guidance on practice for plant layout

33
7/21/2019 Guidance on Practice for Plant Layout http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 1/33  Guidance on Practice for Plant Layout GP 44-10 BP GROUP ENGINEERING TECHNICAL PRACTICES Document No. GP 44-10  Applicability Group Date 7 September 2005

Upload: willstreet

Post on 04-Mar-2016

27 views

Category:

Documents


5 download

DESCRIPTION

guia practica para layouts de planta

TRANSCRIPT

Page 1: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 1/33

 

Guidance on Practice forPlant Layout

GP 44-10

BP GROUPENGINEERING TECHNICAL PRACTICES

Document No. GP 44-10

 Applicabi li ty Group

Date 7 September 2005

Page 2: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 2/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 2 of 33

Foreword

This is the first issue of Engineering Technical Practice (ETP) BP GP 44-10. Guidance on Practice(GP) is based on parts of heritage documents from the merged BP companies as follows:

British Petroleum

RP 44-7 Plant Layout (February 1996).

Amoco

A BD-ELO-00-E Basic Design—Equipment Layout and Spacing—Design Specification

(October 1997).

A BD-ELO-00-G Basic Design—Equipment Layout and Spacing—Guide (October 1997).

ARCO Oil and Gas

Design Guideline 5.5 Safety Design and Analysis – Equipment Spacing (May 1992).

Copyright© 2005, BP Group. All rights reserved. The information contained in thisdocument is subject to the terms and conditions of the agreement or contract under whichthe document was supplied to the recipient’s organization. None of the informationcontained in this document shall be disclosed outside the recipient’s own organizationwithout the prior written permission of Director of Engineering, BP Group, unless theterms of such agreement or contract expressly allow.

Page 3: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 3/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 3 of 33

Table of Contents

Page

1.  Scope .................................................................................................................................... 5 

2.  Normative references............................................................................................................. 5 

3.  Terms and definitions............................................................................................................. 6 

4.  Symbols and abbreviations .................................................................................................... 8 

5.  General.................................................................................................................................. 9 

5.1.   Application of this GP.................................................................................................. 9 

5.2.  Requirements ............................................................................................................. 9 

5.3.  Philosophy ................................................................................................................ 10 

5.4.  Maintenance access ................................................................................................. 10 

5.5.  Future equipment...................................................................................................... 11 

6.  Onsite plant/unit layout ........................................................................................................ 11 

6.1.  Philosophy ................................................................................................................ 11 

6.2.  Site infrastructure...................................................................................................... 12 

6.3.  Buildings ................................................................................................................... 15 

7.  Plot layout............................................................................................................................ 16 

7.1.  General..................................................................................................................... 16 

7.2.  Plant sections ........................................................................................................... 16 

7.3.  Separation distances ................................................................................................ 17 

7.4.  Process units enclosed within buildings .................................................................... 17 

7.5.  Plot drainage............................................................................................................. 17 

7.6.  Special fire risk areas................................................................................................ 18 

7.7.  Plant scale model...................................................................................................... 18 

7.8.  Construction considerations...................................................................................... 18 

8.   Accessways and in plant roads............................................................................................ 19 

8.1.  Philosophy ................................................................................................................ 19 

8.2.  Recommended widths and clearances...................................................................... 19 

8.3.  Routing ..................................................................................................................... 20 

8.4.   Access to platforms................................................................................................... 20 

9.  Piping .................................................................................................................................. 20 

9.1.  References ............................................................................................................... 20 

9.2.  Routing ..................................................................................................................... 20 

9.3.  Minimum clearances................................................................................................. 21 

9.4.  Piping supports and pipe tracks ................................................................................ 21 

9.5.  Pipe racks................................................................................................................. 21 

9.6.  Valve operation......................................................................................................... 22 

9.7.  Spades (blinds)......................................................................................................... 22 

9.8.  Sample points ........................................................................................................... 22 

9.9.  Battery limit isolation................................................................................................. 22 

Page 4: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 4/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 4 of 33

10.  Equipment ........................................................................................................................... 22 

10.1.  Philosophy ................................................................................................................ 22 

10.2.  Rotating equipment................................................................................................... 22 

10.3.  Fired heaters and high-temperature lines.................................................................. 23 

10.4.   Air-cooled heat exchangers ...................................................................................... 24 

10.5.  Shell and tube heat exchangers................................................................................ 24 10.6.   Air intakes and discharges........................................................................................ 25 

10.7.  Pressure relief devices.............................................................................................. 26 

11.   Above-ground bulk storage and transfer areas .................................................................... 26 

11.1.  General..................................................................................................................... 26 

11.2.  Class I, II, III and unclassified liquids......................................................................... 28 

11.3.  Pressurised LPG storage.......................................................................................... 29 

11.4.  LNG storage ............................................................................................................. 30 

 Annex A (Normative) Guidance on clearances.............................................................................. 31 

 A.1.  General..................................................................................................................... 31 

 A.2.  Vertical...................................................................................................................... 31 

 A.3.  Horizontal ................................................................................................................. 31 

Page 5: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 5/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 5 of 33

1. Scope

This GP provides guidance on all aspects of the layout of process plant, associated offsite facilities,

and their equipment and structures within onshore installations. This GP is specifically applicable to

conventional ‘outdoor’ installations for processing, storing, and handling flammable or toxic fluids.

Examples include gas processing plants, refineries, chemical plants, marine loading/unloadingfacilities, and field sites; offshore facilities are excluded. This GP should be used for units constructed

on site or modules fabricated offsite. This document is not retroactive, but as far as practicable, should be applied to expansions and modifications on existing sites as well as the installation of temporary

facilities.

2. Normative references

The following normative documents contain requirements that, through reference in this text,constitute requirements of this technical practice. For dated references, subsequent amendments to, or

revisions of, any of these publications do not apply. However, parties to agreements based on this

technical practice are encouraged to investigate the possibility of applying the most recent editions of

the normative documents indicated below. For undated references, the latest edition of the normativedocument referred to applies.

BP

GP 04-10 Guidance on Practice for Drainage Systems.

GP 04-20 Guidance on Practice for Civil Engineering.

GP 04-30 Guidance on Practice for Design of Buildings Subject to Blast Loading.

GP 12-01 Guidance on Practice for Power System Design.

GP 14-01 Guidance on Practice for Noise Control.

GIS 14-011 Guidance on Industry Standard for Noise Control.

GP 22-10 Guidance on Practice for Design of Fired Heaters to ISO 13705

(API 560).

GP 22-20 Guidance on Practice for Design of Flares (API 537).

GIS 22-201 Guidance on Industry Standard for Flares (API 537).

GP 24-10 Guidance on Practice for Fire Protection – Onshore.

GP 24-03 Guidance on Practice for Inherently Safer Design Concept Selection.

GIS 24-233 Guidance on Industry Standard for Fire Water Pumps and System Design.

GP 26-10 Guidance on Practice for Heat Exchangers.

GP 30-55 Guidance on Practice for Control Rooms.

GP 30-85 Guidance on Practice for Fire and Gas Detection.

GP 34-00 Guidance on Practice for Machinery.

GP 42-10 Guidance on Practice for Design of Process Piping (ASME B31.3).

GP 44-30 Guidance on Practice for Event Modelling and Risk Based Evaluation.

GP 44-60 Guidance on Practice for API RP 500 Area Classification.

GP 44-65 Guidance on Practice for IP 15 Area Classification.

GP 44-70 Guidance on Practice for Overpressure Protection.

GP 44-80 Guidance on Practice for Relief Disposal Systems.

GP 76-01 Guidance on Practice for HSSE in Design and Loss Prevention.

Page 6: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 6/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 6 of 33

American Institute of Chemical Engineers (AIChE)

Center for Chemical Process Safety (CCPS), Guidelines for Facility Siting and Layout.

American Petroleum Institute (API)

API RP 521 Guide for Pressure-Relieving and Depressuring Systems.

API RP 752 Management of Hazards Associated with Location of Process PlantBuildings.

API RP 2001 Fire Protection in Refineries.

API Pub 2218 Fireproofing Practices in Petroleum and Petrochemical Processing Plants.

API Std 2510 Design and Construction of LPG Installations.

API Std 2610 Design, Construction, Operation, Maintenance, and Inspection of

Terminal & Tank Facilities.

British Standards Institute (BSI)

BS 4485 Water Cooling Towers.

European Standard (EN)EN 1473 Installation and Equipment for Liquefied Natural Gas - Design of

Onshore Installations.

Energy Institute (EI) – Formerly the Institute of Petroleum (IP)

IP 19 IP Model Code of Safe Practice – Part 19: Fire Precautions at PetroleumRefineries & Bulk Storage Installations.

National Fire Protection Association (NFPA)

 NFPA 30 Flammable and Combustible Liquids Code.

 NFPA 58 Liquefied Petroleum Gas Code.

 NFPA 59A Standard for the Production, Storage, and Handling of Liquefied Natural

Gas (LNG).

 NFPA 497 Recommended Practice on the Classification of Flammable Liquids,

Gases, or Vapors and of Hazardous (Classified) Locations for Electrical

Installations in Chemical Process Areas.

Process Industry Practices (PIP)

PNC00003 Process Unit and Offsites Layout Guide.

3. Terms and definit ions

For the purposes of this GP, the following terms and definitions apply:

Accessways

Paved areas for either vehicular or pedestrian access within plot limits.

Administration Area

That part of the site containing the main office buildings.

Battery Limit

The boundary of a process unit enclosing all equipment and unit limit block valves.

Page 7: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 7/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 7 of 33

Complex

A group of units, the operation of which is interlinked, e.g. a group consisting of vacuum unit,

catalytic cracker, alkylation unit, and sulphur recovery unit. On a small site, the term ‘complex’ may

refer to all the process units on the site.

Depot

A storage area of capacity less than 5 000 tonnes (5 512 tons), with no processing facilities but withimport and export facilities.

Equipment

The individual items, e.g. heat exchangers, that may make up a section.

Flammable Vapour

A general term to describe a flammable vapour or gas.

Ignition/Open Flame Area

An area containing equipment with open flame and, as practicable, surfaces hot enough to ignite

flammable material in the process area.

In Plant Roads

Roads serving one or more units or sections (of units) within a plot.

Major Site Road

The main network of thoroughfare serving all plots within a site.

Minor Site Road

Other site roads serving one or more plots within the site.

Module

Any assembly of equipment items and their associated piping, instrumentation, electrical equipment,

structure, and fittings, combined into a transportable subsection of a process unit or offsite facility.

The definition includes all sizes and sources of assembly, including contractor or vendor pre-

assembled units, preassembled or dressed complex equipment items, e.g. towers or fired heaters and

 pipe rack units.

Occupied Building

A building is considered to be occupied if any of the following criteria are met:

• A person(s) is (are) assigned to a location as a workstation or command and control center

in case of an emergency.

• A person(s) is (are) assigned to a location designated as a safe haven in case of an

emergency.

• A building is staffed 8 work-hours in a 24 hour period as part of an individual’s primary

 job function.

• Cumulative occupancy is equal to or greater than 200 hours per week.

Offsites

The units and equipment that are not specifically part of the processing units, but which provide a

service to the processing units. Offsites includes utilities (except within a process unit) and tankage.

Pipe Track

A grouping of unburied piping at or slightly below ground level.

Page 8: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 8/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 8 of 33

Plant

A general term to describe any one or all the units on a given site.

Plot

An area of the site where a unit e.g. refinery CDU, chemical plant, or storage terminal is located.

SectionPart of a unit, e.g. the fractionation part of a catalytic cracker.

Service Areas

Workshops, stores, fire station, laboratory, or similar buildings.

Site

The land owned by BP or for which BP is responsible (i.e. the land within the perimeter fence).

Storage Terminal

A storage area with no processing facilities, but with import and export facilities. If the storage

capacity is less than 5 000 tonnes (5 512 tons), this is classified as a depot.

Tank Compound

An area containing one or more tanks.

Unit

A main production component or plant in a refinery or chemical complex, e.g. a catalytic cracker or

acrylonitrile plant. Note that ‘unit’ is the usual term in refineries whereas ‘plant’ is the usual term in

chemical factories.

Utilities

Steam and power generation and transmission; condensate, process water, and cooling water treatmentand supply; instrument and service air supply; effluent treatment and similar services.

4. Symbols and abbreviations

For the purpose of this GP, the following symbols and abbreviations apply:

BI Business interruption

CSE Concept Safety Evaluation

ISBL Inside battery limit(s)

LNG Liquefied natural gas.

LPG Liquefied petroleum gas(es)

 NGL Natural gas liquid(s)

 NPSH Net positive suction head

OSBL Outside battery limit(s)

PD Property Damage

PSR Project Security Review

Page 9: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 9/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 9 of 33

QRA Quantified risk assessment

SI Systeme International d’Unites

5. General

5.1. Application of this GP

5.1.1. General

Layout is concerned with the spatial arrangement of the buildings and process equipment (and

its interconnections) within the plant boundaries, the location of the plant area within the site

 boundaries, and the location of the site relative to the surrounding environment and residential

communities. This GP makes a clear distinction between the layout of the various plants/units

on a site and the arrangement of process vessels or equipment etc. within the plant (or plot).

5.1.2. Application to existing facilities

This document is not retroactive, but as far as practicable, should be applied to expansions and

modifications on existing sites as well as the installation of temporary facilities.

5.1.3. Legislati ve regulations, local codes, and standards

a.  If there are local legislative regulations on layout for the country in which the site is

located, these must be complied with other than where this GP is more rigorous than such

statutory requirements.

 b.  Minimum distance of equipment from site property lines shall comply with national (e.g.

federal), state, and local codes and safety regulations or deed restrictions. If there is a

conflict, the greater distance shall govern.

c.  If local codes and standards for plant layout conflict with guidance given in this GP, the

more stringent text shall govern upon approval by BP.

5.2. Requirements

a.  Projects shall undergo a risk assessment to an appropriate level of detail as defined in

GP 44-30.

1.  Calculations relevant to layout or concerning potential major releases of hazardousmaterials shall be made available for such a review.

2.  Less stringent exceptions to or variances from requirements specified in this GP shall

 be supported and documented by a risk assessment.

 b.   New sites shall undergo a Project Security Review (PSR).

1.  A PSR should be considered for expansions, revamps, and temporary facilities.

2.  A regional security adviser can be located at:

http://gbcweb.bpweb.bp.com/bpsecurity/Contacts/FindYourRSA.asp 

This review ensures that security risks such as terrorist activity and vandalism are

reviewed and mitigated by competent personnel.

c.  Projects shall undergo a Concept Safety Evaluation (CSE) as described in GP 24-03.

GP 24 03 shall be referenced for inherently safer design guidance.

d.  Environmental considerations shall be included in the plant layout design to ensure that projects and developments strive to achieve the corporate goal of “no damage” to the

environment. Projects shall be in compliance with HSSE in design and loss prevention in

accordance with the GP 76-01.

Page 10: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 10/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 10 of 33

 Damage can be caused by:

•   Emissions to the air, water, and ground.

•  Physical interactions (nuisance, e.g. visual impact, noise, footprint, odour, dust,

etc.).

•   Energy inefficiency.

•   Material use and waste generation.

•   Interference with other users of the local environment.

e.  Plant layout shall comply with noise control in accordance with GP 14-01 and GIS 14-011.

5.3. Philosophy

Plant layout is particularly important at the design stage because the potential for

subsequent modification to the layout is very low. Plant layout is a major driver of

the risk that must be managed throughout the lifetime of the facility.

Plant layout shall identify and adopt the safest cost effective layout that meets the requirementsof the process design, safe operation/maintenance, and emergency action.

a.  Minimum spacing within plant shall be in accordance with:1.  Clause 11 for aboveground storage tanks.

2.   NFPA 58 and API Std 2510 (or equivalent European standard) for LPG.

3.  EN 1473 or NFPA 59A for LNG.

4.  API 2001 for fire protection in refineries.

 b.  Separation distances shall satisfy the following:

1.  Provide minimum access clearance for emergency response actions.

2.  Allow safe access for operation and emergency evacuation.

3.  Provide minimum access clearance for maintenance.

4.  Give an economic design.

c.  PIP PNC00003 offers separation distances for common items of equipment that satisfy the

aforementioned criteria.

1.  These distances should be regarded as a maximum for economic layout purposes.

2.  Separation distance adjustments either way may be justifiable if a change could

materially affect the hazard or risk or if unusual access or process reasons exist.

3.  Any proposal to increase these separation distances should be subject to a cost benefit

analysis.

d.  Separation distances are flexible and should be judged on a hazard and risk based

approach. Whilst a quantified risk based approach may be used for location of units,

 buildings etc. within a site, such an approach is, in general, considered impracticable as a

 basis for equipment layout within a unit.

Variations within practicable separation distances are likely to reduce the knock-on

 potential. However, risk reduction within a plot is, in general, more effectively

achieved by measures such as inspection, maintenance, and protective systems (e.g.

 fire protection, shut down systems, drainage etc.).

5.4. Maintenance access

a.  Equipment shall be located with adequate access for mobile handling equipment duringmaintenance.

Page 11: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 11/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 11 of 33

 b.  If elevated equipment requires crane handling, sufficient area to manipulate a boom, a

manual operated travelling crane, or a monorail and trolley shall be provided.

c.  Equipment layout shall avoid the need to lift heavy pieces of frequently maintained

equipment during unit operation over in-service process lines or equipment or provide passive protection (such as concrete containment).

5.5. Future equipment

a.  Space for probable future equipment shall be designated and located adjacent to related

equipment. The allocation of such space should be addressed during the initial project risk

assessment in order to identify potential hazards associated with probable future

equipment.

 b.  Sewers and other underground piping and electrical runs shall be routed clear of known

future equipment foundations.

6. Onsite plant/unit layout

6.1. Philosophy

a.  The site area shall be divided into plots, and if possible the plots should be rectangular.

 b.  The area of a plot shall be no greater than 20 000 m2 (215 278 ft2) and no side should be

greater than 200 m (656 ft).

c.  A single plot may contain more than one process unit or section.

d.  Irrespective of whether process units are on the same or adjacent plots, spacing

requirements outlined in this GP shall be satisfied. Spacing between process units shall

take into account the following factors:

1.  Exposure to possible fire radiation.

2.  Exposure to possible explosion overpressure.

3.  Maintenance requirements, including unrestricted hot work, of one unit whileadjacent units are in service.

4.  Business interruption potential and relative value of the units involved.

5.  Prevailing wind direction.

6.  Access by emergency response equipment.

7.  Future expansion.

e.  Plant separation should consider the following:

Plant separation distances depend on the size and congestion of the plant unit.

Typically the height and the width determine the size of the separation distance. The

key issue is to limit escalation.

1.  Maximum size of flammable gas cloud from one plant area does not significantly

intrude into adjacent areas.

2.  The magnitude of a gas explosion is not significantly increased by proximity ofadjacent plant units.

3.  Damage caused in one area does not lead to escalation in adjacent areas.

f.  If there is flow between individual units, the layout of the units should be, as far as

economical, in a logical order of flow.

The increased cost of wide spacing of process units must be weighed against the

implied safety benefits in the event of a fire or explosion.

Page 12: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 12/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 12 of 33

g.  Process units with hazardous inventories shall be located to minimise the risk of any

inadvertent release of fluid to personnel within the site, and also on activities outside the

site boundary. Topography, prevailing winds, personnel safety, and nearby population

centres shall be considered in selecting the most suitable location.

Project layout philosophy should be developed at an early stage to ensure its

consideration in the safety assurance reviews. See GP 44-30 for guidance on

assessing the risk of such a release.

h.  Flammable material storage should be located on separate plots from process units.

Flammable material may only be stored on a process unit plot provided all other options

for separate plot location have been ruled out, additional risk reduction measures areincorporated, and a comprehensive risk assessment has been conducted.

Though an inherently safer design of separate plot location is recommended for

 flammable material storage and process units, it is recognized it may not always be

 possible. In such situation, possible risk reduction measures to consider include

storage deluge system, remote emergency shutdown (ESD), passive fire protection,

blast protection, storage vessel orientation, etc.

i.  Field fabricated towers, fired heaters, etc. should be located at unit limits for construction

convenience, if practicable. Exceptions may be taken in consideration of process design orhazard management benefits.

 j.  Plant layout studies/ reviews should establish credible fire scenarios and the extent of

direct flame impingement/ thermal radiation produced by the fire.

1.  This should be taken into account when finalising layouts.

2.  Spacing between tanks and other items of plant can be relaxed with a higher degree of

fire protection.

For example, if passive fire protection (i.e. a fire wall) is provided between two

critical product pumps then greater separation may not be required. In some cases,

appropriate fire detection backed up by a rapid fire response (whether by fixed fire

 fighting systems or by manual means) can allow relaxation.

3.  In all cases, criticality of plant and equipment and implications of loss for asset

damage, business interruption and reputation should be considered, as well as those

for life safety.

6.2. Site infrastructure

6.2.1. Roads

a.  Site roads shall separate plots. Refer to GP 04-20 for minimum width for site roads.

 b.  Equipment shall be located so that site roads are not classified as a hazardous area as

defined in GP 44-60 or GP 44-65.

1.  Minor site roads shall not be in an area classified as Zone 0 or 1 (Class I Division 1).2.  Any minor site road or in-plant road classified as Zone 2 (Class I Division 2) shall

have controlled access.

6.2.2. Utilities

a.  Site utility services shall be grouped together in a non-hazardous area with exceptions being utility services integral to process unit operation.

 b.  Site utility services should be located so that essential utility supplies can be maintained

under emergency conditions (i.e. in the event of a flammable vapour release). The

Page 13: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 13/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 13 of 33

separation distances should be determined on a risk-based approach such that essential

utility supply functions can be maintained within an agreed reliability.

The spacing between site utility services and process plant with the capacity to

 produce a major flammable vapour release (or explosion overpressure), is intended

 for large sites where the utilities serve more than one plant. Loss of the utilities in

such a case could, therefore, affect several plants. Typical separation distances

should be approximately 100 m (328 ft) from units with a capacity to produce a flammable vapour release.

c.  Cables shall be routed in accordance with the requirements of GP 12-01.

6.2.3. Firewater pumps

a.  Firewater pumps shall be sufficiently remote from processing, storage, and loading areas to

minimize the risk of fire or blast damage to the pumps given protective measures installed

(e.g. fire/blast resisting enclosure).

 b.  The pumping facilities shall be capable of operation during the reasonable worst-case fire

scenario and during primary power supply outage.

c.  The primary and secondary firewater pumps shall be located in different areas to prevent

common mode failure.

d.  Requirements for firewater supply and distribution are given in GP 24-10 and GIS 24-233.

6.2.4. Cooling tow ers

a.  The direction of the prevailing wind shall be considered in selecting the location of cooling

towers. Cooling towers should be located with air intake sides generally parallel to

direction of prevailing wind.

 b.  The towers shall be located to optimise maintenance accessibility and minimise anynuisance, both within and outside the site, from water blowout, evaporation, drift, and ice

formation.

c.  Cooling towers shall be placed clear of process areas susceptible to fire risk.d.  The requirements of BS 4485 or equivalent national standard shall be met.

6.2.5. Offsi te effluent treatment facilit ies

a.  Contaminated water drainage from onsite and offsite areas shall be routed to suitable

treatment facilities as detailed in GP 04-10 or a particular project specification.

 b.  The facilities should be located to maximise gravity flow.

c.  If flammable vapours are present, consider locating the effluent treatment facilities remote

and downwind from sources of ignition, in the prevailing wind direction.

6.2.6. Flares

a.  The location, spacing, orientation, and height of flares shall be determined, for the particular site, by a full assessment of the factors involved. The design considerations andgeneral principles that determine the type and location of flares, and the routes for closed

relief systems are covered in GP 22-20, 44-70, and 44-80 and GIS 22-201.

 b.  The following principles on siting should be applied:

1.  The flare(s) should, ideally, be located as close as practicable to the process units

served, so as to allow the shortest, most direct, route(s) for the closed relief header(s),

whilst avoiding passage through special fire risk areas.

Page 14: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 14/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 14 of 33

 In practice, because they are a source of thermal radiation, and a possible source of

ignition, flares are generally located remote from process facilities, storage areas,

utility areas, and service/office areas, but well inside the property line.

2.  They should also be as far as practicable from public occupied areas that are, or may be in the future, located adjacent to the site boundaries.

3.  Design of the flare location shall consider thermal radiation, noise, luminosity, potential odour, potential ground level emissions, and ignition source related to the

flare.

4.  A side-wind location (relative to the prevailing wind direction) from process facilities

and similar sources of major release of flammable vapour is preferred.

5.  If more than one flare is provided, the location of each shall be based on operational

requirements. The locations of all flares should be determined by any need for

independent operation or maintenance of individual flares. This may require suitablespacing of separate flare stacks, or a tower-mounted multi-flare stack system. The

latter should have facilities for lowering the stacks separately, to ensure that

maintenance on any one flare stack can be carried out while the remaining flare stacksystem remains in operation.

6.  Minimum spacing of 60 m (197 ft) from aboveground facilities for elevated flares and

150 m (492 ft) for unshielded ground flares or burn-pits are suggested to provide a

 preliminary estimate for a restricted access zone around the flare-tip/stack. The actual

spacing shall be that resulting from design calculations as described in GP 44-80.

 A flare should be considered to be an elevated flare if the tip of the stack is 15 m

(49,2 ft) or more above local grade. This is an arbitrary distinction, but is a height

above which dispersion of smoke and/or toxic gases would begin to improve due to

wind effects, and above which shielding of a single or multiple ground flare becomes

impracticable.

6.2.7. Blow down stacks to atmosphere

Blowdown stack to atmosphere shall comply with GP 44-80.

6.2.8. Bulk rail/road/marine loading and unloading racks

6.2.8.1. Location

a.  If loading and unloading racks handle bulk flammable or hazardous raw materials or

 products, these facilities should, preferably, be consolidated in a single remote area on the

 periphery of the site but should be at a safe distance from any offsite population.

The term 'bulk' cannot be defined precisely, but is used if loading and unloading

 facilities handle a large proportion of the raw material or product for a single

integrated operation, e.g. a refinery or chemical plant.

 b.  This area should be clear of roads, railways, and concentrations of personnel, if any ofthese are not directly associated with the loading or unloading operations.

c.  The loading and unloading facilities should be downwind or crosswind from process units

and sources of ignition based on the prevailing wind. If this is impracticable, theloading/unloading area may be placed upwind at a prudent distance deemed by a thorough

hazard analysis.

d.  For large sites containing several independent plants or units, loading and unloading racks

local to individual plants may be required.

The increase of 'within-site' road and/or rail traffic inherent in such a layout must

also receive full consideration.

Page 15: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 15/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 15 of 33

e.  Access from the site boundary to and from the loading and unloading racks should,

 preferably, be separate from the main access to the site, and shall be located to minimise

traffic through process areas.

6.2.8.2. Layout

a.  Onshore loading/unloading and transfer areas shall be located on level ground.

 b.  Loading/unloading areas for road transport shall have adequate space for access for filling,

 parking, and manoeuvring. A drive through rack arrangement is preferred.

c.  Loading/unloading areas for rail transport shall include adequate spur tracks for standing,

filling, shunting, and may require a siding for unserviceable rolling stock.

d.  Loading/unloading areas for container transport (e.g. bags, drums, crates) shall have

adequate space for lifting and manoeuvring. Space may also be required for temporary

 placement of multiple containers during transfer.

e.  Loading/unloading areas for marine transport shall include adequate space for accessing

transfer lines, docking, and positioning.

f.  For loading and unloading areas with potentially high risk to life, there shall be at least two

independent escape routes for emergency egress.g.  For additional guidance on the layout of material transfer facilities, refer to API Std 2610.

6.2.8.3. Security

Sites shall be within a restricted access perimeter fence. Admission to sites shall be through a

security checkpoint. Some buildings, e.g. amenity buildings, may need to be located outside the

fence.

 Location of units on a site relative to buildings, the boundary, and surrounding

areas may be governed by local regulations and require agreement with the local

authorities. The location of buildings outside the site fence, e.g. offices, restaurants,

and clubhouses depends on the local conditions, especially security. Buildings used

by site personnel during normal daytime working hours should normally be locatedwithin the fence to minimise the number of people leaving and entering the site.

6.3. Buildings

6.3.1. Location

a.  A central control building (with or without satellite control buildings) for regulatory

control and online optimisation may be used for all units in a process complex.

Alternatively, dedicated control buildings may be required for individual process units or

for parts of the site remote from the main processing area, e.g. a main tank farm or product

loading facilities.

 b.  Occupied buildings shall be provided with accessways and ideally should be located in an

area classified as electrically safe.

1.  Occupied buildings shall not be located in any area classified as Zone 0 or Zone 1(Class I Division 1).

2.  If it is unavoidable that an occupied building be located in an area classified as

Zone 2 (Class I Division 2), it should conform to the requirements of GP 44-65(GP 44-60).

c.  Control building shall be located away from noise sources and on prevailing upwind side

of process and ignition/open flame areas, taking into consideration location of existing

units.

Page 16: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 16/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 16 of 33

d.  Control buildings shall be located to allow unobstructed emergency pedestrian escape off

the plot. The escape route shall not cross any special fire risk area (see 7.6) and should not

 pass through an area containing process plant.

e.  Refer to GP 04-30 for occupied buildings including occupied portable buildings such asthose used during construction, startup, commissioning, and turnarounds.

f.  For further location guidance for process plant buildings, refer to API 752 or equivalentindustry standard(s).

6.3.2. Blast resistance

a.  Control buildings and other occupied site buildings whether permanent or temporary shall be designed and located such that the risk to occupants is demonstrated to be acceptable.

 b.  Further guidance is available in GP 04 30 and 30-55.

6.3.3. Toxic hazard considerations

If a unit could produce a major toxic release, the position of the building should be specified

after taking into account the following:

a.  Pressurisation and ventilation of the building. b.  Possible safe haven designation (i.e. possible shelter in place requirements) of the building.

c.  Prevailing wind direction.

d.  Escape routes.

e.  Operator involvement in safe shut down of the plant.

f.  Other design factors.

7. Plot layout

7.1. General

The plot layout shall be an economical design to meet the process and licensors’ objective

reflecting the need for safety to life and property, and allowing adequate access formaintenance, operation, and emergency action.

 A plot may contain a process unit that can be subdivided into a number of sections.

 If such sections can process flammable and/or toxic fluids and may be operated

independently (i.e. one section may be shut down with the other in commission), the

spacing between equipment shall be sufficient to permit simultaneous normal

maintenance on the shut down section. The design should consider areas required

 for lifting equipment, lay-down and subsequent removal of equipment to off-plot

maintenance facilities. For additional guidance on layout methodology, refer to

 AIChE “Guidelines for Facility Siting and Layout”.

7.2. Plant secti ons

a.  The meaning of ‘sections’ in this context must be clearly understood.

1.  It is not intended to imply that there should be additional spacing between equipment.For example, a multiple reactor system with associated separation equipment when

one of the reactors can be shut down for catalyst change with the remaining reactor in

operation; in cases like this, the space required depends on the operations to be

carried out, any requirement for hot work, and the location of likely sources of

release, e.g. sample points.

Page 17: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 17/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 17 of 33

2.  This does not apply to fired heaters with a common stack. It is acceptable to group

together the heaters from more than one section, provided that individual heaters can

 be positively isolated from each other and any common stack.

This layout also has the advantage of collecting the permanent ignition sources

together in one part of a plot.

 b.  If equipment is grouped together, the arrangement should permit, if possible, the use ofcommon structures and maintenance equipment, e.g. a lifting beam.

7.3. Separation dis tances

a.  In determining adequate separation distances between the sections of a unit it is necessary

to define probable maintenance and access needs and the effect of such activities onadjacent equipment.

Within the plot separation distances between individual items of equipment are

generally determined by maintenance and emergency access requirements.

To meet this objective, and subject to the constraints imposed by other ETPs, PIP

PNC00003 provides data on recommended separation distances between process sections.

Annex A provides data on clearances around equipment.

PIP PNC00003 can be access in the Technical Practices Portal website

(http://technical_practices.bpweb.bp.com) selecting the industry standards online

access followed by the PIP option.

 b.  Recommended separation distances listed in this ETP and in external industrial standards

should be treated as default values that the designer may reduce or extend based upon

specific assessment of the risks involved. If possible, the specific risk assessment should:

1.  Address risks external to individual sections of a unit. For example, an external risk

analysis might consider hazards to traffic around process facilities and buildings that

need to be accessible in the event of an emergency.

2.  Consider risks within individual sections of a unit. For example, an internal risk

analysis might assess the degree of confinement and congestion and the potentialimpact upon blast overpressure during an explosion.

7.4. Process units enclosed within build ings

Process units or sections of units handling hazardous materials should not be located in fully

enclosed buildings.

 If there is a specific need for weather protection, enclosure may be necessary, but

equipment in a building should be minimised because of problems in dispersing any

 flammable vapour and providing access and escape, hazard potential is increased

and therefore process plant and material storage should, if possible, be located in

the open.

7.5. Plot drainage

a.  The plot shall be graded so that flammable liquid spills do not flow under or collect under

 process equipment. Grading and paving requirements are defined in GP 04-20, and

drainage requirements are in GP 04-10.

 b.  The plot shall be graded so that any potential spills or leaks from equipment or piping (e.g.

 piperacks) containing LNG do not drain to areas where water has collected or pooled such

that a Rapid Phase Transition (RPT) is possible.

When LNG is spilled on water and suddenly heated, a kind of explosive boiling

caused by a Rapid Phase Transition (RPT) from liquid to gas has the potential to

generate shock waves.

Page 18: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 18/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 18 of 33

c.  The location of spillage collection areas depends on the likely spillage, volatility of the

liquid and position of permanent ignition sources (i.e. the probability of ignition), and the

effect of a pool fire on the equipment. Refer to GP 22-10 for additional requirements for

fired heaters.

d.  Equipment containing strong acids or alkalis, or certain toxic, or other corrosive chemicals

should be grouped together, provided this is practicable and economical. Such areas shall

 be graded so that surface drainage can be segregated.

e.  Equipment containing incompatible or highly reactive chemicals should be segregated,

 provided this is practicable and economical. Such areas shall be graded such that surface

drainage from both areas can be isolated from one another.

7.6. Special fire risk areas

The need for special fire risk areas shall be reviewed to decide if improved equipment design

can justify their reduction or elimination. See also API 2218, GP 24-10 and GP 30-85 fornormative guidance on special fire risk areas.

 In addition to influencing layout, classification as a special fire risk area may have

requirements in other ETPs.

7.7. Plant scale model

Layout design may be aided by the use of 3-dimensional drafting packages and/or plastic

models. The cost benefit of using these tools should be assessed.

7.8. Construct ion considerations

a.  If a plot being developed on (or major modification work is being carried out on an

existing unit), or adjacent to, existing units, any interaction of the construction and

commissioning of the unit(s) of the new plot, and interconnections between the existing

units shall be considered. Measures shall be taken to achieve safe construction and

commissioning of new plant, and to minimise disruption to, or stoppage of, existing units if

this is necessary. Risks from construction activity should be considered and included in the

formal risk assessment to compare the relative risk levels of location options.

Construction work on or adjacent to existing operating facilities can cause

additional problems in construction and in commissioning.

 b.  Points to be considered at an early stage of development, and before the plot selection is

frozen, include:

1.  The construction site should be able to be separated from operating units, e.g. by a

fence. Ideally the fence should be sufficiently far away to allow a blanket hot work

 permit to be issued daily. Consideration must also be given to escape from a fenced

site in an emergency. Use of temporary gas detectors can allow early warning for siteevacuation.

2.  Hot work should be able to be stopped and naked lights extinguished rapidly on theconstruction site should a major gas release occur. For example, all electric powershould be isolated from outside the construction site. The site should be able to be

evacuated if toxic release occurs.

3.  A suitable access route to the construction site should be provided for the workforce

and construction equipment, e.g. cranes. To avoid possible damage by bulky

equipment, the route should avoid roads with overhead pipe crossings or obstructions.

Because of the number of vehicles likely to be involved, the route should be away

from areas with appreciable pedestrian traffic.

4.  On most construction sites, amenity facilities e.g. canteens, washing and toilet

facilities, and a smoking area are required. These should be located away from

Page 19: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 19/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 19 of 33

operating units, and a path between the site and the facilities should be clearly

defined.

5.  The movement of construction equipment and especially operation of cranes and

lifting gear near operating units can be a hazard. Pedestrian and vehicular accessshould be kept separate.

6.  The layout and plant location should allow adequate access for operating,maintenance and fire fighting to the existing and new units, and provide for escape

routes for emergency evacuation.

8. Accessways and in plant roads

8.1. Philosophy

a.  Accessways within each unit shall be provided for maintenance and for fire fighting from

the roads around the plot. The design of the road layout should consider the plant

complexity and the type(s) of fire-fighting appliances (i.e. fire-fighting trucks) likely to be

utilized during an emergency.

 Road widths, gate widths, clearance heights, turning circles and axle loadings for

the various types of vehicles likely to be used during the hazard are items for

consideration. These could include such vehicles as fire-fighting appliance (i.e. fire-

 fighting truck), heavy bulk foam and/or carbon dioxide carriers.

Roads or access over firm ground should be provided to allow fire appliances to approach

within reasonable operating distance of the hazard. Access should be kept free of

obstruction. In certain circumstances, railway lines may impede access for fire appliances.

 b.  Emergency vehicle access points should be reviewed, including means of gaining entry

where unattended or remotely-operated secure entry systems exist. There shall be at least

 pedestrian access for fire fighting from all roads around the plot. At least two roadapproaches shall be wide enough to allow access by emergency equipment to process

areas. If access is only possible from two sides, these should, wherever possible, be the

longest opposite sides. Normally accessways should be arranged in a rectangular grid pattern so that fire fighting can take place from two opposite sides.

 Detailed access requirements for fire fighting depend on the fire protection system

utilised.

c.  Concrete paving shall be provided in accordance with GP 04-20.

8.2. Recommended widths and clearances

a.  Minimum widths for personnel accessways, stairways, elevated walkways, platforms, and

vehicular accessways shall comply with GP 04-20.

 b.  See Annex A for minimum clearance for maintenance access around individual items of

equipment.

 Access to modules or pre-assembled units should be considered at an early stage in

the project development. Because of the structural steel at the base of the modules,

appreciable excavation would be required for the inside of the modules to be at the

same level as the surrounding ground. This can also cause problems with the

drainage system.

 Modules are often installed on raised concrete-filled or tiled plinths. Depending on

the height of plinth, hand railing may be necessary, thus limiting access and escape

routes. The operational and maintenance implications of elevated plinths should be

examined.

Page 20: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 20/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 20 of 33

c.  The use of height clearance indicators/barriers to indicate/prevent potential conflict

 between vulnerable stationary process equipment/piping above accessways and mobile

equipment (e.g. crane jib) should be considered, where necessary, based on a review of the

hazards considering type of traffic on the accessway, type of fluid and inventory in theequipment/piperack, and safeguards in place to prevent contact.

8.3. Routinga.  Accessways may be run longitudinally under pipe racks, provided that all relevant

clearance factors have been considered. However, this shall not apply to roads or an

accessway from a road to a unit.

 b.  Vehicular accessways shall be as straight as practicable and free of overhead structuresexcept where pipe racks, ducts, and conveyors are located, and should not cross main

drainage systems and cable trenches. Equipment shall not protrude into accessways.

c.  Site-run piping and cable trays shall be installed in such a way that they do not affectaccess.

d.  Process equipment shall be located so that the accessways are not classified as being in

Zone 0 or 1 (Class I Division 1) areas, as determined by GP 44 65 (GP 44-60).

e.  Access should take account of the clearance required by the proposed cranes or mobile

handling equipment or if there is an economic advantage in a layout which necessitates the

use of special equipment.

f.  If practicable and economical, the layout shall permit unrestricted access over minor roads

and vehicular accessways for deployment of the largest crane and any other mobile

equipment required for maintenance purposes and emergency services. Overhead pipe

racks, ducts, and obstructions crossing these roads and accessways shall not interfere with

such access.

g.  Where overhead pipe racks, ducts, cables, conveyors, and other obstructions cross a roador accessway, the space available horizontally at grade shall permit access of the largest

crane as required for maintenance purposes, so that the crane can be manoeuvred to the

required position. When the crane is being used for maintenance work, it shall be possibleto raise and extend the jib to the required position without obstruction from overhead pipe

racks, cables ducts, or equipment. Minimum vertical clearances are given in Annex A.

h.  Should the above requirements be considered not economical and practicable, details of the

equipment required to be removed for maintenance access shall be reviewed.

8.4. Access to platforms

a.  Access to platforms shall meet the requirements of GP 04-20.

 b.  Platform escape routes shall not be adjacent to each other.

c.  Platform escape routes shall not be adjacent to sources of hazard.

9. Piping

9.1. References

Requirements for process piping systems are covered in GP 42-10 that includes information onlayout, access, pipe clearances, and routing. Firebreak walls are referred to in GP 42-10 and

GP 04-20.

9.2. Routing

a.  Within a process unit, pipe runs shall be grouped in overhead pipe racks.

Page 21: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 21/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 21 of 33

1.  The pipe racks should be as straight as practicable.

2.  Crossings of accessways should be at right angles to the accessway and as far as

 possible from junctions and bends in the accessway.

3.  Separate, but consistent elevations shall be maintained for both north-south and east-west pipeway routing.

 b.  If pipe leakage during a fire could lead to a major increase in the fire intensity, such pipesshould not be located in any special fire risk area (see 7.6).

1.  Such pipes shall include flare lines and pipes connected to 10 m3 (353 ft

3) or more of

flammable liquid which cannot be remotely isolated.

2.  If this is not practicable, the location of such pipes in the special fire risk area shallhave external passive fire protection applied to meet the requirements specified in

GP 24-10.

c.  Flammable or toxic liquid/gas piping that remains in service during a process unit outage

shall not be routed through that process unit.

d.  Access and space accommodations shall be provided for:

1.  Designated removable pipe sections (e.g. for cleaning).

2.  Inspection needs.

3.  Complying with environmental requirements (e.g. for obtaining Volatile Organic

Compound measurements).

9.3. Minimum clearances

a.  Piping systems shall be designed, and equipment shall be laid out, to provide access by

mobile equipment.

 b.  Accessways shall be planned accordingly, and minimum clearances for this purpose shall

 be as described in Annex A.

9.4. Piping suppor ts and pipe tracks

a.  Piping supports shall not block accessways nor interfere with access.

 b.  Piping support layout should allow for removal of pipe work if expected to be necessary

for maintenance of equipment.

c.  Outside the plot and in tankage areas, pipes should normally be in pipe tracks at grade

level.

d.  The minimum distance between the nearest edge of a pipe track and the toe of a bund

(dike) is provided in GP 42-10.

9.5. Pipe racks

a.  An overhead pipe rack may contain more than one level of piping, provided thatreplacement of any pipe rack piping is feasible during a unit or section overhaul.

 b.  In a multilevel pipe rack, pipes carrying corrosive fluids should be on the bottom level.

c.  In a multilevel pipe rack, utilities should be on the top level of piping, with cable trays

above.

d.  Refer to GP 42-10 for more specific pipe rack guidance.

Page 22: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 22/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 22 of 33

9.6. Valve operation

a.  Valve actuators and hand wheels shall be located so that they may be conveniently reached

when standing at ground level or from a permanent platform.

 b.  Extended spindles or chain-operated valves may be used, but should be avoided if practicable. Chains or extended spindles shall not hang nor be in the path of moving

equipment, e.g. cranes.c.  Refer to GP 42-10 for more specific valve guidance.

9.7. Spades (blinds)

a.  Spading (blinding) positions or other means of positive isolation, e.g. removable spool

 pieces, that require access during routine operation, shall be accessible without anyrequirement for scaffolding. This includes:

1.  Spades (Blinds) that require swinging where normal start-up or shutdown routine

operations occur frequently, e.g. catalyst regeneration.

2.  Other spading (blinding) positions where economically practicable.

 b.  Spading (blinding) requirements are covered in GP 42-10.

9.8. Sample points

Detailed requirements for sample points and associated drains are specified in GP 42-10.

9.9. Battery limi t isolation

a.  It shall be possible to isolate hydrocarbon and utility systems, including steam, instrument

air, plant air, nitrogen, process water, and cooling water at each plot without affecting the

supply to any other plot.

 b.  If the plot contains more than one section, the isolation shall be provided for each section.

c.  The isolating valves shall be readily accessible, and not in an area of special fire risk (see

7.6). They would be isolated in a fire situation to limit hydrocarbon release to the fire andto prevent any loss of containment in a utility system depleting supplies essential toadjacent sections.

10. Equipment

10.1. Philosophy

If available, published equipment spacing tables (such as PIP PNC00003) may be used for

guidance, but should be regarded as default values subject to thorough risk and hazard

assessments. Further considerations for equipment spacing risk assessments may be found in

Guidelines for Facility Siting and Layout by CCPS an AIChE industry technology alliance.

10.2. Rotating equipment

a.  Pumps should be located in the open, at or near grade level. Pumps shall be accessible for

operation and maintenance.

 b.  Adequately ventilated shelters shall be provided for large machines requiring in situmaintenance (see GP 34-00). Adequate space for lifting and handling facilities for

maintenance shall be provided.

c.  Due to asphyxiation risk, nitrogen compressors shall be located in the open or inadequately ventilated houses.

Page 23: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 23/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 23 of 33

d.  Pumps should be located and specified so that an acceptable NPSH can be obtained

without undue elevation of suction vessels or columns. Pumps in flammable or toxic

service shall not be located in pits to meet this requirement.

e.  GP 34-00 specifies various pump seal arrangements that have been selected according tothe potential hazard in the event of leakage. Pumps meeting the requirements of GP 34-00

may be located adjacent to the side of overhead pipe racks, provided that access

requirements have been met.

f.  Recommended distances from other items of equipment are provided in PIP PNC00003.

g.  Firewalls or fire screens may be used to increase protection of adjacent or overhead

equipment, pipe racks, or structures from the effects of a pump fire, provided that accessfor maintenance and fire fighting is not compromised. It is recommended that these

measures (in addition to other active and passive fire prevention/protection means) be

supported by a cost benefit analysis.

Firewalls and fire screens may impair access through the plant and increase

confinement in the event of a flammable release. These increases in risk must be

taken into consideration in any cost benefit analysis.

h.  Pumps, compressors, and blowers in flammable fluid service should be located 15 m

(49 ft) or more horizontally from any part of a fired heater, or any process lines that may

operate at a temperature of 650°C (1 202°F) or greater.

10.3. Fired heaters and high-temperature lines

a.  A heater, or group of heaters, shall be located on the periphery of a plot and immediately

adjacent to an unrestricted road.

 b.  There shall be adequate access for fire-fighting from all sides of a heater and, in the case of

a group of heaters, they shall be separated from the remainder of the unit(s) by vehicular

accessways on the other three sides of the group.

c.  The layout and design of heaters shall normally be such that the tube removal can be

effected by mobile lifting equipment, for which there shall be proper access i.e. the crane

location shall not obstruct emergency access roadways. Space requirements for operation

and for withdrawal of tubes and burners shall be in accordance with GP 22-10. Minimum

clearance guidelines follow:

1.  Horizontal fired heater – tube length plus 3,1 m (10 ft).

2.  Vertical fired heater – not less than 7,6 m (25 ft) wide, for distance equal to 25% of

fired heater circumference.

d.  The following equipment and fittings that handle flammable fluids shall be considered to

 be potential sources of hazard, and shall be located 15 m (49 ft) [or less if justified by riskassessment] horizontally from any part of a heater and any associated electrical equipment

housed in industrial type enclosures:

1.  Pumps and compressors in flammable fluid service.2.  Air-cooled heat exchangers (but also see 10.4).

3.  Sample points.

4.  Hydrocarbon vents and drains open or opened to atmosphere during normal

operation. This shall include drains from fuel and pilot gas knockout drums.

However, outlets from vents and drains that are opened only during plant shutdown or

infrequent maintenance may be less than 15 m (49 ft) from a heater, provided they are

closed and plugged during normal operation.

5.  Control valves, meters, and filters on hydrocarbon gas or low flash point hydrocarbon

liquid duty.

Page 24: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 24/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 24 of 33

e.  Process or utility lines that operate at 650°C (1 202°F) or more including transfer lines to

or from heaters, and gas turbine exhaust should be considered as permanent ignition

sources and taken account of in any risk assessment.

f.  Insulation of lines above 650°C (1 202°F) should cover the lines completely, includingflanges and joints. The effect of the insulation on flange bolt temperatures should,

however, be checked, and the appropriate grade of bolting selected.

g.  Surface drains shall not be located directly under a heater.

10.4. Air-cooled heat exchangers

a.  The location of air-cooled heat exchangers shall be specifically considered with respect to

areas of special fire risk (see 7.6). Such consideration shall include:

1.  The effect of the exchanger on air movement and increased fire spread.

2.  The possibility of failure of exchanger tubes releasing more combustible fluid to the

fire.

3.  The design and operating conditions of adjacent process equipment, in particular

sealing arrangements of pumps.

4.  The height above any surface that can support a pool fire. See API RP 521section 3.15.

 b.  Minimum distance requirements between air-cooled heat exchangers and pumps:

1.  Air-cooled heat exchangers may be located at a minimum distance from pumps in

hydrocarbon service with seals meeting the recommendations of GP 34-00.

2.  For pumps on hydrocarbon duty where seals do not meet the requirements of

GP 34-00, a greater distance is required by calculation of the range of a likely

flammable release.

3.  The horizontal distance shall be measured at the pump or motor.

c.  Pumps should be located after considering overall piping and plot layout, pump NPSH

availability, pump isolation, upstream and downstream inventories, and the consequencesof fire spread and air cooler failure.

d.  The use of flanged joints in pipe racks under, or adjacent to, air-cooled heat exchangers

should be avoided.

e.  Air-cooled heat exchangers shall be located so that the hot air emitted is not a hazard or an

inconvenience to personnel, nor adversely affects the operation of adjacent equipment.

f.  Air-cooled heat exchangers should, if practicable, be at least 15 m (49 ft) horizontally from

fired heaters, to minimise the possibility of circulation of hot air.

10.5. Shell and tube heat exchangers

a.  Shell and tube heat exchangers shall be located so that, when their tube bundles arewithdrawn, they do not project into an emergency escape route or any road with

unrestricted vehicle access.

 b.  Shell and tube heat exchangers shall be arranged so that they can readily be dismantled forcleaning and maintenance.

c.  The spacing between heat exchanger shells shall allow sufficient unobstructed clearance

for access for the bundle withdrawal equipment, and to permit access for shell flange

gasket renewal. These requirements are specified in GP 26-10.

d.  Additional clearance guidelines follow:

1.  Minimum clearances for exchangers with removable bundles shall be as follows:

Page 25: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 25/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 25 of 33

a)  At channel end:

• Longitudinal – tube length plus 3,1 m (10 ft).

• Overhead – 3,7 m (12 ft) for exchangers with centreline within 4,6 m (15 ft)

of grade.• A clear overhead for exchangers with centreline more than 4,6 m (15 ft)

above grade.

 b)  At bonnet end:• Longitudinal – 3,1 m (10 ft).

• Overhead – 3,1 m (10 ft).

2.  Minimum clearances for exchangers with fixed tube sheets are the same as above,except that longitudinal clearance may be provided at either the channel end or the

 bonnet end.

3.  Shell and tube exchangers shall not be stacked more than two high, except smalldiameter exchangers if total height above grade/platform does not exceed 3,4 m

(11 ft).

10.6. Air intakes and discharges

a.  Air intakes, including intakes to heating and ventilating systems, air compressors for process, instrument, plant and breathing air, and to gas turbines, shall be located as far as is

 practicable away from areas where air contamination by dust, or by flammable or toxic

material can occur.

 b.  Air intakes shall not be located in any area classified as Zone 0, 1, or 2 as defined in

GP 44 65 (Class I as defined in GP 44-60), nor located above or below an area classified as

Zone 0 or 1 (Class I Division 1).

c.  Air intakes other than for breathing air may be located:

1.   Not less than 3 m (9,8 ft) above a Zone 2 (Class I Division 2) area if the flammablevapour release is heavier than air.

2.   Not less than 3 m (9,8 ft) below a Zone 2 (Class I Division 2) area if the flammable

release is lighter than air.

3.  In a Zone 2 (Class I Division 2) area provided dedicated flammable gas detection and

 protection system is provided.

The density of the flammable vapour shall be assumed to be at the expected

operating temperature.

Special process conditions may mean lighter than air materials behave heavier than

air and heavier than air materials behave lighter than air.

d.  The location of air intakes shall consider the effects of:

1.  Possible air contamination with dust or with flammable or toxic material.

2.  Additional safety systems, e.g. equipment trips on detection of flammable material inthe air intakes.

3.  Reduced pressure on personnel working in the area.

Some air intakes can be tolerant of contaminants in the air. For example, a process

air compressor discharging at relatively low pressure and temperature (below about

150°C [302°F]) into a process stream containing flammables. Time exists for

remedial action in the event of gas detection in the intake. In these cases it may be

acceptable to locate the intake closer to the boundaries specified above.

 However, there are cases when even a low level of contamination is unacceptable.

 In particular, the air intake for breathing air compressors must be sited where

Page 26: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 26/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 26 of 33

contamination is unlikely. The siting of breathing and instrument air compressors

should consider possible expansion of the site, i.e. they should not be located where

 future processing plant may be constructed.

e.  Intakes and discharges shall be separated to prevent cross contamination by recirculation,taking into account natural wind effects. The distance between intakes and discharges shall

 be not less than 6 m (19,7 ft) unless design provisions can be demonstrated to prevent

recirculation.

f.  Air discharges from heating and ventilating systems from enclosed hazardous areas shall

 be considered as a source of hazardous release and shall be sited accordingly.

g.  Air discharges from heating and ventilating systems, and blow-off facilities associatedwith air compressors and fans, shall be located so that they do not cause a hazard or

inconvenience to personnel nor affect the access to, and operation of, adjacent equipment.

10.7. Pressure relief devices

If atmospheric discharge from relief devices has been permitted and approved by BP (see 5.2.d),

flammable and toxic atmospheric discharges from the pressure relief devices shall comply with

GP 44-70 and the listed guidelines below.

a.  In processing installations, pressure relief devices on hazardous duties shall discharge at a

 point not less than 3 m (9,8 ft) above any platform, equipment, or structure, within a

horizontal radius of 30 m (98 ft) measured from the point of discharge.

 b.  In processing installations, flammable vapour should discharge at a point not less than

30 m (98 ft) measured in a straight line from any permanent source of ignition.

c.  Vapour from LPG and other low boiling point material storage vessels remote from

 process areas shall discharge to atmosphere not less than 2 m (6,6 ft) above the pressure

relief devices, and not less than 2 m (6,6 ft) above any platform within a 6 m (19,7 ft)

radius.

d.  In the case of storage of LPG and other low boiling point materials, there shall be no

 permanent source of ignition within the radii specified in GP 44-65 (GP 44-60) as

measured from the discharge from a pressure relief device.

e.  Flammable vapour should, and toxic vapour shall, discharge at a level not less than 25 m

(82 ft) above grade or any main operating floor.

11. Above-ground bulk storage and transfer areas

11.1. General

a.  Layout and spacing of tanks within a tank farm shall take into consideration the following:

1.  Characteristics of stored product.

2.  Size of tank.

3.  Maximum potential for fire radiation.

4.  Boil over potential.

5.  Business interruption consequences.

6.  Prevailing wind direction.

7.  Access of fire fighting equipment.

8.  Distances from adjoining properties.

9.  Future expansions.

Page 27: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 27/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 27 of 33

 b.  For additional guidance on the layout of storage facilities, refer to API Std 2610 and

IP 19).

c.  Tankage areas should be laid out to meet the requirements of clause 6.1. Any proposal for

larger plot sizes shall be subject to BP approval.

With large storage tanks, it may not be practicable to keep within these plot sizes.

d.  Bulk tanks storing hydrocarbons shall be located 76,2 m (250 ft), minimum, from any process unit.

e.  IP 15 classifies liquids as follows based on the closed-cup flash point (except for LPG):

1.  Class 0 – Liquefied petroleum gas (LPG).

2.  Class I – Liquids, other than Class 0, that have flash points below 21°C.

3.  Class II (1) – Liquids that have flash points from 21°C up to and including 55°C,

handled below flash point.

4.  Class II (2) – Liquids that have flash points from 21°C up to and including 55°C,handled at or above flash point.

5.  Class III (1) – Liquids that have flash points above 55°C up to and including 100°C,

handled below flash point.

6.  Class III (2) – Liquids that have flash points above 55°C up to and including 100°C,

handled at or above flash point.

7.  Unclassified – Liquids that have flash points above 100°C.

Class 0 includes other similar liquefied flammable gases. Class II and III liquids are

subdivided in accordance with the conditions under which they are handled.

Class II (1) or III (1) refers to flammable liquids in Class II or III handled or stored

at a temperature below the flash point. This is based on the maximum operating

temperature of storage. At a temperature above the flash point they fall into

Class II (2) or III (2) and shall be treated as a Class I liquid. Non-flammable liquids

shall be regarded as unclassified.

f.   NFPA 497 classifies liquids as follows:

1.  Class IA – Flammable liquids having flashpoints below 22,8°C (73°F) and having a

 boiling point below 37,8°C (100°F).

2.  Class IB – Flammable liquids having flashpoints below 22,8°C (73°F) and having a

 boiling point at or above 37,8°C (100°F).

3.  Class IC – Flammable liquids having flashpoints at or above 22,8°C (73°F) and below

37,8°C (100°F).

4.  Class II – Combustible liquids having flashpoints at or above 37,8°C (100°F) and

 below 60°C (140°F).

5.  Class IIIA – Combustible liquids having flashpoints at or above 60°C (140°F) and below 93°C (200°F).

6.  Class IIIB – Combustible liquids having flashpoints at or above 93°C (200°F).

7.  Unstable Liquid – A liquid that, in the pure state or as commercially produced or

transported, vigorously polymerizes, decomposes, undergoes condensation reaction,

or becomes self-reactive under conditions of shock, pressure, or temperature.

8.  Stable Liquid – Any liquid not defined as unstable.

g.  Tanks shall be laid out to provide access for fire fighting. There should be no more than

two rows of tanks between adjacent access roads. Tanks of diameter 40 m (131 ft) or

greater should be arranged in a single row.

Page 28: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 28/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 28 of 33

The figure of 40 m (131 ft) diameter is somewhat arbitrary. Because fire fighting is

easier with a single-row tank layout, it may be considered preferable to group tanks

slightly smaller than 40 m (131 ft) diameter in a single row.

h.  Pumps associated with tankage operations shall not be located inside a bunded (diked) tankcompound, and should preferably be grouped together outside the bund (dike) provided

this is practicable and economical.

 Normally, the spacing between pumps is determined by access requirements.

 However, if the pumps are on critical service, and failure would result in total

shutdown of a major facility, then additional spacing or separation may be

specified. An example of this critical duty is the main oil line (MOL) pumps on an

oil-producing site, or the booster pumps on a major pipeline.

11.2. Class I, II, III and unclassif ied liquids

a.  Tank spacing shall comply with whichever is more stringent; NFPA 30, applicable nationalstandards, or the following guidelines:

1.  A minimum spacing of 0,5 of the largest tank diameter (0,5D) shall be provided

 between any two tanks.

The recommended spacing should be regarded as a minimum, especially if the

 financial consequences of the fire affecting adjacent tanks would be especially

severe, e.g. if loss of a second tank would result in a shutdown of production or

 processing operations. Greater spacing is also required on sloping ground. With a

separate bunded (diked) compound for each large crude oil tank, the spacing

between tanks is likely to be greater than the recommended minimum of 0,5 times

tank diameter. With substantially symmetrical arrangements and typical bund (dike)

heights, the tank spacing would probably be about 1 diameter or greater.

2.  Tanks with 80 m (260 ft) diameter or greater shall have spacing between tanks of at

least 2 diameters (2D). However, when the boil-over potential risk (like for crude oil

storage) is present, greater spacing distance may be required and should be reviewed

 by BP Oil Fire Engineering Advisor or BP Group Fire Advisor.

This policy has been implemented at new BP sites worldwide. Once again, industry

experience has shown that the probability of fire escalation and fire losses can be

minimised if this guidance is followed. Reference “Atmospheric Storage Tank Study

 for Oil and Petrochemical Industries Technical and Safety Committee Singapore.

 b.  Liquids defined by IP as Class III(1) and unclassified liquids (NFPA Class IIIA liquids

stored/handled below their flash point and IIIB liquids) should be stored in a separate tank

compound from IP Class I, II, or III(2) liquids (NFPA Class I and II as well as IIIA liquidsstored above their flashpoint).

c.  Aboveground tanks for liquids defined by IP as Class I, II, and III(2) (NFPA Class I and II

as well as IIIA liquids stored/handled above their flashpoint) shall be completelysurrounded by a bund or bunds (dike or dikes). Requirements for the construction of bunds

(dikes) are specified in GP 04-20.

1.  The height of the bund (dike) as measured from outside ground level shall be

sufficient to afford protection for personnel when engaged in fire-fighting, and the

 bund(dike) shall be located so that approach can be made to a tank fire to allow use of

mobile fire-fighting equipment. The bund (dike) shall not restrict ventilation in the

tankage area.

2.  Intermediate walls of lesser height than the main bunds (dikes) may be provided to

divide tankage into groups of a convenient size, to contain small spillages and act asfirebreaks.

Page 29: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 29/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 29 of 33

d.  Unless otherwise specified by BP and reviewed by BP Oil Fire Engineering Advisor or BP

Group Fire Advisor, a separate bunded (diked) compound shall be provided for each tank

with a diameter greater than 40 m (131 ft). For tanks of diameter less than or equal to 40 m

(131 ft), individual bunded (diked) compounds are not required.

The more rigorous spacing and bunding (diking) requirements for large crude oil

tanks (diameter of 40 m [131 ft] or greater) is due to the large value of the

inventory, and the difficulty in extinguishing a fire in such a tank if it were to extendbeyond the rim fire stage. This could lead to a 'boil over' if the heat wave reached

water bottoms, resulting in the fire spreading to within the bund and increasing the

risk to adjacent tanks.

 BP experience of large tank fires has shown that tanks larger than 40 m (131 ft) in

diameter (approximately 30 000 m3 (1,1 E6 ft 3)) are difficult to extinguish in the case

of full surface fires. Additionally, inadequate spacing has been seen to increase fire

losses. (In one case in which there was inadequate spacing, three tanks were lost

due to fire escalation). Individual bunding of tanks > 40 m (131 ft), in most cases,

 provides adequate separation distance of a minimum 0,5 diameters (0,5D).

 Although it is possible to extinguish larger tanks, this requires significant attention

to provision of fire protection, resources, and a well pre-planned fire responsestrategy. This is aside from the normal requirement for operation and maintenance

of tanks to prevent fires in the first instance (refer to LASTFIRE Study carried out by

16 oil companies to review the risks associated with fires in open top floating roof

storage tank which can be obtained via web link

http://hse.bpweb.bp.com/hse/default.asp?subcat=394).

e.  In no case shall the number of tanks in any bunded (diked) compound exceed 6.

f.  The combined capacity of multiple tanks in a single bund (dike) should not exceed60 000 m3 (2,1 E6 ft3) regardless if the tanks are conventional fixed roof tanks or floating

roof tanks (e.g. three 20 000 m3 (0,7 E6 ft3) or two 30 000 m3 (1,1 E6 ft3) tanks in a single

 bund though at the maximum limit would be allowed). Early discussions with local safety

and environmental regulatory agencies may further influence bund (dike) capacity

calculations.

g.  The net capacity of a bunded (diked) tank compound shall be equivalent to the capacity of

the largest tank in the compound plus 10%. The net capacity of a bunded (diked) tank

compound shall be calculated by deducting from the total capacity:

1.  The volume of all tanks, other than the largest, below the level of the top of the bund

(dike).

2.  The volume of all intermediate bunds (dikes).

h.  If there is an absolute requirement to deviate from the guidelines in clause 11.2, advice

should be sought from the BP Oil Fire Engineering Advisor or BP Group Fire Advisor.

i.  For liquids which can cause damage to the environment or personal injury including IP

Class III(1) (NFPA Class IIIA liquids stored/handled below their flash point), unclassifiedliquids (NFPA Class IIIB) and toxic liquids, a bund (dike) compound shall be provided as

defined in clause 11.2 for IP Class I, II, and III(2) or other means of secondary

containment to prevent threat to public health, personnel, water supplies or other

environmental damage. This includes but is not limited to storage of acid and caustics.

11.3. Pressur ised LPG storage

a.  LPG storage shall be laid out in accordance with API Std 2510 or equivalent European

code, except that BP will specify vessel separation.

Page 30: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 30/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 30 of 33

 Acceptable spacing between LPG storage vessels depends on the method of fire

 protection used. Practice in this field is under development, and specialist advice

should be obtained.

 b.  The risk to personnel (both onsite and offsite) from thermal radiation effects (e.g. fromtorch fires, flash fires, pool fires and BLEVEs) should be assessed and compared with the

appropriate criteria.

c.  As guidance in the absence of formal risk calculations thermal radiation at the plot

 boundary, in the event of ignition of the leakage from a single relief valve or from a fire in

a spill-containment area, should not exceed 4,7 kW/m2 (1 490 Btu/hr-ft2). The radiation

may be calculated using the method in API RP 521 and assuming that:

1.  Fraction of heat liberated F = 0,3

2.  Wind speed = 2 m/s (6,6 ft/s)

11.4. LNG storage

LNG storage tank layout shall comply with either EN 1473 or NFPA 59A.

 LNG storage tank(s) spacing varies from country to country depending on the code

compliance basis (i.e. EN 1473 or NFPA 59A), LNG storage tank design (i.e. single,double, or full containment tank design), LNG storage tank roof design (i.e. concrete

or steel), and storage tank capacity.

For further LNG guidance refer to the ETP category 81 for BP LNG philosophies as

well as the expected mid-2006 release of the "Guide to Fire Protection, Detection,

Suppression and Emergency Response on BP LNG facilities" by BP Group

Technology (contact Richard Coates for document status).

Page 31: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 31/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 31 of 33

 Annex A(Normative) 

Guidance on clearances

 A.1. General

a. Items such as the following shall not block operating aisles or maintenance access.

1. Projecting piping.

2. Valve spindles (valve wheels).

3. Instrumentation.

4. Instrument air manifolds.

5. Local panels.

6. Transducer stations.

7. Pneumatic and electrical junction boxes.

8. Grouped steam tracing supply and condensate manifolds.

 b. A minimum of 1 m (3,3 ft) clear working spaces shall be maintained around equipmentthat requires frequent servicing such as pumps, exchangers, control valves, instruments,

tower manways, etc. Also refer to A.3.c for more stringent minimum horizontal clearances

for specific applications.

c. Horizontal and vertical clearances shall meet or exceed those recommended by equipment

suppliers for maintenance and operations.

 A.2. Vertical

a. Overhead clearances shall not be less than:

1. 3,7 m (12 ft) if carry deck crane access is required.

2. 4,6 m (15 ft) if cherry picker (13,6 to 16,3 t [15 to 18 ton] crane) access is required.

3. 3,1 m (10 ft) if 1,8 to 2,7 t (2 to 3 ton) forklift truck access is required.

4. 3,7 m (12 ft) for main pipe racks.

5. 2,2 m (7 ft) from grade or elevated platform for personnel passageway.

6. 3,1 m (10 ft) from pavement for secondary roads (cars, pickups, no mobile

equipment).

7. 4,9 m (16 ft) from pavement for main roadways without crane access.

8. 5,5 m (18,0 ft) from pavement for main roadways and, if necessary, over accessways

for heavy equipment. However, vertical clearance for crane access at main OSBLroadways and ISBL accessways shall be obtained from BP.

 b. Overhead clearance from top of rail for railroads to be confirmed by national (i.e. federal)

and local railway clearances requirements as these vary from site to site.

 A.3. Horizontal

a. Main accessway horizontal clearance for mobile equipment shall be obtained from BP but

shall not be less than:

1. 6,1 m (20 ft).

Page 32: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 32/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 32 of 33

2. 3,1 m (10 ft) if mobile equipment is to service a specific piece of process equipment

and the mobile equipment can operate “straight-in” (no turns).

 b. Minimum rail siding clearance for railroads must comply with national (i.e. federal) and

local railway clearances requirements as these vary from site to site.

c. Minimum horizontal clearance to piping, equipment, and instrumentation shall be as

follows unless otherwise approved by BP:1. 1,5 m (5 ft) for aisles at equipment and machinery.

2. 1,2 m (4 ft) for operating and maintenance areas at grade.

3. 1,2 m (4 ft) for workspace on platforms servicing the heads of shell/tube exchangers

mounted on a structure. Also refer to clause 10.5.

4. 0,9 m (3 ft) for workspace on platforms servicing manways, in addition, the centre

line of the manway should be at an elevation of 1,5 m (5 ft) from the platform.

5. 2,1 m (7 ft) for workspace around compressors, turbines, and large motors shall be provided for operating and maintenance clearances to handle casings, rotors,

crankshafts, flywheels, etc. This minimum spacing shall be validated by the

equipment supplier and approved by BP.

Note Clearances shall be measured from the furthest projectionon equipment, including associated pipe work with itsflanges and insulation boxes, filters, valves in their openposition, drains, cabling, instruments, etc., between gradeand 2,0 m (6,6 ft) above grade.

Page 33: Guidance on Practice for Plant Layout

7/21/2019 Guidance on Practice for Plant Layout

http://slidepdf.com/reader/full/guidance-on-practice-for-plant-layout 33/33

7 September 2005 GP 44-10Guidance on Practice for Plant Layout

Page 33 of 33

Bibliography

[1] AIChE “Guidelines for Facility Siting and Layout”.

[2] LASTFIRE Study (Large Atmospheric Storage Tank Fire Project) "Atmospheric Storage Tank Studyfor Oil and Petrochemical Industries Technical and Safety Committee Singapore" by Technica (dated1990) (link http://hse.bpweb.bp.com/hse/default.asp?subcat=394).

[3] "Guide to Fire Protection, Detection, Suppression and Emergency Response on BP LNG facilities" byBP Group Technology (contact Richard Coates for document status).