group 5
DESCRIPTION
about the groupTRANSCRIPT
-
1
KATHMANDU UNIVERSITY
DEPARTMENT OF CIVIL AND GEOMATICS ENGINEERING
Proposal report on
SUNKOSHI POIOYHYLROJHOY RCRJORPORDWDRORDYHJ (Hydropower Engineering II)
Submitted By:
Swadesh Khatri(27), Pukar Raj Neupane(36),
Kanchan Niroula(37), Saurav Niroula(38), Kantish Sharma(64),
Ajay Gelal(68).
Submitted to:
Prof. Dr. Ing. Ramesh K. Maskey
ASSOCIATE DEAN
SCHOOL OF ENGINEERING
Submitted on:
4/9/2014
-
2
Submitted on:
4/9/2014,
The Project Supervisor,
Prof. Dr. Ing. Ramesh Kumar Maskey,
Associate Dean, School of Engineering,
Kathmandu University.
SUBJECT: APPROVAL FOR THE PROPOSAL
Dear Sir,
Submitted for your review is our proposal for a Sunkoshi Hydropower Project
Rehabilitation, this document is submitted to partially fulfill the requirement of
Engineering Project Work of 4th year 1st semester.
Within this document you will find the following materials:
1. Introduction
2. Objective
3. Rationale
4. Methodology
5. Current Scenarios and some problems
6. Conclusion
7. References
We do hope that you will find our proposal sound and will favor us with positive
response by allowing us to go there on our own risk.
Yours Sincerely,
The Project Team
Enclosure: Proposal
-
3
Contents INTRODUCTION ........................................................................................................................................ 4
OBJECTIVES ............................................................................................................................................... 4
RATIONALE ................................................................................................................................................ 4
METHODOLOGY ....................................................................................................................................... 5
CURRENT SCENARIO AND SOME PROBLEMS ................................................................................... 5
CONCLUSION ............................................................................................................................................. 5
REFERENCES ............................................................................................................................................. 5
-
4
TIRTNUDORTNI Sunkoshi Hydropower Station, located 81 km east from Kathmandu on the upper reach of Sunkoshi river in Sindhupalchowk district, is a run-of-river type power station with an installed capacity of 10.05 MW (3 X 3.35 MW).It consist of three main parts, the headworks area, the canal and the powerhouse area. The power house was commissioned in January 1972 with the friendly cooperation of the Water Conservancy, Electric Power Ministry of the People's Republic of China and the Government of Nepal. This power station is presently at the centre stage specially in the evacuation of power from Sunkoshi Small Hydropower station (2.6 MW), Chaku Khola small Hydropower Station (1.6 MW) and other potential hydropower projects in its vicinity. The interconnection of these hydropower projects with the INPS is through 6.3/66 kV, 6.3 x2 MVA power transformers located at its 66 kV switchyard. Considering the evacuation of power at Sunkoshi corridor, which otherwise may severely overload the existing power transformers, NEA, Grid Operation Department has proposed the construction of 66 kV bay, an extension of the existing 66kV switchyard.
NEVBORTJBO To study the present condition of the project and examine the functionality of its
components.
To suggest the necessary modifications and estimate necessary cost in the
design for the rehabilitation, upgradation and modernization of project.
To investigate whether the blockage can be used to increase the head, if it cant
be cleared.
RATIONALE
The present condition of the country is lack of electricity and excessive loadshedding.
Also the blockage in the Sunkoshi river has caused Sanima HP nonfunctioning as well
as Sunkoshi HP to be stopped for safety consideration until (31/08/2014). This has
created problem over problems. Sunkoshi HPP has much great values in present
context and our country cannot afford to lose 10.05MW power in a condition of energy
crisis. Now it started generation from one unit after 30 days ( 31/08/2014) due
to massive landslide at Jure on 2nd August 2014 which swept away two gates of 10
MW Sunkoshi Power House headworks. The technology and the equipment used in this
projects are old as well as affected by landslide, which can either be replaced by new
technology and more efficient equipment or maintained in various ways thereby
achieving more benefits at low effort. Thus rehabilitation and modification of existing
project to utilize its maximum benefit is a major concern.
-
5
METHODOLOGY
Desk Study
Desk study covers various literature reviews, project planning, etc. Require
information will be gathered via various sources and results from it will be
implemented at various steps of our project implementation.
Consultation and field visits
After consulting with our faculties, frneids, local people and from the substantial
information gathered from the desk study we will be visiting the sites to carry out
the project.
Design
Based on our survey and requirements we will be designing various structures
for improving the capacity and efficiency. Generally it includes increasing the
discharge, reservoir capacity, decreasing the sediment erosion etc.
Estimation
Estimation of the designed structure will be done and the overall cost for
rehabilitating the project will be taken out.
OmttrorsCero tdns oisCnurs tnerruC Sunkoshi HEP which has capacity of 10.05 MW had been stopped until
(31/08/2014) due to massive landslide at Jure on 2nd August 2014. Now it has started
generation but not as its capacity before. Two gates of headworks have been swept
away and has to be reconstructed. The situation is not stable and various unseen
damages may be there which are to be investigated.
CONCLUSION
Thus completion of this project would be helpful for modernization of Sunkoshi HEP and
provide new ideas for rehabilitation, maintenance and operation.
REFERENCES
http://megasushilk.blogspot.com/2012/05/sunkoshi-hydro-power-station-hydropower.html
(2012-2013). Annual Report Of NEA. Kathmandu.
Nepal Electricity Authority. (n.d.). Retrieved August 28, 2014, from www.nea.com.np