guidelines for accelerated bridge construction using precastprestressed concrete components
TRANSCRIPT
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
1/32
PCMAC
Paul C. Chung, MS, PE
Raymond W. Wolfe, PhD, PE
Jason Q. Fang, PhD, PE
ABC- Advisory Council
California Department of Transportation
CaltransCaltrans
Accelerated Bridge ConstructionAccelerated Bridge Construction(ABC)(ABC)
InitiativeInitiative
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
2/32
One Mission One Vision
Enhance Mobility across California
Need for Accelerated Project Delivery ABC works towards reducing roadway delayimpacts on the traveling public
ABC deliver project early, provide speedycapital investments
Minimize construction and reduce safety-related issues, environmental impacts
Improve constructability, product quality
and performance.
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
3/32
The Bigger Picture-
Caltrans Strategic Plan ABC is an element of Accelerated Project
Delivery (APD)
APD encompasses all aspects of project
delivery, including ABC Benefits of APD: lead to expedited capital
improvement (commerce, regional business
& services, traveling public)= expeditiously
Stimulate & Improve the states economy
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
4/32
Accelerated Project Delivery
NCHRP 20-73 Accelerating Transportation
Project and Program Delivery: Conception toCompletion
Charlie Fielder, District 1 Director representing the
Department
Ongoing coordination, discussions, and efforts
with HQ and Districts develop and implementaccelerated project delivery
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
5/32
National Spotlight
2006 ABC Workshop, Reno, NV Guidelines for Accelerated Bridge Construction using
Precast/Prestressed Concrete Components, PCI NortheastBridge Technical Committee (2006)
Seismic ABC Meeting at 2007 TRB Annual Meeting
2007 SABC meeting in San Diego
2008 FHWA ABC Conference in Baltimore, MD
2008 TRB SABC Collaboration Meetings
UDOT ABC Standards Workshop report (anticipated April2008)
FHWA/WashDOT ABC Workshop (September 2008)
FHWA Connections Manual (2008)
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
6/32
ABC XYZ?
Technical
Prefabricating Bridge Elements and Systems
(PBES) and erecting on-site Precast concrete super- and sub-structure- Majorityof PBES in California
Steel superstructure
Steel & FRP superstructure
Segmental construction methods (could be C.I.P.)
Launch or Roll-in (SPMT) girders/superstructures
Contract and Construction
Double shifts
Discentive and Incentives
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
7/32
California Issues
Costs of ABC use
Construction and material costs
Projects programmed before ABC tools considered
Industry reluctance- CIP the preferred method(typically not a speedy operation)
Seismic risk mitigation Performance objectives risk
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
8/32
California ABC Strategic Plan
Engineering Services: ABC- Advisory Council
Pursues further widespread ABC practice for
future standard bridge projects1. Lessons Learned Report and Survey
2. ABC Selection Criteria
3. Industry Engagement
4. Construction Specifications Development
5. Technical Research and Development
6. Project Implementation- Pilot Program
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
9/32
Document Lessons Learned
ABC Projects in California in last three years-(completed in less than ~5 months)
Identify project goals Define ABC techniques employed
Quantify successes/challenges Determine effectiveness
Establish ABC Techniques Selection Guides
Recommend improvements for future projectsand research needs
Living document
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
10/32
Rte99/120 Separation
PC/PS Box Beams, Post-Tensioned w/ Inter Cap
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
11/32
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
12/32
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
13/32
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
14/32
Reduce construction time for abutments to allow quicker girderplacements
Total 12 bridges completed in 3 months
I-40 Marble Wash Bridge Replace
Replace w/ Precast Girders Marble Wash completed in 28 days
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
15/32
ABC Selection Criteria-
Reference- FHWA: PBES Framework for Decision Making
http://www.fhwa.dot.gov/bridge/prefab/framework.cfm
Utah DOT
Quantify Costs/Benefits
Impact on air quality due to increased vehicleemissions, quality of life due to personal time delays,
Untimely business service for workforce, supplier, andcustomers
Incur significant costs to traveling public and regionbusinesses ~tens of thousands of dollars per weekday
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
16/32
ABC Selection Criteria-
Benefits- Reduces traffic delays, hazards, andprovides infrastructure improvement at a fast pace.
Generate cost model for impact time duration (CIT)-
$/day1. Facility: Local street, Major Artery/Highway, LandmarkBridges
o Percentage of traffic effected
2. Type of Impact: Environmental, Traffic Delay, and/orCapacity Improve/Restore
3. Time Duration of Impact: # of days (week or weekend)
Estimate CTI ($/day) for Conventional Construction (CC)
Estimate CTI ($/day) for ABC
Calculate Economic Savings-ECS= CTI (CC) CTI (ABC)
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
17/32
ABC Selection Criteria-
Balance Risks/Benefits State pays construction premium in advance, cost
savings from ABC apply directly to travelingpublic & regional economy.
Economical benefits offset construction costs
ABC Selection for Projects
Partner with project stakeholders, traffic
officials, local agencies
Identify needs, benefits, costs, and risksassociated with ABC
Work with contractors, engineers - consider
whether available ABC techniques appropriate
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
18/32
Industry Engagement Caltrans to sponsor workshop with
consulting engineers, fabricators, erectors,trucking, and general contractors
a. Constructability
shapes, geometry, curvature, tolerancesb. Picking and transporting limits
c. New precast component & details solutions
d. New material applications Work with Industry to improve
construction cost competitiveness
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
19/32
Contract Development
Reflect Delay/Time Costs in Bid Process
Develop use of Incentive/Disincentive
contract clause A+B contract practice
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
20/32
Technical Development
Seismic Issues- future research
NCHRP- TRB, MCEER Research
Caltrans STR & others
A number of research problem topics prioritized
Precast bent cap to column connections
Precast girder to bent cap connections
Precast Segmental Columns Hybrid Connections Other Industries
Grouted splice sleeve couplers
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
21/32
Technical Development
Seismic Research- past Spliced Girder Research- UCSD Testing
Fully reversed horizontal displacement cycles until target
ductilities reached.
T h i l D l
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
22/32
Technical Development
Seismic Research- pastSpliced Girder Research
SuperstructurePerformance
Bent cap withstands plastic
moment induced bycolumn
Girders remain
Essentially Elastic withsmall cracks
Post-tensioned bent cap
clamps girders together
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
23/32
Technical Development
Seismic Research- current
(a.) Bridge Elevation
(c.) Section of cap between girders
Precast Bent Connection Tests- U. Washington
NCHRP 12-74 (UCSD) studying jointed construction
Accelerated Column Construction Tests- U. Washington MCEER ABC research
UCSD-Iowa State Inverted-Tee Bent Cap
(b.) Typical Section
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
24/32
Technical Development
Design & Construction Specifications Design Specifications & Details- findings from
research Areas of LRFD Bridge Design Specifications needs ABC
related modifications
Review FHWA Connection Manual- Develop seismic
standards Fast cure and setting concrete pour, SCC
Assess long-term connection durability & maintainability-install monitoring devices
Develop inspection practices non-destructive evaluation methods & tools
Investigate potential corrosion issues including unbonded
tendon inspection and replacement
P j I l i
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
25/32
Project Implementation-
Pilot Program Establish a pool of candidate projects for ABC-
Select projects based on ABC Selection Criteria-
partner with local and traffic officials and stakeholders
Up-to-date technical research and developments-application and implementation
Engage w/ Contractor during design- Bridge Forum
Partner w/ Construction and Contracts Office (OE)-Develop contracts and construction specifications
ABC P j C did
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
26/32
ABC Project Candidate
Identify candidate at PSR and APS stage I605/I10 Interchange Viaduct- Advanced PlanningAlternative
Southbound I-605 to East I-10 connector, in BaldwinPark, Los Angeles County
Replace existing on-grade connector
Existing traffic safety concern- frequent accidents Proposed bridge crosses I-605 & I-10- curved
alignment
30 feet above I-605 & 75 feet above I-10
Total bridge length= 3300 ft
Bridge width= 27 ft (single lane)
ABC P j C did
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
27/32
ABC Project Candidate
I605/I10 Interchange Viaduct I-605 & I-10 heavily used daily- heavy traffic
congestion during commute hours
Current HOV Widen on I-10- construction
complete in 2011
ABC proposed Minimize construction impact to existing traffic
Accelerate traffic safety improvement Structure Type- ABC Alternative
Precast Segmental Balanced Cantilever
construction- Single-Cell Box Girder
ABC P j t C did t
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
28/32
ABC Project Candidate
I605/I10 Interchange Viaduct
16-spans, span lengths = 210- 270 ft
A C j C did
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
29/32
ABC Project Candidate
I605/I10 Viaduct- proposed construction stage
ABC On LineABC On Line
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
30/32
ABC On-LineABC On-Line
http://www.dot.ca.gov/hq/esc/Structure_Design/accel_bridge_construction/
ABC O LiABC O Li
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
31/32
ABC On-LineABC On-Line
FHWA Seismic ABC Workshop Report Caltrans ABC Strategic Plan
ABC Lessons Learned Report- CA Applications
-
8/11/2019 Guidelines for Accelerated Bridge Construction Using PrecastPrestressed Concrete Components
32/32
Concluding Remarks ABC critical to meet AASHTO SCOBS Grand
Challenge #3:Accelerating Bridge Construction Planning essential to proper application
National and regional coordination essentialand exists
Successful implementation requires
innovation Engage partners to succeed!