hallandale beach, florida · proprietary and confidential © siemens industry investment grade...

160
Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013 City of Hallandale Beach – Volume 1 Investment Grade Energy Audit Updated by Siemens Industry, Inc. March 22, 2014

Upload: others

Post on 13-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 1

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

\[[

City of Hallandale Beach – Volume 1 Investment Grade Energy Audit Updated by Siemens Industry, Inc. March 22, 2014

Page 2: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

1. Table of Contents 1. Table of Contents ....................................................................................................................1

A. Schedule A - Equipment to be Installed by ESCO ...................................................................5

A.1. Lighting Retrofit..............................................................................................................5 A.2. Electric Rate Change at the Cultural Center ..................................................................... 10 A.3. Chiller Replacement at Municipal Complex ...................................................................... 11 A.4. VAV Box Replacement and Improved Return Air Flow at Municipal Complex ....................... 13 A.5. Chilled-Water RTU Replacement at Municipal Complex ..................................................... 15 A.6. Cultural Center RTU Replacements ................................................................................. 17 A.7. Plug Load Management ................................................................................................. 18 A.8. Twist Dial Timers for Guard House Spot Coolers ............................................................... 20 A.9. Upgrade Trane Tracer Software at Municipal Complex ...................................................... 21 A.10. DPW Administration HVAC Scheduling ......................................................................... 22 A.11. Building Envelope – Mechanical Insulation .................................................................. 23 A.12. Water Conservation ....................................................................................................... 25 A.13. Water Meters ................................................................................................................ 28

B. Schedule B - Description of Premises; Pre-Existing Equipment Inventory ............................ 42

B.1. Hallandale Beach Municipal Complex ............................................................................. 42 B.2. Hallandale Beach Cultural Center ................................................................................... 51 B.3. Fire Station #60 ............................................................................................................ 55 B.4. Fire Station #90 ............................................................................................................ 59 B.5. Hepburn Center ............................................................................................................ 62 B.6. DPW Administration ...................................................................................................... 66 B.7. DPW Garage ................................................................................................................. 69 B.8. Crew Quarters and Shop ................................................................................................ 72 B.9. Warehouse ................................................................................................................... 75 B.10. Sanitation West Parcel ................................................................................................... 76 B.11. Golden Isles Tennis Center ............................................................................................. 79 B.12. Three Islands Guardhouses ............................................................................................ 82 B.13. Golden Isles Guard House .............................................................................................. 83

C. Schedule C - Energy Savings Guarantee .............................................................................. 86

D. Schedule D - Compensation to ESCO ................................................................................... 87

D.1. ESCO Compensation / Project Costs ................................................................................ 87

E. Schedule E – Baseline Energy Consumption ........................................................................ 89

E.1. Municipal Complex ....................................................................................................... 92 E.2. Cultural Center ............................................................................................................. 93 E.3. Department of Public Works Administration Building ....................................................... 94 E.4. Crew Quarters .............................................................................................................. 95 E.5. Hepburn Center ............................................................................................................ 97 E.6. Fire Station 60 .............................................................................................................. 98 E.7. Golden Isles Tennis Center ............................................................................................. 99 E.8. DPW Warehouse .......................................................................................................... 102 E.9. Fire Station #90 .......................................................................................................... 103 E.10. Layne Boulevard Guardhouse ....................................................................................... 104 E.11. Three Islands Guards House ......................................................................................... 105

Page 3: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 3

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

E.12. Existing Water Utility Consumption and Costs ............................................................... 106

F. Schedule F - Savings Measurement and Calculation Formulae; Methodology to Adjust Baseline .................................................................................................................................. 114

F.1. Lighting Calculations ................................................................................................... 114 F.2. Occupancy Sensors Calculations .................................................................................. 114 F.3. Water Conservation Calculations .................................................................................. 114 F.4. Plug Load Management Calculations ............................................................................ 114 F.5. Chiller Replacement Calculations ................................................................................. 115 F.6. Cultural Center RTU Replacement Calculations .............................................................. 115 F.7. DPW Administration Calculations ................................................................................. 115 F.8. Others........................................................................................................................ 116 F.9. Methodology to Adjust Baseline ................................................................................... 116 F.10. Temporary Metering .................................................................................................... 119 F.11. Spot Metering ............................................................................................................. 120 F.12. Adjustments to Baseline and Guaranteed Levels of Savings ............................................ 120

G. Schedule G – Construction and Installation Schedule ....................................................... 122

H. Schedule H - Systems Start-Up and Commissioning; Operating Parameters of Installed Equipment ............................................................................................................................... 123

H.1. System Start-up and Commissioning ............................................................................ 123 H.2. Operating Parameters of Installed Equipment ............................................................... 129

I. Schedule I - Standards of Comfort .................................................................................... 132

I.1. TEMPERATURE............................................................................................................. 132 I.2. NOISE ........................................................................................................................ 132 I.3. LIGHTING ................................................................................................................... 132

J. Schedule J - ESCO's Maintenance Responsibilities ............................................................. 133

K. Schedule K - Agency's Maintenance Responsibilities ......................................................... 134

K.1. Lighting ..................................................................................................................... 134 K.2. Water Conservation ..................................................................................................... 134 K.3. Plug Load Management ............................................................................................... 134 K.4. Cultural Center Rate Change ........................................................................................ 134 K.5. Municipal Complex Chiller Plant ................................................................................... 135 K.6. Cultural Center RTU Replacements ............................................................................... 135 K.7. DPW Administration Programmable Thermostats ........................................................... 135 K.8. Commissioners Chambers VAV Replacements and Return Air Flow Improvements ............ 135 K.9. Twist Dial Timers ......................................................................................................... 136 K.10. Mechanical Insulation ................................................................................................. 136 K.11. Commercial Meters ..................................................................................................... 136

L. Schedule L - Facility Maintenance Checklist ...................................................................... 137

M. Schedule M - ESCO's Training Responsibilities ............................................................... 138

M.1. Plug Load Management ............................................................................................... 138 M.2. Building Automation System (BAS) Upgrade .................................................................. 138 M.3. Chiller & RTU .............................................................................................................. 138 M.4. Advanced Meter Infrastructure (AMI) ............................................................................ 138

N. Schedule N - Installment Payment Schedule ..................................................................... 142

Page 4: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 4

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

O. Schedule O - Final Project Cost & Final Project Cash Flow Analysis .................................... 143

Cashflow – Escalating Payments ............................................................................................. 144 Cashflow - Minimum Term ..................................................................................................... 145 Cashflow - Level Payments ..................................................................................................... 146

Exhibits ................................................................................................................................... 147

Exhibit I - Performance Bond/Construction Bond ...................................................................... 147 Exhibit II (i) - Certificate of Acceptance: Technical Audit ........................................................... 148 Exhibit II (ii) - Certificate of Acceptance: Installed Equipment .................................................. 149 Exhibit III - Equipment Warranties ........................................................................................... 150

Page 5: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 5

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

A. Schedule A - Equipment to be Installed by ESCO

A.1. Lighting Retrofit

The following sections describe the interior and exterior lighting scope of work proposed to the City for implementation. The sections are partitioned on retrofit type and facilities covered within that retrofit type.

REPLACE T-12 LIGHTING WITH T-8 TECHNOLOGY

Fluorescent lighting has been used for decades. T-12 fluorescent lamps with magnetic ballasts were once the standard of energy efficient lighting when compared to incandescent lighting. Through the years, improvements in technology have enabled greater energy efficiency in fluorescent lighting. These improvements allow for lower operating and maintenance expenses as well as better light output for building occupants.

The new standard of energy efficient lighting is T-8 fluorescent lamps. These lamps coupled with electronic ballasts draw approximately two-thirds of the power of comparable T-12 lamps with magnetic ballasts. Significant power consumption occurs in the ballast of T-12 lighting technology. The magnetic ballast acts as a transformer for incoming voltage, increasing the voltage and current to illuminate the lamp. T-8 lighting technology utilizes electronic ballasts with solid state devices to increase voltage; solid state transformers draw significantly less power when compared to standard wire coil type transformers.

In addition to increased energy efficiency, T-8 lamps with electronic ballasts offer significant improvements with regards to visibility and comfort. Many individuals complain of discomfort caused by fluorescent lighting. The cause of this discomfort is often due to T-12 lighting with magnetic ballasts. T-12 lighting technology is dependent on the frequency of incoming power; the standard power frequency in the United States is 60 Hertz (Hz). T-12 magnetic ballasts convert the incoming voltage from 60 Hz to 120 Hz. Therefore, light output and refresh rate on the lamp is occurring at 120 Hz – the human body can interpret refresh rates of up to 400 Hz. Thus, individuals who can sense the flicker of the T-12 lamp can feel discomfort. T-8 ballast technology converts the incoming 60 Hz voltage to 40 to 44 kilohertz (kHz). The T-8 lamp output and refresh frequency is significantly higher than what a human body can interpret; effectively eliminating any discomfort due to fluorescent lighting.

With the higher output frequency of the electronic ballast, T-8 lamps have a higher average lamp life than T-12 lamps. T-8 lighting also has a higher color rendering index (CRI) and color temperature when compared to comparable T-12 lighting.

The above retrofit is proposed at the following facilities:

• Cultural Center

Page 6: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 6

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Hepburn Center

• DPW Administration

• DPW Garage

• DPW Warehouse

RETROFIT OLDER T-8 LIGHTING WITH NEW GENERATION T8 LIGHTING

As indicated above, T8 fluorescent lighting is the new standard for energy efficient lighting. This retrofit proposes replacing older generation, 32 watt T8 lamps with the newer 25 watt or 28 watt T-8 technology. The lower light levels requirements in many spaces make the installation of lower watt lamps an ideal application.

The above retrofit is proposed at the following facilities:

• Municipal Complex Police Department

• Municipal Complex: Commissioner Chamber

• Municipal Complex: City Hall

• Cultural Center

• Hepburn Center

• Crew Quarters

• Warehouse

• Fire Station 60

REPLACE HID LIGHTING WITH T-8 TECHNOLOGY

High intensity discharge (HID) lamps are frequently used in storage spaces where lights are left on/off for longer periods (to avoid cycling lights on/off). Although the light output from HID lamps is clear and sharp, they have a high power draw, typically from 400-1100 Watts per fixture, and a long re-strike time. Re-strike time is the time required before the HID lamp can be re-lit, and ranges from 15-20 minutes. HID lamps have an average lamp life of 10,000 hours.

High bay T-8 fluorescent lamps provide clear and sharp lighting at a fraction of the power draw; average lamp life is 15,000 hours and they do not suffer from the long re-strike time.

The above retrofit is proposed at the following facilities:

• DPW Warehouse

• Fire Station 60

Page 7: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 7

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

REPLACE INCANDESCENT LIGHTING WITH COMPACT FLUORESCENT TECHNOLOGY

Incandescent light lamps are very energy inefficient; they create light by heating a thin wire filament which glows and gives off light. Interestingly, approximately 5% of the energy input creates the light while the remaining 95% of the energy input is converted to heat dissipated into the surrounding area. The filament has a life cycle of about 1,000 hours before it fails due to the heat.

A fluorescent lamp is much more energy efficient when compared to an incandescent lamp. Instead of using heat to provide light, the energy is used to excite vapor gas housed inside the bulb which then produces visible light. Because more energy goes into producing light rather than heat, fluorescent lamps are approximately 75% more efficient than incandescent bulbs of similar intensity. In addition to reducing energy consumption, fluorescent lamps have a life cycle 8 to 10 times that of incandescent lamps, or about 8,000 to 10,000 hours. A reduction in heat output can also be felt in the surroundings.

The above retrofit is proposed at the following facilities:

• Cultural Center

• Hepburn Center

• DPW Administration

REPLACE COMPACT FLUORESCENT OR INCANDESCENT LIGHTING WITH LED TECHNOLOGY

LED technology brings a host of benefits not realized in CFL and Incandescent lights. These benefits include longer life, greater energy efficiency, ecologically friendly, durability, light focus, instant on, and so on. This proposed retrofit takes advantage of lower wattage LED technology capable of replacing existing incandescent and compact fluorescent fixtures.

The above retrofit is proposed at the following facilities:

• Golden Isles Guard House

• Municipal Complex: City Hall

REPLACE HID LIGHTING WITH LED TECHNOLOGY

This proposed retrofit takes advantage of LED technology capable by replacing HID fixtures in a variety of spaces and usage settings.

The above retrofit is proposed at the following facilities:

• Municipal Complex Police Department

• Municipal Complex: City Hall

• Cultural Center

Page 8: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 8

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Hepburn Center

• Fire Station 60

INSTALL OCCUPANCY SENSORS

Occupancy sensors are recommended for “group” areas or work spaces where photocells are not feasible, such as meeting rooms, cafeterias, multipurpose rooms, classrooms and designated offices. In areas such as storage spaces that have gone from HID fixtures to fluorescent, occupancy sensors will be installed that can be adjusted to provide a shut off delay of up to twenty minutes to eliminate rapid or excessive cycling of lamps.

The use of photocells is recommended in areas where existing ambient light levels provide an opportunity for additional savings.

Occupancy based controls will be installed in vending machines with non-perishable snacks and beverages to reduce electrical consumption during low occupancy periods.

The above scope is proposed at the following facilities:

• Municipal Complex

• Cultural Center

• Hepburn Center

• DPW Administration and Garage

• Warehouse

• Fire Station 60

SAVINGS FROM LIGHTING IMPROVEMENTS

A detailed room by room survey of lighting fixtures, types, wattage, etc. was performed during the audit to accurately assess the existing lighting type and quantity; the results are contained in the Appendix. Also in the Appendix are the results of the data logging sessions, sorted by space type (common areas, computer rooms, hallways, conference rooms, etc.), and the space operating hours.

The energy and cost savings were developed using the Carrier HAP energy simulation software package (energy modeling) and verified through spreadsheet analysis. The inputs used in the post-implementation model included the higher efficiency lighting fixtures (lower wattage), runtime reductions to match the data logging data for actual occupancy, occupancy sensors, etc.

The table below illustrates a sample of the results obtained from the measured data.

Page 9: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 9

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HEPBURN CENTER: LIGHTING VS. OCCUPANCY DATA

The electrical load reductions as a result of the lighting retrofits also reduces the heat load from the existing lighting fixtures. This reduction in heat provides additional savings due to the reduced required capacity of the HVAC equipment. The cooling benefit is accounted for in the savings for of this facility improvement measure and is calculated with the function of the energy model. Detailed savings calculations are available in the Appendix.

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)*

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

64,508 141.6 $4,770 $138

Cultural Center 56,535 139.6 $4,666 $67

Hepburn Center 53,929 120.7 $4,391 $81

Admin & Garage 39,441 101.7 $3,377 $35

Crew Quarters 20,068 43.7 $1,615 $18

Golden Isles GH 5,951 - $589 $21

Warehouse 13,721 - $1,356 $11

Fire Station 60 109,613 181.5 $8,129 $148

Totals 363,765 728.8 $28,893 $520

*NOTE: The presented Demand savings values are the simulated total over a twelve month period. Demand savings will vary from month to month.

MEASUREMENT AND VERIFICATION – LIGHTING

The Measurement and Verification (M&V) for the Lighting Retrofit and Occupancy Sensor Facility Improvement Measure (FIM) will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key

Page 10: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 10

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.2. Electric Rate Change at the Cultural Center The Municipal Complex is currently on a Florida Power and Light (FP&L) Commercial/Industrial Load Control Program (CILC-1(G)) electric rate structure. This rate structure provides lower consumption and demand charges to coincide with peak/seasonal demand. In return for the lower rates, FPL reserves the right to reduce or suspend electric service for a pre-determined period of time, and with advance warning.

To avoid complete electric shutdown, the facility must be equipped with a generator capable of providing 100% back up power.

1000 kW Backup Generator

The generator installed for the Municipal Complex is large enough to provide backup power for both the Municipal Complex and the Cultural Center. Both buildings are connected to an automatic transfer switch that activates the generator and bypass the electrical source feed for the building to the generator, should power interruption every occur.

Unlike the Municipal Complex, the Cultural Center is on a General Service Demand (GSD-1) rate, which has higher consumption and demand rates than the CILC rates. Although the Cultural Center has 100% backup generation, it does not qualify for the CILC rates because annual peak demand usage of the Cultural Center is roughly 100 kW while the CILC rate structure requires a minimum of 200 kW.

ELECTRIC RATE CHANGE PROJECT SCOPE

This FIM combines the electric feeds to the Municipal Complex and the Cultural Center into one electric meter so the Cultural Center can be billed at the lower CILC rate. An electric submeter will be installed for each building to allow the Finance Department to monitor and internally bill the corresponding departments. The submeter will communicate with the existing Building Automation System (BAS) to provide monthly

Page 11: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 11

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

electric consumption values. This data will be used by the City to accurately divide the FPL electric bill between the Municipal Complex and the Cultural Center.

SAVINGS FROM RATE CHANGE

The energy and cost savings were developed using an energy model and verified with spreadsheet analysis. Both the Municipal Complex and Cultural Center energy models were calibrated to closely match the baseline billing data, and the Cultural Center annual usage profile was adjusted to match the CILC rate structure. The difference between the original profile and the adjusted profile determined the dollar savings associated with this FIM. Since this FIM is strictly a rate change, there are no electrical consumption or demand units saved. Energy model results are provided in the Appendix of this report.

The resulting dollar savings is for this FIM $2,074.

MEASUREMENT AND VERIFICATION – RATE CHANGE

The Measurement and Verification (M&V) of the Electric Rate Change FIM will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.3. Chiller Replacement at Municipal Complex Chillers are the single largest energy consumers in commercial buildings with peaks in electrical power usage during hot summer afternoons. Most chiller plants are oversized for capacity, but even properly sized chillers operate most of the time at low, part-load efficiencies.

As detailed in the Existing Conditions section of this report, the Municipal Complex utilizes two (2) Trane air-cooled chillers, each with two compressors – one chiller at approximately 90 tons and the other at approximately 80 tons of capacity. Chiller #1 operates 24 hours a day and varies in the number of compressors used, and Chiller #2 comes on as needed when the building load is high enough to require additional cooling capacity. Data logging has revealed that Chiller #2 seldom runs.

Both chillers are original to the building, and were installed in 1994. The chillers are at the end of their useful life and are showing signs of wear from weather and outdoor conditions. Chiller #1 was observed operating at 120% current limit, had two (2) condenser fans that were not operational, water leaks, and deteriorating insulation.

Page 12: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 12

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Air-Cooled Chiller Conditions

A.1.A. CHILLER REPLACEMENT SCOPE

This FIM recommends replacing Chiller #1 with a 130 ton, high efficiency air-cooled chiller with variable speed screw compressors. We recommend keeping Chiller #2 in place to achieve redundancy for the chiller plant. The higher efficiency chiller will be installed in the same location as the existing machine, and the pumps, piping and electrical service will not require alterations. The new chiller will be connected to the building automation system and will be controlled to maximize the part load efficiencies associated with this new machine.

SAVINGS

The energy and cost savings were developed using an energy model. Savings are realized from increased operating efficiencies and maximizing the control capabilities of the building automation system and the chiller’s part load efficiencies. The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

194,134 513.95 $15,161 $4,637

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of the Municipal Complex Chiller Replacement FIM will be International Performance Measurement and Verification Protocol (IPMVP) Type A: Retrofit Isolation: Key Parameter Measurement. The key parameter to be measured is kW/ton. The Building Automation System is capable of collecting the data necessary to determine kW/ton efficiency values of the new machine. The existing chiller’s kW/ton value will be accepted as part of the energy model calibration. A Detailed M&V Plan is available in the contract document, Exhibit C.

Page 13: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 13

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

A.4. VAV Box Replacement and Improved Return Air Flow at Municipal Complex

The Commissions Chambers at the Municipal Complex is cooled by the same chilled-water RTU that cools the Police Department, a 24 hour a day operation. While cooling for the Police Department is a 24 hour operation, the Commission Chamber is used an estimated 20 hours a month.

As reported earlier, many components of the air distribution system have fallen in disrepair, including the two (2) VAV boxes responsible to regulating temperature in the Chamber. This has resulted in the 24-hour cooling of this space as well as frequent reports of discomfort by occupants that are too cold.

It is important to note that we suspect that many of the VAV boxes at the Municipal Complex may also be inoperative, but the scope of this project did not support investigating improvements with little to no savings component.

While investigating this issue the City informed Siemens that the Chambers also lacked return air ductwork. The second floor above the Chambers and Police Department is an open plenum for return air to travel back to the RTU for mixing and re-conditioning. The Chambers is separated from the Police Department, on the first floor, by an exterior breeze way. Although the original construction plans called for return air ductwork to connect the two spaces, this ductwork was never installed (see picture below on left). Return air is, however, able to leave the Chambers through two large fire dampers located above the Chamber’s ceiling. This allows return air to use the free plenum above the ceiling tiles as a path back to the RTU (see picture below on right).

With assistance and guidance of City staff, and upon further investigation, we found that Chamber’s return air has a path to leave the space, but does not have a path back to the RTU – return air flow is blocked by hallway fire walls and east half of the Police Department’s second floor. The illustration below shows the fire walls in red and restricted flow of the return air in the building.

Page 14: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 14

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

VAV AND AIR FLOW FIM SCOPE

The scope includes replacing or repairing the two inoperable VAV boxes for the Chambers. New or refurbished VAVs will allow the system to modulate the amount of conditioned air that enters the space, the temperature of supply air, and the cooling times. The new VAVs will be reconnected to, and controlled from, the building automation system. City staff will be responsible to schedule the VAV usage as needed based on scheduled meetings and duration. The intentions are to command the VAV dampers to open one hour before a scheduled meeting in order to pre-cool the space and to return to a minimum damper position one hour after the meeting has concluded.

In addition to the new VAV boxes, the fire walls restricting the flow of return air back to the RTU will be equipped with fire dampers. Fire dampers are approved openings in fire walls that are designed to close with high temperatures/heat. Dampers will remain open otherwise.

Page 15: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 15

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

SAVINGS

The energy and cost savings were developed using the Carrier HAP energy model. The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

45,003 167.2 $4,136 $124

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of this FIM will be International Performance Measurement and Verification Protocol (IPMVP) Option E: Stipulated. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.5. Chilled-Water RTU Replacement at Municipal Complex The Ebtron flow stations in the chilled-water RTU serving the Police Department and Commissioners Chambers has not been operational for several years. Flow stations modulate the flow of outside air into the unit by varying the positions of the outdoor air damper. Outdoor air is brought into building to achieve the proper number of air turnovers to achieve desired indoor air quality levels. The number of air turnovers can depend on building occupancy, cooling load requirements, or time of day. With the replacement of the outdoor air flow stations, outside air flow can be properly monitored and controlled. By properly scheduling the amount of outside air conditioned, based on demand, less unconditioned air needs to be cooled. The reduced cooling requirements imposed on the unit produces energy savings.

Existing Ebtron Flow Station

In addition to failed flow stations, the RTU itself has reached the end of its useful life. Many panels on the unit have rusted out allowing significant amounts of infiltration. The failed control valve has resulted in water leaks and biological growth on its exterior. Door panels on the supply air side leak significant amounts of conditioned

Page 16: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 16

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

air, which reduces the amount of conditioned air put into spaces. This forces the RTU to work more than necessary.

Due to the units deteriorated condition, the unit is prohibited from operating beyond 50 Hz due to its tendency to vibrate and shake the steel stand it sits upon. The steel stands also show signed of deterioration and rust.

Deteriorating Chilled-Water RTU

PROJECT SCOPE

This FIM will replace the chilled-water RTU and the Ebtron flow station at the Municipal Complex. The energy models indicated that the current use of variable frequency drives effectively limits the intake of outdoor air during unoccupied periods. The RTU is currently controlled based on temperature feedback from the VAV thermostats. As occupancy increases, thermal and ventilation load increase. The VFDs react accordingly and, in effect, accomplish the same goal intended by the replacement of the Ebtron flow station. This FIM, therefore, addresses the replacement of the RTU, as it was originally installed, based on structural and equipment need.

SAVINGS

The energy and cost savings were developed using an energy model. Savings are realized from resuming control of operational flow stations to allow the proper amount of outdoor air into each air handling unit based on time of day needs.

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

- - - $9,367

MEASUREMENT AND VERIFICATION

This measure does not require measurement and verification efforts.

Page 17: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 17

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

A.6. Cultural Center RTU Replacements Packaged DX roof top units’ (RTUs) lifetimes vary depending on the types of fans and coils, and on maintenance practices. Typically, RTU motors, dampers, and coils last between 10 and 15 years before requiring replacement. The same applies to split direct expansion (DX) systems, rooftops units, and air-cooled condensers. Water damage due to condensation and rain infiltration is common in such equipment and also reduces the expected lifetimes.

Replacement of HVAC equipment is a high cost improvement measure that typically is vital when the current units have reached the end of their useful lifetime. Financial paybacks are traditionally longer for this improvement measure but should not be judged solely on their economic feasibility due to their critical function in the overall building’s HVAC system.

PROJECT SCOPE

Most of the RTUs at the Cultural Center are 1997 vintage. These have been identified for replacement based on age, efficiency and condition. The remaining units are either new or have not reached the end of their useful life; replacing these units is not economically beneficial.

The following are the 1997 RTUs that have been identified for replacement:

• Unit Serving Kitchen

• Unit Serving Administration Offices,

• Three (3) Units Serving Auditorium

• Unit Serving West Wing Rooms,

• Unit Serving Restrooms and Hallways

Each of the above mentioned units are Carrier models of approximately 11 SEER efficiencies. These will be replaced with 15 SEER Carrier models of the same size to ensure proper alignment with the existing footprints.

SAVINGS

The energy and cost savings were developed using an energy model and verified with spreadsheet analysis. Savings are realized from the improved, higher efficiency of the new RTUs.

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Page 18: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 18

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Cultural Center 21,703 95 $2,110 $4,042

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of RTU Replacements at the Cultural Center will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.7. Plug Load Management Miscellaneous plug loads such as copiers, computers, computer screens, coffee machines, and water fountains can make up a substantial portion of a building’s energy consumption. And while some of these loads may operate efficiently in standby during unoccupied periods, many plug load devices leak significant energy in standby or off mode. BERT, which stands for Best Energy Reduction Technologies, is a patented Wi-Fi based solution that automatically and remotely controls and schedules plug load devices to turn on/off during unoccupied hours.

BERT controllers function with a built in relay that severs the electrical connection between the device and the electrical receptacle. Should use of the device become necessary, each BERT controller is equipped with an override button to release the connected device from its OFF command. The BERT units will not turn off again until the next scheduled shut-off time.

In order to identify plug-load devices suitable for Bert, data logging sessions where conducted on a variety of plug-load devices at the following facilities (facilities with the largest plug loads): Municipal Complex, Hepburn Center, and DPW Administration Building. Following list are devices that are generally good candidates for Bert, and that were logged during the audit.

• Water Fountains

• Workstations with Monitors

• Laptop with Docking stations

• Printers

• Vending Machines

• Letter Sorter

• Coffee Maker

The results of the data logging are provided in the Appendix of this report.

PROJECT SCOPE

Page 19: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 19

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

This facility improvement measure (FIM) is the installation of wireless Bert controllers and integration into the existing Wi-Fi Network; scheduling for BERT will be managed from a central computer.

The data collection process identified many devices that do not warrant BERT; many City employees shut off equipment at the end of the work day. Energy leaks through electric receptacles are not significant enough to produce energy savings of value.

However, several devices would benefit from BERT equipment such as:

• Municipal Complex – Printers (large and small)

• Hepburn Center – Printers and drinking fountains

• DPW Administration Building – Printers and Coffee Maker

The quantities and locations of the BERT equipment is provided within the Appendix, along with calculated energy savings. The schedules associated with the equipment are as follows:

• Municipal Complex – OFF from 6PM to 7AM (Monday through Friday ) and OFF Saturday and Sundays

• Hepburn Center – OFF from 9PM to 7AM (Monday through Friday ) and OFF Saturday and Sundays

• DPW Administration Building – OFF from 6PM to 6AM (Monday through Friday ) and OFF Saturday and Sundays

SAVINGS

The energy and cost savings were developed using the Carrier HAP energy model and verified with spreadsheet analysis. Savings are generated by eliminating the power draws of each plug-load device during scheduled off times.

Page 20: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 20

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year

Dollar Savings

Municipal Complex 10,978 $465

Hepburn Center 1,828 $90

DPW Administration 1,540 $76

Totals 14,346 $631

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of the Plug Load Management FIM will be International Performance Measurement and Verification Protocol (IPMVP) Type A: Retrofit Isolation: Key Parameter Measurement. BERT controllers, specifically equipped with data collection/measurement capabilities, will be utilized to measure energy savings. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.8. Twist Dial Timers for Guard House Spot Coolers The two guard houses on Three Islands Boulevard utilize plug-in spot coolers for air conditioning that were found operating during unoccupied times. However, only the guard house on Three Islands Blvd was found operating for extended periods.

Spot Cooler Left Running

PROJECT SCOPE

This facility improvement measure (FIM) will install a 60 minute twist-dial timer to operate the spot coolers located at the guard on Three Islands Blvd. As mentioned above, the energy model dictates that the spot cooler at the Atlantic Blvd. Guard House is not warranted.

Page 21: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 21

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

SAVINGS

The energy and cost savings were developed using the Carrier HAP energy model. Savings are realized by preventing the spot coolers from running during those times when a guard or police officer is not occupying the guard house.

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year

Dollar Savings

Three Islands Guard House 332 $32

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) for the Twist Dial Timers FIM will be International Performance Measurement and Verification Protocol (IPMVP) Option E: Stipulated. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.9. Upgrade Trane Tracer Software at Municipal Complex The Municipal Complex HVAC equipment is controlled using a building automation system (BAS), a Trane Tracer 100, installed during construction in 1994. The system is operating as intended although the graphical user interface is very outdated; the City has requested that Siemens upgrade the system.

PROJECT SCOPE

The Tracer 100 will be replaced while allowing existing unit controllers to remain in place. Unit controllers will remain on the old communication bus but can be replaced new BACnet controllers upon controller failure.

The upgrade to the control system will provide a BACnet system which will be a web based graphical user interface. The City will need to provide an internet access connection for remote connectivity. This scope provides for a dedicated Ethernet network (City to provide Static IP) for the System Controllers (SC’s) including installation.

The new system will include the following only:

• Enterprise Server

• Web Enabled Building Controller

• Legacy Protocol to BACnet

Page 22: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 22

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Installation of new bridge controller to communicate between legacy controllers and BACnet building controller

• Installation of new building controller

• Programming and Startup of the new control system

• Set up of trend logs for each piece of equipment

• 3D Graphics to include ( Exterior Home page, Chiller System, HVAC Equipment, Up to 2 Floor Plans)

• Training (8 hours)

• Engineering and Engineered control drawings

SAVINGS

There is no energy savings associated with this measure. The following table represents the calculated capital avoidance:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

- - - $2,647

MEASUREMENT AND VERIFICATION

This measure does not require measurement and verification plan.

A.10. DPW Administration HVAC Scheduling Cooling for the Administration Building is provided by two (2) split DX units. Both are Rheem units, with electric heat capabilities, installed in 2002 and 2009. Each unit is responsible for cooling half of the first floor where the administration offices are located.

The two DX units providing conditioned air to the DPW Administration Building are controlled by wall mounted thermostats. Each unit cools its respective area until the temperature set point of its thermostat is met. Both thermostat control systems are cooling the spaces during unoccupied hours, as evidenced in the data logging results depicted below.

Page 23: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 23

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

PROJECT SCOPE

RTU control equipment will be installed for the units serving the DPW Administration Building. Each cooling unit will be controlled based on time and occupancy patterns obtained from administrative and maintenance personnel.

SAVINGS

The energy and cost savings were developed using the Carrier HAP energy model. In the analysis the electric load of the HVAC equipment is measured and/or estimated and scheduled to match the facility’s occupied hours.

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

DPW Administration

4,004 -11.4 $70 -

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of HVAC scheduling will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.11. Building Envelope – Mechanical Insulation Proper insulation reduces distribution losses in heating and cooling systems; good insulation should be in place on all chilled water, hot water, and air distribution ductwork. Replacing inadequate insulation and installing removable insulating jackets

Page 24: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 24

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

is low cost way to improve energy efficiency – the benefits include reduced unwanted heat transfer and lower re-circulating pump power requirements.

Siemens evaluated the performance of the Domestic Hot Water system to identify and assess areas that were not properly insulated. This included systems that were insulated with fiberglass and expanded foam insulations. The following are the results of this evaluation.

Municipal Complex Domestic Hot Water

Hepburn Center Domestic Hot Water

Fire Station #90 Domestic Hot Water

PROJECT SCOPE

This FIM will install the following mechanical insulation.

• Domestic Hot Water - installation of Type A: Knauf 1000° Pipe Insulation

Page 25: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 25

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

o Interior exposed above ambient temperature pumps – installation of Type A: Knauf Fiberglass, Kwikflex Pipe & Tank Insulation

SAVINGS

The energy and cost savings were developed using an energy model. The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Demand

Savings (kW)

First Year

Dollar Savings

Annual Cost Avoidance

Municipal Complex

1,605 3.8 $116 -

Hepburn Center 199 0.95 $28 -

Fire Station 90 317 - $31 -

Totals 2,121 - $175 -

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of Mechanical Insulation will be International Performance Measurement and Verification Protocol (IPMVP) Option E: Stipulation. A Detailed M&V Plan is available in the contract document, Exhibit C.

A.12. Water Conservation This FIM addresses the reduction of water consumption, wastewater production, and hot water energy use through the installation of high efficient plumbing products and controls. The water efficiency devices are detailed below and were selected for their efficiency, durability, minimal maintenance requirement, and improved hygiene.

All of the retrofits meet or exceed the Energy Act of 1992, which mandates the use toilets with 1.6 gallons per flush, showerheads that consume no more than 2.5 gallons per minute, and faucets that deliver less than or equal to 2.0 gallons per minute.

PROJECT SCOPE

Staff and Public Restroom Faucets: Installation of 0.5 gallon per minute (GPM) flow restrictors on faucets currently equipped with 2.0 to 3.0 GPM flow restrictors. The flow restrictors will be tamper proof requiring special keys for removal for any necessary maintenance; maintenance keys will be supplied to the maintenance group. Additionally, current faucets will be repaired and/or replaced as necessary to eliminate leaks. This scope is applicable at the following facilities:

• Hepburn Center

Page 26: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 26

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• DPW Administration

• Garage

• Crew Quarters

• Golden Isles Guard House

General Purpose Sinks: Installation of 1.5 GPM flow restrictors on faucets currently equipped with 2.0 to 3.0 GPM flow restrictors. The flow restrictors will be tamper proof requiring special keys for removal for any necessary maintenance; maintenance keys will be supplied to the maintenance group. Additionally, current faucets will be repaired and/or replaced as necessary to eliminate leaks. This scope is applicable at the following facilities:

• Crew Quarters

• Golden Isles Tennis Center

• Fire Station #60

• Fire Station #90

Single Spigot Cold Only Faucets: Replace single spigot, cold only faucets with delay close (push button) faucet. The push button faucets are designed to deliver ample water for washing hands while eliminating the possibility of leaving the faucet running. This scope is applicable at the following facilities:

• Golden Isles Tennis Center

Water Closet: Replacing 3.5 to 5.0 GPF water closets with 1.28 gallons per flush (GPF) water closet and flush valve. The new fixtures with Sloan flush valves are engineered to ensure they provide flushing performance that meets or exceeds ASME and ANSI performance standards for low-consumption toilets. These toilets are designed with large fully glazed trapways and a state-of-the-art siphon jet system to break up and keep the waste moving without blockage. This scope is applicable at the following facilities:

• Golden Isles Tennis Center

Tank Toilet: Installation of 1.0 gallons per flush (GPF) pressurized tank toilets in place of existing equipment that currently consumes 3.5 GPF. This scope is applicable at the following facilities:

• DPW Administration

Urinal: Installation of 0.5 or 1.0 GPF flush valve (dependent on urinal type). Urinals requiring this retrofit are currently consuming 1.5 GPF or more; the new flush valves will cut the current consumption in half and still provide ample water for flushing the fixture. This scope is applicable at the following facilities:

• Golden Isles Tennis Center

Page 27: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 27

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Showers: Installation of high performance, low flow showerheads. The existing 2.5 to 5.0 GPM showerheads will be replaced with 1.5 GPM heads, and shower valves will be repaired and/or replaced as necessary to eliminate leaks. This scope is applicable at the following facilities:

• Garage

• Crew Quarters

• Golden Isles Tennis Center

• Fire Station #60

Food Service Sinks: The food service sinks will be retrofitted with hands free foot pedal faucet controllers. These pedals will eliminate existing faucet leaks as well as help prevent the user from walking away from the sink while the water running. Most customers prefer the Pedal Valve controls since they eliminate the need to touch the faucet controls and so eliminate hand contamination at the faucets. Pedal Valve controls will be equipped with a locking mechanism for those applications where an unattended constant flow is necessary. This scope is applicable at the following facilities:

• Hepburn Center

Ice Machines: Installation of Vizion Chill heat exchanger on ice machine. This retrofit will pre-cools incoming water by recovering the energy from the purged ice water exiting the ice machine. Reducing the incoming water temperature directly lowers the cooling load of the icemaker’s refrigeration system and improves performance. This scope is applicable at the following facilities:

• Hepburn Center

• Crew Quarters

• Fire Station #60

Disposition of Removed Equipment: All existing equipment will be removed and properly disposed or recycled by the contractor. Due to the probability and nature of contamination of the removed equipment, future use of the materials is not recommended and the material will not be made available for surplus.

SAVINGS

The energy and cost savings were developed using spreadsheet modeling as Carrier HAP energy models are not suitable for calculating water conservation measures outside the confines of HVAC chilled-water applications. The detailed saving analysis is provided in the Appendix.

Page 28: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 28

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The following table represents the calculated energy savings:

Facility First Year Energy

Savings (kWh)

First Year Water Savings (gal)

First Year Dollar Savings

Annual Cost Avoidance

Hepburn Center 3,340 31,170 $376 -

DPW Administration 278 33,915 $244 -

Garage - 4,332 $22

Crew Quarters 3,061 10,379 $209 -

Golden Isles Tennis 1,113 191,322 $1,278

Golden Isles GH - 943 $6 -

Fire Station 60 1,948 7,559 $272 -

Fire Station 90 - 292 $2 -

Totals 9,740 279,914 $2,410 -

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of this Water Conservation FIM will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C. The hot water electric savings will use Option E: Stipulated.

A.13. Water Meters The fundamental principle behind this FIM lies in recovering some of the apparent losses in the City’s water system. Apparent losses per the American Water Works Association (AWWA) are the losses in water system operations due to meter inaccuracies, systematic data errors, and/or unauthorized consumption. This FIM will focus on recovering apparent losses in the observable decline in measurement accuracy of water meters over time and the ability to reduce operational cost associated with reading water meters. The factors affecting the decline of water meter accuracy are measurable and repeatable, which allows the resulting increase in billed meter consumption to be predicted in the future. The operational savings resulting from the installation of an AMI system are easily calculated and the numerous benefits are realized by both the City and its citizens.

The major factors influencing decline in water meter measurement accuracy are cumulative quantity of water measured through the meter over its service life and the quality of the metered water. Meter age is also a factor contributing to meter accuracy decline, but it is a secondary factor to the two factors mentioned above. Subsequently,

Page 29: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 29

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

age is typically not considered a primary factor in determining expected meter accuracy.

The white paper entitled, “Residential Water Meter Replacement Economics“, by S. E. Davis, Sacramento, CA, 2005, is a case study of an Arizona based water district where the specific factors of cumulative water measured and meter age were evaluated in relation to one another. The conclusion of the paper was that cumulative water measured can be clearly shown as the most determining factor in estimating meter measurement accuracy. Age has historically been the parameter used as a simple benchmark used by meter manufacturers to gage meter wear, but age alone is not the most influential factor.

Accordingly, the technical basis for this FIM resides in Siemens’ practical ability to accurately discern the status of existing meter accuracies from an analysis of existing historical meter records and through meter accuracy tests performed on existing field water meters. These two parameters sufficiently benchmark existing meter conditions within a given water authority. Relying on the proven relationship between physical predictability in meter accuracy as a function of cumulative water measured, a profile or model of the efficiencies of the existing water district meter infrastructure can be constructed with confidence.

Additionally, the predictability of future meter accuracy declines within newly installed meters can be benchmarked using the same methodology described above. A process can be developed that enables Siemens to develop payback, and measurement & verification (M&V) criteria around this FIM. Because of this, Siemens can guarantee and support this FIM.

Siemens guarantees increased accuracy in water meter readings through a replacement strategy of older existing water meters. Increased meter accuracy in turn has the effect of increasing the water revenue for the City. The increased billed metered consumption is further enhanced by an associated increase in sewerage charges where the charges are based on the measured water consumption. As the water billed metered consumption increases due to more accurate measurements, the sewerage charges also increase.

The benefits for municipalities implementing this FIM are:

• Revenue enhancement to the municipal water authority;

• Operational cost savings;

• Cost avoidance of future meter failure;

• More accurate billing;

• Recovered revenue;

• Fairness (new water customers do not bear the higher proportion of costs);

• Risk reduction/persistence of revenue;

• Reduction in labor requirements;

• Financial solution to funding issues;

Page 30: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 30

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Real-time data and meter reads;

• Enhanced customer service for their citizens.

Advanced Metering Infrastructure (AMI) is an innovative technology that allows water authorities to take multiple meter readings simultaneously, remotely and to various levels of automation, thereby reducing additional costs associated with reading meters. This fixed-based technology uses fixed based antennas that receive transmissions from all water meters in the service area. This data is then sent to a centralized location within the City where it can be used for billing, analysis, and resolving customer service issues. The system collects all meter readings daily and requires the least effort to perform these tasks.

In addition to the operational costs associated with meter reading, additional cost savings can also be realized through reductions in customer meter inventories. This is attributable to the standardization around the newly installed meters. The Siemens meter warranty and replacement guarantee would not necessitate high meter inventories for the staff to accommodate meter failures.

PROJECT SCOPE

Siemens recommends replacing the water meters currently found at each location with a new water meter with transponder for remote communication. With this system, the City can read the meters from a single point computer workstation without leaving a central site location. Each meter reading is stored in the reading equipment and sent to the main server when called upon. The data is then converted and synchronized with the billing software and the bill is generated. The AMI technology will have a significant and positive impact on operational costs, reading errors, worker compensation costs, risk and liabilities, thus meter reading efficiency is significantly improved.

The turnkey solution proposed by Siemens includes:

• Replacement of water meters with new units. All necessary auxiliary equipment such as curb stops, lids, nuts, boxes, bolts, and gaskets to be provided as required;

• Installation of fixed based AMI system;

• Download of billing account data from the billing system;

• Installation of meter endpoints;

• Programming of meter endpoints;

• Installation of all data collection units on existing water tower

• Installation of 60’ poles at one locations;

• Installation of system software;

• Capture and recording of GPS coordinates for each meter location;

Page 31: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 31

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Upload of all critical billing account data into the billing system;

• Training & administrative support prior to project completion to ensure a functional system;

• Commissioning/verification of the system.

Table below shows the meter quantities that Siemens will install during the implementation phase of this project.

METER QUANTITIES AND TYPES

Qty Size Type

4,605 5/8” Sensus iPERL Meter with 520M SmartPoint Transmitter

1,425 1” Sensus iPERL Meter with 520M SmartPoint Transmitter

387 1.5” Sensus OMNI R2 Meter with 520M SmartPoint Transmitter

407 2” Sensus OMNI R2 Meter with 520M SmartPoint Transmitter

31 3” Sensus OMNI C2 Meter with 520M SmartPoint Transmitter

8 3” Sensus OMNI T2 Meter with 520M SmartPoint Transmitter

52 4” Sensus OMNI C2 Meter with 520M SmartPoint Transmitter

3 4” Sensus OMNI T2 Meter with 520M SmartPoint Transmitter

18 6” Sensus OMNI C2 Meter with 520M SmartPoint Transmitter

4 6” Sensus OMNI T2 Meter with 520M SmartPoint Transmitter

11 6” Sensus OMNI F2 Meter with 520M SmartPoint Transmitter

5 8” Sensus OMNI F2 Meter with 520M SmartPoint Transmitter

2 N/A Sensus M400 Base Stations

SAVINGS

During project development, water meters were chosen among the overall population of meters within city limits; the figured below shows the locations of the test meters. The meters were removed and transported to a third party laboratory for accuracy testing.

Page 32: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 32

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Figure – Location of Test Meters

The selection of meters to be tested within each size group was done randomly and the laboratory tests in accordance with AWWA guidelines. Each meter was tested at three different flow rates as specified by AWWA for different meter sizes and types. The average meter accuracy was calculated as a weighted average, with weights of 15% for the low flow, 70% for the intermediate flow, and 15% for the high flow. The following tables show the results of the water meter tests.

Page 33: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 33

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

WATER METER TEST RESULTS (5/8”)

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%) Weighted Average Accuracy

(%)

SENSUS 70,948,540 263,440 0.25 95.0% 2.00 100.0% 15.00 100.0% 99.3%

SENSUS 72,308,463 117,860 0.25 96.0% 2.00 99.0% 15.00 99.0% 98.6%

SENSUS 70,024,312 186,230 0.25 96.0% 2.00 101.0% 15.00 100.0% 100.1%

SENSUS 73,305,479 66,520 0.25 97.0% 2.00 101.0% 15.00 100.0% 100.3%

SENSUS 70,024,304 150,880 0.25 95.0% 2.00 100.0% 15.00 99.0% 99.1%

SENSUS 41,907,951 98,570 0.25 96.0% 2.00 100.0% 15.00 99.0% 99.3%

SENSUS 68,342,232 73,760 0.25 95.0% 2.00 101.0% 15.00 100.0% 100.0%

SENSUS 30,350,498 149,360 0.25 93.0% 2.00 100.0% 15.00 99.0% 98.8%

SENSUS 22,343,779 1,165,110 0.25 88.0% 2.00 100.0% 15.00 99.0% 98.1%

SENSUS 72,729,406 32,930 0.25 92.0% 2.00 100.0% 15.00 100.0% 98.8%

SENSUS 23,602,465 340,650 0.25 96.0% 2.00 98.0% 15.00 99.0% 97.9%

SENSUS 56,120,302 626,540 0.25 97.0% 2.00 91.0% 15.00 98.0% 93.0%

SENSUS 72,308,424 303,970 0.25 93.0% 2.00 100.0% 15.00 99.0% 98.8%

SENSUS 75,017,633 14,090 0.25 94.0% 2.00 99.0% 15.00 100.0% 98.4%

SENSUS 75,017,441 47,870 0.25 96.0% 2.00 100.0% 15.00 100.0% 99.4%

SENSUS 72,308,546 784,940 0.25 92.0% 2.00 101.0% 15.00 99.0% 99.4%

SENSUS 70,948,537 230,480 0.25 92.0% 2.00 100.0% 15.00 99.0% 98.7%

SENSUS 73,305,311 993,640 0.25 96.0% 2.00 99.0% 15.00 99.0% 98.6%

SENSUS 67,762,875 104,990 0.25 94.0% 2.00 100.0% 15.00 100.0% 99.1%

SENSUS 75,017,584 30,210 0.25 95.0% 2.00 100.0% 15.00 99.0% 99.1%

SENSUS 30,268,542 1,312,900 0.25 88.0% 2.00 99.0% 15.00 99.0% 97.4%

SENSUS 29,409,449 1,448,950 0.25 90.0% 2.00 100.0% 15.00 99.0% 98.4%

SENSUS 71,848,259 165,910 0.25 92.0% 2.00 101.0% 15.00 99.0% 99.4%

SENSUS 71,491,113 296,540 0.25 93.0% 2.00 100.0% 15.00 100.0% 99.0%

SENSUS 70,024,232 565,360 0.25 94.0% 2.00 99.0% 15.00 99.0% 98.3%

SENSUS 73,305,328 55,180 0.25 95.0% 2.00 100.0% 15.00 100.0% 99.3%

SENSUS 67,762,772 368,710 0.25 86.0% 2.00 100.0% 15.00 99.0% 97.8%

SENSUS 71,491,068 598,620 0.25 88.0% 2.00 97.0% 15.00 98.0% 95.8%

SENSUS 72,729,285 918,180 0.25 89.0% 2.00 98.0% 15.00 99.0% 96.8%

SENSUS 17890111 434,950 0.25 84.0% 2.00 99.0% 15.00 100.0% 96.9%

SENSUS 70305350 414,710 0.25 94.0% 2.00 100.0% 15.00 99.0% 99.0%

SENSUS 71206267 9,190 0.25 90.0% 2.00 99.0% 15.00 100.0% 97.8%

Page 34: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 34

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%) Weighted Average Accuracy

(%)

SENSUS 22329101 363,240 0.25 88.0% 2.00 101.0% 15.00 99.0% 98.8%

SENSUS 17036323 282,830 0.25 92.0% 2.00 99.0% 15.00 99.0% 98.0%

SENSUS 75017603 30,920 0.25 93.0% 2.00 100.0% 15.00 100.0% 99.0%

SENSUS 18011124 488,480 0.25 94.0% 2.00 100.0% 15.00 99.0% 99.0%

SENSUS 23675363 1,012,290 0.25 91.0% 2.00 99.0% 15.00 100.0% 98.0%

SENSUS 73305464 21,560 0.25 93.0% 2.00 101.0% 15.00 100.0% 99.7%

SENSUS 69687135 2,083,760 0.25 92.0% 2.00 100.0% 15.00 99.0% 98.7%

SENSUS 68342182 270,710 0.25 94.0% 2.00 99.0% 15.00 99.0% 98.3%

SENSUS 67762774 511,020 0.25 95.0% 2.00 101.0% 15.00 99.0% 99.8%

SENSUS 21618699 476,030 0.25 94.0% 2.00 99.0% 15.00 100.0% 98.4%

SENSUS 26615962 898,000 0.25 82.0% 2.00 99.0% 15.00 98.0% 96.3%

SENSUS 69256496 170,800 0.25 97.0% 2.00 100.0% 15.00 99.0% 99.4%

SENSUS 56201187 524,460 0.25 89.0% 2.00 100.0% 15.00 99.0% 98.2%

SENSUS 17262791 1,110,720 0.25 90.0% 2.00 101.0% 15.00 99.0% 99.1%

WATER METER TEST RESULTS (1”)

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Weighted Average

Accuracy (%)

SENSUS 73305647 65,150 0.75 96.0% 4.00 100.0% 40.00 99.0% 99.3%

SENSUS 64105577 554,460 0.75 96.0% 4.00 101.0% 40.00 100.0% 100.1%

SENSUS 64105580 1,383,370 0.75 86.0% 4.00 99.0% 40.00 99.0% 97.1%

SENSUS 50297141 1,887,260 0.75 94.0% 4.00 100.0% 40.00 99.0% 99.0%

SENSUS 73305634 56,150 0.75 0.0% 4.00 101.0% 40.00 100.0% 85.7%

SENSUS 61043750 300,850 0.75 96.0% 4.00 100.0% 40.00 99.0% 99.3%

SENSUS 67978720 278,360 0.75 0.0% 4.00 99.0% 40.00 99.0% 84.2%

SENSUS 22172138 1,741,770 0.75 93.0% 4.00 100.0% 40.00 99.0% 98.8%

SENSUS 64105552 748,980 0.75 98.0% 4.00 100.0% 40.00 100.0% 99.7%

SENSUS 19332048 94,320 0.75 94.0% 4.00 100.0% 40.00 99.0% 99.0%

SENSUS 64105540 1,514,480 0.75 98.0% 4.00 99.0% 40.00 99.0% 98.9%

SENSUS 58205541 63,630 0.75 96.0% 4.00 100.0% 40.00 99.0% 99.3%

Page 35: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 35

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Weighted Average

Accuracy (%)

SENSUS 73305635 33,300 0.75 0.0% 4.00 98.0% 40.00 99.0% 83.5%

SENSUS 59631897 52,020 0.75 0.0% 4.00 100.0% 40.00 99.0% 84.9%

SENSUS 24310710 283,520 0.75 95.0% 4.00 100.0% 40.00 100.0% 99.3%

WATER METER TEST RESULTS (1.5”)

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Weighted Average

Accuracy (%)

SENSUS 65253931 6,559,600 1.50 95.0% 8.00 100.0% 50.00 101.0% 99.4%

SENSUS 20943381 155,400 1.50 90.0% 8.00 99.0% 50.00 100.0% 97.8%

SENSUS 24649024 1,624,400 1.50 96.0% 8.00 97.0% 50.00 99.0% 97.2%

SENSUS 18228500 0 1.50 90.0% 8.00 98.0% 50.00 99.0% 97.0%

WATER METER TEST RESULTS (2”)

Minimum Flow Intermediate Flow High Flow

Manufacturer Serial # Reading (kgal)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Rate (gpm)

Accuracy (%)

Weighted Average Accuracy

(%)

SENSUS 19926830 361,000 2.00 0.0% 15.00 95.0% 100.00 98.0% 81.2%

SENSUS 21514696 4,133,000 2.00 80.0% 15.00 97.0% 100.00 99.0% 94.8%

SENSUS 24246524 12,118,300 2.00 0.0% 15.00 96.0% 100.00 98.0% 81.9%

SENSUS 22264863 11,245,500 2.00 90.0% 15.00 98.0% 100.00 100.0% 97.1%

SENSUS 20321805 6,314,700 2.00 99.0% 15.00 100.0% 100.00 100.0% 99.9%

It is important to note that water revenue calculations are based on the meter accuracy improvements of only the 1”, 1.5” and 2” meters; meters of all other sizes and designations are included in the scope of the project for which the City will benefit from any accuracy improvements that result from replacing them.

In order to estimate the water revenue increase due to improved meter accuracy the baseline annual billed meter consumption of water for each water and sewer billing tier was calculated from the data provided by the City (September 2012 through August

Page 36: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 36

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

2013). For each billing tier, the estimated billed metered consumption with new meters is calculated as:

BMCafter = (BMCbefore) x (MAafter) / (MAbefore)

BMC [kgal] = Billed Meter Consumption

MA [%] = Meter Accuracy

And the revenue water increase for that billing tier is calculated as:

RWI= [(BMCafter) – (BMCbefore)] x (BR)

RWI [$] = Revenue Water Increase

BMC [kgal] = Billed Meter Consumption

BR [$] = Billing Rate

The table below outlines the calculated revenue increase for year 1 of the performance period.

REVENUE CALCULATION

Year 1 - Annual Revenue Calculations

Item Description Existing Consumption

at 100% Accuracy (kGals)

Existing Meter

Accuracy %

Existing Consumption

(kGals)

New Meter

Accuracy %

Consumption Billed with

New Meters (kGals)

Annual Consumption

Increase (kGals)

Annual Consumption Increase ($)

1 Water - 1" - Tier 1 - 0 to 2,000 Gallons

25,885 95.20% 24,643 98.50% 25,497 854 $906.24

2 Water - 1" - Tier 2 - 2,001 to 5,000 Gallons

30,197 95.20% 28,748 98.50% 29,744 997 $1,129.04

3 Water - 1" - Tier 3 - 5,001 to 10,000 Gallons

29,357 95.20% 27,948 98.50% 28,917 969 $1,426.93

4 Water - 1" - Tier 4 - 10,001 to 25,000 Gallons

39,933 95.20% 38,016 98.50% 39,334 1,318 $3,053.97

5 Water - 1" - Tier 5 - Over 25,001 Gallons

61,436 95.20% 58,487 98.50% 60,514 2,027 $5,116.10

6 Water - 1.5" - Tier 1 - 0 to 2,000 Gallons

6,079 97.80% 5,945 98.50% 5,988 43 $45.14

7 Water - 1.5" - Tier 2 - 2,001 to 5,000 Gallons

8,412 97.80% 8,227 98.50% 8,285 59 $66.71

8 Water - 1.5" - Tier 3 - 5,001 to 10,000 Gallons

12,475 97.80% 12,200 98.50% 12,288 87 $128.62

Page 37: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 37

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Year 1 - Annual Revenue Calculations

Item Description Existing Consumption

at 100% Accuracy (kGals)

Existing Meter

Accuracy %

Existing Consumption

(kGals)

New Meter

Accuracy %

Consumption Billed with

New Meters (kGals)

Annual Consumption

Increase (kGals)

Annual Consumption Increase ($)

9 Water - 1.5" - Tier 4 - 10,001 to 25,000 Gallons

29,704 97.80% 29,051 98.50% 29,259 208 $481.88

10 Water - 1.5" - Tier 5 - Over 25,001 Gallons

139,858 97.80% 136,781 98.50% 137,760 979 $2,470.52

11 Water - 2" - Tier 1 - 0 to 2,000 Gallons

7,177 91.00% 6,531 98.50% 7,069 538 $571.02

12 Water - 2" - Tier 2 - 2,001 to 5,000 Gallons

10,369 91.00% 9,436 98.50% 10,214 778 $881.13

13 Water - 2" - Tier 3 - 5,001 to 10,000 Gallons

16,535 91.00% 15,047 98.50% 16,287 1,240 $1,826.62

14 Water - 2" - Tier 4 - 10,001 to 25,000 Gallons

45,478 91.00% 41,385 98.50% 44,796 3,411 $7,904.65

15 Water - 2" - Tier 5 - Over 25,001 Gallons

459,188 91.00% 417,861 98.50% 452,300 34,439 $86,907.11

16 Sewer - 1" - Tier 1 - 0 to 2,000 Gallons

25,150 95.20% 23,943 98.50% 24,772 830 $2,974.84

17 Sewer - 1" - Tier 2 - 2,001 to 5,000 Gallons

28,608 95.20% 27,235 98.50% 28,179 944 $3,500.56

18 Sewer - 1" - Tier 3 - 5,001 to 10,000 Gallons

25,206 95.20% 23,996 98.50% 24,828 832 $3,212.86

19 Sewer - 1" - Tier 4 - 10,001 to 25,000 Gallons

27,727 95.20% 26,396 98.50% 27,311 915 $3,920.51

20 Sewer - 1" - Tier 5 - Over 25,001 Gallons

42,117 95.20% 40,095 98.50% 41,485 1,390 $6,284.49

21 Sewer - 1.5" - Tier 1 - 0 to 2,000 Gallons

5,222 97.80% 5,107 98.50% 5,144 37 $131.02

22 Sewer - 1.5" - Tier 2 - 2,001 to 5,000 Gallons

6,998 97.80% 6,844 98.50% 6,893 49 $181.64

23 Sewer - 1.5" - Tier 3 - 5,001 to 10,000 Gallons

9,473 97.80% 9,264 98.50% 9,331 66 $256.12

Page 38: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 38

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Year 1 - Annual Revenue Calculations

Item Description Existing Consumption

at 100% Accuracy (kGals)

Existing Meter

Accuracy %

Existing Consumption

(kGals)

New Meter

Accuracy %

Consumption Billed with

New Meters (kGals)

Annual Consumption

Increase (kGals)

Annual Consumption Increase ($)

24 Sewer - 1.5" - Tier 4 - 10,001 to 25,000 Gallons

20,890 97.80% 20,430 98.50% 20,576 146 $626.55

25 Sewer - 1.5" - Tier 5 - Over 25,001 Gallons

94,281 97.80% 92,206 98.50% 92,866 660 $2,984.16

26 Sewer - 2" - Tier 1 - 0 to 2,000 Gallons

5,798 91.00% 5,276 98.50% 5,711 435 $1,558.65

27 Sewer - 2" - Tier 2 - 2,001 to 5,000 Gallons

8,347 91.00% 7,596 98.50% 8,222 626 $2,321.22

28 Sewer - 2" - Tier 3 - 5,001 to 10,000 Gallons

13,335 91.00% 12,135 98.50% 13,135 1,000 $3,862.94

29 Sewer - 2" - Tier 4 - 10,001 to 25,000 Gallons

36,513 91.00% 33,227 98.50% 35,965 2,738 $11,733.84

30 Sewer - 2" - Tier 5 - Over 25,001 Gallons

318,576 91.00% 289,905 98.50% 313,798 23,893 $108,038.01

TOTALS 1,590,322 1,483,960 1,566,467 82,508 $264,503.09

Note: The new meter accuracy shown in the above table (98.5%) corresponds to the accuracy that Siemens is guaranteeing and is above the standard manufacturer’s guarantee.

OPERATIONS AND MAINTENANCE SAVINGS

The O&M savings derived from implementing the water meter replacement with the AMI system are based on the information supplied by the City regarding estimated reduction in operating costs related to the subcontractor required to read the meters, customer service activities, and staff re-read requirements. The total O&M savings calculated by the City for year 1 of the performance contract is $60,000.

In addition to the O&M savings, there will be savings resulting from the City-wide installation of new meters, eliminating the capital cost to replace old meters with new meters. While this is an annual cost that will be eliminated for many years, we are only including capital avoidance of $50,000 for the first five years of the project term.

Page 39: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 39

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

AMI PROPAGATION STUDY

As part of this project development effort, a propagation study was conducted in order to design the fixed-based system of antennas that will collect meter readings and transmit them to the computer system that processes them. The propagation study is a simulation of the performance of the system and is influenced by the geographical location of the transmitters and receivers, and the topography of the area.

The AMI system was designed around two main antennas to be mounted at strategic locations across the city; these locations and antenna heights are listed in the table below.

COLLECTOR LOCATION

BTS Name Latitude Longitude Site Address Total Structure

Height (ft)

Proposed Antenna

Centerline (ft)

North_Beach_Water_Tank 25.986311 -80.118583 2801 E Hallandale Beach Blvd

136 136

Public Works Compound 25.988367 -80.155464 630 NW 2 Street

60 60

Page 40: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 40

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The following table shows the three categories of signal strength depicted in water meter study.

Signal Strength Categories

The figure below shows the result of the propagation study in terms of the quality of signal that is expected to be achieved throughout the coverage area.

Figure – Water Propagation Study Coverage

Page 41: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 41

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

MEASUREMENT AND VERIFICATION

The Measurement and Verification (M&V) of the Water Meter FIM will be International Performance Measurement and Verification Protocol (IPMVP) Option A: Retrofit Isolation: Key Parameter Measurement. A Detailed M&V Plan is available in the contract document, Exhibit C. The operations and maintenance savings will use Option E: Stipulated.

Page 42: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 42

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

B. Schedule B - Description of Premises; Pre-Existing Equipment Inventory

B.1. Hallandale Beach Municipal Complex The Hallandale Beach Municipal Complex, located at 400 South Federal Hwy, is a two-story, multi-building facility housing the Police Department, Commission Chambers, and City Hall administration. The facility was built in 1994 and is approximately 53,500 square feet.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation were obtained from various staff interviews conducted during the site visits.

The hours of operation for the City Hall section of the building are posted as Monday through Friday, 7:30AM-5:00PM. There are a reported 80 staff members working in City Hall with an unknown number of daily visitors.

The Police Department is a 24 hour operation that works in three (3) shifts. There are 147 staff members dedicated to the Police Department with 23 in-office employees working during customary business hours. Each shift has an estimated 41 police officers that frequently come and go as needed.

The Commission Chambers is reported to operate an average of 20 hours per month.

LIGHTING

The Municipal Complex underwent a lighting retrofit in 2011. During this retrofit the City installed new lighting technology and lighting control strategies, which included Lutron occupancy and daylighting sensors. During the investment grade audit occupancy sensors were observed to be operating as expected throughout the facility. The daylighting sensors reduce light levels when there is sufficient daylight available; daylight control was observed to be not functioning, likely from failed sensors.

A detailed lighting audit was conducted to determine the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 25 Watt incandescent fixture • Existing LED • 50 Watt incandescent fixture • 100 Watt incandescent fixture

• 13 Watt screw-in compact fluorescent fixture

• 13 Watt plug-in compact fluorescent fixture

Page 43: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 43

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• 2-Lamp 13 Watt plug-in compact fluorescent fixture

• 26 Watt plug-in compact fluorescent fixture

• 2-Lamp 26 Watt plug-in compact fluorescent fixture

• 1-Lamp 17 Watt T8 with 2' linear fixture

• 1-Lamp 32 Watt T8 with 4' linear fixture

• 2-Lamp 17 Watt T8 with 2' linear fixture

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 3-Lamp 32 Watt T8 with 4' linear fixture

• 50 Watt metal halide fixture • 100 Watt metal halide fixture • 175 Watt metal halide fixture • 400 Watt metal halide fixture • LED Exit Sign

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

Examples of Interior Lighting Equipment

Examples of Exterior Lighting Fixtures

HVAC

Cooling for the entire Municipal Complex is provided by a single chilled-water loop system consisting of two chillers; one (1) 80-Ton and one (1) 90-Ton Trane, Air-cooled, screw compressor chillers. The plant utilizes a primary-secondary configuration for the chilled-water loop. There are two (2) primary and one (1) secondary variable flow chilled-water pumps. The pump motor is equipped with a Magnetek variable frequency drive (VFD).

Page 44: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 44

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Central Energy Plant Equipment

Chilled water from the chillers is distributed to two (2) air handling units (AHUs) and one (1) roof-top unit (RTU). The AHUs serve the first and second floor of City Hall and the chilled-water RTU serves the Police Department and Commission Chambers. Both AHUs and the RTU are equipped with variable frequency drives.

The Police Department also utilizes three (3), chilled-water fan coil units (FCUs) which cool mechanical rooms and the Police Department armory. A constant volume Liebert unit cools the server room located on the second floor of City Hall.

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplates or building drawings obtained from the City. The following table summarizes the equipment specifications of each unit serving the Municipal Complex.

Page 45: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 45

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

MUNICIPAL COMPLEX: HVAC EQUIPMENT

The following equipment points of interest were discovered during the audit.

• Both chillers are original to the building, installed in 1994. Parts have been replaced along the years.

• The pump motors were recently replaced with higher efficiency models.

• The secondary pump was identified as a single point of failure – if this pump fails chilled-water cannot be distributed to the facility’s HVAC equipment.

• The outside air dampers and damper control on both AHUs and the RTU are not operational.

• The VFD controlling the RTU is set to operate at a maximum of 50 Hz to avoid severe vibration issues throughout the building.

• The RTU casing is rusted out allowing significant infiltration of unconditioned outside air into its air distribution system.

Examples of Identified Issues Onsite

Chiller 1 Trane RTAA090 U94J24220 - 90 460 3 168.5 - 0.9 200 - -

Chiller 2 Trane RTAA080 - - 83 460 3 166 - 0.9 200 - -

Primary Pump 1 Baldor JMM3611T 35M205P797H1 3 - 460 3 4.2 87.5% 0.9 200 - -

Primary Pump 2 Baldor - - 3 - 460 3 4.2 87.5% 0.9 200 - -

Secondary Pump 3 Baldor M3311T 36B103T848H1 7.5 - 460 3 10 88.5% 0.79 226 - -

AHU 1 Trane MCCAO25HCC00 K94H61083 15 - 460 3 18 92.4% 0.9 - 11,260 2,140

AHU 2 Trane MCCAO21NBEOA K94H61091 10 - 460 3 13.3 96.5% 0.9 - 9,100 1,550

RTU 1 - WF-RD40PG 60102 25 40 460 3 28.5 - 0.9 - 20,200 5,590

FCU 1 - - - 25 Watts - 115 1 0.2 - 0.9 1 105 -

FCU 2 - - - 130 Watts - 115 1 1.1 - 0.9 3.8 1,200 -

FCU 3 - - - 25 Watts - 115 1 0.2 - 0.9 1 105 -

Liebert Liebert - - 0.75 5 115 1 14.6 - 0.9 - - -

Water Heater 1 Locdhinvar ASME HCX18-120-A E96 1024F - - 480 3 22 - 0.9 - - -

Water Heater 2 Locdhinvar ASME HCX18-120-A - - - 480 3 22 - 0.9 - - -

Circ Pump Emerson S55JXDYD-2680 131-143 0.33 - 115 1 6.2 - 0.9 - - -

O.A. CFMPh Amps Eff /EER P.F. GPM Total

CFMHP Tons V

General Information Size / Capacity Information Obtained from Namplates or Drawings

EQUIPMENT Manufacter Model Number Serial Number

Page 46: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 46

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

AIR MOVING EQUIPMENT

The air distribution system throughout the Municipal Complex is variable air volume (VAV). There are approximately 57 VAV boxes which include a mix of fan powered boxes without electric reheat and, more commonly, VAV boxes with electric reheat. During the audit, various staff members reported that areas of the building become excessively cold.

Examples of VAV Boxes and Indoor Temperature Issues

Inspections of the boxes found more than 10% of the VAV boxes are not operating as intended / expected, and it is anticipated that a great many do not operate properly. However, the energy savings associated with testing each VAV box did not warrant individual testing during the IGA. The following are the identified and reported issues concerning the VAV system at this facility.

• Zone temperature does not match cooling setpoint temperature

• Supply air temperature does not match cooling setpoint temperature

• Valve positions appear inaccurate on building automation system (showing mostly closed when actually mostly open)

• Attempts to temporarily adjust VAV boxes resulted in maintenance staff manually fixing dampers to specific positions

• Some electric reheat are reported to as not operational

• Some fans in the fan powered boxes are reported as not operational

• Some VAV heating setpoints are at 45F (this is not going to call for heat)

• Some flow measurements are not registering (indicates possible problem with the VAV box)

In order to determine the total number of VAV that are no longer operational, and the individual causes of each failure, an in-depth test and troubleshooting investigation must be performed.

Page 47: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 47

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

VAV System Inspection

BUILDING AUTOMATION SYSTEM AND EQUIPMENT OPERATION

The Municipal Complex HVAC equipment is controlled by a Trane Tracer 100 building automation system (BAS) installed during 1994 construction. The system consists of the following components:

• (4) PCM panels – each controls an AHU/RTU and one panel controls the variable secondary pump

• VAV command unit – controls approximately 57 VAV boxes

• TCM panels – each controls the primary pump based off chilled-water temperature

Each panel has a maximum of 20 available control points, with 19 control points currently being utilized with these panels. The following pictures illustrate the different controlled or trended data available of this current BAS.

Existing Controls Capabilities

Although an antiquated technology, the Trane system is mostly operational. Trane is under contract with Hill York to make quarterly visits to inspect and service the BAS system equipment and has managed to keep major equipment on designated operating schedules. All service reports and discovered issues are reported to Hill York. The service agreement with Hill York includes parts for the controls system only.

Page 48: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 48

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

A data logging session conducted for a period of 30 days was utilized to verified the equipment operation runtimes and calibrate the energy model. The results are discussed as follows. The logging data is provided in the appendix of this report.

AHU 1 & 2

The Tracer 100 system schedules this unit to operate from 4AM to 9PM Monday, 5AM to 9PM Tuesday through Friday, and off on weekends and holidays. The data logging session revealed that AHU 1 maintained its intended operation schedule during the measurement period, while the second floor unit, AHU 2, eventually fell off the schedule.

Data Logging Results of AHU 1 &2

CHILLED-WATER RTU

The Tracer 100 system schedules the RTU to operate 24 hours a day; data logging results confirmed this operation.

Data Logging Results of the RTU

Page 49: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 49

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

CHILLER 1 & 2

Chiller 1 operates 24 hours a day to support the 24 hour operation of the Police Department, while Chiller 2 was found to rarely run at all. The data logging session shown below revealed that Chiller 2 operated a total of 18 hours during the 30 day measurement period, which took place in one of the hottest month, September (summer weather conditions).

Data Logging Results of Chillers 1 &2

PLUG LOAD

In order to obtain the energy consumption associated with plug loads, a detailed audit of plug load devices was conducted. Below are the results of this audit.

City Hall

• (80) Office Computers

• (8) Laptops

• (5) BizHubs

• (18) Small desk printers

• Water Fountain

• Vending machine

• (4)Televisions

• (12) Lenovo (Monitor and computer)

Police Department

• (62) Office Computers

• (4) Laptops

• (2) BizHubs

• (13) Small desk printers

• Water Fountains

• (4) Televisions

• Industrial coffee maker

Page 50: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 50

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

A data logging session of various plug load devices was also conducted for a period of 14 days. This data aided in the calibration of the energy models with respect to plug load electric usage. The results of this data logging session are provided, along with calculated energy savings calculations, within the appendix of this report.

WATER

A detailed water consumption audit was conducted at this facility and a summary of the existing equipment identified is listed below. The detailed audit results are provided along with the savings calculations within the appendix of this report.

• Restroom Sinks: o (11) 2.16 gpm standard 4 and 8 inch, hot and cold o (2) 2.0 gpm Standard 4 and 8 inch, hot and cold (shaving) o (30) 2.07 gpm push button delay spigots o (3) 0.5 gpm Cell Sinks:

• Toilets: o (31) 3.5 gpf o (3) 1.6 gpf o (11) 1.0 gpf Urinals:

• Showers: o (1) high flow, standard showers o (3) low flow, standard showers o (3) low flow, institutional showers

• Other o (3) General Purpose Sinks o (2) Efficient or non-adaptable faucets

The measured building water pressure is 45 psig on the first floor and 40 psig on the second floor.

Examples of Existing Water Fixtures

Domestic hot water is provided by two (2) 118 gallon electric water heaters. Hot water is circulated throughout the facility by one (1) 1/3 HP pump motor.

Page 51: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 51

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Domestic Hot Water Equipment

B.2. Hallandale Beach Cultural Center The Hallandale Beach Cultural Center, located at 410 SE 3rd Street, is a single-story facility housing a lobby area, a large event room with stage, and smaller multipurpose functions rooms. The facility was built in 1994 and is approximately 12,500 square feet.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation were obtained from various staff interviews conducted during the site visits.

The Cultural Center has a total of seven (7) staff members; six (6) day shift and one (1) evening shift personnel. The day shifts are Monday through Friday, 8:00AM-6:00PM and the evening shift works to support evening events and when the event room is rented out. The evening shift hours range between 6:00 PM and 11:00PM, Monday through Friday. The facility is utilized an estimated 12 hours on Saturdays and 8 hours on Sunday.

The reported number of visitors per day is 60-70 visitors during the week, and 250-300 visitors per day on weekends.

LIGHTING

A detailed lighting audit was conducted to determine the quantity and types of lamps and fixtures installed. The following is a brief summary of the lighting equipment found at this facility.

• 2 -Lamp 25 Watt incandescent fixture

• 40 Watt incandescent fixture

• 50 Watt incandescent fixture

• 200 Watt incandescent fixture

• 250 Watt incandescent fixture

Page 52: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 52

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• 1-Lamp 32 Watt T8 with 4' linear fixture

• 2-Lamp 32 W T8 with 4' linear fixture

• 2-Lamp T8 U-tube with standard electric ballast fixture

• 3-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 3-Lamp 32 Watt T8 with 4' linear fixture

• 4-Lamp 32 Watt T8 with 4' linear fixture

• 50 Watt metal halide fixture

• 70 Watt metal halide fixture

• 175 Watt metal halide fixture

NOTE: Occupancy sensors are not being utilized at this facility. The detailed lighting audit is provided within the Appendix on this report.

A lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

Examples of Interior Lighting Fixtures

Page 53: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 53

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HVAC

Cooling for the Cultural Center is provided by eleven (11) RTUs; seven of the RTUs are Carrier units installed in 1997, three units were installed in 2002, and the ICP RTU was installed in 2012. The diagram below illustrates the location of each RTU and the areas which it serves.

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplates or building drawings obtained from the City. The following table summarizes the equipment specifications of each unit serving the Cultural Center.

Page 54: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 54

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

CULTURAL CENTER: HVAC EQUIPMENT

HVAC CONTROL AND EQUIPMENT OPERATION

The roof-top units (RTU) are controlled by dedicated thermostats. The building is equipped with various types of thermostats from various manufacturers, as shown in the pictures below. The setpoints assigned to the thermostats range between 70 and 76°F. These setpoints are adjusted as needed.

Examples of HVAC Control

A data logging session was conducted for a period of 2 weeks to obtain equipment operation runtimes and calibrate the energy model. The results of the logging data is provided in the appendix of this report. The data revealed that although none of the RTUs are running 24 hours a day, the units are not on structured operating schedules.

Example Data Logging Data for the RTUs

Size / Capacity

Package DX 1 Carrier 50TFF008 4303G40444 Lobby nameplate info 6.1 460 3 15.4 - 0.9

Package DX 2 Carrier 50HJ-012 0596G30269 Admin Offices nameplate info 10 460 3 24.8 11 0.9

Package DX 3 Carrier 38AHSO24 - Auditorium plans 20 460 3 38.3 11.6 0.9

Package DX 4 Carrier 38AKO28 - Auditorium plans 25 460 3 49.8 11.2 0.9

Package DX 5 ICP RAS150L0CA G113940314 Lobby/Hallway nameplate info 12.5 460 3 24.7 11 0.9

Package DX 6 Carrier 50HJ-006 1296G20102 Bathrrom/Hallway nameplate info 5 460 3 11.6 11.1 0.9

Package DX 7 Carrier 50TJ-005 - Kitchen plans 4 460 3 10.7 9 0.9

Package DX 8 Carrier 50TJ-020 - Stage/Auditorium nameplate info 18 460 3 38.3 8.8 0.9

Package DX 9 Carrier 50TJ-007 - Rooms plans 6 460 3 13.2 9 0.9

Package DX 10 Carrier - - Backstage / Conference Room neither 4 460 3 - - 0.9

Package DX 11 Carrier - - Backstage neither 4 460 3 - - 0.9

General Information Source Information

EQUIPMENT Manufacterer Model Serial Description Ph Amps Eff /EER P.F.Source of

Information Tons V

Page 55: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 55

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

WATER

A detailed water consumption audit was conducted at this facility. Following is a brief summary of the existing equipment found during the audit. The detailed audit results are provided along with the savings calculations within the appendix of this report.

• Restroom Sinks: (7) 1.0 gpm push button delay spigots • Restroom Sinks: (5) Efficient or non-adaptable faucets (0.5 gpm) • Toilets: (13) 1.6 gpf • Urinals: (3) 1.0 gpf • Other: (1) Ice Machine (400 lb) • Other: (3) Efficient or non-adaptable faucets

The measured building water pressure is 48 psig.

Domestic hot water is provided by a standard, 65 gallon, RUUD residential electric water heater.

Examples of Existing Water Fixtures

B.3. Fire Station #60 Fire Station 60, located at 2801 Hallandale Beach Blvd, is a two story building with a mezzanine area located above the first floor. The first floor consists of the truck bay, life safety room, storage and laundry, and the second floor consists of dorms, kitchen, gym, offices, multipurpose rooms, and a living room. The facility was built in 2004 and is approximately 12,500 square feet.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The fire station works on a three shift schedule. The building occupancy is approximately five (5) people at any given time, and is open 24 hours a day, 7 days a week.

Page 56: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 56

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

LIGHTING

A detailed lighting audit was conducted which determined the quantity and type of lamps and fixtures installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 25 Watt incandescent fixture

• Existing LED

• 50 Watt incandescent fixture

• 150 Watt incandescent fixture

• 20 Watt screw-in CFL

• 2-Lamp 20 Watt screw-in compact fluorescent fixture

• 2-Lamp 13 Watt plug-in CFL

• 2-Lamp 26 Watt plug-in CFL

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 2-Lamp T8 U tube with standard electric ballast fixture

• 3-Lamp 32 Watt T8 with 4' linear fixture

• 4-Lamp 32 Watt T8 with 4' linear fixture

• 50 Watt metal halide fixture

• 70 Watt metal halide fixture

• 175 Watt metal halide fixture

• 250 Watt metal halide fixture

• LED Exit Sign

NOTE: Occupancy sensors are not being utilized at this facility.

Examples of Interior Lighting Fixtures

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These

Page 57: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 57

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for this facility is provided by five (5) dedicated split DX units serving various areas of the fire station. Units 1-4 cool the dorms, kitchen, gym and lieutenant’s office, and Unit 5 cools the mezzanine and life safety room. All units are in fair conditions and operational.

A 10 ton package unit is used for supplemental sub-cooling of the halls and most of the building as the individual split systems cannot cool their respective spaces on their own. This 10-ton package unit was replaced in 2013.

Despite having the five DX and one 10-ton package unit, the fire station had trouble cooling the living room area. A plug-in spot cooling was installed in this space and is utilized by occupants as needed.

Examples of HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplates or building drawings obtained from the City. The following table summarizes the equipment specifications of each unit within this facility.

Page 58: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 58

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

FIRE STATION 60: HVAC EQUIPMENT

HVAC CONTROL AND EQUIPMENT OPERATION

The split DX units are controlled by dedicated thermostats. The building is equipped with various types of thermostats from various manufacturers, as shown in the pictures below. The setpoints assigned to the thermostats range between 69 and 72°F and are adjusted as needed.

Examples of HVAC Control

The package unit utilizes a standard thermostat located within the unit. Temperature is controlled based on return air temperature. HVAC equipment, with the exception of the spot cooler in the living room, operates 24 hours a day based off thermostat settings.

Split DX 1

Condenser Carrier 38CKC042 nameplate 3.5 208 1 20.5 10 0.9

AHU Carrier FA4BNC042 nameplate 0.5 208 1 2.9 0.9 1,305 - 38.99 28.9

Split DX 2

Condenser Carrier 38CKC030 nameplate 2.5 208 1 14.2 10 0.9

AHU Carrier FA4BNC030 nameplate 0.33 208 1 2.8 0.9 890 - 27.00 19.7

Split DX 3

Condenser Carrier 38CKC024 nameplate 2 208 1 10.7 10 0.9

AHU Carrier FA4BNC024 nameplate 0.25 208 1 1.8 0.8 670 - 21.71 15.6

Split DX 4

Condenser Carrier 38CKC036 nameplate 3 208 1 16.7 10 0.9

AHU Carrier FA4BNC036 nameplate 0.33 208 1 2.4 0.9 1,120 - 32.55 24.9

Split DX 5

Condenser Carrier 38CKC030 nameplate 2.5 208 1 14.2 10 0.9

AHU Carrier FA4BNC030 nameplate 0.25 208 1 1.5 0.9 930 - 27.00 19.7

OAU Unit 1 Aon RK-10-2-E1-1B1 nameplate 2 10 208 3 17.3 11 0.9 1,500 1,500 128.8 66.1

Tons V

General Information Size / Capacity Source Information

EQUIPMENT Manufacterer Model O.A. CFM

Total MBH

Sensible MBHPh Amps Eff

/EER P.F. Total CFM

Source of Information HP

Page 59: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 59

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Measured building water pressure is 48 psig • Restroom Sinks: (1) 2.0 gpm standard 4 and 8 inch, hot and cold • Restroom Sinks: (4) 2.0 gpm standard 4 and 8 inch, hot and cold • Toilets: (4) 1.6 gpf • Urinals: (1) 1.0 gpf • Showers: (1) high flow (2.0 gpm), standard shower • Showers: (3) low flow (1.5 gpm), standard showers • Other: (2) 2.5 gpm, non-adaptable faucets • Other: (1) truck wash (pulled from fire hydrants) • Other: (1) laundry system (size 1) • Other: (1) ice machine (400 lb)

Examples of Existing Water Fixtures

B.4. Fire Station #90 Fire Station 90, located at 101 Three Islands Blvd, is a single story building comparable to that of a large residence. It consists of a truck bay / garage, an office, dorms, restroom, kitchen, dining area and a living room. The facility was built in 1990 and is approximately 2,600 square feet.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The fire station works a three shift schedule and the occupancy is a maximum of three (3) people at any given time. The fire station is operational 24 hours a day, 7 days a week. The firemen are onsite only part of the day.

Page 60: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 60

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 60 Watt incandescent fixture

• 250 Watt incandescent fixture

• 13 Watt screw-in CFL fixture

• 2-Lamp 26 Watt plug-in CFL fixture

• 2-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 50 Watt metal halide fixture

NOTE: Occupancy sensors are not being utilized at this facility.

Examples of Lighting Equipment

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

The fire station is cooled by one (1) split DX unit; a Carrier model Comfort 13 air conditioner with Puron refrigerant (R-410A) installed in 2011. Since its installation the unit has not experienced any failures or operational issues. The unit operates 24 hours a day and uses a digital thermostat for temperature control.

Page 61: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 61

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HVAC Equipment and Controls

Equipment data for each the aforementioned equipment was collected from nameplates obtained on site. The following table summarizes the equipment specifications of each unit within this facility.

FIRE STATION 90: HVAC EQUIPMENT

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Measured building water pressure is 45 psig • Restroom Sinks: (2) 2.0 gpm standard 4 & 8 inch, hot and cold • Toilets: (1) 1.6 gpf • Urinals: (1) 1.0 gpf • Showers: (1) low flow (1.5 gpm), standard showers • Other: (1) 2.5 gpm, non-adaptable faucets • Other: (1) truck wash (pulled from fire hydrants)

Split DX Unit

Condenser 24ABB360 2511W05757 R- 410A nameplate 0.25 5 208 1 26.4 10.8 0.9

AHU Carrier FB4CNF060 3011A85170 nameplate 0.75 208 1 6 0.9 2011

Water Heater 1 GE40S6AB00 GE 1002B0051000040 Gallons

3.38kW nameplate 208 1 11.5 0.9

Year

Source Information

Ph Amps EER P.F.Source of Information HP Tons V

General Information Size / Capacity

EQUIPMENT Manufacterer Model Serial Description

Page 62: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 62

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Water Fixtures and Domestic Hot Water Equipment

B.5. Hepburn Center The Hepburn Center, located at 750 NW 8th Avenue, is a single story community building that host daily events for senior citizens and an after-school care program. The facility consists of various offices, a conference room, after-school care classrooms, adult learning classrooms, a large kitchen facility, a public computer usage center, and a large multipurpose event room. The facility was built in 1974 and is approximately 13,000 square feet.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Hepburn Center has a total of eight (8) full-time and 29 part-time staff members. Its hours of operation are reported to be 7:30 AM-6:00 PM on Mondays, Thursdays and Fridays, and 7:30 AM-8:00 PM on Tuesdays and Wednesdays. The facility is occasionally utilized for events conducted by the Center on Saturdays, but these events are few and occur sporadically.

The reported number of visitors to the Hepburn Center is 240-300 visitors per day, during the week.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 60 Watt incandescent fixture

• 3-Lamp 13 Watt screw-in CFL fixture

• 20 Watt screw-in CFL fixture

• 2-Lamp 13 Watt plug-in CFL fixture

• 2-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

Page 63: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 63

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 2-Lamp T8 U tube with standard electric ballast fixture

• 4-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 4-Lamp 32 Watt T8 with 4' linear fixture

• 175 Watt Metal Halide fixture

• LED Exit Sign

NOTE: Occupancy sensors are not being utilized at this facility.

Examples of Lighting Equipment

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for the Hepburn is provided by a total of seven (7) RTUs and one (1) split DX unit. The majority of the RTUs are Carrier units with varying installation dates. The split DX unit was installed specifically to provide supplemental cooling to Activity Room 3. The RTU cooling this room and the computer room could not keep up with the cooling needs of both areas. The diagram below illustrates the location of each RTU, as well as the split unit, and the areas which they serve.

Page 64: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 64

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplates or building drawings obtained from the City. The following table summarizes the equipment specifications of each unit serving the Hepburn Center.

HEPBURN CENTER: HVAC EQUIPMENT

RTU-1 Carrier 50HJ-007 computer room 6 nameplate 208 3 20.5 11 0.9 2,100

RTU-2 Carrier 50HJ-012 Lounge, Offices, Act # 1&2 10 nameplate 208 3 17.6 11 0.9 4,000

RTU-3 Carrier 50HJ-008 Conf Room & 2 offices 7 nameplate 208 1 22.9 11 0.9

RTU-4 Bard PA13601-A Lobby/ Director/ Reception 7.5 nameplate 208 3 28 11 0.9 2,750

RTU-5 Carrier 50HJ-006 3 Rooms on East & Pantry 5 nameplate 208 3 17.3 11.1 0.9 1,750

RTU-6 Carrier 50HJ-005 Large Hall 4 nameplate 208 3 13.5 11.2 0.9 1,450

RTU-7 Carrier 50HJ-007 Rooms in back of Large Hall 6 nameplate 208 3 20.5 11 0.9 2,100

Split DX -1 24ABB348A310 Activity Room 3 nameplate 208 1 19.9 0.9

Total CFM

Source of Information V

General Information Nameplate Information

EQUIPMENT Manufacterer Model Description Tons Ph Amps Eff /EER P.F.

Page 65: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 65

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HVAC CONTROL AND EQUIPMENT OPERATION

The roof-top units are each controlled by a dedicated thermostat, with most thermostats locked to prevent visitors and office staff from changing temperature setpoints. There are various types of thermostats from various manufacturers.

A data logging session was conducted for a period of two (2) weeks to obtain equipment operation runtimes and calibrate the energy model. The results of the data logging session are provided in the appendix of this report. The data revealed that most of the RTUs are running 24 hours a day.

Example Data Logging Data for the RTUs

PLUG LOAD

In order to obtain the energy consumption associated with plug load uses, a detailed audit of plug load devices was conducted. Below are the results of this audit.

• (19) Student Computers

• (14) Office Computers

• (2) Drinking Fountains

• (5) Freezers

• (4) Small desk printers

• (5) Televisions

• (2) Vending Machines

• Ice Machines

• Standing Fans

A data logging session of various plug load equipment was also conducted for a period of 14 days. This data aided in the calibration of the energy models with respect to plug

Page 66: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 66

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

load electric usage. The results of this data logging session are provided, along with calculated energy savings calculations, within the appendix of this report.

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Measured building water pressure is 42 psig

• Restroom Sinks: (2) 2.0 gpm standard 4 and 8 inch, hot and cold

• Restroom Sinks: (4) 2.0 gpm push button delay spigots

• Restroom Sinks: (4) 2.0 gpm push button delay spigots (cold only)

• Toilets: (9) 1.6 gpf

• Urinals: (1) 1.0 gpf

• Other: (1) Ice Machine (400 lb)

• Other: (1) Efficient or non-adaptable faucets

B.6. DPW Administration The Department of Public Works (DPW) Administration Building, located at 215 NW 6th Avenue, is restricted to the first floor of a two-story building. The second floor temporarily consists of Sanitation West Parcel which is discussed individually later. The Administration Building consists of offices, a conference room, reception area, and copy room. The facility was built in 1968 and is approximately 8,000 square feet. This square foot value includes the second floor area.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Administration building has a total of 18 full-time staff members and operates 7:00 AM-5:00 PM, Monday through Friday. The facility is closed on weekends.

Page 67: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 67

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 40 Watt incandescent fixture

• 60 Watt incandescent fixture

• 2-Lamp 40 Watt SuperSaver T12 U-tube with standard magnetic ballast fixture

• 4-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• LED Exit Sign

NOTE: Occupancy sensors are not being utilized at this facility.

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for the Administration Building is provided by two Rheem (2) split DX units with electric heat capabilities, and installed in 2002 and 2009. Each unit is responsible for cooling half of the first floor where the administration offices are located.

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplate information obtained on site. The following table summarizes the equipment specifications of each unit serving the Administration Building.

Page 68: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 68

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

DPW ADMINISTRATION BUILDING: HVAC EQUIPMENT

HVAC CONTROL AND EQUIPMENT OPERATION

The DX units are controlled by dedicated Honeywell thermostats, and the staff has full control over each thermostat. At the time of the energy audit both units were set to 70°F. The setpoints are reportedly adjusted as needed.

HVAC Control Method

A data logging session was conducted for 2 weeks to obtain equipment operation runtimes and to calibrate the energy model. The results of the logging data is provided in the appendix of this report. The data revealed that both units are running 24 hours a day.

Data Logging Data for Each DX Unit

Split DX 1

Condenser Rheem RANL-060JAZ 7390W050900640 1st Floor 2009 5 208 1 26.3 0.9

AHU Rheem RBHC-24J11S Electric Heat 7.3 kW 0.5 208 1 2.9 0.9

Split DX 3 1st Floor

Condenser Rheem RAKA-042JAZ 5461F340204022 2002 208 1 18.3 0.9

AHU Rheem RHLL-HM6024JA W251017153 2010 0.75 208 1 4.6 0.9

Ph Amps P.F.Notes HP Tons V

General Information Size / Capacity Nameplate Information

EQUIPMENT Manufacterer Model Serial Description

Page 69: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 69

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

PLUG LOAD

In order to obtain the energy consumption associated with plug load uses, a detailed audit of plug load devices was conducted. Below are the results of this audit.

• (11) Office Computers

• Drinking Fountains

• Small desk printers

• BizHubs

• Industrial coffee maker

A data logging session of various plug load equipment was also conducted for a period of 14 days. This data aided in the calibration of the energy models with respect to plug load electric usage. The results of this data logging session are provided, along with calculated energy savings calculations, within the appendix of this report.

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Measured building water pressure is 48 psig

• Restroom Sinks: (2) 2.0 gpm standard 4 and 8 inch, hot and cold

• Toilets: (2) 3.5 gpf tank toilet (floor/wall type)

B.7. DPW Garage The DPW Garage, located at 630 NW 2nd Street, is directly adjacent to the Administration building. The garage is a single story facility consisting of four (4) bays where mechanics can work of City vehicles, two (2) bays used for storage and as general work areas, and two (2) office spaces. The facility was built in 1968 and is assumed to be a part of the reported 17,900 square feet that includes the Crew Quarters and Warehouse.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Garage has a total of

Page 70: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 70

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

eight (8) staff members working from 7:00 AM to 5:00 PM on Monday through Friday; a three (3) person shift works on Saturdays from 8:00 AM to 4:00PM.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 2-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 2-Lamp F96 SuperSaver T12 with 8' magnetic slim line ballast fixture

• 4-Lamp 34Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 70 Watt metal halide fixture

• 250 Watt metal halide fixture

NOTE: Occupancy sensors are not being utilized at this facility.

Example of Audited Lighting Fixtures

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

LIGHTING RETROFIT: During the energy auditing of all City facilities included within the scope, the City of Hallandale Beach executed a lighting retrofit project within the garage. The scope entailed changing the metal halide fixtures in the bay area to fluorescent, 54 Watt T5 technology.

Page 71: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 71

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Retrofitted Lighting Fixtures

HVAC

The main office space is cooled by a unitary DX package window unit that was replaced in September 2013, while the HVAC maintenance office is cooled by one (1) split DX unit. These units are operated as needed but are often left running 24 hours a day.

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplate information obtained on site. The following table summarizes the equipment specifications of each unit serving the Administration Building.

DPW GARAGE: HVAC EQUIPMENT

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the

Split DX NAC024AKB2 E032844095 namplate namplate 208 1 9.8 0.9

Window Unit 1 Friedrich - Installed 2013 - 208 1 - 0.9

P.F.

General Information Source Information

EQUIPMENT Model Serial Description Source of Information V Ph Amps

Page 72: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 72

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

appendix of this report. The building water pressure is assumed to be the same as for the Administration side of the building: 48 psig.

• Restroom Sinks: (1) 2.0 gpm standard 4 and 8 inch, cold only

• Toilets: (2) 1.6 gpf

• Urinals: (1) 1.0 gpf

• Showers: (1) high flow (2.5 gpm), standard shower

• Other: (1) 2.0 gpm non-adaptable faucets

B.8. Crew Quarters and Shop The Crew Quarters and Shop, located at 640 NW 2nd Street, is a single story building that consists of offices, locker rooms, an employee lounge, and a working wood shop. The facility was built in 2000 and is assumed to be a part of the reported 17,900 square feet that includes the DPW Garage and Warehouse.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Crew Quarters building has a total of 60 full-time staff members entering and leaving the building all week, and the working hours for these staff members are 7:30 AM-5:00 PM, Monday through Friday; the facility is closed on weekends. As a precaution for the occasional need of emergency work and response operations, the building is kept unlocked and available for crews and workers to utilize 24 hours a day, 7 days a week.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 2-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 2-Lamp T8 U tube with standard electric ballast fixture

• 2-Lamp 40 Watt SuperSaver T12 U-tube with standard magnetic ballast fixture

• 4-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

NOTE: Occupancy sensors are not being utilized at this facility.

Page 73: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 73

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Examples of Lighting Equipment

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for this building is available to all areas except the shop. One (1) RTU cools the locker rooms, foreman offices, and employee lounge, and an additional split DX unit provides supplemental cooling for the lounge.

Originally the RTU was the primary source for cooling. The RTU is situated on the roof above the lounge area and was designed to have all return air return through the lounge before entering the RTU. Due to the large heat loads within the lounge (vending machines, ice machines, and multiple employees entering and leaving), the unit was experiencing high return air temperatures and began having trouble cooling the spaces. To correct the situation the DX unit was added to provide additional cooling for the lounge and help drive down the return air temperature experienced by the RTU.

HVAC Equipment

Page 74: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 74

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Equipment data for each the aforementioned equipment was collected from nameplate information obtained on site. The following table summarizes the equipment specifications of each unit serving the Crew Quarters.

Crew Quarters: HVAC Equipment

HVAC CONTROL AND EQUIPMENT OPERATION

The DX and RTU unit are controlled by a dedicated, White Rodgers, digital thermostats. Employees have full control over each thermostat and, at the time of the energy audit, both units were set to 74°F. The room temperature experienced by staff in the lounge was observed to be approximately 77°F during the course of the energy audit. Both units run 24 hours a day.

HVAC Control Method

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report. The building water pressure is assumed to be the same as for the Administration side of the building: 48 psig.

• Restroom Sinks: (4) 2.0 gpm standard 4 and 8 inch, hot and cold

• Toilets: (3) 1.6 gpf

• Toilets: (1) 1.6 gpf tank toilet

Split DX 1

Condenser 24ABB348A310 3508E05479 nameplate 4 208 1 19.9 11 0.9

AHU Carrier FY4ANF048 2708A85530 2008 nameplate 0.75 208 1 4.3 0.9

RTU 1 Bard P1060A1 153C052007098-1 nameplate 0.8333 5 230 1 31.4 0.9

Water Heater 1 GE38S06AAG GE1106B36921 38 Gallons 208 1

Ph Amps EER P.F.Source of Information HP Tons V

General Information Size / Capacity Source Information

EQUIPMENT Manufacterer Model Serial Description

Page 75: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 75

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Urinals: (2) 1.0 gpf

• Showers: (1) high flow (2.5 gpm), standard shower

• Other: (1) 2.0 gpm general purpose sink

• Other: (1) ice machine (400 lb)

Examples of Existing Water Fixtures

B.9. Warehouse The Warehouse, located at 644 NW 2nd Street, is a single story structure used primarily as storage space. There are a total of two (2) small warehouse offices in this building. One of these offices is the City’s water meter shop. The facility was built in 1968 and is assumed to be a part of the reported 17,900 square feet that includes the DPW Garage and Crew Quarters.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Warehouse building has a total of one (1) full-time staff member working from 7:30 AM-5:00 PM, Monday through Friday, and is closed on weekends. The warehouse is utilized as needed during these work hours.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 2-Lamp F96 SuperSaver T12 with 8' magnetic slim line ballast fixture

• 4-Lamp 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

Page 76: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 76

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• 4-Lamp 32 Watt T8 with 4' linear fixture

• 150 Watt High Pressure Sodium fixture

NOTE: Occupancy sensors are not being utilized at this facility. The employees have developed the good habit of manually turning lights on when they arrive and turning them off as they leave.

Examples of Lighting Equipment

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling is only provided to the offices and one (1) small storage area by dedicated unitary package window units. These units are controlled by the employee residing in the office.

B.10. Sanitation West Parcel Sanitation West Parcel is currently located on the second floor of the DPW Administration Building. This second floor space was constructed as an addition to the building to temporarily house this department. The space consists of offices and storage closets. During the audit, it was reported that the remaining City employees utilizing this space will be relocated into a new building. This office space is expected to be vacated by January 2014 and completely removed some time after due to its deteriorating condition caused by extensive termite damage.

Page 77: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 77

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits.

The Sanitation West Parcel facility has a remaining two (2) offices still in use. The hours of operation are the same as for the first floor (Administration Building): 7:00 AM-5:00 PM, Monday through Friday. The facility is closed on weekends.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 60 Watt Incandescent Fixture

• 150 Watt Incandescent Fixture

• (2) Lamp 40W SuperSaver T12 U tube with standard magnetic ballast fixture

• (4) Lamp 34W SuperSaver T12 with 4' magnetic ballast linear fixture

• 100 Watt Metal Halide fixture

NOTE: Occupancy sensors are not being utilized at this facility.

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for the second floor is provided by two (2) Rheem split DX units with electric heat capabilities, installed in 2007. Each unit is responsible for cooling half of the second floor.

HVAC Equipment

Page 78: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 78

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Equipment data for each the aforementioned equipment was collected from nameplate information obtained on site. The following table summarizes the equipment specifications of each unit serving the Sanitation West Parcel.

Sanitation West Parcel: HVAC Equipment

HVAC CONTROL AND EQUIPMENT OPERATION

The DX units are each controlled by dedicated Honeywell digital thermostats and the staff has full control over each thermostat. At the time of the energy audit the temperature setpoints were 72 and 76°F. The setpoints are reportedly adjusted as needed.

HVAC Control Method

A data logging session was conducted for a period of 2 weeks to obtain equipment operation runtimes and calibrate the energy model. The results of the logging data is provided in the appendix of this report. The data revealed that both units are running 24 hours a day.

Split DX 2

Condenser Rheem RANL-060JAZ 7307 M2807 07594 2nd Floor 2007 5 208 1 25.3 0.9

AHU Rheem RBHC-21J11NFC T M3502 07041 0.33 208 1 3.2 0.9

Split DX 4 2nd Floor

Condenser Rheem RAND-042JAZ 7300 M2907 09396 2007 3.5 208 1 19.2 0.9

AHU Rheem RHSA-HM4221JA M1307 04367 2007 0.5 208 1 5.2 0.9

Tons V Ph Amps P.F.

General Information Size / Capacity Nameplate Information

EQUIPMENT Manufacterer Model Serial Description Notes HP

Page 79: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 79

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Data logging Results

WATER

The restrooms on this floor have already been decommissioned and are not operational.

B.11. Golden Isles Tennis Center The Golden Isles Tennis Center, located at 300 Egret Drive, is a two-story building consisting of a retail store on the first floor, a recreational common space on the second floor, and restroom facilities with showers. The building is approximately 3,000 sq ft.

The tennis center also includes a total of 10 tennis courts, arrange in pairs of two, to the north of the building.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits. The Tennis Center is operated by one (1) person from approximately 8:00 AM – 12:00 PM on Monday through Friday. The tennis courts are unlocked and utilized throughout this time, and are reopened again in the evenings.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

Page 80: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 80

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Interior Lighting:

• 3-Lamp, 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

• 4-Lamp, 32Watt T8 with 4' linear fixture

• 2-Lamp, T8 U-tube with standard electric ballast fixture

• 4-Lamp, 34 Watt SuperSaver T12 with 4' magnetic ballast linear fixture

Exterior Lighting (including tennis courts):

• 850 Watt metal halide fixture

• 175 Watt metal halide fixture

• 2-Lamp 150 Watt Incandescent fixture

• 2-Lamp 26 Watt plug-in compact fluorescent fixture

• 400 Watt high pressure sodium fixture

NOTE: Occupancy sensors are not being utilized at this facility.

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

Example Lighting Fixtures

HVAC

Cooling is provided by two (2) split DX and one (1) unitary package window unit. The DX units cool the restrooms and first floor office and retail tennis store.

Page 81: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 81

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

HVAC Equipment

Equipment data for each the aforementioned equipment was collected from nameplate information obtained on site. The following table summarizes the equipment specifications of each unit serving the Golden Isles Tennis Center.

Golden Isles Tennis Center: HVAC Equipment

HVAC CONTROL AND EQUIPMENT OPERATION

The DX units are each controlled by dedicated White Roger digital thermostats and the staff has full control over each thermostats. At the time of the energy audit the temperature setpoints kept above 74°F and are reportedly adjusted as needed. All units were observed to operate 24 hours a day.

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Measured building water pressure is 52 psig

• Restroom Sinks: (5) 2.0 gpm single spigot, cold only

• Toilets: (4) 3.5 gpf

• Urinals: (2) 1.5 gpf

• Showers: (2) high flow (2.5 gpm), standard showers

• Other: (1) general purpose sink

Split DX 1 Rheem RAND-036JAZ 7297 M0706 21270 Restrooms nameplate 0.2 3 208 1 14.4 0.9 2006

Split DX 2 Rheem RAND-024JAZ 729 F3306 14737 1st Floor nameplate 0.1 2 208 1 10.4 0.9 2006

Window Unit 1 Friedmont 2nd Floor 1

Water Heater 1 nameplate

V

General Information Size / Capacity Source Information

EQUIPMENT Manufacterer Model Serial Description Ph Amps EER P.F. YearSource of Information HP Tons

Page 82: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 82

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Examples of Existing Water Fixtures

B.12. Three Islands Guardhouses The Three Islands Guards houses are two (2) guard gates located at 1941 Atlantic Shores Blvd and Three Islands Blvd. Each guard house is approximately 250 square feet and consists of an indoor desk counter and restroom. Both are equipped with an automatic gate lift that allows cars to pass through during the day.

OCCUPANCY AND HOURS OF OPERATION

Police or security officers are sometimes requested to be stationed at a guard house. Their presence is not based on an established schedule or specific times or dates; they are asked to man the guard house sporadically.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility. The detailed lighting audit is provided within the Appendix on this report.

• 2-Lamp 32 Watt T8 with 4' linear fixture

• 150 Watt high pressure sodium fixture

• 175 Watt metal halide fixture

• 400 Watt metal halide fixture

NOTE: Occupancy sensors are not being utilized at this facility. Lights were observed to be off at both guard houses during each site visit.

Page 83: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 83

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Example Lighting Fixtures

HVAC

Each guard house was provided a plug-in spot cooler for use when someone is occupying the space. These spot coolers were observed to be left running during unoccupied periods of time.

Spot Coolers Left Running

B.13. Golden Isles Guard House The Golden Isles Guard House, located at 450 Layne Blvd, is a 200 square feet guard gate with an indoor security desk and restroom. The guard house is equipped with two (2) electric lift gates, one for residents with pass cards and one for visitors that must first check in with a guard.

OCCUPANCY AND HOURS OF OPERATION

The building occupancy and hours of operation for this facility was obtained from various staff interviews conducted during the site visits.

Page 84: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 84

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The Golden Isles Guard House always has one (1) guard manning the gate; 24 hours a day, 7 days a week.

LIGHTING

A detailed lighting audit was conducted which determined the lamp and fixture types and quantities currently installed. The following is a brief summary of this audit indicating the lighting equipment found at this facility.

• 2-Lamp 25 Watt incandescent fixture

• 3-Lamp 67 Watt incandescent fixture

• 100 Watt incandescent fixture

• 100 Watt metal halide fixture

NOTE: Occupancy sensors are not being utilized at this facility.

The detailed lighting audit is provided within the Appendix on this report. In addition to this audit, a lighting occupancy sensor data logging session was conducted for a period of two (2) weeks to measure the usage hours of lighting at this facility. These results can also be found within the Appendix. The results of both studies (the audit and the data logging session) were utilized to calibrate the energy model for this facility.

HVAC

Cooling for the security desk and restroom are provided by a recently installed, 2 Ton split DX unit. The unit is controlled by a White Rodgers digital thermostat. The security guard has full control of the operation of this unit. Based on the 24 occupancy of this guard house, this unit also operates 24 hours a day.

HVAC Equipment and Controls

Page 85: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 85

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

WATER

A detailed water consumption audit was conducted yielding the below results (summary); the detailed audit results, including savings, are provided within the appendix of this report.

• Restroom Sinks: (1) 2.2 gpm standard 4 and 8 inch

• Toilets: (1) 1.6 gpf

Page 86: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 86

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

C. Schedule C - Energy Savings Guarantee

The FIMs analyzed and recommended for implementation are summarized in the following table.

# FIM

Description

Guaranteed Annual Savings Project

Cost

Simple

Payback

(yrs)

Electric

(kWh/yr)

Water

(kgal/yr)

Cost Avoidance & Operational Savings ($/yr)

Total Savings ($/yr)

1 Lighting Retrofit

363,765 - $520 $29,413 $280,742 9.5

2 Water Conservation

- 279.9 $2,410 $26,807 11.1

3 Plug Load Management

14,346 - $631 $4,895 7.8

4 Mechanical Insulation

2,120 - $175 $1,698 9.7

5 Combine Electric Meters

- - $2,074 $18,417 8.9

6 Chiller Replacement

194,134 - $4,637 $19,798 $236,845 12.0

7 MC RTU Replace (1)

- - $9,367 $9,367 $128,172 13.7

8 VAV Replacement &

RA Flow

45,003 - $124 $4,261 $21,775 5.1

9 CC RTU Replace (7)

21,703 - $4,042 $6,151 $118,532 19.3

10 Mechanical Timers

332 - $32 $851 26.4

11 Admin Bldg P-Stats

4,004 - $70 $1,333 19.0

12 Trane BAU Upgrade

- - $2,647 $2,647 $46,509 17.6

13 Water Meters $110,000 $374,503* $4,636,285 12.4

1st Year Savings 645,397 279.9 $131,337 $451,532* $5,522,861

Project Summary

*Includes $50,000 in avoided capital costs during the first five years of the contractterm. No capital cost avoidance used in years 6 – 15.

Page 87: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 87

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

D. Schedule D - Compensation to ESCO

D.1. ESCO Compensation / Project Costs

ARTICLE 1: PAYMENT FOR EQUIPMENT TO BE INSTALLED BY COMPANY

1.1 Price: As full consideration of the Scope of Work described in Schedule A: Equipment to Be Installed By COMPANY, the CITY shall pay to COMPANY $5,772,183 (plus taxes, if applicable). This total includes the City’s Direct Purchase of $2,563,188 of equipment from vendors; net compensation to COMPANY is $3,208,995.

1.2 Escrow: The CITY has agreed to deposit the Price into an Escrow Account at a financial institution satisfactory to both the CITY and COMPANY. All expenses to establish the Escrow Account shall be the complete responsibility of the CITY and the CITY will receive all interest earnings from the Escrow Account. COMPANY will submit periodic invoices to the CITY based on the Progress Payments. The CITY shall be responsible for submitting the necessary documents to the Escrow Agent to allow for timely disbursements from the Escrow Account. The funding of the Escrow Account in an amount equal to or greater than the Price stated in Article 1.1 above shall be a condition precedent to COMPANY obligation to perform or to continue the performance of the Work. If the Escrow Account is not funded within 30 days of the execution of this Amendment, this Amendment shall be null and void. This 30 day funding period may be extended as mutually agreed in writing by the Parties. In the event that the Agreement becomes null and void as described in this paragraph and CITY has previously authorized COMPANY to proceed with the Work, the CITY shall be obligated to reimburse COMPANY either: (i) for the Work performed to date; or (ii) for the Work specifically authorized by the CITY.

1.3 Timely Payments: The CITY agrees to pay COMPANY progress payments based on percentage of work completed. CITY agrees to pay all invoices submitted by COMPANY per Section 5 of the Agreement.

ARTICLE 2: PAYMENT FOR SERVICES PROVIDED BY COMPANY

2.1 Price: As full consideration of the M&V Services described in Schedule F, the CITY shall pay to COMPANY the amounts identified in Table D.2 plus taxes, if applicable, on the dates identified therein.

2.2 Term: The term of the M&V Plan shall commence on the Commencement Date and shall extend for either: (a) the term of the M&V Plan where multi-year obligations are allowed; or (b) for twelve (12) month periods corresponding to Section 3 of the Contract.

Page 88: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 88

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

2.3 Automatic Renewal: The M&V Plan shall automatically renew for successive annual periods consistent with Section 3 of the Contract. Either party may request to amend the M&V Plan at the end of an annual period by giving the other party at least sixty (60) days prior written notice of such amendments and such amendment shall be mutually negotiated by the Parties and effective upon a written amendment signed by both Parties prior to commencement of the next M&V term. Each automatic renewal shall be and remain subject to the terms and conditions of the Contract. COMPANY obligations under the Guarantee are dependent upon and subject to the express condition that the CITY maintains the M&V during the term of the Guarantee.

2.4 Termination: See Section 5.1 of the Agreement.

Table D.2 M&V Plan Billing Schedule

Services and Maintenance: Description of Deliverable Cost (annual payments)

Year 1 Performance Assurance (M&V) $25,315

Year 2 Performance Assurance (M&V) $19,557

Year 3 Performance Assurance (M&V) $20,144

Year 4 Performance Assurance (M&V) $20,748

Year 5 Performance Assurance (M&V) $21,370

Year 6 Performance Assurance (M&V) $22,011

Year 7 Performance Assurance (M&V) $22,672

Year 8 Performance Assurance (M&V) $23,352

Year 9 Performance Assurance (M&V) $24,052

Year 10 Performance Assurance (M&V) $24,774

Year 11 Performance Assurance (M&V) $25,517

Year 12 Performance Assurance (M&V) $26,283

Year 13 Performance Assurance (M&V) $27,071

Year 14 Performance Assurance (M&V) $27,883

Year 15 Performance Assurance (M&V) $28,720

Page 89: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 89

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

E. Schedule E – Baseline Energy Consumption

Each facility investigated within the City of Hallandale Beach consists of its own dedicated electric meter, account, and corresponding billing rate structure. FPL is the primary provider of electrical service across all facilities. The following is a description of each of the different types of electric billing rate structures encountered, those facilities currently billed under each structure, and the corresponding effective rate. The effective rate is a calculated value that includes all applicable taxes and fees associated with each unit of energy. Effective rates are used in the energy calculations in order to account for all costs associated with the reduction in consumption.

General Service Non-Demand (GS-1) – This rate structure is for electric service required for commercial or industrial lighting, power and any other purpose with an electric demand of 20 kW or less. The billing structure consists of a single charge per unit of consumption (kWh).

The following table states the rates, per unit of energy, offered under this rate structure and the facilities to which they pertain.

General Service Demand (GSD-1) – This rate structure is for electric service required for commercial or industrial lighting, power and any other purpose with a measured electric demand in excess of 20 kW and less than 500 kW. Accounts with an electric demand of 20 kW or less may enter an agreement for service under this schedule based on a Demand Charge for a minimum of 21 kW. The billing structure consists of a single charge per unit of demand (kW) and a single, separate charge per unit of consumption (kWh).

The following table states the rates, per unit of energy, offered under this rate structure and the facilities to which they pertain.

GS-1 Rate StructureFaciltiy $/kWHWarehouseFire Station 90Guard House (Layne)Guard House (3 islands)

0.07807$

GSD-1 Rate StructureFaciltiy $/kWH $/kWhDPW AdminCultural CenterCrew QuartersHepburn CenterFire Station 60Golden Isles Tennis

0.04928$ 10.94$

Page 90: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 90

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Commercial/Industrial Load Control Program (CILC-1(G)) – This rate structure is for electric service provided to any commercial or industrial customer as part of the Commercial/Industrial Load Control Program Agreement. This rate structure allows FPL to control at least 200 kW of the Customer’s load or operate Backup Generation Equipment to serve at least 200 kW of the Customer’s load when FPL requires “load shedding”. The (G) designation is for a power demand of greater than 200 kW but less than 500 kW. The billing structure consists of maximum demand, load control on-peak demand, firm on-peak demand, and on-peak and off-peak kWh charges.

The on peak periods are as follows: November 1 – March 31: Monday through Friday, 6 am to 10 am and 6 pm to 10 pm, excluding Thanksgiving Day, Christmas day, and New Year’s Day; and April 1 – October 31, Monday through Friday, 12 noon to 9 pm, excluding Memorial Day, Independence Day, and Labor Day.

The following table states the rates, per unit of energy, offered under this rate structure and the facilities to which they pertain.

Sports Field Service (OS-2) – This is a transitional rate available to municipal, county and school board accounts for the operation of a football, baseball or other playground, or civic or community auditorium, when all such service is taken at the available primary distribution voltage at a single point of delivery and measured through one meter, and who were active as of October 4, 1981. Customer may also elect to receive service from other appropriate rate schedules.

Per the request of the City, 24 months (2 years) of electric data were analyzed to form a baseline for the energy savings performance contract project. Two annual periods of electric data were averaged together, by month, to form the following baseline tables and charts.

CILC-1G Rate Structure

Faciltiy $/kWH Summer on-peak

$/kWH Summer off-peak

$/kWH Winter off-peak

$/kWH Winter off-peak

$/kWh L/C on-peak

$/kWh maximum

Municipal Complex 0.05951$ 0.03658$ 0.04985$ 0.04234$ 5.91$ 3.52$

OS-2 Rate StructureFaciltiy $/kWHGolden Isles Tennis Courts 0.10691$

Page 91: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 91

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The following table summarizes totals from the established baselines of each facility.

ELECTRIC CONSUMPTION SUMMARY FOR ALL FACILITIES

The following pages address the utility breakdown of each facility individually.

Facility Total Consumption (kWh)

Maximum Demand (kW)

Total Billed Cost (dollars)

Municipal Complex 1,467,806 313 113,936$ Cultural Center 240,138 90 24,006$ Hepburn Center 242,580 70 22,429$ DPW Administration/Garage 173,237 48 15,902$ Warehouse 32,924 - 3,459$ Crew Quarters 76,161 20 7,096$ Fire Station 60 236,100 48 19,474$ Fire Station 90 31,022 - 3,265$ Golden Isles Tennis Center 202,170 129 23,429$ Golden Isles Tennis Center Courts 66,215 - 8,064$ Three Island Guard Houses 4,693 - 571$ Godlen Isles Guard House 21,260 - 2,266$

Totals: 2,794,303 716 243,895$

Page 92: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 92

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

E.1. Municipal Complex The Municipal Complex has FPL electric account number: 90002-04306, Meter Number: RV554V0, and falls under the FPL CILC-1(G) electric rate structure.

MUNICIPAL COMPLEX: CILC-1(G) - ELECTRIC CONSUMPTION SUMMARY

MUNICIPAL COMPLEX: ELECTRIC BASELINE PROFILE

The maximum power demand was seen in August with a value of 313 kW, and the maximum energy consumption of 154,320 kWh also occurring in August. The highest power and energy consumption occurring in the summer and early fall months, with maximums occurring both in August, follows the trend of other facilities located in South Florida exhibiting higher electric utility usage during months with the highest outside temperatures. Mechanical cooling equipment is used for the longest periods of the year during the summer months causing the highest electric usage.

Billing Date

Customer Charge

Consumption (kWh)

On-Peak kWh Off-Peak kWh Consumption

Charges

Actual Demand

(kW)

On-Peak kW

Demand Charges Taxes Total Billed

Amount

Aug 103.48$ 154,320 49,982 104,339 6,791$ 313 312.5 2,947$ 1,987$ 11,828$ Sept 103.48$ 130,080 43,753 86,327 5,762$ 308 307.5 2,900$ 1,767$ 10,532$ Oct 103.48$ 126,420 39,804 86,617 5,652$ 275 271.5 2,573$ 1,678$ 10,006$ Nov 103.48$ 115,680 27,202 88,478 5,102$ 221 211 2,023$ 1,454$ 8,683$ Dec 103.48$ 109,920 26,219 83,702 4,851$ 229 201 1,994$ 1,397$ 8,345$ Jan 103.48$ 103,980 26,698 77,282 4,603$ 223 203.5 1,986$ 1,344$ 8,037$ Feb 103.48$ 101,700 26,482 75,218 4,505$ 227 212 2,050$ 1,337$ 7,996$ Mar 103.48$ 108,100 29,310 78,790 4,797$ 230 227 2,151$ 1,418$ 8,469$ Apr 103.48$ 113,760 36,456 77,304 4,997$ 238 238 2,244$ 1,478$ 8,823$ May 103.48$ 130,080 40,647 89,433 5,690$ 267 265 2,504$ 1,672$ 9,970$ Jun 103.48$ 133,140 43,000 90,140 5,856$ 291 291 2,744$ 1,755$ 10,459$ Jul 103.48$ 140,626 44,894 95,732 6,174$ 292 283.5 2,702$ 1,811$ 10,789$

Totals 1,242$ 1,467,806 434,446 1,033,360 64,780$ 313 312.5 28,818$ 19,097$ 113,936$

0

50

100

150

200

250

300

350

0

20,000

40,000

60,000

80,000

100,000

120,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Municipal Complex Baseline Profile

On-Peak kWh Off-Peak kWh kW

Page 93: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 93

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Power demand was seen at a minimum in November with a value of 221 kW, and the minimum energy consumption of 101,700 kWh occurring in February. The power demand minimum was likely the result of more temperate weather in the fall with minimal use of electric reheat. Minimum electric consumption occurs in the winter month with the reduced run hours of mechanical cooling equipment. Power demand is consistent throughout the year with the use of mechanical heating to temper discharge air and also for building heat during cooler, temperate periods of the year.

E.2. Cultural Center The Cultural Center has FPL electric account number: 19294-09439, Meter Number: 6NL0242, and falls under the FPL GSD-1 electric rate structure.

TABLE 3.1.3: CULTURAL CENTER: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

CULTURAL CENTER: ELECTRIC BASELINE PROFILE

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 26,443 1,303$ 86 935$ 2,238$ 222$ 2,479$ Sept 18.63$ 23,646 1,165$ 80 875$ 2,040$ 202$ 2,262$ Oct 18.63$ 19,597 966$ 72 788$ 1,753$ 174$ 1,946$ Nov 18.63$ 14,897 734$ 65 711$ 1,445$ 143$ 1,607$ Dec 18.63$ 15,298 754$ 66 717$ 1,470$ 146$ 1,635$ Jan 18.63$ 14,261 703$ 61 662$ 1,365$ 135$ 1,519$ Feb 18.63$ 15,073 743$ 76 831$ 1,574$ 156$ 1,749$ Mar 18.63$ 15,432 760$ 61 667$ 1,428$ 142$ 1,588$ Apr 18.63$ 19,305 951$ 77 842$ 1,794$ 178$ 1,990$ May 18.63$ 23,022 1,135$ 74 804$ 1,939$ 192$ 2,150$ Jun 18.63$ 24,660 1,215$ 90 985$ 2,200$ 218$ 2,437$ Jul 18.63$ 28,505 1,405$ 90 985$ 2,389$ 237$ 2,645$

Totals 224$ 240,138 11,834$ 90 9,802$ 21,636$ 2,146$ 24,006$

0

10

20

30

40

50

60

70

80

90

100

0

5,000

10,000

15,000

20,000

25,000

30,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Cultural Center Baseline Profile

kWh kW

Page 94: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 94

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The maximum power demand was seen in June and July with a value of 90 kW, and the maximum energy consumption of 28,505 kWh occurring in July. The highest power and energy consumption occurring in the summer months, with maximums occurring in June and July, follows the trend of other facilities located in South Florida exhibiting higher electric utility usage during months with the highest outside temperatures. Mechanical cooling equipment is used for the longest periods of the year during the summer months causing the highest electric usage.

Power demand was seen at a minimum in January with a value of 61 kW, and the minimum energy consumption of 14,621 kWh occurring in January. Minimum power and electric consumption occurs in the winter month period due to reduced run hours of mechanical cooling equipment.

E.3. Department of Public Works Administration Building The Department of Public Works (DPW) Administration Building has FPL electric account number: 50689-43066, Meter Number: 6J39559, and falls under the FPL GSD-1 electric rate structure.

TABLE 3.1.4: DPW ADMIN BUILDING: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 18,117 893$ 47 509$ 1,402$ 153$ 1,573$ Sept 18.63$ 16,725 824$ 48 520$ 1,344$ 146$ 1,509$ Oct 18.63$ 14,900 734$ 46 503$ 1,238$ 135$ 1,391$ Nov 18.63$ 11,933 588$ 41 443$ 1,031$ 112$ 1,162$ Dec 18.63$ 12,529 617$ 40 438$ 1,055$ 115$ 1,189$ Jan 18.63$ 11,537 569$ 39 421$ 990$ 108$ 1,116$ Feb 18.63$ 11,246 554$ 39 427$ 981$ 107$ 1,106$ Mar 18.63$ 11,692 576$ 38 410$ 986$ 107$ 1,112$ Apr 18.63$ 14,567 718$ 42 454$ 1,172$ 128$ 1,318$ May 18.63$ 16,522 814$ 45 487$ 1,301$ 142$ 1,461$ Jun 18.63$ 16,276 802$ 44 476$ 1,278$ 139$ 1,436$ Jul 18.63$ 17,195 847$ 47 514$ 1,362$ 148$ 1,528$

Totals 224$ 173,237 8,537$ 48 5,601$ 14,138$ 1,540$ 15,902$

Page 95: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 95

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

DPW ADMINISTRATION: ELECTRIC BASELINE PROFILE

The maximum power demand was seen in September with a value of 48 kW, and the maximum energy consumption of 18,117 kWh occurring in August. The highest power and energy consumption occurring in the summer and early fall months, with maximums occurring in August and September, follows the trend of other facilities located in South Florida exhibiting higher electric utility usage during months with the highest outside temperatures. Mechanical cooling equipment is used for the longest periods of the year during the summer months causing the highest electric usage.

Power demand was seen at a minimum in March with a value of 81 kW, and the minimum energy consumption of 11,246 kWh occurring in February. Minimum electric consumption occurs in the winter month period due to reduced run hours of mechanical cooling equipment.

E.4. Crew Quarters The Crew Quarters has FPL electric account number: 50699-41093, Meter Number: 6C52588, and falls under the FPL GSD-1 electric rate structure.

0

5

10

15

20

25

30

35

40

45

50

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

DPW Administration Baseline Profile

kWh kW

Page 96: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 96

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

TABLE 3.1.5: CREW QUARTERS: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

CREW QUARTERS: ELECTRIC BASELINE PROFILE

The maximum power demand was seen in June, July, and August with a value of 20 kW, and the maximum energy consumption of 8,989 kWh occurring in August. The highest power and energy consumption occurring in the summer months, with maximums occurring in June, July, and August, follows the trend of other facilities located in South Florida exhibiting higher electric utility usage during months with the highest outside temperatures. Mechanical cooling equipment is used for the longest periods of the year during the summer months causing the highest electric usage.

Power demand was seen at a minimum in November with a value of 14 kW, and the minimum energy consumption of 4,275 kWh occurring in January. Minimum power

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 8,989 443$ 20 219$ 662$ 99$ 779$ Sept 18.63$ 7,232 356$ 18 197$ 553$ 83$ 655$ Oct 18.63$ 5,903 291$ 18 191$ 482$ 72$ 573$ Nov 18.63$ 4,932 243$ 14 153$ 396$ 59$ 474$ Dec 18.63$ 4,836 238$ 15 164$ 402$ 60$ 481$ Jan 18.63$ 4,275 211$ 15 164$ 375$ 56$ 449$ Feb 18.63$ 4,289 211$ 15 164$ 375$ 56$ 450$ Mar 18.63$ 5,102 251$ 15 164$ 416$ 62$ 496$ Apr 18.63$ 6,147 303$ 16 175$ 478$ 71$ 568$ May 18.63$ 7,684 379$ 19 202$ 581$ 87$ 686$ Jun 18.63$ 8,256 407$ 20 213$ 620$ 93$ 731$ Jul 18.63$ 8,519 420$ 20 219$ 639$ 95$ 753$

Totals 224$ 76,161 3,753$ 20 2,226$ 5,979$ 892$ 7,096$

0

5

10

15

20

25

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Crew Quarters Baseline Profile

kWh kW

Page 97: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 97

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

and electric consumption occurs in the winter month period due to reduced run hours of mechanical cooling equipment.

E.5. Hepburn Center The Hepburn Center has FPL electric account number: 07580-54811, Meter Number: 6T36901, and falls under the FPL GSD-1 electric rate structure.

HEPBURN CENTER: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

HEPBURN CENTER: ELECTRIC BASELINE PROFILE

The maximum power demand was seen August with a value of 70 kW, and the maximum energy consumption of 25,950 kWh occurring in August. The highest power and energy consumption occurs in the summer months, with maximums in

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 25,950 1,279$ 70 766$ 2,045$ 220$ 2,283$ Sept 18.63$ 21,960 1,082$ 68 744$ 1,826$ 196$ 2,041$ Oct 18.63$ 21,450 1,057$ 61 662$ 1,719$ 185$ 1,922$ Nov 18.63$ 16,200 798$ 56 607$ 1,406$ 151$ 1,575$ Dec 18.63$ 15,450 761$ 54 591$ 1,352$ 145$ 1,516$ Jan 18.63$ 15,540 766$ 55 596$ 1,362$ 146$ 1,527$ Feb 18.63$ 15,990 788$ 57 618$ 1,406$ 151$ 1,576$ Mar 18.63$ 17,520 863$ 56 613$ 1,476$ 159$ 1,653$ Apr 18.63$ 19,770 974$ 62 673$ 1,647$ 177$ 1,843$ May 18.63$ 24,870 1,226$ 68 738$ 1,964$ 211$ 2,194$ Jun 18.63$ 23,580 1,162$ 68 738$ 1,900$ 204$ 2,123$ Jul 18.63$ 24,300 1,198$ 69 749$ 1,947$ 209$ 2,175$

Totals 224$ 242,580 11,954$ 70 8,096$ 20,050$ 2,155$ 22,429$

0

10

20

30

40

50

60

70

80

0

5,000

10,000

15,000

20,000

25,000

30,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Hepburn Center Baseline Profile

kWh kW

Page 98: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 98

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

August, following the trend of other South Florida facilities exhibiting higher electric utility usage du Mechanical cooling equipment is used for the longest periods of the year during the summer months causing the highest electric usage.

Power demand was seen at a minimum in December with a value of 54 kW, and the minimum energy consumption of 4,275 kWh occurring in December. Minimum power and electric consumption occurs in the winter month period due to reduced run hours of mechanical cooling equipment. Additionally, since the Hepburn Center is a community center, occupancy may have decreased during the December holiday season.

E.6. Fire Station 60 Fire Station 60 has FPL electric account number: 05749-71198, Meter Number: 6U36911, and falls under the FPL GSD-1 electric rate structure.

FIRE STATION 60: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

FIRE STATION 60: ELECTRIC BASELINE PROFILE

Billing Date

Customer Charge

Averaged Consumption (kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 19,710 971$ 41 449$ 1,420$ 157$ 1,596$ Sept 18.63$ 19,530 962$ 48 520$ 1,482$ 164$ 1,665$ Oct 18.63$ 20,280 999$ 46 503$ 1,503$ 167$ 1,688$ Nov 18.63$ 19,020 937$ 46 498$ 1,435$ 159$ 1,613$ Dec 18.63$ 19,920 982$ 45 487$ 1,468$ 163$ 1,650$ Jan 18.63$ 21,270 1,048$ 43 465$ 1,513$ 168$ 1,700$ Feb 18.63$ 21,420 1,056$ 42 454$ 1,510$ 167$ 1,696$ Mar 18.63$ 22,620 1,115$ 45 492$ 1,607$ 178$ 1,804$ Apr 18.63$ 20,670 1,019$ 45 492$ 1,511$ 167$ 1,697$ May 18.63$ 20,880 1,029$ 41 449$ 1,478$ 164$ 1,660$ Jun 18.63$ 19,110 942$ 42 459$ 1,401$ 155$ 1,575$ Jul 18.63$ 11,670 575$ 39 427$ 1,002$ 111$ 1,131$

Totals 224$ 236,100 11,635$ 48 5,694$ 17,329$ 1,921$ 19,474$

0

5

10

15

20

25

30

35

40

45

50

0

5,000

10,000

15,000

20,000

25,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Fire Station 60 Baseline Profile

kWh kW

Page 99: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 99

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The maximum power demand was seen September with a value of 48 kW, and the maximum energy consumption of 22,620 kWh occurring in March. The highest power consumption occurring in the summer months, with the maximum occurring in September, follows the trend of other facilities located in South Florida exhibiting higher electric utility usage during months with the highest outside temperatures. The highest energy consumption occurring in March may be attributed with the nature of the use of fire stations. Traditionally, residential type buildings can have different usage patterns than commercial buildings.

Power demand was seen at a minimum in July with a value of 39 kW, and the minimum energy consumption of 11,670 kWh occurring in July. The minimums occurring in July could be attributed with the recent mechanical equipment replacement that was performed at the fire house. The minimums occurring at peak temperature periods do not follow traditional South Florida historical utility trends of other facilities.

E.7. Golden Isles Tennis Center The Golden Isles Tennis Center has FPL electric account number: 80193-51843, Meter Number: 6V57062, and falls under the FPL GSD-1 electric rate structure. This meter includes the Egret lift station located just south of the tennis center. This electric account does not include the tennis court lighting and only meters the usage of the building and lift station.

GOLDEN ISLES TENNIS CENTER: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

Billing Date

Customer Charge

Averaged Consumption (kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 17,580 866$ 63 689$ 1,556$ 182$ 1,756$ Sept 18.63$ 14,160 698$ 56 613$ 1,310$ 154$ 1,483$ Oct 18.63$ 16,020 789$ 66 717$ 1,506$ 176$ 1,701$ Nov 18.63$ 19,140 943$ 79 864$ 1,807$ 212$ 2,038$ Dec 18.63$ 9,570 472$ 129 1,406$ 1,877$ 220$ 2,116$ Jan 18.63$ 17,520 863$ 64 700$ 1,564$ 183$ 1,765$ Feb 18.63$ 17,820 878$ 96 1,050$ 1,928$ 226$ 2,173$ Mar 18.63$ 16,020 789$ 66 717$ 1,506$ 176$ 1,701$ Apr 18.63$ 17,760 875$ 91 990$ 1,865$ 219$ 2,102$ May 18.63$ 17,580 866$ 60 651$ 1,517$ 178$ 1,714$ Jun 18.63$ 19,260 949$ 116 1,269$ 2,218$ 260$ 2,497$ Jul 18.63$ 19,740 973$ 105 1,143$ 2,116$ 248$ 2,383$

Page 100: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 100

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

GOLDEN ISLES TENNIS CENTER: ELECTRIC BASELINE PROFILE

The maximum power demand was seen December with a value of 129 kW, and the maximum energy consumption of 19,740 kWh occurring in November. Power demand was seen at a minimum in September with a value of 56 kW, and the minimum energy consumption of 9,570 kWh occurring in December. The usage patterns for both power and energy consumption are erratic throughout the year. These usage patterns could be attributed with the occasional use of the facility and its lighting system.

The Golden Isles Tennis Center Tennis Courts have FPL electric account number: 80263-52826, Meter Number: RU3873H, and falls under the FPL OS-2 electric rate structure. .

0

20

40

60

80

100

120

140

0

5,000

10,000

15,000

20,000

25,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Dem

and

(kW

)

Cons

umpt

ion

(kW

h)

Month

Golden Isles Tennis Center Baseline Profile

kWh kW

Page 101: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 101

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

GOLDEN ISLES TENNIS CENTER: GSD-1 - ELECTRIC CONSUMPTION SUMMARY

GOLDEN ISLES TENNIS CENTER – TENNIS COURT: ELECTRIC BASELINE PROFILE

The tennis court lighting is the only electrical load metered under this account. Lights are used nightly by patrons of the Tennis Center. The hours that the courts operate at night have been established by the Center. As a result, electric consumption from month to month is similar. Variations depend on the number of courts in use.

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge

Averaged Demand (kW)

Demand Charge

Total Electric Charges

Calculated Taxes

Total Calculated

AmountAug 18.63$ 5,346 571$ 31 -$ 571$ 61$ 652$ Sept 18.63$ 5,809 621$ 34 -$ 621$ 67$ 706$ Oct 18.63$ 5,562 595$ 35 -$ 595$ 64$ 677$ Nov 18.63$ 5,438 581$ 37 -$ 581$ 63$ 663$ Dec 18.63$ 5,037 538$ 36 -$ 538$ 58$ 615$ Jan 18.63$ 4,944 529$ 30 -$ 529$ 57$ 604$ Feb 18.63$ 5,284 565$ 30 -$ 565$ 61$ 644$ Mar 18.63$ 5,315 568$ 28 -$ 568$ 61$ 648$ Apr 18.63$ 5,963 638$ 30 -$ 638$ 69$ 725$ May 18.63$ 6,087 651$ 30 -$ 651$ 70$ 739$ Jun 18.63$ 5,531 591$ 33 -$ 591$ 64$ 674$ Jul 18.63$ 5,902 631$ 32 -$ 631$ 68$ 717$

Totals 224$ 66,215 7,079$ 37 -$ 7,079$ 761$ 8,064$

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Cons

umpt

ion

(kW

h)

Month

Tennis Court Lighitng Baseline Profile

kWh

Page 102: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 102

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

E.8. DPW Warehouse The Warehouse at the DPW has FPL electric account number: 50,769-42076, Meter Number: AC03524, and falls under the FPL GS-1 electric rate structure.

WAREHOUSE: GS-1 - ELECTRIC CONSUMPTION SUMMARY

DPW WAREHOUSE: ELECTRIC BASELINE PROFILE

The maximum energy consumption of 19,740 kWh occurring in July and the minimum energy consumption occurred in February. The higher energy consumption during the warmer months of the year follows the weather influenced trend of electric

Billing Date

Customer Charge

Averaged Consumption

(kWh)

Consumption Charge Taxes Total Calculated

Amount

Aug 7.13$ 3,280 256$ 80$ 343$ Sept 7.13$ 2,791 218$ 68$ 293$ Oct 7.13$ 2,788 218$ 68$ 293$ Nov 7.13$ 2,265 177$ 55$ 239$ Dec 7.13$ 2,430 190$ 59$ 256$ Jan 7.13$ 2,277 178$ 56$ 240$ Feb 7.13$ 2,194 171$ 54$ 232$ Mar 7.13$ 2,268 177$ 55$ 239$ Apr 7.13$ 2,542 198$ 62$ 268$ May 7.13$ 2,917 228$ 71$ 306$ Jun 7.13$ 3,292 257$ 80$ 344$ Jul 7.13$ 3,883 303$ 95$ 405$

Totals 86$ 32,924 2,570$ 803$ 3,459$

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Cons

umpt

ion

(kW

h)

Month

Warehouse Baseline Profile

kWh

Page 103: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 103

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

consumption in South Florida. Likewise, there is a sharp decrease in energy consumption during late fall to early spring.

E.9. Fire Station #90 Fire Station 90 has FPL electric account number: 89776-54766, Meter Number: AC05905, and falls under the FPL GS-1 electric rate structure.

FIRE STATION 90: GS-1 - ELECTRIC CONSUMPTION SUMMARY

FIRE STATION 90: ELECTRIC BASELINE PROFILE

Billing Date

Customer Charge

Consumption (kWh)

Consumption Charge Taxes Total Billed

AmountAug 7.13$ 3,602 281$ 88$ 376$ Sept 7.13$ 3,186 249$ 78$ 334$ Oct 7.13$ 2,636 206$ 64$ 277$ Nov 7.13$ 2,341 183$ 57$ 247$ Dec 7.13$ 2,359 184$ 58$ 249$ Jan 7.13$ 2,024 158$ 49$ 214$ Feb 7.13$ 1,661 130$ 41$ 177$ Mar 7.13$ 1,754 137$ 43$ 187$ Apr 7.13$ 2,611 204$ 64$ 275$ May 7.13$ 2,749 215$ 67$ 289$ Jun 7.13$ 3,129 244$ 76$ 328$ Jul 7.13$ 2,971 232$ 73$ 312$

Totals 86$ 31,022 2,422$ 757$ 3,265$

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Cons

umpt

ion

(kW

h)

Month

Fire Station 90 Baseline Profile

kWh

Page 104: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 104

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The maximum energy consumption of 3,602 kWh occurring in August and the minimum energy consumption occurred in February with 1,661 kWh. The higher energy consumption during the warmer months of the year follows the weather influenced trend of electric consumption in South Florida. Likewise, there is a sharp decrease in energy consumption during late fall to early spring.

E.10. Layne Boulevard Guardhouse The Guardhouse at Layne Blvd has FPL electric account number: 25350-30098, Meter Number: AC02981, and falls under the FPL GS-1 electric rate structure.

LAYNE BLVD GUARDHOUSE: GS-1 - ELECTRIC CONSUMPTION SUMMARY

GOLDEN ISLES GUARD HOUSE: ELECTRIC BASELINE PROFILE

Billing Date

Customer Charge

Consumption (kWh)

Consumption Charge Taxes Total Billed

AmountAug 7.13$ 2,176 170$ 53$ 230$ Sept 7.13$ 1,912 149$ 47$ 203$ Oct 7.13$ 1,899 148$ 46$ 202$ Nov 7.13$ 1,669 130$ 41$ 178$ Dec 7.13$ 1,701 133$ 42$ 182$ Jan 7.13$ 1,630 127$ 40$ 174$ Feb 7.13$ 1,615 126$ 40$ 173$ Mar 7.13$ 1,448 113$ 35$ 156$ Apr 7.13$ 1,460 114$ 36$ 157$ May 7.13$ 1,806 141$ 44$ 192$ Jun 7.13$ 1,909 149$ 47$ 203$ Jul 7.13$ 2,038 159$ 50$ 216$

Totals 86$ 21,260 1,660$ 520$ 2,266$

0

500

1,000

1,500

2,000

2,500

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Cons

umpt

ion

(kW

h)

Month

Guard House (Layne) Baseline Profile

kWh

Page 105: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 105

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The maximum energy consumption of 2,176 kWh occurring in August and the minimum energy consumption occurred in March with 1,448 kWh. The energy consumption for the guardhouse is consistent throughout the year with some increased consumption during the warmer months of the year. The base usage of the guardhouse is not influenced by weather considerations as significantly as other facilities within the City.

E.11. Three Islands Guards House The Guardhouse at Three Islands Blvd has FPL electric account number: 26212-09499, Meter Number: AC03954, and falls under the FPL GS-1 electric rate structure.

THREE ISLANDS BLVD GUARDHOUSE: GS-1 - ELECTRIC CONSUMPTION SUMMARY

THREE ISLANDS GUARDS HOUSE: ELECTRIC BASELINE PROFILE

Billing Date

Customer Charge

Consumption (kWh)

Consumption Charge Taxes

Total Billed

AmountAug 7.13$ 733 57$ 19$ 83$ Sept 7.13$ 579 45$ 15$ 67$ Oct 7.13$ 290 23$ 7$ 37$ Nov 7.13$ 275 21$ 7$ 36$ Dec 7.13$ 308 24$ 8$ 39$ Jan 7.13$ 262 20$ 7$ 34$ Feb 7.13$ 289 23$ 7$ 37$ Mar 7.13$ 281 22$ 7$ 36$ Apr 7.13$ 409 32$ 10$ 49$ May 7.13$ 489 38$ 12$ 58$ Jun 7.13$ 420 33$ 11$ 51$ Jul 7.13$ 360 28$ 9$ 44$

Totals 86$ 4,693 366$ 119$ 571$

0

100

200

300

400

500

600

700

800

Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Cons

umpt

ion

(kW

h)

Month

Guard House (Three Isles) Baseline Profile

kWh

Page 106: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 106

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The maximum energy consumption of 733 kWh occurring in August and the minimum energy consumption occurred in January with 262 kWh. Within the 24 month utility data provided, August 2011 and September 2011 had noticeably higher energy consumption values than other months. This could be attributed by increased usage by security officers during those times. The baseline energy usage is consistent throughout the year and is not easily influenced by weather otherwise.

E.12. Existing Water Utility Consumption and Costs Each facility investigated within the City of Hallandale Beach consists of its own dedicated water meter, one for domestic water and the other for irrigation purposes (if irrigation is used at the facility). Sewer charges are associated with domestic water meter only, and the irrigation meter is strictly for water consumption. The City of Hallandale Beach supplies water to its facilities. Water is purchased from Broward County and treated by the City. The associated sewer is sent to the City of Hollywood for treatment.

The water tariff is a tiered rate and follows the prescribed table below:

WATER CONSUMPTION SUMMARY OF ALL FACILITIES

0-2000 kgal 1.03$ 3.48$ 2001-5000 kgal 1.10$ 3.60$

5001-10,000 kgal 1.43$ 3.75$ 10,001-25,000 kgal 2.25$ 4.16$

>25,000 kgal 2.45$ 4.39$

Charges/Usage Tier Water (per kgal) Sewer (per kgal)

Base Charge 21.00$ 17.00$

Facility Total Water/Sewer Consumption (kgal)

Total Sprinkler Consumption (kgal)

Total Billed Cost (dollars)

Municipal Complex 461 2,480 9,498$ Cultural Center 76 1,387 4,349$ Hepburn Center 133 - 1,132$ DPW Administration 1,327 90 9,627$ Garage 94 - 911$ Warehouse 2 - 463$ Crew Quarters 83 - 856$ Fire Station 60 238 330 5,847$ Fire Station 90 342 - 944$ Golden Isles Tennis Center 371 - 2,726$ Three Islands Guard House 1 110 - 1,083$ Three Islands Guard House 2 42 - 651$ Golden Isles Guard House 136 - 1,110$

Totals: 3,413 4,287 39,198$

Page 107: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 107

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Per the request of the City, 24 months (2 years) of water consumption data were analyzed to form a baseline for the energy savings performance contract project. Two annual periods of water consumption data were averaged together, by month, to form the following baseline tables and charts.

The Municipal Complex has water account number: 846910, Meter Number: 1291179, and falls under the H IC rate structure.

MUNICIPAL COMPLEX WATER CONSUMPTION

The Municipal Complex’s water usage during the provided baseline is primarily for outdoor sprinklers. Siemens was informed that this annual irrigation value is incorrect. The irrigation system was accidentally left on override during the above annual period. It has since been returned to its scheduled operation. The correction has eliminated the potential for irrigation measures. The water usage for domestic purposes is relatively consistent throughout the year, as predicted by the facility’s type and usage profile.

The Cultural Center has water account number: 851290, Meter Number: unknown, and falls under the H IC rate structure.

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Sprinkler Consumption

(kGal)

Water Charges

Sewer Charges

Sprinkler Charges

Total Billed Amount

Aug 38 38 285 100$ 174$ 712$ 986$ Sept 35 35 250 92$ 160$ 625$ 878$ Oct 33 33 251 86$ 150$ 629$ 865$ Nov 38 38 312 99$ 174$ 778$ 1,051$ Dec 29 29 286 78$ 135$ 706$ 918$ Jan 42 42 335 110$ 192$ 827$ 1,128$ Feb 43 43 89 112$ 197$ 230$ 539$ Mar 41 41 109 106$ 185$ 273$ 563$ Apr 42 42 111 108$ 190$ 283$ 581$ May 39 39 83 101$ 176$ 216$ 492$ Jun 41 41 94 107$ 187$ 241$ 535$ Jul 39 39 276 102$ 178$ 682$ 962$

Totals 461 461 2,480 1,201 2,096 6,201$ 9,498$

Page 108: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 108

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

CULTURAL CENTER WATER CONSUMPTION

The Cultural Center’s water usage is primarily for outdoor sprinklers. The water usage for domestic purposes is relatively consistent throughout the year. Water usage for this facility is relatively low compared to other City facilities.

The Hepburn Center has water account number: 834814, Meter Number: unknown, and falls under the H IC rate structure.

HEPBURN CENTER WATER CONSUMPTION

The water usage for domestic purposes is relatively consistent throughout the year. The usage profile of the building does not vary extensively throughout the year.

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Sprinkler Consumption

(kGal)

Water Charges

Sewer Charges

Sprinkler Charges

Total Billed Amount

Aug 5 5 146 26$ 33$ 365$ 424$ Sept 5 5 73 27$ 37$ 193$ 257$ Oct 7 7 43 29$ 41$ 118$ 189$ Nov 5 5 0 27$ 35$ 21$ 82$ Dec 5 5 0 26$ 34$ 21$ 81$ Jan 6 6 34 28$ 39$ 97$ 163$ Feb 7 7 113 30$ 43$ 289$ 362$ Mar 7 7 141 29$ 42$ 351$ 422$ Apr 8 8 225 30$ 45$ 556$ 631$ May 8 8 186 31$ 46$ 462$ 539$ Jun 8 8 240 30$ 45$ 594$ 669$ Jul 6 6 187 28$ 39$ 464$ 531$

Totals 76 76 1,387 340 478 3,531$ 4,349$

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 11 11 37$ 60$ 96$ Sept 11 11 37$ 60$ 96$ Oct 9 9 33$ 51$ 84$ Nov 10 10 34$ 55$ 89$ Dec 8 8 31$ 46$ 76$ Jan 10 10 34$ 55$ 89$ Feb 9 9 33$ 51$ 84$ Mar 11 11 36$ 59$ 95$ Apr 13 13 41$ 67$ 108$ May 12 12 38$ 61$ 99$ Jun 13 13 40$ 66$ 106$ Jul 13 13 41$ 67$ 108$

Totals 133 133 434 697 1,132$

Page 109: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 109

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The DPW Administration Building has water account number: 834364, Meter Number: unknown, and falls under the H IC rate structure.

DPW ADMINISTRATION WATER CONSUMPTION

The water usage for domestic purposes is varies throughout the year. This facility is a high consumer of water compared to other City facilities.

The Crew Quarters has water account number: 834366, Meter Number: unknown, and falls under the H IC rate structure.

CREW QUARTERS WATER CONSUMPTION

The water usage for domestic purposes is fairly consistent throughout the year. This facility’s water is used for shower, lavatory, and water closet usage.

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Sprinkler Consumption

(kGal)

Water Charges

Sewer Charges

Sprinkler Charges

Total Billed Amount

Aug 133 133 7 331$ 588$ 32$ 951$ Sept 124 124 8 310$ 551$ 33$ 894$ Oct 56 56 7 145$ 253$ 31$ 429$ Nov 125 125 9 313$ 557$ 35$ 905$ Dec 74 74 7 187$ 331$ 32$ 550$ Jan 177 177 8 439$ 781$ 33$ 1,253$ Feb 125 125 9 312$ 555$ 35$ 903$ Mar 146 146 9 363$ 646$ 36$ 1,045$ Apr 147 147 7 367$ 653$ 33$ 1,053$ May 116 116 10 290$ 515$ 37$ 843$ Jun 52 52 9 135$ 236$ 36$ 407$ Jul 52 52 1 134$ 236$ 22$ 393$

Totals 1,327 1,327 90 3,327 5,903 397$ 9,627$

Billing Date

Water Conusmption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 7 7 29$ 42$ 72$ Sept 6 6 28$ 40$ 68$ Oct 5 5 27$ 36$ 62$ Nov 7 7 29$ 41$ 69$ Dec 6 6 28$ 38$ 66$ Jan 6 6 27$ 38$ 65$ Feb 12 12 38$ 62$ 100$ Mar 7 7 29$ 43$ 72$ Apr 6 6 28$ 39$ 68$ May 7 7 30$ 44$ 74$ Jun 7 7 29$ 42$ 71$ Jul 6 6 28$ 40$ 68$

Totals 83 83 351$ 505$ 856$

Page 110: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 110

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The Garage has water account number: 834368, Meter Number: unknown, and falls under the H IC rate structure.

GARAGE WATER CONSUMPTION

The water usage for domestic purposes is fairly consistent throughout the year.

The Warehouse has water account number: 834362, Meter Number: unknown, and falls under the H IC rate structure.

WAREHOUSE WATER CONSUMPTION

The water usage for domestic purposes is fairly consistent throughout the year and is extremely low compared to other faculties.

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 9 9 33$ 50$ 83$ Sept 9 9 32$ 50$ 82$ Oct 7 7 29$ 42$ 70$ Nov 8 8 31$ 46$ 77$ Dec 7 7 29$ 41$ 70$ Jan 7 7 30$ 44$ 74$ Feb 8 8 30$ 45$ 75$ Mar 8 8 31$ 47$ 78$ Apr 7 7 29$ 41$ 70$ May 9 9 33$ 51$ 83$ Jun 7 7 30$ 44$ 74$ Jul 8 8 30$ 45$ 75$

Totals 94 94 366$ 546$ 911$

Billing Date

Water Conusmption

(kGal)

Sewer Conusmption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 0.2 0.2 21$ 18$ 39$ Sept 0.1 0.1 21$ 17$ 38$ Oct 0.2 0.2 21$ 18$ 39$ Nov 0.1 0.1 21$ 17$ 38$ Dec 0.1 0.1 21$ 17$ 38$ Jan 0.2 0.2 21$ 18$ 39$ Feb 0.1 0.1 21$ 17$ 38$ Mar 0.1 0.1 21$ 17$ 38$ Apr 0.2 0.2 21$ 18$ 39$ May 0.1 0.1 21$ 17$ 38$ Jun 0.1 0.1 21$ 17$ 38$ Jul 0.2 0.2 21$ 18$ 39$

Totals 2 2 254$ 210$ 463$

Page 111: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 111

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The Tennis Center has water account number: 839090, Meter Number: unknown, and falls under the H IC rate structure.

TENNIS CENTER WATER CONSUMPTION

The domestic water usage is fairly consistent throughout the year and coincides with the Tennis Center’s year round use.

The Three Island Guardhouse 1 has water account number: 839090, Meter Number: unknown, and falls under the H IC rate structure.

THREE ISLAND GUARDHOUSE I WATER CONSUMPTION

The Three Island Guardhouse II has water account number: 847510, Meter Number: unknown, and falls under the H IC rate structure.

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 50 50 128$ 224$ 351$ Sept 48 48 125$ 219$ 343$ Oct 42 42 109$ 191$ 300$ Nov 28 28 75$ 130$ 205$ Dec 15 15 48$ 77$ 125$ Jan 32 32 85$ 147$ 232$ Feb 32 32 85$ 148$ 233$ Mar 33 33 86$ 150$ 237$ Apr 35 35 95$ 161$ 256$ May 15 15 49$ 77$ 126$ Jun 23 23 67$ 111$ 177$ Jul 17 17 53$ 86$ 139$

Totals 371 371 1,004$ 1,721$ 2,726$

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 2 2 23$ 24$ 47$ Sept 3 3 25$ 29$ 54$ Oct 1 1 22$ 20$ 43$ Nov 4 4 26$ 33$ 59$ Dec 7 7 31$ 43$ 75$ Jan 17 17 56$ 88$ 144$ Feb 19 19 59$ 93$ 152$ Mar 21 21 64$ 102$ 165$ Apr 12 12 41$ 62$ 103$ May 5 5 27$ 36$ 63$ Jun 5 5 26$ 33$ 60$ Jul 14 14 47$ 73$ 120$

Totals 110 110 447$ 636$ 1,083$

Page 112: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 112

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

THREE ISLAND GUARDHOUSE II WATER CONSUMPTION

The Layne Guardhouse has water account number: 839100, Meter Number: unknown, and falls under the H IC rate structure.

LAYNE GUARDHOUSE WATER CONSUMPTION

Billing Date

Water Conusmption

(kGal)

Sewer Conusmption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 2 2 23$ 25$ 48$ Sept 4 4 26$ 32$ 58$ Oct 2 2 23$ 24$ 47$ Nov 2 2 23$ 24$ 46$ Dec 2 2 23$ 25$ 48$ Jan 3 3 24$ 28$ 53$ Feb 3 3 24$ 27$ 51$ Mar 5 5 26$ 34$ 60$ Apr 4 4 26$ 33$ 59$ May 4 4 26$ 32$ 58$ Jun 7 7 29$ 41$ 70$ Jul 4 4 25$ 30$ 55$

Totals 42 42 299$ 352$ 651$

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Water Charges

Sewer Charges

Total Billed Amount

Aug 11 11 35$ 57$ 92$ Sept 8 8 33$ 46$ 79$ Oct 9 9 35$ 51$ 86$ Nov 31 31 81$ 140$ 221$ Dec 31 31 81$ 141$ 222$ Jan 13 13 42$ 67$ 109$ Feb 13 13 43$ 68$ 111$ Mar 20 20 57$ 95$ 152$ Apr 23 23 64$ 109$ 172$ May 20 20 58$ 97$ 155$ Jun 21 21 58$ 99$ 156$ Jul 11 11 37$ 59$ 96$

Totals 210 210 625$ 1,028$ 1,653$

Page 113: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 113

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Fire Station 60 has water account number: 838686, Meter Number: unknown, and falls under the H IC rate structure.

FIRE STATION #60 WATER CONSUMPTION

Billing Date

Water Consumption

(kGal)

Sewer Consumption

(kGal)

Sprinkler Conusmption

(kGal)

Water Charges

Sewer Charges

Sprinkler Charges

Total Billed

AmountSept 17 17 14 144$ 200$ 43$ 387$ Oct 19 19 10 150$ 208$ 35$ 393$ Nov 17 17 11 151$ 209$ 35$ 396$ Dec 15 15 13 140$ 193$ 41$ 374$ Jan 18 18 12 160$ 222$ 39$ 422$ Feb 22 22 16 191$ 268$ 48$ 507$ Mar 23 23 27 199$ 279$ 74$ 552$ Apr 23 23 37 197$ 276$ 98$ 571$ May 24 24 50 208$ 291$ 129$ 628$ Jun 20 20 63 177$ 246$ 161$ 584$ July 19 19 41 169$ 235$ 107$ 511$ Aug 21 21 34 180$ 252$ 92$ 524$

Totals 238 238 330 2,067$ 2,879$ 902$ 5,847$

Page 114: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 114

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

F. Schedule F - Savings Measurement and Calculation Formulae; Methodology to Adjust Baseline

F.1. Lighting Calculations KW Savings = Pre KW Measurement – Post KW Measurement

Annual KWH Savings = Pre Lighting Burn Hours x Pre KW Measurement – Post Lighting Burn Hours x Post KW Measurement

Annual KW Demand Savings = KW savings x demand months

Annual Dollar Savings ($) = KWH Savings x $/KWH Rate + kW demand savings x $/kW rate

F.2. Occupancy Sensors Calculations Annual Occupancy Sensor Savings (KWH) = Burn Hours Saving x Post KW

Annual Dollar Savings ($) = Occupancy Sensor KWH savings x KWH Rate

F.3. Water Conservation Calculations Annual Water Savings (Gallons):

Toilets and Urinals = (Pre Gallons per Flush – Post Gallons per Flush) x Frequency per Occupant x Number of Occupants x Days per Year

Sinks / Shower Heads = (Pre Flow Rate GPM – Post Flow Rate GPM) x Avg. Time of Use x Frequency per Occupant x Number of Occupants x Days per Year

Dish Sink = (Pre Flow Rate GPM – Post Flow Rate GPM) x Avg. Time of Use per Day x Days per Year

Annual Heating Saving (MMBTU) = Gallons per Year x (Hot Water Temperature – City/Well Water Temperature) x 8.346 lbs/gal / Heater Efficiency / 1,000,000

Annual Dollar Saving ($) = (Gallons Saved) x (Water Rate $/gal + Sewer Rate $/ gal) + MMBTU Savings x (1/MMBTU/Unit of Fuel) x $/ Unit of Fuel

F.4. Plug Load Management Calculations Using logging data, average the wattage draw of each device during the scheduled “off” periods of each facility.

KWH Savings = Pre KWH Measurement – Post KWH Measurement

Page 115: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 115

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

F.5. Chiller Replacement Calculations Trended data will be taken for a period of 30 days, every year of the Performance guarantee, during the summer and winter seasons.

Chiller Load (Tonnage) = (Supply Temp – Return Temp) x Chiller Loop GPM x 8.346 lbs/gallon x 60 / 12,000

Chiller kW = Trended current x measured voltage x 0.9 assumed power factor / 1000

Outdoor Air Temperature = trended using data logger or building automation system

Using calculated kW/ton and measured outdoor air temperature, a comparison of pre and post chiller load efficiency at these values will be made. For example, if the post measurement data results in 95F outdoor air temperature and, based on tonnage, the chiller is 80% loaded, the calculated post kW/ton will be compared to the pre modeled kW/ton efficiency under those same conditions.

Bin weather data will be used to obtain operating hours during the year. For example, if the measured outdoor air temperature is 95F, Bin weather data will be used to obtain the total hours in a year that the outdoor air temperature is 95F.

The bin weather hours will be used to determine kWh savings.

Annual Chiller Savings (kWh) = (kW/Ton Pre – kW/Ton Post) x Bin Weather hours based on measured outdoor air temperature.

Annual Chiller Savings (kW) = (kW/Ton Pre – kW/Ton Post) x calculated cooling capacity (tons) x 12 months

Annual Dollar Savings ($) = KWH Savings x KWH Rate + KW Savings + KW Rate

F.6. Cultural Center RTU Replacement Calculations The following saving calculations will be executed for one of each unit type of RTU replaced. The trending session will be conducted for 14 days every year to determine the annual energy savings.

Unit Energy Savings:

Annual Savings (KWH) = Baseline hours x (Pre Unit KW – Post Unit KW)

Annual Saving KW = (Pre Unit KW – Post Unit KW) x 12 months

Annual Dollar Savings ($) = KWH Savings x KWH Rate + KW Savings + KW Rate

F.7. DPW Administration Calculations Savings generated by scheduling the HVAC equipment serving the Administration building shall be based on the new equipment’s operating hours. Both units will be trended in order to verify and validate the guaranteed reduction in hours of operation.

Unit Energy Savings:

Page 116: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 116

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Annual Savings (KWH) = (Trended Baseline Operating Hours x Pre Unit KW) – (Trended Operating Hours x Post Unit KW)

Annual Dollar Savings ($) = KWH Savings x KWH Rate

F.8. Others Option E (Stipulation) has been selected to verify Savings for the following FIMs. No additional measurement s and savings calculations will be taken.

• Commissioners Chambers VAV Replacements and Return Air Flow Improvements

• Twist Dial Timers

• Mechanical Insulation

• Domestic Hot Water Savings from Water Conservation

F.9. Methodology to Adjust Baseline Baseline development is critical to the success of an Energy Performance Contract. Therefore, Siemens Industry performs the upfront analysis and measurements required to adequately and appropriately define the existing operation of the affected systems.

Siemens first establishes baseline energy use for a facility by analyzing historical utility bills, developing system level energy models, performing an energy balance of the major energy systems and reconciling the energy balance with actual utility bill usage data. Typically, Siemens prefers using system level energy baseline models in addition to building level utility bill models, which are heavily influenced by variations in building usage, occupancy, weather, equipment changes and installed plug loads (computers, etc.). Operating characteristics are more easily measured and variations can be isolated with system level models. The baseline models are developed using in-house and third party software programs such as Trane Trace and DOE-2. Industry accepted energy calculation methodologies, such as those developed by ASHRAE, are used in all models.

Siemens typically uses the MetrixTM software application by SRC Technologies for these whole building baseline models. MetrixTM utilizes linear regression analysis methods and allows for modeling of baseline adjustments due to material facility changes. The “Metrix” software uses the following calculations in its regression analysis:

Page 117: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 117

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

BL = B x (Ti - Ti-1) + CH x HDDBH,I + Cc x CDDBC,I + C1 x U1,I + C2 x U2,I + C3 x U3,i

where:

BL = Baseline (Utility Units)

B = Baseload consumption per unit time (Utility Units/day)

Ti - Ti-1 = time interval between date Ti and Ti-1 (days)

CH, CC = Coefficients for Heating and Cooling Degree-days (Utility units/ deg-day)

HDDBH,I = Time history of Heating degree-days °F-day or °C-day)

CDDBC,I = Time history of Cooling degree-days (°F-day or °C-day)

BH, BC = Heating and Cooling degree-day base temperatures (°F-day or °C-day)

C1, C2, C3 = Coefficients for user variables 1,2,3 (e.g. occupancy/schedule, space utilization, added load)

U1,I, U2,I, U3,I = Coefficients for user variables 1,2,3

The baseline for each month of the annual savings period for each energy type for kW demand adjustments will be calculated as follows:

DBl = B + CH x HDDBH,I + Cc x CDDBC,I + C1 x U1,I + C2 x U2,I + C3 x U3,i

where:

B = Baseload consumption per unit time (Utility Units/day)

Ti - Ti-1 = time interval between date Ti and Ti-1 (days)

CH, CC = Coefficients for Heating and Cooling Degree-days (Utility units/ deg-day)

HDDBH,I = Time history of Heating degree-days (°F-day or °C-day)

CDDBC,I = Time history of Cooling degree-days (°F-day or °C-day)

BH, BC = Heating and Cooling degree-day base temperatures (°F-day or °C-day)

C1, C2, C3 = Coefficients for user variables 1,2,3 (occupancy/schedule, space utilization, added load)

U1,I, U2,I, U3,I = Coefficients for user variables 1,2,3

Page 118: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 118

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Monthly energy savings will be calculated as follows:

ES = BL - AU and DS = DBl - Dp

where:

ES = monthly unit energy savings

BL = Baseline

AU = post retrofit monthly energy usage

DBl = adjusted demand

DS = kW demand savings

Dp = post retrofit kW demand usage

The energy costs avoided will be calculated as follows:

CS = ((DS x dr) - Adc) + (( ES x uc) - Aec) + Os

where:

CS = Monetary savings

ur = The greater of the floor price of demand and the current costs

uc = The greater of the floor price of energy and the current costs.

For energy sources concerning utility rate structures, the cost decreases with increasing usage. This cost refers to the marginal unit cost from a month's utility bill. For electricity, this marginal cost shall be determined for energy (starting with the amount paid for the last kilowatt-hour purchased including fuel adjustment cost) and demand (amount paid for the last kilowatt purchased) including, if applicable, the effect of demand on the energy cost.

In order to gather data for the baseline calculations, our engineers will perform a site audit. The specific tasks conducted during the preliminary building audits which directly involve baseline model development include the following:

• In-depth site investigations on a room-by-room, system-by-system basis

• Observation of building and equipment conditions

• Observation of system performance during both occupied and unoccupied periods.

• Review of available drawings

• Analysis of historical electric, natural gas and water bills

Page 119: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 119

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Review of control system design and operation

• Interviews with building operators and users.

• Collection of field data including equipment specifications, control set points, etc.

• Field measurements, as necessary, to determine or confirm system operation

• Calculation of individual system baseline energy usage with computerized ASHRAE bin data models

• Consolidation of system level energy models into overall building energy balance

• Analysis of actual utility bill usage data and applicable rate structures

• Reconciliation of system models and energy balance with actual utility bill usage data

The baseline utility usage and energy balances are used to substantiate the parameters defined in the baseline system models, such as power draws, fuel rates, efficiencies, space conditions, control sequences, set-points, loads, operating hours, etc. Savings projections are developed by evaluating “before” and “after” system models based on the recommended changes to system operation.

Siemens may perform a series of ‘pre-measurements’ using either temporary metering or spot measurement as described below.

F.10. Temporary Metering Temporary metering involves the installation of metering equipment such as:

• Light loggers to verify operating hours, lumens in a given space and, in many cases, occupancy

• Data loggers (measuring amperage), BAS trends, BAS schedules and/or time clock settings to verify or operating hours and peak electric demand contributions of equipment.

These extended measurements provide the basis for predicting the energy usage and loads associated with various pieces of equipment. This approach also provides an indication of the influence of factors such as weather and operating schedules that impact the operation of the equipment. For example, the following calculations indicate the energy usage of the chilled-water systems from the measurements performed:

[ ] [ ] [ ]24

FTgpmFlowTonLoad °∆×=

Page 120: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 120

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

[ ] [ ] [ ]( )∑=

∆×=−n

ii hrtTonLoadhrsTonLoad

1

[ ][ ] [ ]

×××

=

kWW

kVAkWrPowerFactoAAmperageVVoltage

kWPower1000

φ

[ ] [ ] [ ]( )∑=

∆×=n

ii hrtkWPowerkWhEnergy

1

Both the loads and energy of the chiller system can be graphed as a function of outside air temperature for occupied and unoccupied periods. Then a linear correlation of the loads’ outside air temperature and energy usage and outside air temperature produces a method to predict the loads and energy in the future.

F.11. Spot Metering Spot metering is used when there is little variation in equipment operation over known or conservative operating hours. For example, in conjunction with the temporary metering using light loggers or BAS trends/schedules, the energy draw of a constant speed motor does not vary significantly while it is on. A one-time measurement of the motor power draw provides indication of the motor draw for all operating hours. This is also performed on lighting circuits (usually a minimum of 10%). The Voltage, Amperage, and Kilowatts for each are measured and noted. These measurements are typically witnessed and approved by the customer.

The measurement of operating hours is then multiplied by the spot measurements to define the baseline energy usage.

[ ] [ ] [ ]hrursNumberOfHokWPowerkWhEnergy ×=

F.12. Adjustments to Baseline and Guaranteed Levels of Savings

During the guarantee period, there may be changes in a facility's usage and/or operation for which a calculated adjustment to the baseline is necessary.

The energy baseline or actual energy performance can be adjusted for any of the following:

• Local weather conditions

• Occupancy level changes, hours of operation

Page 121: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 121

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Structural modifications, modifications to energy consuming equipment

• Damaged or malfunctioning equipment

• Any variances from the proposed operating schedules, strategies and conditions upon which the calculated savings are based on, and described in the "Contracted Baseline" that could affect energy usage

Prior to installation of new equipment, adjustments to the baseline demand may be required for non-operating components that are normally operating or intended for operation. In addition, after each installation, adjustments to baseline demand may be required because of factors such as remodeling or changes in occupancy. The Customer can recommend a suitable method for making adjustments to the baseline, if necessary. Alternately, Siemens will base the adjustments on engineering calculations that adequately describe the increased/decreased requirements.

The annual reports will document changes in conditions that may affect savings persistence. When using regression analysis, the greater of the baseline loads (and therefore, the energy usage) or the post-installation loads plus the calculated interactive effects of related measures will account for changes in facility operation or occupancy. The higher of the current or baseline utility costs will be used to determine the dollar savings associated with the measure on an annual basis.

Page 122: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA - Volume-1 | 122

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

G. Schedule G – Construction and Installation Schedule

Page 123: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry IGA – Volume- 1 | 123

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

H. Schedule H - Systems Start-Up and Commissioning; Operating Parameters of Installed Equipment

H.1. System Start-up and Commissioning

As the Performance Contractor for the City of Hallandale project, Siemens Industry, Inc. (Siemens) is committed to making sure all Facilities Improvement Measures (FIM) proposed to the City of Hallandale will function as designed and reduce energy costs. In order to insure that each FIM is properly installed and functioning as designed, Siemens will commission and verify the quality and functionality of each FIM.

DEFINITION AND OBJECTIVE OF THE COMMISSIONING PROCESS:

The main objective of commissioning is to affect the safe and orderly handover of systems from the Contractor to the Owner, guaranteeing its operability in terms of performance, reliability, safety and traceability. Additionally, when executed in a planned and effective way, commissioning normally represents an essential factor for the fulfillment of schedule, costs, safety and quality of the project.

Many of the project facility improvement measures (FIMs) are relatively simple in nature and do not require extensive commissioning work, while other project FIMs require a more extensive commission process. The procedures/steps for both scenarios are covered on the following pages.

It is important to note that often in a performance contract only a portion of a system is replaced or upgraded. For example, if a facility has an existing energy management system (EMS) and the Performance Contractor intends to expand the EMS as part of a project, only the expanded portion of the EMS is relevant in the commissioning procedures for an EMS.

Accordingly, the FIMs that are being proposed to the City of Hallandale by Siemens Industry, Inc. are as follows:

• Interior lighting

• Water conservation

• Mechanical Insulation

• Chiller replacement

• RTU replacement

• VAV box replacements (2)

Page 124: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 124

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

• Mechanical timers

• Programmable Thermostats

• EMS system upgrade

COMMISSIONING: INTERIOR LIGHTING FIM:

1. Review existing lighting detailed in descriptions from the energy audit reports from Siemens' lighting subcontractor.

2. Review the actual existing lighting installation at each facility and compare to the existing lighting count performed by the lighting subcontractor at each facility.

3. Compare Items 1 & 2 and note any discrepancies.

4. Measure the existing KW and KWH for all lighting at each respective facility at the electrical panels serving the existing lighting fixtures using calibrated KW & KWH recording meter(s).

5. Review proposed high efficiency lighting product proposals from the lighting subcontractor and examine the quantity and KW usage compared to the existing lighting fixtures.

6. Quantify the actual existing and installed lighting and compare both in a spreadsheet and report. Describe any discrepancies between the existing and the new lighting installations.

COMMISSIONING: MECHANICAL INSULATION:

1. Review existing insulation including the quantity, type, thickness, and R-values in each facility as shown by Siemens in the Energy Audit Report.

2. Field check the existing insulation noted in Item 1 and note any discrepancies.

3. Review proposed replacement insulation products, including quantity, type, thickness and R-values.

4. Field check installed insulation product for each facility and compare to the insulation that was replaced or insulating that was missing.

5. Compare items 1, 2, 3 & 4 above and note any discrepancies.

6. Examine the quality of the insulating work and note any insulation work of poor quality.

COMMISSIONING: PROGRAMMABLE THERMOSTATS:

1. Compare existing thermostats to the descriptions contained in the energy audit report.

Page 125: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 125

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

2. Review existing thermostat installations at each facility and compare to the existing thermostat count contained in the audit report.

3. Compare Items 1 & 2 and note any discrepancies.

4. Field-check the installations and compare to the number of new thermostats depicted in the energy audit. Note any discrepancies.

5. Examine the programming of each new thermostat (hours of operation) and submit schedules to the owner for approval/confirmation.

6. Test the operation of the thermostats by adding logging devices at the breakers of the controlled equipment; monitor for two weeks. Note any discrepancies.

7. Place a temperature and humidity recording device in each building and record for two weeks. Examine the trend log data and note if temperature or humidity levels are too high during equipment off times.

8. If temperature or humidity levels rise to levels above acceptable tolerance, reprogrammed thermostats for shorter off hours or duty cycling, as necessary.

COMMISSIONING: MECHANICAL TIMERS:

1. Review specifications of timers to be installed.

2. Field-check the installation of the timers and compare to the number of timers specified in the Energy Audit. Note any discrepancies.

3. Examine the settings of each timer.

4. Test the operation of the new timers using logging devices at the breakers for a period of two weeks. Ensure that thermostats are functioning as set. Note any discrepancies.

COMMISSIONING: VAV BOX REPLACEMENT (2):

1. Review energy audit data on the VAV boxes to be replaced.

2. Determine the maximum air flow required by each new VAV box from the engineering drawings. Check VAV box specifications to ensure that the specified VAV boxes will deliver the designed flow rate.

3. Have T&B contractor balance each new VAV box to the designed flow rates and submit T&B report.

4. Check the thermostat feeding each new VAV box to ensure the thermostat is in good condition and able to control the VAV boxes.

5. If VAV boxes are intended to also heat the zone, ensure the VAV box has a heating strip attached.

6. Test each VAV box for cooling by setting the temperature to 70 degrees and check that the temperature, or similar, is achieved.

Page 126: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 126

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

7. Check the VAV box minimum setting, say 30 percent open.

8. After a low temperature setting, described in Item 6, has been achieved switch to the heating mode to ensure the strip heater turns on and warm air is provided. Make sure the VAV box is in the minimum position during heating. (This assumes that the respective VAV box was designed for heating in addition to cooling). Note any discrepancies in the above items.

9. Summarize the above findings in a report.

COMMISSIONING: WATER CONSERVATION:

1. Review energy audit report and identify existing water fixtures to be replaced and new water-conserving devices to be installed. Review specifications of proposed water-conserving devices.

2. Review existing water fixtures at each facility and compare to the fixture count described in the energy audit. Note any discrepancies.

3. Field-check the installation of the new water fixtures and compare to the number of new water fixtures depicted in the energy audit. Note any discrepancies.

4. Submit fixture specifications to the Owner for approval.

5. Use the following steps to test for the performance of the water-saving fixtures (select a random sample of fixtures, such as one in twenty):

• For spigots measure flow into a bucket for 20 seconds

• For urinals measure discharge per flush

• For wall mounted toilets measure discharge per flush

6. Review water billing for each facility for two months and examine any change in billing. Report findings.

7. Summarize the above findings in a report to the Contractor and Owner.

COMMISSIONING: EMS SYSTEM UPGRADES:

1. Based on the FIM description in the energy audit, a team meeting will be held between the Owner, Siemens, the Controls Subcontractor, the Design Engineer, and the Commissioning Agent (CxA). The CxA will explain the purpose and steps of the commissioning process. The CxA will be involved throughout the entire process to include the final turnover of the new system and performance after start-up. ASHRAE Guidelines will be used throughout the commissioning process.

2. The Controls Subcontractor will generate all necessary pre-design control upgrade drawings for review by the team members, including the CxA. All team members will review these documents and respond with any necessary change requests.

Page 127: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 127

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

3. The Controls Subcontractor will present 95 percent design documents to all team members for their review and all team members will respond with the final set of comments.

4. If any changes are required in Item 3 above, the Controls Subcontractor will re-issue a final set of control drawings and apply for construction permits, as required.

5. The Controls Subcontractor will commence construction and will hold periodic reviews with the appropriate team members. All necessary shop drawings, submittals and calibration procedures shall be provided by the Controls Subcontractor.

6. After construction is complete, all team members will conduct a thorough review of the construction noting any discrepancies.

7. If required, discrepancies will be corrected and inspected by the CxA. The Startup Phase will start with a team meeting to discuss the start up procedures and testing. The first start up and testing sequence will occur after hours to test for performance compared to the design documents. The Controls Subcontractor will be primarily responsible for this testing.

8. The system will be testing during occupied hours with the CxA and the Controls Subcontractor in attendance; the CxA will verify the system operation meets all design requirements and functions per the manufacturer's standards.

9. Following successful start up and commissioning, the CxA will conduct periodic inspections of system performance for a period of six month. These inspections can be done either in person or by remote access to the EMS. The CxA will note any discrepancies to all parties and the Controls Subcontractor will make the necessary changes and present documentation that the corrections were made.

10. Final documents, including maintenance manuals, as-built drawings, controls documentation and all related turn-over documents, will be reviewed and approved by the CxA and the Engineer prior to turnover to the Owner.

11. All training will be accomplished by the Controls Subcontractor to the satisfaction of all parties, including the CxA. Training will be in compliance with the training section of this document.

HIGH EFFICIENCY AIR-COOLED CHILLER INSTALLATION

1. A team meeting will be held with the Owner, Siemens, the Mechanical Subcontractor, the Test and Balance Contractor (T&B), the Design Engineer, and the Commissioning Agent (CxA). The CxA will explain the ASHRAE Guidelines for the commissioning process, and the purpose and steps of system commissioning. The CxA will remain involved throughout the installation process, including the project turnover, and follow-up inspections to ascertain system performance.

Page 128: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 128

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

2. The team will review the schematic design drawings noting any anomalies before final design is completed.

3. The Engineer will present 95 percent design documents to the team members for their review and comment. The Mechanical Subcontractor will issue the final set of signed drawings to Siemens.

4. Once the permits are obtained, the team will meet to discuss the installation schedule. All necessary shop drawings, submittals and calibration procedures shall be provided by the Mechanical Subcontractor to the Engineer and the CxA for approval.

5. Following installation the team will conduct a thorough review of the installation noting and resolving any discrepancies, if applicable.

6. A team meeting will be held to discuss the started up and testing procedures. The first start up and test will be conducted after hours. The Mechanical Subcontractor and the Test and Balance Contractor will be primarily responsible for testing the new chiller.

7. A follow on test will be conducted during occupied hours with the Engineer, the CxA and the Mechanical Subcontractor in attendance. The CxA will verify that the operation of the new high efficiency air-cooled chiller meets all design requirements and functions per the design and manufacturer's requirements. Any discrepancy will be noted and remedied by the Mechanical Subcontractor.

8. The CxA will make periodic performance inspections over the next six months following the successful startup; inspections will be either in person or by remote access via the EMS. The CxA will note any discrepancies and the Mechanical Subcontractor will resolve any issues and document that the corrections were completed.

9. All documents including maintenance manuals, as-built drawings, controls documentation and any related turn-over documentation will be reviewed and approved by the CxA and the Engineer prior to turnover to the Owner.

10. Training will be accomplished in accordance to the training requirements discussed in the Training section of this document.

NEW HIGH EFFICIENCY ROOFTOP AIR-CONDITIONING UNITS INSTALLATION

1. A team meeting will be held with the Owner, Siemens, the Mechanical Subcontractor, the Test and Balance Contractor (T&B), the Design Engineer, and the Commissioning Agent (CxA). The CxA will explain the ASHRAE Guidelines for the commissioning process, and the purpose and steps of system commissioning. The CxA will remain involved throughout the installation process, including the project turnover, and follow-up inspections to ascertain system performance.

2. The team will review the schematic design drawings noting any anomalies before final design is completed.

Page 129: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 129

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

3. The Engineer will present 95 percent design documents to the team members for their review and comment. The Mechanical Subcontractor will issue the final set of signed drawings to Siemens.

4. Once the permits are obtained, the team will meet to discuss the installation schedule. All necessary shop drawings, submittals and calibration procedures shall be provided by the Mechanical Subcontractor to the Engineer and the CxA for approval.

5. Following installation the team will conduct a thorough review of the installation noting and resolving any discrepancies, if applicable.

6. A team meeting will be held to discuss the started up and testing procedures. The first start up and test will be conducted after hours. The Mechanical Subcontractor and the Test and Balance Contractor will be primarily responsible for testing the new system.

7. A follow on test will be conducted during occupied hours with the Engineer, the CxA and the Mechanical Subcontractor in attendance. The CxA will verify that the operation of the new high efficiency RTU meets all design requirements and functions per the design and manufacturer's requirements. Any discrepancy will be noted and remedied by the Mechanical Subcontractor.

8. The CxA will make periodic performance inspections over the next six months following the successful startup; inspections will be either in person or by remote access via the EMS. The CxA will note any discrepancies and the Mechanical Subcontractor will resolve any issues and document that the corrections were completed.

9. All final documents including maintenance manuals, as built drawings, controls documentation and all related turn-over documents will be reviewed and approved by the CxA and the Engineer prior to turnover to the Owner. Also, all training will be accomplished by the Mechanical Subcontractor to the satisfaction of all parties, including the Engineer and the CxA.

H.2. Operating Parameters of Installed Equipment The following tables detail the Facility operating parameters that are required to be implemented on the Guarantee Date or on such time as agreed upon by the Parties. This specific configuration of Facility operating parameters is the Contracted Baseline and failure of the CLIENT to maintain the Contracted Baseline may result in a Material Change which may require a modification of the Performance Guarantee pursuant to the Agreement.

Page 130: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 130

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

NEW DPW ADMINISTRATION HVAC OPERATING HOURS

Day of Week Occupied

Hours (Equipment ON)

Unoccupied

Hours (Equipment OFF)

Monday 6:00 AM – 6:00 PM 6:00 PM – 6:00 AM

Tuesday 6:00 AM – 6:00 PM 6:00 PM – 6:00 AM

Wednesday 6:00 AM – 6:00 PM 6:00 PM – 6:00 AM

Thursday 6:00 AM – 6:00 PM 6:00 PM – 6:00 AM

Friday 6:00 AM – 6:00 PM 6:00 PM – 12:00 AM

Saturday 12:00 AM – 12:00 AM

Sunday 12:00 AM – 12:00 AM

Holiday 12:00 AM – 12:00 AM

MUNICIPAL COMPLEX PLUG LOAD OPERATING HOURS

Day of Week Occupied

Hours (Equipment ON)

Unoccupied

Hours (Equipment OFF)

Monday 7AM to 6PM 6PM to 7AM

Tuesday 7AM to 6PM 6PM to 7AM

Wednesday 7AM to 6PM 6PM to 7AM

Thursday 7AM to 6PM 6PM to 7AM

Friday 7AM to 6PM 6PM to 12AM

Saturday 12AM to 12AM

Sunday 12AM to 12AM

Holiday 12AM to 12AM

HEPBURN CENTER PLUG LOAD OPERATING HOURS

Day of Week Occupied Unoccupied

Page 131: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 131

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Hours (Equipment ON) Hours (Equipment OFF)

Monday 7AM to 9PM 9PM to 7AM

Tuesday 7AM to 9PM 9PM to 7AM

Wednesday 7AM to 9PM 9PM to 7AM

Thursday 7AM to 9PM 9PM to 7AM

Friday 7AM to 9PM 9PM to 12AM

Saturday 12AM to 12AM

Sunday 12AM to 12AM

Holiday 12AM to 12AM

NEW DPW ADMINISTRATION PLUG LOAD OPERATING HOURS

Day of Week Occupied

Hours (Equipment ON)

Unoccupied

Hours (Equipment OFF)

Monday 6AM to 6PM 6PM to 6AM

Tuesday 6AM to 6PM 6PM to 6AM

Wednesday 6AM to 6PM 6PM to 6AM

Thursday 6AM to 6PM 6PM to 6AM

Friday 6AM to 6PM 6PM to 12AM

Saturday 12AM to 12AM

Sunday 12AM to 12AM

Holiday 12AM to 12AM

Page 132: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 132

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

I. Schedule I - Standards of Comfort

I.1. TEMPERATURE Summer Design Parameters

• Indoor Design = 75 Degree F (dry bulb) and 50% RH

Winter Design Parameters

• Indoor Design = 68 Degree F (dry bulb) and 50% RH

I.2. NOISE Noise levels due to air conditioning unit fan, ventilating equipment, ducts, grilles, diffusers and air system pressure reducing devices shall conform to the RC Noise Rating Procedure outlined in the latest edition of the ASHRAE HVAC Applications Handbook. Classrooms and all spaces, other than those listed below shall be designed for maximum noise criteria level of RC-30 (N). The exceptions shall be:

Corridor, Lobbies RC-40

Chiller Rooms RC-60 (N)

Storage, Toilets, Custodial RC-45 (N)

Mechanical Rooms RC-45 (N)

Kitchens RC-40 (N)

I.3. LIGHTING AREA AVERAGE MULTIPLE LEVELS

Classroom 60-Foot Candle

Auditoriums 30-70 Foot Candle

Media Center 70-Foot Candle

Clerical 50-60 Foot Candle

Interior Corridors 30-Foot Candle

Computer Labs 30-50 Foot Candle

Page 133: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 133

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

J. Schedule J - ESCO's Maintenance Responsibilities

City has elected to self-implement maintenance of the FIMs. Therefore Company shall not perform any on-going maintenance services, although the parties may negotiate a separate agreement for such services at a later date. City agrees that it will maintain the equipment per manufacturer specifications and that it will operate the Equipment in accordance with the Contract Documents.

Page 134: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 134

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

K. Schedule K - Agency's Maintenance Responsibilities

CITY acknowledges that it has an integral role in the success of the Guarantee and agrees to the supplemental responsibilities set forth below:

K.1. Lighting The City shall replace lamps and ballasts per manufacturer specifications

The City shall replace burned out lamps from stock.

The City shall replace fuses in fixtures as required.

The City shall replace ballasts as needed from stock.

The City shall replace failed out-of-warranty LED exit sign kits.

The City shall replace out-of-warranty or failed occupancy sensors as required.

The City shall maintain utilization of installed occupancy sensors.

K.2. Water Conservation The City shall maintain plumbing and fixtures per manufacturer specifications.

K.3. Plug Load Management SIEMENS will program the operating schedule each of device with the City.

The City is to update and maintain each device’s operating schedule as needed. Wireless network issues that result in communication losses to the BERT devices are to be address by the City’s IT Department. BERT devices are will store programmed schedules for 24 hours in case of such an occurrence.

K.4. Cultural Center Rate Change The City is to provide SIEMENS access to online utility billing, the electric bill corresponding to this new combined service meter for a period of no less than 12 months after completion of the FIM.

Page 135: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 135

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

K.5. Municipal Complex Chiller Plant On a quarterly basis the City shall maintain and service the chiller plant components including:

• Chilled water pumps

• Condenser water pumps

• Isolation valves

• Piping

• New chiller Installed by Siemens

The City shall provide SIEMENS with semiannual access to the Trane Tracer trending data necessary to perform the above calculations.

The City shall contact Siemens Building Technologies for service issues regarding: New chiller installed by Siemens Building Technologies

K.6. Cultural Center RTU Replacements The City shall performed manufacture recommended on-going scheduled maintenance of new package equipment.

K.7. DPW Administration Programmable Thermostats The City shall maintain programmed schedule of operating hours for equipment.

The City shall perform standard on-going manufacturer recommended maintenance necessary to maintain control system.

K.8. Commissioners Chambers VAV Replacements and Return Air Flow Improvements

The City shall perform standard on-going manufacturer recommended scheduled maintenance necessary to maintain control system.

The VAV boxes serving the Commissioners Chamber will be monitored and controlled by the City to operate as needed, based on scheduled meetings and/or events held within the space. The City is aware that energy savings cannot be met if VAV boxes are allowed to provide continuous cooling and are not scheduled to close dampers to a minimum position one hour after meetings and events have concluded.

Page 136: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 136

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

K.9. Twist Dial Timers The City shall perform standard on-going manufacturer recommended maintenance necessary to maintain control system

K.10. Mechanical Insulation The City shall perform standard on-going manufacturer recommended maintenance necessary to maintain equipment insulation.

K.11. Commercial Meters The periodic testing of commercial (meter sizes of 1.5 inches and larger) should be in support of the American Water Works Association (AWWA) Standard C702-10, Appendix A.6:

(1-1/2” can be treated the same as 2” meters)

The above AWWA guidelines are recommended testing frequency; the Utility Department should develop testing schedules that best suit the City’s requirements and usage patterns. For example, meters with abnormally high or low usage can be tested at shorter or longer interval periods, respectively.

Page 137: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 137

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

L. Schedule L - Facility Maintenance Checklist

Inspector: _________________________ Date: _____________________

Yes No Comments/Actions

Lighting Retrofit

Lights in working order

Light covers are not cracked or missing

Light fixtures rusted or damaged

Water Conservation

Is sink fixture in working order

Is shower head flowing freely

Do toilets flush contents successfully

Is toilet/urinal caulking in tact

Is toilet/urinal cracked or otherwise damaged

Mechanical Insulation

Are intended covered surfaces properly covered

Is insulation wet or matted

Is insulation damaged

Plug Load

Does plug load device respond to control signal

Is plug load device damaged or missing

Municipal Complex Chiller Replacement

(Please see checklist included in chiller documentation)

Chilled Water RTU Replacement

(Please see checklist included in chiller documentation)

Cultural Center RTU Replacement

(Please see checklist included in chiller documentation)

Programmable Thermostats

Is measured temperature accurate

Do all of modes of operation work as expected

Mechanical Timers

Does timer function as expected

Is timer damaged or missing

Page 138: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 138

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

M. Schedule M - ESCO's Training Responsibilities

M.1. Plug Load Management SIEMENS will provide training to the City on the usage of the BertBrain plug device programming software. Training will include how to program schedules into each device, how to track and trend energy usage, and how to development trending tables using the proprietary software. Up to 4 hours of initial training will be provided, but additional training will also be provided should staff change and refresher training be required.

M.2. Building Automation System (BAS) Upgrade Siemens, or the subcontractor, will provide on-site EMS training for the operations and maintenance personnel. Training is not to exceed 16 hours, delivered in up to 4 sessions on-site. Additional operator coaching is provided through any service component of this agreement through the on-site specialist.

M.3. Chiller & RTU Siemens, or the subcontractor, will provide on-site training on the mechanical start-up and basic functions of the chiller and RTU operations, parameter readings, etc. This training will last up to 4 hours and conducted on-site.

M.4. Advanced Meter Infrastructure (AMI) Siemens, or the subcontractor, will provide on-site FlexNet AMI training. This training will be to familiarize the utility personnel with the operation of the Logic Meter Data Management (head end) software. The following two pages contain the specific course description for the full 1-day training session.

Page 139: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 139

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 140: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 140

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 141: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 141

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

In addition to the factory-led training shown above, HD Supply will provide the following training:

1. Set up and use of the FieldLogic handheld and programming software. This is typically performed in the field with live equipment and focuses on best practices in both installation and troubleshooting of the meters and AMI equipment. The training is 1 day, however HD Supply will make itself available for refresher courses and new employee training during the first year following installation.

2. Supplemental training and support related to the operation of the Logic MDM software. HD Supply will be available for continued support; this supplemental training can range from phones conferences, WebEx meetings, and all day on-site visits, depending on the specific situation warrants.

Page 142: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 142

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

N. Schedule N - Installment Payment Schedule

Timely Payments: The CITY agrees to pay COMPANY progress payments based on percentage of work completed. CITY agrees to pay all invoices submitted by COMPANY per Section 5 of the Agreement. Below is an estimated payment schedule.

Percent Payment

Payment Amount

Contract Signing 5% $288,560

Month 1 5% $288,560

Month 2 5% $288,560

Month 3 10% $577,121

Month 4 10% $577,121

Month 5 10% $577,121

Month 6 10% $577,121

Month 7 15% $865,681

Month 8 10% $577,121

Month 9 5% $288,560

Month 10 5% $288,560

Month 11 5% $288,560

Month 12 5% $288,560

100% $5,771,207

Page 143: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 143

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

O. Schedule O - Final Project Cost & Final Project Cash Flow Analysis

Please see the following pages for our project estimates and projections numbers.

Page 144: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 144

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Cashflow – Escalating Payments

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total

PROGRAM SAVINGSEnergy Savings 55,693$ 57,364$ 59,085$ 60,857$ 62,683$ 64,563$ 66,500$ 68,495$ 70,550$ 72,667$ 74,847$ 77,092$ 79,405$ 81,787$ 84,241$ 1,035,829$

Operational Savings 345,839$ 382,049$ 420,121$ 460,134$ 502,169$ 517,234$ 532,751$ 554,608$ 577,297$ 600,849$ 625,293$ 650,664$ 676,994$ 704,319$ 732,673$ 8,282,995$ Construction Savings 4,561$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 4,561$

Annual Gross Savings 406,093$ 439,413$ 479,206$ 520,991$ 564,852$ 581,797$ 599,251$ 623,103$ 647,847$ 673,515$ 700,140$ 727,756$ 756,399$ 786,106$ 816,914$ 9,323,385$ Cumulative Savings 406,093$ 845,506$ 1,324,712$ 1,845,703$ 2,410,555$ 2,992,352$ 3,591,604$ 4,214,707$ 4,862,555$ 5,536,070$ 6,236,210$ 6,963,966$ 7,720,365$ 8,506,471$ 9,323,385$

Annual Contribution 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 250,000$

PROGRAM COSTSPrincipal & Interest 327,157$ 366,235$ 405,442$ 446,622$ 489,861$ 481,496$ 495,940$ 510,819$ 526,143$ 541,927$ 558,185$ 574,931$ 592,179$ 609,944$ 628,242$ 7,555,124$ Service TSP -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Performance Assurance 25,315$ 19,557$ 20,144$ 20,748$ 21,370$ 22,011$ 22,672$ 23,352$ 24,052$ 24,774$ 25,517$ 26,283$ 27,071$ 27,883$ 28,720$ 359,469$

Annual Gross Costs 352,471$ 385,792$ 425,586$ 467,370$ 511,231$ 503,507$ 518,612$ 534,171$ 550,196$ 566,702$ 583,703$ 601,214$ 619,250$ 637,828$ 656,962$ 7,914,593$ Cumulative Costs 352,471$ 738,263$ 1,163,849$ 1,631,219$ 2,142,450$ 2,645,957$ 3,164,569$ 3,698,740$ 4,248,935$ 4,815,637$ 5,399,339$ 6,000,553$ 6,619,803$ 7,257,631$ 7,914,593$

-$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ CASH FLOW -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Annual Net Cash Flow 103,621$ 103,621$ 103,621$ 103,621$ 103,621$ 78,290$ 80,639$ 88,933$ 97,652$ 106,814$ 116,437$ 126,542$ 137,149$ 148,278$ 159,951$ 1,658,792$ Cumulative Net Cash Flow 103,621$ 207,243$ 310,863$ 414,485$ 518,105$ 596,395$ 677,035$ 765,967$ 863,619$ 970,433$ 1,086,870$ 1,213,413$ 1,350,562$ 1,498,840$ 1,658,792$

Program Cost 5,771,207.17$ Rebates -$ Down Payment -$ Amount Financed 5,771,207.17$

Annual Program Savings 401,531.86$ Simple Payback (years) 14.4

Annual Interest Rate 3.00%Finance Period 15Payments per Year 12Total Interest Payments 1,783,916.70$

Energy Escalation 3%Operational Escalation 3%Service Escalation 3%

Page 145: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 145

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Cashflow - Minimum Term

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total

PROGRAM SAVINGSEnergy Savings 55,693$ 57,364$ 59,085$ 60,857$ 62,683$ 64,563$ 66,500$ 68,495$ 70,550$ 72,667$ 74,847$ 77,092$ 79,405$ 81,787$ 84,241$ 1,035,829$

Operational Savings 345,839$ 382,049$ 420,121$ 460,134$ 502,169$ 517,234$ 532,751$ 554,608$ 577,297$ 600,849$ 625,293$ 650,664$ 676,994$ 704,319$ 732,673$ 8,282,995$ Construction Savings 4,561$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 4,561$

Annual Gross Savings 406,093$ 439,413$ 479,206$ 520,991$ 564,852$ 581,797$ 599,251$ 623,103$ 647,847$ 673,515$ 700,140$ 727,756$ 756,399$ 786,106$ 816,914$ 9,323,385$ Cumulative Savings 406,093$ 845,506$ 1,324,712$ 1,845,703$ 2,410,555$ 2,992,352$ 3,591,604$ 4,214,707$ 4,862,555$ 5,536,070$ 6,236,210$ 6,963,966$ 7,720,365$ 8,506,471$ 9,323,385$

Annual Contribution 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 250,000$

PROGRAM COSTSPrincipal & Interest 430,778$ 469,856$ 509,063$ 550,243$ 593,481$ 559,786$ 576,580$ 599,751$ 623,795$ 648,741$ 674,623$ 701,473$ 201,240$ -$ -$ 7,139,410$ Service TSP -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Performance Assurance 25,315$ 19,557$ 20,144$ 20,748$ 21,370$ 22,011$ 22,672$ 23,352$ 24,052$ 24,774$ 25,517$ 26,283$ 27,071$ 27,883$ 28,720$ 359,469$

Annual Gross Costs 456,093$ 489,413$ 529,206$ 570,991$ 614,852$ 581,797$ 599,251$ 623,103$ 647,847$ 673,515$ 700,140$ 727,756$ 228,311$ 27,883$ 28,720$ 7,498,880$ Cumulative Costs 456,093$ 945,506$ 1,474,712$ 2,045,703$ 2,660,555$ 3,242,352$ 3,841,604$ 4,464,707$ 5,112,554$ 5,786,069$ 6,486,209$ 7,213,966$ 7,442,276$ 7,470,160$ 7,498,880$

-$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ CASH FLOW -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Annual Net Cash Flow (0)$ (0)$ (0)$ (0)$ 0$ 0$ (0)$ 0$ 0$ 0$ 0$ 0$ 528,088$ 758,223$ 788,194$ 2,074,505$ Cumulative Net Cash Flow (0)$ (0)$ (0)$ (0)$ (0)$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 528,089$ 1,286,311$ 2,074,505$

Program Cost 5,771,207.17$ Rebates -$ Down Payment -$ Amount Financed 5,771,207.17$

Annual Program Savings 401,531.86$ Simple Payback (years) 14.4

Annual Interest Rate 2.85%Finance Period 15Payments per Year 12Total Interest Payments 1,368,203.21$

Energy Escalation 3%Operational Escalation 3%Service Escalation 3%

Page 146: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 146

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Cashflow - Level Payments

Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total

PROGRAM SAVINGSEnergy Savings 55,693$ 57,364$ 59,085$ 60,857$ 62,683$ 64,563$ 66,500$ 68,495$ 70,550$ 72,667$ 74,847$ 77,092$ 79,405$ 81,787$ 84,241$ 1,035,829$

Operational Savings 345,839$ 382,049$ 420,121$ 460,134$ 502,169$ 517,234$ 532,751$ 554,608$ 577,297$ 600,849$ 625,293$ 650,664$ 676,994$ 704,319$ 732,673$ 8,282,995$ Construction Savings 4,561$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 4,561$

Annual Gross Savings 406,093$ 439,413$ 479,206$ 520,991$ 564,852$ 581,797$ 599,251$ 623,103$ 647,847$ 673,515$ 700,140$ 727,756$ 756,399$ 786,106$ 816,914$ 9,323,385$ Cumulative Savings 406,093$ 845,506$ 1,324,712$ 1,845,703$ 2,410,555$ 2,992,352$ 3,591,604$ 4,214,707$ 4,862,555$ 5,536,070$ 6,236,210$ 6,963,966$ 7,720,365$ 8,506,471$ 9,323,385$

Annual Contribution 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 250,000$

PROGRAM COSTSPrincipal & Interest 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 492,805$ 7,392,082$ Service TSP -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Performance Assurance 25,315$ 19,557$ 20,144$ 20,748$ 21,370$ 22,011$ 22,672$ 23,352$ 24,052$ 24,774$ 25,517$ 26,283$ 27,071$ 27,883$ 28,720$ 359,469$

Annual Gross Costs 518,120$ 512,362$ 512,949$ 513,553$ 514,176$ 514,817$ 515,477$ 516,157$ 516,858$ 517,579$ 518,323$ 519,088$ 519,877$ 520,689$ 521,525$ 7,751,551$ Cumulative Costs 518,120$ 1,030,482$ 1,543,431$ 2,056,985$ 2,571,160$ 3,085,977$ 3,601,454$ 4,117,612$ 4,634,470$ 5,152,049$ 5,670,372$ 6,189,460$ 6,709,337$ 7,230,026$ 7,751,551$

-$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ CASH FLOW -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Annual Net Cash Flow (62,027)$ (22,949)$ 16,257$ 57,438$ 100,676$ 66,981$ 83,774$ 106,946$ 130,989$ 155,936$ 181,817$ 208,668$ 236,522$ 265,417$ 295,389$ 1,821,834$ Cumulative Net Cash Flow (62,027)$ (84,976)$ (68,719)$ (11,281)$ 89,395$ 156,375$ 240,149$ 347,095$ 478,085$ 634,021$ 815,838$ 1,024,506$ 1,261,028$ 1,526,445$ 1,821,834$

Program Cost 5,771,207.17$ Rebates -$ Down Payment -$ Amount Financed 5,771,207.17$

Annual Program Savings 401,531.86$ Simple Payback (years) 14.4

Annual Interest Rate 3.00%Finance Period 15Payments per Year 12Total Interest Payments 1,620,874.43$

Energy Escalation 3%Operational Escalation 3%Service Escalation 3%

Page 147: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 147

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Exhibits

Exhibit I - Performance Bond/Construction Bond The Performance Bond will be provided prior to construction.

Page 148: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 148

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Exhibit II (i) - Certificate of Acceptance: Technical Audit I, the undersigned, hereby certify that I am the duly qualified and acting officer of Agency identified below and represent and warrant that:

1. The Technical Audit has been delivered in accordance with Agency's Specifications, and has been fully accepted by Agency on the 20th day of December 2013.

AGENCY: ______________________

Signature: _______________________

Title:___________________________

Date: __________________________

Page 149: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 149

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Exhibit II (ii) - Certificate of Acceptance: Installed Equipment I, the undersigned, hereby certify that I am the duly qualified and acting officer of Agency identified below and, with respect to the above-referenced Equipment to be Installed Schedule dated _________________, ______ to the Contract dated as of ___________________, by and between Agency and _________________ ("Company"), represent and warrant that:

1. The equipment described in Schedule A purchased from [Company] , and properly invoiced, has been delivered and installed in accordance with Agency's Specifications, is in good working order and is fully operational and properly functioning and has been fully accepted by Agency on the _____ day of _____________, _____.

2. Agency certifies that it has inspected the installation and operation of the Conservation Measure’s listed on Schedule A, pursuant to Contract Section ___ and that it finds the equipment listed on Schedule A is fully and properly functioning.

AGENCY: ______________________

Signature: _______________________

Title:___________________________

Date: __________________________

Page 150: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 150

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Exhibit III - Equipment Warranties The following warranties are provided for project scope.

Lighting

o Linear Fluorescent Lamps: 3 Years o Linear Fluorescent Ballast: 5 Years o Retrofitted HID Lamps: 6 – 24 Months based on lamp o Retrofitted HID Ballasts: 24 Months o LED Exit Signs: 5 Years o Light Fixtures: Varies by Manufacturer (Typically 1 Year) o Sensors: Varies by Manufacturer (Typically 5 Years) o 2 year warranty on Sylvania CFL lamps

Water Conservation: 1 year warranty from the date of installation

Chiller Replacement

o 3 year warranty of the chiller o 5 year warranty of the compressor

Roof-top Unit Replacements: 1 year warranty of unit

Plug Load Management: 1 year warranty

Mechanical Insulation: 1 year warranty from the date of installation

Programmable Thermostats: 30 day warranty of part

Mechanical Timers: 30 day warranty of part

Sample warranty documents provided on the following pages; actual documents will be delivered following equipment installation.

Page 151: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 151

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 152: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 152

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 153: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 153

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 154: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 154

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 155: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 155

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 156: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 156

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

The specific chiller manufacturer to be used on this project will be established following final project bids; the selected manufacturer will provide warranty information following installation.

The following “sample” warranty is provided for informational purposes only.

Page 157: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 157

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 158: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 158

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 159: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 159

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013

Page 160: Hallandale Beach, Florida · Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume- 1 | Page 2 Siemens – City of Hallandale Beach Investment Grade Energy

Proprietary and Confidential © Siemens Industry Investment Grade Audit – Volume I | Page 160

Siemens – City of Hallandale Beach Investment Grade Energy Audit | December 2013