grid code requirement in connecting solar pv rooftop for...

29
1 Grid Code Requirement in Connecting Solar PV rooftop for various Plant Capacities Dr. H. M. Wijekoon Chief Engineer (Transmission Planning) DGM (Transmission and Generation Planning ) Branch Ceylon Electricity Board, P.O. 540, Colombo 02

Upload: buikhuong

Post on 02-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

1

Grid Code Requirement in Connecting Solar PV

rooftop for various Plant Capacities

Dr. H. M. Wijekoon

Chief Engineer (Transmission Planning)

DGM (Transmission and Generation Planning ) Branch

Ceylon Electricity Board, P.O. 540,

Colombo 02

2

A grid code is a technical specification

which defines the parameters, a facility

connected to a public electric network

has to meet to ensure safe, secure and

economic proper functioning of the

electric system. The facility can be an

electricity generating plant, a consumer,

or another network.

What is a Grid Code?

3

NET METERING / NET ACCOUNTING ARRANGEMENT FOR PARALLEL OPERATION OF ON-GRID SMALL-SCALE RENEWABLE ENERGY FACILITIES

[NOT INTENDED FOR STAND ALONE OPERATION]

Distribution Transformer

Service Main to Consumer up to contract demand

AC/DC

Inverter

M

Consumer’s Main

Distribution Panel

Disconnection Switch with Visible Separation (should be able to be locked against

unauthorized operation)

Automatic Disconnection

During mains failure

Bi-directional

Meter

Visible Separation of

the circuit is required

Consumer

Load

Consumer’s Small-Scale Renewable Energy Facility up to contract demand 3phase

(Neutral to be

kept open at

all times)

N

Connection Arrangement for Scheme 1 and 2

4

Consumer

Load

NET METERING / NET ACCOUNTING ARRANGEMENT FOR PARALLEL OPERATION OF ON-GRID SMALL-SCALE RENEWABLE ENERGY FACILITIES

[NOT INTENDED FOR STAND ALONE OPERATION]

Distribution Transformer

Service Main to Consumer up to contract demand

AC/DC

Inverter

M

Disconnection Switch with Visible Separation (should be able to be locked against

unauthorized operation)

Automatic DisconnectionDuring mains failure

Bi-directional Meter

Consumer’s Small-Scale Renewable Energy Facility up to contract demand 3phase

(Neutral to be kept open at

all times)

N

M

Connection Arrangement for Scheme 3

5

HT Interconnection Arrangement

The inverter of the Solar PV system Shall run on Voltage control

mode and CEB official should check the mode at the inspection

Collect Application and Agreement from respective

Area Office

Submission of Application& Documents to respective

Area Engineer after the payment of initial review fee

Comply with CEB

Standards

Contact Applicant for Clarifications and

request Applicant to comply with standards

Net Energy Metering EstimateIssued to the Customer byArea Engineer after initial

review

Net Energy Metering Estimate

Payment by the Applicant

Joint Inspection by Area Engineer, Applicant and

Consulting Engineer after installation

Comply with CEB

Standards

Corrections as per the CEB Standards

Joint Testing, Commissioning by Area

Engineer, Consulting Engineer, and Customer

No

Yes

No

Yes

Application Process on Net Energy Meter Connection

7

Application Procedure (HT Metering)

8

Circular Instructions Circular No.: 2017/DCC/COM-11

o HT Metering solar should be treated differently from LT

metered and be connected to HT side of the distribution

network

o Customer has to install required step up transformer and other

required equipment for the connection

o The connection cost should be borne by the customer

o CEB guide for Grid Interconnection of Embedded Generators

2000, Part 1 & Part 2 (Annex 1 & Annex 2)

o Addendum to above guide is given for Solar PV Connection

(Annex 3)

o Decided to follow same procedure for all the DDs. Connection

procedure is given as Annex 4

GRID CONNECTION REQUIREMENT FOR LARGE SCALE ROOF TOP

SOLAR POWER PLANTS -ADDENDUM TO THE CEB GUIDE FOR GRID

INTERCONNECTION OF EMBEDDED GENERATORS, DECEMBER 2000

(ANNEXURE 3)

(1) Data requirement for grid impact studies

i. Single line diagram of the solar PV plant up to the main installation circuit breaker.

This shall include all the technical parameters related to the conductors, and step

up transformers of the power collector system.

ii. Details of voltage support facilities such as switched capacitors, static var

compensators and, dynamic var compensators including the intended power factors

for full MW range. (Curve depicting power factor Vs solar plant output power)

iii. PV plant model data from the manufacturer, format acceptable to SYNERGY /

PSS/E software, and general plant characteristics including power curve to conduct

simulation studies at 33/11 kV level.

iv. PV plant layout, as per micro siting, on a 1:10,000 map.

10

Plant Monitoring

The developer of the PV plant should keep provision for monitoring the output of

the PV plant and the developer should be able to provide data on line as and when

requested by CEB for secure operation of the power system

On line Data Provision

The generating company should build the necessary data transmission facility to

provide following parameters to system control

(i)Status of the main circuit breaker of the PV plant

(ii) Active power export from the PV plant

(iii)Active power imported by the Solar PV plant

(iv)Reactive power import by the PV plant

(v)Reactive power export from the Solar PV plant

(vi)Solar Plant voltage at the main circuit breaker of the solar plant

(vii)Solar Irradiation level of the site.

11

Connection Requirement

o The quality of power provided by the PV system is governed by practices

and standards on voltage, flicker, frequency, harmonics and power factor.

o Power quality parameters must be measured at the utility interface(PCC)

unless stated otherwise.

o At PCC, the power quality requirements must comply to CEB Distribution

Connection Code and this Technical Guidebook

a. The measurement before and after energizing the PV must be

taken and submitted to relevant office of the CEB for

approval by the developer.

b. All measurement at site will be done with the representative

from CEB.

12

Normal Voltage Operating Range

Voltage Level Steady state voltage limits

LV (400 V, 230 V) 6% (0.94 PU to 1.06 PU)

11 kV 5% (0.95 PU to 1.05 PU)

33 kV 5% (0.95 PU to 1.05 PU)

Frequency Requirement

Frequency (Hz) System Conditions

50.5 - 52.0 Emergency

49.5 - 50.5 Normal

47.0 - 49.5 Emergency

Power Factor

The PV plant shall operate in the range of 0.90 leading to 0.90 lagging. The exact level

of reactive power support required from a PV plant will depend on the out come of

grid interconnection studies review in time to time.

13

Power output variation in a day of 650 kW Hambantota

Power output variation in a day of 10 MW Hambantota

14

3. Solar

Renewable Energy Resource Estimation

Sample Solar measurement data ( 1 minute time step) in

Kilinochchi.

0

200

400

600

800

1000

1200

1400

1

59

11

7

17

5

23

3

29

1

34

9

40

7

46

5

52

3

58

1

63

9

69

7

75

5

81

3

87

1

92

9

98

7

10

45

11

03

11

61

12

19

12

77

13

35

13

93

Sola

r Ir

rad

ian

ce (

W/m

2)

Mins

19th Jan 9th Feb 11th March

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Cap

acit

y (M

W)

Hours

Day1 Day2 Day3 Day4 Day5

Estimated output of a 10 MW Solar PV plant for consecutive

five days

16

Low Voltage Ride Through (LVRT) Capability

17

Power Quality

The power quality depends on the interaction between the grid and solar plant . Thus

the grid connected solar plants do affect the power quality. Hence, power quality in

terms of voltage and frequency should be maintained as specified below.

The harmonics are as defined in IEEE -519 2014

Voltage Distortion Limits

Bus Voltage V at PCC Individual harmonics (%)Total Harmonic

distortion THD (%)

𝑽 ≤ 𝟏. 𝟎 𝒌𝑽 5.0 8.0

𝟏𝒌𝑽 ≤ 𝑽 ≤ 𝟔𝟗. 𝟎 𝒌𝑽 3.0 5.0

18

Current Distortion Limits for system rated voltage 120 V through

69 kV

Maximum harmonic current distortion in percent of IL

Individual harmonic order (odd harmonics)a,b

𝐼𝑠𝑐/𝐼𝐿 3 ≤ ℎ< 11

11 ≤ ℎ< 17

17 ≤ ℎ< 23

23 ≤ ℎ< 35

35 ≤ ℎ< 50

TDD

20c 4.0 2.0 1.5 0.6 0.3 5.0

2050 7.0 3.5 2.5 1.0 0.5 5.0

20100 10.0 4.5 4.0 1.5 0.7 12

100<100

0

12.0 5.5 5.0 2.0 1.0 15

>1000 15.0 7.0 6.0 2.5 1.4 20

aEven harmonics are limited to 25% of odd harmonic limit above

bCurrent distortion that result in a dc offset e.g half wave converters are not allowed

cAll power generation equipment is limited to these values of currents distortions regardless

of actual ISC/IL

where ISC – Maximum short-circuit current at PCC

IL – Maximum demand load current (fundamental frequency components) at PCC under

normal operating condition

19

DC Injection

The PV system shall not inject DC current greater than 1 % of the rated

inverter output current into the utility interface under any operating

condition.

Flicker

Distribution system

voltage level

Absolute short term

flicker index (Pst)

Absolute long term

flicker index (Plt)

LV systems 1.0 0.8

11 kV- 33 kV 0.9 0.7

Voltage unbalance

The unbalance voltage shall not exceed 1% for 5 occasions within

any 30 minute time period at the terminals of a user’s installation

20

Controls

o The Solar PV plant shall provide the necessary controlling facility to limit the out

put variation of the solar PV plant by incorporating necessary controls.

o A large penetration of PV will increase current injection to the network.

o The output has to be reduced to avoid such situations.

o In future, the CEB will impose a limit on the penetration level after carrying out

a detail study.

o Further, the output of a solar PV plant will suddenly drop to very low value due

to cloud coverage.

21

Protection Requirement

o It is preferable to use proven protection equipment supplied by a reputable

manufacturer with a track record in this type of application.

o The performance of all protection relays shall be within the scope of IEC

protection product family Standard IEC 60255.

o It is recommended that control and protection panels are soak tested (i.e.

the protection relay panels are energized for several hours or days) prior to

being put into operation.

o During the soak test the operation of the protection relays should be

checked periodically.

o Protection relays and the associated sensing circuits must be designed to

maintain accuracy and operation in fault conditions.

o Current and voltage transformers should be appropriately selected and

comply with product standards IEC 60185 and IEC 60186.

22

PV generating facilities shall be equipped with the following protective

functions to sense abnormal conditions on CEB distribution system

Generating facility should be automatically disconnected as given in this

guide from CEB distribution system or to prevent the generating facility

from being connected to CEB distribution system inappropriately.

Under Voltage

Over Voltage

Under Frequency

Over Frequency

PV active islanding detection (Non islanding inverter)

Protection Schemes

23

The coordination of auto re-closure in CEB network

o PV tripping needs to be coordinated with the CEB feeder reclosing

practices to eliminate any possibility of out of phase reclosing.

o PV system shall cease to energize the CEB network circuit to which it

is connected prior to re-closure by the CEB network.

After the inverter tripping, no inverter reconnection will take place until

the CEB network voltage and frequency are maintained within the limits

for a stabilization period of 3 minutes.

The PV stabilization period starts once the inverter detects the voltage

and frequency to be within the normal range.

PV reconnecting time

Voltage disturbance

The inverter should sense abnormal voltage and respond according to the conditions given in following table.

Voltage (pu) Maximum trip time (sec)

V< 0.05 0.1 (100 msec)

0.05V0.5 0.2 (200 msec)

0.5V0.95 0.5 (500 msec)

0.95V1.05 Continuous

V >1.05 0.1 (100 msec)

When the inverter sense the voltage lies outside its operating limits, the recommended action shall be as given in following table

Frequency disturbance

The under frequency and over frequency levels and the corresponding inverter trip time shall be as follows:

a) When the utility frequency f < 47 Hz and f > 52 Hz

b) Trip time shall be less than 0.20 sec.

Islanding protection

During islanding, PV system shall cease to energize the grid in case of voltageand frequency situation stated above. During islanding detection, the PVsystem shall cease to energize the CEB network through the PCC within 0.5seconds of the formation of an island due to:

Safety issues Power quality problem Inverter technical limit

Fault current contribution

The fault current contribution by the inverter will be limited usually by inverter control.

Based on IEEE 1547, the short circuit current typically ranges between 100% and 200% of the rated inverter current.

The CEB will request the developer as and when required to reduce fault current contribution from PV plant.

PV interconnection must incorporate utility interface disconnect switch to allowdisconnection of PV system output from the interconnecting with CEB for safe utilityline works. The switch shall be manual, lockable, load break disconnect switch that:

a) Provide clear indication of switch positionb) Visible and accessible to maintenance and operational personnelc) Provide visual verification of the switch contact position when the switch is inopen position

Connection Arrangement

Q & A

20

40

60

80

100

47 48 49 50 51 5249.5 50.5 51.2

Fequency

Pow

er o

utpu

t(%

)Ramp = 10%/min

Ramp = 5%/sec

Power Curtailment Requirement

Limit