going & seeing in construction

19
Financial models & going & seeing in construction Jaskaran singh saini Kartikeya Pandey Manisha minu MBA Infrastructure

Upload: kartikeya-pandey

Post on 20-May-2015

120 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: Going & seeing in construction

Financial models & going & seeing in construction

Jaskaran singh sainiKartikeya Pandey

Manisha minu

MBA Infrastructure

Page 2: Going & seeing in construction

Why This Study ?

• How to improve operations and plan reliability in a large laboratory replacement project? (In San Diego with the concept of going & seeing concern)

Page 3: Going & seeing in construction

How they researched

• Analyzing root causes the team realized the two categories that reduced reliability were over-committing and revising the plan.

• Tools employed to track the data included value stream maps and employee feedback to inform project planning.

• The counter measures employed improved performance in these categories, which improved reliability of meeting scheduled commitments.

• But the concrete walls pours increase. • Thus making them use Going & seeing concern.

Page 4: Going & seeing in construction

Results

• “Going and seeing” brought the team closer to managing the project as a production line.

• data collected provided insight to the contributing factors to production cycle times including – wait time,– inventory, and – rework

• Thus providing necessary balance to complement the implementation of last planner on this project.

Page 5: Going & seeing in construction

• Limitations: data were collected from a single project.

• Implications: Real time data collected directly from field observations and feedback from workers was used to make adjustments every week.

• Value for practitioners: examples from a project that used the principle of going and seeing to continuously improve production and increase the reliability of weekly work plans.

Page 6: Going & seeing in construction

Introduction• A general contractor team’s journey from learning

about the main production problems to going and seeing in the field.

• How to improve operations and plan reliability on a large laboratory replacement project in San Diego, CA.

• The data collected from “going and seeing” provided valuable insight to the contributing factors to production cycle times including, wait time, inventory, and rework.

• This helped the team to understand where did they needed to improve

Page 7: Going & seeing in construction

The Case

• The case refers to Ohno & Shingo with their team who observed the productions .

• This process became famous by the name of “Gemba walks” (gemba Actual Place) as observing production gives more details and insights.

• In doing so you look at the minimal details scientifically & how they impact the production.

• Making TPS very sucessful

Page 8: Going & seeing in construction

VSM

• The term going and seeing is recognized in the Lean Production literature relates to the action of verifying data at the source through personal observation.

• The glasses sign in the Value stream maps refers to the Go & See the field by direct observation.

• VSMs are maps that show the sequence of tasks in a value stream using symbols that have been standardized and popularized by the Lean Enterprise

• Institute, based on the work developed at Toyota. VSMs depict data related to each activity (value-added, non-value added and supporting) while simultaneously illustrating the flows of material and information to deliver a product or service to the client

Page 9: Going & seeing in construction

Plan-Do-Check-Act (PDCA)

• Going and seeing is one step• PDCA cycle (Deming/Shewhart Cycle) provides a

structured way to improve production through a series of structured observations, test, and documentations.

• The Last Planner System of Production Control™ (LPS™) is an example of a system that uses the basic tenets of the PDCA cycle and the going and seeing principle to shield construction operations against uncertainty

Page 10: Going & seeing in construction

• Ideally last planners make ready process during the lookahead plan preparation.

• in reality production pressures bring some tension to the planning process.

• There are times when managers choose to push tasks ,which have not been completely screened through the make ready process.

Page 11: Going & seeing in construction

• After the end of each planning cycle, the completion of work packages is tracked and causes for non-completion are recorded.

• actions to prevent recurrence of problems are defined.

• The planning and control cycle continues as the plan for the following week addresses the shortcomings of the previous week and defines new work packages.

Page 12: Going & seeing in construction

• The planning and control cycle continues as the plan for the following week addresses the shortcomings of the previous week and defines new work packages.

• Work on it by cycle namely – plan, – try,– reflect, and – Standardize

• “standardize” means that uniform ground rules are set based on the way operations are currently executed

Page 13: Going & seeing in construction

• Standardization also allows small continuous improvement activities (kaizen) to depart from a common ground (standard) which is used as a step to the next level

Page 14: Going & seeing in construction

The project and the work methods

• The new $60 million facility will provide oceanic research to assist in the management and maintenance of the marine ecosystems in the Pacific Ocean.

• The total constructed area will be 287,000 square feet, which includes – new parking, offices and laboratory areas.– an extensive aquaria area, necropsy lab, biology

labs, chemistry labs– Class 100 clean room and a new 1-million-liter

seawater ocean technology development tank

Page 15: Going & seeing in construction

• The project is funded by the American Recovery and Reinvestment Act and is seeking LEED Gold certification through numerous sustainable features, including – a 250KW rooftop photovoltaic system, vegetative

roofs for storm water management, recycled andregionally sourced building materials, and natural ventilation systems

• The contract structure is a firm-fixed price based solely upon project solicitation instructions, plans and specifications

Page 16: Going & seeing in construction

Work Method – Going and seeing

• The use of LPS™ was employed from the start of the project and was familiar to a good percentage of the project team management staff.

• LPS™ was a new process to the self-performed concrete personnel assigned to the project.

• two major factors were contributing to reducing reliability– over-committing and design changes

• the team employed two countermeasures to help address the causes of these problems– Preplanning meetings and constraint analysis

Page 17: Going & seeing in construction

• To address the over-committing, early on the team initiated a weekly concrete production pre-planning meeting to discuss activities for the week related to self performed concrete.

• The intent of this meeting was to thoroughly analyze the plan for self-performed work and confirm the commitments that would be shared in the weekly subcontractor foremen planning meeting.

• This effort helped to increase reliability and affirm realistic commitments for the week.

• Data told that this meeting helped to reduce the incidence of over-committing as a problem that contributed to unreliable plans

Page 18: Going & seeing in construction

• Anticipation– a contributing factor toreducing plan reliability would be the

impact of design and constructability issues• Being a traditional design-bid-build project, there was no

cross-functional team during the development of the design documents.

• a thorough constraint analysis effort was developed and employed as a part of owner architect contract

• A constraint log was used to document the items that needed attention and make them visible to all involved

• The constraint log was updated weekly and summarized a variety of constraint types in a concise one-page report

• The list was prioritized by importance and employed visual categorization to improve communication. Since this report was a “work plan” for the Design team and Owner, reliability was measured to track performance.

Page 19: Going & seeing in construction