guidelines for accelerated bridge construction using precastprestressed concrete components

Upload: jayant-lakhlani

Post on 02-Jun-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    1/32

    PCMAC

    Paul C. Chung, MS, PE

    Raymond W. Wolfe, PhD, PE

    Jason Q. Fang, PhD, PE

    ABC- Advisory Council

    California Department of Transportation

    CaltransCaltrans

    Accelerated Bridge ConstructionAccelerated Bridge Construction(ABC)(ABC)

    InitiativeInitiative

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    2/32

    One Mission One Vision

    Enhance Mobility across California

    Need for Accelerated Project Delivery ABC works towards reducing roadway delayimpacts on the traveling public

    ABC deliver project early, provide speedycapital investments

    Minimize construction and reduce safety-related issues, environmental impacts

    Improve constructability, product quality

    and performance.

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    3/32

    The Bigger Picture-

    Caltrans Strategic Plan ABC is an element of Accelerated Project

    Delivery (APD)

    APD encompasses all aspects of project

    delivery, including ABC Benefits of APD: lead to expedited capital

    improvement (commerce, regional business

    & services, traveling public)= expeditiously

    Stimulate & Improve the states economy

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    4/32

    Accelerated Project Delivery

    NCHRP 20-73 Accelerating Transportation

    Project and Program Delivery: Conception toCompletion

    Charlie Fielder, District 1 Director representing the

    Department

    Ongoing coordination, discussions, and efforts

    with HQ and Districts develop and implementaccelerated project delivery

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    5/32

    National Spotlight

    2006 ABC Workshop, Reno, NV Guidelines for Accelerated Bridge Construction using

    Precast/Prestressed Concrete Components, PCI NortheastBridge Technical Committee (2006)

    Seismic ABC Meeting at 2007 TRB Annual Meeting

    2007 SABC meeting in San Diego

    2008 FHWA ABC Conference in Baltimore, MD

    2008 TRB SABC Collaboration Meetings

    UDOT ABC Standards Workshop report (anticipated April2008)

    FHWA/WashDOT ABC Workshop (September 2008)

    FHWA Connections Manual (2008)

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    6/32

    ABC XYZ?

    Technical

    Prefabricating Bridge Elements and Systems

    (PBES) and erecting on-site Precast concrete super- and sub-structure- Majorityof PBES in California

    Steel superstructure

    Steel & FRP superstructure

    Segmental construction methods (could be C.I.P.)

    Launch or Roll-in (SPMT) girders/superstructures

    Contract and Construction

    Double shifts

    Discentive and Incentives

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    7/32

    California Issues

    Costs of ABC use

    Construction and material costs

    Projects programmed before ABC tools considered

    Industry reluctance- CIP the preferred method(typically not a speedy operation)

    Seismic risk mitigation Performance objectives risk

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    8/32

    California ABC Strategic Plan

    Engineering Services: ABC- Advisory Council

    Pursues further widespread ABC practice for

    future standard bridge projects1. Lessons Learned Report and Survey

    2. ABC Selection Criteria

    3. Industry Engagement

    4. Construction Specifications Development

    5. Technical Research and Development

    6. Project Implementation- Pilot Program

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    9/32

    Document Lessons Learned

    ABC Projects in California in last three years-(completed in less than ~5 months)

    Identify project goals Define ABC techniques employed

    Quantify successes/challenges Determine effectiveness

    Establish ABC Techniques Selection Guides

    Recommend improvements for future projectsand research needs

    Living document

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    10/32

    Rte99/120 Separation

    PC/PS Box Beams, Post-Tensioned w/ Inter Cap

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    11/32

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    12/32

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    13/32

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    14/32

    Reduce construction time for abutments to allow quicker girderplacements

    Total 12 bridges completed in 3 months

    I-40 Marble Wash Bridge Replace

    Replace w/ Precast Girders Marble Wash completed in 28 days

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    15/32

    ABC Selection Criteria-

    Reference- FHWA: PBES Framework for Decision Making

    http://www.fhwa.dot.gov/bridge/prefab/framework.cfm

    Utah DOT

    Quantify Costs/Benefits

    Impact on air quality due to increased vehicleemissions, quality of life due to personal time delays,

    Untimely business service for workforce, supplier, andcustomers

    Incur significant costs to traveling public and regionbusinesses ~tens of thousands of dollars per weekday

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    16/32

    ABC Selection Criteria-

    Benefits- Reduces traffic delays, hazards, andprovides infrastructure improvement at a fast pace.

    Generate cost model for impact time duration (CIT)-

    $/day1. Facility: Local street, Major Artery/Highway, LandmarkBridges

    o Percentage of traffic effected

    2. Type of Impact: Environmental, Traffic Delay, and/orCapacity Improve/Restore

    3. Time Duration of Impact: # of days (week or weekend)

    Estimate CTI ($/day) for Conventional Construction (CC)

    Estimate CTI ($/day) for ABC

    Calculate Economic Savings-ECS= CTI (CC) CTI (ABC)

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    17/32

    ABC Selection Criteria-

    Balance Risks/Benefits State pays construction premium in advance, cost

    savings from ABC apply directly to travelingpublic & regional economy.

    Economical benefits offset construction costs

    ABC Selection for Projects

    Partner with project stakeholders, traffic

    officials, local agencies

    Identify needs, benefits, costs, and risksassociated with ABC

    Work with contractors, engineers - consider

    whether available ABC techniques appropriate

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    18/32

    Industry Engagement Caltrans to sponsor workshop with

    consulting engineers, fabricators, erectors,trucking, and general contractors

    a. Constructability

    shapes, geometry, curvature, tolerancesb. Picking and transporting limits

    c. New precast component & details solutions

    d. New material applications Work with Industry to improve

    construction cost competitiveness

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    19/32

    Contract Development

    Reflect Delay/Time Costs in Bid Process

    Develop use of Incentive/Disincentive

    contract clause A+B contract practice

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    20/32

    Technical Development

    Seismic Issues- future research

    NCHRP- TRB, MCEER Research

    Caltrans STR & others

    A number of research problem topics prioritized

    Precast bent cap to column connections

    Precast girder to bent cap connections

    Precast Segmental Columns Hybrid Connections Other Industries

    Grouted splice sleeve couplers

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    21/32

    Technical Development

    Seismic Research- past Spliced Girder Research- UCSD Testing

    Fully reversed horizontal displacement cycles until target

    ductilities reached.

    T h i l D l

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    22/32

    Technical Development

    Seismic Research- pastSpliced Girder Research

    SuperstructurePerformance

    Bent cap withstands plastic

    moment induced bycolumn

    Girders remain

    Essentially Elastic withsmall cracks

    Post-tensioned bent cap

    clamps girders together

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    23/32

    Technical Development

    Seismic Research- current

    (a.) Bridge Elevation

    (c.) Section of cap between girders

    Precast Bent Connection Tests- U. Washington

    NCHRP 12-74 (UCSD) studying jointed construction

    Accelerated Column Construction Tests- U. Washington MCEER ABC research

    UCSD-Iowa State Inverted-Tee Bent Cap

    (b.) Typical Section

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    24/32

    Technical Development

    Design & Construction Specifications Design Specifications & Details- findings from

    research Areas of LRFD Bridge Design Specifications needs ABC

    related modifications

    Review FHWA Connection Manual- Develop seismic

    standards Fast cure and setting concrete pour, SCC

    Assess long-term connection durability & maintainability-install monitoring devices

    Develop inspection practices non-destructive evaluation methods & tools

    Investigate potential corrosion issues including unbonded

    tendon inspection and replacement

    P j I l i

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    25/32

    Project Implementation-

    Pilot Program Establish a pool of candidate projects for ABC-

    Select projects based on ABC Selection Criteria-

    partner with local and traffic officials and stakeholders

    Up-to-date technical research and developments-application and implementation

    Engage w/ Contractor during design- Bridge Forum

    Partner w/ Construction and Contracts Office (OE)-Develop contracts and construction specifications

    ABC P j C did

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    26/32

    ABC Project Candidate

    Identify candidate at PSR and APS stage I605/I10 Interchange Viaduct- Advanced PlanningAlternative

    Southbound I-605 to East I-10 connector, in BaldwinPark, Los Angeles County

    Replace existing on-grade connector

    Existing traffic safety concern- frequent accidents Proposed bridge crosses I-605 & I-10- curved

    alignment

    30 feet above I-605 & 75 feet above I-10

    Total bridge length= 3300 ft

    Bridge width= 27 ft (single lane)

    ABC P j C did

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    27/32

    ABC Project Candidate

    I605/I10 Interchange Viaduct I-605 & I-10 heavily used daily- heavy traffic

    congestion during commute hours

    Current HOV Widen on I-10- construction

    complete in 2011

    ABC proposed Minimize construction impact to existing traffic

    Accelerate traffic safety improvement Structure Type- ABC Alternative

    Precast Segmental Balanced Cantilever

    construction- Single-Cell Box Girder

    ABC P j t C did t

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    28/32

    ABC Project Candidate

    I605/I10 Interchange Viaduct

    16-spans, span lengths = 210- 270 ft

    A C j C did

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    29/32

    ABC Project Candidate

    I605/I10 Viaduct- proposed construction stage

    ABC On LineABC On Line

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    30/32

    ABC On-LineABC On-Line

    http://www.dot.ca.gov/hq/esc/Structure_Design/accel_bridge_construction/

    ABC O LiABC O Li

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    31/32

    ABC On-LineABC On-Line

    FHWA Seismic ABC Workshop Report Caltrans ABC Strategic Plan

    ABC Lessons Learned Report- CA Applications

  • 8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components

    32/32

    Concluding Remarks ABC critical to meet AASHTO SCOBS Grand

    Challenge #3:Accelerating Bridge Construction Planning essential to proper application

    National and regional coordination essentialand exists

    Successful implementation requires

    innovation Engage partners to succeed!