  • German LNG Terminal GmbH

    Marcel Tijhuis, 17-06-2020

  • Introduction – Germany ready for LNG

    16-6-2020 www.germanlng.com 2

    Nuclear power generation being phased out by 2022: “Atomausstieg”

    Phase out of coal & lignite: “Kohleausstieg”

    Dutch gas accelerated decline of production to zero by 2022

    TTF currently Europe's most liquid gas hub

    German hubs NCG & Gaspool to be merged by 2022

    Future market integration Germany and Netherlands ??

    ➢ One single market area of approximately 130 BCM, Europe’s biggest energy market

    LNG solution to reduce dependency on pipeline imports

    Strong momentum for LNG in Germany

    Hamburg

  • German LNG Terminal, scope

    16-6-2020 www.germanlng.com 3

    Regasification capacity: 8 bcm/year Storage capacity: 1 tank 240,000 cbm or 2 tanks of 165.000 cbmLarge jetty able to receive up to Q-max vesselsSeparate jetty for LNG distribution by vessels Truckloading facilities