guidelines for rubblization - captg · rubblization guidelines for airfields • research team: –...

43
Guidelines for Rubblization AAPTP Project 04-01

Upload: others

Post on 12-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Guidelines for RubblizationAAPTP Project 04-01

Page 2: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

AAPTP

AirportAsphaltPavementTechnologyProgram

www.AAPTP.US

Page 3: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Cracking on Airfield Pavement Surfaces Leads to Foreign

Object Debris (FOD)

Page 4: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

F-16D

- 285 psi tire pressure on main gear

- Single engine low to the ground

Page 5: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

ASPHALT INSTITUTE

Aircraft loads can exceed 1M pounds

Page 6: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

AAPTP Project 04 – 01: Developing Rubblization Guidelines for Airfields

• Research Team:– Mark Buncher (PI), Gary Fitts, Roy McQueen and

Tom Scullion • Overall Objectives

– Document state-of-the-art rubblization technology– Develop guidance for the design, construction and

quality control aspects of airfield rubblization– Prepare guide spec, design and construction manual

• Started Sept 2005– Duration: 24 months

Page 7: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

What is Rubblization?

• Fracturing techniques that:– Rubblizes PCC slabs into high quality agg. base – Eliminates slab action and other inherent distresses

• Reflective cracking• D-cracking • ASR• Slab rocking, pumping, curling, etc.

– Destroys bond between concrete and any steel• Converts failed rigid system into new flexible

system– Utilizes in-place materials/ layers below PCC

Page 8: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Earliest Use of Rubblization on Airfields: 1997, 10in PCC, Jacksonville NAS TW “A”

Photo taken in 2003

Page 9: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

• Technology developed for highways– Approx. 2% of all rubblization SYs has been airfields

• Same with crack/break and seat

• Became predominate PCC rehab technique in 1990’s– From 1994 - 2004, > 50 million sq yds rubblized

• Most highway thicknesses between 8-14 inches

But What About Thicker PCC on Heavy Load Airfields?

State DOT’s Adopt Rubblization

Page 10: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

• Resonant Pavement Breaker at Wright-Patterson AFB, OH, 2002

• Up to 26 inches

• Multi-Head Breaker at Selfridge ANGB, MI, 2002

• Up to 21 inches

Page 11: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

RB-500 at WPAFB

• 2000 lbf blows @ 44 cycles/second

• < 1 in amplitude

• 9-12 in wide, multiple passes

Page 12: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Test pits at WPAFB confirmed:– Complete slab destruction full

depth (26 inches) – Max particle size: 12in

Page 13: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Rubblization Process at Selfridge

• Edgedrains and Cross Underdrains

• Pre-fracture• Rubblize• Test Pits

– agency approval before full scale

• Rolling– Z-grid roller– 25-ton proof roller

• Leveling Course– crushed PCC

• Paving

Page 14: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

In May 2002, 85,000 sq yds of PCC RW was rubblized in 16 days (5300 sq yds/ day)

Completed Selfridge RW

Page 15: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Some Preliminary Findings and Recommendations from

AAPTP 04-01

(not necessarily the views of AAPTP, the FAA, etc)

Page 16: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Conclusions on Material Characterization

• Data Shows Range of In-service Erub: 100 to 430 ksi– Avg of 205 ksi– Closer to HMA Base than CAB– Larger Particles and Steel Result in Higher Erub

– Poor Underlying Support Can Result in Larger Particles – Poor Correlation of Erub to Slab Thickness– Erub May be Related to Pre-fractured Modulus

• Better correlation, but less data

• For CBR Designs: Consider Equivalency Factors– 10” Rub = 10+” CAB

Page 17: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Other Findings Regarding Material Characterization

• Several (4) Projects Show Erub Tends to Increase With Time• Erub Dependent On Rubblization Effort

– Repeated Runs Of Either Equipment Type Reduces Erub.

• No Rubblization Project Found In Literature That Reported Reflective Cracking From Underlying PCC– But Full Depth Fracture Can Be A Challenge On PCC That Is

Reinforced, Very Thick (>20”) Or Very Thin (<9”) With Poor Support

• No Change In Subgrade Moduli After Rubblization• No Consistent Difference In Erub With Two Equipment Types

Page 18: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Minimum HMA Overlay ThicknessRecommendations

• If HMA Placed Directly Over Rubblized Material– 5 inches Minimum HMA Total

• At least 2 lifts, but 3 preferred (for smoothness)• 1st lift at least 3 inches (to achieve density)

• If Unbound Material Directly Over Rubblized– Use Existing Minimum HMA Thickness Criteria For

That Unbound Material (RAP, CAB, Etc)• Typically 3 or 4 inches

– Leveling Courses Often Used On Runway and Taxiway Projects To Correct Grade

• Design May Require Greater Thicknesses

Page 19: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Assessing Suitability of Project for Rubblization

• Marginal candidates are thin slabs (< 9” approx.) with poor underlying support– Either no subbase or thin select fill– Weak or saturated subgrade– Typical of WWII era airfields – Three recent runway projects

• Pratt, Kegelman, Tullahoma

Page 20: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Pratt RW, KSPratt RW, KS--6” PCC, virtually no subbase, subgrade CBR of 26” PCC, virtually no subbase, subgrade CBR of 2--44--Spec required RPBSpec required RPB--Edge drains installed but no water ever drainedEdge drains installed but no water ever drained-- Rubblization started OK on edge, but problems as moved Rubblization started OK on edge, but problems as moved toward centertoward center

Page 21: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Pratt RWPratt RW-- 45% of first phase required full depth patching45% of first phase required full depth patching

Page 22: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives
Page 23: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

KegelmanKegelman AuxillaryAuxillary Field, OKField, OK-- 5”5”--6.5” PCC, thin to no sandy subbase, clay subgrade6.5” PCC, thin to no sandy subbase, clay subgrade-- RPB required RPB required -- Poor drainage and “couldn’t afford” edge drainsPoor drainage and “couldn’t afford” edge drains-- No punchNo punch--thrusthrus but excessive rutting (>2”)but excessive rutting (>2”)-- 30% of project had full depth patches (230% of project had full depth patches (2--4’ in subgrade)4’ in subgrade)

Page 24: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Tullahoma TN Airport RW

• Built During WWII• 7.25” PCC Over Clay Subgrade• CBRs Reported of 4 to 12

– Variable levels of moisture and strength• Closed For Some Time• Design Called For Rubblization With 6” CAB and

5” HMA Overlay• Suggested Trial Demo With Both Types Of

Rubblization Equipment Before Project Let

Page 25: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Start-up of MHB, normal ht (24”) and spacing

Page 26: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

MHB “Modified” Crack and Seat Process (low drop ht, large spacing)

Page 27: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Test Pit from MHB “Modified” or Crack and Seat Process, low (16”) drop ht, large (10”) spacing

Page 28: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

PB-4 Proof Rolled and Failed a MHB Section

Page 29: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Typical PB-4 Sections (rutting, poor breakage)

Page 30: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Best PB-4 Sections (Dryer Subgrade)

Page 31: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Best PB-4 Sections (Dryer Subgrade)

Page 32: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

More difficult to get good break on outer thickened and reinforced edge

ReinforcedEdge CTB

9-6-9 JCP

SH 70 in TX, MHB, No Base, 9-6-9 slabs on clay subgrade

Page 33: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Problem Areas found during HMA placement

Belly Dump operation

Page 34: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Large Particle Rotation

Page 35: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives
Page 36: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Assessing risk of having inadequate structural support for effective rubblization (resulting in inconsistent breakage, large and shifting PCC particles, punch-thus or rutting from construction equipment).

0

2

4

6

8

10

12

14

16

18

20

0 1 2 3 4 5 6 7 8 9 10

Subgrade CBR

Thic

knes

s of

PC

C a

nd B

ase

High Risk

Low RiskModerate

Risk

Project Feasibility

Page 37: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Avoiding Problems on Marginal Candidates

• Assess risk before starting project– Estimate % of high, medium and low risk areas

• Proof rolling very important, especially if using the MHB– Don’t want to find weak spots when paving starts

• Consider trial demo• Start rubblization away from wet season• Consider other design options

– crack and seat– Placing CAB layer before HMA

Page 38: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Other Recommendations for Marginal Candidates

• Always install edge drains before rubblization– Unless one is existing or self draining subgrade– Eases rubblization, better long-term performance

• Include full depth patching of unstable areas as separate bid item with estimated quantity – Provides competitive price

• If saturated subgrade, turn off vibrators on rollers• Consider construction sequencing options with

first lift– Keep trucks on adjacent unbroken PCC or new HMA– Cautious of using heavy MTV on first lift– Use tracked pavers on first lift

Page 39: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Remove all HMA

Did not completely remove old HMA at all locations

Scraping off HMA after rubblization revealed no breaking accomplished beneath HMA

Page 40: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives
Page 41: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

2”dense-graded

# 57 Stone

3 % Slope Outlet

Filter Fabric

Shoulder Area

Rubblized PCC

Base Course

Subgrade

Permeable Zone

Rubblization Side Drainage

Permeable/Crack-relief

Semi-solid/Interlocked

• Prior to rubblization • Directly against edge of concrete• Rigid PVC with smooth interior• Drain for several days

Page 42: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

Isolate Adjacent Pavements Not To Be Rubblized

Protect structural integrity of adjacent pavement with:

• wheel saw relief trench, or

• two parallel diamond blade saw cuts

Page 43: Guidelines for Rubblization - CAPTG · Rubblization Guidelines for Airfields • Research Team: – Mark Buncher (PI), Gary Fitts, Roy McQueen and Tom Scullion • Overall Objectives

The End

Questions?