT policy item:

    WisDOT policy requires a multi-column bentto be designed as a redundant rigid frame.

    Hence when a bent contains at least 4

    columns then the resistance factors should

    be increased by 20 percent.

  • 8/9/2019 Geo Lrfd Jeffh

    24/51

    Process Description

    Process

  • 8/9/2019 Geo Lrfd Jeffh

    25/51

    Process

  • 8/9/2019 Geo Lrfd Jeffh

    26/51

    Soil Boring Example

  • 8/9/2019 Geo Lrfd Jeffh

    27/51

    Soil Boring Example

    SPT Hammer Efficiency Correction, AASHTO Code

  • 8/9/2019 Geo Lrfd Jeffh

    28/51

  • 8/9/2019 Geo Lrfd Jeffh

    29/51

    SPT Hammer 

    EfficiencyCorrection

    FHWA Driven Software

  • 8/9/2019 Geo Lrfd Jeffh

    30/51

    FHWA Driven Software

  • 8/9/2019 Geo Lrfd Jeffh

    31/51

  • 8/9/2019 Geo Lrfd Jeffh

    32/51

  • 8/9/2019 Geo Lrfd Jeffh

    33/51

  • 8/9/2019 Geo Lrfd Jeffh

    34/51

    Site Investigation Report Table

  • 8/9/2019 Geo Lrfd Jeffh

    35/51

    Site Investigation Report Table

    Drivability Evaluation - GRLWEAP Software

  • 8/9/2019 Geo Lrfd Jeffh

    36/51

    Drivability Evaluation GRLWEAP Software

  • 8/9/2019 Geo Lrfd Jeffh

    37/51

    10 ¾” Diameter CIP Pile using a D-16-32

  • 8/9/2019 Geo Lrfd Jeffh

    38/51

  • 8/9/2019 Geo Lrfd Jeffh

    39/51

  • 8/9/2019 Geo Lrfd Jeffh

    40/51

  • 8/9/2019 Geo Lrfd Jeffh

    41/51

  • 8/9/2019 Geo Lrfd Jeffh

    42/51

  • 8/9/2019 Geo Lrfd Jeffh

    43/51

  • 8/9/2019 Geo Lrfd Jeffh

    44/51

    Plan Documents

    Current Language

    Abutments to be supported on HP 10 x 42

  • 8/9/2019 Geo Lrfd Jeffh

    45/51

    Abutments to be supported on HP 10 x 42

    steel piling driven to a minimum bearing valueof 55 tons per pile.

    Estimated Length 70 feet.

    New Language

    Abutments to be supported on HP 10 x 42

    steel piling driven to a Required DrivingResistance of 275 tons per pile as determined

    by the modified Gates dynamic formula.

    Estimated Length 70 feet.

    New Language for General Plan Notes

    The factored axial resistance of piles in

  • 8/9/2019 Geo Lrfd Jeffh

    46/51

    The factored axial resistance of piles in

    compression used for design is the requireddriving resistance multiplied by a resistance

    factor of 0.4 using the modified Gates

    dynamic formula to determine driven pile

    capacity.

    New Pile Driving Specification

  • 8/9/2019 Geo Lrfd Jeffh

    47/51

    Purpose: To revise the currentspecification, which has three sections

    •508 Timber Piling•510 Cast in Place Concrete Piling

    •511 Steel Piling

    to one comprehensive specification

    •508 Driven Piles (modified Gates or

    WEAP)

    Why make the Change ?

  • 8/9/2019 Geo Lrfd Jeffh

    48/51

    1. The old specification is written forwood piles and then steel piles.

    2. The old specification uses the

    modified ENR formula to determine an

    allowable bearing, FS could ranged

    from 0.6 to 20.3. The old specification does little to

    address the pile driving system.4. The old specification do not discuss

    pre-cast concrete piles.

    5. Pile specification are over threesections

  • 8/9/2019 Geo Lrfd Jeffh

    49/51

    Pile Hammer 

    System

    WisDOT Contacts ?

  • 8/9/2019 Geo Lrfd Jeffh

    50/51

    Scott Becker, Structure [email protected]

    608-266-5161

    Bob Arndorfer, Geotechnical Unit

    [email protected]

    Jeff Horsfall, Geotechnical Unit

     [email protected]

    608-243-5993

  • 8/9/2019 Geo Lrfd Jeffh

    51/51

    Questions and Comments