geotek alaska, inc. v. jacobs engineering group, inc., alaska (2015)

Upload: scribd-government-docs

Post on 01-Mar-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    1/24

    Notice: This opinion is subject to correction before publication in the PACIFICREPORTER.

    Readers are requested to bring errors to the at tention of the Clerk of the Appel late Courts,

    303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, em ail

    [email protected].

    THESUPREMECOURTOFTHESTATEOFALASKA

    GEOTEKALASKA,INC.,

    Appellant,

    v.

    JACOBSENGINEERINGGROUP,

    INC.,andJACOBSFIELDSERVICESNORTHAMERICA,

    INC.,

    Appellees.

    )

    ) SupremeCourtNo.S-15449

    SuperiorCourtNo.3AN-12-05453

    OPINION

    No.7031-August14,2015

    )

    ) CI

    )

    )

    )

    ))

    )

    )

    )

    )

    AppealfromtheSuperiorCourtoftheStateofAlaska,Third

    JudicialDistrict,Anchorage,ErinB.Marston,Judge.

    Appearances: Michael Jungreis and Jason Hartz, Davis

    WrightTremaineLLP,Anchorage,forAppellant.RobertJ.

    DicksonandChristopherJ.Slottee,Atkinson,Conway&

    Gagnon,Anchorage,forAppellees.

    Before:Fabe,ChiefJustice,Winfree,Stowers,Maassen,and

    Bolger,Justices.

    MAASSEN,Justice.

    I. INTRODUCTION

    Aninsolventsubcontractorfailedtopayitssub-subcontractorforwork

    performed, and the sub-subcontractor sought payment directly from the general

    contractor through a demand for arbitration. The general contractor declined to

    mailto:[email protected]:[email protected]
  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    2/24

    participate. Thearbitrator awarded damages to the sub-subcontractor,who filedan

    actiontoconfirmtheawardinsuperiorcourt.Thesub-subcontractoralsobroughta

    negligenceclaim,contendingthatthegeneralcontractorknewofitssubcontractors

    financialinstabilityandnegligentlyfailedtoensurethatthesub-subcontractorwouldbe

    paid.Thesuperiorcourtgrantedsummaryjudgmenttothegeneralcontractoronboth

    theenforceabilityofthearbitrationawardandtheviabilityofthenegligenceclaim. The

    sub-subcontractorappeals.

    We affirm, concluding that whether the general contractor effectively

    exerciseditscontractualrighttodeclinearbitrationisanissueofarbitrability,correctly

    decidedbythesuperiorcourt,andthatthegeneralcontractorhadnoextra-contractual

    dutyintorttoguaranteeitssubcontractorspaymentobligations.

    II. FACTSANDPROCEEDINGS

    A. Facts

    JacobsEngineeringGroup,Inc.wasawardedacontractbytheUnited

    StatesAirForceforenvironmentalremediation. Whilepreparingtobidontheproject,

    JacobsEngineeringGroupanditssubsidiaryJacobsFieldServicesNorthAmerica,Inc.

    (collectivelyJacobs)sentoutarequestforproposal(RFP)forsoilsamplingservices

    atatankfarmnearNomeandattheNikolskiRadioStationonUmnakIsland.Included

    in the RFP was a requirement that the subcontractor have bonding tocoverall its

    payment and performance obligations. One of the recipients of Jacobss RFP was

    PrecisionSampling, Inc.,doingbusinessasDirectSensing, Inc. (DSI). Ultimately

    JacobsawardedthesubcontracttoDSI.DSIenteredintoasecond-tiersubcontractwith

    GeoTek Alaska, Inc., to provide the required Ultra-Violet Optical Screening Tool(UVOST)equipment.

    DSIsparentcorporationinCanadawasundergoingfinancialdifficulties

    atthetimeofthebiddingprocess;thepartiesdisputewhatJacobskneworshouldhave

    -2- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    3/24

    knownaboutDSIssituation. TheyalsodisputetheextenttowhichJacobssawardof

    the subcontract toDSIwasbecauseof Jacobssdesire to work withGeoTek. It is

    undisputed,however,thatDSIwasunabletoobtainthepaymentandperformancebonds

    requiredbytheRFPandaskedJacobstowaivetherequirement.Jacobsagreedtomove

    forwardwiththeDSIsubcontract,butitdevelopedariskmanagementplanrequiringthat

    15percentofJacobsspaymenttoDSIberetainedto assure thepaymentofDSIs

    second-tiersubcontractorsandthatthosesecond-tiersubcontractorssubmitreleasesof

    claims,certifyingtheyhadbeenpaid.

    ShortlybeforeGeoTekdeployedtotheNomeprojectlocation,itlearned

    thatJacobshadwaiveditsrequirementthatDSIbebonded.GeoTeknonethelesssigned

    itssecond-tiersubcontractwithDSIafewdayslater. Accordingtoitsvicepresidents

    affidavit,[a]tthatpointGeoTekwascommitted,andhadnootherworkavailableon

    shortnotice;andadditionallywasreassuredbyJacobsspolicyofensuringthatitslower

    tiersubcontractorsarepaid.

    DSIandGeoTeksatisfactorilycompletedtheNomeproject. Jacobspaid

    DSIand DSIsigneda release inSeptember2009,certifying that ithad paid forall

    servicesfurnishedinconnectionwiththecontract.Jacobsdidnotretainanyamountsor

    require a release from GeoTek, ascontemplated by the riskmanagement plan. In

    September2009,DSIandGeoTekattempteddeploymenttoNikolskibutweredelayed

    inDutchHarborbecauseofweather. Theprojectwaseventuallyputoffuntil2010but,

    forreasonsnotrelevanttothisappeal,DSIandGeoTekneverreachedNikolskiand

    neverdidanyworkthere.

    DSIdidnotpayGeoTekforitsworkontheNomeprojectorforits2009mobilizationforNikolski.

    -3- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    4/24

    B. Proceedings

    JacobsscontractwithDSIincludedanarbitrationprovisionthatiscentral

    tothisappeal. Theprovisionslanguagewillbedissectedlaterinthisopinion,butin

    summaryitgivesJacobstheunilateralrighttoacceptorrejectarbitrationonceademand

    hasbeenmade. JacobsdidnothaveacontractwithGeoTek,butJacobsscontractwith

    DSIincludedaprovisionthatrequiredDSItoflowdownalltermsandconditionsof

    thesubcontractintoanysub-subcontract.TheJacobs-DSIcontractalsohadaprovision

    onassignment,whichprovides:

    Neither thisSubcontract noranyinterest therein including

    anyclaimthereundershallbeassignedortransferredbythe

    Subcontractor to another entity, except as expresslyauthorized in writing by the Subcontract Manager. The

    Company reserves the exclusive right to assign this

    Subcontractandallrightsandinteresttherein.

    InademandforarbitrationdatedApril28,2010,GeoTekassertedaclaim

    againstJacobsfortheamountsDSIhadfailedtopayit.1 Thedemandwasapparently

    forwardedtoJacobsbytheAmericanArbitrationAssociation(AAA).Jacobsresponded

    toGeoTeksdemandforarbitrationonMay13,assertinginalettertotheAAAthat

    JacobsdoesnothaveacontractwithGeoTekandtherefore,GeoTekhasnobonafide

    contract claim against Jacobs and it would be inappropriate for Jacobs to engage

    GeoTekinanarbitrationproceeding. JacobsstatedthatitrejectsGeoTeksdemand

    forarbitrationandrecommendsthatGeoTekpursueitscontractualrightsandclaims

    againstitscustomer,[DSI].

    GeoTekproceededalonewitharbitrationundertheaegisoftheAAA. On

    January20,2011,DSIandGeoTekexecutedanagreementinwhichtheyassertedthat

    GeoTeksarbitrationdemandisnotintherecord,butneitherpartydisputes

    thatitwasmade;itsdateisreferencedinJacobssresponse.

    -4- 7031

    1

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    5/24

    [n]eitherDSI[norGeoTekhas]beenpaidinfullbyJacobsfortheworkdoneonthe

    WestNomeorNicolski[sic]ProjectsandDSIassigneditsclaimsagainstJacobsto

    GeoTek,retainingarightto30percentofanyamountscollected. OnGeoTeksmotion,

    thearbitratorthenruledonthearbitrabilityoftheseclaims,decidingthatbothGeoTeks

    originalclaimsagainstJacobsandDSIsassignedclaimswerearbitrable.Thearbitrator

    allowedGeoTektoamenditsdemandforarbitrationtoincludebothsetsofclaimsand

    gaveJacobs14daystorespondtotheamendeddemand. Therecordshowsnofurther

    writtenresponsefromJacobs.

    ThearbitratorheldanevidentiaryhearinginAugust2011,whichwas

    attendedonlybyrepresentativesofGeoTekandDSI;thearbitratorsfindingsoffactand

    conclusionsoflawnotethatJacobswasagaincontactedbutdeclinedtoparticipate. The

    arbitratorawardedGeoTek$257,687.62onbehalfofworkdonebyGeoTekAlaskaand

    [DSI],withinterestcontinuingtoaccrueat10.5percentperannum.

    GeoTek filed a complaint in superior court seeking to confirm the

    arbitration award and asserting several other theories of recovery against Jacobs,

    includingbreachofcontract,unjustenrichment,quantummeruit,andbreachofthe

    covenantofgoodfaithandfairdealing.Jacobsansweredandmovedforsummary

    judgment,arguingthatithadnocontractwithGeoTekand,ifitdid,ithadeffectively

    exercised itscontractualrighttorefusetoarbitrate. GeoTekfileda cross-motionto

    confirmthearbitrationaward.ThesuperiorcourtgrantedJacobsssummaryjudgment

    motion,concludingthatJacobstimelyrejectedGeoTeksdemandtoarbitrate...[and

    that]Jacobswasnotlegallyobligatedtoparticipateinthearbitration.

    Whilethecourtsdecisionofthesemotionswaspending,GeoTekamendeditscomplainttoassertanegligenceclaim. Jacobsmovedforsummaryjudgmentonthat

    claimaswell,andthesuperiorcourtgrantedsummaryjudgmentonthegroundthat

    JacobsdidnotoweGeoTekadutyofcareintorttoensureitwaspaidbyDSI.

    -5- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    6/24

    OnappealGeoTekarguesthatthesuperiorcourterredingrantingJacobss

    motionsforsummaryjudgment. GeoTekarguesthat(1)ithadanagreementtoarbitrate

    withJacobs,anditwasuptothearbitratortodecidewhetherJacobshadexercisedits

    right to reject arbitration; and (2) Jacobs had an actionable duty in tort to protect

    GeoTeksfinancialinterests.

    III. STANDARDSOFREVIEW

    Asuperiorcourtsdecisionreviewinganarbitrationawardissubjectto

    denovoreview.2 Whether[a]claimisarbitrableisaquestionoflawsubjecttode

    novoreview.3Theexistenceandextentofadutyofcarealsopresentsaquestionof

    law,whichwereviewdenovo.4

    IV. DISCUSSION

    A. TheSuperiorCourtDidNotErrInGrantingSummaryJudgmentTo

    JacobsOnTheArbitrabilityIssue.

    ThesuperiorcourtcorrectlydecidedthatwhetherJacobshadagreedto

    arbitratethisdisputewasaquestionforthecourtratherthanthearbitrator.Thesuperior

    courtthenreliedonthespecificlanguageofthearbitrationprovisionatissuetoconclude,

    againcorrectly,thatJacobsdidnotagreetoarbitratethisdisputeandthat theawardthereforecouldnotbeconfirmed.

    2 Johnson v. Aleut Corp.,307P.3d942,947(Alaska2013).

    3 Lexington Mktg. Grp., Inc. v. Goldbelt Eagle, LLC,157P.3d470,472

    (Alaska2007).

    4 Hurn v. Greenway,293P.3d480,483(Alaska2013).

    -6- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    7/24

    Forpurposesofargumentweassume,asthesuperiorcourtapparentlydid, 5

    thatthearbitrationprovisionintheJacobsscontractwithDSIfloweddownandby

    flowingdowngovernedtherelationshipbetweenJacobsandGeoTekaswell.

    1. WhetherJacobsagreedtoarbitratethedisputewasaquestionforthecourt,notthearbitrator.

    6TheFederalArbitrationAct andAlaskasUniformandRevisedUniform

    7 8ArbitrationActs allreflectastrongpolicyinfavorofthearbitrationofdisputes. Like

    federal law, Alaskas statutes provide that [a]n arbitrator shall decide whether a

    conditionprecedenttoarbitrabilityhasbeenfulfilled. 9Alaskasstatutesalsoprovide,

    however,that[t]hecourtshalldecidewhetheranagreementto arbitrateexistsora

    5 Atoral argumenton Jacobss first motion for summary judgment, the

    superiorcourtaskedcounselforJacobswhetheritwasJacobsspositionthatevenif

    therewasaflow-down,aforcibleflow-downprovision,...thatitdoesntreallymatter,

    becausewithin30daystheyhavethesolerighttoacceptorreject[,][a]nd,inthiscase,

    theyunequivocallyrejectedthearbitration.ThecourtlateraskedcounselforGeoTek

    whetheritwashispositionthateveniftherewasanassignmentoraflowdown,thatdoesntchangethetermsofthearbitrationclause...thatJacobswouldstillhavethe

    right toarbitrate ornot, at their discretion. Both counsel agreed with the courts

    characterizationsoftheirclientspositions.

    6 9U.S.C.1etseq.(2012).

    7 AS09.43.010 .180 (UniformArbitration Act); AS09.43.300 .595

    (RevisedUniformArbitrationAct).

    8

    Gibson v. Nye Frontier Ford, Inc.,205P.3d1091,1096(Alaska2009).9 AS09.43.330(d);see BG Grp., PLC v. Republic of Argentina,134S.Ct.

    1198,1207(2014)(citationsomitted)(explainingthatcourtspresumethattheparties

    intendarbitrators,notcourts,todecidedisputesaboutthemeaningandapplicationof

    particularproceduralpreconditionsfortheuseofarbitration).

    -7- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    8/24

    controversyissubjecttoanagreementtoarbitrate,10mirroringfederallawthatcourts

    aretheproperforumtodeterminewhetheradisputeisarbitrable. 11Onereasonforthis

    divisionofauthorityis[that][b]ecausearbitratorshavesuchbroaddiscretion,itisoften

    problematicforthemtodecidetheirownjurisdiction,foriftheyarewrong,theremay

    beessentiallynoreviewbecauseoftheextremedeference[thatacourtwillgive]to

    thearbitrator.12

    The first question wemust answer in thiscase,therefore, iswhether

    Jacobssconsentwasnecessarybeforeaparticulardisputecouldbesubjectto[the]

    agreement to arbitrate in which case the issue is one of arbitrability under

    AS09.43.330(c),andthequestionofconsentwasforthesuperiorcourttodecide;or,on

    theotherhand,whetherJacobssconsentwasaconditionprecedenttoarbitrability

    inwhichcasethequestionofconsentwasuptothearbitratorunderAS09.43.330(d).

    The United States Supreme Court recently described this dichotomy in terms of

    presumptionsthathelpcourtsdeterminepartiesintentifthecontractissilentonthe

    matter of who primarily is to decide threshold questions about arbitration.13

    According to the Court, parties are presumed to intend that courts will decide

    arbitrabilityissuessuchaswhetherthepartiesareboundbyagivenarbitration

    clause,orwhetheranarbitrationclauseinaconcededlybindingcontractappliestoa

    10 AS09.43.330(c).

    11 Lexington Mktg. Grp., Inc. v. Goldbelt Eagle, LLC,157P.3d470,477

    (Alaska2007).

    12 Classified Emps. Assn v. Matanuska-Susitna Borough Sch. Dist.,204P.3d

    347,353(Alaska2009)(quotingFairbanks Fire Fighters Assn, Local 1324 v. City of

    Fairbanks,48P.3d1165,1169(Alaska2002))(internalquotationmarksomitted).

    13 BG Grp., PLC,134S.Ct.at1206.

    -8- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    9/24

    particulartypeofcontroversy.14 Ontheotherhand,partiesarepresumedtointendthat

    arbitratorswilldecidedisputesaboutparticularproceduralpreconditionsfortheuseof

    arbitration,whichmayincludewhetherprerequisitessuchastimelimits,notice,laches,

    estoppel, and other conditions precedent to an obligation to arbitrate have been

    satisfied.15

    Werecognizethatsomeconditionsprecedentcanreadilyberecharacterized

    asquestionsofarbitrability;apartycouldargue,forexample,thatithasagreedto

    arbitrateonlythosedisputesthataresubmittedtoarbitrationbyacertaintime,orona

    certainform,oratacertainaddressraisingissuesofarbitrabilitythatclearlyhinge

    on the determination of what are actually procedural preconditions. For a cogent

    explanationofhow todifferentiatethetwo,Jacobsdirectsus toRockland County v.

    Primiano Construction Co.16 In that case the Court of Appeals of New York,

    recognizingthat[w]hethertheparticularrequirementfallswithinthejurisdictionofthe

    courtsorofthearbitratorscouldbereducedtoagameofsemantics,explainedthatthe

    realdifferencedependson[therequirements]substanceandthefunctionitisproperly

    perceivedasplayingwhetheritisinessenceaprerequisitetoentryintothearbitration

    processoraproceduralprescriptionforthemanagementofthatprocess.17Thecourt

    notedthattheparties,bycontract,mayhaveerectedaprerequisitetothesubmissionof

    anydisputetoarbitration,ineffectapreconditiontoaccesstothearbitralforum,and

    14 Id. (quotingHowsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84

    (2002)).

    15 Id.at1206-07(internalfootnotes,citations,andinternalquotationmarksomitted).

    16 409N.E.2d951(N.Y.1980).

    17 Id.at954.

    -9- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    10/24

    that[i]nsucheventthereluctantpartymaybeforcedtoarbitrationonlyifthecourt

    determinesthatthisportionoftheagreementhasbeencompliedwith. 18Itcitedanother

    casewithparallelstothisone:Opan Realty Corp. v. Pedrone,inwhichapartnership

    agreementstipulatedthatanydisputewouldbedecidedbytheAmericanArbitration

    Associationbutthatadisputeshallnotbedeterminedtoexistthereunderuntilthe

    matterisfirstsubmittedfordeterminationtothepartnership,whichcouldresolvethe

    matterbyan80percentvote.19 ThecourtinOpan Realty heldthatwhetherthiscondition

    hadbeenfulfilledwasaquestionatleastinitiallyforthecourt,notthearbitrator. 20

    AndthecourtinRockland Countyconcluded: Beyondthatitistoberememberedthat

    inasmuchastheentirearbitrationprocessisacreatureofcontract,thepartiesbyexplicit

    provisionoftheiragreementhavetheabilitytoplaceanyparticularrequirementinone

    categoryortheother. 21

    TheUnitedStatesSupremeCourtundertookasimilaranalysisinHowsam

    v. Dean Witter Reynolds, Inc., in which it categorized all threshold questions as

    gatewayquestionsthatcanbesortedintoquestionsofarbitrabilitydecidedbythecourt

    andproceduralquestionsdecidedbythearbitrator.22 LikethecourtinRockland County,

    theSupremeCourtrecognizedthatthesemanticdifficultyindrawingtheboundary

    betweenthetwotypesofgatewayquestionsisbestresolvedbydeterminingwhetherthe

    18 Id.(footnoteomitted).

    19 335N.E.2d854,855(N.Y.1975).

    20 Id.

    21 409N.E.2dat955. Notably,theNew YorkCourtofAppealsusedan

    earlierformulationoftherelevantdichotomy,inwhichquestionsofarbitrability,rather

    thanproceduralpreconditions,weretermedconditionsprecedent. Id.at954-55.

    22 537U.S.79,83-85(2002).

    -10- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    11/24

    particularquestionatissueisofatypethatthepartieswouldlikelyexpecttobedecided

    byanarbitratororajudge:

    TheCourthasfoundthephrase[questionofarbitrability]

    applicable in the kind of narrow circumstance where

    contractingpartieswouldlikelyhaveexpectedacourttohave

    decidedthegatewaymatter,wheretheyarenotlikelytohave

    thoughtthattheyhadagreedthatanarbitratorwoulddoso,

    and,consequently,wherereferenceofthegatewaydisputeto

    the court avoids the risk of forcing parties to arbitrate a

    matterthattheymaywellnothaveagreedtoarbitrate.

    ....

    At the same time the Court has found the phrase

    questionofarbitrabilitynotapplicableinotherkindsofgeneralcircumstancewherethepartieswouldlikelyexpect

    thatanarbitratorwoulddecidethegatewaymatter. Thus

    proceduralquestionswhichgrowoutofthedisputeand

    bearon its final disposition arepresumptivelynotforthe[ ]judge,butforanarbitrator,todecide.23

    Withinthisgeneralframeworkweseektodeterminewhatthepartiestothe

    Jacobs-DSIcontractcouldreasonablyhaveexpectedfromthespecificlanguagethey

    usedtodescribethearbitrationoption.Weresolveambiguitiesinfavorofarbitrability

    where such construction is not obviously contrary to the parties intent.24 But

    [b]ecausearbitrationisacreatureofcontract,partiescanonlybecompelledtoarbitrate

    amatterwhentheyhaveagreedtodoso.25Accordingly,ifadisputeisnot,undera

    plausible interpretation,coveredunderthearbitrationclauseofa[n] ...agreement,it

    23 Id.at83-84(emphasisinoriginal)(internalfootnotesandcitationsomitted).

    24 Lexington Mktg. Grp., Inc. v. Goldbelt Eagle, LLC,157P.3d470,476

    (Alaska2007)(quotingUniv. of Alaska v. Modern Constr., Inc.,522P.2d1132,1138

    (Alaska1974)).

    25 Id.at477.

    -11- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    12/24

    shouldnotbearbitratedbecauseapartycannotberequiredtosubmittoarbitrationany

    disputewhichhehadnotagreedsotosubmit. 26Wearethereforerequiredtovacate

    anarbitrationawardifwefindthattherewasnotanagreementtoarbitrate. 27

    TheDisputesonClaimssectionoftheJacobs-DSIcontractbeginswith

    thesubcontractorsagreementtofirstsubmitanyclaimordisputearisingunder,related

    toor inconnectionwith theWork, thisSubcontract,or theProject, toCompany in

    writingpriortoinitiatinganylegalorotherdisputeprocedure.Afewparagraphslater

    thearbitrationprovisionreads,inrelevantpart:

    All claims, disputes and other matters in question

    betweenSubcontractorandCompanyarisingoutoforrelated

    totheWork,thisSubcontractortheProject...shall, at thesole option of the Company,bedecidedbyarbitration.In the

    event the Company elects to have the matter resolved through

    arbitration,then atCompanysdirection,Subcontractorshall

    submitthemattertotheAmericanArbitrationAssociationfor

    processing under the appropriate Industry Rules of the

    AmericanArbitrationAssociationthenineffect.Ifaclaim

    is made, or a demand for arbitration is filed, by

    Subcontractor,Company will adviseSubcontractorwithin

    thirty30days[sic]afterthereceiptofsuchademandfor

    arbitration...,if Company exercises the option to arbitrate

    or rejects arbitration; such election, once made, shall be[ ]binding. 28

    Weconcludethatthisprovisionisunambiguous.TheonlyclaimsJacobshasagreedto

    arbitrateare those itelects,on acase-by-casebasis, tohavedecidedby arbitration.

    26 Classified Emps. Assn v. Matanuska-Susitna Borough Sch. Dist.,204P.3d

    347,353(Alaska2009)(quotingAT & T Techs., Inc. v. Commcns Workers of Am.,475U.S.643,648(1986)).

    27 AS09.43.500(a)(5).

    28 Emphasisadded.

    -12- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    13/24

    ArbitrationofanyclaimwilloccuratJacobsssoleoption,whichJacobswillexercise

    within30daysofreceivingademand.Jacobsselection,oncemade,isbinding.And

    it isonly [i]n the event [that] [Jacobs]elects tohave the matter resolved through

    arbitration that the matter will then be referred to the American Arbitration

    AssociationforprocessingundertheAAArules.

    Jacobssconsenttoarbitrateanyparticulardisputeisnotamereprocedural

    preconditionto arbitrability, such as time limits, notice, laches, estoppel, andother

    conditionsprecedenttoanobligationtoarbitrate.29Jacobsagreedtoarbitratealimited

    categoryofdisputes:thoseitidentified,onacase-by-casebasis,asdisputesitwas

    willingtosubmittoarbitration. TheissueofJacobssconsentthereforepresenteda

    questionofarbitrabilitywhether[the]controversyissubjectto[the]agreementto

    arbitrateandwasproperlyforthecourttodecide. 30

    2. ThesuperiorcourtcorrectlyheldthatJacobsdidnotagreeto

    arbitrateGeoTeksclaim.

    GeoTekapparentlydemandedarbitrationonApril28,2010.31Although

    it is not apparentfromtherecordwhenJacobs receivedGeoTeks demand,Jacobs

    respondedon May 13,2010,wellwithin 30days of the demandsdate. Jacobss

    response was unequivocal: Jacobs rejects Geo Teks demand for arbitration and

    recommendsthatGeoTekpursueit[s]contractualrightsandclaimsagainstitscustomer,

    [DSI]. Jacobssresponsecouldnotreasonablyhavebeenmisunderstood.Itsclearand

    29 See BG Grp., PLC v. Republic of Argentina,134S.Ct.1198,1207(2014)

    (internalquotationmarksandcitationomitted).

    30 AS09.43.330(c).

    31 Asnotedabove,JacobssresponsetotheAmericanArbitrationAssociation

    referencedtheAssociationsMay5,2010letterandGeoTeksApril28,2010demand.

    -13- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    14/24

    unequivocaldecision nottoarbitratewas,accordingtothecontract,bindingonthe

    parties.

    3. GeoTeksargumentsareunpersuasive.

    GeoTekcontendsthattherequirementofJacobssconsenttoarbitrationis

    notadeterminantofarbitrabilitybutratheraconditionprecedenttoarbitration,likethe

    others time limits, notice, laches, and estoppel that courts have left for the

    arbitratorsdetermination. GeoTekalsoassertsthatthesuperiorcourtfailedtoengage

    in the limited arbitrability inquiry allowed under Alaska law because the courts

    decisionwasnotlimitedtowhetherthepartieshadanarbitrationagreementorwhether

    itcoveredthepartiesdispute.GeoTekarguesthatJacobssletter[rejectingarbitration]

    didnotabsolveitofanyobligationtoparticipateinthearbitrationbecauseitwas

    necessaryforJacobs toparticipatein thearbitrationto theextentitobjectedto the

    arbitrators exercise of jurisdiction. Finally, GeoTek argues that even if Jacobss

    rejectionpresentedanissueofarbitrability,thesuperiorcourtshouldnothaveaddressed

    itbecausethepartieshadexplicitlydelegatedarbitrabilitydeterminationstothearbitrator

    throughtheirincorporationoftheAAAIndustryRules.

    Asexplainedabove,discerningthepartiesintentisourparamountconcern

    whenwearedecidingwhetherconsenttoarbitrationpresentsaquestionofarbitrability

    oraproceduralconditionprecedent.32 Wehaverepeatedlyrecognizedthat[b]ecause

    arbitrationisamatterofcontract,partiescanonlybecompelledtoarbitrateamatter

    wheretheyhaveagreedtodoso.33Thus,iftherearetermsinacontractthateither

    excludearbitrationorindicatethatanissueshouldnotbesubjecttoarbitration,then

    32 Lexington Mktg. Grp., Inc. v. Goldbelt Eagle, LLC,157P.3d470,478

    (Alaska2007)(providingforarbitrationwhenitisconsistentwiththepartiesintent).

    33 Id.at477.

    -14- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    15/24

    requiringthatthematterbesenttoarbitrationwouldbeinappropriate.34 Inthiscasewe

    areconvinced that the plain languageof thearbitration provisiondemonstrates the

    parties intent that Jacobs decide unilaterally whether any given dispute will be

    arbitrated;thatis,adisputesarbitrabilityisdeterminedbywhetherJacobsagreesto

    arbitrateit.Werespectthepartieschoiceoflanguage.ToadoptGeoTeksposition

    insteadwouldbetoholdthatapartythathasbargainedforthecontractualrighttoavoid

    arbitrationatitssoleoptionmustinfactarbitrateinordertovindicatethatrightwith

    noprospectofdenovojudicialreview.

    GeoTek also argues that the parties arbitration provision expressly

    providesthatdisputesshallberesolvedaccordingtotheappropriateIndustryRulesof

    theAmericanArbitrationAssociationandthattheserulesgivethearbitratorthepower

    toruleon his orher ownjurisdiction, including any objections with respect tothe

    existence,scope,orvalidityofthearbitrationagreement. 35 Weneednotdecidewhat

    theAAAIndustryRuleswouldrequireinthiscase,becausewedisagreewithGeoTeks

    assertionthattheygoverntheprocedurethepartieshaveadoptedfortheinitiationof

    arbitration.

    Thepresumptionthatarbitrabilityisaquestionforthecourtscanonlybe

    rebuttedifthepartieshave clearlyandunmistakablyprovide[d]otherwise.36 The

    arbitrationprovisionatissuehereplainlystatesthatamattershallbesubmittedtothe

    AmericanArbitrationAssociationforprocessingundertheappropriateIndustryRules

    34 Classified Emps. Assn v. Matanuska-Susitna Borough Sch. Dist.,204P.3d

    347,353(Alaska2009).

    35 See Am.ArbitrationAssn,Comm.ArbitrationRule7(a)(2013).

    36 State v. Pub. Safety Emps. Assn,798P.2d1281,1285(Alaska1990)

    (quotingAT & T Techs., Inc. v. Commcns Workers of Am.,475U.S.643,649(1986)).

    -15- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    16/24

    oftheAmericanArbitrationAssociationthenineffectonly[ i]n the event [Jacobs]

    elects to have the matter resolved through arbitration;ifJacobssoelects,thenthe

    matterwillbesubmittedtotheAAAat[Jacobss]direction.37Underthecontracts

    explicitlanguage,theAAArulescomeintoplayonlyafterJacobshasagreedtosubmit

    aclaimtoarbitrationwhichinthiscaseitrefusedtodo. 38 Thepartiesdidnotclearly

    andunmistakablyprovidethatthearbitratordeterminequestionsofarbitrability,but

    rathertheopposite. 39

    B. TheSuperiorCourtDidNotErrInGrantingSummaryJudgmentTo

    JacobsOnGeoTeksNegligenceClaims.

    GeoTekalsoappealsfromthesuperiorcourtsgrantofsummaryjudgment

    toJacobsonGeoTeksnegligenceclaims.GeoTekallegedinitsamendedcomplaintthat

    JacobswasresponsibleforDSIspaymentstoGeoTekbecauseofJacobssnegligent

    failure (1) torequireDSI to post a performance bond toensure the paymentof its

    subcontractors,asrequiredbyJacobssformcontract;(2)tofollowtheprovisionsofits

    proposedriskmanagementplanregardinga15percent retainageand signedreleases

    fromDSIssecond-tiersubcontractors;and(3)toinformGeoTekthatithadnottaken

    thesesteps.Thesuperiorcourtfoundnosupportinthecontract,instatutes,orinthe

    37 Emphasisadded.

    38 See Opan Realty Corp. v. Pedrone,335N.E.2d854,855(N.Y.1975)

    (holdingthatwherepartnershipagreementstatedthatanydisputewouldbedecidedby

    theAmericanArbitrationAssociationbutmustfirstbesubmittedtothepartnershipfor

    consideration,whetherthispreconditionhadbeensatisfiedwasamatterforthecourt).39 We necessarily reject GeoTeks additional argument that the claims

    assignedtoitbyDSIwereseparatelyarbitrable.ArbitrabilitydependedonJacobss

    electiontoarbitrate,whichitnevermadewithregardtoanyoftheclaimsatissue,

    whetherdirectorassigned.

    -16- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    17/24

    commonlawfortheimpositionofanegligencedutyonJacobs. Weconcludethatthe

    superiorcourtdidnoterr.

    1. ThesuperiorcourtcorrectlyheldthatJacobsdidnothavean

    extra-contractualdutytoprotectGeoTekagainsttheriskof

    nonpaymentbyDSI.

    Todeterminewhetheradefendantowesaplaintiffadutyofreasonable

    care,wefirstdeterminewhetheradutyisimposedbystatute,regulation,contract,

    undertaking,thepartiespreexistingrelationship,orexistingcaselaw.40Ifthese

    sources do not resolve the issue, we apply the multi-factor approach discussed in

    D.S.W....todeterminewhetheranactionabledutyexists. 41Theso-calledD.S.W.

    factorsaresevenpublicpolicyconsiderationsweusetodeterminewhetherweshould

    recognizeanegligencedutynototherwisedefinedbylaw.42

    40 McGrew v. State, Dept of Health & Soc. Servs., Div. of Family & Youth

    Servs.,106P.3d319,322(Alaska2005)(footnoteomitted).

    41 Id.(citingD.S.W. v. Fairbanks N. Star Borough Sch. Dist.,628P.2d554,

    555(Alaska1981)).

    42 TheD.S.W.factorsare:

    The foreseeability of harm to the plaintiff, the degree of

    certaintythattheplaintiffsufferedinjury,theclosenessofthe

    connectionbetweenthedefendantsconductandtheinjury

    suffered, the moral blame attached to the defendants

    conduct,thepolicyofpreventingfutureharm,theextentof

    the burden to the defendant and consequences to the

    communityofimposingadutytoexercisecarewithresultingliabilityforbreach,andtheavailability,costandprevalence

    ofinsurancefortheriskinvolved.

    D.S.W.,628P.2dat555(quotingPeter W. v. San Francisco Unified Sch. Dist.,131Cal.

    Rptr.854,859-60(Cal.App.1976)).

    -17- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    18/24

    Foritsimpositionofadutyinthiscase,GeoTekreliesonMattingly v.

    Sheldon Jackson College.43InMattingly weheldthatadefendantowesadutyofcare

    totakereasonablemeasurestoavoidtheriskofcausingeconomicdamages,asidefrom

    physicalinjury[orpropertydamage],toparticularplaintiffsorplaintiffscomprisingan

    identifiableclass[ofpersonswho]defendantknowsorhasreasontoknowarelikelyto

    suffer such damages from its conduct.44 GeoTek contends that [i]n accord with

    Mattingly,...JacobssawarenessofGeoTekcombinedwithitsknowledgethatGeoTek

    couldsuffer[the]economicharmofnotbeingpaidbyDSIiswhatgaverisetoaduty.

    ButGeoTekmisinterpretsourholdinginMattingly. Mattingly didnot

    createanewdutyintort,letaloneonesobroadastoprovideanegligencecauseof

    action for any foreseeable economic harm caused by anothers lack of due care.

    Mattingly simply expanded liability in tort to include purely economic losses; this

    marked asignificantdeparturefrom thelong-standingvirtuallyper se rulebarring

    recoveryforeconomiclossunlessthenegligentconductalsocausedphysicalharm.45

    AfterMattingly wehaveneverheldthatforeseeableeconomicharmtoan

    identifiableplaintiffisallthatisrequiredtoestablishadutyofcare. 46Forexample,in

    Mesiar v. HeckmanweconsideredwhethertheAlaskaDepartmentofFishandGame

    43 743P.2d356(Alaska1987).

    44 Id.at360(quotingPeople Express Airlines, Inc. v. Consol. Rail Corp.,495

    A.2d107,116(N.J.1985))(firstalterationinMattingly;secondalterationadded).

    45 Id.at359(quotingPeople Express,495A.2dat109).

    46

    AfederalcourtrecognizedthisinU.S. ex rel. N. Star Terminal & StevedoreCo. v. Nugget Constr., Inc., 445 F. Supp. 2d 1063, 1076 n.42 (D. Alaska 2006)

    (Mattingly ...standsforthepropositionthatapartythatisonlyeconomicallyinjured

    cannonethelesssuefornegligence,so long as a duty exists.Itdefinestheparametersof

    anexistingdutyanddoesnot,asPlaintiffsimply,imposeanewdutywherethere

    otherwisewouldbenone.)(emphasisadded).

    -18- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    19/24

    couldbeliableonclaimsithadnegligentlymiscountedasalmonrun,therebycausing

    unnecessary restrictionson certainYukonRiverfisheriesandeconomicharmto the

    plaintiffs.47Todeterminewhetheranactionabledutyofcareexist[ed]weturnedtothe

    D.S.W. factors.48InourdiscussionofthefirstD.S.W. factortheforeseeabilityof

    harmwecitedMattinglyforthepropositionthatforpurelyeconomicharm,the

    identifiableclassofplaintiffsmustbeparticularlyforeseeableinnumber,type,and

    economicexpectations.49 WeagreedwiththeplaintiffsthattheDepartmentsclosure

    decisionspredictablyandspecificallyharmedusers[includingtheplaintiffs].50 But

    notingthatanyfisheries-managementactionthatharmsoneusergroupmayfavorothers,

    weconcludedthattheforeseeabilityofharmto[theplaintiffs]isnotadispositive

    factorindeterminingtheexistenceofatortdutyandwentontoweightheremaining

    D.S.W. factors.51WeultimatelyconcludedthattheDepartmentowednoactionableduty

    totheplaintiffsaconclusionwewouldnothavereachedifallthatisrequiredunder

    Mattingly foradutytoexististheforeseeabilityofeconomicharmtoanidentifiable

    plaintiff.52

    47 964P.2d445,448-49(Alaska1998).

    48 Id. at450(citingD.S.W. v. Fairbanks N. Star Borough Sch. Dist.,628P.2d

    554,555(Alaska1981)).

    49 Id.

    50 Id.

    51

    Id.

    52 Id. at452;see also Lynden Inc. v. Walker,30P.3d609,614(Alaska2001)

    (summarizingMesiar and noting that in that case, [d]espite the foreseeability of

    economicinjurytofishermenifdatawasimproperlycollected,wefoundthat[other

    D.S.W.]factorsarguedagainstimposingaduty).

    -19- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    20/24

    WefollowedthesamecourseinStephens v. State, Department of Revenue,

    decidedjustafewmonthsafterMattingly.53AtaxpayersuedtheState,allegingthatthe

    Department of Revenue hadnegligently and maliciously attempted to collect on a

    judgment for unpaid taxes after the debt had been discharged in bankruptcy.54 To

    determine whether the defendant owed the plaintiff a duty of care under the

    circumstances,wereviewedtheD.S.W.factors.55Weobservedinitiallythat[i]nnocent

    defendantsorthosenotliabletoaplaintiffwillforeseeablysufferharmasadirectresult

    ofanegligentlybroughtprosecutionorlawsuit,butagaintheforeseeabilityofeconomic

    harmtoanidentifiableplaintiffwasnotsufficienttoestablishaduty: weanalyzedthe

    remainingpublicpolicyconsiderationsfromD.S.W. andconcludedthatnodutyexisted.56

    Notably,theNewJerseycasewefollowedinMattingly,People Express

    Airlines v. Consolidated Rail Corp.,57recognizedthelimitsoflookingtoforeseeability

    alonetodeterminewhetheradutyintortexists. Reflectingourownrelianceonpublic

    policy concerns as identified inD.S.W., the New Jersey Supreme Court inPeople

    Expressobservedthatcourtswillberequiredtodrawuponnotionsoffairness,common

    senseandmoralitytofixthelinelimitingliabilityasamatterofpublicpolicy,ratherthan

    anuncriticalapplicationofparticularforeseeability.58NewJerseycourtssincePeople

    53 746P.2d908(Alaska1987).

    54 Id.at909.

    55 Id.at910.

    56 Id.at911.

    57 495A.2d107(N.J.1985).

    58 Id.at116.

    -20- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    21/24

    Express haveheldthatforeseeabilityaloneisinsufficienttoshowtheexistenceofaduty

    inanegligencecaseclaimingeconomicharm. 59

    Insum,whilewehavelabeledforeseeabilitythesinglemostimportant

    criterionforimposingadutyofcare, 60itisclearthatAlaskascourtsmuststillconsider

    thefullpanoplyofD.S.W. factorswhendecidingwhetheranactionabledutyofcare

    exists.WerejectGeoTeksargumentthat,underMattingly,Jacobssknowledgeof

    DSIsfinancialsituationanditsknowledgethatGeoTekwouldbeharmedifDSIdidnot

    pay its subcontractors would be enough, without more, to establish a duty of care

    actionableintort.61

    59 See, e.g.,Carter Lincoln-Mercury, Inc., Leasing Div. v. EMAR Grp., Inc.,

    638A.2d1288,1294(N.J.1994)(Abilitytoforeseeinjurytoapotentialplaintiffdoes

    notinitselfestablishtheexistenceofaduty.... Oncetheforeseeabilityofaninjured

    party is established, we must decide whether considerations of fairness and policy

    warranttheimpositionofaduty.(citationsomitted)).

    60 R.E. v. State, 878 P.2d 1341, 1346 (Alaska 1994);see also State v.

    Sandsness,72P.3d299,305-06(Alaska2003)(WhilethemostimportantsingleD.S.W.

    factorisforeseeability,itisnotdispositive.).

    61 GeoTek also contends that, independent of Mattingly, Jacobss

    developmentofariskmanagementplanwasavoluntaryundertakingthatextendedits

    liabilitybeyondwhatwasotherwiserequiredbylaw,citingGuerrero v. Alaska Hous.

    Fin. Corp.,6P.3d250,258(Alaska2000).GeoTekdoesnotdevelopthisargument

    further. In Guerrero we reviewed the dismissal of a complaint under the lenient

    standardsofAlaskaCivilRule12(b)(6)andheldthattheallegationsofthecomplaintdidnot necessarily rule out the possibility that the defendant landlord had voluntarily

    expandedthescopeofitsdutyofcare.Butwenotedthatourrulingontheimpropriety

    ofadismissalunderRule12(b)(6)doesnotnecessarilyprecludethesuperiorcourtfrom

    decidingdisputedissuesofdutyonsummaryjudgment,id. at 258n.33,ashappened

    inthiscase.

    -21- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    22/24

    2. GeoTek does not identify other D.S.W. factors that could

    supporttherecognitionofadutyinthiscase.

    Intheabsenceofanyothersourceofadutyofcare,weweightheseven

    D.S.W.factorstodeterminewhetheracommonlawdutyofcareexists.62Hingingits

    argumentonforeseeabilityaloneunderMattingly,GeoTekdoesnotaddresstheother

    D.S.W. factors.Thesuperiorcourtdidnotaddressthemeither,findingthatthequestion

    ofdutywascontrolledbyourdecisioninMunicipality of Anchorage v. Tatco, Inc.63 The

    plaintiffs in Tatco had supplied materials to the contractor on a municipal landfill

    project.64Whenthecontractorfailedtopay,thesupplierssuedtheMunicipalityforits

    failuretorequirethecontractortopostapaymentbondortocertify,beforebeingpaid,

    thatithadpaidallitslaborersandsuppliers.65WeheldthattheMunicipalitywasentitled

    tosummaryjudgmentbecauseapaymentbondforthebenefitofsubcontractorswasnot

    required either by statute66 or by the contract between the Municipality and the

    contractor.67 WedonotconsiderTatco controllinginthiscase,however,asthesuppliers

    62 See Parnell v. Peak Oilfield Serv. Co.,174P.3d757,767(Alaska2007)

    (quotingBolieu v. Sisters of Providence in Wa.,953P.2d1233,1235(Alaska1998))

    (internalquotationmarksomitted).

    63 774P.2d207(Alaska1989).

    64 Id.at208.

    65 Id.

    66

    Wedeterminedthatthecontractatissuewasnotcoveredby theLittleMillerAct,AS36.25.010.025,andspecificallyitsrequirementthatpublicentities

    requirepublic-workscontractorstopostbondsforthepaymentoflaborersandsuppliers,

    AS36.25.010(a).Id.at211.

    67 Id.at210-12.

    -22- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    23/24

    in Tatco apparently did not ask the court to decide whether the Municipality had

    breachedadutyintortindependentofstatuteandcontract.

    BecauseGeoTekdoesnotanalyzetheD.S.W. factorsinitsbriefingbefore

    us,weneednotdecidewhethertheyrequireustorecognizeanactionabledutyintort.68

    We do note, however, that most factors militate against it. First, as contrasted to

    negligence creating a risk of death or physical injury, we have ascribed little

    blameworthinesstoordinarynegligencethatmerelycauseseconomic...harm.69This

    isparticularlytruewhenpartiesareinapositiontohavecontractedaroundtherisk;

    GeoTeksinjurywouldnothaveoccurredabsentitsowndecisiontoenterintoacontract

    withDSI,knowing,asitdid,thatDSIhadfailedtosecurebonding.Thepolicyof

    preventingfutureharmalsodoesnotrequirerecognitionofanoveldutyintort,asother

    contractingpartieshavetheabilitytoprotectthemselveseitherbyrefusingtoenterinto

    relationships theyconsiderfinancially fraughtor bynegotiatingformoreprotective

    provisionsintheircontractsbeforesigningthem.70 Imposingadutyincaseslikethisone

    wouldsubjectcontractorstotheaddedburdenofprotectingthepurelyeconomicinterests

    ofpartieswithwhomtheyhavenoprivity; 71itwouldalsoenhancetheirriskofhaving

    68 See Glover v. Ranney,314P.3d535,545(Alaska2013)([W]hereapoint

    isgivenonlyacursorystatementintheargumentportionofabrief,thepointwillnotbe

    consideredonappeal.)(internalquotationmarksomitted).

    69 See Mesiar v. Heckman,964P.2d445,451(Alaska1998).

    70 See Alaska Pac. Assurance Co. v. Collins,794P.2d936,946(Alaska1990)

    (notingthat[p]romisessetforthinacontractmustbeenforcedbyanactiononthat

    contract).71 See Imperial Mfg. Ice Cold Coolers, Inc. v. Shannon,101P.3d627,630

    (Alaska2004)(explainingthat theLittleMillerActisbasedonthepremisethat the

    governmentcannotbechargedbythosewithwhomthegovernmenthasnocontractual

    (continued...)

    -23- 7031

  • 7/25/2019 GeoTek Alaska, Inc. v. Jacobs Engineering Group, Inc., Alaska (2015)

    24/24

    topaytwiceforthesamelaborormaterials.72Andfinally,GeoTekdoesnotprovide

    public-policysupportfromotherjurisdictions;itdoesnotciteanycasesinwhichcourts

    imposed an extra-contractual duty on contractors to answer for the debts of their

    subcontractorsincircumstanceslikethosepresentedhere.

    V. CONCLUSION

    ThesuperiorcourtsgrantsofsummaryjudgmentareAFFIRMED.73

    71(...continued)

    relationship).

    72 See id. (holding that the Little Miller Act does not provide a private

    negligencecauseofactionagainstagovernmententityforitsfailuretorequireapayment

    bondinpartbecauseifthelegislaturehadintendedtoimposegovernmentliability

    ineffect...torequirepublicentitiestopaytwiceforapublicprojectthisintentionwouldhavebeenexpressedbecauseitisasignificantvariationfromtheexistingnorm).

    73 Becauseweaffirmthesuperiorcourtsjudgment,wenecessarilyreject

    GeoTeksargumentthatitshouldbeconsideredtheprevailingpartyforpurposesofan

    attorneysfeesaward.

    -24- 7031