Halton CommunityHousing Corporation Halton CommunityHousing Corporation
DEVELOPMENT COMMITTEE
Agenda
March 23, 2010
2
HCHC Development Committee
Agenda Item 1
�Update on Ontario St. (Milton) Project
2
3
HCHC Development Committee
AHP-E Year 2 - Timelines
• Submission due date to the Province was Feb 1, 2010 [no
later dates are anticipated]
– Ontario St. project was submitted by the deadline
– Funding Commitments (CLC) within 30 days (end of March)
– Contribution Agreement (CA) in place 30 days after CLC (end of
April)
– Construction must start 3 months after CA is signed (end of July,
2010)
4
HCHC Development CommitteeRFP Timelines
Tuesday April 13, 2010
Health and Social Services Committee Review:
- Contribution Agreement with HCHC
- Building/land lease arrangement with Region
Proposed meeting HCHC Board
Tuesday April 13, 2010
Anticipated HCHC Board approval of:
- Budget for project
- Design Builder
- Contribution Agreement with Region
- Building/land lease arrangement with Region
Within 60 days of Council ApprovalExpected date of Execution of Design-Build Agreement
Wednesday April 21, 2010Anticipated Council Approval
End of March 2010 AnticipatedAnticipated Conditional Letter of Commitment of funding from the
Province
Thursday March 18, 2010 at 2:00 pmDeadline for RFP Submission
Wednesday, March 10, 2010Deadline for Written Questions from Proponents
Thursday, March 4, 2010 from 10:00 to 11:00amNon-Mandatory Information Session on RFP
Thursday, February 25, 2010Release of RFP
Date/TimeDescription
3
5
HCHC Development CommitteeSite Plan
6
HCHC Development Committee
Preliminary Rendering
4
7
HCHC Development Committee
Preliminary Landscape Plan
8
HCHC Development Committee
South and East Elevations
5
9
HCHC Development Committee
North and West Elevations
10
HCHC Development Committee
Birdseye Rendering
6
11
HCHC Development Committee
Site Plan Application
• Site Plan Application was submitted by Regional
Architects in coordination with Asset Management to the
Town of Milton - March 5, 2010
– Expect conditions back by mid April
• Functional Servicing Report by Valdor Engineering Inc.
confirmed water and sanitary servicing capacity
– Service Permit will allow connection and occurs after Site plan
approval
12
HCHC Development Committee
Other updates
• Community Information Meeting, hosted by Local Councillors from the Town of Milton, prior to site plan submission February 24, 2010– Everyone present welcomed the project and believed that it was much needed
– The rents will still be too high for many, particularly older women with limited pension income
– Concern that if hydro costs were not included, rents would not be affordable
– Geothermal should be strongly considered because of operating cost & environmental benefits (Renewable Energy Initiative)
– Interest in whether support services for residents would be coordinated or if they would need to be arranged on an individual basis
• CCAC
• Support agencies
7
13
HCHC Development Committee
HCHC Pre Development Business Decisions
HCHC Board Approval
Feb/10 Staff Report
Feb 2/10Board to approve design and construction approach and
issuance of RFP (HC-03-10)
HCHC Board Approval
Feb/10 Staff Report
Jan/10HCHC Development Cttee to recommend design and
construction approach and issuance of RFP
Region Approval
Feb/10 Staff Report
Feb 2/10Re-submission of revised Project to the Province for Year
Two funding (SS-05-10)
HCHC Board Approval
Apr 13/10 Staff Report
Apr 13/10Approval of Successful Proponent
Receive from Province, Region to Sign
Mar/10Director’s Letter from Province to SM indicating Terms and Conditions of Commitment
Region Approval Apr 13/10
Staff Report
Same timing as CACommitment of Project Financing committed by Region
HCHC Board Approval – Apr 13/10 Staff Report
30 days after receipt of the CLC
Execute Contribution Agreement between HCHC and the Region (SM)
ProvinceEnd of Mar/10
Anticipated
Anticipated Conditional Letter of Commitment (CLC)
from Province
RequiresTimelinePre Development Tasks
14
HCHC Development Committee
Next Steps
• Regional Architects to coordinate responses to Site application
conditions – “permit ready status”
• Evaluate proponent RFP submissions
• Award RFP to proponent
• Construction start 3 months after CA is signed, (July/10)
8
15
HCHC Development Committee
Agenda Item 2
�Update on HCHC/New Horizon Project
(Burlington)
16
HCHC Development Committee
OMB Appeal• OMB hearing March 1, 2010
– All minor variances granted
– “Minutes of settlement” with appellant
• Site plan review/approval of conditions to proceed as quickly as possible– New Horizon currently working to meet all conditions
• Building Permit Application submitted February 24, 2010
• Resolution of planning issues are a condition of the Region’s draft agreements with developer
• Region will purchase land now (when permit ready) subject to conditions of the strata plan and conveyance of the commercial space after construction completion
9
17
HCHC Development Committee
HCHC Pre Development Business Decisions
HCHC Board Approval
Feb2/10 Staff Report
Feb2/10Authority to enter into Agreements between HCHC and
Developer (HC-02-10)
Receive from Province,
Region to Sign
Mid-late NovDirector’s Letter from Province to SM indicating Terms
and Conditions of Commitment
HCHC Board Approval
Dec 1 Staff Report
Dec1/09Confirmation of Upset Limit of Project Budget
Region Approval Dec16/09
Staff Report
Same timing as CACommitment of Project Financing committed by Region
HCHC Board Approval -
Dec1/09 Staff Report
30 days after
receipt of the CLC
Execute Contribution Agreement between HCHC and
the Region (SM)
ProvinceEarly Nov/09Conditional Letter of Commitment (CLC) from Province
RequiresTimelinePre Development Tasks
18
HCHC Development Committee
Other Updates and Next Steps
• Supported@home – Memorandum of Understanding
• City of Burlington – Library update
• Renewable Energy Initiative Submissions
– Must have Project approval under either SHRRP or AHPE
– must use a Vendor(s) from the Vendor List
• Purchase of Sale for the land and Construction agreements are being finalized and staff are in negotiation with developer
• Construction start by March 31, 2010