Gully assessment and

prevention/control measuresLakew Desta

Page 2: Gully assessment and prevention/control measures

Presentation Outline

1. Processes of soil erosion and gully formation

2. Occurrence and development of gullies

3. Assessment and mapping of gullies

4. Principles of gully prevention and control

5. Basic gully treatment measures (Physical and Biological measure)

6. Gully Related to Road Drainage

7. Gully as a RWH structure

8. Management/Maintenance and utilization of rehabilitated gullies

9. Observed changes and Impacts

Page 3: Gully assessment and prevention/control measures

1. PROCESSES OF SOIL EROSION AND GULLY

FORMATION

Definition: a gully is a channel resulting from erosion

and caused by concentrated but intermittent flow of

water usually during and immediately following

heavy rains

Page 4: Gully assessment and prevention/control measures

1. PROCESSES OF SOIL EROSION

AND GULLY FORMATION Continued…

The principal effect of splash erosion is to detach soil

The principal effect of the other forms of erosion is to transport the detached soil

Based on the nature and extent/form of soil removal, wash erosion is classified as:

sheet erosion

rill erosion

gully erosion

stream bank erosion

Land slumping / collapsing, piping, tunnelling

Page 5: Gully assessment and prevention/control measures

Rill Erosion:

Rill erosion is the removal of soil by running water forming shallow channels (<30cm depth) - “Maresha”

Rill erosion is regarded as a transition stage between sheet erosion and gulling

Gully Erosion:

Is the removal of soil by running water

Channels cannot be smoothened out completely by normal cultivation operation

It is an advanced stage of rill erosion

It is associated with accelerated and concentrated overland flow

Cattle paths, earth tracks, dead furrows, tillage furrows, or other small depressions down a slope favour concentration of water

1. PROCESSES OF SOIL EROSION

AND GULLY FORMATION Continued…

Page 6: Gully assessment and prevention/control measures

8/3/2015

Gully advancing backwards b/c of

waterway and traditional ditches –

Gerchech, Zimac gully

Page 7: Gully assessment and prevention/control measures

Gullies in Tana Beles

project areas – road drains

8/3/2015

Page 8: Gully assessment and prevention/control measures

8/3/2015

Enkulal, Gelawdeos gully – “It is as

if we are on the moon”

Page 9: Gully assessment and prevention/control measures

8/3/2015

Problem of under estimating, technology selection and dimensioning

Page 10: Gully assessment and prevention/control measures

8/3/2015

Page 11: Gully assessment and prevention/control measures

Some of the gully control practices are like this in the field

Poor gully treatment exercise in Sekela, Lij Ambera - Mewalel8/3/2015

Page 12: Gully assessment and prevention/control measures

8/3/2015

Page 13: Gully assessment and prevention/control measures

Poorly designed and constructed road is a

main cause of gully formation and its

expansion!!!

8/3/2015

Page 14: Gully assessment and prevention/control measures

8/3/2015

9 culverts in

one CW 530ha.

Page 15: Gully assessment and prevention/control measures

Gully created as a result of the culvert – in Dhangego KA of Kersa

8/3/2015

Page 16: Gully assessment and prevention/control measures

Gully from the culvert eating perennial crops (chat) in Dhangego KA of Kersa

8/3/2015

Page 17: Gully assessment and prevention/control measures

Culvert not

extended to

the natural

waterway –

in Harla

Belina KA

8/3/2015

Page 18: Gully assessment and prevention/control measures

8/3/2015

Page 19: Gully assessment and prevention/control measures

8/3/2015

Alamata, Gira Kasso asphalt road and being a closed

area and afforested is a good example of stable

environment

Page 20: Gully assessment and prevention/control measures

2. Occurrence and development of

gullies

2.1 Gully development process: A gully develops in three distinct phases ;

a. Waterfall erosion /gully head advancement

b. Channel erosion along gully beds – side cutting typical of U-shaped

gully

c. Land-slide erosion on gully banks, sink holes, slumping, piping, tunneling

Page 21: Gully assessment and prevention/control measures

The soil collapsing as its get wet in the first rain – dry season

8/3/2015

Drying and is attached to cracking i.e. Deep cracking

Page 22: Gully assessment and prevention/control measures

The soil collapsing as its get wet in the first rain

8/3/2015

Page 23: Gully assessment and prevention/control measures

8/3/2015Source: Thomas, 1997

Classification of gullies

Classes of gully: gullies are classified under several xics

Gully classes Gully depth (m) Gully drainage area (ha)

(a) Small gully < 1.5 < 10

(b) Medium Gully 1.5 to 3 10 to 30

(c) Large gully > 3 > 30

a) Gully class based on size:

Page 24: Gully assessment and prevention/control measures

Gully stream ordering of finger/branch gullies

8/3/2015

Page 25: Gully assessment and prevention/control measures

8/3/2015

Cross-section of a gully

Page 26: Gully assessment and prevention/control measures

8/3/2015

Page 27: Gully assessment and prevention/control measures

8/3/2015

b) Gully class based on shape:

Classification of gullies continued…

Page 28: Gully assessment and prevention/control measures

Effects of gully:

The effects of gully can be summarized as follows:

Loss of productive land

Dissection and fragmentation of land

Reduced amenity and property values such as fences,…

Silting up of storage dams, ponds, waterways and irrigation canals

Silting up of fertile agricultural fields – “Masachin BemamaKumet Tekebere”

Local lowering of the water table – gullies suck water (NPC)

Damage to infrastructures such as roads, bridges, culverts, buildings and irrigation or water supply schemes

Page 29: Gully assessment and prevention/control measures

Gully acting as moisture suction from the soil in deeper profiles

8/3/2015

Page 30: Gully assessment and prevention/control measures

Gully threatening community well for water supply – Sekela, Lij Ambera8/3/2015

Page 31: Gully assessment and prevention/control measures

8/3/2015

Page 32: Gully assessment and prevention/control measures

8/3/2015

Gully tracking using GPS

Page 33: Gully assessment and prevention/control measures

8/3/2015

Basic gully control measures

continued…

Physical measuresGully reshaping and re-vegetation

Use of various types of checkdams

Brushwood checkdam

Loose stone checkdam

Gabion checkdam

Arc weir checkdam

Organic gabion box checkdam

Sand bag checkdam

Page 34: Gully assessment and prevention/control measures

A. Gully reshaping and revegetation

45°)

)

Gully Depth: 8.0 m

Gully Width: 10.0 m

6.0 m

2.0 m

6.0 m

1.0 m1.0 m

Retention walls , only required when gully walls are

reshaped shortly before the rainy season

checkdam

Gully control measures continued …

8/3/2015

Page 35: Gully assessment and prevention/control measures

Gully

Most gullies expand by erosion caused from lateral runoff water

entering through unprotected gully flanks

Basic gully treatment measures continued…

8/3/201535

Page 36: Gully assessment and prevention/control measures

Trench

Gully Wall

Reshaping and planting

Gully planting & cultivation

2.0 m

1.0 m1.0 m

2.0 m

Construct trench bund

along the reshaping

boundary

Reshape Gully Wall Plant Cuttings

& SeedlingsIncrease Height

of checkdams

Reshape 2nd Gully Wall

Construct trench bund

along the reshaping

boundary

Basic gully treatment measures continued…

8/3/201536

Page 37: Gully assessment and prevention/control measures

8/3/2015

Page 38: Gully assessment and prevention/control measures

• Trenches are excavated into the undisturbed soil profile and

are therefore more stable than furrows

• Trenches do not collapse when walked on during watering

period

• Trenches need not be constructed exactly in the contour line

and therefore are more simple to construct – staggered

• Trenches harvest water and hold seedlings better than

furrows

• Watering of seedlings in trenches is more efficient than

watering of furrows

Basic gully treatment measures continued…

Page 39: Gully assessment and prevention/control measures

Basic gully treatment measures continued…

Planting reshaped gully with elephant grass

Page 40: Gully assessment and prevention/control measures

Looks very simple but amazing (Erosion control and water harvesting)

8/3/2015

Page 41: Gully assessment and prevention/control measures

Gabion checkdam filled with soil: These are gabion

checkdams filled with soil which are good alternatives in areas

where stone is not available – therefore, “No complain!!!” on

the non-presence of stones

8/3/2015

Plastic gabion filled with soils

Page 42: Gully assessment and prevention/control measures

8/3/2015

Page 43: Gully assessment and prevention/control measures

8/3/2015

Page 44: Gully assessment and prevention/control measures

Loose stone checkdams covered

with bamboo mat

Loose stone checkdam with apron and

parabolic spillway

8/3/2015

Page 45: Gully assessment and prevention/control measures

Gabion checkdam:

• Gabions are rectangular boxes varying in size and are mostly made of

galvanized steel wire woven in to mesh.

• The boxes are tied together with wire and then field with stone

and placed as building blocks.

• Gabion boxes are commonly used gully treatment, roadside

protection, dam construction, river training, retaining wall, etc.

• Gabion checkdams are built by placing the galvanized wire boxes

across gullies, “usually not higher than 1.5 m spillway height”

Page 46: Gully assessment and prevention/control measures

•Gully offset

•Gully bed

Gully head

Gullies have got four distinctive parts:

8/3/2015

Page 47: Gully assessment and prevention/control measures

Live checkdams can replace physical structures after a while8/3/2015

Page 48: Gully assessment and prevention/control measures

Stabilizing physical structures with biological measures8/3/2015

Page 49: Gully assessment and prevention/control measures

Green gold behind the Gabion checkdam8/3/2015

Page 50: Gully assessment and prevention/control measures

Popular or willow sticks can be plugged in to the plastic

for stabilization and additional biomass

8/3/2015

Page 51: Gully assessment and prevention/control measures

Roads foot paths, cattle trafficking lines, cattle routs, small, medium, and big roads

Watershed treatment and then road construction – after???

Do roads on the ridges only versus short cuts???

By road construction we are creating intervention to the natural (stable) system

Even here we can not harvest the whole water so control/ appurtenant structures are important

In high R/F areas see off the runoff well to its mother water course

There is evidence there is no problem on the approaching side, but on the leaving side

Drain checks, catch drains, etc.

Runoff diversion structures - with all its auxiliary structures

Gullies are major sources of sedimentation and infrastructural damages

RWH from roads is a noble idea - give priority to moisture stress areas –‘’two flies in one slam’’

8/3/2015

Gully Related to Road Drainage

Page 52: Gully assessment and prevention/control measures

8/3/2015

Page 53: Gully assessment and prevention/control measures

8/3/2015

Page 54: Gully assessment and prevention/control measures

8/3/2015

Page 55: Gully assessment and prevention/control measures

8/3/2015

Page 56: Gully assessment and prevention/control measures

ERA Bridges8/3/2015

Page 57: Gully assessment and prevention/control measures

8/3/2015

Page 58: Gully assessment and prevention/control measures

CONSTRUCTION OF CHECK SCOUR/ DAMS

8/3/2015

Page 59: Gully assessment and prevention/control measures

Cutoff drains should be properly connected to waterways

Stone paved sections of

a waterway

Drop structures

Scour checks

8/3/2015

Page 60: Gully assessment and prevention/control measures

Waterways should be provided with scour checks and drop

structures and covered with vegetation

8/3/2015

Page 61: Gully assessment and prevention/control measures
Page 62: Gully assessment and prevention/control measures

8/3/2015

Chute for steep slopes

Page 63: Gully assessment and prevention/control measures

On the road from

Kibuye to Kigali

8/3/2015

Page 64: Gully assessment and prevention/control measures

RUNOFF DIVERSION FROM ROAD CULVERTS CROP-CATA EDULIS (DIRE DAWA – BISHAN BEHE) – CHANNEL SOURCE

8/3/2015

Page 65: Gully assessment and prevention/control measures

What was the problem with these side drain checkdams?

8/3/2015

Page 66: Gully assessment and prevention/control measures

Check-dams/gully plugging structures

Mortar plastered gabion checkdams

Arecwier checkdams

Plastic gabion checkdams

SS-Dams

8/3/2015

Gully as a RWH Structure

Page 67: Gully assessment and prevention/control measures

Water Harvesting Check-dam

Water harvesting check dam: is a check dam

constructed in watercourses (i.e. rivers, streams,

gullies) to harvest surface runoff.

Water harvesting check-dams are primarily built for

two purposes :

to provide direct irrigation when rains fail (diversions)

to facilitate the recharging of surrounding wells and

springs through percolation of water from check-dams

(reservoirs).

8/3/2015

Page 68: Gully assessment and prevention/control measures

Major requirements

To harvest water in a gully

Treat the watershed properly and reduce the sediment

load

Put check-dams which can serve as sediment trapping

structures on the upper parts of the gully

Avoid water leakage through the foundation

Select appropriate site: suitable reservoir and command

areas

8/3/2015

Page 69: Gully assessment and prevention/control measures

Emphasis for water harvesting: Creating catchment area

8/3/2015

Page 70: Gully assessment and prevention/control measures

Bamboo mat (left) and soil filled (right) gabion check-dams

Existing experiences:

8/3/2015

Page 71: Gully assessment and prevention/control measures

Cont’d

Small barriers having tremendous effect in harvesting water

8/3/2015

Page 72: Gully assessment and prevention/control measures

• Arc-weir is a structure made up of stones connected with

mortar of cement and sand

• When properly constructed, it is highly resistant to greater

water pressure

• The structure is very susceptible to damage as a result of

runoff coming with boulders

• From technical and economic point of view its

importance for gully rehabilitation is very limited

Arcweir checkdams

Page 73: Gully assessment and prevention/control measures

Site / place for arcweir

checkdam

Enkulal

8/3/2015

Page 74: Gully assessment and prevention/control measures

Site / place for

arcweir checkdam

Alekt-Wenz

8/3/2015

Page 75: Gully assessment and prevention/control measures

Proper foundation is important for archweir construction

8/3/2015

Page 76: Gully assessment and prevention/control measures

8/3/2015Gravel filling in the foundation

Page 77: Gully assessment and prevention/control measures

The checkdam should be locked to each side of the gully 8/3/2015

Page 78: Gully assessment and prevention/control measures

Watering is necessary until it finishes its curing period8/3/2015

Page 79: Gully assessment and prevention/control measures

Properly constructed archweir

with apron

A lot of sediment is trapped already

and hence it is possible to plant on it

8/3/2015

Page 80: Gully assessment and prevention/control measures

Disadvantages of arch weirs:

• Need cement and special tools for masonry

• Need experienced masons/builders

• Need sand (sometimes difficult to get in the highlands)

• Regular shapes of stones are required (square or flat, not round)

• They are not cheap to build

Page 81: Gully assessment and prevention/control measures

Cont’d

Arc-weir structures have multiple functions

• They trap sediment and create new land in a gully

• Harvest water/moisture in the soil/sand

• Recharge ground watertable and maintain base flow

8/3/2015

Page 82: Gully assessment and prevention/control measures

Cont’d

Estimating the stored

water volume :

• Length = 40m

• Av. Width = 5m

• Av. Depth = 2m

• Volume = 40*5*2

= 400m3

This is more than the

volume of 3 HH ponds

8/3/2015

Page 83: Gully assessment and prevention/control measures

Gabion check-dams for water harvesting

Gabion check dams are used to plug gullies

In addition they can be used for water harvesting if

plastered with cement

8/3/2015

Page 84: Gully assessment and prevention/control measures

Gully as an opportunity rather than a threat

8/3/2015

Page 85: Gully assessment and prevention/control measures

8/3/2015

Page 86: Gully assessment and prevention/control measures

8/3/2015

Page 87: Gully assessment and prevention/control measures

8/3/2015

Page 88: Gully assessment and prevention/control measures

8/3/2015

Page 89: Gully assessment and prevention/control measures

8/3/2015

Page 90: Gully assessment and prevention/control measures

8/3/2015

Page 91: Gully assessment and prevention/control measures

8/3/2015

Page 92: Gully assessment and prevention/control measures

8/3/2015

Page 93: Gully assessment and prevention/control measures

8/3/2015

Page 94: Gully assessment and prevention/control measures

8/3/2015

Page 95: Gully assessment and prevention/control measures

8/3/2015

Page 96: Gully assessment and prevention/control measures

8/3/2015

Page 97: Gully assessment and prevention/control measures

Observed/measured changes and impacts

March 2012 August 2013

8/3/2015

Look the changes: Awzet gully, Farta woreda

Page 98: Gully assessment and prevention/control measures

8/3/2015

Page 99: Gully assessment and prevention/control measures

8/3/2015

Page 100: Gully assessment and prevention/control measures

Cont’d

March 2012 August 2013

8/3/2015

Page 101: Gully assessment and prevention/control measures

Cont’d

March 2012: Trainees presenting

outputs

August 2013: Impact on water

harvesting and biomass production

8/3/2015

Page 102: Gully assessment and prevention/control measures

Cont’d

Regeneration of endangered indigenous grass species (look the one with

brown pod)

8/3/2015

Page 103: Gully assessment and prevention/control measures

Cont’d

Even simple structures (brushwood) have pivotal role in rehabilitating the gully8/3/2015

Page 104: Gully assessment and prevention/control measures

Gully treatment in

Farta, Alekt Wenz CW

8/3/2015

Page 105: Gully assessment and prevention/control measures

Gully treatment in Farta,

Alekt Wenz CW8/3/2015

Page 106: Gully assessment and prevention/control measures

8/3/2015

Page 107: Gully assessment and prevention/control measures

Impact studies – hydrological

monitoring

Page 108: Gully assessment and prevention/control measures
Page 109: Gully assessment and prevention/control measures

Number of observations and samples in

MMP 2009 – 2012

Achievement: Significant hydrological database (Excel and HYDATA) housed at BoWRD

Achivements continued...

Page 110: Gully assessment and prevention/control measures

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00A

ug

Oct

Dec

Feb

Apr

Jun

Aug

Oct

Dec

Feb

Apr

Jun

Aug

Oct

Dec

Feb

Apr

Jun

Aug

Oct

Dec

2009 2010 2010 2011 2012

Sedim

ent co

nce

ntr

ation g

/l

Average monthly sediment concentration for all Stations (up to 2012)

Average all 17 stations Average Project Average Control

Sediment concentration analyses and results

n =

Achievement: Proof that watershed

management and gully plugging works!

Indicator 1: Does Sediment Concentration decrease?

Mmaximum monthly average

sediment concentraion from

14 g/l in 2010 to 8 g/l in 2012)

≈ 43%

Page 111: Gully assessment and prevention/control measures

Can watershed management....

.... reduce erosion?

Page 112: Gully assessment and prevention/control measures

Examples in Ethiopia–“Arego” from Kombolcha to Dessie on the left side

Page 113: Gully assessment and prevention/control measures
Page 114: Gully assessment and prevention/control measures

Model Watershed Development

Page 115: Gully assessment and prevention/control measures

Plateau treated with stone faced bunds

with runoff-runon system using C/CA

1:1 – tie ridging and stabilization along

bunds with legume trees/shrubs +

control grazing.

Escarpment under

closure + checkdams

on small gullies

Hillsides with trenches

and eyebrow basins C/CA

3-5:1 for trees +/- cash

crops in lower slopes.

SS dams in series + closure of

catchment area (plantation of

crops on SS dam based upon

sedimentation rate – start with

ring cultivation).

Farm dam for

livestock uses, fish,

etc.

Irrigated perimeters using hand-

dug wells (each for 0.1-0.25 ha

plots) – horticulture. Microponds

also possible, including in villages.

Large water pond based on

flooded area using percolation

dam (earth dam + gabion flow

structure). Cultivation during

the dry season on residual

moisture.

Stone bunds on upper parts

and stone faced soil bunds on

medium and lower slopes +

lateral spillways and gully

control. Bunds also stabilised

with legume shrubs.

Streambank

plantation and

stabilisation.

PWD: RECOGNIZING PEOPLE’S AND

WATERSHED POTENTIALS

Page 116: Gully assessment and prevention/control measures
Page 117: Gully assessment and prevention/control measures

Maccaferi Gabions

Page 118: Gully assessment and prevention/control measures
Page 119: Gully assessment and prevention/control measures
Page 120: Gully assessment and prevention/control measures

Gully planting & cultivation

Trench bundTrench bund

Vetiver Grass

Phalaris, Eragrostis curvula, other grasses

Elephant Grass Sesbania, Pigeonpea, Leucaena, Senna artemisioides etc.

Populus, Willow, Stink Bean etc. Shamboko, Elephant-, Bana-Grass, Green Gold, Sesbania etc.

Note: No row planting inside the gully bed!

Accacia, Graevillea, Senna

artemisioides, Saltbush etc.

Vision for gully rehabilitation

Prevention is better than cure

Page 121: Gully assessment and prevention/control measures

PROTECT AND ENJOY THE LANDSCAPE !!!

8/3/2015

Prevention is better than cure

Page 122: Gully assessment and prevention/control measures

Supported by: