Page 1: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

1

Green Line Extension UpdateFiscal and Management Control BoardJohn Dalton, Program ManagerApril 13, 2020

Page 2: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

2

Agenda

• GLX Project Update• GLT Lechmere Viaduct Rehabilitation (B22CN02) & Coordination with

GLX• Lechmere Station Closure and Bus Diversion

Page 3: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

3

Design Build Entity Contract Cash Flow & Spending

Updated Quarterly. Revised as of December 31, 2019.Actuals = Paid only (does not include retainage or change orders)

Page 4: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

4

Gilman Square

Lechmere Viaduct and Station Area (existing and

future)

Page 5: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

5

Red Bridge Viaduct Area

(looking north)

Page 6: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

6

Future East Somerville

Station

Page 7: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

7

Broadway Bridge Steel

Erection

Page 8: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

8

Broadway Bridge Steel

Erection

Page 9: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

9

Future Union Square Station

Page 10: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

10

GLX Site Overview

Project Coordination Area

Page 11: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

11

Lechmere Station Demolition & New Viaduct Section

Historic Concrete Viaduct Rehabilitation

by GLT

Demolition of Existing Steel Viaduct – Spring

2020

Page 12: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

12

Lechmere Project Limits

GLX – Project Limits GLT – Lechmere Viaduct Rehabilitation Project

Green Line Extension (GLX) Green Line Transformation (GLT)

Page 13: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

13

Charles River Dam RdEd

win H

Land

Blvd GLT: Lechmere Viaduct

Rehabilitation Project

Gilm

ore B

ridge

Physical Conditions• The existing railing, deck, and stringer

conditions warrant replacement due to extensive chloride intrusion and map cracking of the concrete

• Additional concrete and steel repairs necessary to extend the life of the structure

Strength Requirements• The structure’s current load rating indicates

the concrete arches are below statutory requirements, restricting the number of simultaneous revenue vehicles and work cars on the viaduct

GLT Lechmere Viaduct Rehabilitation Project

Science Park/West End Station

Concurrent with GLX: Lechmere Station Demolition & Relocation

GLX Project Limit

Page 14: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

• Existing Service Maintained: Bus Routes 69, 80, 87, and 88 continue to connect Somerville, Cambridge, Arlington, and Medford to Lechmere

• Green Line Shuttle: A separate fleet of accessible shuttle buses will connect Lechmere to North Station to meet or exceed existing Green Line headways

• Station Bus Infrastructure: Existing Bus Garage and Operator Facilities to remain until new bus loop and new Lechmere Station are fully functional

Lechmere Station Operations

Lechmere Bus Replacement Service

Bus Replacement Service expected to start on or around May 25th

Page 15: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

• Conversion to all-day two-way bus lanes, and accompanying bus lanes conversion in Cambridge and Boston

Charles River Dam Road (Craigie Dam)

Existing

Conversion with bus lanes

Lechmere Bus Replacement Service

Page 16: Green Line Extension GLX Update Presented to the Board On

Green Line Extension Project Update

Bus lanes are needed to maintain people capacity

• In the absence of buses, many of the 14,000+ Green Line riders may choose to drive and overload the roadway system

• Congestion may increase with or without bus lane, but bus lane guarantees a reliable transit alternative

• Bus Lanes also projected to save up to 15 minutes round-trip per passenger during weekday peak travel times

Lechmere Bus Replacement Service